Unified Contractor, Inc. v. Albuquerque Housing Auth. ( 2017 )


Menu:
  •  1      IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO
    2 Opinion Number: __________
    3 Filing Date: April 24, 2017
    4 NO. 34,826
    5 UNIFIED CONTRACTOR, INC.,
    6        Plaintiff/Counterdefendant-Appellant,
    7 v.
    8 ALBUQUERQUE HOUSING
    9 AUTHORITY, a political subdivision,
    10        Defendant/Counterclaimant-Appellee.
    11 APPEAL FROM THE DISTRICT COURT OF BERNALILLO COUNTY
    12 Valerie A. Huling, District Judge
    13 Calvert Menicucci, P.C.
    14 Sean R. Calvert
    15 Albuquerque, NM
    16 for Appellant
    17   City of Albuquerque
    18   Jessica M. Hernandez, City Attorney
    19   John E. DuBois, Assistant City Attorney
    20   Kevin A. Morrow, Assistant City Attorney
    21   Albuquerque, NM
    22 for Appellee
    1                                        OPINION
    2 WECHSLER, Judge.
    3   {1}   This litigation and appeal result from a contractual dispute between Appellant
    4 Unified Contractor, Inc. (Unified) and Appellee Albuquerque Housing Authority
    5 (AHA). Unified appeals from the district court’s ruling that both parties breached the
    6 contract (the Contract) between them and that both parties were liable for damages.
    7   {2}   In its letter decision, the district court made various factual findings and legal
    8 conclusions. It also instructed the parties to submit requested findings of fact and
    9 conclusions of law within fourteen days. Neither party timely submitted findings of
    10 fact and conclusions of law.
    11   {3}   Unified characterizes several of its appellate arguments as either questions of
    12 law or mixed questions of law and fact. As discussed in detail below, to the extent
    13 that Unified’s appellate arguments simply re-purpose questions of fact as questions
    14 of law, they are not well-taken.
    15   {4}   Unified does, however, raise legal arguments related to (1) its entitlement to
    16 notice of deficient performance and the opportunity to cure such deficient
    17 performance (notice and opportunity to cure) under the Contract and general
    18 principles of contract law, (2) the district court’s decision to allow AHA to raise
    19 grounds for termination of the Contract other than those articulated as the basis for
    1 termination prior to trial, (3) the district court’s method of calculating damages, and
    2 (4) the district court’s refusal to consider Unified’s motion for reconsideration. With
    3 the exception of Unified’s argument as to the district court’s method of calculating
    4 damages, these arguments lack merit. As to the calculation of damages, we adopt and
    5 apply the “contract price limitation rule” to the facts of this case; a decision requiring
    6 that we reverse the district court’s judgment in favor of AHA in the amount of
    7 $33,281.37 and remand to the district court for entry of a final judgment in favor of
    8 AHA in the reduced amount of $22,257.34.
    9   {5}   Finally, Unified argues that it is entitled to statutory interest pursuant to the
    10 Prompt Payment Act. NMSA 1978, §§ 57-28-1 to -11 (2001, as amended through
    11 2007). For the reasons discussed herein, we disagree. We therefore affirm in part,
    12 reverse in part, and remand to the district court for entry of a final judgment
    13 consistent with this opinion.
    14 BACKGROUND
    15 The Contract
    16   {6}   Unified submitted a bid in response to AHA’s invitation for bids number
    17 B13001 (IFB B13001). IFB B13001 called for various construction services at four
    18 residential properties owned by AHA. The physical addresses of the properties in
    2
    1 Albuquerque are 514 Morris NE, 716 Morris NE, 903 Nakomis NE, and 2905
    2 Chelwood NE.
    3   {7}   Section 2.0 of IFB B13001 outlined the scope of work and technical
    4 specifications for the project. Subsection 2.3 provided that bidders could propose to
    5 substitute for products specified in IFB B13001 so long as the substitute product was
    6 “substantially equivalent or exceeding to the product[] identified.” Subsection 2.4.1.5
    7 required the bidder to “[p]aint [the] entire exterior of [each] building with one coat
    8 of [a]crylic base primer and one coat of elastomeric coating.” Subsection 2.4.6.1.2.8
    9 defined elastomeric coating by reference to “El Rey elastomeric coating, or equal[.]”
    10 IFB B13001 did not define a “coat” of elastomeric coating.
    11   {8}   AHA accepted Unified’s bid, and the parties entered the Contract on July 15,
    12 2013. The Contract expressly incorporated Form HUD-5370 (11/2006), which
    13 outlines general conditions for the termination of a construction contract due to
    14 default by the contractor or for the convenience of the agency. The Contract also
    15 contained various clauses related to billing and payment, including (1) a prompt
    16 payment clause, which required payment for “properly completed invoice[s]” within
    17 thirty days, and (2) a disputed billings clause, which required AHA to pay any
    18 undisputed portions of billings and to formally notify Unified of any disputed billings
    19 within ten days of receipt.
    3
    1   {9}    On August 8, 2013, Unified submitted an elastomeric coating manufactured by
    2 UltraKote Products, Inc. for use in the project. AHA did not approve this product for
    3 use. On September 3, 2013, Unified submitted an elastomeric coating manufactured
    4 by ParexUSA for use in the project. Although disputes as to which product AHA
    5 approved continued throughout the litigation, the record shows that AHA approved
    6 ParexUSA elastomeric coating for use on the project on September 9, 2013.1
    7 ParexUSA elastomeric coating can be applied in one or two coats by spray, brush, or
    8 roller over porous or smooth surfaces. The stucco surfaces at issue in this case were
    9 porous. Using the “one coat” method, each pail of ParexUSA elastomeric coating
    10 would cover 125-180 square feet of a porous surface. Using the “two coat” method,
    11 each pail of ParexUSA elastomeric coating would cover 250-375 square feet of a
    12 porous surface.
    13 The Project
    14   {10}   In September 2013, Unified began work at 716 Morris NE and 903 Nakomis
    15 NE. The contract price for these properties was $278,349. Unified submitted its first
    1
    16          Significant confusion exists as to whether El Rey elastomeric coating and
    17   ParexUSA elastomeric coating are identical products. We refer to ParexUSA
    18   elastomeric coating throughout this opinion because it is the product approved by
    19   AHA for use on the project and purchased by Unified. Whether AHA intended to
    20   approve ParexUSA elastomeric coating for use on the project is unclear but
    21   immaterial to this opinion.
    4
    1 itemized invoices for work at these locations on September 24, 2013. Attachments to
    2 these invoices indicate that Unified had not yet patched stucco or applied elastomeric
    3 coating at either location. AHA paid these invoices in full.
