State ex rel. AWMS Water Solutions, L.L.C. v. Mertz (Slip Opinion) , 2020 Ohio 4509 ( 2020 )


Menu:
  • [Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as State
    ex rel. AWMS Water Solutions, L.L.C. v. Mertz, Slip Opinion No. 2020-Ohio-4509.]
    NOTICE
    This slip opinion is subject to formal revision before it is published in an
    advance sheet of the Ohio Official Reports. Readers are requested to
    promptly notify the Reporter of Decisions, Supreme Court of Ohio, 65
    South Front Street, Columbus, Ohio 43215, of any typographical or other
    formal errors in the opinion, in order that corrections may be made before
    the opinion is published.
    SLIP OPINION NO. 2020-OHIO-4509
    THE STATE EX REL. AWMS WATER SOLUTIONS, L.L.C., ET AL., APPELLANTS,
    v. MERTZ,1 DIR., ET AL., APPELLEES.
    [Until this opinion appears in the Ohio Official Reports advance sheets, it
    may be cited as State ex rel. AWMS Water Solutions, L.L.C. v. Mertz, Slip
    Opinion No. 2020-Ohio-4509.]
    Oil and gas—Regulatory takings—Summary judgment—Genuine issues of material
    fact exist regarding whether state’s suspension of operations at private
    company’s       saltwater-injection       well    constituted     total    or    partial
    governmental taking of property—Judgment reversed and cause remanded.
    (No. 2019-0493—Submitted April 7, 2020—Decided September 23, 2020.)
    APPEAL from the Court of Appeals for Trumbull County, No. 2016-T-0085,
    2019-Ohio-923.
    _________________
    1. James Zehringer, the former director of the Ohio Department of Natural Resources (“ODNR”),
    was originally named as a respondent in this case. Mary Mertz has since replaced Zehringer as
    ODNR’s director.
    SUPREME COURT OF OHIO
    FISCHER, J.
    {¶ 1} In this regulatory-takings case, appellants, AWMS Water Solutions,
    L.L.C.; AWMS Holdings, L.L.C.; and AWMS, Rt. 169, L.L.C. (collectively,
    “AWMS”), filed a petition for a writ of mandamus in the Eleventh District Court
    of Appeals to compel appellees, the Ohio Department of Natural Resources
    (“ODNR”); ODNR’s director, Mary Mertz; ODNR’s Division of Oil and Gas
    Resources Management (“the division”); and the division’s chief, Richard Simmers
    (collectively, “the state”), to initiate property-appropriation proceedings. AWMS
    alleged that it had suffered a taking of its property when the division suspended
    AWMS’s operation of one of its two saltwater-injection wells. The division
    suspended the operation of the well because of concerns that the well had induced
    a pair of earthquakes in its vicinity. The Eleventh District granted summary
    judgment to the state and denied the writ, determining that AWMS had suffered
    neither a total nor a partial governmental taking.
    {¶ 2} Regulatory-takings cases present “complex and difficult” questions
    that often elude a “simple solution.” State ex rel. R.T.G., Inc. v. State, 98 Ohio
    St.3d 1, 2002-Ohio-6716, 
    780 N.E.2d 998
    , ¶ 1 (plurality opinion). This case is no
    different. As we will explain below, the court of appeals erred by entering summary
    judgment in favor of the state when genuine issues of material fact remained
    regarding whether AWMS had suffered a total or partial taking. Accordingly, we
    reverse the Eleventh District’s judgment and remand this cause to the court of
    appeals for further proceedings consistent with this opinion.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    A. AWMS obtains permits to drill and inject wells, earthquakes ensue, and
    the division suspends the operation of one of AWMS’s wells
    {¶ 3} On December 19, 2011, AWMS, a disposer of waste from oil-and-gas
    production and drilling sites, secured a leasehold right to operate one or more Class
    II saltwater-injection wells on 5.2 acres of industrial property in Weathersfield
    2
    January Term, 2020
    Township, Trumbull County, Ohio. A Class II saltwater-injection well is used for
    the purpose of disposing of saltwater, a byproduct of oil- and natural-gas
    production. A saltwater-injection well is designed to isolate the injected fluid in a
    specific formation and prevent the contamination of freshwater. United States
    Environmental Protection Agency, Class II Oil and Gas Related Injection Wells,
    https://www.epa.gov/uic/class-ii-oil-and-gas-related-injection-wells#dw_protect
    (accessed Sept. 14, 2020) [https://perma.cc/CH23-MYWS]. The lease obligated
    AWMS to pay the lessor a 5 percent royalty on its disposal revenue.
