IN THE MATTER OF THE IMPLEMENTATION OF L. 2018, C. 16, ETC. (NEW JERSEY BOARD OF PUBLIC UTILITIES) ( 2021 )


Menu:
  •              NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-3939-18
    IN THE MATTER OF THE
    IMPLEMENTATION OF L. 2018,
    C. 16 REGARDING THE
    ESTABLISHMENT OF A ZERO
    EMISSION CERTIFICATE               APPROVED FOR PUBLICATION
    PROGRAM FOR ELIGIBLE
    March 19, 2021
    NUCLEAR POWER PLANTS,
    APPELLATE DIVISION
    and
    APPLICATION FOR ZERO
    EMISSION CERTIFICATES OF
    SALEM 1 NUCLEAR
    POWER PLANT,
    APPLICATION FOR ZERO
    EMISSION CERTIFICATES OF
    SALEM 2 NUCLEAR
    POWER PLANT,
    APPLICATION FOR ZERO
    EMISSION CERTIFICATES OF
    HOPE CREEK NUCLEAR
    POWER PLANT.
    ____________________________
    Argued December 9, 2020 – Decided March 19, 2021
    Before Judges Whipple, Rose, and Firko.
    On appeal from the New Jersey Board of Public
    Utilities, Docket Nos. EO18080899, EO18121338,
    EO18121339 and EO18121337.
    Stefanie A. Brand, Director, argued the cause for
    intervenor-appellant New Jersey Division of Rate
    Counsel (Stefanie A. Brand, attorney; Stefanie A.
    Brand, Brian O. Lipman, Litigation Manager, and
    Sarah H. Steindel, Assistant Deputy Rate Counsel, on
    the briefs).
    David Chester Apy, Assistant Attorney General,
    argued the cause for respondent New Jersey Board of
    Public Utilities (Gurbir S. Grewal, Attorney General,
    attorney; Melissa H. Raksa, Assistant Attorney
    General, of counsel; Alex Moreau, Deputy Attorney
    General, on the brief).
    Christopher S. Porrino argued the cause for
    intervenors-respondents Public Service Enterprise
    Group Incorporated and PSEG Nuclear, LLC
    (Lowenstein Sandler, LLP, attorneys; Christopher S.
    Porrino, Peter Slocum, Tamara Linde, Grace H. Park,
    Aaron I. Karp, and Joseph Accardo, Jr., on the brief).
    Steven S. Goldenberg argued the cause for intervenor-
    respondent New Jersey Large Energy Users Coalition
    (Giordano, Halleran & Ciesla, PC, attorneys; Steven
    S. Goldenberg, of counsel and on the brief).
    George C. Jones argued the cause for intervenor-
    respondent PJM Power Providers Group (McElroy,
    Deutsch, Mulvaney & Carpenter, LLP, attorneys;
    Joseph P. LaSala, of counsel; George C. Jones, on the
    brief).
    Matthew M. Weissman, attorney for intervenor-
    respondent Public Service Electric and Gas Company;
    Cozen O'Connor, PC, attorney for intervenor-
    respondent Jersey Central Power & Light Company;
    and Philip J. Passanante, attorney for intervenor-
    respondent Atlantic City Electric Company (Matthew
    A-3939-18
    2
    M. Weissman, Gregory Eisenstark, and Philip J.
    Passanante, on the joint brief).
    Day Pitney, LLP, Jeanne J. Dworetzky (Exelon
    Generation Company, LLC) of the District of
    Columbia bar, admitted pro hac vice, and Matthew E.
    Price (Jenner & Block, LLP) of the District of
    Columbia and Massachusetts bars, admitted pro hac
    vice, attorneys for intervenor-respondent Exelon
    Generation Company, LLC (Christopher John Stracco,
    Jeanne J. Dworetzky, Matthew E. Price, and Andrew
    J. Lichtman, on the brief).
    Carlin & Ward, PC and Jeffrey W. Mayes (Monitoring
    Analytics, LLC) of the Pennsylvania, Virginia, and
    District of Columbia bars, admitted pro hac vice,
    attorneys for intervenor-respondent Monitoring
    Analytics, LLC (Michael J. Ash and Jeffrey W.
    Mayes, of counsel and on the brief).
    Szaferman, Lakind, Blumstein & Blader, PC,
    attorneys for amicus curiae AARP (Janine G. Bauer,
    on the brief and Evelyn Liebman).
    Connell Foley, LLP, and Ann Brewster Weeks (Clean
    Air Task Force) of the Massachusetts bar, admitted
    pro hac vice, attorneys for amicus curiae Clean Air
    Task Force (Thomas S. Cosma and Ann Brewster
    Weeks, on the brief).
    Richard M. Pescatore, PC, and Bethany A. Davis Noll
    (Institute for Policy Integrity) of the New York bar,
    admitted pro hac vice, attorneys for amicus curiae
    Institute For Policy Integrity (Jennifer Carlson and
    Bethany A. Davis Noll, on the brief).
    Sills Cummis & Gross, PC, attorneys for amicus
    curiae Nuclear Energy Institute, Inc. (Peter G.
    Verniero and Michael S. Carucci, of counsel and on
    the brief).
    A-3939-18
    3
    The opinion of the court was delivered by
    WHIPPLE, J.A.D.
    In 2007, the New Jersey Legislature passed the Global Warming
    Response Act, N.J.S.A. 26:2C-37 to -68, having declared that it was in the
    State's interest to reduce greenhouse gas emissions by eighty percent by 2050.
    In furtherance of that goal, in 2018 the Legislature enacted a Zero Emission
    Certificate (ZEC) program for eligible nuclear power plants, L. 2018, c. 16,
    codified at N.J.S.A. 48:3-87.3 to -87.7 (the ZEC Act). The purpose of the ZEC
    Act is to subsidize nuclear power plants at risk of closure, helping them to
    remain operational despite competition from other carbon-emitting power
    sources, in the interest of New Jersey's clean energy goals. The Board of
    Public Utilities (the Board) administers the ZEC program, reviews
    applications, and selects eligible nuclear power plants to receive ZECs.
    The Board considered ZEC applications from the Salem 1, Salem 2 and
    Hope Creek nuclear power plants located in Salem County. Following an
    extensive review of the applications, including voluminous confidential
    financial information about the nuclear power plants' costs and revenues,
    certifications that the plants would shut down in three years absent a material
    financial change, as well as consideration of thousands of public comments,
    the Board determined that all three applicants satisfied the five statutory
    A-3939-18
    4
    eligibility criteria codified at N.J.S.A. 48:3-87.5(e) and should receive ZECs.
    In this appeal, we address challenges to the Board's decision. Because the
    Board's decision is adequately supported by the record and consistent with
    both the ZEC Act's plain language and the legislative intent, we affirm.
    I.
    Significant ZEC subsidy costs are ultimately passed on to consumers;
    thus, the New Jersey Division of Rate Counsel (Rate Counsel) appealed the
    Board's decision, arguing it was arbitrary, capricious, or contrary to law for
    various reasons. Rate Counsel contended none of the nuclear power plants
    need ZECs to remain financially viable and therefore do not satisfy the third
    statutory eligibility criterion. Rate Counsel advanced other general challenges
    to aspects of the Board's findings and conclusions, asserting the Board did not
    interpret certain aspects of the ZEC Act correctly, and further argued that the
    Board ignored its responsibility to ensure that the $0.004-per-kilowatt-hour
    charge mandated in the ZEC Act to fund the ZEC program was just and
    reasonable.
    Rate Counsel was an intervenor before the Board based upon its
    statutory authority to represent and protect the public interest.      N.J.S.A.
    52:27EE-48(a).    Respondent     Monitoring    Analytics,   LLC    (Monitoring
    Analytics), also an intervenor, is the Independent Market Monitor (IMM) for
    A-3939-18
    5
    PJM Interconnection, LLC. 1      In its role as IMM, Monitoring Analytics
    objectively monitors the competitiveness of PJM's markets.