    4   {11}   On October 16, 2013, AHA’s site inspections revealed deficiencies in the
    5 appearance of the finished walls at 716 Morris NE and 903 Nakomis NE. AHA sent
    6 numerous emails and a letter between October 16, 2013 and November 13, 2013
    7 requesting confirmation that the approved elastomeric coating was being installed in
    8 accordance with the manufacturer’s recommendations. Unified repeatedly responded
    9 in the affirmative.
    10   {12}   On October 24, 2013, Unified submitted a second set of itemized invoices for
    11 work at 716 Morris NE and 903 Nakomis NE. Attachments to these invoices indicate
    12 that Unified had completed eighty-eight percent of stucco patching and elastomeric
    13 coating application at each location.
    14   {13}   On November 25, 2013, Unified submitted a third set of itemized invoices for
    15 work at 716 Morris NE and 903 Nakomis NE. Attachments to these invoices indicate
    16 that Unified had completed ninety-seven percent of stucco patching and elastomeric
    17 coating application at 716 Morris NE and one hundred percent of stucco patching and
    18 elastomeric coating application at 903 Nakomis NE.
    5
    1   {14}   On November 26, 2013, AHA sent an email notifying Unified that, with respect
    2 to the October 24, 2013 invoices, AHA would pay for certain itemized work and
    3 withhold payment for other itemized work at the respective properties.
    4   {15}   On December 9, 2013, AHA sent another email notifying Unified that AHA
    5 would pay for certain work itemized in the November 25, 2013 invoices and would
    6 withhold payment for other itemized work. This email included attachments that
    7 differentiated between invoiced items by marking certain items “OK.” On the same
    8 day, AHA exercised its contractual right to audit. The audit requested invoices
    9 demonstrating that Unified purchased the approved elastomeric coating for the
    10 project.
    11   {16}   On December 17, 2013, Unified produced the invoices and a certification letter
    12 from its supplier, ProBuild. The invoices showed that, between September 10, 2013
    13 and October 23, 2013, Unified purchased seventy-nine pails of ParexUSA elastomeric
    14 coating.
    15   {17}   On December 18, 2013, Unified filed a complaint in district court for breach
    16 of contract, unjust enrichment, and violation of the Prompt Payment Act. The
    17 complaint alleged that AHA breached the Contract by failing to provide notice of
    18 billing disputes within ten days and by failing to make prompt payment for
    19 undisputed, invoiced items.
    6
    1   {18}   On December 29, 2013, Unified submitted itemized invoices for work at 716
    2 Morris NE and 514 Morris NE. Attachments to these invoices indicate that Unified
    3 had completed one hundred percent of stucco patching and elastomeric coating
    4 application at 716 Morris NE and twenty percent of stucco patching and elastomeric
    5 coating application at 514 Morris NE. AHA did not pay these invoices.
    6   {19}   On January 3, 2014, AHA terminated the Contract. As grounds for termination,
    7 AHA stated that Unified materially breached the Contract by failing to (1) use
    8 contractually required construction materials, and (2) follow the manufacturer’s
    9 recommended application process for the construction materials used. AHA alleged
    10 that its inspections revealed that Unified was not following the manufacturer’s
    11 recommended application process. Unified amended its complaint to include a claim
    12 of wrongful termination of the Contract. AHA answered the amended complaint and
    13 filed a counterclaim for breach of contract.
    14 The Trial
    15   {20}   The parties conducted discovery, and the district court set the matter for trial
    16 in February 2015. Unified filed a motion for partial summary judgment, which
    17 alleged that AHA breached the Contract by failing to comply with contract provisions
    18 related to bill payment and billing disputes. The district court entered a preliminary
    7
    1 order granting the motion with respect to liability but reserving judgment on the issue
    2 of damages.
    3   {21}   Witnesses at trial included (1) Unified President Ivan Santistevan, (2) AHA
    4 Capital Improvements Projects Coordinator James Tacosa, (3) ProBuild employee
    5 Kenneth Garcia, (4) licensed stucco contractor/expert witness Danny Carrillo,2 (5)
    6 AHA Capital Improvements Manager Patrick Strosnider, and (6) AHA Executive
    7 Director Linda Bridge. Both Santistevan and Tacosa provided overviews of the events
    8 leading up to AHA’s termination of the Contract, including the approval of
    9 ParexUSA elastomeric coating for use on the project. The other witnesses testified
    10 more narrowly and only with respect to their own expertise or involvement in the
    11 project.
    12   {22}   Santistevan testified that (1) AHA approved ParexUSA elastomeric coating for
    13 use on the project, (2) Unified applied ParexUSA elastomeric coating according to
    14 the manufacturer’s recommendations, (3) the ProBuild invoices indicated that Unified
    15 purchased seventy-nine pails of ParexUSA elastomeric coating, (4) seventy-nine pails
    16 of ParexUSA elastomeric coating would cover between 9,875 and 14,220 square feet
    2
    17           AHA did not expressly qualify Carrillo as an expert witness. However, when
    18   Unified raised this issue, the district court stated “I’m from that school where you
    19   don’t have to offer the expert, but if the expert starts to testify and you don’t believe
    20   that he’s qualified, then you need to make the objection.” Unified did not offer further
    21   objection to Carrillo’s testimony or expertise.
    8
    1 of porous surface, (5) 716 Morris NE is 18,986 square feet, (6) 903 Nakomis NE is
    2 19,592 square feet, and (7) Unified “would have” purchased additional pails of
    3 elastomeric coating to complete the project.
    4   {23}   Garcia testified that (1) the ProBuild invoices indicated that Unified purchased
    5 seventy-nine pails of ParexUSA elastomeric coating, (2) the stucco surfaces at issue
    6 were porous, (3) seventy-nine pails of ParexUSA elastomeric coating would cover
    7 between 9,875 and 13,5003 square feet of porous surface, and (4) he did not recall
    8 Unified purchasing elastomeric coating in addition to the quantity reflected on the
    9 invoices.
    10   {24}   Due to the discrepancy between Santistevan’s testimony and Garcia’s
    11 testimony with respect to the purchase of additional elastomeric coating, the district
    12 court allowed Unified to recall Garcia for the purpose of introducing additional
    13 invoices. Unified declined to recall Garcia.
    14   {25}   Tacosa testified that 716 Morris NE and 903 Nakomis NE consist of between
    15 40,000 and 43,000 square feet of surface area that required elastomeric coating under
    16 the Contract. He further testified that he suspected that Unified was under-applying
    17 the elastomeric coating because the ProBuild invoices indicated that Unified
    18       3
    This calculated range appears to result from a multiplication error during
    19 Garcia’s testimony. The correct range as per the manufacturer’s guide, and as
    20 indicated above, is 9,875 to 14,220 square feet.