    {¶ 4} On December 23, 2011, AWMS applied to the division for permits to
    construct and operate two wells on the site: “well #1” and “well #2.” The next day,
    a 2.7-magnitude earthquake was recorded in Youngstown, Ohio, about seven miles
    from AWMS’s Weathersfield Township site and about one mile from an injection
    well known as “Northstar #1” that was not related to AWMS’s wells. On December
    30, 2011, the division decided that Northstar #1 should be “shut in”—that is, taken
    out of operation. On December 31, 2011, a 4.0-magnitude earthquake was recorded
    within one mile of Northstar #1. That earthquake was felt by over 4,000 people in
    parts of northeastern Ohio, western Pennsylvania, and Ontario, Canada. The
    division later issued a report in which it found that a “compelling argument” existed
    linking the activities at Northstar #1 to the two December 2011 earthquakes.
    {¶ 5} To put these events in context, we note that the United States
    Geological Survey estimates that more than one million earthquakes of magnitude
    2.0 or greater occur naturally per year globally. Ground Water Protection Council
    & Interstate Oil & Gas Compact Commission, Potential Injection-Induced
    Seismicity Associated with Oil & Gas Development: A Primer on Technical and
    Regulatory Considerations Informing Risk Management and Mitigation 44 (2015),
    http://www.gwpc.org/sites/default/files/finalprimerweb.pdf (accessed Sept. 14,
    2020) [https://perma.cc/H9SS-FVKF]. Earthquakes of about magnitude 2.0 or less
    are called “microseismic events” because they usually cannot be felt by people.
    Id. 3
                                   SUPREME COURT OF OHIO
    Buildings usually do not suffer structural damage unless an earthquake in their
    vicinity reaches a magnitude of 5.0, although nonstructural damage can occur to a
    building during a 4.0-magnitude earthquake depending on the building’s age and
    the materials used to construct it.
    Id. at
    50. 
    AWMS’s expert witness on seismicity,
    Michael A. Hasting, testified at a March 2015 hearing in this case that Ohio
    probably experiences a couple of 2.0-magnitude earthquakes per day.
    {¶ 6} Immediately after the December 31, 2011 earthquake occurred,
    former Governor John Kasich imposed a moratorium on certain injection-well
    activities, thereby enabling the division to study whether the earthquakes were due
    to “induced seismicity,” a term used to describe earthquakes triggered by human
    activity.   Thereafter, the division adopted rules regarding induced seismicity,
    developed a seismic monitoring network, hired a seismologist, and participated in
    workgroups to enhance its understanding of induced seismicity.
    {¶ 7} The former governor’s moratorium delayed the processing of
    AWMS’s application for its operating permits. But on July 18, 2013, the division
    authorized AWMS to drill wells #1 and #2. AWMS spent approximately $5.6
    million constructing its facilities, which included the costs of wells #1 and #2,
    infrastructure, drilling, tanks, pumps, installation, and start-up. Well #2, the deeper
    of the two wells, was drilled to a depth of 8,502 feet, which enabled it to accept 95
    percent of total injections.
    {¶ 8} In September 2013, AWMS prepared a “confidential offering
    memorandum” for prospective investors in which it offered membership shares for
    $50,000 each. AWMS disclosed several investment risks in the memorandum,
    including that the government’s regulation of injection wells could increase in
    scope and complexity due to growing industry awareness, that AWMS’s wells
    could cause a seismic event similar to the events that had occurred in Youngstown,
    and that a seismic event caused by AWMS’s wells could lead to the suspension of
    its injection operations.
    4
    January Term, 2020
    {¶ 9} On March 24, 2014, the division authorized AWMS to commence
    injections into wells #1 and #2. AWMS’s permits did not contain express language
    empowering the division to suspend AWMS’s operations due to a seismic event of
    a specific magnitude.
    {¶ 10} The risks that AWMS outlined in its offering memorandum turned
    out to be well founded. On July 28, 2014, a 1.7-magnitude earthquake was recorded
    near well #2. And on August 31, 2014, a 2.1-magnitude earthquake was recorded
    in the same area. The Ohio Oil and Gas Commission (“the commission”) later
    determined that the “July and August events were not detectable on the surface, and
    no property damage was reported.”
