Orion Technical Resources, LLC v. Los Alamos National Security, LLC , 2 N.M. 599 ( 2012 )


Menu:
  •                                                              I attest to the accuracy and
    integrity of this document
    New Mexico Compilation
    Commission, Santa Fe, NM
    '00'04- 10:48:42 2012.09.27
    IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO
    Opinion Number: 
    2012-NMCA-097
    Filing Date: August 6, 2012
    Docket No. 30,928
    ORION TECHNICAL RESOURCES, LLC,
    Plaintiff-Appellant,
    v.
    LOS ALAMOS NATIONAL SECURITY, LLC and
    COMPA INDUSTRIES, INC.,
    Defendant-Appellees.
    APPEAL FROM THE DISTRICT COURT OF BERNALILLO COUNTY
    Beatrice J. Brickhouse, District Judge
    Freedman Boyd Hollander Goldberg Ives & Duncan, P.A.
    David Freedman
    David H. Urias
    Albuquerque, NM
    for Appellant
    Carolyn Callaway, P.C.
    Carolyn Callaway
    Albuquerque, NM
    Allegra A. Hanson, P.C.
    Allegra A. Hanson
    Albuquerque, NM
    Miller Stratvert P.A.
    Richard L. Alvidrez
    Albuquerque, NM
    for Appellee COMPA Industries, Inc.
    Stelzner, Winter, Warburton, Flores, Sanchez & Dawes, P.A.
    1
    Luis G. Stelzner
    Robert P. Warburton
    Sara N. Sanchez
    for Appellee Los Alamos National Security, LLC
    OPINION
    VANZI, Judge.
    {1}     Plaintiff Orion Technical Resources, LLC (Orion) appeals from the district court’s
    order dismissing its claim for breach of implied contract against Defendant Los Alamos
    National Security, LLC (LANS) and for denying its motion for injunctive relief against
    LANS and Defendant COMPA Industries, Inc. (COMPA) (collectively, Defendants). We
    address two issues on appeal: (1) whether an implied-in-fact contract can ever exist between
    a disappointed bidder and the solicitor of bids in the private procurement process and (2)
    whether the district court erred when it concluded as a matter of law that injunctive relief is
    never available to a disappointed bidder. Here, Orion filed a complaint alleging that there
    was an implied-in-fact contract between it and LANS that arose within the context of
    LANS’s solicitation for bids. Specifically, Orion alleged that the implied-in-fact contract
    required LANS to follow certain procedures in evaluating the proposals of the prospective
    bidders and selecting the winner of the subcontract. We first hold that a disappointed bidder
    is not barred as a matter of law from bringing a claim based on an implied-in-fact contract
    in the context of the private solicitation process, and we reverse the district court on that
    issue. In addition, although we conclude that the district court properly denied Orion’s
    request for injunctive relief, we reverse its decision that injunctive relief is never available
    to a disappointed bidder under any circumstances. Finally, because we conclude that
    expectancy damages can be a possible remedy in this type of case, we reverse the district
    court’s ruling that Orion’s only available remedy is limited to reliance damages.
    BACKGROUND
    {2}     LANS is the management and operating contractor at the Los Alamos National
    Laboratory (LANL). In 2007, LANS issued a request for proposals (RFP) for a subcontract
    to provide vendor management and staff augmentation services (service contract) to LANL.
    Orion and COMPA were two of the three companies that submitted bids and were selected
    as finalists. After providing their best and final offers, LANS awarded the contract to
    COMPA.
    {3}    Shortly after COMPA executed the service contract with LANS, Orion filed a
    complaint for injunctive relief and damages claiming that LANS breached an implied-in-fact
    contract with Orion that arose out of the RFP bid selection process. The twenty-three-page
    complaint set out detailed factual allegations regarding the process by which LANS solicited
    and selected bids for the service contract. For example, it alleged that
    2
    [p]ursuant to LANS’s [RFP], Source Selection Plan[,] and custom and norms
    for [management and operations] procurements, LANS was obligated to
    ensure that the bid selection process followed basic principles of fairness and
    competition. LANS violated its obligation to ORION to conduct a fair and
    competitive procurement process by failing to follow[] its own RFP,
    including the Source Selection Plan, its Procurement Policies and
    Procedures, and the well-established customs and norms for [management
    and operations] procurement bids.
    The complaint also alleged that LANS assured bidders that the solicitation process would
    be fair, competitive, and negotiated; that LANS deviated from the selection process and
    criteria set out in its RFP and Source Selection plan by engaging in discussions with only
    one bidder and awarding the service contract to a bidder that did not meet the requirements
    of the RFP; and that LANS failed to follow “well-established customs and norms in
    procurement and acquisition practices that are necessary for a full, open and competitive
    process.” In these ways, Orion claimed that LANS breached the alleged implied-in-fact
    contract that required LANS to give fair consideration to Orion and to strictly comply with
    the representations it made in its RFP and Source Selection Plan.
    {4}      Based on the allegations in the complaint, Orion filed a motion for preliminary
    injunction and an application for a temporary restraining order requesting that the district
    court restrain and permanently enjoin LANS and COMPA from proceeding with the
    performance of the service contract, order LANS to reimburse Orion for the cost of
    preparing the bid, award Orion other costs, damages, and attorney fees, and provide any
    other relief deemed appropriate. The district court initially granted Orion’s application for
    a temporary restraining order and prohibited Defendants from continuing to process any
    transition-related documentation for current employees of Orion until Orion’s motion for a
    preliminary injunction was heard. Thereafter, in a memorandum opinion and order dated
    June 29, 2009, the district court vacated the temporary restraining order and denied Orion’s
    motion for a preliminary injunction. At this point, COMPA had already begun to transition
    to full operation on the service contract and expected to start full performance within days
    of the district court’s order.
    {5}      In March 2010, LANS filed a motion for judgment on the pleadings for failure to
    state a claim under Rule 1-012(C) NMRA. LANS argued that Orion’s claim for breach of
    implied-in-fact contract required dismissal because New Mexico does not recognize that
    cause of action in the private procurement context. LANS filed a separate motion for
    judgment on the pleadings on Orion’s request for permanent injunctive relief, arguing that,
    because the service contract had already been awarded, an injunction would not remedy
    improper conduct but would only serve to punish LANS. COMPA filed a similar motion
    pursuant to Rule 1-056 NMRA and asked the district court to grant partial summary
    judgment to COMPA on Orion’s request for injunctive relief. The district court granted both
    of LANS’s Rule 1-012(C) motions and COMPA’s Rule 1-056 motion. Orion timely
    appealed.
    3
    DISCUSSION
    {6}      In this appeal, we first address whether an implied-in-fact contract may arise between
    parties in the private bid solicitation and selection process. Because we answer that question
    in the affirmative, we then discuss whether injunctive relief is ever available to a
    disappointed bidder if the solicitor of bids breaches such an implied-in-fact contract.
    Although we conclude that injunctive relief may be appropriate under certain circumstances,
    it is not available to Orion under this set of facts. However, the district court erred when it
    limited recovery to reliance damages incurred by a bidder based upon the preparation and
    submission of its bid.
    An Implied-In-Fact Contract May Exist in the Private Procurement Context
    {7}     Orion argues that the district court erred in finding that an implied-in-fact contract
    to follow certain procedures in evaluating and selecting bids can never exist between private
    companies in the bidding and procurement context. Here, the district court ruled that the
    only time an implied contract can be found in the procurement process is when a
    governmental entity is soliciting bids. The court reasoned that in the public procurement
    context, there are statutes governing the bid selection process that may give rise to an
    implied contract. Those statutes specifically provide that public entities will consider all
    bids fairly and equitably. Private solicitors of bids, on the other hand, are not bound by such
    statutes. Orion counters that even where no such statutes control, if a non-governmental
    solicitor of bids makes specific representations regarding the processes by which a contract
    will be awarded and a bidder reasonably relies on those representations in deciding to bid,
    an implied-in-fact contract can arise between the parties. For the reasons that follow, we
    agree with Orion.
    {8}     Our review of a district court’s grant of a motion for judgment on the pleadings is de
    novo. Glaser v. LeBus, 
    2012-NMSC-012
    , ¶ 8, 
    276 P.3d 959
    . “A motion to dismiss on the
    pleadings . . . is similar to a motion to dismiss for failure to state a claim upon which relief
    can be granted[.]” Shovelin v. Cent. N.M. Elec. Coop., Inc., 
    115 N.M. 293
    , 302, 
    850 P.2d 996
    , 1005 (1993). Where, as here, the district court considered matters contained solely
    within the pleadings, a judgment on the pleadings is treated as a motion to dismiss. Glaser,
    
