In re Application of Buckeye Wind, L.L.C. , 131 Ohio St. 3d 449 ( 2012 )


Menu:
  • [Cite as In re Application of Buckeye Wind, L.L.C., 
    131 Ohio St.3d 449
    , 
    2012-Ohio-878
    .]
    IN RE APPLICATION OF BUCKEYE WIND, L.L.C., FOR A CERTIFICATE TO
    CONSTRUCT WIND-POWERED ELECTRIC GENERATION FACILITIES IN
    CHAMPAIGN COUNTY, OHIO; UNION NEIGHBORS UNITED ET AL., APPELLANTS;
    POWER SITING BOARD ET AL., APPELLEES.
    [Cite as In re Application of Buckeye Wind, L.L.C.,
    
    131 Ohio St.3d 449
    , 
    2012-Ohio-878
    .]
    Power Siting Board—Wind-powered electric generation facility—Determination
    approving siting of facility was lawful, reasonable, and not manifestly
    against the weight of the evidence—Board did not improperly delegate its
    decisionmaking authority to staff.
    (No. 2010-1554—Submitted September 21, 2011—Decided March 6, 2012.)
    APPEAL from the Power Siting Board, No. 08-666-EL-BGN.
    __________________
    LANZINGER, J.
    {¶ 1} This is the first time that we have reviewed an order involving the
    grant of authority to construct a proposed wind-powered electric generation
    facility.   After full review of the record and consideration of the parties’
    arguments, we hold that the order of the Power Siting Board should be affirmed
    because the board acted in accordance with all pertinent statutes and regulations.
    I. Background
    {¶ 2} The General Assembly enacted legislation, 2007 Am.Sub.S.B. No.
    221, effective July 31, 2008, to require utilities to provide a portion of their
    electricity supply from alternative energy sources by 2025. See R.C. 4928.64 and
    4928.65. The term “alternative energy resource” includes a “renewable energy
    resource.” R.C. 4928.64(A)(1). Wind energy is listed within the definition of
    “renewable energy resource.” R.C. 4928.01(A)(35). Under R.C. 4906.03, the
    SUPREME COURT OF OHIO
    board has been granted exclusive authority to issue certificates for construction,
    operation, and maintenance of major utility facilities.
    {¶ 3} A private developer, Buckeye Wind, L.L.C. (“Buckeye”),
    developed a plan to build 70 wind turbines over approximately 9,000 acres in
    Champaign County, Ohio, where Buckeye perceived a favorable blend of wind,
    open land, and access to the electric power grid. This project is one of the first
    wind farms in Ohio. The wind farm’s expected generation capacity exceeded 126
    megawatts, qualifying it under R.C. 4906.01(B)(1) as a “major utility facility”
    that required the approval of the board. R.C. 4906.03.
    {¶ 4} In April 2009, Buckeye filed with the board a 1,500-page
    application for a certificate of environmental compatibility and public need. See
    R.C. 4906.04. A group of neighboring landowners, Union Neighbors United
    (“UNU”), Robert and Diane McConnell, and Julia Johnson (collectively, “the
    neighbors”), opposed the application.          Several other entities, including
    Champaign County and several local townships (collectively, “the county”), also
    intervened.
    {¶ 5} The neighbors were concerned about noise and the turbines’
    proposed setbacks of 914 feet from homes and 541 feet from property lines.
    Wind turbines such as those proposed by Buckeye can stand as tall as 328 feet,
    with a blade at the highest point being 492 feet high. The neighbors also raised
    issues of “shadow flicker,” a potentially annoying phenomenon caused by the
    swinging of turbine blades between the ground and the sun, and the possibility of
    blade detachment. Unlike landowner-lessors who host turbines, the neighbors
    received no compensation from Buckeye, and they also noted the effect the
    proposed facility could have on property values. The board rejected most of the
    neighbors’ requests and approved construction of most of the proposed turbines.
    {¶ 6} The county did not oppose the siting of the turbines but sought
    financial protection through bond requirements that would ensure that adequate
    2
    January Term, 2012
    money was available to (1) repair any roads damaged by the project and (2)
    remove (or “decommission”) the turbines if and when they became inoperable.
    The board agreed to require a $5,000 bond for the first year of operation. The
    county was dissatisfied with the bond amount as well as the fact that the
    Champaign County Engineer did not have final say on the amount.
    {¶ 7} The county appealed, as did the neighbors. Buckeye intervened on
    behalf of the board. The county raised three propositions of law, the neighbors
    raised ten propositions of law, and the Ohio Farm Bureau filed an amicus brief
    urging affirmance.
    II. Legal Analysis
    A. The Board Conducted Appropriate Public Hearings
    {¶ 8} In their ninth proposition of law, the neighbors argue that the board
    deprived the neighbors of “the statutory right to call and examine witnesses at the
    hearing.”   Although the neighbors argue that the board has violated R.C.
    4906.07(A) by failing to hold a full hearing and considering testimony from the
    opponents before acting on Buckeye’s application to construct wind turbines in
    Champaign County, the record belies this conclusion.
    {¶ 9} First,   appellants   were       active   participants   throughout   the
    administrative process. The neighbors and the Ohio Farm Bureau Federation were
    allowed to intervene on July 31, shortly after Buckeye had filed its initial
    application on April 24, 2009. The townships of Goshen, Rush, Salem, Urbana,
    and Wayne, the city of Urbana, the Urbana Country Club, the Board of
    Commissioners of Champaign County, the Champaign Telephone Company, and
    the Piqua Shawnee Tribe also were permitted to intervene in the proceedings
    before the board.
