Enduro Operating LLC v. Echo Prod., Inc. , 413 P.3d 866 ( 2018 )


Menu:
  •  1        IN THE SUPREME COURT OF THE STATE OF NEW MEXICO
    2 Opinion Number:______________
    3 Filing Date: February 15, 2018
    4 NO. S-1-SC-36225
    5 ENDURO OPERATING LLC,
    6        Plaintiff-Respondent,
    7 v.
    8   ECHO PRODUCTION, INC.; TALUS, INC.;
    9   TWIN MONTANA, INC.; CIMARRON RIVER
    10   INVESTMENTS, LLC; CMW INTERESTS, INC.;
    11   D2 RESOURCES, LLC; ELGER EXPLORATION
    12   INC.; PLAINS PRODUCTION, INC.; SOLIS
    13   ENERGY LLC; THE ALLAR COMPANY;
    14   KEN SELIGMAN; and W. GLEN STREET, JR.,
    15        Defendants-Petitioners.
    16 ORIGINAL PROCEEDING ON CERTIORARI
    17 Lisa B. Riley, District Judge
    18 Rodey, Dickason, Sloan, Akin & Robb, P.A.
    19 Edward R. Ricco
    20 Albuquerque, NM
    21   Cotton, Bledsoe, Tighe & Dawson, P.C.
    22   Jared Mark Moore
    23   Terry W. Rhoads
    24   Midland, TX
    25 Michael J. Henry, Attorney at Law, P.C.
    1 Michael J. Henry
    2 Forth Worth, TX
    3   for Petitioners Echo Production, Inc.; Talus, Inc.; Twin Montana, Inc.; Cimarron
    4   River Investments, LLC; CMW Interests, Inc.; D2 Resources, LLC; Elger
    5   Exploration, Inc.; Plains Production, Inc.; Solis Energy LLC; The Allar Company;
    6   and W. Glenn Street, Jr.
    7 McCormick, Caraway, Tabor & Byers, L.L.P.
    8 Cas. F. Tabor
    9 Albuquerque, NM
    10 for Petitioner Ken Seligman
    11   Hinkle Shanor LLP
    12   Andrew J. Cloutier
    13   Parker B. Folse
    14   Roswell, NM
    15 for Respondent
    1                                       OPINION
    2 CHÁVEZ, Justice.
    3   {1}   Echo and Enduro are two of several parties to a joint operating agreement1
    4 (JOA). Under the JOA, Echo, as a party wishing to undertake a new drilling project,
    5 had to provide notice of the proposed project to the other parties to the JOA, who then
    6 had thirty days to decide whether to opt in or out of the project. By opting in, a party
    7 agrees to share in the cost and risk of the project. If a party opts out of the
    8 project—as Enduro did in this case—then the party is deemed “non-consenting,” and
    9 is exempt from any of the cost or risk associated with the new project, but cannot
    10 share in any of the profits from the new project until the consenting parties have
    11 recovered four-hundred percent of the labor and equipment costs invested in the new
    12 project. For the consenting parties to recover the nonconsenting parties’ forfeited
    13 share of profits, the consenting parties must “within ninety (90) days after the
    14 expiration of the notice period of thirty (30) days . . . actually commence the proposed
    15 operation and complete it with due diligence.” Together, the JOA’s provisions
    16 provide the consenting parties with 120 days after proposing the project to “actually
    17 commence” the operation, which in this case is the drilling of an oil well. If the
    18      1
    The substance of the parties’ JOA was adopted, with slight modification, from
    19 a model form published by the American Association of Petroleum Landmen
    20 (A.A.L.P) Form 610-1982.
    1 consenting parties do not commence the proposed operation within 120 days, but one
    2 or more of them “still desires to conduct said operation,” then the parties wishing to
    3 proceed with the operation must repropose the operation to the nonconsenting parties
    4 “as if no prior proposal had been made.”
