Village of Barrington, IL v. STB ( 2018 )


Menu:
  •                                              In the
    United States Court of Appeals
    For the Seventh Circuit
    ____________________
    No. 17‐3586
    VILLAGE OF BARRINGTON, ILLINOIS,
    Petitioner,
    v.
    SURFACE TRANSPORTATION BOARD, et al.,
    Respondents,
    and
    CANADIAN NATIONAL RAILWAY COMPANY, et al.,
    Intervening Respondents.
    ____________________
    On Petition for Review of an Order of the
    Surface Transportation Board.
    STB Finance Docket No. 35087.
    ____________________
    ARGUED MAY 22, 2018 — DECIDED JUNE 11, 2018
    ____________________
    Before FLAUM and RIPPLE, Circuit Judges, and GETTLEMAN,
    District Judge.*
    * Of the Northern District of Illinois, sitting by designation.
    2                                                       No. 17‐3586
    FLAUM, Circuit Judge. In 2007, Canadian National Railway
    Company  (“CN”)  sought  approval  from  the  Surface  Trans‐
    portation Board (the “Board”) of its acquisition of control of
    the Elgin, Joliet, and Eastern Railway Company (“EJ & E”) rail
    line near Chicago. As part of its review, the Board considered
    the  impact  of  the  acquisition  on  112  railroad  crossings
    throughout the Chicagoland area, including the intersection
    at  U.S.  Highway  14  (“U.S.  14”)  in  the  Village  of  Barrington
    (the  “Village”).  Crossings  projected  to  be  “substantially  af‐
    fected”  by  the  acquisition  were  eligible  for  mitigation
    measures imposed by the Board as a condition to its approval,
    up to and including grade separation between the roadway
    and rail line. The Board approved CN’s acquisition in 2008,
    but determined that U.S. 14 would neither be substantially af‐
    fected nor warrant a grade separation. The Village unsuccess‐
    fully petitioned the Board to reopen its decision in 2011 and
    2014. It failed for a third time in 2017, and now appeals the
    Board’s most recent denial. Because the Village does not pre‐
    sent  new  evidence  or  substantially  changed  circumstances
    that mandate a different result, we deny the petition for re‐
    view.
    I. Background
    A. Factual Background
    CN  is  one  of  Canada’s  two  major  railroads,  extending
    from Halifax, Nova Scotia on the Atlantic coast to Vancouver
    and Prince Rupert, British Columbia on the Pacific. Through
    its  Grand  Trunk  Corporation  subsidiary,  the  company  also
    controls numerous rail carriers in the United States. Its Amer‐
    ican railway system extends north/south from Chicago to the
    Gulf Coast, and east/west from Pennsylvania to Minnesota.
    No. 17‐3586                                                       3
    EJ  &  E  West  Company  (“EJ  &  EW”)  is  a  wholly  owned,
    noncarrier subsidiary of EJ & E. The EJ & E rail line, located
    in  northeastern  Illinois  and  northwestern  Indiana,  encom‐
    passes a 120‐mile arc of mainline track around Chicago.
    Beginning in the 1990s, the EJ & E line became a means for
    freight moving through Chicago to avoid railway congestion
    in the center of the city. Notably, Chicago is the only city in
    the United States where all seven Class I railroads (railroads
    with annual operating revenues of $250 million or more) op‐
    erate. According to the Board, “one third of all rail freight in
    the  United  States  moves  to,  from,  or  through  Chicago,”  in‐
    cluding more than 600 freight trains each day. “Converging
    in  the  Chicago  Terminal  District—a  2,800  mile  rail  network
    containing 70 train yards and terminals—these freight trains
    compete for track and yard space with each other and with
    over  750  commuter  trains  and  78  Amtrak  trains  per  day,
    which together serve over 84 million passengers a year.” Vill.
    of Barrington v. STB, 636 F.3d 650, 652 (D.C. Cir. 2011) [herein‐
    after  Barrington  I].  “The  resulting  congestion  slows  freight
    traffic to a crawl.” Id.
    In 2007, CN sought acquisition of control of EJ & EW in
    order to move a majority of its Chicago rail traffic to the EJ & E
    line. At the time, CN’s rail network “converge[d] on the city
    like the spokes of a wheel … meet[ing] in the heart of the Chi‐
    cago Terminal District.” Id. As a result, trains passing through
    the city were forced to “contend with the city’s congestion,”
    which often turned the thirty‐mile journey into a twenty‐four
    hour endeavor. Id. The EJ & E line, however, cut across CN’s
    existing rail lines, thus allowing trains the opportunity to by‐
    pass the city center.
    4                                                                  No. 17‐3586
    Under  federal  law,  the  Board  “has  authority  to  regulate
    the  construction,  operation,  and  abandonment  of  most  rail‐
    road lines in the United States,”  Caldwell v. United States, 391
    F.3d 1226, 1228 (Fed. Cir. 2004), including the“[a]cquisition of
    control  of  a  rail  carrier  by  any  number  of  rail  carriers.”  49
    U.S.C. § 11323(a)(3).1 The Board must approve and authorize
    any transaction “consistent with the public interest,” but may
    nonetheless  “impose  conditions  governing  the  transaction.”
    Id. § 11324(c). CN applied for Board approval on October 30,
    2007.
    Many roadways that intersect the EJ & E line are important
    to regional mobility. At the time of the proposed acquisition,
    “nearly 340,000 people live[d] in close proximity to the EJ & E
    line,”  and  “73%  of  road  crossings  lack[ed]  bridges  over  the
    tracks.” Barrington I, 636 F.3d at 653. Consequently, the Board
    conducted  an  environmental  review  in  accordance  with  the
    National  Environmental  Policy  Act  (“NEPA”),2  42  U.S.C.
    1 The Board is the successor agency to the Interstate Commerce Com‐
    mission and assumed control on January 1, 1996. See 49 U.S.C. § 1302.
    2 The NEPA requires federal agencies to “include in every recommen‐
    dation  or  report  on  …  major  Federal  actions  significantly  affecting  the
    quality of the human environment, a detailed statement” on:
    (i)  the  environmental  impact  of  the  proposed  action,
    (ii) any  adverse  environmental  effects  which  cannot  be
    avoided should the proposal be implemented, (iii) alter‐
    natives  to  the  proposed  action,  (iv)  the  relationship  be‐
    tween  local  short‐term  uses  of  man’s  environment  and
    the maintenance and enhancement of long‐term produc‐
    tivity, and (v) any irreversible and irretrievable commit‐
    ments of resources which would be involved in the pro‐
    posed action should it be implemented.
    42 U.S.C. § 4332(C).
    No. 17‐3586                                                            5
    §§ 4321–4370m‐12.  The  Board’s  Office  of  Environmental
    Analysis (“OEA”)3 prepared an Environmental Impact State‐
    ment  (“EIS”)  examining  112  crossings  along  the  EJ  &  E  rail
    line,  including  the  intersection  at  U.S.  14  in  Barrington.  It
    “studied  how  increased  freight  traffic  would  worsen  traffic
    congestion, increase the risk of collisions, slow emergency re‐
    sponders, and increase the likelihood of hazardous material
    spills  in  communities  along  the  rail  line.”  Barrington  I,  636
    F.3d  at  668.  In  the  course  of  preparing  the  EIS,  OEA  “pub‐
    lish[ed] notices in the Federal Register and ads in local news‐
    papers, [held] twenty‐two public meetings attended by over
    7200 people, consult[ed] with local, state, and federal agencies
    and officials, publish[ed] for comment a 3500 page draft envi‐
    ronmental impact statement, [and held] a sixty day comment
    period  on  that  draft,”  during  which  it  received  over  13,500
    comments. Id. at 653.
    Substantially affected crossings were eligible for the impo‐
    sition of mitigation measures as a condition to the Board’s ap‐
    proval.  Possible  mitigation  measures  included:  traffic  advi‐
    sory signs that notified drivers to stay clear of intersections;
    roadway  modifications  (such  as  widening);  and,  most  rele‐
    vant  here,  grade  separation  between  the  roadway  and  rail
    line. Critically, however, a substantially affected crossing did
    not automatically warrant mitigation. Rather,  in determining
    what  (if  any)  measures  would  be  appropriate,  OEA  consid‐
    ered  “the  individual  characteristics  of  each  highway/rail  at‐
    grade crossing site.” These factors included, inter alia, “the im‐
    portance  of  the  highway  at  the  crossing  to  regional  traffic
    3 Portions of the record refer to OEA under its predecessor name, the
    Section of Environmental Analysis (“SEA”). For consistency, we refer to
    the entity as OEA throughout this opinion.
    6                                                            No. 17‐3586
    flows, existing congestion, existing structures (such as mature
    trees and local roadways) near the highway/rail at‐grade in‐
    tersection, and the cost of a grade separation.”
    To determine whether a crossing would be substantially
    affected  by  the  acquisition,  OEA  studied  impacts  on  traffic
    congestion  by  examining  rail  and  vehicle  projections  for
    2015.4  Specifically,  OEA  examined  three  data  “thresholds.”5
    The first was the crossing level of service (“LOS”), a measure