    2012-NMSC-012
    , ¶ 8; see Rule 1-012(B)(6). “[A] motion to dismiss for failure to state a
    claim upon which relief can be granted tests the legal sufficiency of the complaint.”
    Shovelin, 
    115 N.M. at 302
    , 
    850 P.2d at 1005
    . “In reviewing a district court’s decision to
    dismiss for failure to state a claim, we accept all well-pleaded factual allegations in the
    complaint as true and resolve all doubts in favor of sufficiency of the complaint.” Glaser,
    
    2012-NMSC-012
    , ¶ 8 (internal quotation marks and citation omitted). The motion “should
    be granted only when it appears that the plaintiff is not entitled to recover under any facts
    provable under the complaint.” 
    Id.
     (internal quotation marks and citation omitted). “[A]
    motion to dismiss for failure to state a claim is granted infrequently.” Shovelin, 
    115 N.M. at 302
    , 
    850 P.2d at 1005
     (internal quotation marks and citation omitted).
    4
    {9}     In its complaint, Orion alleges that there was an implied-in-fact contract between it
    and LANS. The distinction between an express and implied contract involves “no difference
    in legal effect, but lies merely in the mode of manifesting assent.” Restatement (Second) of
    Contracts § 4 cmt. a (1981). Implied-in-fact contracts are “founded upon a meeting of
    minds, which, although not embodied in an express contract, is inferred . . . from conduct
    of the parties showing, in the light of the surrounding circumstances, their tacit
    understanding.” Hercules, Inc. v. United States, 
    516 U.S. 417
    , 424 (1996) (internal
    quotation marks and citation omitted); see also 1 Williston on Contracts § 1:5 (4th ed. 2012)
    (“[I]ntention to make a promise may be manifested in language or by implication from other
    circumstances, including the parties’ course of dealing or course of performance, or a usage
    of trade.”). An implied-in-fact contract is “based on the parties’ mutual assent as manifested
    by their conduct.” Garcia v. Middle Rio Grande Conservancy Dist., 
    1996-NMSC-029
    , ¶ 15
    n.1, 
    121 N.M. 728
    , 
    918 P.2d 7
     (internal quotation marks and citation omitted).
    {10} We have previously said that “[e]vidence of custom or course of conduct between
    the parties may give rise to a contract implied in fact.” Sanchez v. Martinez, 
    99 N.M. 66
    , 70,
    