    5   {2}   The question before us is what activities are adequate as a matter of law to
    6 satisfy the contractual requirement that a consenting party actually commence the
    7 drilling operation. The Court of Appeals in Johnson v. Yates Petroleum Corp.,
    8 1999-NMCA-066, ¶ 11, 
    127 N.M. 355
    , 
    981 P.2d 288
    , held that “any activities in
    9 preparation for, or incidental to, drilling a well are sufficient” even if “only the most
    10 modest preparations for drilling have been made.” (internal quotation marks omitted)
    11 (citing Howard R. Williams & Charles J. Meyers, 3 Oil and Gas Law § 618.1 at
    12 320-21 (1998)). In Johnson, the Court of Appeals found the following combination
    13 of activities adequate as a matter of law to satisfy the actual commencement
    14 requirement: (1) staking and surveying the location, (2) filing for and receiving a
    15 permit to drill a well, (3) entering into an agreement with a contractor to have the
    16 location of the well prepared for drilling, and (4) beginning the clearing of brush and
    17 the leveling of the area. 
    Id. at ¶
    7.
    18   {3}   In its opinion below, the Court of Appeals concluded that the language in
    2
    1 Johnson indicating that “any” preparatory activities would be sufficient was too
    2 permissive. See Enduro Operating LLC v. Echo Prod., Inc., 2017-NMCA-018, ¶¶ 25,
    3 29, 
    388 P.3d 990
    . The Court of Appeals was persuaded that Echo’s lack of on-site
    4 activity at the proposed well site, other than surveying and staking, and lack of a
    5 permit to commence drilling was evidence as a matter of law that Echo had not
    6 actually commenced drilling operations. 
    Id. ¶¶ 22,
    29. The Court of Appeals reversed
    7 the district court’s grant of summary judgment in favor of Echo and remanded for an
    8 entry of summary judgment in favor of Enduro. 
    Id. ¶ 31.
    We reverse the Court of
    9 Appeals and hold that the failure to obtain an approved drilling permit within the
    10 relevant commencement period is not dispositive. A party may prove that it has
    11 actually commenced drilling operations with evidence that it committed resources,
    12 whether on-site or off-site, that demonstrate its present good-faith intent to diligently
    13 carry on drilling activities until completion.
    14 I.      DISCUSSION
    15 A.      Commencement of Operations
    16 1.      A party has commenced operations if it engages in actions that
    17         demonstrate a present good-faith intent to diligently carry on drilling
    18         activities until completion
    19   {4}   When resolving a dispute over the meaning of terms in a contract, our goal is
    3
    1 to “ascertain the intentions of the contracting parties with respect to the challenged
    2 terms at the time they executed the contract.” Strata Prod. Co. v. Mercury Expl. Co.,
    3 1996-NMSC-016, ¶ 29, 
    121 N.M. 622
    , 
    916 P.2d 822
    . “[I]f the parties attached
    4 different meanings to [disputed] language, the court’s task is the more complex one
    5 of applying a standard of reasonableness to determine which party’s intention is to
    6 be carried out at the expense of the other’s.” Allan E. Farnsworth, Farnsworth on
    7 Contracts 285 (3rd ed. 2004). To determine the reasonable construction of contract
    8 terms, “[w]ords and other conduct are interpreted in the light of all the circumstances,
    9 and if the principal purpose of the parties is ascertainable it is given great weight.”
    10 Restatement (Second) of Contracts § 202 (1981).
    11   {5}   Cases interpreting the meaning of commencement clauses in the context of oil
    12 and gas lease agreements provide insight into how we should construe the
    13 commencement clause in the parties’ JOA. Only a Texas court has interpreted the
    14 meaning of the commencement provision in the model-form JOA used by the parties
    15 in this case, and the Texas court also relied on several lease agreement cases to
    16 determine the meaning of “actually commence” under the model-form JOA. See
    17 Valence Operating Co. v. Anadarko Petroleum Corp., 
    303 S.W.3d 435
    , 438-41 (Tex.
    
    18 Ohio App. 2010
    ).
    4
    1   {6}   In the context of lease agreements, the majority rule is that a party has
    2 commenced where “modest preparations for drilling have been made” so long as the
    3 preparations are “part of a good-faith effort to obtain production.” See 3 Patrick H.