    9
    1 purchased insufficient material to cover the surface area in question to the thickness
    2 required by the manufacturer.
    3   {26}   AHA offered expert testimony from Carrillo, whom it hired to provide an
    4 independent analysis of Unified’s performance. Carrillo conducted visual inspections
    5 of 716 Morris NE, 903 Nakomis NE, and 514 Morris NE and prepared a written
    6 report that presented his findings. The district court received Carrillo’s report in
    7 evidence. Carrillo’s inspection evaluated Unified’s performance against the scope of
    8 work outlined in IFB B13001 and concluded that:
    9          There are numerous instances where new paint was applied directly to
    10          existing damaged wood, without adhering to the printed specifications.
    11          . . . Paint was not applied to 100% of CMU wall surfaces. In addition
    12          there were many instances of paint not being applied to the proper
    13          thickness. In order for an elastomeric paint to protect the underlying
    14          CMU the paint must be applied such that no moisture can enter below
    15          the paint, (no pin-holing). CMU walls were painted without installing
    16          cap blocks. . . . Cracks were simply patched with El Rey Premium
    17          stucco, no fiber mesh and basecoat. Large holes were left in stucco,
    18          allowing points for moisture infiltration. Some walls were painted
    19          lacking the proper paint thickness. The lack of proper thickness paint is
    20          visually evident, and will remain so for the life of the stucco system.
    21          Pin-holing is a characteristic of application, not aging.
    22 Carrillo’s testimony was consistent with his report. Carrillo also testified that there
    23 would be “no way to get the proper thickness” if the quantity of elastomeric coating
    24 purchased by Unified was applied to approximately 40,000 square feet of surface area
    10
    1 and agreed with AHA’s counsel that the incorrect application of elastomeric coating
    2 “is almost worse than not putting it on at all.”
    3   {27}   Both parties offered testimony related to damages resulting from the others’
    4 breach of the Contract. Strosnider testified that he walked the project sites with a
    5 general contractor for the purpose of estimating the scope and cost of required repairs
    6 at 716 Morris NE and 903 Nakomis NE. This estimate was memorialized as
    7 Defendant’s Exhibit HHH, which the district court received in evidence. The estimate
    8 indicated a cost of $125,600 for repairs at 716 Morris NE and 903 Nakomis NE,
    9 including (1) applying a second coat of elastomeric coating to the buildings and
    10 walls, and (2) sanding, patching, priming and painting the fascia.
    11   {28}   After the close of the testimony, the parties submitted closing arguments in
    12 writing. Unified’s argument articulated its position that the Contract required AHA
    13 to provide Unified with notice and opportunity to cure prior to termination. On April
    14 10, 2015, the district court issued its letter decision, stating that both parties breached
    15 the Contract and were liable for damages.
    16   {29}   AHA’s breach resulted from its failure to follow the disputed billing provision
    17 of the Contract. However, the district court ruled that because Unified provided
    18 notice of a “major dispute” as of October 15, 2013, AHA was not subject to sanctions
    11
    1 under the Prompt Payment Act. The district court awarded Unified $92,318.63 for
    2 completed, but unpaid, work at 716 Morris NE, 903 Nakomis NE and 514 Morris NE.
    3   {30}   Unified’s breach resulted from its failure to apply elastomeric coating in
    4 accordance       with   the manufacturer’s        specifications   and   its   intentional
    5 misrepresentations as to the same. The district court ruled that Unified’s conduct
    6 resulted in a “material[] breach[]” of the Contract and justified termination by AHA.
    7 The district court awarded $125,600 in damages on AHA’s counterclaim. It
    8 specifically tied this amount to necessary repairs at 716 Morris NE and 903 Nakomis
    9 NE. The district court did not award additional damages sought by AHA due to
    10 insufficient evidence.
    11   {31}   In its letter decision, the district court ordered the parties to submit requested
    12 findings of fact and conclusions of law within fourteen days if either party wished to
    13 appeal. Neither party did so, and the district court entered its judgment on April 24,
    14 2015. On April 27, 2015, Unified filed a motion for reconsideration. This motion
    15 addressed (1) whether AHA’s evidence of damages was sufficient as a matter of law,
    16 (2) the district court’s method of calculating damages, and (3) the district court’s
    17 refusal to grant interest pursuant to the Prompt Payment Act. The district court
    18 refused to consider Unified’s motion. In doing so, it noted that neither party timely
    19 filed findings of fact or conclusions of law. Unified filed requested findings of fact
    12
    1 and conclusions of law on June 3, 2015 and filed its notice of appeal on June 11,
    2 2015. The district court did not act on the June 3, 2015 filing.
    3 PRESERVATION
    4   {32}   To preserve an alleged error for appeal, a litigant must make known to the court
    5 the action that the litigant desires the court to take or the litigant’s objection to the
    6 action of the court and the grounds therefor. Rule 1-046 NMRA. In their appellate
    7 briefing, both parties discuss the effect of Unified’s failure to request findings of fact
    8 and conclusions of law on our appellate jurisdiction and standard of review.
    9 Historically, the failure to request findings of fact and conclusions of law was a bar
    10 to appellate review of the sufficiency of the evidence in a civil case. See, e.g., Duran
    11 v. Montoya, 1952-NMSC-025, ¶ 6, 
    56 N.M. 198
    , 
    242 P.2d 492
    (“We have . . .
    12 repeatedly held a party could not obtain a review of the evidence where he failed to
    13 make requested findings or file exceptions.”). However, in Cockrell v. Cockrell, our
    14 Supreme Court expressly held that “a request for findings [of fact and conclusions of
    15 law] is not the only means of preserving error based upon insufficiency of the
    16 evidence to support a judgment.” 1994-NMSC-026, ¶ 1, 
    117 N.M. 321
    , 
    871 P.2d 977
    .
    17 As such, a party may preserve questions as to the sufficiency of the evidence if the
    18 party timely submits findings of fact and conclusions of law or “otherwise call[s] the
    13
    1 [district] court’s attention to a problem with the sufficiency of the evidence[.]” 
    Id. ¶¶ 8-9.
    2   {33}   In the current case, Unified failed to timely submit requested findings of fact
    3 and conclusions of law but did file a motion for reconsideration of the judgment. Had
    4 this motion addressed the sufficiency of the evidence, it could have preserved a
    5 sufficiency argument on appeal. However, as noted in its brief in chief, the purpose
    6 of Unified’s motion for reconsideration was not to “challenge any findings made by
    7 the [district] court in its letter decision.” Instead, the motion for reconsideration
    8 “assumed that the [district] court was correct” and “challenged only the legal issues”
    9 related to the damages award.