    {¶ 11} On September 3, 2014, the division issued orders requiring AWMS
    to suspend its operations at wells #1 and #2, stating that the two earthquakes from
    July and August 2014 were related to AWMS’s operations at the wells. The
    division also required AWMS to “submit a written plan to the Division for
    evaluating the seismic concerns associated with the operation of” well #2. Two
    days later, the division issued new orders clarifying that the seismic events “may”
    have been related to AWMS’s wells. The division later determined that well #1
    likely did not contribute to seismicity in the area, terminated its suspension of
    operations at well #1, and allowed AWMS to resume operations at well #1. It left
    the suspension of operations at well #2 in place.
    {¶ 12} On September 17, 2014, AWMS submitted to the division its written
    plan for well #2. In its plan, AWMS explained that it had not received direction
    from the division about what to include in the plan. Nevertheless, AWMS’s plan
    included several proposals addressing the division’s concerns, including a proposal
    to establish certain operational and management controls over injections at well #2.
    The division found AWMS’s plan to be “generic and inadequate.”
    {¶ 13} On October 2, 2014, AWMS appealed the division’s suspension of
    operations at well #2 to the commission. During the pendency of the appeal,
    5
    SUPREME COURT OF OHIO
    AWMS and the division held two meetings during which they discussed the
    induced-seismicity issue. In the first meeting, which took place near the end of
    October 2014, the division communicated to AWMS that it was planning to adopt
    a statewide policy on induced seismicity that it expected to be completed in “four
    to six” months. According to Stephen G. Kilper, vice president of AWMS, the
    division stated at that meeting that it was not prepared to address the suspension
    order regarding well #2 or AWMS’s plan until the statewide policy was in place.
    {¶ 14} In the second meeting, which was held near the end of February
    2015, the division presented AWMS a single sheet of paper containing 14 criteria
    that the division was considering for evaluating induced seismicity in its statewide
    policy. According to Kilper, the division stated at that meeting that it would not
    implement the statewide induced-seismicity policy for at least eight months and
    that it would not recommend a policy to ODNR unless the policy “guaranteed zero
    risk.”
    {¶ 15} A few days after the February 2015 meeting, AWMS sent an e-mail
    to the division seeking clarification of some of the division’s proposed criteria, to
    which Robert Worstall, deputy chief of the division, responded that AWMS should
    propose whatever it thought was appropriate. In early March 2015, AWMS
    submitted a plan to the division addressing the division’s proposed criteria.
    Nothing in the record suggests that the division responded to AWMS’s plan.
    B. Administrative and judicial proceedings regarding the division’s
    suspension order
    {¶ 16} On August 12, 2015, the commission issued a decision affirming the
    division’s suspension of operations at well #2. The commission noted that two of
    AWMS’s expert witnesses had testified that the seismic events in July and August
    2014 were likely associated with well #2. The commission also observed that while
    both experts had opined that operations at well #2 could be safely resumed subject
    to certain conditions, neither could state that the division’s suspension order was
    6
    January Term, 2020
    unreasonable under the circumstances that had led to the order. Turning to the
    testimony of Simmers, the division’s chief, the commission noted that he favored a
    temporary cessation of injections at well #2 pending further investigation and the
    implementation of a statewide policy on induced seismicity.
    {¶ 17} In upholding the suspension order, the commission acknowledged
    that under the circumstances, the division could be perceived as acting slowly in
    implementing a statewide policy to address induced seismicity.                But the
    commission stressed that regulating induced seismicity caused by saltwater
    injection is a “complicated process that does not happen overnight.”              The
    commission also determined that while there had been no evidence presented
    establishing that AWMS had violated the terms and conditions of its permit, the
    absence of a violation could not justify its lifting the suspension in light of the
    division’s determination that further injection operations at well #2 could result in
    imminent danger to public health and safety or damage to the environment.
    {¶ 18} AWMS appealed the commission’s order to the Franklin County
    Court of Common Pleas, which vacated the order. The court determined that
    although the division had the authority to issue the suspension order, the division’s
    failure to respond to AWMS’s plan for resuming operations was unreasonable. The
    court stated, “[I]t defies logic as to how [the division] can expect [AWMS] to
    formulate and submit a comprehensive plan that would comply with a statewide
    policy that has yet to be formulated and completed.” The court then ordered the
    parties to submit proposed plans for restarting operations at well #2, which both
    parties did. Thereafter, the court ordered that operations at well #2 could be
    restarted under certain conditions, including that AWMS would cease injection
    operations if an imminent threat to public safety and health or to the environment
    occurred at or near the well. In the event of such a threat, the court’s order dictated
    that operations could not be restarted unless two AWMS representatives and two
    commission representatives determined that the threat had passed.
