State Ex Rel. Ohio Attorney General v. Shelly Holding Co. , 135 Ohio St. 3d 65 ( 2012 )


Menu:
  • [Cite as State ex rel. Ohio Atty. Gen. v. Shelly Holding Co., 
    135 Ohio St. 3d 65
    , 2012-Ohio-
    5700.]
    THE STATE EX REL. OHIO ATTORNEY GENERAL, APPELLEE, v. SHELLY
    HOLDING COMPANY ET AL.; SHELLY MATERIALS, INC., ET AL., APPELLANTS.
    [Cite as State ex rel. Ohio Atty. Gen. v. Shelly Holding Co.,
    
    135 Ohio St. 3d 65
    , 2012-Ohio-5700.]
    Air-pollution     control—42       U.S.C.     7413(e)(2)—Continuing           violations—R.C.
    3704.05—Penalties.
    (No. 2011-0252—Submitted November 16, 2011—Decided December 6, 2012.)
    APPEAL from the Court of Appeals for Franklin County,
    No. 09AP-938, 
    191 Ohio App. 3d 421
    , 2010-Ohio-6526, 
    946 N.E.2d 295
    .
    __________________
    CUPP, J.
    {¶ 1} This appeal asks us to determine the proper method of calculating
    the civil penalty to be levied against an industrial facility for noncompliance with
    the terms of its air-pollution-control permit. The appellate court concluded that
    according to the terms of the Shelly Materials, Inc., permits, the penalty is to be
    calculated from the initial date of noncompliance until the facility demonstrates
    that it no longer violates the permits.
    {¶ 2} We conclude that the appellate court reached the proper conclusion
    in this matter, and therefore, we affirm the judgment of the court of appeals.
    I. Factual and Procedural Background
    a. Shelly Company
    {¶ 3} The Shelly Company is an Ohio corporation engaged in the
    business of surfacing roads. It owns several subsidiaries, including appellants
    Shelly Materials, Inc., and Allied Corporation (collectively, “Shelly”).1 Shelly
    1. The original defendants in the state’s complaint were the Shelly Holding Company, the Shelly
    Company, Shelly Materials, Inc., Allied Corporation, and Stoneco, Inc. At the close of the state’s
    SUPREME COURT OF OHIO
    owns multiple hot-mix asphalt facilities in Ohio that support its road-surfacing
    activities.
    {¶ 4} The hot-mix asphalt facilities release pollutants into the air, such as
    particulate matter, carbon monoxide, nitrogen oxides, sulfur dioxide, and volatile
    organic compounds. The facilities are regulated by the Ohio Environmental
    Protection Agency (“Ohio EPA”) pursuant to air-pollution-control permits issued
    to Shelly.
    b. The Air-Pollution-Control Permits
    {¶ 5} The air-pollution-control permits issued to Shelly have a variety of
    requirements with which Shelly must comply, including terms that specify the
    emission limits for the applicable types of pollutants, set operational restrictions,
    and establish monitoring, recordkeeping, and reporting requirements.
    {¶ 6} The permits also prescribe the testing method each Shelly facility
    must use to establish its compliance with the permit’s emission limit for each
    pollutant. The prescribed testing method is set forth at Part II, Section (E) of the
    permits, and specifies:
    E. Testing Requirements
    1. Compliance with the emission limitations specified in
    Section A.I of these terms and conditions shall be determined in
    accordance with the following methods:
    a. Emissions Limitation:
    ***
    Applicable Compliance Method:
    case, the Shelly Holding Company and the Shelly Company were dismissed. As relevant to the
    issues presented in this appeal, only Shelly Materials, Inc., and Allied Corporation are involved.
    2
    January Term, 2012
    The permittee shall conduct, or have conducted, emission
    testing for this emissions unit in accordance with the following
    requirements:
    ***
    iv. The test(s) shall be conducted while the emissions unit
    is operating at or near its maximum capacity, burning on-spec oil
    and using virgin materials, unless otherwise specified or approved
    by the Central District Office.
    Each air-pollution-control permit further provides that the Shelly permit holder
    “shall remain in full compliance with all applicable State laws and regulations and
    the terms and conditions of this permit.”
    {¶ 7} In 2002 and 2006, five of Shelly’s hot-mix asphalt facilities
    performed the facility testing as required by their permits. During the facility
    testing, these five hot-mix asphalt facilities emitted pollutants in excess of the
    allowable emission limit set forth in the permits and, in doing so, failed to comply
    with the maximum-capacity stack-test (“stack-test”) requirement of the permit.2
    c. Trial Court Decision
    {¶ 8} In July 2007, the state of Ohio, by and through the attorney
    general, filed suit for injunctive relief and civil penalties.                   The complaint
    presented 20 claims for relief.            In the complaint, the state alleged that the
    companies had violated state law and Ohio’s federally approved plan for the
    implementation, maintenance, and enforcement of air-quality standards as
    required by the federal Clean Air Act, when it
    2. In each of the five instances, Shelly ultimately remedied the permit violation. Three facilities
    obtained a modified permit from the Ohio EPA increasing the allowable emission limit. One
    facility conducted another test and met the emission limit contained in the permit. Another facility
    also complied with the emission limit contained in the permit upon subsequent testing, but Shelly
    nevertheless requested a modified permit from the Ohio EPA to increase the allowable emission
    limit.