    {¶ 10} Second, these intervening parties, as well as the general public, had
    an opportunity to be heard. A public informational hearing was held on June 10,
    2008, shortly after Buckeye notified the board of its intention to apply for a
    3
    SUPREME COURT OF OHIO
    construction certificate. After the application was filed and staff conducted its
    investigation, a local public hearing was held, in accordance with Ohio Adm.Code
    4906-7-01(A), on October 28, 2009, in North Lewisburg, Ohio. The adjudicatory
    hearing began on October 27, was continued on November 9, and initial
    testimony concluded on November 20, 2009; rebuttal testimony was presented on
    December 1 and 2, 2009.
    {¶ 11} Third, the intervenors conducted discovery before the hearing,
    participated in pretrial hearings, and filed motions to ensure the presentation of
    written testimony and of witnesses. Buckeye called 11 witnesses, the board staff
    called 8, and intervenors presented 17. Forty-six people testified at the local
    public hearing.
    {¶ 12} Fourth, the board’s summary of the evidence, consideration of
    arguments for and against every point, and careful recitation of the requirements
    of R.C. 4906.10(A) are clearly presented in its opinion, order, and certificate,
    which was entered on March 22, 2009. The 101-page order is thorough and
    shows that the board considered all points of view, including the intervenors’
    positions on every issue.
    B. The Board Did Not Improperly Delegate Decisionmaking to Its Staff
    {¶ 13} We stated in In re Application of Am. Transm. Sys., Inc., 
    125 Ohio St.3d 333
    , 
    2010-Ohio-1841
    , 
    928 N.E.2d 427
    , ¶ 20-21:
    R.C. Chapter 4906, the board’s enabling statute, expressly
    allows the board to delegate many responsibilities to subordinates.
    * * * R.C. 4906.02(C) states, “The chairman of the public utilities
    commission may assign or transfer duties among the commission's
    staff.” * * *
    One responsibility, however, cannot be delegated: “the
    board’s authority to grant certificates under section 4906.10 of the
    4
    January Term, 2012
    Revised Code shall not be exercised by any officer, employee, or
    body other than the board itself.” R.C. 4906.02(C).
    {¶ 14} Appellants argue that the board improperly delegated its
    decisionmaking authority because the order allows staff members to (1) approve
    new sites for three turbines, (2) review and accept plans regarding the design and
    siting of electric-collection lines, transportation routing, tree clearing, emergency
    services, and complaint resolution, (3) resolve the maximum potential distance
    that a detached turbine blade could be thrown, and (4) determine the specific
    model of wind turbine to be used.        The issues characterized as improperly
    deferred, however, simply require additional submissions that Buckeye will make
    to staff before the preconstruction conference.
    {¶ 15} The order explains that the purpose of the preconstruction
    conference is to (1) demonstrate compliance with the requirements of other state
    and federal agencies, (2) demonstrate compliance with the certificate issued by
    the board, and (3) show that the complaint procedures address public concerns.
    Pub. Util. Comm. No. 08-666-EL-BGN, at 81-82 (2010). Nothing in the order
    suggests that actions would occur secretly—the board specifically acknowledges
    its duty under R.C. 4906.07 and expressly rejects the neighbors’ claim that the
    public would be foreclosed from providing input:
    Any party to a certificate application has an opportunity, as UNU
    has done in this matter, to oppose staff’s recommended conditions
    or to propose additional conditions. Furthermore, the Board notes
    that, in accordance with Section 4906.07, Revised Code, the Board
    is required to hold a hearing in the same manner as on the
    application, where the amendment of a certificate involves any
    5
    SUPREME COURT OF OHIO
    material increase in any environmental impact or substantial
    change in the location of all or a portion of the facility.
    (Emphasis added.) Id. at 82. Thus it appears that interested parties will have the
    right to file before the board if Buckeye violates the terms of the certificate.
    {¶ 16} Contrary to arguments that the issues challenged by appellants
    must be finally resolved by the board before a certificate may be issued, R.C.
    4906.10(A) allows a certificate to be issued upon such conditions as the board
    considers appropriate. The statutes authorize a dynamic process that does not
    end with the issuance of a construction certificate. The General Assembly vested
    the board with authority to allow its staff to monitor Buckeye’s compliance with
    conditions that the board has set, conditions upon which the neighbors already
    had the chance to be heard.
    {¶ 17} The board has limited Buckeye’s certificate, adding 70 separate
    conditions. The board followed statutory requirements in establishing each one.
    The order recognizes that proper facility siting is subject to modification as the
    process continues—proposals are tested and matched to the defined conditions.
    Simply because certain matters are left for further review and possible public
    comment does not mean they have been improperly delegated to staff. Any
    material modification to the certificate is subject to hearing “in the same manner
    as on the application.” The neighbors’ right to be heard is safeguarded by R.C.
    4906.07. Furthermore, Buckeye must continue to abide by the conditions as
    presently set by the board in the certificate.
    {¶ 18} The board did not improperly delegate its responsibility to grant or
    deny a provisional certificate when it allowed for further fleshing out of certain
    conditions of the certificate.
    6
    January Term, 2012
    1. Staff Review and Acceptance
    {¶ 19} The board’s staff is responsible for ensuring compliance in the
    field and initiating enforcement actions when needed. Condition 8 of the order
    requires Buckeye to submit a variety of reports that contain final, detailed
    descriptions of its construction plan. The neighbors were not foreclosed from an
    opportunity to explore these matters at the hearing. The provision requesting
    additional submissions is designed to ensure compliance with the conditions
    already ordered by the board.