    Numerous other stakeholders participated before the Board and in this
    appeal. Respondent Exelon Generation Company, LLC (Exelon) participated
    as co-owner of the Salem 1 and Salem 2 nuclear power plants with respondent
    PSEG Nuclear, LLC (PSEG Nuclear). PSEG Nuclear is the sole owner of the
    Hope Creek nuclear power plant and has the sole and exclusive authority to
    make decisions regarding the retirement of all three plants. PSEG Nuclear
    submitted ZEC applications to the Board for Salem 1, Salem 2, and Hope
    Creek.
    Respondents Public Service Electric and Gas Company (PSE&G), Jersey
    Central Power & Light Company (JCP&L), and Atlantic City Electric
    Company (ACE), are investor-owned electric distribution companies (EDCs).
    Respondent PJM Power Providers Group (P3) is a nonprofit organization
    of power providers whose mission is to promote properly designed and well-
    functioning competitive wholesale electricity markets in the region served by
    1
    PJM Interconnection, LLC (PJM) manages the regional, high-voltage
    electricity grid serving all or parts of thirteen states including New Jersey and
    the District of Columbia, operates the regional competitive wholesale electric
    market, manages the regional transmission planning process, and establishes
    systems and rules to ensure that the regional and in-state energy markets
    operate fairly and efficiently. N.J.S.A. 48:3-51.
    A-3939-18
    6
    PJM. Respondent New Jersey Large Energy Users Coalition (NJLEUC) is an
    association of large volume electric customers.
    We also granted AARP, Nuclear Energy Institute, Inc. (NEI), Institute
    for Policy Integrity (IPI) and Clean Air Task Force leave to file amicus briefs.
    II.
    As a subsidy promoting nuclear power, a ZEC is "a certificate, issued by
    the [B]oard or its designee, representing the fuel diversity, air quality, and
    other environmental attributes of one megawatt-hour of electricity generated
    by an eligible nuclear power plant selected by the [B]oard to participate in the
    program." N.J.S.A. 48:3-87.4. To be deemed eligible by the Board, a nuclear
    power plant must meet the following five criteria:
    (1) be licensed to operate by the United States Nuclear
    Regulatory Commission by the date of enactment of
    this Act and through 2030 or later;
    (2) demonstrate to the satisfaction of the [B]oard that
    it makes a significant and material contribution to the
    air quality in the State by minimizing emissions that
    result from electricity consumed in New Jersey, it
    minimizes harmful emissions that adversely affect the
    citizens of the State, and if the nuclear power plant
    were to be retired, that that retirement would
    significantly and negatively impact New Jersey's
    ability to comply with State air emissions reduction
    requirements;
    (3) demonstrate to the satisfaction of the [B]oard,
    through the financial and other confidential
    information submitted to the [B]oard pursuant to
    A-3939-18
    7
    subsection a. of this section, and any other information
    required by the [B]oard, . . . that the nuclear power
    plant's fuel diversity, air quality, and other
    environmental attributes are at risk of loss because the
    nuclear power plant is projected to not fully cover its
    costs and risks, or alternatively is projected to not
    cover its costs including its risk-adjusted cost of
    capital, and that the nuclear power plant will cease
    operations within three years unless the nuclear power
    plant experiences a material financial change;
    (4) certify annually that the nuclear power plant does
    not receive any direct or indirect payment or credit
    [from the state, federal government, or regional
    compact] . . . despite its reasonable best effort to
    obtain any such payment or credit, for its fuel
    diversity, resilience, air quality or other environmental
    attributes that will eliminate the need for the nuclear
    power plant to retire, except for any payment or credit
    received under the provisions of this act; and
    (5) submit an application fee to the [B]oard in an
    amount to be determined by the [B]oard, but which
    shall not exceed $250,000, to be used to defray the
    costs incurred by the [B]oard to administer the ZEC
    program.
    [N.J.S.A. 48:3-87.5(e).]
    The central issue in this appeal is the satisfaction of the third statutory
    criterion, financial eligibility. ZEC applicants must provide the Board with
    extensive financial information about the nuclear power plant,
    including, but not limited to, certified cost projections
    over the next three energy years, including operation
    and maintenance expenses, fuel expenses, including
    spent fuel expenses, non-fuel capital expenses, fully
    allocated overhead costs, the costs of operational risks
    A-3939-18
    8
    and market risks that would be avoided by ceasing
    operations, and any other information, financial or
    otherwise, to demonstrate that the nuclear power
    plant's fuel diversity, air quality, and other
    environmental attributes are at risk of loss because the
    nuclear power plant is projected to not fully cover its
    costs and risks, or alternatively is projected to not
    fully cover its costs and risks including its risk-
    adjusted capital.
    [N.J.S.A. 48:3-87.5(a).]
    For purposes of this subsection, operational risks include, but are not
    limited to, the risk that operating costs will be higher than anticipated because
    of new regulatory mandates or equipment failures and the risk that per-
    megawatt-hour costs will be higher than anticipated because of a lower than
    expected capacity factor. Market risks include, but are not limited to, the risk
    of a forced outage and the associated costs arising from contractual
    obligations, and the risk that output from the nuclear power plant may not be
    able to be sold at projected levels. Id.
    Applicants must also include a certification that the nuclear power plant
    will cease operations within three years unless the nuclear power plant
    experiences a material financial change; the certification shall specify the
    necessary steps required to be completed to cease the nuclear power plant's
    operations.
    A-3939-18
    9
    2
    The ZEC Act contains a confidentiality provision             to protect the
    information submitted by ZEC applicants and mandates procedural timelines
    for establishment of the ZEC program by the Board, submission of ZEC
    applications and selection of eligible nuclear plants to receive ZECs, all of
    which were met. N.J.S.A. 48:3-87.5(b), (c), (d).
    The selected nuclear power plants must certify annually that they remain
    eligible for ZECs pursuant to the ZEC Act's requirements. N.J.S.A. 48:3-
    87.5(h)(2), (3). For the first energy year, the eligible nuclear power plant
    receives a number of ZECs equal to the number of megawatt-hours of
    electricity it produced in that energy year starting on the date the Board
    selected it. N.J.S.A. 48:3-87.5(g)(2). For each subsequent energy year, the
    eligible nuclear power plant receives a number of ZECs equal to the number of
    megawatt-hours of electricity that it produced in that energy year. Ibid.
    2
    During the Board proceedings, the Attorney General and the Board approved
    the requests by intervenors for access to confidential information in the record,
    including the three ZEC applications, pursuant to N.J.S.A. 48:3-87.5(a), upon
    determining that both parties were "essential to aid the Board in making the
    applicable determinations under the [ZEC] Act" and that the disclosure would
    not harm competition. None of the other parties were granted access to any of
    the confidential information. Consequently, the Board issued two versions of
    its order, decision, and attachments thereto:         a public version and a
    confidential version. Rate Counsel, Exelon, and PSEG Nuclear filed public
    and confidential versions of their appellate briefs and appendices. Our
    decision is based on the confidential record.
    A-3939-18
    10
    The ZEC Act requires the Board to determine the price of a ZEC for
    each energy year:
    by dividing the total number of dollars held by electric
    public utilities in the accounts established pursuant to
    paragraph (1) of subsection j. of this section at the end
    of the prior energy year by the greater of: [forty]
    percent of the total number of megawatt-hours of
    electricity distributed by the electric public utilities in
    the state in the prior energy year, or the number of
    megawatt-hours of electricity generated in the prior
    energy year by the selected nuclear power plants.
    [N.J.S.A. 48:3-87.5(i)(1).]
    The ZEC Act further requires EDCs to purchase ZECs on a monthly
    basis from each selected nuclear power plant with payment to follow within
    ninety days after the conclusion of the first energy year in which selected
    nuclear power plants receive ZECs, and within ninety days after the conclusion
    of each subsequent energy year. N.J.S.A. 48:3-87.5(i)(2). The total number of
    ZECs that each EDC is required to purchase is equal to the total number of
    ZECs received by the selected nuclear power plants for the prior energy year,
    multiplied by the percentage of electricity distributed in the State by the
    electric public utility as compared to other electric public utilities in New
    Jersey. Id.