    3
    SUPREME COURT OF OHIO
    installed and thereafter operated new sources of air pollution
    without obtaining appropriate permits, modified and thereafter
    operated existing sources of air pollution without obtaining
    appropriate permits, exceeded air pollutant emission limitations,
    burned fuel containing excessive levels of mercury, lead and other
    hazardous chemical constituents, and violated the terms and
    conditions of applicable air pollution permits.
    The state did not allege any violations, or seek to enforce any provision, of the
    federal act.
    {¶ 9} The state’s seventh claim for relief alleged that in 2002 and 2006,
    the Shelly facilities emitted pollutants in excess of the allowable emission limit
    set forth in the permits and, in doing so, failed to comply with the stack-test
    requirement. The state alleged that the Shelly facilities violated R.C. 3704.05(C),
    which provides that “no person who is the holder of a permit * * * shall violate
    any of the permit’s terms or conditions.”
    {¶ 10} Shelly entered into stipulations with the state in which Shelly
    admitted liability to various claims in the complaint and acknowledged that when
    it conducted the stack testing, its facilities emitted pollutants in excess of the
    allowable amounts set forth in the permits and the facilities violated their
    respective permits. After a bench trial, the court issued a decision finding for the
    state on some, but not all, claims for relief. On the state’s seventh claim for relief,
    the only claim relevant here, the court acknowledged that Shelly did not dispute
    that on the days of stack testing in which the emissions exceeded the limits set
    forth in the permits, the permits were violated. The court accepted Shelly’s
    stipulations as findings of fact.
    4
    January Term, 2012
    {¶ 11} In    determining     the   appropriate   penalty,   the   trial   court
    acknowledged that the question remaining to be decided was whether, for
    purposes of calculating the penalty, the violation should be deemed to have
    occurred only on the day the facility failed the stack tests and emitted in excess of
    the permitted emission limitation or whether the violation should be presumed to
    be continuing until a new stack test demonstrated compliance with the permit.
    {¶ 12} The trial court concluded that the violation occurred only on the
    day on which the facility failed the stack tests. The court accepted Shelly’s
    argument that the conditions under which Shelly conducted the required stack
    tests did not represent the facilities’ normal operating conditions and that it
    operated its facilities within the permitted emission limits. Therefore, the court
    concluded, it was not reasonable to infer that the violation continued for every day
    thereafter until a subsequent emission test demonstrated compliance. The court
    assessed a civil penalty of $4,500 on the seventh claim for relief and a total of
    $350,123.52 on all claims.
    d. Appellate Court Decision
    {¶ 13} The state appealed and challenged the manner in which the trial
    court had calculated the civil penalties. The state asserted that the penalty should
    be assessed for each day a facility was out of compliance with its permit, which
    would be from the day it failed the stack testing and continuing until the facility
    demonstrated that it no longer failed the stack test as required by the permit.
    Under the state’s rationale, the time period for calculating the penalty commenced
    on the day that the stack test was conducted and showed that the facility exceeded
    the allowable emission limit of its permit. The last penalty day, according to the
    state, could be (1) the day on which the facility conducts a subsequent maximum-
    capacity test and the facility emissions are within the allowable limits of the
    permit, (2) the day on which the Ohio EPA issues a new permit for the facility
    with revised emission limits that are the same as or greater than the emission
    5
    SUPREME COURT OF OHIO
    released on the day when the facility conducted its initial emission test, or (3) the
    day on which the facility could show that it would pass a subsequently conducted
    maximum-capacity test because intervening facility modifications were made.
    {¶ 14} The appellate court sustained the state’s assignment of error in this
    regard and remanded the matter to the trial court for recalculation of the fine, in
    its discretion. 
    191 Ohio App. 3d 421
    , 2010-Ohio-6526, 
    946 N.E.2d 295
    , ¶ 66.3
    {¶ 15} Thereafter, we accepted Shelly’s appeal under our discretionary
    jurisdiction. 
    128 Ohio St. 3d 1481
    , 2011-Ohio-2055, 
    946 N.E.2d 240
    .
    II. Air-Pollution-Control Legislation
    {¶ 16} The principal federal legislation in this matter is the Clean Air Act,
    42 U.S.C. 7401 et seq., which is intended “to protect and enhance the quality of
    the Nation’s air resources” and to encourage pollution prevention through
    reasonable federal, state, and local governmental actions. 42 U.S.C. 7401(b)(1)
    and (c). Pursuant to the authority of the Clean Air Act, the administrator of the
    United States Environmental Protection Agency (“EPA”) establishes national
    standards for air quality and certain types of air pollutants. 42 U.S.C. 7409(a)(2)
    and (b)(1); 40 C.F.R. 50.1 through 50.17. The act also requires that the states
    adopt and submit to the administrator a plan for specifying how these air-quality
    standards will be achieved and maintained. 42 U.S.C. 7407(a) and 7410(a). The
    act anticipates that states will achieve the air-quality standards through use
    permits, enforcement, and emission monitoring. 42 U.S.C. 7410(a). Enforcement
    and penalty-calculation provisions are set forth at 42 U.S.C. 7413.
    {¶ 17} The purposes of Ohio’s Air Pollution Control Act, R.C. Chapter
    3704, are “to protect and enhance the quality of the state’s air resources” and “to
    3. In addition to presenting to the appellate court an assignment of error challenging the trial
    court’s calculation of civil penalties, the state presented three additional assignments of error. 
    191 Ohio App. 3d 421
    , 2010-Ohio-6526, 
    946 N.E.2d 295
    , ¶ 4. The remaining assignments of error
    were each sustained at least in part, and the appellate court’s disposition was to affirm the trial
    court’s judgment in part, reverse it in part, and remand the cause “for further proceedings in
    accordance with law and consistent with” the appellate court’s decision. 