    2. Concerns over Blade Shear
    {¶ 20} In its order, the board considered the possibility that a rotor blade
    may drop or be thrown from the turbine, a situation known as “blade shear.”
    There is testimony in the record that previous instances of blade shear involved a
    blade model not considered by Buckeye. The board adopted Condition 33, which
    states: “Prior to the preconstruction conference, Buckeye shall provide staff with
    both the maximum potential distance for a blade shear event from the three
    turbine models under consideration and the formula used to calculate the
    distance.”
    {¶ 21} Buckeye presented evidence that no member of the public has ever
    been injured by blade shear, that technology now includes two independent
    braking systems that will automatically shut down a turbine at wind speeds over
    the manufacturer’s threshold, and that turbines will stop if significant vibrations
    or rotor-blade stress is sensed by the monitoring systems. The board found that
    Buckeye “sufficiently demonstrated that the setbacks, as currently configured,
    when combined with advances in wind turbine technology, are sufficient to
    protect residents from any risk of blade shear.” Pub. Util. Comm. No. 08-666-
    EL-DGN, 42-43.      Condition 33 mitigates the risk of injury even further by
    adopting the staff’s recommendation that Buckeye provide a formula to support
    its consultant’s calculations. The board specifically found that this condition
    7
    SUPREME COURT OF OHIO
    responded to the neighbors’ concerns. Given these measures, the board did not
    act unreasonably or unlawfully in addressing the blade-shear concerns.
    3. Turbine Relocation
    {¶ 22} Conditions 45 and 46 pertain to turbines 70 and 57, for which the
    proposed locations were not approved.          The order provides that if Buckeye
    chooses to modify the location of these turbines, additional information must be
    submitted to the staff for review and approval before construction, and Buckeye
    “shall comply” with all conditions of the order, including setbacks. Condition 40
    provides that the location of turbine 37 is conditioned upon “an in-depth vertical
    Fresnel-Zone analysis” to determine whether relocation of the turbine is necessary
    because of microwave interference. By providing clear directions stating where
    turbines may not be placed and guidelines setting forth requirements for
    permissible sites, the board did not unreasonably or unlawfully give the staff
    general discretion to approve new sites.
    4. Choice of Turbine Model
    {¶ 23} Condition 49 provides:
    At least 60 days prior to construction, Buckeye shall file a
    letter with the Board that identifies which of the three turbine
    models listed in the application has been selected. If Buckeye
    selects a turbine model other than one of the three models listed in
    the application, in addition to the letter, Buckeye shall also: file
    copies of the safety manual for the turbine model selected and
    manufacturer contact information; and provide assurances that no
    additional negative impacts would be introduced by the model
    selected.
    8
    January Term, 2012
    {¶ 24} No issue will arise unless Buckeye selects a turbine model other
    than the models listed in its application.        However, the conditions of the
    certificate must be met, and there must be assurances that the turbines will have
    no negative impacts. The conditions under which the proposed turbines have
    been evaluated were based upon a worst-case scenario (the model with the
    greatest potential impact was evaluated), according to staff member Stuart
    Siegfried. If a different model were selected than the one proposed, any potential
    impact necessarily would be lessened. This is hardly a blank check for Buckeye.
    {¶ 25} Furthermore, any choice of turbine model by Buckeye will be a
    matter of public record.       As a board created within the Public Utilities
    Commission of Ohio, R.C. 4906.02, all facts and information in the board’s
    possession “shall be public, and all reports, records, files, books, accounts, papers,
    and memorandums of every nature in its possession shall be open to inspection by
    interested parties or their attorneys.” R.C. 4905.07.
    III. The Board’s Order Should Be Affirmed
    A. The Board’s Order Followed Statutory Requirements
    {¶ 26} The board has exclusive jurisdiction over construction of wind
    farms such as the one proposed by Buckeye. See R.C. 4906.13. Pursuant to R.C.
    4906.12, this court must apply the same standard of review to power-siting
    determinations that it applies to orders of the Public Utilities Commission.
    Accord Chester Twp. v. Power Siting Comm., 
    49 Ohio St.2d 231
    , 238, 
    361 N.E.2d 436
     (1977). “R.C. 4903.13 applies to board proceedings pursuant to R.C. 4906.12
    and provides that an order ‘shall be reversed, vacated, or modified by this court
    only when, upon consideration of the record, the court finds the order to be
    unlawful or unreasonable.’ ” In re Application of Am. Transm. Sys., Inc., 
    125 Ohio St.3d 333
    , 
    2010-Ohio-1841
    , 
    928 N.E.2d 427
    , ¶ 17, quoting Constellation
    NewEnergy, Inc. v. Pub. Util. Comm., 
    104 Ohio St.3d 530
    , 
    2004-Ohio-6767
    , 
    820 N.E.2d 885
    , ¶ 50. We have “ ‘complete and independent power of review as to all
    9
    SUPREME COURT OF OHIO
    questions of law’ ” in appeals from the board. Ohio Consumers’ Counsel v. Pub.
    Util. Comm., 
    121 Ohio St.3d 362
    , 
    2009-Ohio-604
    , 
    904 N.E.2d 853
    , ¶ 13, quoting
    Ohio Edison Co. v. Pub. Util. Comm., 
    78 Ohio St.3d 466
    , 469, 
    678 N.E.2d 922
    (1997).