    4 Martin & Bruce M. Kramer, Williams & Meyers Oil and Gas Law, § 618.1 at 319,
    5 321 (2016). Although actual drilling would obviously suffice as evidence of “actual
    6 commencement,” actual drilling is not required. See Eugene Kuntz, A Treatise on the
    7 Law of Oil and Gas, § 32.3(b) at 75 & n.4 (1989) (collecting cases supporting the
    8 proposition that “it is generally held that acts which are preparatory to drilling are
    9 sufficient to constitute the commencement of a well and that it is not essential that the
    10 lessee be in the process of making a hole”).
    11   {7}   Preparatory activity at the well site is also sufficient to prove that a drilling
    12 operation has actually commenced. As one treatise explained:
    13                Where the lessee has the ability to drill the well to completion and
    14         the lessor can make no showing the lessee lacks a present intent to
    15         diligently carry on drilling activities until completion, very little in the
    16         way of physical activities must be performed on the site to support a
    17         conclusion that the lessee has commenced operations . . . . A minimum
    18         of physical activities seems to include the staking of the well site plus
    19         some acts on the land itself such as leveling the site and digging slush
    20         pits.
    21 Owen L. Anderson, et al., Hemingway Oil and Gas Law and Taxation, § 6.7 at 293
    22 (4th ed. 2004). See also, e.g., Duffield v. Russell, 
    1899 WL 1336
    , at *2 (Ohio Cir. Ct.
    5
    1 May 1899), aff’d, 
    63 N.E. 1127
    (1902) (holding that a party demonstrated
    2 commencement where on the last day of the commencement period it staked the well
    3 and cut a “portion of the timber” to be used for the drilling rig); Petersen v. Robinson
    4 Oil & Gas Co., 
    356 S.W.2d 217
    , 219-20 (Tex. Civ. App. 1962) (holding that a party
    5 demonstrated commencement where it staked the well and, on the last day of the
    6 commencement period, moved a maintainer onto land and spent two hours leveling
    7 the well location). In each of these cases, the commitment of resources at the drilling
    8 site was sufficient evidence to prove the operator had actually commenced drilling
    9 operations because the evidence proved the operator’s present good-faith intent to
    10 diligently carry on drilling activities until completion. Other cases have found a
    11 combination of on-site and off-site activity was adequate to prove that an operator has
    12 commenced drilling activities. See Kaszar v. Meridian Oil & Gas Enters., Inc., 499
    
    13 N.E.2d 3
    , 4-5 (Ohio Ct. App. 1985) (holding that a party demonstrated
    14 commencement where it staked the well, cleared the well site, and filed paperwork
    15 with the Securities and Exchange Commission); Jones v. Moore, 
    338 P.2d 872
    , 874-
    16 75 (Okla. 1959) (holding that a party demonstrated commencement where on the last
    17 day of the commencing period it staked the well, dug a slush pit, and signed
    18 equipment contracts).
    6
    1   {8}   The question we must still answer is whether the off-site commitment of
    2 resources can ever be adequate evidence of the parties present good-faith intent to
    3 diligently carry on drilling activities until completion where the only on-site activity
    4 was the surveying and staking of the well. In its opinion, the Court of Appeals relied
    5 heavily on the Valence case to discount the evidentiary value of off-site activities.
    6 See Enduro, 2017-NMCA-018, ¶ 26. The Valence court held that when “there is
    7 doubt or controversy as to the intent of the party claiming to have commenced
    8 operations for drilling by performing preparatory acts, the question is one of mixed
    9 law and fact and should be submitted to the 
    jury.” 303 S.W.3d at 441
    . More
    10 importantly, the Valence court held that the following ‘“backroom preparations’ . . .
    11 with no on-site activity except a preliminary staking of wells” were not sufficient, as
    12 a matter of law, to prove the party had actually commenced drilling operations: (1)
    13 preparing an authorization for expenditures, (2) receiving a topographic map of the
    14 well locations, (3) staking locations, (4) photographing the well sites, (5) obtaining
    15 a preliminary list of instruments regarding title, (6) holding several meetings to
    16 discuss locations and how to build on the locations, (7) preparing detailed cost and
    17 facility estimates for all wells, (8) preparing preliminary run sheets, and (9) obtaining
    18 drilling permits for all four wells. 