    Id. at ¶
    68.
    6
    January Term, 2012
    enable the state, through the director of environmental protection, to adopt and
    maintain a program for the prevention, control, and abatement of air pollution that
    is consistent with the federal Clean Air Act.” R.C. 3704.02(A)(1) and (2). Ohio’s
    Air Pollution Control Act states that it is to be construed consistently with the
    federal Clean Air Act. R.C. 3704.02(B).
    {¶ 18} The director of the Ohio EPA is vested with the authority to
    administer R.C. Chapter 3704. The director is authorized to, among other things,
    (1) adopt air-quality standards for the state that are no more stringent than
    counterpart federal standards, (2) adopt emissions-standard rules necessary to
    meet those standards, (3) adopt rules requiring installation permits from the
    director as a prerequisite to constructing new sources of air pollution, (4) adopt
    rules prohibiting the operation of air-contaminant sources without either a permit
    to operate in compliance with applicable rules or a variance issued by the director,
    (5) adopt rules pertaining to the issuance, revocation, modification, or denial of
    variances that authorize emissions in excess of the applicable emission standards,
    (6) require operators of pollution sources to monitor emissions or air quality and
    to provide such reports as the director prescribes, and (7) enter upon private or
    public property for the purpose of making inspections, taking samples, and
    examining records or reports to ascertain compliance with air-pollution statutes,
    regulations, or orders. R.C. 3704.03(D), (E), (F), (G), (H), (I), and (L).
    {¶ 19} The Ohio EPA director has established administrative rules
    requiring air-contaminant sources4 to have either a permit to operate or a variance
    4. “Air contaminant source” means “each separate operation, or activity that result or may result in
    the emission of any of the following air contaminants:
    (1) An air contaminant or precursor of an air contaminant for which a
    national ambient air quality standard has been adopted under the Clean Air Act.
    (2) An air contaminant for which the source is regulated under the
    Clean Air Act.
    (3) A toxic air contaminant for which the source is regulated under the
    Clean Air Act.
    7
    SUPREME COURT OF OHIO
    and has adopted rules that govern allowable emissions. Ohio Adm.Code 3745-
    31-02(A) and 3745-31-09 and Chapters 3745-15 through 3745-26. Variances
    afford an exemption from the permit-to-operate requirement and authorize, under
    certain conditions, an air-contaminant source to operate without complying with
    applicable emission-control requirements. Ohio Adm.Code 3745-31-09(A).
    {¶ 20} The Ohio Air Pollution Control Act prohibits certain acts. The
    most basic of the prohibitions is that “emissions of an air contaminant” shall not
    be “caused, permitted, or allowed” unless a permit or variance allowing the
    release of the contaminant has been issued. R.C. 3704.05(A) and (B). See also
    Ohio Adm.Code 3745-31-02(A). Additional prohibitions particularly relevant to
    the matter under consideration in this case are that “[n]o person who is the holder
    of [an air-pollution-control] permit * * * shall violate any of its terms or
    conditions,” and that “[n]o person shall violate any order, rule, or determination
    of the director issued, adopted, or made under this chapter.” R.C. 3704.05(C),
    (G), (J)(2).
    {¶ 21} Violations of R.C. 3704.05 may result in civil and criminal
    liability. R.C. 3704.06(C) provides that a “person who violates section 3704.05
    * * * of the Revised Code shall pay a civil penalty of not more than twenty-five
    thousand dollars for each day of each violation.” Injunctive relief and criminal
    penalties are also available. R.C. 3704.06(B) and 3704.99.
    III. Analysis
    {¶ 22} At the outset, we note that Shelly does not dispute that when a
    facility emits pollutants in excess of its permitted limit while operating “at or near
    its maximum capacity,” it is out of compliance with its air-pollution-control
    permits and is liable for a civil penalty on the day of the failed stack test. Shelly
    has stipulated that its facilities emitted pollutants in excess of the respective
    Ohio Adm.Code 3745-31-01(I).
    8
    January Term, 2012
    permits’ emission limits during the stack-testing process. Thus, the issue raised in
    this appeal is not whether any of the Shelly facilities violated their Ohio EPA-
    issued permits. Rather, the issue is how long the violation continued in the
    interim period until Shelly demonstrated compliance with the permit terms.
    Specifically, the issue is whether that violation may be presumed to be continuing
    until Shelly rebuts the presumption with competent evidence that a facility is
    either (1) not violating its permit or (2) not violating its permit in a continuing
    manner. The answer to this question will also answer whether the civil penalty
    for the failed stack test is to be calculated according to the rationale applied by the
    trial court or to that applied by the appellate court.
    {¶ 23} Although it is well established that the amount of a civil penalty
    imposed for a violation of pollution-control policies lies within the discretion of
    the trial court, e.g., State ex rel. Brown v. Dayton Malleable, 
    1 Ohio St. 3d 151
    ,
    157-158, 
    438 N.E.2d 120
    (1982), Shelly and the state acknowledge that the issues
    involved in this case are matters of law and fact. 
    191 Ohio App. 3d 421
    , 2010-
    Ohio-6526, 
    946 N.E.2d 295
    , ¶ 5. Consequently, our focus is whether the appellate
    court properly determined that the trial court’s decision to limit emission
    violations and resulting penalties to the date of the nonconforming emission
    results was without some competent, credible evidence to support it. 