    653 P.2d 897
    , 901 (Ct. App. 1982). Our courts will also look to “written representations[,]
    . . . oral representations, . . . the conduct of the parties, or . . . a combination of
    representations and conduct” to determine whether an implied-in-fact contract exists.
    Garcia, 
    1996-NMSC-029
    , ¶ 10 (internal quotation marks and citation omitted); see Beggs
    v. City of Portales, 
    2009-NMSC-023
    , ¶ 17, 
    146 N.M. 372
    , 
    210 P.3d 798
    ; Kestenbaum v.
    Pennzoil Co., 
    108 N.M. 20
    , 24, 
    766 P.2d 280
    , 284 (1988). Whether an implied-in-fact
    contract arises from the representations of the parties is dependent on whether the
    representations create a reasonable expectation of contractual rights. Garcia, 1996-NMSC-
    029, ¶ 11; Ruegsegger v. Bd. of Regents of W. N.M. Univ., 
    2007-NMCA-030
    , ¶ 24, 
    141 N.M. 306
    , 
    154 P.3d 681
    . “The reasonableness of expectations is measured by just how definite,
    specific, or explicit . . . the representation or conduct relied upon” has been. Hartbarger v.
    Frank Paxton Co., 
    115 N.M. 665
    , 672, 
    857 P.2d 776
    , 783 (1993). Accordingly, our courts
    have recognized an action based on an implied-in-fact contract in a number of different
    contexts. For example, we have considered whether certain conduct and facts gave rise to
    an implied-in-fact employment contract sufficient to overcome the presumption of at-will
    employment. See Garcia, 
    1996-NMSC-029
    , ¶¶ 10-11; Hartbarger, 
    115 N.M. at 672
    , 
    857 P.2d at 783
    ; Kestenbaum, 
    108 N.M. at 22-23
    , 
    766 P.2d at 282-83
    ; Newberry v. Allied Stores,
    Inc., 
    108 N.M. 424
    , 426-27, 
    773 P.2d 1231
    , 1233-34 (1989); Lukoski v. Sandia Indian Mgmt.
    Co., 
    106 N.M. 664
    , 666-67, 
    748 P.2d 507
    , 509-10 (1988); Sanchez v. The New Mexican, 
    106 N.M. 76
    , 78, 
    738 P.2d 1321
    , 1324 (1987). This Court relied on the approach used in
    employment cases to determine whether a student successfully stated a claim for breach of
    an implied contract against a post-secondary educational institution based on the
    representations contained in a student handbook. Ruegsegger, 
    2007-NMCA-030
    , ¶¶ 22-24,
    36. In other circumstances, ranging from an alleged promise to procure fire insurance, to a
    title company’s failure to disperse escrow funds, to a dispute over whether an individual was
    hired by a company, our courts have considered claims based on implied-in-fact contracts.
    See Gordon v. N.M. Title Co., 
    77 N.M. 217
    , 218, 
    421 P.2d 433
    , 433-34 (1966); Roan v. D.
    5
    W. Falls, Inc., 
    72 N.M. 464
    , 466-67, 
    384 P.2d 896
    , 898 (1963); Sanchez, 99 N.M. at 68, 653
    P.2d at 899.
    {11} Here, the parties disagree about whether an implied-in-fact contract can exist in the
    private bid solicitation and selection process. Their dispute centers on our Supreme Court’s
    decision in Planning & Design Solutions v. City of Santa Fe, 
    118 N.M. 707
    , 714-15, 
    885 P.2d 628
    , 635-36 (1994), in which the Court held that by issuing an RFP, the city impliedly
    promised to abide by the governing statutes in evaluating the bids and therefore to consider
    all bids fairly and equitably. Agreeing with LANS’s interpretation of Planning & Design,
    the district court found that the only time a disappointed bidder can have a viable claim
    based on an implied contract is when a governmental body solicited the bids. Orion
    contends that nothing in Planning & Design precludes a claim for breach of an implied-in-
    fact contract arising out of a private procurement process.
    {12} In Planning & Design, the city issued a RFP that listed four weighted criteria that the
    city would apply in evaluating the bids. 
    Id. at 709
    , 
    885 P.2d at 630
    . Under the laws
    governing the public procurement process, the city was required to apply the criteria set out
    in the RFP—and no others—in evaluating the proposals. 
    Id. at 711
    , 
    885 P.2d at 632
    .
    However, in selecting the winning bid, the city relied on a fifth criterion that was not
    included in the RFP. 
    Id.
     The plaintiff, a disappointed bidder, sued the city for violations of
    the Procurement Code and the city’s own purchasing regulations. 
    Id. at 709
    , 
    885 P.2d at 630
    . The district court in that case ruled that because the disappointed bidder did not have
    a formal contract with the city, the city could not be liable for breach of contract. 
    Id.
    {13} Our Supreme Court disagreed and concluded that although there was no formal
    contract between the parties, an implied contract could be found in the bid solicitation
    process. 
    Id. at 714, 716
    , 
    885 P.2d at 635, 637
    . The Court recognized that, generally, “[a]
    request for bids ‘is not an offer but a request for offers’ and bidders are making offers when
    they submit bids.” 
    Id. at 714
    , 
    885 P.2d at 635
     (quoting Restatement (Second) of Contracts
    § 28 cmt. c (1981)). Accordingly, no contract generally occurs until acceptance of a bid by
    the soliciting party. Id. However, because the Procurement Code required the city to treat
    all bids fairly and equitably and because other statutes required the city to consider only
    those criteria listed in its RFP, the Court reasoned that by issuing the RFP, the city had made
    an implied promise to abide by these statutory requirements. Id. at 713-14, 
    885 P.2d 634
    -35.
    The plaintiff had relied on the promise as a guarantee that any award would be based only
    on the criteria set out in the RFP and changed its position accordingly. Id. at 714-15, 
    885 P.2d at 635-36
    . Had the promise been different, the plaintiff might have chosen not to bid
    at all. 
    Id. at 715
    , 
    885 P.2d at 636
    . The Court’s conclusion was consistent with the rule in
    other jurisdictions that recognize that “it is an implied condition of every invitation for bids
    issued by a public contracting authority that each bid submitted pursuant to the invitation
    will be fairly considered in accordance with all applicable statutes.” Paul Sardella Constr.
    Co. v. Braintree Hous. Auth., 
    329 N.E.2d 762
    , 767 (Mass. App. Ct. 1975), aff’d, 
    356 N.E.2d 249
     (Mass. 1976).
    6
    {14} In our view, Planning & Design does not stand for the proposition that an implied-in-
    fact contract, as a matter of law, can never exist between two parties in the private
    procurement context. The Supreme Court did not address this question. Instead, it
    addressed only the question whether an implied contract existed in the public procurement
    context. Although the promise to consider all bids fairly, which is implied in the public
    procurement context, is based on statute and thus cannot automatically be implied in private
    bid solicitations, the absence of statutory obligations does not foreclose the possibility that
    an implied-in-fact contract may arise between parties in the private procurement context
    based on their own representations, course of conduct, and other factors that have been held
    to give rise to an implied-in-fact contract.
    {15} At least one other jurisdiction has recognized a cause of action based on an implied
    contract in the private bid solicitation and selection process. In New England Insulation Co.
    v. General Dynamics Corp., 
    522 N.E.2d 997
    , 998 (Mass. App. Ct. 1988), a company
    soliciting bids made representations in its solicitation that the bids submitted would remain
    in a locked file only to be opened after the closing date. The plaintiff’s bid was unsealed
    early, and the information it contained was shared with the plaintiff’s competitor, who was
    ultimately awarded the contract. 
    Id. at 998-99
    . The plaintiff brought suit against the
    company, alleging that it relied on the solicitor’s representations in deciding to bid. 
    Id.
     As
    is the case here, the defendant company challenged the legal theory of the complaint. 
    Id. at 999
    .
    {16} The Massachusetts court held that the plaintiff could pursue a claim based on an
    implied contract. 
    Id. at 1000-01
    . The court recognized that “requests for bids are usually
    nonbinding invitations for offers” and that the defendant retained the discretion to choose
    with whom it would contract. 
    Id. at 999
     (alteration, internal quotation marks, and citation
    omitted). However, the court reasoned that “[i]t does not necessarily follow . . . that [the
    defendant] could not limit its freedom to act by making representations in its invitations to
    bid which it knew or should have known would be reasonably relied upon by the plaintiff.”
    