    {¶ 27} In granting a certificate for the construction, operation, and
    maintenance of a major utility facility, the board must determine eight specific
    points. R.C. 4906.10(A).1 And if the board conditions issuance of a certificate
    1. R.C. 4906.10 states:
    (A) The power siting board shall render a decision upon the record either granting or denying
    the application as filed, or granting it upon such terms, conditions, or modifications of the
    construction, operation, or maintenance of the major utility facility as the board considers
    appropriate. The certificate shall be conditioned upon the facility being in compliance with
    standards and rules adopted under sections 1501.33, 1501.34, and 4561.32 and Chapters 3704.,
    3734., and 6111. of the Revised Code. The period of initial operation under a certificate shall
    expire two years after the date on which electric power is first generated by the facility. During the
    period of initial operation, the facility shall be subject to the enforcement and monitoring powers
    of the director of environmental protection under Chapters 3704., 3734., and 6111. of the Revised
    Code and to the emergency provisions under those chapters. If a major utility facility constructed
    in accordance with the terms and conditions of its certificate is unable to operate in compliance
    with all applicable requirements of state laws, rules, and standards pertaining to air pollution, the
    facility may apply to the director of environmental protection for a conditional operating permit
    under division (G) of section 3704.03 of the Revised Code and the rules adopted thereunder. The
    operation of a major utility facility in compliance with a conditional operating permit is not in
    violation of its certificate. After the expiration of the period of initial operation of a major utility
    facility, the facility shall be under the jurisdiction of the environmental protection agency and shall
    comply with all laws, rules, and standards pertaining to air pollution, water pollution, and solid
    and hazardous waste disposal.
    The board shall not grant a certificate for the construction, operation, and maintenance of a
    major utility facility, either as proposed or as modified by the board, unless it finds and determines
    all of the following:
    (1) The basis of the need for the facility if the facility is an electric transmission line or gas or
    natural gas transmission line;
    (2) The nature of the probable environmental impact;
    (3) That the facility represents the minimum adverse environmental impact, considering the
    state of available technology and the nature and economics of the various alternatives, and other
    pertinent considerations;
    (4) In the case of an electric transmission line or generating facility, that the facility is consistent
    with regional plans for expansion of the electric power grid of the electric systems serving this
    state and interconnected utility systems and that the facility will serve the interests of electric
    system economy and reliability;
    (5) That the facility will comply with Chapters 3704., 3734., and 6111. of the Revised Code and
    all rules and standards adopted under those chapters and under sections 1501.33, 1501.34, and
    4561.32 of the Revised Code. In determining whether the facility will comply with all rules and
    10
    January Term, 2012
    upon modification of the location of the facility, it may add that condition. R.C.
    4906.10(B).2 In this matter, the board issued a detailed 101-page order on March
    22, 2010, granting a certificate to Buckeye for the construction, operation,
    maintenance, and decommissioning of the proposed wind-powered electric
    generation facility as modified by 70 separate conditions.
    {¶ 28} The neighbors maintain that the board’s imposition of six
    conditions—8, 33, 40, 45, 46, and 49—supports a conclusion that the board asked
    the staff to make its decisions, not enforce them. Condition 8 requires Buckeye to
    submit plans for staff review and acceptance. Condition 33 requires Buckeye to
    provide a calculation of “the maximum potential distance for a blade shear event.”
    Conditions 40, 45, and 46 relate to the approval of three turbine sites. And
    condition 49 requires specific identification of the turbine model to be used.
    {¶ 29} If Buckeye provides further information to the board’s staff that
    would require an amendment of the certificate, the board is required to hold a
    hearing on the amendment:
    standards adopted under section 4561.32 of the Revised Code, the board shall consult with the
    office of aviation of the division of multi-modal planning and programs of the department of
    transportation under section 4561.341 of the Revised Code.
    (6) That the facility will serve the public interest, convenience, and necessity;
    (7) In addition to the provisions contained in divisions (A)(1) to (6) of this section and rules
    adopted under those divisions, what its impact will be on the viability as agricultural land of any
    land in an existing agricultural district established under Chapter 929. of the Revised Code that is
    located within the site and alternative site of the proposed major utility facility. Rules adopted to
    evaluate impact under division (A)(7) of this section shall not require the compilation, creation,
    submission, or production of any information, document, or other data pertaining to land not
    located within the site and alternative site.
    (8) That the facility incorporates maximum feasible water conservation practices as determined
    by the board, considering available technology and the nature and economics of the various
    alternatives.
    2. R.C. 4906.10(B) states: “If the board determines that the location of all or a part of the
    proposed facility should be modified, it may condition its certificate upon that modification,
    provided that the municipal corporations and counties, and persons residing therein, affected by
    the modification shall have been given reasonable notice thereof.”
    11
    SUPREME COURT OF OHIO
    On an application for an amendment of a certificate, the
    board shall hold a hearing in the same manner as a hearing is held
    on an application for a certificate if the proposed change in the
    facility would result in any material increase in any environmental
    impact of the facility or a substantial change in the location of all
    or a portion of such facility * * * .
    (Emphasis added.) R.C. 4906.07(B).
    {¶ 30} But the board must retain authority to determine what is subject to
    hearing—surely not every issue (e.g., whether white or gray screws are used in
    the control room), as that would be unworkable. In this case, we conclude that the
    board reasonably drew the line regarding the issuance of the certificate and the
    imposition of its conditions.