    Id. at ¶
    55.
    {¶ 24} The method prescribed by the permit for determining whether
    Shelly is operating within the pollution-emissions limitations of its permit is the
    stack test. Failing a stack test is a violation of the permit. Likewise, the stack test
    would normally be used also to determine when the facility has returned to
    compliance. When the facility passes a subsequent stack test, it has used the
    methodology prescribed by the permit for establishing that the facility is in
    compliance with the permit’s pollution-emission limits. When the trial court
    determines, within its discretion, the amount of the penalty to be assessed for the
    facility’s permit violation, the court must consider all of the days on which the
    9
    SUPREME COURT OF OHIO
    facility was out of compliance with its permit. Under the stack-test method that
    the permit specifies, this would logically include all of the days between the failed
    stack test and the subsequently passed stack test.
    {¶ 25} Shelly, however, argues two points against considering all of the
    days between the failed stack test and the subsequently passed stack test as days
    that the law requires the court to include in its penalty assessment.
    {¶ 26} First, Shelly argues that the court may not presume that the facility
    would exceed the permit’s limit on its pollution emissions unless the state first
    makes a prima facie showing that the violation is likely to be ongoing or
    continuing. Second, Shelly argues that even if the state makes a showing that the
    violation is likely to be ongoing, giving rise to a presumption that the violation
    continued for the entire time between the failed stack test and the subsequently
    passed stack test, Shelly still may rebut that presumption with evidence other than
    the stack test to show that the facility did not exceed its emissions limits on
    certain days.5
    a. What constitutes a “showing”?
    {¶ 27} Shelly first asserts that the state failed to show by a preponderance
    of the evidence that any particular Shelly facility was likely to, or actually did,
    emit pollutants in excess of its allowable permit limitation for each and every day
    of the alleged continuing violation period, including on those days when the
    facility was operating under normal conditions rather than at maximum capacity.
    5. Shelly’s first proposition of law:
    In a civil enforcement action, the state has the burden of proof to
    demonstrate by a preponderance of the evidence each and every day of
    violation.
    Shelly’s second proposition of law:
    If a continuing violation of permit terms can be inferred, a permit
    holder must be given the opportunity to rebut the inference.
    10
    January Term, 2012
    {¶ 28} The foundation for Shelly’s argument is R.C. 3704.06(B), which
    states that the attorney general has the authority to institute proceedings for
    violations of R.C. 3704.05 “upon the showing that the person has violated this
    chapter or rules adopted thereunder.” (Emphasis added.) Shelly contends that the
    phrase “upon the showing” is a standard legal term, which means the act of
    establishing through evidence or proof. Shelly further states that because this is
    civil litigation, the traditional burdens of proof apply and require the state to carry
    its evidentiary burden by a preponderance of evidence.             Shelly also cites
    decisional law that it claims supports its argument. United States v. Hoge Lumber
    Co., N.D.Ohio No. 3:95 CV 7044, 
    1997 U.S. Dist. LEXIS 22359
    (May 7, 1997);
    State ex rel. Celebrezze v. Thermal-Tron, Inc., 
    71 Ohio App. 3d 11
    , 
    592 N.E.2d 912
    (1992).
    {¶ 29} R.C. 3704.06(B) is silent as to what evidentiary requirements are
    necessary to constitute a “showing” for purposes of the provision. However,
    Ohio’s air-pollution-control statutes, regulations, and policies incorporate the
    standards contained in the federal act, which bear upon this question.
    {¶ 30} Since 1993, Ohio law has required that all the provisions that
    constitute the chapter of Ohio’s air-pollution-control statutes and “all the rules
    adopted under it, and all permits, variances, and orders issued under it shall be
    construed, to the extent reasonably possible, to be consistent with the federal
    Clean Air Act and to promote the purposes of the chapter.” R.C. 3704.02(B);
    1993 Am.Sub.S.B. No. 153, effective Oct. 29, 1993. Also, since 2004, 42 U.S.C.
    7413(e)(2) has been incorporated by reference into Ohio’s air-pollution-control
    regulations.    Ohio Adm.Code 3745-31-01(AAAAAA)(2)(mmm).6                     Section
    7413(e)(2) states:
    6. Ohio Adm.Code 3745-31-01(AAAAAA) provides:
    11
    SUPREME COURT OF OHIO
    A penalty may be assessed for each day of violation. For
    purposes of determining the number of days of violation for which
    a penalty may be assessed * * * where * * * an air pollution
    control agency has notified the source of the violation, and the
    plaintiff makes a prima facie showing that the conduct or events
    giving rise to the violation are likely to have continued or recurred
    past the date of notice, the days of violation shall be presumed to
    include the date of such notice and each and every day thereafter
    until the violator establishes that continuous compliance has been
    achieved, except to the extent that the violator can prove by a
    preponderance of the evidence that there were intervening days
    during which no violation occurred or that the violation was not
    continuing in nature.
    (Emphasis added.) Section 7413(e)(2).
    {¶ 31} The legislative history of Section 7413(e) provides additional
    insight into the intent and rationale underlying the continuing-violation
    presumption. The Senate report accompanying the 1990 reenactment of Section
    Incorporation by reference. This chapter includes references to certain
    matter or materials. The text of the incorporated materials is not included in the
    regulations contained in this chapter. The materials are hereby made a part of the
    regulations in this chapter. For materials subject to change, only the specific
    version specified in the regulations are incorporated. Material is incorporated as
    it exists on the effective date of this rule. Except for subsequent annual
    publication of existing (unmodified) Code of Federal Regulation compilations,
    any amendment or revision to a referenced document is not incorporated unless
    and until this rule has been amended to specify the new dates.