    of how freely traffic moves at a crossing. The LOS at a partic‐
    ular crossing was characterized by a letter from A through F,
    with  “LOS  A”  indicating  relatively  free‐flowing  traffic  and
    “LOS  F”  indicating  extreme  congestion.  A  crossing  was  de‐
    clared substantially affected if it would be classified as LOS E
    or F as a result of the acquisition. Second, OEA examined ef‐
    fects  on  vehicle  queue  length,  or  how  far  traffic  backs  up
    when a train passes. Crossings were deemed substantially af‐
    fected  where  acquisition‐related  queues  were  projected  to
    block a major thoroughfare that would not otherwise be ob‐
    structed. Finally, OEA analyzed the total length of delay for
    all vehicles stopped at a crossing. Crossings expected to expe‐
    4 These projections accounted for proposed upgrades to the EJ & E line
    that were scheduled to be completed before 2015. The Board felt that this
    “horizon year … represented the limit of what [was] reasonably foreseea‐
    ble with regard to projected rail traffic on the EJ & E line.”
    5  These threshold measurements derived from the Federal Highway
    Administration’s Railroad‐Highway Grade Crossing Handbook. See U.S. Dep’t
    of Transp., Fed. Highway Admin., Railroad‐Highway Grade Crossing Hand‐
    book (2d ed. 2007), https://www.fra.dot.gov/Elib/Details/L02829 (last vis‐
    ited June 4, 2018).
    No. 17‐3586                                                                     7
    rience more than forty hours of acquisition‐related vehicle de‐
    lay  in  a  twenty‐four  hour  period  were  considered  substan‐
    tially affected.
    OEA’s draft EIS projected that if the acquisition were ap‐
    proved,  20.3  CN  trains  would  travel  across  the  Barrington
    segment of the EJ & E line each day by 2015, with an average
    length of 6,829 feet and speed of 40 miles per hour. OEA fur‐
    ther  concluded  that  U.S.  14  did  not  exceed  any  of  the  three
    thresholds for substantially affected crossings. In particular,
    it determined that, as a result of the acquisition, the intersec‐
    tion  would:  (1)  remain  at  LOS  A;  (2) not  experience  queues
    that blocked a major thoroughfare (although average queue
    lengths were expected to increase from 558 to 1,048 feet); and
    (3) encounter only 31.78 hours of daily acquisition‐related ve‐
    hicle  delay  (compared  to  2.49  hours  if  no  CN  trains  were
    added).
    In response to the draft EIS, the Village conducted its own
    independent “VISSIM”6 study using a different methodology
    than the EIS. The Village claimed that its VISSIM model cal‐
    culated 135–249 hours of daily acquisition‐related vehicle de‐
    lay at U.S. 14, an amount substantially higher than the draft
    EIS  forecast  and  above  the  forty‐hour  threshold  established
    for substantially affected crossings.
    6  “VISSIM” is a German acronym which translated means “traffic in
    towns—simulation.” According to the Village, the model examines “indi‐
    vidual driver behaviors and the resulting vehicle interactions to simulate
    actual traffic flows” and projects train and transit operations “under con‐
    straints such as roadway and railway configurations, speed limits, traffic
    composition,  vehicle  characteristics,  traffic  signals,  transit  stops,  train
    blockages, and driver behaviors.”
    8                                                     No. 17‐3586
    To  address  the  Village’s  study,  the  Board  performed  an
    additional VISSIM traffic analysis specifically focused on the
    Barrington area, referred to as the Village of Barrington Traf‐
    fic  Operational  Analysis  (the  “VOBTOA  Study”).  The
    VOBTOA Study concluded that during morning and evening
    peak periods, overall vehicle delay in the Barrington region
    would  increase  by  4%  and  5%,  respectively.  It  also  found,
    however, that “the major source of congestion” was not the
    proposed  acquisition,  but  rather  “excess  vehicle  demand  at
    existing major thoroughfare intersections,” which “backs up
    traffic into significant queues.” As a result, it determined that
    “construction of a grade separation … at … [U.S. 14] … [was]
    not  a  feasible  way  to  address  regional  congestion,”  and
    “would only be beneficial if capacity improvements [were] in‐
    corporated at the upstream and downstream signalized inter‐
    sections.”
    In the final EIS published on December 5, 2008, OEA pre‐
    sented  the  VOBTOA  Study  and  recommended  final  mitiga‐
    tion  conditions  for  the  proposed  acquisition.  The  final  EIS
    found that thirteen crossings would be substantially affected.
    Of  these,  OEA  recommended  mitigation  for  eight  crossings
    (including two grade separations); it determined that mitiga‐
    tion was not needed for the remaining five. Once again, how‐
    ever, it concluded that the U.S. 14 intersection did not meet
    the criteria for a substantially affected crossing, much less a
    grade separation.
    More importantly, the final EIS determined that even if a
    grade separation at U.S. 14 were constructed, it “would have
    minimal benefit to traffic flow” because “existing traffic sig‐
    nals in proximity to one another, as well as the [existence of a
    separate commuter rail line that intersects with the EJ & E line
    No. 17‐3586                                                              9
    in  Barrington],  would  result  in  substantial  queuing
    along … US 14.” OEA stated that as a result, “it [was] not the
    responsibility of [CN] to mitigate for [this] existing traffic con‐
    gestion in the community by grade separating US 14.”
    B. Procedural Background
    1. The Board’s 2008 Decision
    The Board approved the acquisition on December 24, 2008,
    subject  to  CN  implementing  the  environmental  mitigation
    conditions discussed in the final EIS.7 See Canadian Nat’l Ry.
    Co.—Control—EJ & E W. Co., STB Finance Docket No. 35087,
    2008 WL 8139694 (Dec. 24, 2008). Although the Board recog‐
    nized  that  “numerous  commenters  requested  grade  separa‐
    tions,” it ultimately agreed with OEA’s analysis “explaining
    why  a  grade  separation … would  not  be  practical  or  war‐
    ranted at those crossings.” Still, it imposed a “monitoring and
    oversight” period, during which CN was required to submit
    regular operational and environmental reports and the Board
    retained  the  authority  to  impose  additional  mitigation
    measures.8 CN completed its acquisition of the EJ & E line on
    January 21, 2009, at a cost of $303 million.
    Following  the  Board’s  decision,  approximately  a  dozen
    governmental  entities,  including  the  Village,  filed  petitions
    7 The Board ruled that CN would be responsible for 67% and 78.5% of
    the cost of the two approved grade separations, respectively. Overall, CN
    has spent over $120 million in voluntary and Board‐imposed mitigation
    measures.
    8 Although this oversight period was originally scheduled to last five
    years, subsequent decisions of the Board extended it through January 23,
    2017.
    10                                                                No. 17‐3586
    for review in the D.C. Circuit Court of Appeals. See Barrington
    I, 636 F.3d at 654. The Village argued that the Board “failed to
    take the requisite ‘hard look’ at traffic congestion and emer‐
    gency  responder  delays  in  Barrington”  and  “failed  to  ade‐
    quately examine strategies for mitigating those impacts.” Id.
    at 672. The D.C. Circuit denied the Village’s petition on March
    15, 2011. Id. at 672–73.
    2. The 2011 Petition to Reopen9
    On October 14,  2011, the Village petitioned the Board to
    reopen its 2008 decision and require CN to bear at least 84%
    of the cost of a grade separation at U.S. 14. In relevant part,
    the Village highlighted that the Illinois Department of Trans‐
    portation  (“IDOT”)  had  designated  U.S. 14  a  Strategic  Re‐
    gional Arterial (“SRA”).10 It also submitted an updated ver‐
    sion of its 2008 VISSIM study. The revised analysis projected
    9 Between the Board’s 2008 decision and the Village’s 2011 petition to
    reopen, the Board commissioned a third‐party audit of CN’s operational
    and environmental reports, based upon allegations that the company was
    underreporting the number of crossing blockages lasting for ten minutes
    or more. In 2010, the Board found that CN had knowingly underreported
    the  number  of  blocked  crossings  and  issued  a  $250,000  fine  against  the
    carrier. See Canadian Nat’l Ry. Co.—Control—EJ & E W. Co., (Decision No.
    27),  STB  Finance  Docket  No.  35087  (Dec.  21,  2010).  The  Board  also  ex‐
    tended the scheduled oversight period one year and directed CN to pro‐
    vide  additional  information  in  its  reports  regarding  crossing  blockages.
    See Canadian Nat’l Ry. Co.—Control—EJ & E W. Co., (Decision No. 26), STB
    Finance Docket No. 35087 (Dec. 21, 2010).
    10  The SRA system “is intended to carry larger volumes of traffic at
    higher speeds as a complement to the region’s expressway system. Efforts
    are made to preserve the level of service on these roadways through ap‐
    propriate  access  and  traffic  signal  locations  and  spacing.”  Strategic  Re‐