    B. Further Hearing Is Unnecessary
    {¶ 31} The dissenters argue that this matter should be remanded for
    further hearing.   It is difficult to understand what additional hearings might
    accomplish. All the issues were debated at length by the parties and witnesses at
    the evidentiary hearing.        Buckeye must comply with the certificate and its
    conditions as imposed by the board. This certificate is based explicitly upon
    public information as set forth in the application and at the hearing. Furthermore,
    we emphasize that the board specifically recognized in its order that “in
    accordance with Section 4906.07, Revised Code, the Board is required to hold a
    hearing in the same manner as on the application, where the amendment of a
    certificate involves any material increase in any environmental impact or
    substantial change in the location of all or a portion of the facility.” Pub. Util.
    Comm. No. 08-666-EL-BGN, at 82. Contrary to the dissenters’ argument, the
    public was provided with a full opportunity for hearing, and further hearings may
    be held if significant changes are made to the certificate.
    12
    January Term, 2012
    {¶ 32} The board’s order allows Buckeye to provide additional
    information on several issues as the construction process evolves. But Buckeye
    must construct its wind farm in accordance with the certificate issued by the
    board. R.C. 4906.98. Penalties may be assessed if Buckeye does not comply
    with the certificate. R.C. 4906.97. We now hold that the board acted within its
    authority in granting Buckeye’s certificate based on its 70 conditions. There is no
    need for delay.
    {¶ 33} The neighbors’ first three propositions of law assert that the
    operational noise limits set by the board are either vague or unreasonable. To the
    contrary, the order sets discernible noise limits. That the standard is flexible
    poses no legal problem—an agency, particularly when facing new issues, may
    proceed on an incremental, case-by-case basis.        See Securities & Exchange
    Comm. v. Chenery Corp., 
    332 U.S. 194
    , 202-203, 
    67 S.Ct. 1575
    , 
    91 L.Ed. 1995
    (1947) (an “agency may not have had sufficient experience with a particular
    problem to warrant rigidifying its tentative judgment into a hard and fast rule,”
    and thus “the agency must retain power to deal with the problems on a case-to-
    case basis if the administrative process is to be effective”). As for the neighbors’
    proposed standards, the testimony of Buckeye’s acoustic consultant showed that
    they were unrealistic and would effectively prohibit the development of wind
    energy in Ohio. Thus, the board properly rejected appellants’ proposals.
    {¶ 34} The neighbors’ fourth proposition contends that the board-
    approved setbacks are not supported by the record, but ample evidence supports
    the order, and numerous conditions in the order will ensure their adequacy. The
    fifth proposition asserts that one of Buckeye’s witnesses lacked sufficient expert
    knowledge to testify regarding technical issues. The neighbors have not shown
    that he lacked expert knowledge or that they were prejudiced. Finally, in its sixth
    proposition, the neighbors assert that the board erred by disallowing the testimony
    13
    SUPREME COURT OF OHIO
    of one of its witnesses. The witness was unable to attend the hearing, and the
    neighbors have not shown that the board erred in requiring his attendance.
    {¶ 35} Finally, the political-subdivision appellants do not present any
    arguments that warrant reversal. The pertinent statutes do not require the county
    engineer to have final say over the amount of any road bond, and evidence
    introduced at the hearing supported the amount required for the decommissioning
    bond.
    IV. Conclusion
    {¶ 36} Pursuant to R.C. 4906.12, we must apply the same standard of
    review to determinations of the Power Siting Board as we do to orders of the
    Public Utilities Commission. Accord Chester Twp., 49 Ohio St.2d at 238, 
    361 N.E.2d 436
    . An order “shall be reversed, vacated, or modified by this court only
    when, upon consideration of the record, the court finds the order to be unlawful or
    unreasonable.” Constellation NewEnergy, Inc., 
    104 Ohio St.3d 530
    , 2004-Ohio-
    6767, 
    820 N.E.2d 885
    , ¶ 50.
    {¶ 37} The General Assembly has enacted statutes to require utilities to
    provide a portion of their electricity supply from alternative energy sources by
    2025. R.C. 4928.64 and 4928.65. Our decision today does not give the board a
    free pass to avoid dealing with controversial or complex issues or to resolve
    issues without public participation or judicial review.          To the contrary, the
    statutory process within R.C. Chapter 4906 is detailed and requires input of
    various stakeholders before a certificate is granted for construction of a new
    electric generation facility. In this case, the board has followed all statutes and
    has based its determinations on the evidence in the record. The board’s decision
    is reasonable and lawful, and the order is therefore affirmed.
    Order affirmed.
    O’CONNOR, C.J., and MCGEE BROWN, J., concur.
    O’DONNELL, J., concurs in judgment only.
    14
    January Term, 2012
    PFEIFER, LUNDBERG STRATTON, and CUPP, JJ., dissent.
    __________________
    PFEIFER, J., dissenting.
    {¶ 38} “Ill blows the wind that profits nobody.” William Shakespeare,
    Henry VI, Part III, Act II, Scene 5.
    {¶ 39} I join Justice Stratton’s dissent. I further dissent because I would
    hold in favor of appellants Champaign County and Goshen, Salem, and Union
    Townships on the decision of the Ohio Power Siting Board (“OPSB”) regarding
    bonding to cover the cost of removing decommissioned windmills.