    ***
    (2) Incorporated materials:
    ***
    (mmm) Section 113 of the Clean Air Act; contained in 42 USC 7413;
    “Federal enforcement;” published January 19, 2004 in Supplement III of the
    2000 Edition of the United States Code.
    12
    January Term, 2012
    7413(e) noted that the section was rewritten to “identify explicitly a uniform set
    of factors that both the court and the Administrator shall consider in determining
    the appropriate amount of any penalty assessed under [the section].” S.Rep. No.
    101-228, at 365 (1989), reprinted in 1990 U.S.C.C.A.N. 3385, 3748 (1990). The
    report continued:
    In addition, once the government * * * establishes a prima
    facie case showing a violation of an ongoing nature, the burden of
    proof would shift to the source to prove by a preponderance of the
    evidence that it has cured the violation or that the violation was not
    of a continuing nature and did not recur. Otherwise, and until the
    date the source establishes that it has come into compliance, the
    court should presume that the violation was continuous, and should
    assess penalties for each day of that violation. This shift in the
    burden of proof is appropriate because the source is in a better
    position than EPA to establish its compliance status.         In this
    respect, the amendment overrules United States v. SCM Corp., 
    667 F. Supp. 1110
    (D.Md.1987), in which the court refused to shift to
    the source the burden of proving compliance after EPA established
    that the source was in violation of the Act.
    
    Id. at 336,
    reprinted in 1990 U.S.C.C.A.N. at 3749.
    {¶ 32} In this case, the trial court’s approach to the continuing-violation
    presumption and civil-penalty calculation was similar to that in the discredited
    SCM Corp. decision. Accordingly, the appellate court properly rejected the trial
    court’s conclusions and applied the federally established, and state-incorporated,
    continuing-violation presumption. It correctly concluded that the trial court, to
    ensure that the state’s air-pollution-control laws were construed consistently with
    13
    SUPREME COURT OF OHIO
    the federal act’s provisions as required by R.C. 3704.02, should have considered
    the permit violations as continuing until it was proved by the violator that a
    particular plant was no longer in violation of its permit.
    {¶ 33} Consequently, for the purposes of calculating the penalty for an
    air-pollution-control violation, the state must (1) establish that there was a
    violation of the permit requirements, (2) establish that the permit holder was
    notified of the violation, and (3) make a “prima facie showing that the conduct or
    events giving rise to the violation are likely to have continued or recurred past the
    date    of    notice.”     Section     7413(e)(2);      see    Ohio      Adm.Code        3745-31-
    01(AAAAAA)(2)(mmm). Establishing the foregoing gives rise to a rebuttable
    presumption that the violation includes “the date of such notice and each and
    every day thereafter until the violator establishes that continuous compliance has
    been achieved” and that a penalty may be assessed for each day of violation. 
    Id. The violator
    may rebut this presumption and avoid the imposition of a penalty by
    proving “by a preponderance of the evidence that there were intervening days
    during which no violation occurred or that the violation was not continuing in
    nature.” 
    Id. b. A
    Permit Violation and Notice of the Violation
    {¶ 34} As to establishing a violation, it is undisputed, and Shelly has so
    stipulated, that when the facilities failed the stack-testing requirement of the
    permit, a mandatory and legally enforceable term of the permit was violated and
    that violation is subject to the imposition of a civil penalty. R.C. 3704.05(C) and
    3704.06; Section 7413(e). It is also undisputed that Shelly was given notice of the
    permit violation.7 Section 7413(e).
    7. The failure to pass a stack test is a different and independent permit violation from a permit
    violation in which a facility has emitted in excess of the allowable limit set forth in its permit or
    variance. This would be a violation of R.C. 3704.05(A) and (B). Compare State ex rel. Brown v.
    Dayton Malleable, Inc., 
    1 Ohio St. 3d 151
    , 155, 
    438 N.E.2d 120
    (1982) (in the analogous context
    of water-pollution control, each term and condition of a permit is to be considered and given effect
    14
    January Term, 2012
    c. The Prima Facie Showing
    {¶ 35} We next consider the third element and whether the state made a
    prima facie showing “that the conduct or events giving rise to the violation are
    likely to have continued or recurred past the date of notice.” Section 7413(e)(2).
    In light of Shelly’s stipulations, a reasonable inference arises that if a Shelly
    facility failed the stack test on one day, and if no changes were made, it would fail
    the same test on a subsequent day. 
    Id. Conversely, it
    would be illogical to
    conclude that without some change in the conditions or circumstances that
    produced the failed stack test, continuous compliance with the permit terms had
    been achieved.
    {¶ 36} Therefore, when the state establishes that a permit holder failed to
    pass the stack test required by its permit, as is the case here, a prima facie
    showing is made that the violation is likely to continue. The burden of proof then
    shifts to the permit holder to show that either continuous compliance has been
    achieved or that some change in conditions has occurred to cause the violation not
    to be a continuing one. Section 7413(e)(2). In this regard, Shelly’s reliance on
    the Hoge Lumber and Thermal-Tron cases is inapposite. In Hoge Lumber, the
    court determined that the prima facie presumption that the violation was of a
    continuing nature applied because the defendant-polluter failed to provide any
    contrary rebuttal evidence, and Thermal-Tron predates the 1993 amendments to
    Ohio’s air-pollution-control statutes.8
    d. Rebuttal Evidence
    {¶ 37} Section 7413(e)(2) allows Shelly to rebut the presumption of a
    continuing violation, and the state conceded this point at oral argument.
    in determining whether a permit has been violated; whether the pollution-discharge limit was
    improperly exceeded is only one part of the inquiry).