    10   {34}   We reiterate that a party need not request findings of fact and conclusions of
    11 law to preserve certain issues for appeal. Blea v. Sandoval, 1988-NMCA-036, ¶ 7,
    12 
    107 N.M. 554
    , 
    761 P.2d 432
    . However, in the absence of findings of fact and
    13 conclusions of law, or an alternate manner of calling the insufficiency of the evidence
    14 to the attention of the district court, our review is limited to “review [of] the [district]
    15 court’s decision to determine whether it is legally correct, and whether it is supported
    16 by findings of fact, if any, made by the [district] court.” 
    Id. 17 BREACH
    OF CONTRACT BY UNIFIED
    18   {35}   The district court found that Unified materially breached the Contract and
    19 concluded that AHA properly terminated the Contract. Unified argues that the district
    14
    1 court’s finding of breach was erroneous because AHA did not give Unified notice and
    2 opportunity to cure as required by the Contract itself and general principles of
    3 contract law. AHA argues in response that notice and opportunity to cure are not
    4 required to terminate a contract if the alleged breach is “vital” to the existence of the
    5 contract or if providing notice and opportunity to cure would be “futile.”
    6   {36}   Both parties assert that we should review this issue as a mixed question of fact
    7 and law. We agree but note that our review addresses two distinct questions: (1)
    8 whether the Contract required that AHA provide Unified with notice and opportunity
    9 to cure prior to termination; and (2) if not, whether Unified materially breached the
    10 Contract. The first question is one of law, which we review de novo. See Rivera v.
    11 Am. Gen. Fin. Servs., Inc., 2011-NMSC-033, ¶ 27, 
    150 N.M. 398
    , 
    259 P.3d 803
    12 (“Contract interpretation is a matter of law[.]”). The second question is one of fact,
    13 which we review under a substantial evidence standard. See Collado v. City of
    14 Albuquerque, 2002-NMCA-048, ¶ 15, 
    132 N.M. 133
    , 
    45 P.3d 73
    (“Breach of contract
    15 is a question of fact that we review under a substantial evidence standard.”);
    16 KidsKare, P.C. v. Mann, 2015-NMCA-064, ¶ 20, 
    350 P.3d 1228
    (“The materiality of
    17 a breach is a specific question of fact.” (alteration, internal quotation marks, and
    18 citation omitted)). “Substantial evidence is such relevant evidence as a reasonable
    19 mind might accept as adequate to support a conclusion.” Collado, 2002-NMCA-048,
    15
    1 ¶ 15 (internal quotation marks and citation omitted). However, a party that fails to
    2 “request or timely submit findings [of fact and conclusions of law] or otherwise call
    3 the [district] court’s attention to a problem with the sufficiency of the evidence . . .
    4 waive[s the] right to appellate review.” Cockrell, 1994-NMSC-026, ¶ 9.
    5 Notice and Opportunity to Cure
    6   {37}   Unified’s brief in chief cites various out-of-state cases for the proposition that
    7 “notice and an opportunity to cure is normally considered to be a condition precedent
    8 to termination [of a contract] by default.” See, e.g., Blaine Econ. Dev. Auth. v. Royal
    9 Elec. Co., 
    520 N.W.2d 473
    , 476-77 (Minn. Ct. App. 1994) (holding that the contract
    10 at issue required written notice and opportunity to cure prior to termination for
    11 default). In response, AHA cites various out-of-state cases for the proposition that
    12 exceptions to such requirements apply under certain factual circumstances. See, e.g.,
    13 Olin Corp. v. Cent. Indus., Inc., 
    576 F.2d 642
    , 646-47 (5th Cir. 1978) (holding that
    14 a breach that is “vital to the existence of the contract” excuses performance); Giuffre
    15 Hyundai, Ltd. v. Hyundai Motor Am., 
    756 F.3d 204
    , 210 (2d Cir. 2014) (holding that
    16 performance is excused “when the breaching party’s misfeasance is incurable and
    17 when the cure is unfeasible” (alteration, internal quotation marks, and citation
    18 omitted)).
    16
    1   {38}   Either argument may have merit under different circumstances. At common
    2 law, “[t]he concept of cure is deeply engrained . . . as an implied condition in every
    3 contract.” Philip L. Bruner & Patrick J. O’Connor, Jr., 5 Bruner & O’Connor
    4 Construction Law § 18:37 (2016). In the current case, however, the language of the
    5 Contract militates against drawing inferences and instead allows for a decision based
    6 upon basic rules of contract interpretation. In Public Service Company of New Mexico
    7 v. Diamond D Construction Company, this Court compiled and reiterated these basic
    8 rules as follows:
    9          [W]e view the contract as a harmonious whole, give meaning to every
    10          provision, and accord each part of the contract its significance in light
    11          of other provisions. We will not interpret a contract such that our
    12          interpretation of a particular clause or provision will annul other parts
    13          of the document, unless there is no other reasonable interpretation.
    14          Apparently conflicting provisions must be reconciled so as to give
    15          meaning to both, rather than nullifying any contractual provision, if
    16          reconciliation can be effected by any reasonable interpretation of the
    17          entire instrument in light of the surrounding circumstances.
    18 2001-NMCA-082, ¶ 19, 
    131 N.M. 100
    , 
    33 P.3d 651
    (internal quotation marks and
    19 citations omitted). We apply these rules to the Contract.
    20   {39}   Section 10.1 of the Contract, entitled “Remedies for Contractor Breach[,]”
    21 includes four subsections, numbered 10.1.1 through 10.1.4. The pertinent parts of
    22 Section 10.1 and Subsections 10.1.1 and 10.1.2 read:
    23          10.1 . . . Pertaining to contract-related issues, it is the responsibility
    24          of both [AHA] and [Unified] to communicate with each in as clear and
    17
    1        complete a manner as possible. If at any time during the term of this
    2        contract [AHA] or [Unified] is not satisfied with any issue, it is the
    3        responsibility of that party to deliver to the other party communication,
    4        in writing, fully detailing the issue and corrective action[.] . . . Further,
    5        [AHA] shall, at a minimum, employ the following steps in dealing with
    6        [Unified] as to any performance issues:
    7              10.1.1        If [Unified] is in material breach of the [C]ontract,
    8                            [AHA] may promptly invoke the termination clause
    9                            detailed within Form HUD-5370 (11/2006) . . . and
    10                            terminate the [C]ontract for cause. . . .
