Riegal Sack Co. v. Tidewater Portland Cement Co. , 158 N.Y.S. 954 ( 1916 )


Menu:
  • Lehman, J.

    The plaintiff brought an action for breach of contract. The complaint alleges that the plaintiff and the defendant entered into an agreement in writing whereby ‘1 the defendant agreed to purchase from the plaintiff, and the plaintiff agreed to furnish, sell and deliver to the defendant at Union Bridge, Maryland, two hundred and fifty thousand seven-ounce first quality Osnaburg cement sacks, and the defendant agreed to pay the plaintiff for said sacks the sum of $82.50 per thousand; and it was further agreed by the terms of said contract that delivery of the said sacks was to be made as ordered by the defendant between June 22, 1914, and December 31, 1914.

    *204“ That the said sacks were to be manufactured by the plaintiff at Jersey City, New Jersey, and were to be transported therefrom and delivered to the defendant at Union Bridge, Maryland, and that said agreement related wholly to interstate commerce.

    That plaintiff duly- performed all the conditions of said agreement on its part to be performed except the furnishing, sale and delivery of the 169,182 sacks hereinafter" mentioned, and furnished to the defendant under said agreement and as ordered by it, 80,818 of the said sacks, which were accepted and paid for by the defendant, but the defendant, prior to the «31st day of December, 1914, cancelled all outstanding orders theretofore given and notified the plaintiff that it would not order or accept from the plaintiff the remaining 169,182 sacks or pay therefor, and neglected and refused to order, accept or pay for the same. That plaintiff -was at all times ready and willing to perform the said agreement on its part with respect to furnishing, selling and delivering the said 169,182 sacks and to furnish, sell and deliver the same in accordance with the terms of said agreement, and would have furnished, sold and delivered said 169,182 sacks to defendant according to the terms of the said agreement, but for defendant’s cancellation, notification, neglect and refusal.

    “ That by reason of the defendant’s said default, the plaintiff was damaged in the sum of $3,806.60, no part of which has been paid, except the sum of $1,903.30, although the balance thereof has been duly demanded.”

    The answer in addition to certain denials sets up as a“ separate defense ” that on or about October 7, 1914, the defendant by letter ordered plaintiff to make up at once a carload of said sacks and requested plaintiff to notify the defendant by return mail when same *205would be ready for shipment. That plaintiff on the following day notified the defendant that it would be unable to deliver the sacks so ordered by defendant for two or three weeks and the defendant thereupon cancelled its said order for a carload of cement sacks and said notice of cancellation was given in writing. “ That because of plaintiff’s failure and refusal to deliver said carload of sacks in accordance with the terms and provisions of said contract, defendant was compelled to purchase said carload of sacks which would number about 84,500 elsewhere. That it was mutually understood and agreed between the parties hereto that plaintiff could and would ship to defendant a carload of cement sacks in four or five days after receipt of order for same but would like ten days ’ notice at the most in which to make delivery of a carload of sacks.” Annexed to the answer are all the writings which passed between the parties.

    The plaintiff filed a reply to this so-called separate defense in which it admitted most of the material allegations in the answer except that it sets forth —“Answering the allegations in paragraph eight of said answer, the plaintiff admits that under ordinary circumstances from four to ten days after receipt of an order would be a reasonable time within which to make delivery of the bags referred to; admits that the plaintiff requested the defendant to give it at least ten days ’ notice of its required shipments of bags and admits that the defendant, on or about the 30th day of July, 1914, promised to give the plaintiff at least ten days’ notice of all required deliveries of bags, and that on or about the 7th day of October, 1914, the defendant notified the plaintiff that it would not require of the plaintiff any further shipments of bags until the latter part of December, 1914; but, except as admitted, denies that there was any agreement between *206the parties with respect to the delivery of said bags except that said bags should be delivered within such time after receipt of an order therefor as was reasonable under all the circumstances then existing; and except as admitted, denies each and every other allegation contained in said paragraph eight.”

    The reply also states “ Further replying, plaintiff alleges that prior to the 7th day of October, 1914, defendant notified plaintiff that it would place an order for a carload of the sacks under the existing contract between the parties, provided the plaintiff would alter the terms thereof so that payment therefor could be made in thirty days instead of ten days, which plaintiff refused to do, and thereupon defendant notified plaintiff that it would not order any of said bags until the latter part of December, 1914, and did not prior to the 7th day of October, 1914, withdraw or modify said notice, and plaintiff accepted and relied thereon. That the reasonable time for the plaintiff to manufacture and deliver to the defendant the said carload of bags under the circumstances existing on the 7th day of October, 1914, was from two to three weeks. ’ ’

    At the opening of the trial the defendant made a motion to dismiss the complaint on the ground that it failed to set forth a cause of action. A discussion followed between court and counsel and in the course of that discussion it developed that after the plaintiff had received the cancellation of the order of October seventh it gave orders to stop manufacturing the sacks and that the defendant thereafter did not order any more sacks but made a settlement in regard to the third carload. After this discussion the trial judge granted judgment to the defendant upon the pleadings and upon the agreed facts.”