    {¶ 40} How many windmills does it take to power a light bulb? As many
    as the government will subsidize. It may not be geographically preposterous to
    build windmills in Ohio—not like building a solar energy farm in Upper
    Sandusky—since we do have wind. But for how long will government be willing
    to subsidize a form of energy production that is uneconomical and undependable?
    The mechanical obsolescence of windmills is one matter of concern; that is, what
    will become of these whopping, white whirligigs when they become
    technologically outmoded even in comparison to other windmills?
    {¶ 41} But there is a bigger concern.        The winds that really power
    alternative-energy projects like these, political winds, are also subject to change,
    sometimes abrupt change. From a recent article in the Chicago Tribune:
    The wind power industry is predicting massive layoffs and
    stalled or abandoned projects after a deal to renew a tax credit
    failed Thursday in Washington.
    The move is expected to have major ramifications in states
    such as Illinois, where 13,892 megawatts of planned wind
    projects—enough to power 3.3 million homes per year—are
    seeking to be connected to the electric grid. Many of those projects
    15
    SUPREME COURT OF OHIO
    will be abandoned or significantly delayed without federal
    subsidies.
    Chicago Tribune, End of Tax Credit a Blow for Wind Power Industry,
    http://www.chicagotribune.com/business/ct-biz-0217-wind-ptc-20120217,0,7153
    601.story?page=1 (accessed Feb. 17, 2012).
    {¶ 42} When windmill welfare ends, the companies that build windmills,
    dependent as they are on government largesse and regulation, will disappear.
    Then what? Ohio’s public utilities do not own the windmills—they are just
    forced to purchase the power generated from them—and will thus be under no
    obligation to decommission them. Windmills will become relics, 492-foot-tall
    white elephants, monuments to our quixotic quest for alternative energy. One
    such monument would do the trick; 70 are too many for Champaign County.
    {¶ 43} Granted, in this case we are dealing with the amount of a bond to
    cover the period from the commencement of construction of the windmills
    through the first year. The OPSB set that bond at $5,000 per turbine, despite the
    fact that the board heard testimony from appellants’ expert that decommissioning
    could cost as much as $300,000 per turbine.          But Buckeye Wind’s witness
    testified that it is “inconceivable” that the project will need to be decommissioned
    within the first five years. He uses that word “inconceivable,” but I do not think it
    means what he thinks it means. The technology behind the windmills might
    prove untouchable for five years, but it is entirely conceivable that the bottom
    could drop out of the market for wind power or that Buckeye Wind could fail as a
    company. It would not be the first alternative-energy concern to turn off its lights.
    The question is not whether the turbines work, it’s whether the economics work.
    The answer to our energy future is likely not blowing in the wind.
    {¶ 44} It is incumbent on the OPSB to insist that there is reasonable
    protection   for    the   decommissioning       of   windmills,    whenever      that
    16
    January Term, 2012
    decommissioning might occur. There was no evidence presented at the hearing
    that the $5,000 per turbine required by the OPSB is adequate in any way to
    actually bring down a windmill. No witness testified that that nominal amount
    was sufficient to protect the public interest if the windmills were abandoned.
    {¶ 45} And the public most certainly has an interest that needs protection.
    The interest does not lie just with the homeowners who thought they were buying
    a little piece of rural heaven in Champaign County and now have their pristine
    views obscured. The public at large has an interest because, ultimately, the state
    could be left to deal with the aftermath of a failed experiment.
    {¶ 46} I suspect that this latest generation of windmills will go the way of
    the leisure suit: fashionable for a time, but ultimately causing us to say, “What
    were we thinking?” But there’s no Goodwill store in the world big enough to take
    them off our hands.
    LUNDBERG STRATTON, J., concurs in the foregoing opinion.
    __________________
    LUNDBERG STRATTON, J., dissenting.
    {¶ 47} The Power Siting Board is vested with an important public power,
    and it is frequently called upon to resolve disputes between major utility
    companies and ordinary citizens. Today’s decision allows the board to sidestep
    public scrutiny and judicial review whenever it desires. But the public’s business
    should be done in public, and that is not only common sense, it is the law.
    Therefore, I dissent.
    I. The board and lead opinion have denied the citizens affected
    by this project their only opportunity to be heard.
    {¶ 48} In our state, the power to oversee the construction and operation of
    major utility facilities has been given to one entity alone: the Power Siting Board.
    Local authorities—elected representatives, zoning commissions, county courts—
    have no say over whether, where, or how major power projects may be built and
    17
    SUPREME COURT OF OHIO
    run. R.C. 4906.13. So when the neighboring landowners, appellants in this case,
    learned that Buckeye wanted to build wind turbines the height of skyscrapers only
    a few hundred feet from their land and homes, they went to the board, the only
    place they could go.
    {¶ 49} The neighbors’ investigation of the project turned up some very
    real concerns. Take one for example: Wind turbines are very large machines, and
    machines can break down. One type of breakdown is known as “blade shear,”
    that is, a blade shearing off at the hub. Blade shear would present a serious risk of
    danger, to say the least. The blades are mounted over 300 feet from the ground,
    reach almost 500 feet into the air, and stretch half the length of a football field.
    {¶ 50} Buckeye assured the board that a shorn blade could fly only 500
    feet. That was only 41 feet less than the minimum setback from neighboring
    properties, leaving little margin for error. When the board’s staff asked Buckeye
    for supporting data, it turned out that Buckeye’s prediction pertained to a
    different, smaller turbine, and the company informed staff that “no such
    calculation existed” for the proposed turbines.        Nevertheless, despite lacking
    either evidence or sufficient competence in physics even to attempt to calculate
    the distance a blade could fly, the staff member responsible signed off on
    Buckeye’s proposal. His portion of the investigatory report stated, “Staff believes
    that the Applicant has adequately evaluated and described the potential impact
    from blade shear at the nearest property boundary.”