    11              10.1.2        Prior to termination, [AHA] may choose to warn
    12                            [Unified] verbally or in writing, of any issue of non-
    13                            compliant or unsatisfactory performance. Such
    14                            written warning may include placing [Unified] on
    15                            probation, thereby giving [Unified] a certain period
    16                            of time to correct the deficiencies or potentially
    17                            suffer termination.
    18 (Emphasis added.) As a threshold matter, the Contract distinguishes between
    19 “contract-related issues” and “performance issues.” While the Contract does not
    20 define these terms, AHA’s notice of termination indicates a dispute arising from
    21 Unified’s performance. Statements by AHA to Unified indicating AHA’s
    22 dissatisfaction with Unified’s performance include, but are not limited to,
    23               Given your failure to perform in compliance with contractual
    24        requirements to use the material required for construction services as
    25        identified in the Technical Specifications . . . and your failure to follow
    26        the manufacturer’s recommended application process for these materials
    27        in the construction services you have provided . . . you are in material
    28        breach of the . . . Contract[.]
    29 (Emphasis added.)
    18
    1   {40}   Viewing the Contract as a harmonious whole, performance-related issues are
    2 a subset of contract-related issues and are afforded distinct treatment with respect to
    3 notice and opportunity to cure requirements. Subsections 10.1.1 through 10.1.4 relate
    4 directly to remedies for contractor breach arising from performance-related issues.
    5 Subsection 10.1.2 articulates that AHA “may” elect to provide notice and opportunity
    6 to cure. See Cerrillos Gravel Prods., Inc. v. Bd. of Cty. Comm’rs of Santa Fe Cty.,
    7 2005-NMSC-023, ¶ 12, 
    138 N.M. 126
    , 
    117 P.3d 932
    (noting that the word “may” is
    8 permissive). This language, of course, also affords AHA the right not to provide such
    9 notice.
    10   {41}   Unified argues that language in Section 10.1 requires that AHA provide notice
    11 and opportunity to cure in the context of performance-related disputes. But such a
    12 reading would nullify the language of Subsection 10.1.2. See Diamond D Constr. Co.,
    13 2001-NMCA-082, ¶ 19 (“Apparently conflicting provisions must be reconciled so as
    14 to give meaning to both, rather than nullifying any contractual provision[.]” (internal
    15 quotation marks and citation omitted)).
    16   {42}   Unified additionally argues that Form HUD-5370 requires that AHA provide
    17 notice and opportunity to cure. In support of this argument, Unified cites to
    18 Subsection 20(H) of Form HUD-5370, which provides:
    19          If the Contractor does not promptly replace or correct rejected work, the
    20          [public housing authority] may (1) by contract or otherwise, replace or
    19
    1          correct the work and charge the cost to the Contractor, or (2) terminate
    2          for default the Contractor’s right to proceed.
    3   {43}   Subsection 20(h) of Form HUD-5370, however, merely provides an alternate
    4 justification for a public housing authority to terminate a contract for default. It in no
    5 way limits AHA’s right to terminate for material breach as provided in the Contract.
    6 Subsection 10.1.1 of the Contract expressly allows AHA to “promptly invoke the
    7 termination clause detailed within Form HUD-5370 . . . and terminate the [C]ontract
    8 for cause” if Unified “is in material breach[.]” Subsection 20(h) of Form HUD-5370
    9 is not a termination clause. Compare Form HUD-5370 § 20, with Form HUD-5370
    10 §§ 32, 34.
    11   {44}   The United States Court of Claims has strictly construed the default clause
    12 within Form HUD-5370. See Prof’l Servs. Supplier, Inc. v. United States, 
    45 Fed. Cl. 13
    808, 810 (Fed. Cl. 2000) (holding that federal acquisition requirement (FAR) 48
    14 C.F.R. Section 52.249-10 “does not require that a contractor be afforded a period in
    15 which to cure defects before a contract is terminated for default”);4 Bruner &
    16 
    O’Connor, supra
    at § 18:37 (“[T]he absence of an express reference to ‘cure notice’
    17 in the default clause . . . mean[s] that a federal construction contractor has no right to
    4
    18         Prior to its recent amendment, the default clause contained within 48 C.F.R
    19 Section 52.249-10(a) was identical to that contained in Form HUD-5370. After the
    20 amendment, the clauses remain nearly identical.
    20
    1 cure its defaults before termination of its contract.”). We see no reason to interpret
    2 this federal regulation more broadly than our federal courts.
    3   {45}   Although deficiencies in Unified’s performance undoubtedly could have been
    4 cured, neither the Contract nor the default clause contained within Form HUD-5370
    5 requires that AHA provide notice and opportunity to cure performance-related issues
    6 prior to termination. As such, AHA was within its contractual rights to terminate the
    7 Contract if Unified’s conduct resulted in a material breach. See KidsKare, P.C., 2015-
    8 NMCA-064, ¶ 20 (“A material breach of a contract excuses the non-breaching party
    9 from further performance under the contract.”).
    10 Material Breach of the Contract
    11   {46}   Because the district court did not err as a matter of law with respect to
    12 Unified’s entitlement to notice and opportunity to cure, we turn to the district court’s
    13 factual findings. Unified argues that the district court’s finding that Unified breached
    14 the Contract is “directly contrary to all of the evidence.”
    15   {47}   In its letter decision, the district court expressly found that (1) “[i]t would have
    16 been mathematically impossible for [Unified] to have properly applied the
    17 elastomeric coating[,]” and (2) Unified’s failure “to prosecute the work . . . [or]
    18 acknowledge[] that [it] had not purchased enough coating to properly complete the
    19 work” resulted in a material breach of the Contract. These findings relate to the
    21
    1 testimony of Santistevan and Garcia who addressed the quantity and coverage of
    2 elastomeric coating pursuant to the manufacturer’s recommendations. Unified did not
    3 timely submit findings of fact and conclusions of law. As stated above, a party that
    4 fails to “request or timely submit findings [of fact and conclusions of law] or
    5 otherwise call the [district] court’s attention to a problem with the sufficiency of the
    6 evidence . . . waive[s the] right to appellate review.” Cockrell, 1994-NMSC-026, ¶ 9.
    7 As a result, the district court’s findings and conclusions as articulated in its letter
    8 decision are binding on this Court.
    9 Substantial Evidence of Unified’s Deficient Performance
    10   {48}   Unified additionally claims that “the [district] court erred in finding that [it]
    11 failed to apply the elastomeric coating in accordance with the manufacturer’s
    12 recommended thickness.” Although Unified characterizes this as a separate argument
    13 on appeal, its alleged under-application of the elastomeric coating was the specific
    14 basis of the breach. Therefore, these arguments are inextricably linked.