    In granting this judgment he stated in effect, that *207he felt that the judgment so ordered was correct and that the procedure adopted was calculated to bring up before this court for review, in the most speedy and economical manner, the questions that were doubtful in this case. Both parties acquiesced in this procedure but the record shows clearly that the case was not actually submitted to the court for any final decision upon an agreed state of facts. The discussion shows that the defendant claimed first, that the complaint sets forth no cause of action; second, that if the complaint does set forth a cause of action then the pleadings taken together with the agreed facts show, as a matter of law, that the defendant never breached the contract: and third, that if it did breach the contract the plaintiff would not, under the pleadings and the agreed facts, be able to show any damages. The purpose of the procedure adopted was to finally determine these questions as matters of law and if the pleadings, as amplified by the agreed facts, still leave any issues open, then the plaintiff is entitled to a reversal.

    The defendant claims that the complaint fails to set forth a cause of action in that it does not set forth that the plaintiff was able to perform; or that the cancellation by the defendant was wrongful. The complaint sets forth that the plaintiff was at all times “ ready and willing to perform the said agreement on its part with respect to furnishing, selling and delivering the said 169,182 sacks and to furnish, sell and deliver the same in accordance with the terms of the agreement and would have furnished, sold and delivered the said 169,182 sacks to defendant according to the terms of the said agreement but for defendant’s cancellation, notification, neglect and refusal.” There seems to me to be no doubt but that these words are sufficient to show that the plaintiff was able to perform. There is strong authority in cases decided in *208other jurisdictions for the view that an allegation of readiness to perforin implies also ability to perform and in this case the allegation that the plaintiff was ready and willing to perform is supplemented by the allegation that it would have performed but for the defendant’s cancellation, notification, neglect or refusal. These allegations, in my opinion, are amply sufficient to show that the plaintiff was able to perform, if performance had not been prevented by the defendant. The cases in this state which the defendant cites are not contrary to this view. They hold only that an allegation of readiness or willingness or of readiness, ability and willingness to perform is not equivalent to an allegation of tender of performance. In this case the plaintiff must also allege either a tender of performance or waiver by the defendant of such a waiver. He has attempted to allege such a waiver by alleging an anticipatory breach of the contract in the words “ but the defendant prior to the 31st day of December, 1914, cancelled all outstanding orders theretofore given and notified the plaintiff that it would not order or accept from the plaintiff the remaining 169,182 sacks or pay therefor and refused to order, accept or pay for the same.” It seems to me that where the complaint sets forth a cause of action upon a contract to sell goods and to deliver them when ordered within a certain time, an allegation of a cancellation of outstanding orders and a refusal to give any further orders is sufficient to show a breach of the contract and a notification that the defendant would not order or accept any further deliveries was a clear waiver of further tenders, especially in view of the allegation that the plaintiff was to manufacture the goods to fill the order. - The defendant urges however that this is true only if the allegations of the complaint show that the cancellation and refusal to order *209or accept was wrongful and that the court cannot presume that a cancellation made is a wrongful cancellation. As a rule of law this statement is correct, but it has no application to the ease at bar. The cancellation of outstanding orders is not made the basis of this action. The breach claimed is the refusal to order or accept the sacks and the cancellation of outstanding orders is material only upon the point whether such refusal was, as a matter of law, wrongful if the plaintiff had, up to that time, duly performed all the other conditions of the agreement, and was ready to furnish, sell and deliver these sacks u in accordance with the terms of the agreement.” The complaint sets forth all these facts and the conclusion that the cancellation of outstanding orders and the refusal to give any further orders were wrongful necessarily follows as a matter of law. The defendant seems throughout to misunderstand the legal effect of these allegations of the complaint and has set forth as a separate and affirmative defense allegations which constitute really a denial of the allegations on the part of the plaintiff that at the time of the cancellation it was ready and willing to furnish and deliver and would have furnished and delivered the remaining sacks “ in accordance with the terms of the agreement ” if the defendant had not notified it of its cancellation of outstanding orders and refusal to accept further deliveries. Under these allegations of the complaint the plaintiff sufficiently raises the issue of whether the refusal was wrongful. If this refusal was wrongful then there is no doubt but that plaintiff may prove its damages as provided in section 145 of the Personal Property Law without proof that it actually manufactured or bought the bags.'

    The only question which requires consideration is whether, upon the agreed facts, the defendant’s can*210cellation of its order to deliver the second carload and its refusal to give a new order were justified as a matter of law; in other words, whether under the agreed facts the plaintiff was ready, able and willing to deliver the sacks in accordance with its contract. The contract is silent as to the time of delivery after an order was given and therefore a term will be implied in the contract that such deliveries should be made in a reasonable time. Both sides agree that under ordinary circumstances a reasonable time would be from four to ten days. It is further agreed that the plaintiff notified the defendant that it could not deliver the bags ordered for two or three weeks. The defendant contends that under these circumstances it was justified, as a matter of law, in refusing to accept such a delivery. That contention, however, is unsound, for the plaintiff claims that these bags were not ordered under ordinary circumstances but that prior to the giving of the order the defendant notified it that it would not order any bags until December. If such notification was given it would not constitute a modification of the contract but it would be material upon the question of what would be a reasonable time for delivery of the bags under those particular conditions. There is nothing in the record which would permit the inference that under those circumstances a delivery of these sacks two or three weeks thereafter would not be within a reasonable time. The plaintiff is entitled under its pleadings.to have this issue determined by the jury.

    Judgment should, therefore, be reversed and a new trial ordered, with costs to appellant to abide the event.

    Pendleton and Whitaker, JJ., concur.

    Judgment reversed and new trial ordered, with costs to appellant to abide event.

Document Info

Citation Numbers: 95 Misc. 202, 158 N.Y.S. 954

Judges: Lehman

Filed Date: 5/15/1916

Precedential Status: Precedential

Modified Date: 1/13/2023