    gional Arterial Resources, Chicago Metropolitan Agency for Planning (July
    No. 17‐3586                                                             11
    2015  traffic  conditions  by  examining  actual  post‐acquisition
    CN operations in mid‐2011 rather than the pre‐acquisition es‐
    timates  created  in  2008.  This  time,  the  Village’s  study  pre‐
    dicted  98–100  hours  of  acquisition‐related  vehicle  delay  at
    U.S. 14. As in 2008, the Village argued that this projection sat‐
    isfied  one  of  the  criteria  used  by  the  Board  in  determining
    substantially affected crossings. However, the Village’s study
    also indicated that, even if CN trains were not added to the EJ
    & E line, vehicle delay in 2015 would increase by 260 hours
    compared to 2007 levels.
    In addition, the Village introduced evidence that in 2010,
    it received a $2.8 million federal grant under the Transporta‐
    tion Investment Generating Economic Recovery (“TIGER II”)
    program to undertake preliminary engineering studies for a
    grade  separation  at  U.S.  14.  It  argued  that  its  receipt  of  the
    TIGER II grant showed that the Board erred in not ordering a
    grade separation in 2008. Finally, it cited a growing “industry
    trend”  of  increased  train  lengths  and  slower  train  speeds,
    which it argued the Board did not consider when developing
    its 2008 mitigation framework.
    The  Board  denied  the  Village’s  petition  on  November  8,
    2012. See Canadian Nat’l Ry. Co.—Control—EJ & E W. Co., STB
    Finance Docket No. 35087, 2012 WL 5458828 (Nov. 8, 2012). It
    concluded that “SRA designation alone … did not warrant a
    grade separation at a given intersection, particularly in areas
    with  preexisting  roadway  capacity  constraints.”  It  further
    found that because the Village’s 2011 study projected less im‐
    pact on vehicle delay than its 2008 analysis, the Village had
    16, 2013), http://www.cmap.illinois.gov/data/transportation/traffic/sra‐re‐
    sources.
    12                                                      No. 17‐3586
    not  presented  new  evidence  or  changed  circumstances  that
    would have materially altered its 2008 decision. It also noted
    that  the  Village’s  study  confirmed  that  “even  if  CN’s  addi‐
    tional  trains  were  to  add  98–100  hours  of  increased  vehicle
    delay at U.S. 14 … existing capacity constraints on U.S. 14 will
    contribute  much  more  significantly  to  the  vehicle  delays  at
    that  crossing  than  will  additional  CN  trains  on  the  EJ  &  E
    line.”
    Additionally, the Board reiterated that “exceeding the 40‐
    hour  traffic  delay  threshold  did  not  automatically  war‐
    rant … a grade separation.” As evidence, it pointed to the five
    crossings  deemed  substantially  affected  in  2008  that  ulti‐
    mately  did  not  receive  any  mitigation  measures.  Citing  the
    VOBTOA  Study  and  final  EIS,  the  Board  emphasized  that
    while the acquisition would increase delay at U.S. 14 “to some
    degree,” it “would not substantially modify the basic nature
    of  the  traffic  congestion  that  motorists  were  already  experi‐
    encing and would continue to experience in Barrington due
    to preexisting roadway capacity constraints.”
    Regarding  the  TIGER  II  grant,  the  Board  stated  that  the
    Village did not cite “any statements relating to the awarding
    of the grant that refute[d] the Board’s decision in the [2008]
    Final  Decision  not  to  impose  a  grade  separation.”  Last,  it
    found  that  the  Village  failed  to  show  that  its  supposed  “in‐
    dustry trends” involving train length and speed “appl[ied] to
    or reflect[ed] CN’s operations on the EJ & E rail line.”
    Once again, the Village filed a petition for review, which
    the D.C. Circuit denied on July 18, 2014. Vill. of Barrington v.
    STB, 758 F.3d 326 (D.C. Cir. 2014) [hereinafter Barrington II].
    No. 17‐3586                                                              13
    3. The 2014 Petition to Reopen
    The Village filed another petition with the Board on No‐
    vember 26, 2014, this time asking that CN be forced to con‐
    tribute 79% of the cost of a grade separation (equal to $47 mil‐
    lion).  The  Village  referenced  unexpected  “energy‐related
    market developments on CN’s rail network.” Specifically, it
    claimed  that  the  acquisition,  combined  with  an  unexpected
    rise  in  global  energy  prices,  had  “facilitated … increased
    movement  of  energy  commodity  traffic  (namely,  crude  oil,
    ethanol, and frac sand shipments) and that these unforeseen
    traffic  volumes  were  not  factored  in  the  projections  relied
    upon by the Board in its 2008 Final Decision.” It asserted that
    “it necessarily follow[ed] that CN’s projections could not have
    allowed  the  Board  to  weigh  the  profound  long‐term  im‐
    pact … on Barrington.” It also maintained that this energy‐re‐
    lated traffic resulted in “unanticipated movement of flamma‐
    ble hazardous materials through Barrington [that] pose[d] a
    threat  to  public  safety  not  previously  considered  by  the
    Board.”
    Additionally,  the  Village  contended  that  the  average
    length  of  CN  trains  had  significantly  increased  (from  5,800
    feet  in  2011  to  8,568  feet  in  2014).  It  stated  that  this  created
    greater vehicles delays and threatened emergency medical re‐
    sponse. It also raised the prospect of “double‐tracking,” i.e.,
    the addition of a second parallel track along the EJ & E line. It
    claimed  that,  based  upon  the  increase  in  energy‐related
    freight traffic, as well as emails sent by CN personnel in 2013,
    “it  [was]  only  a  matter  of  time  before  CN  [would]  double
    track through Barrington” in order to maximize its transpor‐
    tation capabilities.
    14                                                             No. 17‐3586
    Finally, the Village reemphasized its receipt of the federal
    TIGER II grant, and added that it had since received an addi‐
    tional $700,000 local match from IDOT. As in 2011, it argued
    that this funding “reflect[ed] the federal government’s deter‐
    mination  that  a  grade  separation  at  the  U.S.  Highway  14
    crossing [was] essential.”
    The Board denied the Village’s petition on May 15, 2015.
    See  Canadian  Nat’l  Ry.  Co.—Control—EJ  &  E  W.  Co.,  STB  Fi‐
    nance Docket No. 35087, 2015 WL 2339001 (May 15, 2015). The
    Board found that, contrary to the Village’s assertions, traffic
    volumes on the EJ & E line were actually lower than levels pro‐
    jected  in  2008,  even  when  anticipated  future  growth  in  en‐
    ergy‐related traffic was considered.11  Thus, it concluded that
    its 2008 decision “did in fact consider the impacts of rail line
    operations in Barrington at the traffic levels that are moving
    through Barrington today and are expected in the near term.”
    It also highlighted that the final EIS recognized “that increases
    in freight rail traffic on the EJ & E line would also increase the
    risk of adverse hazardous materials incidents,” but nonethe‐
    less concluded that the acquisition “[did] not create any new
    threats” because “a variety of hazardous materials, including
    flammable liquids, already moved over the line pre‐transac‐
    tion.”
    Regarding  the  length  of  trains,  the  Board  stated  that  the
    Village’s  cited  figure  “[did]  not  offer  a  complete  account  of
    11 Recall that in 2008, the EIS projected that U.S. 14 would experience
    an average of 20.3 trains per day in 2015. According to CN’s operational
    reports, the actual number of trains in 2014 averaged only 17.5 per day.
    CN anticipated that future growth in energy‐related traffic would only in‐
    crease this number by an additional 2.5 trains per day, still below the 2008
    projection.
    No. 17‐3586                                                     15
    rail traffic” because it only analyzed trains that blocked cross‐
    ings for more than ten minutes. In reality, the average train
    length  was  only  6,916  feet,  which  was  “not  substantially
    greater” than the 6,829 feet projected by the Board in 2008.
    The Board further echoed that, regardless of the potential
    change  in  circumstances,  a  substantially  affected  crossing
    “did not automatically warrant mitigation.” Rather, “[a] host
    of other factors … went into determining whether any miti‐
    gation  was  appropriate  for  a  ‘substantially  affected’  cross‐
    ing,” including “preexisting congestion.” It restated that the
    final EIS determined that a grade separation at U.S. 14 “would
    provide minimal benefit to the traffic flow in the Barrington
    area,  primarily  due  to  preexisting  roadway  capacity  con‐
    straints near U.S. 14.” As a result, “[i]n keeping with its prac‐
    tice  of  mitigating  only  impacts  resulting  directly  from  the
    transaction and not requiring mitigation for preexisting con‐
    ditions …  the  Board  concluded  that  the  U.S.  14  intersec‐
    tion … did not meet the Board’s criteria for a grade‐separated
    crossing.” It found that the Village failed to present new evi‐
    dence that would alter this determination.