    15   {49}   As noted immediately above, the district court expressly found that Unified did
    16 not apply the elastomeric coating in accordance with the manufacturer’s
    17 recommendations. Because Unified waived its right “to object that the judgment is
    18 not supported by the evidence” the district court’s factual findings as to Unified’s
    22
    1 under-application of elastomeric coating are again binding on this Court. 
    Id. ¶ 8
    2 (emphasis omitted).
    3 GROUNDS FOR TERMINATION
    4   {50}   Unified argues that the district court erred in allowing AHA to raise grounds
    5 for termination other than those articulated as the basis for termination prior to trial.
    6 In doing so, it makes both evidentiary and legal arguments. Unified’s evidentiary
    7 argument again relates to the district court’s findings of fact as to the application of
    8 elastomeric coating. We decline to re-address this argument. See 
    id. We review
    9 Unified’s legal argument de novo. Eker Bros. Inc. v. Rehders, 2011-NMCA-092, ¶ 7,
    10 
    150 N.M. 542
    , 
    263 P.3d 319
    .
    11   {51}   AHA’s notice of termination cited Unified’s (1) use of a non-approved
    12 elastomeric coating and (2) failure to follow the manufacturer’s recommended
    13 application process. The notice of termination detailed the second justification,
    14 referring to Unified’s failure to utilize a “two coat” application process. At trial, AHA
    15 expanded this justification to include the theory that Unified simply under-applied
    16 elastomeric coating, regardless of the number of coats applied.
    17   {52}   Unified argues that federal contracting law—arguably applicable here due to
    18 the Contract’s incorporation of Form HUD-5370—prohibited AHA from raising the
    19 theory at trial that Unified under-applied elastomeric coating. In support of this
    23
    1 argument, Unified cites McDonnell Douglas Corp. v. United States, 
    35 Fed. Cl. 358
    2 (Fed. Cl. 1996), rev’d on other grounds by McDonnell Douglas Corp. v. United
    3 States, 
    182 F.3d 1319
    (Fed. Cir. 1999).
    4   {53}   In McDonnell Douglas, the United States Court of Claims held that “[a]
    5 termination for default may be justified at trial on other grounds in some
    6 circumstances, if the Government exercised discretion in terminating the contract.”
    
    7 35 Fed. Cl. at 374
    . The court, however, limited its holding to circumstances in which
    8 “the reason used must have been a non-curable one, so that the contractor would not
    9 be prejudiced by the lack of a cure notice.” 
    Id. As discussed
    above, Unified is not
    10 entitled to notice and opportunity to cure under the Contract or Form HUD-5370.
    11 McDonnell Douglas is, therefore, distinguishable inasmuch as the prejudice sought
    12 to be prevented does not arise in the absence of the right to notice and opportunity to
    13 cure. In the absence of prejudice, we discern no reason to limit the grounds upon
    14 which a governmental entity, as a contract purchaser, may attempt to prove a default
    15 by a contractor. See Coll. Point Boat Corp. v. United States, 
    267 U.S. 12
    , 15-16
    16 (1925) (holding that a party to a contract “may . . . justify an asserted termination,
    17 rescission, or repudiation, of a contract by proving that there was, at the time, an
    18 adequate cause, although it did not become known to him until later”); Kelso v. Kirk
    19 Bros. Mech. Contractors, Inc., 
    16 F.3d 1173
    , 1175 (Fed. Cir. 1994) (holding that a
    24
    1 default termination shall be sustained “if justified by circumstances at the time of
    2 termination, regardless of whether the Government originally removed the contractor
    3 for another reason”).
    4   {54}   Our conclusion is bolstered by the nature of Unified’s argument on this issue.
    5 The evidence and notice of termination provide that AHA was concerned that
    6 Unified’s application of elastomeric coating did not comply with the manufacturer’s
    7 requirements. Whether AHA articulated this concern by reference to a certain number
    8 of coats, or by reference to the gross quantity of elastomeric coating applied, is a
    9 distinction without a meaningful difference. Both provide an adequate basis for a
    10 finding of material breach due to the under-application of the elastomeric coating.
    11 Based upon the evidence presented, it was impossible for Unified to comply with the
    12 manufacturer’s recommended application requirements and to properly coat all the
    13 porous surfaces of the two buildings. The seventy-nine pails of coating purchased
    14 were insufficient to comply with the Contract, regardless of whether Unified agreed
    15 to apply the coating in a one-step process or a two-step process for 716 Morris NE
    16 and 903 Nakomis NE. Under the circumstances of this case, the district court did not
    17 err in considering the grounds presented by AHA at trial—the misapplication of the
    18 elastomeric coating—as the basis for the termination of the Contract.
    25
    1 DAMAGES
    2   {55}   Unified makes two arguments related to the district court’s award of damages:
    3 (1) whether “as a matter of law, the evidence provided by AHA was sufficiently
    4 certain to be the basis for an award of damages,” and (2) if so, whether the district
    5 court erred by calculating damages in a manner that resulted in a double recovery to
    6 AHA.
    7 Substantial Evidence of Damages
    8   {56}   As a general rule, the amount of damages claimed for breach of contract must
    9 be reasonably ascertainable. Louis Lyster, Gen. Contractor, Inc. v. Town of Las
    10 Vegas, 1965-NMSC-097, ¶ 7, 
    75 N.M. 427
    , 
    405 P.2d 665
    . “Damages which are
    11 speculative, conjectural, or remote are not to be considered for compensation.” City
    12 of Santa Fe v. Komis, 1992-NMSC-051, ¶ 11, 
    114 N.M. 659
    , 
    845 P.2d 753
    (internal
    13 quotation marks and citation omitted). Unified argues, essentially, that the evidence
    14 at trial is insufficient to meet these standards as a matter of law. We disagree with
    15 Unified’s characterization of its evidentiary argument as a question of law and
    16 reiterate that “we review findings regarding damages to determine whether they are
    17 supported by substantial evidence.”Jones v. Auge, 2015-NMCA-016, ¶ 48, 
    344 P.3d 18
    989 (internal quotation marks and citation omitted).
    26
    1   {57}   In Louis Lyster, cited by Unified on appeal, our Supreme Court reversed an
    2 award of damages because it was based upon a “rough estimate”—a circumstance that
    3 arguably occurred in the current case. 1965-NMSC-097, ¶ 8. But Louis Lyster was not
    4 reversed as a matter of law. It was reversed because substantial evidence did not
    5 support the award. 