    Id. at 440.
    Instead, it was for the jury to determine
    7
    1 whether these activities “showed a bona fide intent to commence actual work on the
    2 proposed operation before the deadline and proceed with diligence to the completion
    3 of the wells.” 
    Id. at 441.
    4   {9}    Importantly, in Valence, the operator had not signed drilling contracts, built
    5 access roads, restaked the well locations, secured title opinions, and had not actually
    6 begun drilling, before the deadline for actually commencing the drilling operation.
    7 
    Id. at 440.
    Although the Valence court made it clear that “[a]ctual drilling is not
    8 necessary in order to comply with an obligation to commence operations for drilling,”
    9 
    id., we do
    not know if the Valence court would have held that proof of one or more
    10 of the latter activities was sufficient as a matter of law to prove commencement.
    11   {10}   Building access roads and/or restaking well locations involves the commitment
    12 of resources. And, as one commentator explained, the focus of a commencement
    13 clause is on whether a party has taken actions that amount to an “irrevocable
    14 commitment to conduct operations, to completion, on the lease land. The best
    15 evidence of this, absent actual drilling of the premises, is an enforceable contract with
    16 a third party to drill a well on the leased land.” Martin & Kramer, supra, § 618.1 at
    17 318-19 n.10.2 (quoting 1 D. Pierce, Kansas Oil and Gas Handbook 9.34 (1991)). We
    18 agree that an enforceable drilling contract that commits an operator’s resources is
    8
    1 sufficient evidence, as a matter of law, to establish that the operator actually
    2 commenced drilling operations, even in the absence of on-site activities.
    3   {11}   We also conclude that a drilling permit is not essential for an operator to prove
    4 that it actually commenced drilling operations.               The Court of Appeals
    5 overemphasized the importance of obtaining an approved drilling permit within the
    6 commencement deadline. The court relied on a provision in the New Mexico
    7 Administrative Code (NMAC) stating that the purpose of the drilling permit rules was
    8 to “require an operator to obtain a permit prior to commencing drilling” and
    9 concluded that it would be condoning unpermitted drilling by deciding that a party
    10 could commence operations without a permit. Enduro, 2017-NMCA-018, ¶ 22
    11 (quoting 19.15.14.6 NMAC) (internal quotation marks omitted). One jurisdiction has
    12 held that commencement cannot occur without a permit. See Goble v. Goff, 42
    
    13 N.W.2d 845
    , 846-47 (Mich. 1950). However, the Texas Court of Appeals, in a later
    14 case dealing with language similar to the language in New Mexico’s permit
    15 regulations, declined to follow Goble and concluded that the absence of a permit
    16 would not preclude a determination that a party commenced operations. Gray v.
    17 Helmerich & Payne, Inc., 
    834 S.W.2d 579
    , 582 (Tex. App. 1992). The court’s
    18 reasoning in Gray is persuasive.
    9
    1   {12}   In Gray, the court held that the language in the Texas Administrative Code
    2 should not control the meaning of the language in the party’s contract because the
    3 code and the contract were drafted to serve different purposes. 
    Id. The court
    4 explained that an oil and gas lease is a private agreement between two parties that is
    5 designed to allocate property rights between the lessor and lessee. See 
    id. By 6
    contrast, the Gray court concluded that the Texas Administrative Code provision,
    7 which states that “[o]perations of drilling . . . shall not be commenced until the permit
    8 has been granted,” was designed to carry into effect the state’s conservation laws.
    9 
    Gray, 834 S.W.2d at 579
    , 582 (omission original) (quoting 16 Tex. Admin. Code §
    10 3.5(c)).