    The  Village  filed  a  petition  for  reconsideration  of  the
    Board’s  decision,  which  the  Board  denied  on  November  4,
    2015. See Canadian Nat’l Ry. Co.—Control—EJ & E W. Co., STB
    Finance Docket No. 35087, 2015 WL 6749916 (Nov. 4, 2015).
    The Board found that a majority of the Village’s reconsidera‐
    tion claims were  “simply  restatements of prior arguments.”
    As  a  result,  the  Village’s  “repeated  arguments  regarding
    grade‐separation mitigation at U.S. 14 [did] not provide suffi‐
    cient basis for reconsideration.” The Village did not seek judi‐
    cial review.
    16                                                     No. 17‐3586
    4. The 2017 Petition to Reopen
    On January 10, 2017, the Village, this time joined by IDOT,
    once again petitioned the Board to require CN to pay 58% of
    the cost of a grade separation (equal to $37.5 million). The Vil‐
    lage asserted that its renewed request was based upon “un‐
    anticipated  new  evidence  of  substantially  changed  circum‐
    stances regarding CN’s operations and the impacts through‐
    out the region.” It reiterated U.S. 14’s designation as an SRA,
    as well as its receipt of federal and state grant funding. Addi‐
    tionally, it predicted that an anticipated increase in annual ca‐
    pacity of the Fairview Terminal at the Port of Prince Rupert
    (“PPR”) in British Columbia, Canada would increase future
    CN freight traffic moving through Chicago. It also repeated
    that CN was actively planning to double‐track the Barrington
    portion of the EJ & E line. Finally, it stated that during three
    months  in  2016,  the  average  length  of  trains  had  grown  to
    7,800 feet, their average speed had fallen to 28 miles per hour,
    and the number of hazmat cars had risen to over 400 per day.
    It asserted that these increased figures led to more blockages
    of U.S. 14.
    The Board denied the petition on April 26, 2017, finding
    that the Village “[did] not present new evidence or substan‐
    tially changed circumstances that warrant[ed] reopening [the]
    proceeding.” See Canadian Nat’l Ry. Co.—Control—EJ & E W.
    Co., STB Finance Docket No. 35087, 2017 WL 1509296 (Apr. 26,
    2017). After outlining the case’s extensive procedural history,
    the Board noted that “the traffic volumes on the EJ & E line
    have been and continue to be lower than the projected levels
    relied upon by the Board in its 2008 Final Decision.” Accord‐
    ing  to  CN’s  operational  reports,  U.S.  14  averaged  only  19.6
    No. 17‐3586                                                          17
    trains  per  day  in  2015  and  18.1  trains  per  day  in  2016,  both
    below the 20.3 trains per day originally projected in 2008.
    The Board further found that the Village failed to provide
    “persuasive evidence to support their claim that a significant
    increase  in  rail  traffic  …  [was]  imminent.”  Citing  verified
    statements submitted by senior CN executives, it stated that
    the purported PPR expansion, if completed, would result in
    only 0.5 additional trains per day traveling through Barring‐
    ton. It also accepted CN’s assurance that it had “no need and
    no current plans to double‐track the line” over U.S. 14. Addi‐
    tionally, it noted that, even if CN’s traffic volumes did increase
    in the future, it was unlikely “that any such increases would
    be attributable to [the acquisition], which was approved over
    eight years ago.” Rather, “a variety of other factors unrelated
    to the transaction, such as changes in the industry, economic
    growth, and energy prices, [were] now just as likely to play a
    role in future fluctuations in rail traffic.”
    Although  the  Board  acknowledged  that  CN  trains  were
    marginally longer and slower than originally projected, it ex‐
    plained that this could actually reduce overall crossing activa‐
    tion times, because “the amount of time a crossing is activated
    before and after the arrival of each train is fixed, regardless of
    train length.” It further noted that CN’s train speeds were re‐
    duced as an added safety precaution and that the U.S. 14 in‐
    tersection averaged less than one reportable blocked crossing
    each month in 2016. It also adopted CN’s claim that because a
    commuter line with priority over CN’s traffic also crosses the
    EJ &  E  line  in  Barrington, “the windows available to  CN to
    move its traffic through Barrington generally are short.” As a
    result, “CN paces its trains to get past the Barrington cross‐
    ings  and,  if  necessary,  hold  them  outside  the  Barrington
    18                                                      No. 17‐3586
    area.”  According  to  the  Board,  these  “operational  reasons”
    made it unlikely that blockages would increase in the future.
    Finally, the Board observed that, contrary to the Village’s
    estimates,  the  average  number  of  hazmat  cars  in  2016  (254,
    127 of which were actually loaded) was only slightly higher
    than  the  209.4  projected  by  the  Board  in  2008.  Moreover,  it
    cited  multiple  federal  agencies  (including  the  Federal  Rail‐
    road  Administration,  the  Transportation  Security  Admin‐
    istration,  and  the  Pipeline  and  Hazardous  Materials  Safety
    Administration)  with  established  regulations  for  the
    transport of hazardous material by rail “which, along with the
    mitigation  measures  imposed  in  the  2008  Final  Decision,
    should appropriately minimize the safety risks.”
    In sum, the Board concluded that, on the whole, the Vil‐
    lage’s new complaints “would [not] warrant a different result
    under the criteria relied upon by the Board in 2008.”
    On May 16, 2017, the Village filed a petition for reconsid‐
    eration. This time, the Village argued that the Board’s deter‐
    mination—originally reached in 2008—that the traffic issues
    at the U.S. 14 intersection were primarily the result of preex‐
    isting  conditions  constituted  material  error.  As  evidence,  it
    cited: (1) the Board’s own EIS projections that U.S. 14 would
    experience only 2.49 hours of delay without CN’s acquisition,
    compared  to  31.78  hours  of  delay  once  the  transaction  was
    taken into account; (2) the VOBTOA Study’s conclusion that
    total  vehicle  delay  time  in  the  Barrington  region  would  in‐
    crease by 4% and 5% during morning and evening peak peri‐
    ods  following  the  acquisition;  and  (3)  the  Village’s  VISSIM
    studies from 2008 and 2011.
    No. 17‐3586                                                         19
    The Village also proffered new evidence (based upon ex‐
    trapolations of its 2011 study using data from 2015 and 2016)
    that annual delay at the U.S. 14 intersection had reached 118
    hours  in  the  spring  of  2016.  It  believed  this  information
    “demonstrate[d] that U.S. 14 experiences vehicular traffic de‐
    lay that exceeds the 40‐hour threshold criterion for a ‘substan‐
    tially affected’ crossing” and therefore required a grade sepa‐
    ration.
    The  Board  denied  the  Village’s  petition  for  reconsidera‐
    tion on October 30, 2017. See Canadian Nat’l Ry. Co.—Control—
    EJ  &  E  W.  Co.,  STB  Finance  Docket  No.  35087,  2017  WL
    5639664 (Oct. 30, 2017). Regarding the Village’s claims of ma‐
    terial error, the Board stated that the EIS’s thirty‐hour delay
    prediction  was  “consistent  with  the  Board’s  determination
    that U.S. 14 was not a ‘substantially affected’ crossing.” Addi‐
    tionally,  it  highlighted  the  VOBTOA  Study’s  finding  that
    “[a]lthough … peak period queue lengths [at U.S. 14] would
    increase, … such  increases  were  primarily  caused  by  high
    traffic volumes and a preexisting lack of capacity at the inter‐
    section  of  …  U.S.  14,  rather  than  by  the  [acquisition].”  This
    conclusion was buttressed by the Village’s own traffic studies,
    which  “showed  that  preexisting  capacity  constraints  in  the
    Barrington street network would contribute much more sig‐
    nificantly to the vehicle delays at [the U.S. 14 crossing] than
    would additional CN trains on the EJ & E line.”
    The Board similarly rejected the Village’s proffered “new
    evidence”  of  increased  vehicle  delay.  It  first  noted  that  the
    2015 and 2016 data sets used by the Village to conduct its ex‐
    trapolation were available before it filed its original January
    2017  petition.  Moreover,  the  underlying  calculations  were
    performed in February 2017, prior to the announcement of the
    20                                                                No. 17‐3586
    Board’s  April  26,  2017  decision.  The  Board  found  that
    “[b]ecause the data was readily available to Barrington when
    the record was developed,” the calculations did not constitute
    “new evidence.”
    Regardless, the Board stated that even if the Village’s pro‐
    jections  were  considered,  they  “would  not  change  the  out‐
    come of the Board’s previous decisions.” It highlighted that
    the Village’s revised delay projection was still lower than the
    estimates  provided  in  their  original  2008  traffic  study,  “the
    conclusions of which were already before the Board when it
    issued  its  2008  Final  Decision.”  Furthermore,  it  reaffirmed