    Id. at 999
    . The court assumed without deciding that a promise to give fair consideration to
    all bids could not be implied in every private request for bids. 
    Id. at 1000
    . However, it
    stated that this did not mean that, as a matter of law, the specific promise made by the
    solicitor to the bidder could not create a binding obligation. 
    Id.
     It noted that “[t]here is
    surely no policy which would be served by allowing solicitors of bids in the private sector
    to ignore the conditions they themselves set and ask others to rely upon.” 
    Id.
     The court
    reversed the district court’s grant of the defendant’s motion to dismiss and remanded for an
    analysis of the facts. 
    Id. at 1001
    .
    {17} We are persuaded by the reasoning in New England Insulation. We recognize that
    in this case, Orion alleges that LANS made specific representations regarding the bid
    solicitation and selection process, which it relied upon, while in New England Insulation, the
    plaintiff’s decision to bid was based on the solicitor’s specific representation that it would
    keep all bids in a locked box until the closing date. 
    Id. at 998
    . Although the cases are
    factually distinguishable in terms of what representations were made and how the promises
    7
    were allegedly breached, at this stage in the proceedings, the distinctions are irrelevant. For
    purposes of a motion to dismiss, it is significant that the New England Insulation court
    clearly recognized that the promises made by the solicitor in its requests for bids could be
    legally binding. 
    Id. at 1000-01
    . Consequently, we agree with the Massachusetts court that
    no policy “would be served by allowing solicitors of bids in the private sector to ignore the
    conditions they themselves set and ask others to rely upon.” 
    Id. at 1000
    .
    {18} Relying on the general principles of implied-in-fact contracts, we conclude that in
    the private solicitation context, as in other contexts, an implied-in-fact contract may be found
    based on the representations and conduct of the parties. We continue to recognize that the
    general private sector rule regarding solicitations for bids is that “unless a contrary intention
    is manifested” a request for bids “is not an offer but a request for offers[.]” Restatement
    (Second) of Contracts § 28 cmt. c; Planning & Design, 
    118 N.M. at 714
    , 
    885 P.2d at 635
    .
    However, as Planning & Design indicates, there are circumstances in the bid solicitation
    process that may give rise an implied contract regarding the process by which a bid will be
    selected. 
    118 N.M. at 714
    , 
    885 P.2d at 635
    . Thus, an implied-in-fact contract could arise
    in the private procurement process if a solicitor of bids makes specific representations
    regarding the processes by which it will select a bid, and a bidder reasonably relies on those
    representations in deciding to bid. 
    Id. at 715
    , 
    885 P.2d at 636
    . Although these promises are
    not imposed by statute, that does not mean that they cannot be legally binding. See New
    England Insulation, 
    522 N.E.2d at 1000
    .
    {19} The employment context is analogous here. Ordinarily in New Mexico, an employee
    is at will, and an employer may fire him or her for any or no reason. See Garcia, 1996-
    NMSC-029, ¶ 10. However, an employer may restrict its freedom to fire at-will employees
    by making specific promises that, when reasonably relied upon by the employee, give rise
    in an implied-in-fact employment contract. It follows that in the private bid solicitation
    context the solicitor of bids could restrict its freedom to select a contractor through any
    process it chooses by making specific promises regarding the selection process on which it
    would expect a bidder to reasonably rely in deciding to bid. Therefore, Orion’s claim for
    breach of implied-in-fact contract is not barred as a matter of law.
    {20} LANS contends that any reliance on our cases considering whether an implied-in-fact
    contract exists in the employment context and other contexts is misplaced. It contends that,
    aside from the public procurement case, in our other implied-in-fact contract cases, the
    parties had a pre-existing relationship. We consider this is a distinction without difference.
    An implied-in-fact contract is “based on [the] parties’ mutual assent as manifested by their
    conduct.” Garcia, 
    1996-NMSC-029
    , ¶ 15 n.1 (internal quotation marks and citation
    omitted). The parties’ pre-existing relationship is but one factor to consider in determining
    whether the parties’ conduct gave rise to an implied-in-fact contract, and it is not necessarily
    the determining one. Under either type of relationship, there is a presumption that no
    binding agreement is generally recognized, and it is only after a unilateral extension of an
    additional promise by one party that an implied-in-fact contract can potentially be created.
    8
    {21} Further, LANS cites to the out-of-jurisdiction cases of King v. Alaska State Housing
    Authority, 
    633 P.2d 256
     (Alaska 1981), and Hoon v. Pate Construction Co., 
    607 So. 2d 423
    (Fla. Dist. Ct. App. 1992) (per curiam), as authority for the proposition that a private party
    soliciting bids does not have the same obligations as a public entity. We are not persuaded
    by the application of these cases to the circumstances here. In King, the Alaska Supreme
    Court considered whether bidders for a government redevelopment project who alleged
    improprieties in the selection process could recover under contract law. King, 633 P.2d at
    258-59. Like our Supreme Court in Planning & Design, the court found “merit in the
    contention that an agency, in soliciting bids, implicitly contracts to give those bids fair and
    honest consideration.” King, 633 P.2d at 261. The court held that “in exchange for a
    bidder’s investment of the time and resources involved in bid preparation, a government
    agency must be held to an implied promise to consider bids honestly and fairly.” Id. at 263.
    Nevertheless, the court stated that while this rule “recognizes that a promise of honest and
    fair consideration of bids can reasonably be implied in the public contract context, . . . such
    a promise cannot be implied in the private sphere.” Id. at 262. This is because private