    This purchase is funded through a charge imposed on retail customers.
    N.J.S.A. 48:3-87.5(j)(1). The ZEC Act requires EDCs to file a tariff to recover
    A-3939-18
    11
    from its retail distribution customers a charge in the amount of $0.004 per
    kilowatt-hour, which reflects the emissions avoidance benefits associated with
    the continued operation of selected nuclear power plants.        Following an
    opportunity for comment, public hearing and the Board's approval, the revenue
    collected from the charge is held in a separate, interest-bearing account used
    solely to purchase ZECs. Any excess money in that account at the end of each
    energy year is refunded to customers. N.J.S.A. 48:3-87.5(j)(2). The ZEC Act
    also contains refund mechanisms triggered by a nuclear power plant's cessation
    of operations despite having received ZECs. N.J.S.A. 48:3-87.5(k).
    In order to ensure that the ZEC program remains affordable to New
    Jersey retail distribution customers, and notwithstanding the provisions of
    N.J.S.A. 48:3.87.5(j)(1), the Board may reduce the $0.004-per-kilowatt-hour
    charge at certain times, and under certain circumstances set forth in N.J.S.A.
    48:3-87.5(j)(3)(c). For example, the Board may reduce the charge if it does
    not certify any nuclear power plants for a subsequent eligibility period upon
    determining that a reduced charge will nonetheless be sufficient to achieve the
    state's air quality.   This would meet other environmental objectives by
    preventing the retirement of the nuclear power plants that meet the eligibility
    criteria established pursuant to subsections (d) and (e).
    A-3939-18
    12
    III.
    On August 29, 2018, the Board initiated the ZEC program, with a
    vigorous application and review process. The Board created an Eligibility
    Team (ET) to evaluate and rank the applications based upon the five criteria
    set forth in the ZEC Act and stated its intent to hire a consultant to assist its
    staff. It determined that after the initial three-year award of ZECs to a unit, it
    would evaluate the set kilowatt-hour charge established by the ZEC Act and
    modify that amount if necessary, pursuant to N.J.S.A. 48:3-87.5(j)(3).
    The Board issued orders accepting the tariffs filed by EDCs for the
    recovery of the ZEC charges from their customers but directed that the tariffs
    not be implemented unless and until the Board issues a final order authorizing
    the EDCs to implement the ZEC program. The Board selected Levitan &
    Associates, Inc. (Levitan) as a consultant to assist its staff with evaluation and
    ranking of the ZEC applications.
    IV.
    With these procedures in place, on December 19, 2018, PSEG Nuclear
    submitted ZEC applications for Salem 1, Salem 2 and Hope Creek. Applicants
    each submitted a confidential application designed to elicit information that
    tracked the statutory eligibility criteria, which included: I. General Applicant
    Information; II. Generation Asset Information and Operation; III. Zero
    A-3939-18
    13
    Emission Credit Justification – Financial; IV. Zero Emission Credit
    Justification – Environmental; V. Impact of the Unit's Deactivation; and VI.
    Miscellaneous. Section VII sought thirty-eight supplemental submissions from
    each applicant, including a certification that the nuclear power generation unit
    will cease operations within three years unless the nuclear power plant
    experiences a material financial change.        The information sought from
    applicants in Section III of the application pertained to projected costs and is
    especially relevant to the issues raised on appeal.       The first category of
    information sought:
    [C]ertified cost projections over the next three (3)
    energy years, including operation and maintenance
    expenses; fuel expenses, including spent fuel
    expenses; on-fuel capital expenses; fully allocated
    overhead costs; the costs of operational risks and
    market risks that would be avoided by ceasing
    operations to demonstrate that the plant is projected to
    not fully cover its costs and risks, or alternatively is
    projected to not fully cover its costs and risks,
    including its cost of capital, or alternatively its risk-
    adjusted cost of capital.
    The second category required applicants to:
    Demonstrate that the unit is financially unviable, i.e.,
    if the unit's revenue and funding outweighs the
    avoided costs expenses (operations, training,
    engineering, materials, fuel, etc.) of the unit, for each
    year through 2030.              Provide all backup
    documentation.
    A-3939-18
    14
    Because Rate Counsel does not contend on appeal that the applicants
    failed to satisfy all of the eligibility criteria, we limit our discussion to those
    aspects of the applications pertaining to the third eligibility criterion, codified
    at N.J.S.A. 48:3-87.5(e)(3), financial viability.
    The applicants' cost projections included the following categories of
    expenses:    labor and materials, outside services such as contractors and
    maintenance, real estate taxes, support services such as accounting, human
    resources, etc., fully allocated corporate overhead, spent fuel, working capital,
    fuel and non-fuel capital expenditures, regulatory and other fees and expenses,
    operational risks and market risks. Their revenue projections included energy,
    capacity, and ancillary revenue.
    Rate Counsel asserted the applicants are financially viable without ZECs
    because the applicants improperly included operational risks, market risks,
    spent fuel costs, certain support service and overhead costs and certain capital
    expenditures in their cost projections. Thus, we focus on these five categories
    and how the Board reviewed them.
    1. Operational Risks
    For each applicant, PSEG Nuclear included "a cost of operational risk in
    its financial evaluation equal to ten percent of total costs, which is consistent
    with operating cost estimation rules adopted in the [Federal Energy Regulatory
    A-3939-18
    15
    Commission]-approved PJM tariff." PSEG Nuclear explained that the cost of
    operational risk for each plant included potential regulatory mandates,
    equipment failures and attendant outages for repairs.
    Addressing regulatory mandates, PSEG Nuclear asserted that nuclear
    plants are subject to stringent safety- and security-focused regulatory oversight
    by the United States Nuclear Regulatory Commission (NRC), and can face
    significant unseen regulatory requirements at any time, such as recent orders
    issued by the NRC after a 2011 "nuclear event" in Japan that required all
    United States nuclear plants to upgrade their facilities. These upgrades cost
    Salem 1, Salem 2 and Hope Creek approximately $105 million.             Security
    requirements after the September 11, 2001, terrorist attacks cost Salem 1,
    Salem 2 and Hope Creek approximately $140 million.
    PSEG Nuclear cited unexpected expenditures in 2008 at Salem 1 of
    approximately $266 million.      In addition, PSEG Nuclear asserted that the
    cumulative impact of even relatively modest capital projects required to
    address unforeseeable equipment failure issues can be significant.       It also
    asserted that unexpected outages for repairs not only increase the total unit
    costs but can also dramatically increase the per-megawatt-hour cost, and that
    such outages can be prolonged.
    A-3939-18
    16
    2. Market Risks
    For each applicant, PSEG Nuclear included the cost of market risks in its
    projections at a rate of $4.2/megawatt hours for Hope Creek and Salem 1, and
    $4.3/megawatt hours for Salem 2. PSEG Nuclear divided its market risks into
    two categories:     forced outage risk and price volatility risk.         In each
    application, PSEG Nuclear explained that forced outage risk is:
    that actual generation will fall short of forecasted
    generation, resulting in lower than expected revenues
    or a mismatch between previously contracted sales
    and actual generation so that the generation owner will
    have to "cover" its contracted sales during outages by
    purchasing energy in the spot market at prices
    potentially much higher than the contracted price – or
    hedged price.
    It further explained that price volatility risk is the risk that the forecasted
    generation output from the nuclear power plant may not be able to be sold at
    projected prices – or forward prices.
    To assess each applicant's market risks, PSEG Nuclear utilized an energy
    risk modeling software application, Lacima Analytics. It explained how it
    used the same software application, inputs, and modeling approach that it uses
    in the ordinary course of business to assess market risk for its entire portfolio.
    In keeping with its normal business practice to assess and manage portfolio
    market risk at the ninety-five-percent confidence level, PSEG Nuclear used
    that same level to assess the cost of market risks in each application.
    A-3939-18
    17
    3. Spent Fuel Costs
    Spent fuel costs arise from a charge imposed by the United States
    Department of Energy (DOE) on nuclear plants for the costs of fulfilling its
    legal obligation to dispose of the nuclear fuel used to generate power. Because
    this charge was most recently assessed at a rate of $0.955 per megawatt-hour,
    that rate was used in each applicant's cost projections.