    7
    SUPREME COURT OF OHIO
    {¶ 19} The division appealed the common pleas court’s judgment to the
    Tenth District Court of Appeals. In a two-to-one decision, the court of appeals
    affirmed in part, reversed in part, and after modifying the common pleas court’s
    judgment, affirmed the commission’s decision and reimposed the suspension of
    operations at well #2. Am. Water Mgt. Servs., L.L.C. v. Div. of Oil and Gas
    Resources Mgt., 2018-Ohio-3028, 
    118 N.E.3d 385
    , ¶ 59-60 (10th Dist.) (“AWMS
    I”). The court of appeals held that the common pleas court had erred in requiring
    two commission members to determine that an imminent threat had passed before
    operations at well #2 could be restarted.
    Id. at
    ¶ 28-31. The court of appeals also
    held that the court had erred in drawing certain conclusions from the record about
    the seismic risks posed by restarting operations at well #2.
    Id. at
    ¶ 39-49. AWMS
    appealed the judgment in AWMS I to this court, which denied AWMS’s
    discretionary appeal, see 
    154 Ohio St. 3d 1431
    , 2018-Ohio-4670, 
    111 N.E.3d 1192
    ,
    and subsequent motion for reconsideration, see 
    154 Ohio St. 3d 1467
    , 2018-Ohio-
    5209, 
    114 N.E.3d 216
    .
    C. AWMS’s mandamus action
    {¶ 20} On August 26, 2016, while AWMS’s appeal in AWMS I was
    pending, AWMS filed a petition for a writ of mandamus in the Eleventh District to
    compel the state to commence property-appropriation proceedings. AWMS alleged
    that the suspension order effected a governmental taking of its property requiring
    the state to pay AWMS just compensation. In support, AWMS argued that it had
    complied with the relevant law and AWMS’s permit conditions, had not
    endangered public health and safety or the environment, and had been subjected to
    a “permanent shutdown” (rather than a temporary suspension) of its operations.
    AWMS emphasized that its mandamus action was not an attempt to challenge the
    suspension order.
    {¶ 21} The state moved for summary judgment, asserting that AWMS had
    failed to establish that a taking occurred. After the Tenth District issued its decision
    8
    January Term, 2020
    in AWMS I, the Eleventh District granted the state’s summary-judgment motion and
    denied AWMS’s mandamus petition, 2019-Ohio-923, 
    132 N.E.3d 1151
    , ¶ 50-51.
    First, the Eleventh District determined that the state had not effected a total
    regulatory taking because AWMS had not been deprived of all economically
    beneficial use of its property. In support, it reasoned that after the state had
    suspended operations at well #2, well #1 remained in operation for a period of time;
    that AWMS had derived revenue from processing, storing, recycling, treating, and
    disposing brine; that third parties had contacted AWMS about using the property;
    and that AWMS could put the property to other uses related to the oil-and-gas
    industry.
    Id. at
    ¶ 15-17. Second, the court of appeals determined that the state had
    not effected a partial regulatory taking. The court found it significant that the
    suspension order had been designed to “protect[] the public’s health and safety from
    the realistic potential of increased induced seismicity resulting from injection
    activities” at well #2.
    Id. at
    ¶ 40. 
    It also found it significant that AWMS’s investors
    had been aware of the seismic activities in the Youngstown area and of the risks
    involved with the operation of AWMS’s injection wells.
    Id. at
    ¶ 44, 49.
    {¶ 22} AWMS appealed the Eleventh District’s judgment to this court.
    II. APPLICABLE LEGAL STANDARDS
    A. Summary-judgment standard
    {¶ 23} This court reviews a grant of summary judgment de novo. Ratonel
    v. Roetzel & Andress, L.P.A., 
    147 Ohio St. 3d 485
    , 2016-Ohio-8013, 
    67 N.E.3d 775
    ,
    ¶ 18. Under Civ.R. 56(C), summary judgment is appropriate when (1) there is no
    genuine issue of material fact, (2) the moving party is entitled to judgment as a
    matter of law, and (3) it appears that after construing the evidence most strongly in
    the nonmoving party’s favor that reasonable minds can come to but one conclusion.