    parties do not have an obligation “to select the bid most consistent with the public interest.”
    Id. While it is true that King recognized the distinction between the public and private
    procurement process, the case did not address the issue of whether one party can make a
    promise that will then be binding in the private procurement process.
    {22} In Hoon, the Florida appellate court considered whether a district court erred in
    granting a disappointed bidder relief based on breach of an implied contract in a private
    solicitation. 
    607 So. 2d at 424-25
    . There, the plaintiff alleged that the solicitor of bids
    promised to award a job to the lowest bidder and breached an implied contract by failing to
    award it the job after it submitted the lowest bid. 
    Id. at 425
    . The plaintiff asserted that there
    was an implied contract that its bid would receive fair consideration. 
    Id. at 425-26
    . The
    appellate court disagreed. 
    Id. at 426-27
    . The court recognized the general rule that in
    private construction a party soliciting a bid has the freedom to accept or reject it for any
    reason and agreed with the principle that “no contract is formed when a bid is made pursuant
    to an invitation to bid.” 
    Id. at 425-26
    . The court’s ruling relied on the fact that, although the
    bid solicitation stated an intent to award the bid to the lowest bidder, it also stated the
    “[o]wner reserves [the] right to reject any or all bids for whatever reason he may deem
    necessary for his best interest, and to waive any or all formalities in regard to acceptance or
    rejection of any bid.” 
    Id. at 425
     (internal quotation marks omitted). The court concluded
    that “[t]o recognize an implied contract in a situation where the parties agree that the written
    document provides that the owner may ‘reject a bid for any reason’ would be to emasculate
    the effect of that provision.” 
    Id. at 427
    . Thus, the court concluded that, based upon the
    actual claim set out in the pleadings, the defendants were entitled to a directed verdict on the
    plaintiff’s implied contract claim. 
    Id. at 426-27
    .
    {23} Hoon does not suggest that there can never be an implied-in-fact contract in the
    private procurement process. The court simply stated the general rule that a private solicitor
    of bids may contract with whomever it chooses and then determined that the defendant’s
    specific reservation of the right to reject any or all bids was binding on the parties. 
    Id.
     at
    9
    426. We cannot disagree with this determination, however, it does not answer the question
    before this Court: Can the solicitor of a private procurement bid create an implied-in-fact
    contract if the solicitor makes sufficient promises to the bidders that limit the solicitor’s
    inherent freedom to select the recipient of the contract?
    {24} To the extent the court in Hoon relied on the specific provision in the written bid
    solicitation to conclude that no implied contract was established, New Mexico courts have
    taken a broader approach toward the determination of whether an implied-in-fact contract
    exists. For example, our courts have held that an implied contract may exist between the
    parties even where a writing disclaims any intention of forming a contractual obligation. See
    Beggs, 
    2009-NMSC-023
    , ¶ 20; Madrid v. Vill. of Chama, 2012-NMCA-___, ¶ 15, ___ P.3d
    ___ (No. 30,764, May 1, 2012), cert. denied, 
    2012-NMCERT-006
    , ___ P.3d ___; West v.
    Wash. Tru Solutions, LLC, 
    2010-NMCA-001
    , ¶¶ 17-18, 
    147 N.M. 424
    , 
    224 P.3d 651
    . In
    determining whether an implied-in-fact contract exists, “it is not any single act, phrase or
    expression, but the totality of all of these, given the circumstances and the parties’ situation
    and objectives, which will control.” Kestenbaum, 
    108 N.M. at 26
    , 
    766 P.2d at 286
    . Because
    Hoon stated that the rights of the parties were controlled by the written bid solicitation, it is
    not clear whether a plaintiff’s cause of action based upon an implied contract could have
    been recognized in Florida under another set of facts.
    {25} LANS also argues that to recognize a cause of action based on an implied-in-fact
    contract in the private procurement context would be an unprecedented expansion of New
    Mexico law and encourage unprecedented litigation by disappointed bidders. We are not
    persuaded. New Mexico recognizes implied-in-fact contracts in a variety of factual
    circumstances. Certainly, our Supreme Court’s decision in Planning & Design did not open
    the floodgates of litigation in the public procurement arena as that has been the only
    appellate decision on the issue since 1994. We see no reason that allowing Orion to bring
    its claim for breach of an implied-in-fact contract would be any different. The fact that there
    have been no formal appellate opinions addressing this issue in New Mexico in the past does
    not prevent Orion from seeking recovery based upon a well recognized theory of law, the
    implied-in-fact contract.
    {26} We hold that Orion’s claim for breach of an implied-in-fact contract may proceed.
    Based on the principles of implied-in-fact contracts that are set out in New Mexico case law,
    we conclude that an implied-in-fact contract can arise in the private solicitation context. We
    therefore reverse the district court’s order dismissing Orion’s claims.
    Injunctive Relief Is Not Available Under the Circumstances Here
    {27} In its complaint, Orion requested that the district court permanently enjoin LANS and
    COMPA from proceeding with the performance of the contract at issue. Both Defendants
    filed motions seeking the dismissal of Orion’s claim for permanent injunctive relief. LANS
    filed a motion for judgment on the pleadings pursuant to Rule 1-012(C) in which it argued
    that permanent injunctive relief was never available to a disappointed bidder. COMPA filed
    10
    a motion for partial summary judgment in which it asserted that injunctive relief was
    unavailable because Orion had an adequate remedy at law. The district court granted
    Defendants’ motions.
    {28} Our review of the district court’s grant of LANS’s motion for judgment on the
    pleadings is de novo. See Glaser, 
    2012-NMSC-012
    , ¶ 8. We also review the district court’s
    grant of COMPA’s motion for partial summary judgment de novo. See Smith v. Durden,
    