    11   {13}   The difference in purpose between the NMAC provisions and the JOA
    12 provisions convinces us that the intended meaning underlying the phrase “actually
    13 commence the proposed operations” in the JOA is different from the phrase
    14 “commencing drilling” in the NMAC. The NMAC requires a party to file a “[r]eport
    15 of commencement         of   drilling   operations”    within    ten   days   following
    16 “commencement” and the report “shall indicate the hour and the date the operator
    17 spudded2 the well.” 19.15.7.14(C) NMAC. The majority of cases that have looked
    2
    18         Spudding in is defined as “[t]he first boring of the hole in the drilling of an
    19 oil well.” 8 Martin & 
    Kramer, supra, at 996
    (2017).
    10
    1 at commencement clauses in private contracts have found that actual spudding is not
    2 required. See, e.g., Kuntz, supra, § 32.3(b) at 75 & n.4 (1989). Hence, the language
    3 in the JOA was not only designed to serve a different purpose than the language in
    4 19.15.14.6 NMAC but was also likely used with a different intended meaning.
    5   {14}   Several courts have upheld findings of commencement when the party had not
    6 obtained a drilling permit within the primary term. See Henry v. Chesapeake
    7 Appalachia, L.L.C., 
    739 F.3d 909
    , 912-13 (6th Cir. 2014); Cason v. Chesapeake
    8 Operating, Inc., 47,084 pp. 10-11 (La. App. 2 Cir. 4/11/12), 
    92 So. 3d 436
    , 442-43;
    9 
    Gray, 834 S.W.2d at 582
    . We also note that even if Echo’s drilling permit was
    10 approved prior to the deadline, it would have said little about its concurrent good-
    11 faith intent to diligently carry on drilling activities until completion because the
    12 permit was valid for two years and did not require the spudding of a well within any
    13 particular time period.
    14   {15}   Without a clear indication in the JOA that the parties intended to require a
    15 permit before a party can demonstrate commencement, the language in the NMAC
    16 should not control the meaning of the JOA. Here, as in Gray, we conclude that the
    17 JOA and the NMAC serve different purposes. The JOA that the parties used was
    18 adopted from a model form “commonly used in the oil and gas industry in New
    11
    1 Mexico and other producing states to set forth the arrangement between interest
    2 owners as to exploration and development of jointly owned interests.” Nearburg v.
    3 Yates Petroleum Corp., 1997-NMCA-069, ¶ 2, 
    123 N.M. 526
    , 
    943 P.2d 560
    4 (discussing A.A.P.L. Form 610–1977).             Its purpose is to allocate rights and
    5 responsibilities between the individual parties, whereas the purpose of NMAC
    6 permitting requirements is to carry out the commission’s duty to promulgate rules
    7 relating to “the conservation of oil and gas and the prevention of waste of potash as
    8 a result of oil or gas operations in this state.” NMSA 1978, § 70-2-6(A) (1979).
    9 Accordingly, we disagree with the Court of Appeals and hold that when an operator
    10 has applied for but has not obtained an approved drilling permit within the
    11 commencement period, the operator is not precluded from relying on other activities
    12 to demonstrate that it actually commenced drilling operations.
    13   {16}   In summary, unless the parties’ include language in their contract indicating
    14 otherwise, to prove that an operator has actually commenced drilling operations: (1)
    15 actual drilling is conclusive proof, but is not necessary, (2) obtaining a permit is not
    16 essential, (3) activities such as leveling the well location, digging a slush pit, or other
    17 good-faith commitment of resources at the drilling site will suffice as evidence of the
    18 parties’ present intent to diligently carry on drilling activities until completion, and
    12
    1 (4) the off-site commitment of resources, such as entering into an enforceable drilling
    2 contract requiring the diligent completion of the well, will also suffice as evidence
    3 that the operator actually commenced drilling operations. With these principles in
    4 mind we turn next to consider the summary judgment motions in this case.
    5 2.       Decisions to grant summary judgment motions are reviewed de novo
    6   {17}   Almost four years after Echo sent notice of its proposed well operation Enduro
    7 filed a complaint against Echo and the other defendants for breach of contract,
    8 conversion, violation of the Oil and Gas Proceeds Payment Act under NMSA 1978,
    9 Sections 70-10-1 to 6 (1985), and declaratory relief. The parties filed a series of
    10 cross-motions for summary judgment, three of which addressed whether Echo had
    11 commenced operations under the terms of the JOA. On January 14, 2015, the district
    12 court held a consolidated hearing on all of the motions for summary judgment. The
    13 court granted Echo’s motion for summary judgment and issued a final judgment in
    14 Echo’s favor on February 3, 2015. The court then awarded attorneys’ fees against
    15 Enduro consistent with NMSA 1978, Section 70-10-6 (1991). Enduro appealed both
    16 the order granting summary judgment on the issue of commencement and the order
    17 awarding attorneys’ fees.