    that “exceeding a certain level of vehicle delay at a crossing
    did not automatically warrant mitigation under the Board’s
    criteria,” but rather was “only one factor in determining if a
    crossing was eligible for mitigation.” It stood by its longstand‐
    ing  view  that  “a  grade  separation  at  U.S.  14  [was]  not  war‐
    ranted because Barrington’s vehicle delays were primarily at‐
    tributable to preexisting traffic conditions and capacity con‐
    straints.” Accordingly, “Barrington’s evidence, even if it were
    timely, would not have altered the outcome the Board previ‐
    ously reached.” This appeal followed.12
    II.       Discussion
    A. The Specific Order at Issue
    As  a  preliminary  matter,  we  must  establish  the  precise
    Board  decision  subject  to  judicial  scrutiny.  Under  Federal
    12 The Village’s January 10, 2017 petition also sought extension of the
    Board’s oversight period until January 9, 2019. This request was denied by
    the Board in its April 26, 2017 decision. The Village did not request recon‐
    sideration of this aspect of the Board’s decision, and it is not at issue in this
    appeal.
    No. 17‐3586                                                        21
    Rule  of  Appellate  Procedure  15,  a  petition  for  review  must
    “specify  the  order  or  part  thereof  to  be  reviewed.” Fed.  R.
    App. P. 15(a)(2)(C). Similarly, 28 U.S.C. § 2344 requires a pe‐
    titioner to “attach to the petition, as exhibits, copies of the or‐
    der, report, or decision of the agency.” “Failure to specify the
    correct  order  can  result  in  dismissal  of  the  petition.”  En‐
    travision  Holdings,  LLC  v.  FCC,  202  F.3d  311,  312  (D.C.  Cir.
    2000); see also City of Benton v. Nuclear Reg Comm’n, 136 F.3d
    824, 826 (D.C. Cir. 1998); John D. Copanos & Sons, Inc. v. FDA,
    854 F.2d 510, 527 (D.C. Cir. 1988). On the other hand:
    A mistaken or inexact specification of the order to be
    reviewed will not be fatal to the petition … if the peti‐
    tioner’s intent to seek review of a specific order can be
    fairly  inferred  from  the  petition  for  review  or  from
    other contemporaneous filings, and the respondent is
    not misled by the mistake.
    Entravision, 202 F.3d at 313; compare Martin v. FERC, 199 F.3d
    1370, 1371–73 (D.C. Cir. 2000) (finding that petitioner’s intent
    to seek review of different agency decision than order speci‐
    fied in petition for review could be fairly inferred from con‐
    temporaneous  filings  and  that  respondent  was  not  preju‐
    diced),  and  Damsky  v.  FCC,  199  F.3d  527,  532–34  (D.C.  Cir.
    2000) (same), with Sw. Bell Tel. Co. v. FCC, 180 F.3d 307, 313
    (D.C. Cir. 1999) (finding that petitioner’s intent to seek review
    was not fairly inferable from petition of review or subsequent
    filings), and Brookens v. White, 795 F.2d 178, 180 (D.C. Cir. 1986)
    (similar).
    Respondents  argue  that  we  should  dismiss  the  Village’s
    arguments  to  the  extent  they  concern  the  Board’s  April  26,
    2017 order (or other prior decisions). Their point is well taken.
    The D.C. Circuit’s decision in Entravision is instructive. There,
    22                                                       No. 17‐3586
    the petitioner submitted comments to the Federal Communi‐
    cations Commission (“FCC”) suggesting that certain protec‐
    tions be granted to stations that would be displaced by a pro‐
    posed relocation of broadcast television channels. Entravision,
    202 F.3d at 312. In a “Report and Order,” the FCC adopted the
    reallocation proposal but declined to adopt the recommended
    protections. Id. The petitioner then filed a petition for partial
    reconsideration  that  was  subsequently  denied  in  a  “Memo‐
    randum  Opinion  &  Order.”  Id.  On  appeal,  the  D.C.  Circuit
    held that only the Memorandum Opinion & Order was at is‐
    sue because that was the order specified in, and attached to,
    the  petition  for  review.  Id.  at  314.  Although  the  Report  and
    Order  was  briefly  mentioned,  it  was  “only  in  the  course  of
    stating  the  history  of  the  proceeding  prior  to  the  order  of
    which  review  [was]  being  sought.”  Id.  Moreover,  the  peti‐
    tioner’s docketing statement and preliminary statement of is‐
    sues  only  specified  the  Memorandum  Opinion  &  Order.  Id.
    As a result, the court concluded that the petitioner “ha[d] not
    brought the Report & Order before [the] court for review.” Id.
    (emphasis removed).
    The same reasoning applies here. Although the Village’s
    appellate  brief  levels numerous attacks  at  the  Board’s  April
    26, 2017 decision denying the Village’s January 10, 2017 peti‐
    tion to reopen, its Petition for Review only requests examina‐
    tion  of  the  Board’s  October  30,  2017  order  denying  the  Vil‐
    lage’s May 16, 2017 petition for reconsideration. Specifically,
    the  Village  requests  that  we  “review  …  the  decision,  dated
    October 30, 2017,” and “set aside the October 2017 Decision
    and remand this case to the Board.” Furthermore, the Village
    attached only the October 30, 2017 decision to its petition, and
    the  jurisdictional  statement  of  the  Village’s  opening  brief
    No. 17‐3586                                                     23
    states that “[t]his case involves judicial review of the final or‐
    der of the [Board], dated October 30, 2017.”
    Nevertheless, in the interest of completeness, we address
    the Village’s claims pertaining to both its January 10, 2017 pe‐
    tition and May 16, 2017 petition for reconsideration. As out‐
    lined infra, this expanded review does not alter our ultimate
    conclusion, as none of the Village’s claims in either petition
    warrant judicial relief.
    Both petitions requested that the Board reopen its original
    2008 decision and impose additional mitigation measures. By
    statute, the Board may “reopen a proceeding” and “change an
    action  of  the  Board”  based  upon:  (1) “material  error”;
    (2) “new  evidence”;  or  (3)  “substantially  changed  circum‐
    stances.” 49 U.S.C. § 1322(c); see also 49 C.F.R. § 1115.4. Nota‐
    bly,  regardless  of  the  avenue  pursued,  the  alleged  grounds
    must be sufficient to lead the Board to materially alter its prior
    decision. If a party has presented no material error, new evi‐
    dence, or changed circumstances “that would mandate a dif‐
    ferent result,” then the Board need not reopen its proceedings.
    See Montezuma  Grain Co., LLP v. STB, 339  F.3d 535, 542  (7th
    Cir. 2003). The Village argues that all three categories are ap‐
    plicable here.
    B. Material Error
    First, the Village’s claims of material error fall outside our
    jurisdiction. Barrington II, 758 F.3d at 328. In ICC v. Brotherhood
    of Locomotive Engineers, the Supreme Court held that “where a
    party petitions an agency for reconsideration on the ground
    of ‘material error,’ i.e., on the same record that was before the
    agency when it rendered its original decision, ‘an order which
    24                                                           No. 17‐3586
    merely denies rehearing of ... [the prior] order is not itself re‐
    viewable.’” 482 U.S. 270, 280 (1987) [hereinafter BLE] (altera‐
    tion in original) (quoting Microwave Commc’ns, Inc. v. FCC, 515
    F.2d 385, 387 n.7 (D.C. Cir. 1974)). This is true even where, as
    here, “the agency ‘order refusing reconsideration discusse[s]
    the merits of the [petitioner’s] claims at length,’ as long as the
    agency’s  ‘formal  disposition  is  to  deny  reconsideration,
    and … it makes no alteration in the underlying order.’” Bar‐
    rington  II,  758  F.3d  at  328  (alterations  added)  (quoting  BLE,
    482  U.S.  at  280);  see  also  U.S.  Postal  Serv.  v. Postal  Regulatory
    Comm’n, 841 F.3d 509, 513 (D.C. Cir. 2016) (“Simply discuss‐
    ing the merits of an earlier agency decision does not open a
    reconsideration denial to review.”).
    Both the Board’s April 26 and October 30, 2017 orders de‐
    nied reopening its 2008 decision. “Accordingly, there is noth‐
    ing more we can say about Barrington’s claims of material er‐
    ror.” See Barrington II, 758 F.3d at 328; see also Schneider Nat’l,
    Inc. v. ICC, 948 F.2d 338, 344 (7th Cir. 1991); Advance Transp.
    Co. v. United States, 884 F.2d 303, 305 (7th Cir. 1989); Town of
    Springfield v. STB, 412 F.3d 187, 189 (D.C. Cir. 2005) (“[W]hen
    a reopening petition rested on ‘material error,’ the court has
    no  jurisdiction  to  review  a  denial  of  the  petition.”);
    Schoenbohm v. FCC, 204 F.3d 243, 245 (D.C. Cir. 2000) (“Denial
    of a petition for reconsideration … is generally nonreviewable
    unless the request for reconsideration was based on new evi‐
    dence or changed circumstances.”). We therefore dismiss the
    material  error  arguments  interspersed  throughout  the  Vil‐
    lage’s pleadings.
    No. 17‐3586                                                             25
    C. New  Evidence  and  Substantially  Changed  Circum‐
    stances
    Judicial review is available “[i]f the petition that was de‐
    nied  sought  reopening  on  the  basis  of  new  evidence  or
    changed  circumstances.”  BLE,  482  U.S.  at  284.  Even  in  this