    2012-NMSC-010
    , ¶ 5, 
    276 P.3d 943
    . Summary judgment is appropriate when there is no
    genuine issue of material fact and the moving party is entitled to judgment as a matter of
    law. Id.; see Rule 1-056. Here there are no disputes of material fact; therefore, we only
    consider whether summary judgment was appropriate as a matter of law.
    {29} In granting Defendants’ motions, the district court concluded that injunctive relief
    was never available to a disappointed bidder like Orion. The district court based its
    conclusion on Planning & Design, which it understood to limit a disappointed bidder’s
    remedy to reliance damages that include the expenses incurred in preparing and submitting
    the bid. Orion argues that Planning & Design was decided on the facts and does not
    preclude a court from granting a permanent injunction to a disappointed bidder as a matter
    of law. We agree with Orion that the district court erred in concluding that injunctive relief
    was never available to a disappointed bidder. However, we hold that injunctive relief is not
    available under the circumstances here and, therefore, dismissal of Orion’s claim for
    injunctive relief was proper. In addition, we hold that the district court’s limitation on the
    available remedies in a private sector breach of implied-in-fact contract case was in error.
    We first address the basis of the district court’s ruling and then discuss what remedies may
    be available to Orion.
    {30} Planning & Design did not establish a blanket rule that permanent injunctive relief
    was never available to a disappointed bidder where the solicitor of bids has breached an
    implied contract in the procurement process. There, the district court had preliminarily
    enjoined the city from awarding the contract to anyone but the plaintiff. 
    118 N.M. at 709
    ,
    