    When the federal Yucca Mountain Nuclear Waste Repository was
    defunded, this fee was suspended, at which point PSEG Nuclear ceased
    accruing for that expense in its financial statements.      It explained that it
    nonetheless included spent fuel costs in its cost projections because DOE still
    has a legal obligation to dispose of nuclear fuel and will need to pay for the
    costs of whatever that ultimate solution is through a fee on nuclear generators.
    4. Support Services and Overhead Costs
    For each applicant, PSEG Nuclear included support services and fully
    allocated overhead in its cost projections, which represented:
    [A]ccounting, legal, communications, procurement,
    human resources, information technology, treasury
    and financial, investor relations, stockholder services,
    real estate, insurance, risk management, tax, security
    and claims, corporate secretarial and certain planning,
    budgeting, forecasting services, and general
    administrative expenses and other corporate overhead
    costs.
    A-3939-18
    18
    5. Capital Expenditures
    For each applicant, PSEG Nuclear included fuel and non-fuel capital
    expenditures in its cost projections. It described fuel capital expenditures as
    the fuel capital expenditures associated with refueling outages and non-fuel
    capital expenditures as spending on long-lived plant equipment required to
    maintain safe and reliable operations.
    The Board considered comments from Rate Counsel, Monitoring
    Analytics, P3 and NJLEUC, among others, on the applications, along with
    reply comments from PSEG Nuclear and others. Rate Counsel contended the
    applicants' financial projections overstated costs and understated revenues.
    The comments also focused upon the $2.9 billion in "stranded costs"
    previously paid by ratepayers for the nuclear units as a result of electric public
    utility deregulation in 1999 and asserted that the Board was required to
    determine not only whether a ZEC is warranted, but also whether the rate set
    forth in the statute is just and reasonable.
    The comments pertaining to overstated costs and understated revenues
    echoed the findings of Rate Counsel's experts, who submitted two
    certifications.   First, a certification from Andrea Crane, president of the
    Columbia Group, Inc., a consulting firm specializing in utility regulation,
    primarily addressed the applicants' overstated costs. A certification from Bob
    A-3939-18
    19
    Fagan and Maximilian Chang of Synapse Energy Economics (Synapse), a
    consulting firm that provides economic and expert advice to public interest
    clients on electricity matters, primarily addressed the applicants' understated
    revenues.
    These experts both criticized the methodologies used by PSEG Nuclear
    to assess the financial viability of each plant and conducted independent
    assessments in which they eliminated the assumption of operational and
    market risks from the financial projections. With those categories excluded
    entirely, they opined that each plant would be financially viable for the next
    three years and that, therefore, none of the applicants qualified for the ZEC
    program.
    Rate Counsel argued PSEG Nuclear's financial projections pertaining to
    costs for each applicant were flawed because the methodologies used for
    forecasting operational and market risks were speculative and unverifiable, and
    because PSEG Nuclear included capital expenditures as "costs" and included
    improper and inflated operational costs such as spent fuel, support services,
    and overhead costs. Rate Counsel and Crane acknowledged that PSEG
    Nuclear's estimates may be the best indicator of expected future costs but
    nonetheless maintained that this approach placed an unreasonable burden on
    ratepayers.
    A-3939-18
    20
    As to PSEG Nuclear's market risks methodology, Rate Counsel and
    Crane asserted that it virtually guaranteed the claimed "cost" will cover all
    contingencies despite the fact the ZEC Act does not provide for ratepayers to
    be guarantors for all possible contingencies relating to market risks. They
    urged the Board to consider the history of these deregulated units and the fact
    that they have earned profits significantly higher than anticipated since
    deregulation occurred approximately twenty years ago.
    Rate Counsel and Crane also argued the cash flow approach utilized by
    PSEG Nuclear violates a basic accounting principle that costs which provide a
    benefit over multiple years should be recovered over a multi-year period. The
    cash flow approach burdens ratepayers by funding one hundred percent of
    capital expenditures for these supposedly unregulated entities, but provides no
    right to benefit from any excess returns on those investments.
    Rate Counsel and Crane objected to the inclusion of spent fuel costs
    since the spent fuel charge for Yucca Mountain was suspended in May 2014.
    They also claimed that the variable portion of the support services and
    overhead costs which PSEG Nuclear included was inflated and it was unlikely
    that most of these costs will go away if the nuclear units are shut down.
    Citing the Synapse certification, Rate Counsel contended that PSEG
    Nuclear understated each applicant's energy price projections and capacity
    A-3939-18
    21
    price projections and failed to account for other sources of revenue. They
    argued recent actual energy prices were higher than those projected by the
    applicants and that the applicants failed to look at future natural gas prices,
    which are generally viewed as a good indication of where future energy prices
    will fall, and failed to analyze the price impacts if only one or two of the units
    shuts down, rather than all three.
    In further support of its objection to the ZEC program, Rate Counsel
    discussed the 1999 enactment of the Electric Discount and Energy Competition
    Act (EDECA), N.J.S.A. 48:3-49 to -98, which mandated the restructuring of
    the electric and natural gas industry in order to lower prices through
    competition. Overall, Rate Counsel contended that the historical impact of the
    EDECA and the restructuring process on ratepayers should be considered by
    the Board in connection with the ZEC applications.
    During restructuring under the EDECA, electric companies divested
    most of their generation fleets but continued to transmit and deliver power to
    customers.   The divestitures created "stranded costs" because the value of
    some plants on a utility's books was higher than what the electric utility
    received when divesting its asset. PSE&G had divested its ownership share of
    Salem 1, Salem 2 and Hope Creek to its affiliate. Rate Counsel asserted that
    the affiliate assumed the risks of ownership and operation of the nuclear plants
    A-3939-18
    22
    as part of this transaction, which allowed it to earn unregulated returns on the
    assets being transferred. According     to   Rate   Counsel,    PSE&G      already
    recovered approximately $2.9 billion in stranded costs from ratepayers, which
    included costs from the nuclear plants and other fossil fuel plants that it
    divested.
    Finally, Rate Counsel's comments also addressed the reasonableness of
    the $0.004-per-kilowatt-hour charge mandated in the ZEC Act, claiming the
    Board has an obligation to determine not only whether a ZEC is warranted, but
    also whether the rate set forth in the statute is just and reasonable pursuant to a
    different statute, N.J.S.A. 48:2-21(b).      It criticized the Act for failing to
    explain how the charge was calculated and contended that the Board should
    interpret the ZEC Act in pari materia with N.J.S.A. 48:2-21(b), a public
    utilities statute concerning ratemaking. Rate Counsel further contended that
    unless the Board finds that a nuclear plant's application demonstrates that the
    $0.004 rate is just and reasonable, the Board must either deny the ZEC in its
    entirety or approve some lesser amount.
    Monitoring Analytics's comments echoed Rate Counsel's assertions of
    overstated costs, understated revenues and that none of the units required
    subsidies. P3 agreed with Rate Counsel and Monitoring Analytics that the
    applicants' nuclear plants are highly profitable and do not need ZECs. It also
    A-3939-18
    23
    noted several pending PJM market reforms that could lead to additional
    revenue for the applicants, asserting that if New Jersey rejoins the Regional
    Greenhouse Gas Initiative (RGGI), power prices will increase and nuclear
    units will make an additional thirty to seventy million dollars a year in profits.
    P3 maintained that abandoning the competitive market, and awarding
    unnecessary ZECs, will make New Jersey's high electricity rates even higher
    and agreed with Rate Counsel and Monitoring Analytics that, ultimately, the
    Board should reject the ZEC applications.          To support its position, P3
    submitted a sworn affidavit from its expert, Paul M. Sotkiewicz, PhD,
    President and Founder of E-Cubed Policy Associates, LLC, and former Chief
    Economist in the Market Service Division of PJM Interconnection, LLC.