    context, however, “[o]ur review of a decision by the Board is
    narrow.” Decatur Cty. Comm’rs v. STB, 308 F.3d 710, 714 (7th
    Cir. 2002). The Board is not required to reopen proceedings
    simply because a petition presents new evidence or changed
    circumstances. See Jost v. STB, 194 F.3d 79, 85 (D.C. Cir. 1999).
    Thus, “overturning the refusal to reopen requires ‘a showing
    of the clearest abuse of discretion.’” BLE, 482 U.S. at 278 (quot‐
    ing United States v. Pierce Auto Freight Lines, 327 U.S. 515, 535
    (1946)).
    “The Administrative Procedure Act governs our review of
    the [Board’s] decision, and in pertinent part it instructs us to
    consider whether that decision was arbitrary or capricious, an
    abuse of discretion, or otherwise not in accordance with law.”
    Wis. Cent. Ltd. v. STB, 112 F.3d 881, 886 (7th Cir. 1997) (citing
    5 U.S.C. § 706(2)(A)). “This is a deferential standard of review
    that  precludes  us  from  substituting  our  own  judgment  for
    that  of  the  [Board].”  Id.;  see  also  Motor  Vehicle  Mfrs.  Ass’n  v.
    State Farm Mut. Ins., 463 U.S. 29, 43 (1983) (“[A] court is not to
    substitute its judgment for that of the agency.”). “A decision
    is not arbitrary or capricious when it is possible to offer a rea‐
    soned, evidence‐based explanation for a particular outcome.”
    R.R. Ventures, Inc. v. STB, 299 F.3d 523, 548 (6th Cir. 2002). “If
    an  agency  considers  the  proper  factors  and  makes  a  factual
    determination” that a particular result is compelled, “that de‐
    cision implicates substantial agency expertise and is entitled
    26                                                         No. 17‐3586
    to deference.” Highway J Citizens Grp. v. Mineta, 349 F.3d 938,
    953 (7th Cir. 2003).
    Such deference is particularly owed in cases involving the
    imposition of protective conditions on railroad acquisitions,
    where  “the  Board  ‘has  extraordinarily  broad  discretion.’”
    Commuter Rail Div. of Reg’l Transp. Auth. v. STB, 608 F.3d 24,
    31  (D.C.  Cir.  2010)  (quoting  Grainbelt  Corp.  v.  STB,  109  F.3d
    794, 798 (D.C. Cir. 1997)). We afford “great deference to the
    [Board’s] selection of such conditions,” and we “will deny a
    petition  for  review  so  long  as  the  [Board’s]  decision  is  sup‐
    ported by substantial evidence in the record and was reached
    by  reasoned  decision‐making.”  Id.  (alterations  in  original)
    (quotation marks omitted) (quoting Grainbelt, 109 F.3d at 798–
    99).  “So  long  as  ‘the  agency’s  path  may  reasonably  be  dis‐
    cerned’ and there is ‘warrant in the law and the facts’ for what
    the [Board] has done, we are obligated to sustain the [Board’s]
    decision.”  Wis.  Cent.,  112  F.3d  at  886  (first  quoting  Bowman
    Transp.,  Inc.  v.  Ark.‐Best  Freight  Sys.,  Inc., 419  U.S.  281,  286
    (1974), then quoting Pierce Auto, 327 U.S. at 536).
    At the same time, “narrow and deferential review does not
    equate with no review at all. The inquiry still must be thor‐
    ough  and  probing.” Id.  (quoting  Bagdonas  v.  Dep’t  of  Treas‐
    ury, 93 F.3d 422, 426 (7th Cir. 1996)). “Within the range of rea‐
    son, it is for the [Board], of course, to decide what inferences
    to  draw  from  the  evidence  before  it  and  to  determine  what
    weight the evidence should be given.” Id. “But the [Board’s]
    factual  findings  must  have  the  support  of  substantial evi‐
    dence in the record, and there must be a rational relationship
    between the facts as the [Board] finds them and its ultimate
    conclusion.” Id. at 886–87. Meanwhile, “[q]uestions of law are
    subject to plenary review, and if the [Board] departs from one
    No. 17‐3586                                                            27
    of its own precedents, it is obligated to articulate a reasoned
    justification for doing so.” Id. at 887 (citations omitted). “Fi‐
    nally, although the [Board’s] understanding of the scope of its
    regulatory jurisdiction is entitled to deference, … we remain
    the final arbiter of the [Board’s] jurisdiction and authority ….”
    Id. (citations omitted).
    One final point warrants discussion. “[I]n an administra‐
    tively  final  case  it  is  only  fair  that  new  evidence  be  in  fact
    new.” Friends of Sierra R.R. v. ICC, 881 F.2d 663, 667 (9th Cir.
    1989) (quoting Platnick Bros., Inc. v. Norfolk & W. Ry. Co., 367
    I.C.C.  782,  785  (1983)  (internal  quotations  omitted)).  Section
    1322(c) does not define “new evidence,” but courts have de‐
    finitively  said  what  it  is  not.  First,  new  evidence  is  not  the
    same as “newly raised evidence.” Id. That is, new evidence is
    “facts which through no fault of [the petitioner’s], the original
    proceeding did not contain.” Jost, 194 F.3d at 84 (alteration in
    original) (quoting Sw. Bell, 180 F.3d at 312); see also Toledo, Pe‐
    oria & W. Ry v. STB, 462 F.3d 734, 753 (7th Cir. 2006) (“[T]he
    term new evidence refers to evidence that was not reasonably
    available  to  the  party  when  the  record  was  developed,  and
    not simply newly raised.” (internal quotation marks omitted)
    (quoting Tex. Mun. Power Agency v. Burlington N. & Sante Fe
    R.R. Co., STB Docket No. 42056, 2004 WL 2619767, at *2 (Sept.
    27, 2004))). “Thus, evidence that was reasonably available to
    the parties before the proceeding is not new evidence for pur‐
    poses of the statute.” Friends of Sierra, 881 F.2d at 667 (quoting
    Platnick Bros., 367 I.C.C. at 785); see also Toledo, 462 F.3d at 753
    (“[T]he Board generally does not consider new issues raised
    for the first time on reconsideration where those issues could
    have and should have been presented in the earlier stages of
    the  proceeding.”  (alteration  in  original)  (quoting  Tex.  Mun.
    Power Agency, 2004 WL 2619767, at *2)). Second, new evidence
    28                                                       No. 17‐3586
    does more than simply provide “new insight on the signifi‐
    cance of the existing record evidence.” Berry v. U.S. Dep’t of
    Labor, 832 F.3d 627, 638 (6th Cir. 2016).
    Here, a close review of the record reveals that most of the
    arguments in the Village’s 2017 petitions merely rehash those
    previously  raised—and  rejected—during  the  ten‐year
    lifespan  of  this  proceeding.  Meanwhile,  the  few  claims  that
    arguably fall outside this category do not compel an alternate
    result. We address each in turn.
    1. Designation of U.S. 14 as an SRA
    The Village contends that the Board’s 2017 decisions im‐
    properly ignored U.S. 14’s status as an SRA. This is not new
    evidence.  IDOT  labeled  U.S.  14  as  an  SRA  as  early  as  1993.
    Indeed, the Village specifically referenced the designation in
    its 2011 petition, more than five years before the filing of its
    2017 petition to reopen. At that time, the Board concluded that
    “SRA designation alone … did not warrant a grade separation
    at a given intersection, particularly in areas with preexisting
    roadway constraints.” Therefore, the Board did not abuse its
    discretion in declining to reopen its 2008 decision on that ba‐
    sis.
    2. Receipt of Federal and State Funding
    The  Village  argues  that  the  importance  of  U.S.  14  to  re‐
    gional traffic mobility is underscored by Barrington’s receipt
    of  its  federal  TIGER  II  grant  and  local  match  from  IDOT.
    However,  the  TIGER  II  grant  was  awarded  on  October  15,
    2010,  and  the  Village  referenced  its  receipt  of  government
    funding in both its 2011 and 2014 petitions. At that time, the
    Board determined that the grants did not “refute the Board’s
    No. 17‐3586                                                       29
    decision” to not impose a grade separation. They accordingly
    do not constitute new evidence.
    3. Crude‐By‐Rail  and  Hazardous  Material  Traffic  In‐
    creases
    The Village claims that during the oversight period, “un‐
    foreseen ‘crude‐by‐rail’ traffic has substantially increased the
    amount of highly flammable hazmat that CN had originally
    projected would move through Barrington.” The Village be‐
    lieves this increase “threaten[s] emergency responders’ ability
    to  respond  to  a  potentially  catastrophic  disaster  if  a  train
    transporting multiple cars of highly flammable crude oil were
    to derail and catch fire.” However, the Village presented the
    exact  same concern in 2014, when  energy‐related rail  traffic
    was even higher than in 2017. At that time, the Board found
    that the acquisition “[did] not create any new threats” because
    hazardous materials moved over the EJ & E line even before
    CN’s acquisition. As a result, it does not qualify as new evi‐
    dence. Regardless, the Village’s fears are overstated. In 2008,
    the  Board  projected  that  by  2015,  209.4  hazmat  cars  would
    move across the EJ & E line each day. According to CN, the
    actual number in 2016 was only slightly higher (254, only 127
    of which were actually loaded). Therefore, the Board did not
    abuse its discretion in declining to reopen its 2008 decision on
    that basis.
    4. Increased Vehicle Delay
    In  its  petition  to  reconsider,  the  Village  argued—for  the
    first  time—that  annual  delay  at  the  U.S.  14  intersection