    885 P.2d at 630
    . However, by the time the case reached our Supreme Court, the city had
    rejected all bids on the project. 
    Id. at 712
    , 
    885 P.2d at 633
    . Thus, in contrast to this case,
    the city in Planning & Design did not award any contract under the allegedly flawed
    procurement process and, therefore, there was no performance to enjoin. Thus, the Court
    concluded, “under the circumstances, injunctive relief [was] pointless.” 
    Id. at 715
    , 
    885 P.2d at 636
    . Injunctive relief was simply not feasible based on the facts before the Court and,
    thus, reliance damages were the appropriate remedy. 
    Id.
     However, this ruling does not
    preclude a district court from granting a permanent injunction under another set of facts.
    See, e.g., AshBritt, Inc. v. United States, 
    87 Fed. Cl. 344
    , 378-79 (2009) (granting limited
    injunctive relief in post-award bid protest where the current contracts would be left in place
    while bids were reevaluated in accordance with statute and regulation); Spiniello Constr. Co.
    v. Town of Manchester, 
    456 A.2d 1199
    , 1200, 1202-03 (Conn. 1983) (upholding the district
    court’s grant of a permanent injunction restraining a municipality and a bidder from entering
    into a public works contract where the bidding statute had been violated).
    11
    {31} Notwithstanding that injunctive relief may be the proper remedy in this type of case,
    we conclude that, under the facts of this case, injunctive relief is unavailable to Orion.
    “Injunctions are harsh and drastic remedies that should issue only in extreme cases of
    pressing necessity and only where there is no adequate remedy at law.” Insure N.M., LLC
    v. McGonigle, 
    2000-NMCA-018
    , ¶ 7, 
    128 N.M. 611
    , 
    995 P.2d 1053
     (alterations, internal
    quotation marks, and citation omitted). An irreparable injury for which there is no adequate
    remedy at law is one “which cannot be compensated or for which compensation cannot be
    measured by any certain pecuniary standard.” State ex rel. State Highway & Transp. Dep’t
    v. City of Sunland Park, 
    2000-NMCA-044
    , ¶ 19, 
    129 N.M. 151
    , 
    3 P.3d 128
     (internal
    quotation marks and citation omitted). Here, where COMPA has been performing on the
    contract since mid-2009, the damage to COMPA outweighs any harm to Orion. More
    importantly, there is also an adequate remedy at law in this case.
    {32} Orion’s complaint seeks both permanent injunctive relief and money damages as
    remedies for the breach of the alleged implied-in-fact contract between it and LANS. Our
    case law establishes that money damages are available to a disappointed bidder who prevails
    on a breach of implied contract claim in order to “compensate the bidder’s ‘interest in being
    reimbursed for loss caused by reliance on the contract by being put in as good a position as
    he would have been in had the contract not been made.’” Planning & Design, 
    118 N.M. at 715
    , 
    885 P.2d at 636
     (quoting Restatement (Second) of Contracts § 344(b) (1981)). There
    is no dispute that these damages can be readily calculated.
    {33} Additionally, COMPA does not dispute that expectancy damages are available to
    Orion in the event that it can prove that, but for LANS’s breach of the alleged implied-in-fact
    contract, Orion would have been awarded the contract. Thus, to the extent Orion argues that
    it would have been awarded the contract, COMPA contends that Orion may be adequately
    compensated for its alleged injuries. Orion agrees that injunctive relief is not necessary if
    expectancy damages are an available remedy. Although disappointed bidders in the public
    procurement context are often limited by public policy or statute to the recovery of reliance
    damages, these constraints are not present here. Cf. 
    28 U.S.C. § 1491
    (b)(2) (2011)
    (conferring jurisdiction on the Court of Claims to “award any relief [it] considers proper,
    including declaratory and injunctive relief except that any monetary relief shall be limited
    to bid preparation and proposal costs” (emphasis added)); Planning & Design, 
    118 N.M. at 715
    , 
    885 P.2d at 636
     (joining other jurisdictions that award the expenses incurred in
    preparing and submitting a bid to disappointed bidders of flawed public procurements); State
    Mech. Contractors, Inc. v. Vill. of Pleasant Hill, 
    477 N.E.2d 509
    , 511 (Ill. App. Ct. 1985)
    (explaining that the public purpose is not served by requiring the taxpayer to pay the contract
    price to the bidder awarded the contract and profits that a disappointed bidder would have
    realized if it had been awarded the contract). Accordingly, we see no reason that a
    disappointed bidder in a private solicitation could not pursue a claim for expectation
    damages. See Restatement (Second) of Contracts § 347 (1981) (discussing the general
    measure of damages). Money damages are available to Orion in this case, and Orion has not
    alleged any facts nor made any argument to persuade us that money damages would not
    compensate it for the alleged injury here. We affirm the district court’s dismissal of Orion’s
    12
    claim for injunctive relief. We hold that the appropriate remedy in this type of case is not
    limited to reliance damages and may include expectation damages.
    CONCLUSION
    {34} For the reasons set forth above, we reverse the district court’s order dismissing
    Orion’s claim for breach of implied contract and dismissal of its complaint with prejudice.
    We affirm the district court’s order denying Orion’s motion for injunctive relief. However,
    we reverse the district court’s ruling limiting the nature of damages available to Orion.
    {35}   IT IS SO ORDERED.
    ____________________________________
    LINDA M. VANZI, Judge
    WE CONCUR:
    ____________________________________
    MICHAEL E. VIGIL, Judge
    ____________________________________
    TIMOTHY L. GARCIA, Judge
    Topic Index for Orion Technical Resources, LLC v. Los Alamos Natl. Security, LLC, No.
    30,928
    APPEAL AND ERROR
    Preservation of Issues for Appeal
    Standard of Review
    CIVIL PROCEDURE
    Judgment on the Pleadings
    CONTRACT
    Bid
    Breach
    Implied Contract
    Public Policy
    EMPLOYMENT LAW
    Employment at Will
    JUDGMENT
    Judgment on the Pleadings
    13
    REMEDIES
    Injunctions
    Measure of Damages
    14
    