    {¶ 51} Understandably, the neighbors neither were satisfied with this
    investigation nor wanted to be the guinea pigs in a blade-shear experiment, so
    they took this issue to the board. But the board, rather than withhold approval of
    the project until safe setbacks were determined, approved the project. It simply
    required Buckeye to provide staff, and no one else, with the “formula” used to
    calculate the distance a blade could be thrown. Since this same staff had lacked
    the competence to even attempt such a calculation in the first place, it is open to
    18
    January Term, 2012
    question what good providing such a formula would do. And the board did not
    require Buckeye or staff to share the formula with other parties, to file it in the
    public record, or otherwise to resubmit the issue for review, so no one else would
    ever be entitled to scrutinize Buckeye’s calculations.
    {¶ 52} Thus, even though this appeal represents the final review of the
    final order of the board, we have no evidence that the project is being built safely
    away from yards and homes, and we never will. Yet the lead opinion affirms the
    order.3
    {¶ 53} The law requires otherwise. The legislature has required the board
    to settle issues like this up front on a public record, and it specifically guarantees
    affected citizens the right to participate in the review process and to have their
    voices heard. See R.C. 4906.07 (requiring that the board hold public hearings),
    4906.08(A)(3) (neighboring citizens are entitled both to party status and to call
    and examine witnesses), 4906.09 (requiring the board to keep a record of its
    proceedings), 4906.10(A) (requiring the board to make all substantive
    determinations before authorizing construction), and 4906.11 (requiring the board
    to issue a written opinion stating the reasons for its decisions). Issues are not to
    be settled after construction is approved, much less by unaccountable staff
    members without public scrutiny or judicial review. Yet that is precisely what
    the board, and now the lead opinion, has allowed.
    3. This is not the only major issue that the board left unresolved. Among other things, the board
    approved this project but allowed its staff to approve new locations for several turbines. It also
    allowed Buckeye to use new turbines that had not been examined at hearing—even though
    Buckeye’s own witness had admitted on the record that if a different turbine were used than the
    ones that he had studied, his “whole analysis would have to be rerun.”
    19
    SUPREME COURT OF OHIO
    II. The lead opinion does not offer any workable response
    to the denial of the citizens’ right to a public hearing.
    {¶ 54} The lead opinion suggests there are three remedies now available
    to the neighbors, but none of them cures the problem. The lead opinion ignores
    the solution plainly required by law: give the neighbors their hearing.
    A. The order plainly permits nonpublic proceedings.
    {¶ 55} First, the lead opinion states that “[n]othing in the order suggests
    that [staff’s] actions would occur secretly.” That is simply not true. Each one of
    the issues challenged by appellants as improperly delegated allows the staff to
    resolve those issues either alone or in consultation with Buckeye alone. In re
    Application of Buckeye Wind, Pub. Util. Comm. No. 08-666-EL-BGN, at 83-84
    (2010) (collection system plan, complaint procedures, and other issues), 90 (Blade
    throw), 91 (relocation of turbines), and 92 (turbine model). The order does not
    require that notice be given of the time and place of any meeting with Buckeye.
    The order does not require records to be kept of these meetings. The order does
    not require that other parties be allowed to attend. The order does not require that
    materials shared at these meetings be shared with other parties. The order does
    not require that decisions be put in writing. The order does not require further
    review by the board. And the effect of all this is to avoid any further review by
    this court.
    {¶ 56} This suggests secrecy in any meaningful sense. The lead opinion
    points to no provisions that cut the other way, i.e., that allow third-party
    participation or review. Although the board did not affirmatively order that its
    staff meet with Buckeye alone at an undisclosed time and place without keeping
    records or putting decisions in writing, it has allowed such secret meetings to
    occur.
    20
    January Term, 2012
    B. The statute cited in the lead opinion offers the neighbors no protection.
    {¶ 57} The lead opinion also suggests that the neighbors will have
    additional process before the board. But the order and the statutes point the other
    way.
    {¶ 58} The lead opinion claims that the board did not foreclose the
    neighbors from providing input. This is not true. In fact, the portion of the order
    quoted by the lead opinion makes precisely the opposite point, stating that the
    neighbors have already had their chance: “Any party to a certificate application
    has an opportunity, as [the group of neighbors] has done in this matter, to oppose
    staff’s recommended conditions or to propose additional conditions.” (Emphasis
    added.) The board’s appellate brief confirms this point. Rather than assure us
    that the neighbors will have any additional process, the board asserts that they
    have received “all [the process] that is required.”
    {¶ 59} The lead opinion also states that there are statutes that give the
    neighbors “the right to file before the board if Buckeye violates its certificate.” It
    cites R.C. 4906.07, but that section does not authorize the neighbors to do
    anything; it authorizes Buckeye to file “an application for an amendment of a
    certificate.” Buckeye will never need to amend its certificate as far as the issues
    delegated to the staff are concerned. The certificate does not create a substantive
    standard to govern the project, but simply requires meetings with staff. So long as
    Buckeye meets with staff, it will not—it cannot—run afoul of the pertinent parts
    of its certificate. Where there is no rule, there can be no violation, and there will
    be no need for an amendment.