    reached 118 hours in the spring of 2016. This is not new evi‐
    dence. As the Board highlighted in its October 30, 2017 deci‐
    30                                                            No. 17‐3586
    sion, the Village’s traffic delay figure is based upon extrapo‐
    lations of its 2008 and 2011 VISSIM traffic studies using data
    sets from 2015 and 2016, both of which were available at the
    time the Village filed its January 10, 2017 petition to reopen.
    Moreover,  the  traffic  delay  calculations  were  performed  on
    February 8 and February 17, 2017, before the Village filed a re‐
    ply  to  its  original  petition  to  reopen  on  February  23,  2017.
    However,  the  Village  did  not  present  this  evidence  to  the
    Board  until  it  filed  its  petition  for  reconsideration  in  May.
    Thus,  the  evidence  is  not  “newly  available”  because  it  was
    available to the Village at the time the record was created; in‐
    stead,  the  Village’s  118‐hour  delay  figure  is  “simply  newly
    raised.” See Toledo, 462 F.3d at 753.
    Even if the Village’s traffic delay calculation was new evi‐
    dence, the Board did not abuse its discretion in declining to
    reopen its 2008 decision. The Village submitted similar esti‐
    mates in both its comments to the 2008 draft EIS and its 2011
    petition. On those occasions, the Village’s VISSIM model pro‐
    jected  135–249  and  98–100  hours  of  daily  vehicle  delay,  re‐
    spectively. Both times, the Board concluded that the amounts
    did not warrant a grade separation at U.S. 14. The Village’s
    new  118‐hour  figure  falls  directly  within  the  scope  of  those
    prior computations, and is actually less than the Village ini‐
    tially projected in 2008.13
    13 The Village claims its 118‐hour figure shows a 4,639% increase over
    the delay projection provided in the final EIS. As the Board pointed out,
    however, the Village’s VISSIM study and the final EIS utilized different
    methodologies, making any attempted comparison “of extremely limited
    value.”
    No. 17‐3586                                                                  31
    Regardless, the Board’s October 30, 2017 decision reason‐
    ably echoed its prior admonishments that “exceeding a cer‐
    tain level of vehicle delay at a crossing did not automatically
    warrant mitigation under the Board’s criteria.” Rather, “total
    vehicle delay was only one factor in determining if a crossing
    was eligible for mitigation.” The Village’s revised traffic delay
    figure did nothing to rebut the Board’s conclusion that “Bar‐
    rington’s vehicle delays were primarily attributable to preex‐
    isting traffic conditions and capacity constraints.” Nor did it
    invalidate  the  Village’s  own  2011  traffic  analysis  that  pro‐
    jected 260 hours of vehicle delay even without CN’s acquisi‐
    tion of the EJ & E line.14 Thus, as the Board concluded, “even
    if CN’s additional trains have added 118 hours of increased
    vehicle delay at U.S. 14, Barrington’s own model shows that
    existing  capacity  constraints  at  U.S.  14  would  contribute
    much  more  significantly  to  the  vehicle  delays  at  that  cross‐
    ing.”15 Accordingly, the Village’s argument fails.
    5. Port of Prince Rupert Expansion
    The Village believes intermodal traffic arriving into PPR
    has increased exponentially since 2008, and that the port will
    continue to expand in the near future. This evidence can be
    fairly characterized as “new.” True, the Village mentioned the
    anticipated PPR expansion in both its response to the draft EIS
    14 In its appellate brief, the Village argues that the Board’s conclusion
    that traffic issues at U.S. 14 are primarily attributable to preexisting traffic
    conditions “is not supported by any evidence of record.” This claim is be‐
    lied by the Village’s own 2011 traffic analysis. It is further undermined by
    the final EIS and the Board’s 2008 VOBTOA Study.
    15 For the same reasons, the Village’s claim that a grade separation is
    needed “solely because of changed circumstances caused by CN’s traffic”
    is unavailing.
    32                                                       No. 17‐3586
    and its 2014 petition to reopen. Since that time, however, the
    amount  of  annual PPR  container traffic  handled by  CN  has
    steadily  increased,  from  approximately  two  million  metric
    tons in 2008 to nearly eight million metric tons in 2015. Evi‐
    dence of the surge from the last three years was not reasona‐
    bly available at the time of the Village’s prior submissions.
    Nevertheless, the Board did not abuse its discretion by re‐
    fusing to reopen the proceedings on this ground. The Board’s
    April  26,  2017  decision  found  that  although  CN’s  total  PPR
    traffic  has  consistently  increased,  the  Village  did  not  show
    that  rail  volume specifically  moving  through Barrington has
    been  materially  impacted.  Substantial  evidence  supported
    this finding. A senior CN executive provided a verified state‐
    ment  that  only  a  portion  of  PPR  traffic  moves  through  Bar‐
    rington, and that future port expansions would result in only
    0.5  additional  trains  per  day  traveling  across  U.S.  14.  This,
    along with the fact that the overall number of trains still falls
    below  2015  projections,  is  sufficient  to  sustain  the  Board’s
    conclusion that the Village’s PPR evidence would not materi‐
    ally alter its 2008 decision.
    6. Double‐Tracking
    The same goes for the Village’s purported fear of double‐
    tracking. Like the PPR expansion, the Village raised the issue
    of double‐tracking in  2014.  However, the  Village  supported
    the claim in its 2017 petitions with a new Request for Proposal
    (“RFP”)  issued  by  CN  in  2016  for  double‐tracking  on  the
    EJ & E line. This sufficiently constitutes new evidence.
    However, the Board did not abuse its discretion by deter‐
    mining that CN “has no need and no current plans to double‐
    No. 17‐3586                                                         33
    track  the  line  in  or  near  Barrington.”  This  finding  was  sup‐
    ported by a CN executive’s verified statement that “[t]he cited
    RFP was issued as part of CN’s regular assessment of capacity
    and fluidity on its network” in order to “identify those pro‐
    jects that would have the greatest impact on fluidity and ca‐
    pacity.”  From  this  assessment,  CN  concluded  that  “the  ex‐
    pected return on investment would be insufficient to justify
    such a project.” As a result, “CN has not designed or allocated
    money for a second track in or near Barrington” and would
    be  unlikely  to  do  so  in  the  near  future.  The  Village  may  be
    skeptical of CN’s assurances, but “it is for the [Board] … to
    determine  what  weight  the  evidence  should  be  given.”  See
    Wis. Cent., 112 F.3d at 886.
    7. Longer, Slower Trains
    That leaves the Village’s emphasis on longer, slower trains.
    Although the Village raised the same objection in earlier peti‐
    tions,  its  alleged  figures  from  2016  (average  train  length  of
    7,800 feet, average speed of 28 miles per hour) are more ex‐
    treme than those previously cited. Therefore, they sufficiently
    constitute new evidence. However, they do not mandate a dif‐
    ferent result. True, CN’s trains are slightly longer and slower
    than originally projected in 2015. But as the Board recognized,
    at least “some variance between what was projected and what
    has  occurred  is  expected,”  particularly  given  the  nine‐year
    gap between the Board’s initial projections and the Village’s
    current data. More important is the Village’s own study that
    found less traffic delay than initially projected in 2008, and the
    Board’s supported finding that the U.S. 14 intersection aver‐
    aged less than one reportable blocked crossing each month in
    2016.
    34                                                       No. 17‐3586
    D. Summary
    In short, this Court does not possess jurisdiction over the
    portions of the Village’s petition alleging material error. Alt‐
    hough we retain cognizance over the Village’s allegations of
    new  evidence  and  substantially  changed  circumstances,
    nearly all of these claims were not only available, but consid‐
    ered  at  earlier  stages  of  this  proceeding.  The  Board  did  not
    abuse its discretion in finding that the limited exceptions to
    this general rule were insufficient to demand material altera‐
    tions to its prior decision.
    At bottom, despite its repeated attempts over the past dec‐
    ade, the Village has never presented sufficient new evidence
    to  overcome  the  Board’s  original  finding  that  “the  major
    source of congestion” at U.S. 14 is “excess vehicle demand at
    existing major thoroughfare intersections” and “existing traf‐
    fic signals in proximity to one another,” not CN’s acquisition
    of the EJ & E line. Consequently, the Board has consistently
    acted within the scope of its authority by declining to impose
    the  dramatic  remedy  the  Village  seeks.  We  defer  to  the
    Board’s reasoned judgment.
    III.    Conclusion
    For  the  foregoing  reasons,  we  DENY  the  petition  for  re‐
    view.
    