    NJLEUC also contended that the ZEC program will have a detrimental
    effect on large businesses in the State, which consume a much greater number
    of kilowatt hours of electricity than residential customers. Based upon a poll
    of its member businesses, it argued that the average cost of the ZEC program
    to large businesses will be $570,000 per year.
    On April 17, 2019, the ET, which consisted of Board staff, New Jersey
    Department of Environmental Protection (NJDEP) staff, and the Board
    consultant, Levitan, submitted three memoranda to the Board that addressed
    each applicant's eligibility for ZECs. The ET submitted two other documents
    A-3939-18
    24
    with each memorandum that it had reviewed, incorporated, and relied upon to
    support its recommendations: the Application Eligibility Report from Levitan,
    and a memorandum from NJDEP addressing the applicants' environmental
    eligibility under the second statutory criterion.
    The ET found all three applications were complete, and based on the
    submitted applications, each applicant had satisfied the first, fourth, and fifth
    statutory criteria since: (1) each unit was licensed to operate beyond 2030; (2)
    each unit has not and was not currently receiving any other subsidies; and (3)
    each applicant paid the requisite application fee. Thus, the ET determined that
    eligibility for ZECs came down to the environmental and financial
    determinations, the second and third statutory criteria.
    Overall, the ET found that the closing of each unit would require the use
    of substitute capacity resources to supplement PSEG Nuclear's committed
    energy in the three-year ahead capacity market and that solar and wind energy
    resources could not replace the base load from the nuclear units.
    Consequently, the supplemental energy would most likely come from natural
    gas-fired plants within PJM and quite possibly from its own inventory.
    NJDEP agreed in its memo that, within the three-year study period,
    replacement generation would come from existing fossil-fuel-fired facilities.
    A-3939-18
    25
    The ET determined that closure of Salem 1, Salem 2, and Hope Creek
    will have a negative impact on air quality in New Jersey based on increased
    emissions, including harmful emissions, from electric-generating sources, and
    will not significantly and negatively impact New Jersey's ability to comply
    with 2020 Global Warming requirements, but may make New Jersey's ability
    to comply with 2050 Global Warming requirements more challenging and
    would likely make New Jersey's ability to comply with ozone air quality
    standards more challenging.
    However, the ET agreed with Rate Counsel, Monitoring Analytics, and
    P3 that a unit's avoidable costs is the proper focus of the evaluation of the
    unit's financial viability under the ZEC Act. It noted that in other proceedings,
    the Board has supported a net avoidable cost rate as an appropriate measure of
    a generator's competitive offer into the markets.
    The ET excluded one-half of projected labor costs, one-half of projected
    non-labor costs and all projected spent fuel costs from PSEG Nuclear's cost
    projections for each applicant. It cited Levitan's analysis and concluded that
    because the cost of handling spent fuel is not a true cost that is incurred, it is
    not a cost that would be avoided by ceasing operations. After making various
    adjustments to the applicants' cost projections, the ET concluded that all three
    A-3939-18
    26
    units would operate profitably through May 2022 and would therefore not need
    to cease operations within the next three years.
    The Board did not agree and on April 18, 2019, determined that the
    applicants had satisfied the ZEC Act's eligibility criteria to receive ZECs. In
    Sections I and II of its comprehensive decision, the Board summarized the
    matter's background and procedural history. And in Section III, the Board
    summarized the commenters' respective positions, along with PSEG Nuclear's
    reply thereto.
    In its decision, the Board outlined the eligibility process, incorporated
    the majority of the ET's findings, and summarized the ET's determination on
    the applications.     The Board analyzed the ET's six key determinations
    pertaining to the third criterion, financial eligibility, as follows:
    [1] The market and operational "risks" included by
    PSEG [Nuclear] (and Exelon as part owner for Salem
    1 and 2) in the applications should be excluded.
    These "risks" are planning projection tools used by the
    applicant and are not true "costs" that would be
    incurred by PSEG [Nuclear] beyond their normal
    [operating and marketing] costs. These "risks" are not
    costs that can be avoided by ceasing operations
    because they are not incurred. . . .
    [2] Staff determined that evaluating whether a unit is
    covering its avoidable costs with revenues is the
    appropriate approach to assessing whether the unit has
    met the financial criterion under the [ZEC] Act, based
    on staff's interpretation of the [ZEC] Act. . . .
    A-3939-18
    27
    [3] The spent fuel costs . . . are based on an unrealized
    and unpaid fee established in a DOE order for future
    storage as spent fuel. PSEG [Nuclear] demonstrated
    that these costs have not been historically paid or
    accounted for in historical finances since 2014. In
    summary, the spent fuel cost is not in effect, is not an
    avoidable cost, and should also be excluded from the
    financial analysis.
    [4] Avoided costs by shutting down the units would
    not be as simple as zero labor and materials savings.
    The units must be maintained by personnel, at
    approximately a [fifty percent] level for five to seven
    years, until all decommissioning is completed and all
    spent fuel is secured. Because one-half of the unit's
    projected labor and non-labor costs are avoidable, they
    should be considered at this level in the financial
    analysis.
    [5] The Board has traditionally used a net avoidable
    cost rate method to measure a generator's competitive
    offer into the markets.
    [6] Levitan and staff concluded that, if the above
    referenced questionable costs such as risks and spent
    fuel . . . along with other adjustments – are removed
    from the financial projections, the units are financially
    viable as they stand.
    The Board also noted the ET considered factors beyond the five main criteria
    of N.J.S.A. 48:3-87.5(e), including, in part, fuel resilience, fuel diversity, and
    PJM market changes.
    The Board concluded that the Legislature was clear and specific
    regarding the criteria according to which the applicants were to be evaluated,
    and said criteria included consideration of operational and market risks as per
    A-3939-18
    28
    the ZEC Act's plain language. The Board found that the ZEC Act required an
    applicant to demonstrate that the nuclear power plant is projected to not fully
    cover its costs and risks and that "risks" as defined in the ZEC Act included
    "operational risks, [such as] operating costs higher than anticipated," along
    with "market risks, [such as] market energy and capacity price volatility." The
    Board cited numerous cases in support of its plain language interpretation of
    the ZEC Act and recognized it may not, under the guise of interpretation, give
    the statute any greater effect than the statutory language allows.
    The Board further found that the ZEC Act required it to consider other
    outside factors and legitimate policy goals of the state such as fuel diversity,
    resilience and the impact of nuclear power plant retirement on RGGI, New
    Jersey's economy, carbon and global warming. While the Board acknowledged
    the ET's finding that closure of the three nuclear power plants may have a
    relatively small impact on fuel diversity, the Board found that it was also
    important to consider that the nuclear power plants in New Jersey currently
    supply the equivalent of thirty-two percent of our power needs.
    Concerning the environmental impact of closure, the Board found that
    neither solar nor offshore wind energy had the capacity to replace the loss of
    base load from the nuclear units.      As a result, replacement power would
    increase carbon, which is in contravention of the state's stated goal of carbon
    A-3939-18
    29
    reduction, and New Jersey would become reliant on fossil fuel plants to make
    up for the loss of zero-emission capacity over the next three years.
    Consequently, the Board concluded that if the plants retire, it would likely be
    more difficult for New Jersey to meet its obligations to reach the state's goal of
    one-hundred percent clean energy by 2050.
    As to the economic impact of closure, the Board addressed Levitan's
    conclusion about potential for negative resultant economic impact to the
    region. It explained that Levitan's economic impact analysis was based on a
    report concerning the Indian Point Nuclear Station in Westchester County,
    New York, an area with different demographics and a different economy than
    Salem County. According to the report, the relative impact of plant retirement
    in Salem County would likely be much greater compared to Westchester
    County and result in direct job loss not only to employees of the units but also
    to the ancillary businesses in the area. The Board concluded Salem County
    cannot afford this type of potential economic loss and that there are not enough
    employers in the county to support the layoffs from the closing units.