    “Neither we nor the trial court may weigh the proof or choose among reasonable
    inferences in deciding whether summary judgment should be granted.” Perez v.
    Scripps-Howard Broadcasting Co., 
    35 Ohio St. 3d 215
    , 218, 
    520 N.E.2d 198
    9
    SUPREME COURT OF OHIO
    (1988). At the summary-judgment stage, a “court should not reject one expert
    opinion for another simply because it believes one theory over the other.” Miller
    v. Bike Athletic Co., 
    80 Ohio St. 3d 607
    , 613, 
    687 N.E.2d 735
    (1998).
    B. Mandamus standard
    {¶ 24} To prevail on its mandamus claim, AWMS must show (1) a clear
    legal right to compel the state to commence property-appropriation proceedings,
    (2) a clear legal duty on the part of the state to institute that action, and (3) the lack
    of an adequate remedy in the ordinary course of the law. State ex rel. Gilmour
    Realty, Inc. v. Mayfield Hts., 
    122 Ohio St. 3d 260
    , 2009-Ohio-2871, 
    910 N.E.2d 455
    , ¶ 15. “Mandamus is the appropriate action to compel public authorities to
    commence appropriation cases when an involuntary taking of private property is
    alleged.” State ex rel. Shelly Materials, Inc. v. Clark Cty. Bd. of Commrs., 
    115 Ohio St. 3d 337
    , 2007-Ohio-5022, 
    875 N.E.2d 59
    , ¶ 15.
    C. Regulatory-takings doctrine
    {¶ 25} AWMS has asserted that it is entitled to compensation for the state’s
    regulatory taking of its property under the Takings Clause of the Fifth Amendment
    to the United States Constitution. The Takings Clause provides that private
    property shall not “be taken for public use, without just compensation.” The clause
    applies to the states through the Fourteenth Amendment. Chicago, Burlington &
    Quincy RR. Co. v. Chicago, 
    166 U.S. 226
    , 239-241, 
    17 S. Ct. 581
    , 
    41 L. Ed. 979
    (1897).
    {¶ 26} We acknowledge that “ ‘[e]very sort of [real property] interest the
    citizen may possess’ counts as a property interest under the Fifth Amendment.”
    (Brackets sic.)      Cienega Gardens v. United States, 
    331 F.3d 1319
    , 1329
    (Fed.Cir.2003) (“Cienega Gardens I”), quoting United States v. Gen. Motors Corp.,
    
    323 U.S. 373
    , 378, 
    65 S. Ct. 357
    , 
    89 L. Ed. 311
    (1945). Accordingly, “the holder of
    an unexpired leasehold interest in land is entitled” to invoke the Takings Clause’s
    10
    January Term, 2020
    guarantees. Alamo Land & Cattle Co., Inc. v. Arizona, 
    424 U.S. 295
    , 303, 
    96 S. Ct. 910
    , 
    47 L. Ed. 2d 1
    (1976).
    {¶ 27} AWMS has also referred to its right to compensation for the state’s
    alleged taking of its property under the Ohio Constitution. “Section 19, Article I
    of the Ohio Constitution also provides that private property shall not be taken for
    public use without just compensation.” Shelly Materials, 
    115 Ohio St. 3d 337
    ,
    2007-Ohio-5022, 
    875 N.E.2d 59
    , at ¶ 16. Although AWMS makes a passing
    reference to that provision, its substantive arguments rely on Fifth Amendment
    takings jurisprudence so we focus our analysis here on that jurisprudence.
    {¶ 28} Although the federal Takings Clause had been originally understood
    to apply only to situations involving the direct appropriation of property or the
    functional equivalent of a practical ouster of an owner’s possession, Lucas v. South
    Carolina Coastal Council, 
    505 U.S. 1003
    , 1014, 
    112 S. Ct. 2886
    , 
    120 L. Ed. 2d 798
    (1992) (collecting cases), the United States Supreme Court has recognized that the
    clause may also be applied to overly burdensome governmental regulations of
    property, Pennsylvania Coal Co. v. Mahon, 
    260 U.S. 393
    , 415, 
    43 S. Ct. 158
    , 
    67 L. Ed. 322
    (1922) (“while property may be regulated to a certain extent, if regulation
    goes too far it will be recognized as a taking”). Since Mahon, principles have been
    established for identifying regulations that go too far. See Lingle v. Chevron U.S.A.,
    Inc., 
    544 U.S. 528
    , 538-540, 
    125 S. Ct. 2074
    , 
    161 L. Ed. 2d 876
    (2005).