Document Info

Docket Number: 17-3586

Judges: Flaum

Filed Date: 6/11/2018

Precedential Status: Precedential

Modified Date: 6/12/2018

Authorities (28)

railroad-ventures-inc-boardman-township-ohio-and-boardman-township-park , 299 F.3d 523 ( 2002 )

Wisconsin Central Ltd. v. Surface Transportation Board and ... , 112 F.3d 881 ( 1997 )

Decatur County Commissioners v. Surface Transportation Board , 308 F.3d 710 ( 2002 )

montezuma-grain-co-llp-and-redevelopment-commission-of-parke-county , 339 F.3d 535 ( 2003 )

Joseph K. Bagdonas v. Department of Treasury, United States ... , 93 F.3d 422 ( 1996 )

Advance Transportation Company v. United States of America ... , 884 F.2d 303 ( 1989 )

Village of Barrington, Ill. v. Surface Transp. Bd. , 636 F.3d 650 ( 2011 )

John D. Copanos and Sons, Inc. And Kanasco, Ltd. v. Food ... , 854 F.2d 510 ( 1988 )

Benoit Brookens v. Dawn White , 795 F.2d 178 ( 1986 )

City of Benton v. Nuclear Regulatory Commission , 136 F.3d 824 ( 1998 )

Friends of Sierra Railroad, Inc. And Tuolumne Park and ... , 881 F.2d 663 ( 1989 )

schneider-national-incorporated-schneider-transport-incorporated , 948 F.2d 338 ( 1991 )

highway-j-citizens-group-v-norman-mineta-in-his-official-capacity-as , 349 F.3d 938 ( 2003 )

toledo-peoria-western-railway-v-surface-transportation-board-and-united , 462 F.3d 734 ( 2006 )

Damsky v. Federal Communications Commission , 199 F.3d 527 ( 2000 )

Town of Springfield v. Surface Transportation Board , 412 F.3d 187 ( 2005 )

Kevin Jost,petitioners v. Surface Transportation Board and ... , 194 F.3d 79 ( 1999 )

microwave-communications-inc-and-mci-telecommunications-corporation-v , 515 F.2d 385 ( 1974 )

Commuter Rail Division of Regional Transportation Authority ... , 608 F.3d 24 ( 2010 )

grainbelt-corporation-and-farmrail-corporation-v-surface-transportation , 109 F.3d 794 ( 1997 )

View All Authorities »