    18   {18}   Summary judgment on whether Echo had actually commenced drilling
    13
    1 operations would only be appropriate if “there are no genuine issues of material fact”
    2 and either Echo or Enduro is “entitled to judgment as a matter of law.” See Encinias
    3 v. Whitener Law Firm, P.A., 2013-NMSC-045, ¶ 6, 
    310 P.3d 611
    (quoting Self v.
    4 United Parcel Serv., Inc., 1998-NMSC-046, ¶ 6, 
    126 N.M. 396
    , 
    970 P.2d 582
    )
    5 (internal quotation marks omitted). We review the grant of a summary judgment de
    6 novo, viewing “the facts in a light most favorable to the party opposing summary
    7 judgment and draw[ing] all reasonable inferences in support of a trial on the merits”
    8 because summary judgment is a “drastic remedy.” 
    Id. ¶ 6
    (internal quotation marks
    9 and citation omitted).
    10 3.       An issue of material fact pertinent to whether Echo timely commenced
    11          drilling operations must be resolved by the factfinder
    12   {19}   On December 1, 2010, Echo sent Enduro’s predecessor in interest, Conoco
    13 Phillips, notice that Echo was proposing a plan to drill a new well (6H Well). On
    14 December 28, Conoco “elected to not participate in the drilling of the” 6H Well. On
    15 December 29, 2010, Enduro executed an agreement to purchase Conoco’s interests
    16 in the property covered by the JOA. Echo’s 120-day period to commence operations
    17 ended on April 2, 2011.
    18   {20}   Echo submitted evidence that it had engaged in the following activities prior
    19 to April 2, 2011, as proof that it actually commenced drilling operations. On
    14
    1 November 30, 2010, it surveyed and marked the well site, the center line for the
    2 access road, and “other points.” Prior to November 30, 2010, it contacted a petroleum
    3 engineer, Joe Janica, to assist with securing a drilling permit from the New Mexico
    4 Oil Conservation Division (OCD). Janica arranged for activities required to obtain
    5 the permit: surveying and marking the 6H Well site, designing a closed loop waste-
    6 removal system for the well, and preparing the drilling permit application. Echo also
    7 began consulting with John Thoma, a geologist with expertise in horizontal wells.
    8 And Echo contacted a fracking contractor who, in January 2011, “committed” to
    9 providing fracking services for the 6H Well sometime between May 15 and June 15,
    10 2011. On or around March 24, 2011, Echo entered into a contract with JW Drilling
    11 to provide drilling services for the 6H Well and agreed to a $70,000 liquidated
    12 damages clause in favor of the contractor. The contract provided that JW Drilling
    13 would be available to drill the 6H Well on May 20, 2011, or as soon as it finished
    14 work on another well in Lea County, New Mexico. Finally, on March 31, 2011, Echo
    15 submitted its drilling permit application to OCD.
    16   {21}   No party disputes what occurred after April 2, 2011. Echo did not repropose
    17 the project to Enduro. Instead, Echo moved forward with the project. OCD approved
    18 Echo’s application for a permit on April 13, 2011. The 6H Well site was prepared for
    15
    1 drilling between May 6 and May 14, 2011. JW Drilling commenced drilling the well
    2 on May 25 and completed drilling by June 10, 2011. The well was prepared for
    3 fracking and fracked between June 16 and July 7, 2011. Finally, the well began
    4 pumping on or about August 5, 2011.
    5   {22}   The Court of Appeals acknowledged that Echo “designed a closed loop system,
    6 and obtained a drilling procedure, spud program, and casing program . . .