    Ultimately, the Board concluded had the ET and Levitan considered the
    two risk factors as well as the other externalities, and had they reviewed the
    financial filings as submitted by the applicants, the plants would have been
    deemed eligible to receive subsidies, as a matter of fact.            The Board
    A-3939-18
    30
    determined that Salem 1, Salem 2 and Hope Creek were eligible to receive
    ZECs and directed the EDCs to submit final tariffs consistent with its order. 3
    This appeal followed.
    V.
    On appeal, Rate Counsel argues that the Board's decision is arbitrary,
    capricious, and unreasonable because the record does not support the
    conclusion that the applicants satisfied the financial eligibility requirement
    codified at N.J.S.A. 48:3-87.5(e)(3), and advances other general adequacy
    challenges.   Notably, Rate Counsel does not contend on appeal that the
    applicants failed to satisfy any of the four remaining statutory criteria.
    Monitoring Analytics, P3 and NJLEUC also support reversal of the
    Board's decision, as does amicus curiae AARP.            PSEG Nuclear, Exelon,
    PSE&G, JCP&L, ACE and the Board, along with amicus curiae NEI, ask us to
    affirm the Board's decision. 4
    3
    One Board member, Commissioner Upendra J. Chivukula, dissented from
    the eligibility determination. Chivukula asserted the Board heavily considered
    the overall policy goal of achieving fifty-percent clean energy by 2030 and did
    not adequately consider its role as an economic regulator.
    4
    Amicus curiae IPI advocates for neither affirmation nor reversal but explains
    why the social cost of carbon referenced in the ZEC Act at N.J.S.A. 48:3-
    87.3(b)(8) is the best available estimate for valuing the harm caused by carbon
    dioxide emissions.       Similarly, Clean Air explains how nuclear plants
    contribute to cleaner air in New Jersey.
    A-3939-18
    31
    "Judicial review of agency determinations is limited."      Allstars Auto
    Grp., Inc. v. N.J. Motor Vehicle Comm'n, 
    234 N.J. 150
    , 157 (2018) (citing
    Russo v. Bd. of Trs., Police & Firemen's Ret. Sys., 
    206 N.J. 14
    , 27 (2011)).
    "[We] afford[] a 'strong presumption of reasonableness' to an administrative
    agency's exercise of its statutorily delegated responsibilities." In re Restrepo,
    Dep't of Corr., 
    449 N.J. Super. 409
    , 417 (App. Div. 2017) (quoting Lavezzi v.
    State, 
    219 N.J. 163
    , 171 (2014)); see In re N.J. Am. Water Co., 
    169 N.J. 181
    ,
    195 (2001) ("[A]n agency's administrative action is presumptively valid.").
    Thus, "[a]n administrative agency's final quasi-judicial decision will be
    sustained unless there is a clear showing that it is arbitrary, capricious, or
    unreasonable, or that it lacks fair support in the record." Allstars Auto, 234
    N.J. at 157 (quoting Russo, 
    206 N.J. at 27
    ); see also N.J.S.A. 48:2-46
    (explaining that this court may "review any order of the board [of Public
    Utilities] and . . . set aside such order in whole or in part when it clearly
    appears that there was no evidence before the board to support the same
    reasonably.").
    Rate Counsel argues there was error in the Board's rejection of its
    experts and methodology excluding operational risks, market risks and other
    non-realized costs from the applicants' certified cost projections. Rate Counsel
    also contends the ZEC Act's plain language required the applicants to
    A-3939-18
    32
    demonstrate that the nuclear power plant is projected to not fully cover its
    costs and risks, including operational risks, such as, operating costs higher
    than anticipated, along with market risks, such as market energy and capacity
    price volatility.
    "The goal in cases of statutory construction is simple. It is the court's
    duty to seek and give effect to the Legislature's intent."     Nw. Bergen Cty.
    Utils. Auth. v. Donovan, 
    226 N.J. 432
    , 443-44 (2016).          A "statute's plain
    language . . . is the 'best indicator' of legislative intent." State v. Rodriguez,
    
    238 N.J. 105
    , 113 (2019) (quoting DiProspero v. Penn, 
    183 N.J. 477
    , 492
    (2005)).    "When the Legislature's chosen words lead to one clear and
    unambiguous result, the interpretive process comes to a close, without the need
    to consider extrinsic aids." State v. Shelley, 
    205 N.J. 320
    , 323 (2011). "Only
    if there is ambiguity in the statutory language will we turn to extrinsic
    evidence," including legislative history. Richardson v. Bd. of Trs., Police &
    Firemen's Ret. Sys., 
    192 N.J. 189
    , 195-96 (2007).
    If a statute's plain language is ambiguous, we "are . . . warranted in
    placing considerable weight on the construction of the statute . . . by the
    administrative agency charged by the statute with the responsibility of making
    it work." In re PSE&G Co.'s Rate Unbundling, 
    167 N.J. 377
    , 384 (2001)
    (quoting Passaic Daily News v. Blair, 
    63 N.J. 474
    , 484 (1973)). Under those
    A-3939-18
    33
    circumstances, we "defer to 'the agency's interpretation . . . provided it is not
    plainly unreasonable.'" 
    Ibid.
     (quoting Merin v. Maglaki, 
    126 N.J. 430
    , 437
    (1992)). "Deference is particularly appropriate when, as here, the agency must
    construe and implement a new statute, 'or when the agency has been delegated
    discretion to determine the specialized and technical procedures for its tasks.'"
    In re Adoption of N.J.A.C. 7:26E-1.13, 
    377 N.J. Super. 78
    , 98-99 (App. Div.
    2005) (citation omitted). "However, a reviewing court is 'in no way bound by
    [an] agency's interpretation of a statute or its determination of a strictly legal
    issue.'" Allstars Auto, 234 N.J. at 158 (quoting Dep't of Children & Families
    v. T.B., 
    207 N.J. 294
    , 302 (2011)).
    Here, the ZEC Act's financial eligibility criterion states that an applicant
    must:
    demonstrate to the satisfaction of the [B]oard, through
    the financial and other confidential information
    submitted to the [B]oard pursuant to subsection a. of
    this section, and any other information required by the
    board, . . . that the nuclear power plant's fuel diversity,
    air quality, and other environmental attributes are at
    risk of loss because the nuclear power plant is
    projected to not fully cover its costs and risks, . . . and
    that the nuclear power plant will cease operations
    within three years unless the nuclear power plant
    experiences a material financial change[.]
    [N.J.S.A. 48:3-87.5(e)(3).]
    A-3939-18
    34
    The plain language of the subsection makes clear that the Legislature
    intended for the Board to consider the applicants' "costs and risks" when
    determining eligibility. Had the Legislature intended for the Board to exclude
    the applicants' operational and market risks when analyzing financial
    eligibility under subsection (e)(3) and to instead assess only whether the
    applicants were "projected to not fully cover [their] costs," it would not have
    included the words "and risks" after "costs."      In our view, to adopt Rate
    Counsel's position that the Board should have accepted the experts'
    methodology would render the Legislature's use of the words "and risks" in
    subsection (e)(3) meaningless, contrary to established principles of statutory
    construction.
    The plain language of N.J.S.A. 48:3-87.5(a) lends further support to the
    Board's interpretation of the ZEC Act and its rejection of the experts' opinions.
    Subsection (a) mandates that the applicants' certified cost projections include
    "operation and maintenance expenses, fuel expenses, including spent fuel
    expenses, non-fuel capital expenses, fully allocated overhead costs, [and] the
    costs of operational risks and market risks that would be avoided by ceasing
    operations," along with "any other information . . . to demonstrate that . . . the
    nuclear power plant is projected to not fully cover its costs and risks . . . ."
    N.J.S.A. 48:3-87.5(a). It defines operational risks as including "the risk that
    A-3939-18
    35
    operating costs will be higher than anticipated because of new regulatory
    mandates or equipment failures and the risk that per-megawatt-hour costs will
    be higher than anticipated because of a lower than expected capacity factor."
    
    Ibid.
     It defines market risks as including "the risk of a forced outage and the
    associated costs arising from contractual obligations, and the risk that output
    from the nuclear power plant may not be able to be sold at projected levels."
    
    Ibid.