    {¶ 29} Two of those principles bear on this case.            The first is the
    “categorical rule” discussed in Lucas, which applies to “total regulatory takings.”
    Lucas at 1026. Under that rule, the government’s payment of just compensation is
    required when its regulation “deprives land of all economically beneficial use,”
    id. at 1027,
    unless “background principles of the State’s law of property and nuisance”
    impose independent restrictions on the owner’s usage
    , id. at 1029.
    The second
    principle derives from the Supreme Court’s decision in Penn Cent. Transp. Co. v.
    New York City, 
    438 U.S. 104
    , 
    98 S. Ct. 2646
    , 
    57 L. Ed. 2d 631
    (1978), which applies
    11
    SUPREME COURT OF OHIO
    to “ ‘partial’ regulatory taking[s],” Shelly Materials at ¶ 19. The ad hoc, fact-
    specific analysis established in Penn Cent. requires a court to consider three factors:
    “(1) the economic impact of the regulation on the claimant, (2) the extent to which
    the regulation has interfered with distinct investment-backed expectations, and (3)
    the character of the governmental action.”
    Id. III.
    ANALYSIS
    {¶ 30} We begin our analysis by addressing two preliminary questions, the
    answers to which will influence our regulatory-takings analysis. First, we consider
    the state’s argument that this case is unripe. Second, we consider the state’s
    argument that it effected at most a temporary suspension, rather than a permanent
    shutdown, of well #2. After addressing those questions, we turn to the main issue
    in this case, i.e., whether the state effected either a total taking of well #2 under the
    standard established in Lucas or a partial taking of it under the standard established
    in Penn Cent.
    A. Ripeness
    {¶ 31} The state faults AWMS for having failed to submit a comprehensive
    plan for restarting operations at well #2, stating that it “stands by willing to allow
    operation of the AWMS #2 Well if [AWMS] submits a comprehensive plan
    protective of public health and safety.” (Emphasis sic.) Although the state does
    not precisely identify a legal doctrine in support of its argument, the crux of its
    position, as we understand it, is that AWMS’s takings claim is unripe.
    {¶ 32} “[A] claim that the application of government regulations effects a
    taking of a property interest is not ripe until the government entity charged with
    implementing the regulations has reached a final decision regarding the application
    of the regulations to the property at issue.” Williamson Cty. Regional Planning
    Comm. v. Hamilton Bank of Johnson City, 
    473 U.S. 172
    , 186, 
    105 S. Ct. 3108
    , 
    87 L. Ed. 2d 126
    (1985), overruled on other grounds, Knick v. Twp. of Scott, ___ U.S.
    ___, 
    139 S. Ct. 2162
    , 2179, 
    204 L. Ed. 2d 558
    (2019). “Where further administrative
    12
    January Term, 2020
    process could reasonably result in a more definite statement of the impact of the
    regulation, the property owner is generally required to pursue that avenue of relief
    before bringing a takings claim.” Morris v. United States, 
    392 F.3d 1372
    , 1376
    (Fed.Cir.2004).
    {¶ 33} The “[r]ipeness doctrine does not,” however, “require a landowner
    to submit applications for their own sake.” Palazzolo v. Rhode Island, 
    533 U.S. 606
    , 622, 
    121 S. Ct. 2448
    , 
    150 L. Ed. 2d 592
    (2001). Accordingly, “[a] failure to
    secure a final decision may be excused under the futility exception, ‘where [an]
    agency’s decision makes clear that pursuing remaining administrative remedies
    will not result in a different outcome.’ ” (Second bracket sic.) Freeman v. United
    States, 
    875 F.3d 623
    , 628 (Fed.Cir.2017), quoting Morris at 1376. “A landowner
    need not resort to futile piecemeal litigation or submit to repetitive application
    requirements to make a taking claim ripe.” Cooley v. United States, 
    324 F.3d 1297
    ,
    1302 (Fed.Cir.2003). Because a takings claim is ripe after a governmental entity’s
    final decision, “an applicant need not submit further applications” before it can
    pursue its claim.