    {¶ 60} Two other statutes, R.C. 4906.97 and 4906.98, do authorize the
    neighbors to complain to the board if Buckeye builds or runs its project “other
    than in compliance with the certificate [it] has obtained.” R.C. 4906.98(B). But
    the same problem presents itself; as to the issues delegated to the staff, the
    certificate does not create any standard to govern the project. It simply requires a
    21
    SUPREME COURT OF OHIO
    meeting with staff. Once Buckeye meets with staff, it has complied with the
    certificate, the staff’s decisions will be implemented, and any complaint for a
    violation of the certificate would fail.
    {¶ 61} Finally, even if the neighbors did have some mechanism to
    challenge staff’s decisions in the future, that remedy would not justify
    disregarding the neighbors’ right to a hearing now. Realistically, overturning a
    decision after it has been made and implemented presents a higher hurdle than
    swaying a decision up front—it is always harder to unring the bell. And if the
    neighbors were somehow to prevail on a postconstruction complaint, this could
    impose significant costs on Buckeye.
    {¶ 62} Suppose that Buckeye chooses a different turbine than the model
    analyzed at hearing; the order allows Buckeye to do so on the simple condition
    that it “provide assurances that no additional negative impacts would be
    introduced.”4 Suppose that despite Buckeye’s assurances, the new turbine turns
    out to be loud enough that it violates the noise standards in the certificate. The
    neighbors would be legally entitled to have the turbines shut down, replaced, or
    removed. But surely the more efficient, cost-effective outcome would have been
    to analyze and reject the offending model before it was purchased and installed.
    C. R.C. 4906.10(A) requires the board to resolve relevant,
    material issues before it grants a certificate.
    {¶ 63} Finally, the lead opinion states that R.C. 4906.10(A) does not
    require that issues be “finally resolved by the board before a certificate may be
    issued.” This simply ignores the language of the statute.
    {¶ 64} R.C. 4906.10(A) states, “The board shall not grant a certificate
    * * *, either as proposed or as modified by the board, unless it” makes the
    4. In fairness, Buckeye also had to provide staff with copies of the safety manual and
    manufacturer contact information.
    22
    January Term, 2012
    required findings and determinations. The default position is “shall not grant,”
    and that only changes when the board makes its findings and determinations. All
    of the issues delegated by the board related to one or more of those necessary
    findings. So, contrary to the lead opinion’s statement, the law required these
    issues to be resolved before the certificate is issued.
    {¶ 65} The irony here is that the lead opinion, in making these points,
    seems to recognize that allowing unaccountable staff members to resolve issues in
    private is a problem. But it offers no workable solution to that problem. The
    necessary solution is simply to reverse the order and require that accountable
    persons resolve these issues after following the public process required by law.
    III. Today’s decision renders ineffectual the laws designed to
    protect the interests of citizens living near proposed utility projects.
    {¶ 66} The outcome of this decision is unfortunate for anyone living near
    the site of a proposed high-voltage transmission line, electric substation, high-
    pressure gas pipeline, or generation plant. If the board runs into an issue that for
    whatever reason it does not want to deal with—or if it simply prefers to resolve an
    issue without the discomfort of public participation and judicial review—it now
    has a broad off-ramp. Approve the project now; work out the details with the
    company later. The public retains a formal right to participate, but it is up to the
    board whether that right amounts to anything more than a formality.
    {¶ 67} This is not alarmist but precisely what happened in this case. If, as
    it did in this case, the power siting board can delegate the very siting of
    facilities—its core duty, the duty from which the power siting board derives its
    name—it can delegate anything and everything. The lead opinion identifies no
    enforceable limits on the board’s power to delegate but apparently trusts that the
    board will exercise its new discretion wisely.            One can hope that the lead
    opinion’s trust proves well founded, but in my view, the public’s business should
    not be left to the unreviewable discretion of appointed staff members who are not
    23
    SUPREME COURT OF OHIO
    accountable to the public. The board’s decisions should have to see and bear the
    light of day.
    {¶ 68} For these reasons, I dissent, and I would reverse the order and
    remand this case for completion of the public proceeding required by law.
    PFEIFER and CUPP, JJ., concur in the foregoing opinion.
    __________________
    Van Kley & Walker, L.L.C., Jack Van Kley, and Christopher A. Walker,
    for appellants Union Neighbors United, Robert McConnell, Diane McConnell,
    and Julia F. Johnson.
    Nick A. Selvaggio, Champaign County Prosecuting Attorney, and Jane A.
    Napier, Assistant Prosecuting Attorney, for appellants Champaign County and
    Goshen, Salem, and Union Townships.
    Michael DeWine, Attorney General, and William L. Wright, Werner L.
    Margard III, and John H. Jones, Assistant Attorneys General, for appellee.
    Vorys, Sater, Seymour & Pease, L.L.P., M. Howard Petricoff, Stephen M.
    Howard, and Michael J. Settineri, for intervening appellee, Buckeye Wind, L.L.C.
    Larry Gearhardt, Chad A. Endsley, and Leah F. Finney, urging affirmance
    for amicus curiae, Ohio Farm Bureau Federation.
    ______________________
    24
    

Document Info

Docket Number: 2010-1554

Citation Numbers: 2012 Ohio 878, 131 Ohio St. 3d 449

Judges: Brown, Cupp, Lanzinger, Lundberg, McGee, O'Connor, O'Donnell, Pfeifer, Stratton

Filed Date: 3/6/2012

Precedential Status: Precedential

Modified Date: 8/31/2023