    8. Hoge Lumber also involved permit violations that predated the 1993 amendments to Ohio’s air-
    pollution-control statutes (of the eight violations, five were before 1993).
    15
    SUPREME COURT OF OHIO
    However, the parties disagree on what evidence may be used to properly rebut the
    continuing-violation presumption to mitigate the imposition of penalties. There is
    no apparent dispute between the parties that the penalties ceased when the Shelly
    facilities came back into compliance with their respective permits because they
    obtained modified permits or variances or conducted subsequent stack testing
    demonstrating that the facility was in compliance with permit requirements.
    {¶ 38} The state contends, however, that Shelly could mitigate its
    penalties by also offering rebuttal evidence that shows that the permit violation
    was not of a continuing nature, with evidence such as days of nonoperation or
    subsequent modifications to a facility. To the extent that Ohio’s air-pollution-
    control policies incorporate the federal enforcement and penalty-calculation
    provisions, we agree that the additional considerations of whether there were
    intervening days during which the permit violation did not occur or that the
    violation was not continuing in nature are “not limited to * * * evidence that is
    based solely on the applicable test method in the State implementation or
    regulation” and may include “evidence from continuous emission monitoring
    systems, expert testimony, and bypassing and control equipment malfunctions,
    even if these are not the applicable test methods.” S.Rep. No. 101-228 at 366,
    reprinted in 1990 U.S.C.C.A.N. at 3749.
    {¶ 39} Therefore, Shelly was not limited to presenting evidence that
    showed successful compliance with a subsequent stack test to mitigate its penalty
    for the permit violation. Rather, Shelly could have offered evidence that showed
    that the permit violation was not of a continuing nature, such as evidence that the
    operating conditions documented during the stack testing no longer existed, that
    mechanical failures were repaired, that raw materials and fuels were changed, or
    that Shelly scheduled retests.
    16
    January Term, 2012
    {¶ 40} Shelly declined to present evidence of this character into the
    record.9    Instead, Shelly presented what it calls a “normal operations defense.”
    According to Shelly, because the operation of the Shelly facilities at maximum-
    capacity for the stack test was only a snapshot of a plant’s emissions over the
    course of a one-hour period using worst-case fuels and materials, the stack test did
    not reflect the normal, daily operating conditions of Shelly’s facilities and, under
    such normal operating conditions, the normal release of emissions. Shelly asserts
    that because it does not normally operate any of its facilities under the conditions
    required for the stack testing, the failed stack test cannot be used by the state to
    demonstrate that the Shelly facilities were systemically out of compliance with
    their respective permits—only that there was noncompliance on the day of the
    test.
    {¶ 41} Shelly’s normal-operations argument does have intuitive appeal:
    that the operation of a facility at less than maximum capacity will result in the
    emission of fewer pollutants. Nevertheless, Shelly’s normal-operations argument
    does not provide any actual evidence that the emissions released while operating
    normally are within the permit’s emission limit. The burden is on the violator to
    prove by a preponderance of the evidence that there were intervening days on
    which no violation occurred or that the violation was not continuing in nature.
    Consequently, Shelly’s normal-operations argument, without more, does not show
    how the permit violation was not of a continuing nature.
    {¶ 42} Based on the foregoing, we cannot conclude that Shelly presented
    sufficient evidence to rebut the application of a continuing-violation presumption.
    9. Shelly implied at oral argument that it possessed this type of evidence but that it declined to
    submit it, relying instead on its argument that the state bore the burden of proof to show that the
    permit violation was of a continuing nature and on the testimonial evidence supporting its normal-
    operations defense.
    17
    SUPREME COURT OF OHIO
    IV. Conclusion
    {¶ 43} We hold that the Shelly facilities were out of compliance with their
    air-pollution-control permits, and thus subject to civil penalty, from the date on
    which stack testing showed emissions in excess of the limits specified in the
    permit until the permit holder demonstrated compliance with permit terms.
    Accordingly, we conclude that the appellate court’s judgment remanding this
    matter to the trial court for a recalculation of the civil penalty, within the trial
    court’s sound discretion, was appropriate.
    {¶ 44} Nonetheless, on the state’s invitation, we remand this matter to the
    trial court for reopening of the record to allow Shelly the opportunity to identify
    evidence that demonstrates that the permit violation was not a continuing
    violation. At that time, Shelly may identify the rebuttal evidence that addresses
    the actions taken by its facilities from the time when the facilities initially failed
    to comply with that requirement and until the facilities came back into
    compliance, either through a subsequent compliance-demonstrating stack test or
    revised permits or variances, and Shelly may demonstrate that the violation of the
    stack-test requirement was not of a continuing nature.
    {¶ 45} The judgment of the court of appeals is affirmed, and the cause is
    remanded for proceedings consistent with this opinion.
    Judgment affirmed
    and cause remanded.
    O’CONNOR, C.J., and PFEIFER, LUNDBERG STRATTON, and MCGEE
    BROWN, JJ., concur.
    O’DONNELL and LANZINGER, JJ., dissent.
    _________________
    LANZINGER, J., dissenting.