    Id. 6 {58}
      The district court expressly found that “[t]he site inspection did reveal defects
    7 with regard to the elastomeric coating, a hole in the soffit, failure to properly prepare
    8 the fascia for painting, and other defects[.]” Carrillo’s expert testimony and
    9 Defendant’s Exhibit III, which detailed deficiencies in Unified’s performance,
    10 support these findings. The district court also expressly found that AHA suffered
    11 damages in the amount of $125,600. Strosnider’s testimony and Defendant’s Exhibit
    12 HHH, which detailed the scope and cost of required repairs, support this finding. A
    13 district court’s calculation of the amount of damages “will not be disturbed unless
    14 clearly wrong.” Davis v. Campbell, 1948-NMSC-041, ¶ 18, 
    52 N.M. 272
    , 
    197 P.2d 15
    430. As discussed repeatedly in this opinion, Unified’s failure to preserve its
    16 sufficiency argument results in the waiver of its right to a review of the evidence on
    17 appeal. Cockrell, 1994-NMSC-026, ¶¶ 8-9. Unified’s argument that the evidence at
    18 trial is insufficient as a matter of law is not well-taken.
    27
    1 Erroneous Calculation
    2   {59}   Unified additionally argues that the district court’s failure to offset AHA’s
    3 damages by the value of uncompensated services Unified provided was an error that
    4 resulted in a double recovery for AHA. In support of this argument, Unified claims
    5 that even the defective work it performed added value to AHA’s property. We
    6 disagree that Unified is entitled to additional payment or an offset of damages for
    7 defective work. However, “[i]t is a fundamental tenet of the law of contract remedies
    8 that, regardless of the character of the breach, an injured party should not be put in
    9 a better position than had the contract been performed.” Paiz v. State Farm Fire &
    10 Cas. Co., 1994-NMSC-079, ¶ 30, 
    118 N.M. 203
    , 
    880 P.2d 300
    (internal quotation
    11 marks and citation omitted).
    12   {60}   UJI 13-850 NMRA provides that damages for defective or unfinished
    13 construction are measured by “[t]he reasonable cost of completing the construction
    14 called for in the contract.” This instruction does not, however, discount general
    15 principles of contract law, one of which requires that damages for breach of contract
    16 “must be the amount of money that will place [the injured party] in the position [it]
    17 would have been in if the contract had been performed.” UJI 13-843 NMRA.
    18   {61}   The interplay between these jury instructions is captured in Castricone v.
    19 Michaud, in which the Illinois Court of Appeals applied the “contract price limitation
    28
    1 rule” under similar circumstances. 
    583 N.E.2d 1184
    , 1186 (Ill. App. Ct. 1991). In
    2 Castricone, the defendant was a building contractor who entered a contract to build
    3 a single-family home for the plaintiffs. 
    Id. at 1184.
    A dispute arose over the quality
    4 of workmanship, and the defendant ceased work prior to completing the project. 
    Id. 5 The
    contract price was $89,000, of which the plaintiffs paid $76,400 prior to the date
    6 on which the defendant ceased work. 
    Id. at 1184,
    1186. “[T]he plaintiffs expended
    7 $27,407.88 to finish the home, and to repair and replace defective construction.” 
    Id. 8 at
    1185.
    9   {62}   At trial, the district court awarded the plaintiffs $27,407.88, the entire cost
    10 incurred in completing and repairing the house. 
    Id. The appellate
    court reversed and
    11 reduced the plaintiffs’ award for breach of contract damages to $14,807.88. 
    Id. at 12
    1186. In so holding, the appellate court applied the contract price limitation rule,
    13 which provides that “the measure of damages is the difference between the total cost
    14 of completing the building less the contract price.” 
    Id. at 1185.
    See 24 Richard A.
    15 Lord, Williston on Contracts §66:17, at 462 (2002 4th ed.) (“If the defect causing the
    16 breach is remediable from a practical standpoint, recovery generally will be based on
    17 the market price of completing or correcting the performance, minus the unpaid part
    18 of the contract price.”).
    29
    1   {63}   In the current case, the district court awarded contract damages to both Unified
    2 and AHA. It based Unified’s damages on the value of previously uncompensated
    3 work at three project sites: (1) $47,996.84 at 716 Morris NE; (2) $15,842.79 at 903
    4 Nakomis NE; and (3) $28,478.99 at 514 Morris NE. It based AHA’s damages on the
    5 estimate to repair and complete work at 716 Morris NE and 903 Nakomis NE: a total
    6 of $125,600. The district court then fully offset the awards, which resulted in a
    7 judgment against Unified in the amount of $33,281.37.
    8   {64}   We adopt and apply the contract price limitation rule in this case because it
    9 comports with the general principles of contract law applied in New Mexico. See
    10 Paiz, 1994-NMSC-079, ¶ 30 (“It is a fundamental tenet of the law of contract
    11 remedies that, regardless of the character of the breach, an injured party should not
    12 be put in a better position than had the contract been performed.” (internal quotation
    13 marks and citation omitted)). Under the contract price limitation rule, the district
    14 court’s judgment was error.
    15   {65}   As noted in the district court’s letter decision, AHA had previously paid
    16 Unified $52,444.98 and $87,200.72 for work performed at 716 Morris NE and 903
    17 Nakomis NE respectively. Therefore, under the district court’s decision, Unified will
    18 receive, and AHA will pay, a total of $100,441.82 for work performed at 
    716 Morris 19
    NE and $103,043.51 for work performed at 903 Nakomis NE. These payments,
    30
    1 totaling $203,485.33, amount to less than the contract price of $278,349 for both
    2 properties. To affirm the district court’s award of damages to AHA of $125,600 with
    3 regard to the 716 Morris NE and 903 Nakomis NE properties, in light of the payments
    4 totaling $203,485.33, would place AHA in a better position than if the contract had
    5 been fully performed.
    6   {66}   Instead, AHA is entitled to “the market price of completing or correcting the
    7 performance, minus the unpaid part of the contract price.” 24 Lord, supra, § 66:17,
    8 at 462. Therefore, the correct measure of Unified’s liability for AHA’s damages with
    9 respect to 716 Morris NE and 903 Nakomis NE is the difference between the
    10 $125,600 required to complete and correct the performance and the unpaid part of the
    11 contract price of $74,863.67. This calculation results in damages to AHA of
    12 $50,736.33.
