Mandeville v. Reed , 13 Abb. Pr. 173 ( 1850 )


Menu:
  • By the Court.— Jewett, J.

    —The two defendants, having made a joint contract in writing, with Gillman, for the erection of two houses, although one was to be, and was placed on a lot owned in severalty by one defendant, and the other on another lot owned in like manner by the other defendant, under the provisions of the Act of 1830 (Laws of 1830, ch. 330, 412), are jointly liable to the plaintiff, who performed the work in building the stairs in the houses respectively, if the plaintiff has complied, on his part, with the provisions of the statute, requisite to entitle one to obtain a lien, who performs work towards the erection, construction, or finishing of any building in the city of Hew York, erected under a contract in writing, between the owner and builder or other person. The fact that the defendants did not jointly own the lots on which the houses were erected, is, as I think, wholly immaterial. They may he regarded as owners, in respect to the contract with the builder of the houses, within the true interpretation of the statute. The plaintiff agreed with Gillman, as the evidence shows, to erect the stairs in both houses for $100. Having finished the work on the 24th of July, 1847, he made out an “attested account” against Gillman of fifty dollars, for building three flights of stairs in the building one door above 36th-street, in Hew York; and a like account of fifty dollars for building the like stairs in a building two doors above the same, street, both on the westerly'side of the 10th Avenue; and made an affidavit annexed to each account that it was just and true, and a correct account of the amount and value of the work and labor done and performed by him towards the erection of the building above mentioned, and that there was then due and remaining unpaid and unsatisfied for the same, the sum of fifty dollars.

    They were the same buildings contemplated to he built by the contract made between the defendants and Gillman.

    There was, also, an affidavit subjoined to each account, inade by Thomas Jameson the same day, to the effect that the value *177of the work performed by the plaintiff, was correctly stated in the account.

    There was a notice annexed- to each account, subscribed by the plaintiff; the one annexed to the account first mentioned, was addressed to the defendant, David B. Reed, and the other to Eli H. Reed, and stated that the subscriber had a demand as in the within account stated, amounting to fifty dollars, which remained unpaid. These accounts, with the affidavits and notice annexed, were served on the 24th day of July, 1847. The first named, on David B. Reed, and the other, on Eli H. Reed. When the account, &e., was served on David B. Reed, he said that the plaintiff had been expeditious in finishing up the contract, expressed himself satisfied, and stated that there was $690 due to the contractor.

    On the trial it was objected to the giving the accounts in evidence, on the ground that each was made out against one defendant for one half of the amount claimed to be due to the plaintiff under the contract.

    The objection was overruled, and the evidence received. It was also insisted, on a motion for a nonsuit, that there was a misjoinder of the defendants; that the plaintiff having made out his account for the work done on each house separately,, could not sustain an -action for the recovery of the whole sum due him against the defendants jointly, -but should have proceeded against them severally for the recovery of the accounts as made out by him. There was no objection made, that both accounts, affidavits, and notices had not been served or delivered to both defendants.

    The attested accounts were not made against the defendants, or either of them, but against Gillman, the builder, and the employer of the plaintiff, as is contemplated by the statute; and might as well, as it respects their legal effect, be made as they were, in two accounts, one for each house, identifying it upon which the work was performed, as in one account showing that work of the value of $50 had been performed on each house. The mechanic, &e., to entitle himself to- the benefit of the provisions of the statute, is required, not only to make “ an attested- account of the amount and value of the work and labor performed and unpaid,” but he is- required to deliver the ■ same to the owner of the building. If the defendants may be *178regarded, as between themselves and the contractor and other persons doing work towards the erection of the buildings contracted to be built, as joint-owners, by reason of their joint.contract (and I think they may), it would probably be sufficient for the mechanic, &c., in order to acquire a right as against .the owners of the building to be paid the sum due him out of the fund due or to become due from them to the contractor, ■ to deliver his account" so attested to either of such joint-owners.I think it comes within the rule which prevails (except in -giving notice to. charge indorsers of commercial paper), that .where “several are jointly bound to do an act, upon notice to them, notice to one is sufficient.” (3 Com. Dig., tit. Condition, L. 9 ; 5 Ib., tit. Pleader, C., 71. See, also, Crowder a. Shee, 1 Campb., 374.) But it is -not necessary, for the disposition of this cause, to decide that questien, and I do not intend to express a decided opinion upon it; for, as I have already observed, the question, was not made on the trial, nor has it been made on. the - argument here. Upon the delivery of such account to the owners, of the building, the statute makes it. their duty to retain out of their subsequent payments .to the contractor, the amount of such work and labor, for the benefit of the person who has so. performed the same. . :

    The defendants proved by Gillman, that when the. plaintiff’s, attested- accounts were served, it would cost about $8 to, fulfil his contract with him; that he did not contest the account .of. the plaintiff, .because he had made an assignment to Jarvis, and supposed that it.took away all right from him to do,-so. .

    The second section of the statute provides, that whenever any amount of labor performed .on- a building erected under such contract shall be placed in .the. hands of .the owner of such building or -his authorized agent, it. shall, be the duty.of such-owner or agent, to-furnish his contractor with- a copy of such papers, in order that if -there shall be any disagreement between such contractor and his creditor,,they.may,-by amicable.adjustment between themselves, or by arbitration, ascertain , the true sum due. And if the contractor- shall not, within ten days.-after! the receipt of such papers, give the owner-written notice that he. intends to dispute the claim; or if in ten days after-giving .such, notice, he shall refuse or neglect to have the matter adjusted -as aforesaid,.-he .shall be considered as assenting to. the demand,- *179and the owner shall pay the same when it becomes due. Section 3 provides for the submission to arbitration, in case the contractor shall dispute the claim of the person performing the work, &c. And section 4 provides that when the amount due shall be adjusted as before provided, and the contractor shall not within ten days after pay the sum due to his creditor, with costs incurred, the owner shall pay the same out of the fund, as provided by the statute, and that amount due may be recovered from the owner by the creditor of his contractor, &c. The accounts of the plaintiff having been served, as provided by the statute, and Gillman having neglected to give the defendants notice that he intended to dispute the plaintiff’s claim, he must be considered, as provided by the statute, as assenting to it. And the defendants became liable to pay it out of the moneys due or to become due to Gillman.

    The assignment by Gillman to Jarvis did not change the relation existing between the defendants and Gillman by the contract, or affect the relation between the latter and the plaintiff. Gillman remained after, as before, the contractor, and responsible to the defendants for the performance of his contract with them, as well as with the plaintiff, who could as well after, as before, acquire a right to be paid the amount due to him from the defendants, in respect to the money to become due from them as owners, on the performance of the contract made with them by Gillman. Jarvis, the assignee, was not substituted in his place, nor did he contract any obligation to perform the contract, or acquire any right to the moneys to become due on its performance, beyond the balance which might remain, after the defendants had retained enough to discharge such sums as were due to such persons as had performed any work towards the construction of the buildings as Gillman had employed, and who had acquired a right to be paid, by delivering their attested accounts to the defendants. Upon the whole, I think the judgement should be affirmed.

Document Info

Citation Numbers: 13 Abb. Pr. 173

Judges: Jewett

Filed Date: 7/15/1850

Precedential Status: Precedential

Modified Date: 1/12/2023