    {¶ 46} I respectfully dissent. By affirming the judgment of the Tenth
    District Court of Appeals, holding that excessive air emissions occurring during a
    18
    January Term, 2012
    stack test conducted at a facility’s maximum capacity establishes a presumption
    that a continuing violation exists, the majority allows the state a lesser burden of
    proof and disregards the defendants’ right to due process.
    {¶ 47} After a lengthy trial and meticulous findings of fact, and as part of
    the total enforcement penalty of $350,123.52, the trial court assessed a civil
    penalty of $4,500 for Shelly’s admitted violations in the seventh claim for relief.
    The court of appeals reversed without determining that the trial court’s
    conclusions were against the manifest weight of the evidence. State ex rel. Ohio
    Atty. Gen. v. Shelly Holding Co., 
    191 Ohio App. 3d 421
    , 2010-Ohio-6526, 
    946 N.E.2d 295
    . Shelly does not dispute that in 2002 and 2006, five of its facilities
    violated the air-emissions levels set forth in their permits to install (“PTIs”)
    during the time that stack tests measured them at maximum capacity. What
    Shelly does contest is its ongoing liability for a “continuing violation” based on
    the record of this case.
    {¶ 48} I would accept Shelly’s argument that no continuing civil penalty
    may be assessed because notwithstanding the excess pollutants that were emitted
    on the day of testing, the state has not met its burden of proving that excess
    pollutants were emitted every day for which a penalty is sought.
    I. Legal Argument
    A. The State Must Prove a Continuing Violation to Collect Ongoing Civil
    Penalties
    {¶ 49} As the majority explains it, the issue here is “how long the
    violation continued in the interim period until Shelly demonstrated compliance
    with the permit terms. Specifically, the issue is whether that violation may be
    presumed to be continuing until Shelly rebuts the presumption with competent
    evidence that a facility is either (1) not violating its permit or (2) not violating its
    permit in a continuing manner.” Majority opinion at ¶ 22. In other words, is the
    defendant liable for a civil penalty for a continuing violation?
    19
    SUPREME COURT OF OHIO
    {¶ 50} This is a civil enforcement action. Ohio law requires the state to
    show by a preponderance of the evidence that a violation of law actually occurred
    for each day the state seeks a penalty or that an ongoing violation occurred before
    the state can collect penalties for a continuing violation. Cincinnati, Hamilton &
    Dayton Ry. v. Frye, 
    80 Ohio St. 289
    , 
    88 N.E. 642
    (1909), paragraph two of the
    syllabus (“In civil cases the jury deals only with probabilities, and the burden of
    proof is ordinarily carried by a preponderance of the evidence”); Ohio Valley
    Radiology Assocs. v. Ohio Valley Hosp. Assn., 
    28 Ohio St. 3d 118
    , 122, 
    502 N.E.2d 599
    (1986) (“the sole responsibility of a defendant who has effectively
    contested the claimant’s allegations by pleading is to refute the claimant’s case
    after the latter has established a prima facie case by proper evidence” [emphasis
    sic]).
    {¶ 51} Even under 42 U.S.C. 7413(e)(2), the section of the Clean Air Act
    that sets forth the standard for federal enforcement actions, the plaintiff must
    make a prima facie showing that the conduct or events giving rise to the violation
    are likely to have continued or recurred after the defendant has been notified of
    the violation:
    [W]here the Administrator or an air pollution control agency
    has notified the source of the violation, and the plaintiff makes
    a prima facie showing that the conduct or events giving rise to
    the violation are likely to have continued or recurred past the
    date of notice, the days of violation shall be presumed to
    include the date of such notice and each and every day
    thereafter until the violator establishes that continuous
    compliance has been achieved, except to the extent that the
    violator can prove by a preponderance of the evidence that there
    20
    January Term, 2012
    were intervening days during which no violation occurred or
    that the violation was not continuing in nature.
    (Emphasis added.) 42 U.S.C. 7413(e)(2).
    {¶ 52} In other words, in a federal enforcement action, there is no
    presumption of a continuing permit violation unless a prima facie showing has
    been made. The government carries the burden of making a prima facie showing
    that the conduct or events giving rise to the violation are likely to have continued
    each day. It is only after this prima facie showing is made that the defendant must
    offer rebuttal evidence that a continuing violation has not occurred.
    {¶ 53} A federal enforcement action brought under the Clean Air Act
    offers guidance as to what a state could do to fulfill its own burden to prove a
    violation under its own environmental laws. United States v. Hoge Lumber Co.,
    N.D.Ohio No. 3:95 CV 7044, 
    1997 U.S. Dist. LEXIS 22359
    (May 7, 1997). In
    Hoge, the court found that a continuing violation had occurred based on
    unrebutted evidence offered by the Department of Justice showing actual stack-
    test exceedances (eight in all) plus (1) an affidavit from an expert engineer who
    testified that the permit holder performed eight stack tests on its boiler under
    various operational conditions, including operating conditions as low as 22
    percent of capacity (i.e., not maximum operating capacity) and that all eight stack
    tests showed emissions violations, (2) testimony by a company witness who
    testified that the boiler was not operating in compliance with its air permit limits
    and expressed doubt that the boiler could ever meet the emission limit required by
    the air permit, and (3) evidence of actual days on which the defendant operated its
    boiler in a manner exceeding emissions—700 days over a 12-year period.
    {¶ 54} But here, in contrast, the state did not offer any evidence that “the
    conduct or events giving rise to the violation are likely to have continued or
    21
    SUPREME COURT OF OHIO
    recurred past the date of notice.” 42 U.S.C. 7413(e)(2). And the majority holds
    that the state establishes a prima facie case with a single failed stack test.