    Id. at
    1302-1303.
    
           {¶ 34} In this case, the state suggests that if AWMS would submit a restart
    plan for well #2 that meets the standards it set out during the parties’ common-
    pleas-court litigation (standards the state settled on after AWMS filed its mandamus
    petition), then AWMS would be able to restart its operations. Broadly speaking,
    the state’s standards outlined a five-step restart plan directing AWMS to (1) gather
    information, (2) perform well-construction modifications, (3) install monitoring
    equipment, (4) perform pre-operation testing, and (5) follow a schedule of
    operations with defined injection pressures and maximum amounts to be injected,
    subject to modifications or the suspension of operations depending on seismicity in
    the area of well #2.
    {¶ 35} The state ignores that AWMS twice tried—and failed—to persuade
    the division to allow it to restart operations at well #2. AWMS first tried to do this
    13
    SUPREME COURT OF OHIO
    by submitting its September 2014 plan. According to Simmers, the division had
    found that plan to be “generic and inadequate,” although, as noted by the court of
    appeals in AWMS I, the division did not contact AWMS to collaborate on the plan
    or to critique the plan, 2018-Ohio-3028, 
    118 N.E.3d 385
    , at ¶ 7, and the record does
    not show that the division responded to the plan. Moreover, AWMS submitted a
    second plan in March 2015 to which the division apparently never responded either
    , id. at ¶ 8.
            {¶ 36} Now, the state argues that AWMS should be faulted for having failed
    to submit a third restart plan for well #2 based on standards the state set out after
    AWMS filed its mandamus complaint and after it twice tried to satisfy the state’s
    standards. The state’s argument, if we were to accept it, would invite protracted
    litigation. Also, because there is no indication that the state’s standards, if met,
    would be binding on the state, the division could change them at any time, which,
    under the state’s logic, could create yet another opportunity for it to say that all
    AWMS needs to do is submit another plan. We decline the state’s invitation to
    issue a decision establishing precedent permitting the state to create moving targets.
    {¶ 37} In summary, the division either rebuffed or ignored the two plans
    that AWMS had submitted to restart well #2. We conclude that AWMS was
    justified in pursuing compensation through a takings action rather than submitting
    a third restart plan and that AWMS’s claim was ripe at the time it instituted its
    takings action. See 
    Cooley, 324 F.3d at 1302-1303
    .
    B. Permanent versus temporary takings
    {¶ 38} The state next argues that the suspension of operations at well #2 is
    merely temporary and cannot amount to a categorical taking. In casting the
    suspension as temporary, the state seeks the benefit of the rule articulated in Tahoe-
    Sierra Preservation Council, Inc. v. Tahoe Regional Planning Agency, 
    535 U.S. 302
    , 
    122 S. Ct. 1465
    , 
    152 L. Ed. 2d 517
    (2002), in which the United States Supreme
    Court determined that the principles espoused in Penn Cent., rather than those set
    14
    January Term, 2020
    forth in Lucas, should apply to a moratorium on property development of finite
    duration, provided the duration of the moratorium is reasonable under the
    circumstances. Tahoe-Sierra at 341-342 (considering a 32-month moratorium).
    The court reasoned that Lucas’s categorical rule should not apply to that situation
    because a temporary prohibition on property use could not permanently deprive the
    property of all its value. “Logically, a fee simple estate cannot be rendered
    valueless by a temporary prohibition on economic use, because the property will
    recover value as soon as the prohibition is lifted.”
    Id. at
    332.
    
           {¶ 39} The state contends that its suspension of operations at well #2 is
    temporary for two reasons. First, it argues that the division did not order the well
    to be permanently plugged under R.C. 1509.12(B).             But from a functional
    standpoint, there is no material difference between a plugged well and a suspended
    well—neither can be used. Second, it argues that the restart of operations at well
    #2 is entirely within the control of AWMS because all AWMS needs to do is submit
    another restart plan. But that is simply untrue. Even if AWMS were to submit
    another plan, the division might again fail to respond to it or disapprove it.
    {¶ 40} The state’s attempt to characterize the suspension of operations at
    well #2 as temporary founders on its open-endedness. See Wyatt v. United States,
    
    271 F.3d 1090
    , 1097 (Fed.Cir.2001), fn. 6 (“The essential element of a temporary
    taking is a finite start and end to the taking”). Unlike in Tahoe-Sierra, which
    involved a prohibition on land use of finite duration, this case involves a suspension
    of operations without a fixed expiration date. Indeed, the record shows that the
    suspension will remain in effect unless and until the division decides that operations
    at well #2 may be restarted.