    7 communicated with . . . a geologist[] regarding the design and engineering of a lateral
    8 for Well 6H . . . , [and] entered into a drilling contract” all before the end of the 120-
    9 day period. Enduro, 2017-NMCA-018, ¶ 16. But the court wrote that it would be a
    10 “mistake” to allow “‘any’ preparations to count as commencement” and thus held that
    11 Echo’s actions could not be “characterized as ‘commencement’. . . as a matter of
    12 law.” 
    Id. ¶ 29.
    13   {23}   Echo argues that off-site activities relating to the planning and organizing of
    14 a drilling project should be considered when determining whether a party has
    15 commenced operations. Specifically, it contends that the recent changes in industry
    16 practices, brought on by the advent of lateral drilling and hydraulic fracturing, have
    17 made the planning and organizing of oil wells more complicated and that, as a result,
    18 the nonphysical activities involved in well drilling should be given more weight when
    16
    1 determining if a party has commenced operations.
    2   {24}   Enduro, on the other hand, asserts that planning, meetings, and other “back-
    3 room” activities cannot substitute for meaningful on-site activity demonstrating
    4 commencement. During oral argument Enduro also argued that on-site physical acts
    5 are superior to off-site activities because “under the JOA, [Enduro] is completely
    6 dispossessed of any right to any record of the operation,” and therefore Enduro “can’t
    7 verify” the off-site activities in which Echo engaged. We are not persuaded by this
    8 argument. To the extent Enduro’s argument is that on-site activities are superior
    9 because it could have traveled to the well site and observed the activities, we note that
    10 the only provision in the JOA stating anything about denying the nonconsenting
    11 parties access to business records would also deny the nonconsenting party any “right
    12 to observe such operation . . . until such time as the Nonconsenting party’s share of
    13 the cost of such operation and the non-consent penalty applicable thereto has been
    14 recovered by the Consenting parties as provided for herein.” (emphasis added).
    15   {25}   No provision appears in the plain language of the JOA indicating that only on-
    16 site physical activities should be considered when determining whether a party has
    17 commenced operations.        If anything, the JOA can be read as indicating the
    18 importance of off-site activities in demonstrating commencement. For instance, the
    17
    1 JOA includes a provision allowing an operator to unilaterally extend the
    2 commencement period if the extension is “necessary to obtain permits from
    3 government authorities, surface rights (including rights of way) or appropriate drilling
    4 equipment, or to complete title examination.”3 Obtaining permits, surface rights, and
    5 completing title examination are all off-site organizational and planning activities.
    6   {26}   Echo produced verifiable documentary evidence that it surveyed and staked the
    7 well site, entered into a contract for drilling services, prepared and submitted a
    8 drilling permit, and consulted with its geologist regarding the design of the 6-H Well.
    9 It provided testimonial evidence that it obtained a commitment for fracking services.4
    10 Of these acts, the most probative evidence that Echo committed resources
    11 demonstrating its intent to diligently carry on drilling activities until completion was
    3
    12            The provision was not available to Echo in this case because it only applied
    13   in situations where all parties to the JOA had consented to the proposed operation.
    4
    14            Enduro objected to the admissibility of the testimonial evidence because it
    15   came from affidavits in which the affiants recalled out of court conversations in
    16   which the contractor “commit[ted]” to providing services between May 15 and June
    17   15, 2011. The statement should have been admissible for the nonhearsay purpose of
    18   showing how the delay in availability of a fracking crew influenced Echo’s
    19   coordination and planning for the 6H Well. See State v. Reyes, 2002-NMSC-024, ¶
    20   29, 
    132 N.M. 576
    , 
    52 P.3d 948
    (“[I]f an out-of-court statement is offered in evidence
    21   merely for the purpose of establishing what was said at the time, and not for the truth
    22   of the matter, the testimony is not hearsay.”), abrogated on other grounds by Allen
    23   v. LeMaster, 2012-NMSC-001, ¶ 29, 
    267 P.3d 806
    .
    18
    1 its entry into a drilling contract. Without the drilling contract, the factfinder would
    2 have to weigh Echo’s other off-site activities when deciding whether Echo actually
    3 commenced drilling operations. If it is undisputed that Echo entered into a binding
    4 drilling contract before April 2, 2011, we would conclude as a matter of law that Echo
    5 actually commenced drilling operations.