    Had the Legislature intended for the Board to exclude the applicants'
    operational and market risks from their certified cost projections when
    analyzing financial eligibility under subsection (e)(3), there would have been
    no need for the Legislature to require applicants to provide information about
    their operational and market risks in subsection (a), or to define those terms.
    Similarly, had the Legislature intended for the Board to exclude operation and
    maintenance expenses, fuel expenses, including spent fuel expenses, non-fuel
    capital expenses and fully allocated overhead costs from the "costs" referenced
    in subsection (e)(3) when analyzing financial eligibility, there would have
    been no need for the Legislature to require applicants to provide this
    information to the Board.
    In sum, the experts' methodology was inconsistent with the ZEC Act's
    plain language, which does not exclude operational risks, market risks and
    A-3939-18
    36
    other non-realized costs from the financial eligibility analysis. Thus, it was
    reasonable for the Board to reject the experts' opinions and to consider those
    categories of costs and risks. The Board was under no obligation to adopt the
    opinions of respondents' experts or the expert consultant that it retained to
    assist its staff. Board staff are charged with making recommendations to the
    Board. N.J. Dep't of Pub. Advocate v. Bd. of Pub. Utils., 
    189 N.J. Super. 491
    ,
    518 (App. Div. 1983). But per the plain language of N.J.S.A. 48:3-87.5, the
    ultimate eligibility determination for ZECs is to be made by the Board alone.
    Additionally, the Board's decision concerning the applicants' financial
    eligibility for ZECs is amply supported by the voluminous financial
    submissions contained in the record, including but not limited to, the
    applications and the comments. In compliance with N.J.S.A. 48:3-87.5(e)(3),
    PSEG Nuclear certified on behalf of each applicant that each plant's projected
    costs exceeded its projected revenues and that each plant will cease operations
    within three years unless it experiences a material financial change. PSEG
    Nuclear submitted extensive financial information to support each plant's
    certified cost projections, summarized in charts listing various subcategories of
    costs and revenues showing that its costs and risks were projected to exceed its
    revenues by millions of dollars each year.        PSEG Nuclear explained its
    inclusion of operational and market risks, consistent with the ZEC Act's
    A-3939-18
    37
    definition of those terms, along with its inclusion of spent fuel, support
    services, fully allocated overhead and capital expenditures as part of each
    plant's certified cost projections.
    Consistent with the ZEC Act's plain language, the Board properly
    considered the applicants' operational and market risks, spent fuel costs,
    support services costs, fully allocated overhead costs, and capital expenditures
    included in their certified cost projections as part of its financial eligibility
    determination.    The Board also considered the ET's recommendations, the
    experts' independent analyses, the comments, among other information, and
    came to the reasoned conclusion that each plant is projected to not fully cover
    its costs and risks, and will cease operations within three years absent a
    material financial change, in satisfaction of N.J.S.A. 48:3-87.5(e)(3).
    Although Rate Counsel does not contend that the applicants failed to
    satisfy the four remaining statutory eligibility criteria, it nonetheless asserts
    other general adequacy challenges pertaining to the Board's findings and
    conclusions. Rate Counsel claims the Board: (1) failed to acknowledge that
    each of the five eligibility criteria must be met; (2) allowed "considerations
    beyond the five statutory criteria to color its analysis" by giving them greater
    weight; and (3) based its decision on a "fear" that PSEG Nuclear would close
    all three plants if it did not receive ZECs for each of them. We disagree.
    A-3939-18
    38
    Despite the fact that the Board's discussion focused primarily upon the
    financial eligibility criterion, N.J.S.A. 48:3-87.5(e)(3), as it disagreed with the
    ET's findings and conclusions pertaining to financial eligibility, it also
    explained that applicants must satisfy all five statutory criteria. The Board
    summarized each of them in its decision in three different places, and
    recounted the ET's determination that the applicants had satisfied the first,
    fourth, and fifth criteria, explaining: (1) the units were "licensed to operate
    beyond 2030"; (2) the units "have not [or] are not receiving any other
    subsidies"; and (3) "the appropriate application fees were received."
    The determinations track the plain language of the eligibility criteria
    found at N.J.S.A. 48:3-87.5(e)(1), (4), and (5). Although the Board did not
    expressly state that it was adopting the ET's findings as to the first, fourth, and
    fifth criteria, it did not disagree with those findings, which are adequately
    supported by the record and not disputed on appeal. Thus, we can infer from
    the broader context of the Board's decision that it incorporated those findings
    and conclusions as to the first, fourth, and fifth criteria.
    Although the Board did not expressly state that the applicants had
    satisfied N.J.S.A. 48:3-87.5(e)(2), the Board's findings, coupled with the ET's
    more detailed determinations, support the implied conclusion that each plant,
    as a zero-emission facility, makes a significant and material contribution to the
    A-3939-18
    39
    air quality in the State by minimizing emissions that result from electricity
    consumed in New Jersey, minimizes harmful emissions that adversely affect
    the citizens of the State, and that retirement would significantly and negatively
    impact New Jersey's ability to comply with state air emissions reduction
    requirements, particularly with regard to global warming and ambient air
    quality. N.J.S.A. 48:3-87.5(e)(2).
    Rate Counsel's assertion that the Board weighed certain other
    considerations, including fuel diversity, fuel security, and the economic impact
    of closure on the region and the State, more heavily than the eligibility criteria
    codified at N.J.S.A. 48:3-87.5(e), is unsupported by the record.         There is
    nothing in the Board's decision to indicate that it weighed these factors more
    heavily than the statutory criteria. The extensive record in this case belies
    Rate Counsel's contention that the Board's decision is based on a fear that
    regardless of whether the eligibility criteria were met PSEG Nuclear would
    close the plants if it did not get subsidies for all three units.
    Accordingly, Rate Counsel has not made a clear showing that the
    Board's ZEC eligibility determination is arbitrary, capricious, or unreasonable,
    or lacks fair support in the record. Allstars Auto, 234 N.J. at 157 (quoting
    Russo, 
    206 N.J. at 27
    ).
    A-3939-18
    40
    VI.
    In its second point, Rate Counsel contends the Board's decision is
    arbitrary, capricious, and unreasonable because it failed to reduce the $0.004 -
    per-kilowatt-hour charge established in the ZEC Act at N.J.S.A. 48:3-
    87.5(j)(1). Rate Counsel relies on a different section of the statute, N.J.S.A.
    48:2-21(b), to support its contention, claiming that it mandates that the Board
    "[f]ix just and reasonable" rates to be imposed "by any public utility" and that
    the Board was required to harmonize N.J.S.A. 48:2-21(b) with the ZEC Act.
    Respondent NJLEUC and amicus curiae AARP support reversal for the same
    reasons. We reject this argument for the following reasons.
    Citing N.J.S.A. 48:3-87.5(j), the Board found the ZEC Act required each
    EDC to file with the Board a tariff to recover from its retail distribution
    customers a charge in the amount of $0.004 per kilowatt-hour, which,
    according to the ZEC Act, reflects the emissions avoidance benefits associated
    with the continued operation of selected nuclear power plants. It furth er found
    that the ZEC Act provided that the Board shall approve the appropriate tariff
    after notice, the opportunity for comment, and public hearings, within sixty
    days after the EDCs' tariffs were filed.    The applicants for ZECs are not
    regulated utilities and do not have authorized rates of return, nor are they
    subject to rate cases. Upon finding that each applicant was eligible to receive
    A-3939-18
    41
    ZECs, the Board directed the EDCs to submit final tariffs consistent with the
    Board's order.
    "Administrative agency power derives solely from a grant of authority
    by the Legislature." Gen. Assembly of N.J. v. Byrne, 
    90 N.J. 376
    , 393 (1982).