    13   {67}   In order to reach the final damages amount, the $50,736.33 must be reduced
    14 by $28,478.99 to account for damages awarded to Unified for previously
    15 uncompensated work at 514 Morris NE. This reduction results in total damages to
    16 AHA of $22,257.34. We reverse the district court’s judgment in favor of AHA and
    17 remand to the district court for entry of a final judgment in favor of AHA in the
    18 amount of $22,257.34. See Miller v. Bank of Am., N.A., 2014-NMCA-053, ¶ 47, 326
    
    19 P.3d 20
    (recalculating compensatory damages and remanding to the district court for
    31
    1 entry of a final judgment consistent with the opinion), rev’d on other grounds by
    2 Miller v. Bank of Am., N.A., 2015-NMSC-022, 
    352 P.3d 1162
    .
    3 NOTICE OF BILLING DISPUTES AND STATUTORY INTEREST
    4   {68}   Unified argues that AHA failed to provide timely and sufficient notice of
    5 billing disputes as required by the Prompt Payment Act and the Contract. Unified also
    6 argues that the district court erred in concluding that it was not entitled to statutory
    7 interest under the Prompt Payment Act.
    8   {69}   With respect to the Contract, the district court found that AHA “technically
    9 breached the [C]ontract by failing to follow the disputed billing provision of Section
    10 9.0.” While it is possible that this breach merited damages in the form of interest in
    11 accordance with the terms of the Contract, the district court did not rule upon or
    12 discuss this issue in its letter decision. See Rule 12-321(A) NMRA (“To preserve an
    13 issue for review, it must appear that a ruling or decision by the trial court was fairly
    14 invoked.”).
    15   {70}   With respect to the Prompt Payment Act, the district court ruled that AHA’s
    16 mid-October 2013 correspondence constituted sufficient notice of a billing dispute
    17 to limit statutory liability. This ruling raises questions of statutory interpretation,
    18 which we review de novo. Diamond D, 2001-NMCA-082, ¶ 48.
    32
    1   {71}   The Prompt Payment Act provides, in pertinent part, that “all construction
    2 contracts shall provide that payment for amounts due shall be paid within twenty-one
    3 days after the owner receives an undisputed request for payment.” Section 57-28-
    4 5(A). The statute does not define “undisputed” as used therein.
    5   {72}   “Our principal goal in interpreting statutes is to give effect to the Legislature’s
    6 intent. To do so, we first look to the language used and the plain meaning of that
    7 language.” Morris v. Brandenburg, 2015-NMCA-100, ¶ 15, 
    356 P.3d 564
    (internal
    8 quotation marks and citation omitted), aff’d 2016-NMSC-027, 
    376 P.3d 836
    .
    9 Dictionary definitions provide guidance as to the plain meaning of the words at issue.
    10 Griego v. Oliver, 2014-NMSC-003, ¶ 21, 
    316 P.3d 865
    .
    11   {73}   Webster’s International Dictionary defines the word “undisputed” as “not
    12 disputed: unchallenged, unquestioned[.]” Webster’s Third New Int’l Dictionary, 2492
    13 (unabridged ed. 2002). Given this definition, raising a challenge or question as to an
    14 invoiced item limits a defendant’s liability for statutory interest. Nothing in the plain
    15 language of the statute applies additional requirements—for example, those provided
    16 by contract—as a consideration in determining liability.
    17   {74}   The district court concluded that inquiries by AHA related to the application
    18 of elastomeric coating placed Unified on notice of a “major dispute” and limited
    33
    1 AHA’s liability for statutory interest under the Prompt Payment Act. Under the
    2 circumstances of this case, we agree.
    3   {75}   The correspondence considered by the district court in formulating its decision
    4 directly relates to Unified’s performance under the Contract. For example, the
    5 October 16, 2013 post-inspection email messages from AHA to Unified (1) indicated
    6 dissatisfaction with the application of elastomeric coating at 716 Morris NE and 903
    7 Nakomis NE, and (2) asked Unified to confirm that it was applying the elastomeric
    8 coating in accordance with the manufacturer’s recommendations. Similar
    9 correspondence continued through mid-November.
    10   {76}   As indicated by Tacosa’s trial testimony, AHA suspected, but was unaware of
    11 the extent to which, Unified’s performance was deficient. Nevertheless, the mid-
    12 October 2013 correspondence from AHA put Unified on notice that a question, or
    13 dispute, existed with respect to Unified’s entitlement to payment for the subsequently
    14 invoiced work—regardless of whether AHA initially indicated that certain items were
    15 payable. Such notice is sufficient to limit liability for statutory interest under the
    16 Prompt Payment Act.
    17 MOTION TO RECONSIDER
    18   {77}   Unified finally argues that the district court erred in denying its motion for
    19 reconsideration. We review the denial of a motion for reconsideration for abuse of
    34
    1 discretion. Deaton v. Gutierrez, 2004-NMCA-043, ¶ 9, 
    135 N.M. 423
    , 
    89 P.3d 672
    .
    2 This Court has held that a district court does not abuse its discretion in denying a
    3 motion for reconsideration that “was merely a restatement of the arguments [the
    4 defendants] had already advanced.” 
    Id. ¶ 10;
    see, e.g., Servants of Paraclete v. Does,
    5 
    204 F.3d 1005
    , 1012 (10th Cir. 2000) (holding that a motion for reconsideration “is
    6 not appropriate to revisit issues already addressed or advance arguments that could
    7 have been raised in prior briefing”).
    8   {78}   Unified’s motion for reconsideration raised three issues: (1) whether AHA’s
    9 evidence of damages was sufficient as a matter of law, (2) the district court’s refusal
    10 to grant interest pursuant to the Prompt Payment Act, and (3) the district court’s
    11 method of calculating damages. Unified expressly raised the first two arguments in
    12 its written closing argument. As such, the district court did not abuse its discretion in
    13 refusing to reconsider these issues. Deaton, 2004-NMCA-043, ¶ 9.
    14   {79}   The third issue relates to the district court’s method of calculation of damages.
    15 We do not need to address this issue. Even if, in light of our reversal, the district court
    16 abused its discretion in denying Unified’s motion to reconsider on this issue, the
    17 purpose of Unified’s motion to reconsider has been realized. Unified stated in its brief
    18 in chief that its motion for reconsideration challenged only “whether the [district]
    35
    1 court had legally miscalculated its award of damages[.]” We have addressed this issue
    2 on appeal.
    3 CONCLUSION
    4   {80}   For the foregoing reasons, we affirm in part, reverse in part, and remand to the
    5 district court for entry of a final judgment consistent with this opinion.
    6   {81}   IT IS SO ORDERED.
    7                                                  ________________________________
    8                                                  JAMES J. WECHSLER, Judge
    9 WE CONCUR:
    10 ________________________________
    11 TIMOTHY L. GARCIA, Judge
    12 ________________________________
    13 STEPHEN G. FRENCH, Judge
    36