    6   {27}   However, Enduro contends that there is a genuine issue of material fact as to
    7 whether Echo timely accepted JW Drilling’s bid proposal because the signature from
    8 Echo’s agent is not dated. The bid proposal was required to be accepted within ten
    9 days of when JW Drilling signed the proposal. JW Drilling signed the proposal on
    10 March 14, 2011. Arguably because the acceptance date is unknown the proposal
    11 might have been accepted after the April 2, 2011, deadline for commencing drilling
    12 operations, and even if it was signed before the April 2, 2011, deadline, the contract
    13 may not have been enforceable. Echo admits that its contract signature was not dated,
    14 but asserts that because the terms of the proposal required acceptance within ten days
    15 of being received, Echo must have accepted the proposal on or before March 24,
    16 2011. The drilling contractor indicated that he did not have “any doubt” that the
    17 drilling contract was effective in mid-March of 2011, but also admitted that it was
    18 “possible but unlikely” that Echo responded outside the ten-day deadline because the
    19
    1 drilling company might have allowed parties to accept after the ten-day deadline in
    2 the past. Additionally, Echo’s corporate representative could not confirm the date on
    3 which he signed the contract proposal on behalf of Echo. Yet, it remains undisputed
    4 that JW Drilling drilled the well in accordance with the proposal signed by both
    5 parties.
    6   {28}   Whether Echo and JW Drilling entered into a binding contract before the April
    7 2, 2011, deadline is a genuine issue of material fact that remains in this case.
    8 Summary judgment should not be granted if there is a genuine issue of material fact
    9 in dispute. Cebolleta Land Grant, ex rel. Bd. of Trustees of Cebolleta Land Grant v.
    10 Romero, 1982-NMSC-043, ¶ 3, 
    98 N.M. 1
    , 
    644 P.2d 515
    . Accordingly, the district
    11 court and Court of Appeals erred in granting summary judgment.
    12 B.       The Court of Appeals Award of Attorneys’ Fees was Premature
    13   {29}   The Court of Appeals should not have issued an order granting attorneys’ fees
    14 and costs to Enduro while a writ of certiorari on the merits of its decision was
    15 pending in this Court. Echo correctly points to NMSA 1978, Section 34-5-14(B)
    16 (1972), which states that “upon filing of the application [for a writ of certiorari], the
    17 judgment and mandate of the court of appeals shall be stayed pending final action of
    18 the supreme court.” The statute’s language indicates that the mere filing of a writ of
    20
    1 certiorari automatically stays both the “judgment and mandate” of the Court of
    2 Appeals. Rule 12-403 NMRA states that costs and fees are only awarded to the
    3 “prevailing party.” Whether Enduro was a prevailing party on appeal would depend
    4 on the “judgment and mandate” of the Court of Appeals. But the court’s “judgment
    5 and mandate” were suspended on December 16, 2016, when Echo petitioned this
    6 Court for a writ of certiorari. Therefore, there was no underlying basis on which the
    7 Court of Appeals could award costs and fees on January 10, 2017, when Echo’s writ
    8 of certiorari was still pending in this Court.
    9 II.      CONCLUSION
    10   {30}   We reverse the Court of Appeals’ award of summary judgment in favor of
    11 Enduro and its award of appellate costs and attorneys’ fees to Enduro. We also
    12 reverse the district court’s grant of summary judgment to Echo and remand for
    13 proceedings consistent with this opinion.
    14   {31}   IT IS SO ORDERED.
    15                                                  ______________________________
    16                                                  EDWARD L. CHÁVEZ, Justice
    17
    18 WE CONCUR:
    21
    1 ___________________________________
    2 JUDITH K. NAKAMURA, Chief Justice
    3 ___________________________________
    4 PETRA JIMENEZ MAES, Justice
    5 ___________________________________
    6 CHARLES W. DANIELS, Justice
    7 ___________________________________
    8 BARBARA J. VIGIL, Justice
    22