    {¶ 55} In another case dealing with the need for a PTI to control air
    emissions, we stated:
    Keeping in mind the purposes of R.C. Chapter 3704, we
    must strive to reach a balance between promoting and enhancing
    clean air and protecting and encouraging economic growth and
    opportunities for the people of this state. This requires that
    business entities not be subjected to an interminable task of dealing
    with excessive regulation or requirements not explicitly covered by
    statute or rule. Therefore, any uncertainty with regard to the
    interpretation of R.C. Chapter 3704 and rules promulgated
    thereunder should be construed in favor of the person or entity
    (manufacturer or otherwise) affected by the law.
    State ex rel. Celebrezze v. Natl. Lime & Stone Co., 
    68 Ohio St. 3d 377
    , 385, 
    627 N.E.2d 538
    (1994). At the very least, the state must be held to its burden of proof.
    B. One Failed Stack Test Does Not Prove a Continuing Violation
    {¶ 56} Each of Shelly’s PTIs requires the facility to be operating within
    the allowable levels of various pollutants as established for each facility. Part II,
    Section A.1 of the individual permits sets forth both emissions limits per hour and
    emissions limits per year. Each permit sets allowable levels of emissions for
    certain classes of air pollutants. Part II, Section E.1 of the permits specifies the
    testing methods that the plant must use to establish compliance. In Shelly’s case,
    the use of a plant’s maximum operating capacity is a stated part of the testing
    protocol. On testing day, facility emissions are tested when a plant is operating its
    air-pollution sources at the maximum capacity possible. (“The test shall be
    22
    January Term, 2012
    conducted while the emissions unit is operating at or near its maximum capacity
    * * *.”) While the permit limits emissions both by hour and by year, the stack test
    requires measurement of emissions only on a particular day.
    {¶ 57} The majority treats this testing requirement as a separate permit
    term. But the seventh claim for relief in the complaint against Shelly alleges air-
    emission violations, not testing violations. There is no allegation that Shelly
    violated the testing requirements themselves—the tests were done in accordance
    with the maximum-capacity protocol set forth in the permit. Stated another way,
    the permit does not mandate that Shelly’s plants operate at a constant maximum
    capacity so as to support a presumption that emissions levels are continuously
    being exceeded once an initial stack test has been failed.
    {¶ 58} Shelly’s argument that a stack test does not represent normal
    operating conditions at its facilities is compelling. Thus, on days when a facility
    is not running at maximum capacity, it is possible that air emissions are within the
    limit established in that facility’s PTI. In failing to show that the emissions
    violations (appearing when the facility was running at maximum capacity) were
    likely to continue, the state failed to present evidence to support the presumption
    of a continuing air-emission violation that justified daily penalties.
    {¶ 59} A civil penalty pursuant to R.C. 3704.06(C) was in order based
    upon Shelly’s admitted violations of facilities named in the seventh claim for
    relief. Nevertheless, the state offered no evidence beyond the single failed test to
    show that a continuing violation existed beyond the dates of each failed stack test.
    {¶ 60} The court of appeals’ opinion looked at a snapshot in time—stack
    testing at maximum capacity—and created an irrebuttable presumption that the
    company is continuously violating its permit until it shows that it can pass another
    stack test, which realistically will not occur before at least 30 days after Shelly
    gives the requisite notice to the Ohio Environmental Protection Agency,
    according to Part II, Section E.1 of the permits. Even if this court applies the
    23
    SUPREME COURT OF OHIO
    federal Clean Air Act’s prima facie burden-of-proof standard, as the state now
    urges, the state still has the burden to show that the conduct or events giving rise
    to the violation are likely to have continued or recurred. 42 U.S.C. 7413(e)(2).
    II. Conclusion
    {¶ 61} Civil penalties of up to $25,000 a day are significant deterrents to
    environmental violations, and potential penalties should be imposed only for each
    day that the state has proven a violation by a preponderance of the evidence.
    {¶ 62} Because a continuing violation has not been proven in this case, I
    would reverse the judgment of the court of appeals. I would hold that in a civil
    action pursuant to R.C. 3704.06, the state must prove each day of violation for
    which it seeks a civil penalty.
    O’DONNELL, J., concurs in the foregoing opinion.
    __________________
    Michael DeWine, Attorney General, Alexandra T. Schimmer, Solicitor
    General, and Gregg H. Bachmann and Gary L. Pasheilich, Assistant Attorneys
    General, for appellee.
    Bott Law Group, L.L.C., and April R. Bott; Chester, Wilcox & Saxbe,
    L.L.P., and Sarah Morrison, for appellants Shelly Materials, Inc. and Allied
    Corporation.
    Brady, Coyle & Schmidt, Ltd., and Brian P. Barger, urging reversal for
    amici curiae Ohio Chamber of Commerce, Ohio Aggregates and Industrial
    Minerals Association, Flexible Pavements, Inc., Ohio Coal Association, Ohio
    Contractors Association, and Associated General Contractors of Ohio.
    ________________________
    24
    

Document Info

Docket Number: 2011-0252

Citation Numbers: 2012 Ohio 5700, 135 Ohio St. 3d 65

Judges: Brown, Cupp, Lanzinger, Lundberg, McGee, O'Connor, O'Donnell, Pfeifer, Stratton

Filed Date: 12/6/2012

Precedential Status: Precedential

Modified Date: 8/31/2023