    "An administrative agency exercises its delegated authority and applies its
    intended expertise pursuant to the Legislature's enabling act that frames the
    performance of the agency's assigned tasks." Acoli v. N.J. State Parole Bd.,
    
    224 N.J. 213
    , 226 (2016). We "review de novo an agency's interpretation of a
    statute and legal conclusions." Kaminskas v. State of N.J., Dep't of Law &
    Pub. Safety, 
    236 N.J. 415
    , 422 (2019). As noted, "[w]hen considering the
    meaning of a statutory provision, absent any legislative intent to the contrary,
    courts must give effect to the language of the provision."       PSE&G's Rate
    Unbundling, 
    167 N.J. at 383-84
    . "If a statute's plain language is clear, we
    apply that plain meaning and end our inquiry." Garden State Check Cashing
    Serv., Inc., v. State Dep't of Banking & Ins., 
    237 N.J. 482
    , 489 (2019).
    The ZEC Act's plain language makes clear that the Legislature did not
    authorize the Board to alter the $0.004-per-kilowatt-hour charge at the time of
    its initial eligibility determination. Under the plain meaning rule of statutory
    construction, "the Legislature's choice of the word 'shall,' . . . is ordinarily
    intended to be mandatory, not permissive." Jersey Cent. Power & Light Co. v.
    A-3939-18
    42
    Melcar Utility Co., 
    212 N.J. 576
    , 587-88 (2013).          Thus, N.J.S.A. 48:3-
    87.5(j)(1), through its use of the word "shall," requires the Board to effectuate
    the $0.004-per-kilowatt-hour charge to fund the ZEC program as follows:
    The [B]oard shall order the full recovery of all
    costs associated with the electric public utility's
    required procurement of ZECs and with the board's
    implementation of the ZEC program under this act,
    through a non-bypassable, irrevocable charge imposed
    on the electric public utility's retail distribution
    customers.     Within 150 days after the date of
    enactment of this act, each electric public utility shall
    file with the [B]oard a tariff to recover from its retail
    distribution customers a charge in the amount of
    $0.004 per kilowatt-hour which reflects the emissions
    avoidance benefits associated with the continued
    operation of selected nuclear power plants. Within
    [sixty] days after the tariff filing required pursuant to
    this paragraph, after notice, the opportunity for
    comment, and public hearing, the [B]oard shall
    approve the tariff, provided that it is consistent with
    the provisions of this subsection. No later than the
    date of the [B]oard's order establishing the initial
    selected nuclear power plants to receive ZECs, each
    electric public utility shall implement the tariff and
    begin collecting from its retail distribution customers
    the approved charge.
    Subsection (j)(3) of N.J.S.A. 48:3-87.5 specifies two limited scenarios
    under which the Board may reduce the per-kilowatt-hour charge to ensure that
    the ZEC program remains affordable to New Jersey retail distribution
    customers after its initial eligibility determination. These may apply if the
    Board determines that a reduced charge will nonetheless be sufficient to
    A-3939-18
    43
    achieve the state's air quality and other environmental objectives by preventing
    the retirement of the nuclear power plants that meet the eligibility criteria
    established pursuant to subsections (d) and (e) of this section.              Neither
    scenario is present here.
    Under the first scenario, if the above criteria are met, "the [B]oard may,
    in its discretion, reduce the per-kilowatt hour charge imposed by paragraph (1)
    of this subsection starting in the second three year eligibility period and for
    each subsequent three year eligibility period thereafter . . . ." N.J.S.A. 48:3 -
    87.5(j)(3)(a). Under the second scenario, if the above criteria are met, and "the
    [B]oard does not certify any nuclear power plants for a subsequent eligibility
    period pursuant to this Act, the [B]oard may, in its discretion, reduce the per
    kilowatt-hour charge imposed pursuant to paragraph (1) of this subsection . . .
    in the final year of the first eligibility period . . . ." N.J.S.A. 48:3-87.5(j)(3)(c).
    Had the Legislature intended to grant the Board authority to reduce the
    $0.004-per-kilowatt-hour charge at the time of its initial eligibility
    determination, it would have said so. Instead, it carefully limited the Board's
    authority to alter the $0.004-per-kilowatt-hour charge. In short, the Board
    does not have the authority to override the Legislature's imposition of the
    $0.004-per-kilowatt-hour charge at the time of its initial eligibility
    determinations. See Jersey Cent. Power & Light Co., 212 N.J. at 600 ("[A]n
    A-3939-18
    44
    administrative agency can only act reasonably within the scope of its delegated
    authority.").
    N.J.S.A. 48:2-21(b), last amended in 1962, states, in relevant part:
    The [B]oard may after hearing, upon notice, by order
    in writing:
    1. Fix just and reasonable individual rates, joint
    rates, tolls, charges or schedules thereof, as well as
    commutation, mileage and other special rates which
    shall be imposed, observed and followed thereafter by
    any public utility, whenever the [B]oard shall
    determine any existing rate, toll, charge or schedule
    thereof . . . to be unjust, unreasonable, insufficient or
    unjustly discriminatory or preferential. In every such
    proceeding the [B]oard shall complete and close the
    hearing within [six] months and enter its final order
    within [eight] months after the filing of the order of
    the [B]oard initiating such proceeding, when such
    proceeding is on the [B]oard's own motion; or after
    issue is joined through the filing of an answer to a
    complaint, when such proceeding is initiated by
    complaint.
    It is clear from the plain language of N.J.S.A. 48:2-21(b) that it applies
    to rate hearings involving public utilities either initiated on the Board's own
    motion or by complaint. "A rate hearing involves (a) the determination of the
    value of utility property (rate base), (b) an examination of utility expenses, and
    (c) the fixing of a fair rate of return to investors. The result is the base rate
    which the utility may charge its customers." In re Jersey Cent. Power & Light
    Co., 
    85 N.J. 520
    , 529 (1981).
    A-3939-18
    45
    The matter before the Board was not a rate hearing pursuant to N.J.S.A.
    48:2-21(b). But rather, it was implementation of the ZEC program under the
    ZEC Act, which was enacted decades after N.J.S.A. 48:2-21(b), and eligibility
    determinations on the three ZEC applications made by unregulated nuclear
    power plants. Although N.J.S.A. 48:2-21(b) and N.J.S.A. 48:3-87.5(j) are both
    included in Title 48, they do not reference each other and were not designed to
    serve a common purpose.        Marino v. Marino, 
    200 N.J. 315
    , 331 (2009).
    Therefore, it is unnecessary to interpret these two provisions in pari materia
    with each other. See Richard's Auto City v. Dir., Div. of Taxation, 
    140 N.J. 523
    , 540 (1995) ("Aside from the[ir] clearly distinct purposes . . . the fact that
    the acts were not enacted during the same time and make no specific
    references to each other further indicates that they were not intended to be read
    in pari materia.").
    Rate Counsel's reliance on In re Proposed Increase Intrastate Industrial
    Sand Rates, 
    66 N.J. 12
    , 14 (1974), is similarly unavailing. There, Central
    Railroad Company of New Jersey initiated a rate proceeding for a freight
    carriage rate increase affecting "the transportation of industrial sand from
    point of origin to several glass manufacturing companies in Northern New
    Jersey."   
    Id. at 16
    . The Board found that the rate increase was "just and
    reasonable," approving it without establishing a rate base and the fair rate of
    A-3939-18
    46
    return. 
    Id. at 17-18
    . We reversed and remanded the matter because the Board
    failed to establish "a rate base and a fair rate of return thereon." 
    Id. at 18
    . The
    Supreme Court affirmed. 
    Id. at 19, 29
    .
    Based on our review, Industrial Sand also does not support the
    proposition urged by Rate Counsel that the Board had authority to reduce the
    statutorily   mandated    $0.004-per-kilowatt-hour      charge   to   ensure     its
    constitutionality during the ZEC proceedings. The only relevant takeaway
    from Industrial Sand is that aggrieved parties may seek relief via other
    remedies, either "in the legislative halls" or in the courts by way of an action to
    restrain enforcement of a statute alleged to be unconstitutional, where a rate is
    set either unreasonably low and confiscatory, or unreasonably high and
    extortionate upon the public. 
    66 N.J. at 23-24, 29
    .
    The parties' remaining arguments are without sufficient merit to warrant
    discussion in a written opinion. R. 2:11-3(e)(1)(E).
    Affirmed.
    A-3939-18
    47