Document Info

Docket Number: Docket 30,928

Citation Numbers: 2012 NMCA 97, 2 N.M. 599, 2012 NMCA 097

Judges: Garcia, Linda, Michael, Timothy, Vanzi, Vigil

Filed Date: 8/6/2012

Precedential Status: Precedential

Modified Date: 8/6/2023

Authorities (20)

Hoon v. Pate Const. Co., Inc. , 607 So. 2d 423 ( 1992 )

State Mechanical Contractors, Inc. v. Village of Pleasant ... , 132 Ill. App. 3d 1027 ( 1985 )

Glaser v. Lebus , 1 N.M. Ct. App. 585 ( 2012 )

Roan Ex Rel. Roan v. D. W. Falls, Inc. , 72 N.M. 464 ( 1963 )

New England Insulation Co. v. General Dynamics Corp. , 26 Mass. App. Ct. 28 ( 1988 )

PAUL SARDELLA CONSTR. v. Braintree Hous. Auth. , 3 Mass. App. Ct. 326 ( 1975 )

Planning & Design Solutions v. City of Santa Fe , 118 N.M. 707 ( 1994 )

Shovelin v. CENTRAL NM ELEC. CO-OP. , 115 N.M. 293 ( 1993 )

Sanchez v. the New Mexican , 106 N.M. 76 ( 1987 )

Kestenbaum v. Pennzoil Co. , 108 N.M. 20 ( 1988 )

Gordon v. New Mexico Title Company , 77 N.M. 217 ( 1966 )

Lukoski v. Sandia Indian Management Co. , 106 N.M. 664 ( 1988 )

Smith v. Durden , 1 N.M. Ct. App. 566 ( 2012 )

Newberry v. Allied Stores, Inc. , 107 N.M. 424 ( 1989 )

Insure New Mexico, LLC v. McGonigle , 128 N.M. 611 ( 2000 )

West v. WASHINGTON TRU SOLUTIONS, LLC , 147 N.M. 424 ( 2009 )

State Ex Rel. State Highway & Transportation Department v. ... , 129 N.M. 151 ( 2000 )

Hartbarger v. Frank Paxton Co. , 115 N.M. 665 ( 1993 )

Garcia v. Middle Rio Grande Conservancy District , 121 N.M. 728 ( 1996 )

Hercules, Inc. v. United States , 116 S. Ct. 981 ( 1996 )

View All Authorities »