    {¶ 41} Also instructive here is our decision in State ex rel. BSW Dev. Group.
    v. Dayton, 
    83 Ohio St. 3d 338
    , 
    699 N.E.2d 1271
    (1998). In that case, we rejected a
    property owner’s argument that the government had permanently taken the owner’s
    property because the government indicated that it would have granted the owner’s
    15
    SUPREME COURT OF OHIO
    application for a permit upon the owner’s fulfilment of certain ministerial
    requirements.
    Id. at
    342-343. 
    Here, the conditions that the division has asked
    AWMS to meet to restart operations at well #2 are hardly ministerial.
    {¶ 42} In summary, we reject the state’s argument that the suspension of
    operations at well #2 is temporary.
    C. Whether the division effected a total taking
    1. Economically beneficial use
    {¶ 43} We start our analysis of AWMS’s total-takings claim with the rule
    espoused in Lucas, which applies to the “relatively rare situations where the
    government has deprived a landowner of all economically beneficial 
    uses.” 505 U.S. at 1018
    , 
    112 S. Ct. 2886
    , 
    120 L. Ed. 2d 798
    . Under Lucas, the “determinative
    factor” is whether the regulation effects a “complete elimination of a property’s
    value.” 
    Lingle, 544 U.S. at 539
    , 
    125 S. Ct. 2074
    , 
    161 L. Ed. 2d 876
    . See also R.T.G.,
    Inc., 
    98 Ohio St. 3d 1
    , 2002-Ohio-6716, 
    780 N.E.2d 998
    , at ¶ 39 (plurality opinion)
    (“Lucas applies where the regulation has deprived the property of all economic
    value”).
    {¶ 44} AWMS supports its argument that it suffered a total taking with the
    report of its expert witness, Dr. William W. Wade, who determined, using a net-
    present-value calculation that AWMS had lost 99.4 percent of its investment by
    September 2015 and 101.5 percent of its investment by June 2017. Dr. Wade
    determined that the division’s continued enforcement of its suspension order for
    well #2 created a situation in which AWMS could not cover its operating costs
    despite any operating revenues generated by well #1. As he explained, “operations
    without Well #2 are not economically viable” because “Well #2 is essential to the
    business operations.”
    {¶ 45} The state’s expert witnesses faulted Dr. Wade’s analysis as relying
    on an overly optimistic projection of the volume of wastewater that AWMS’s wells
    would have accepted. In their view, the well-capacity limitations of AWMS’s
    16
    January Term, 2020
    wells, not the division’s suspension order, had been one of the leading culprits for
    AWMS’s decline in operating revenues. Had Dr. Wade accounted for those
    limitations, the state says, he would not have concluded that AWMS suffered a total
    taking.
    {¶ 46} We need not decide which expert witness was right, for a court may
    not weigh competing expert-witness opinions at the summary-judgment stage.
    
    Miller, 80 Ohio St. 3d at 613
    , 
    687 N.E.2d 735
    . We hold, however, that these
    differences of opinion are enough to establish a genuine issue of material fact
    concerning whether AWMS suffered a total taking under Lucas. For that reason,
    we reverse the Eleventh District’s judgment granting summary judgment to the
    state and remand to that court for further proceedings on AWMS’s total-takings
    claim.
    {¶ 47} In reaching this decision, we reject the state’s argument that AWMS
    did not suffer a total taking because AWMS used and could continue to use its site
    after the division suspended operations at well #2. The state emphasizes that
    AWMS could use the site to (1) conduct saltwater-injection operations at well #1,
    (2) store, recycle, and treat wastewater, and (3) sell byproducts of the wastewater.
    According to the state, nothing prevents AWMS from continuing those uses. Our
    concern here, however, is not whether AWMS’s property is capable of being used,
    but whether it is capable of being used in an “economically beneficial or
    productive” manner. 
    Lucas, 505 U.S. at 1015
    , 1017, 
    112 S. Ct. 2886
    , 
    120 L. Ed. 2d 798
    . As Dr. Wade opined, the uses to which the state refers yield monthly net
    losses. For the purposes of summary judgment, his opinion is enough to establish
    a genuine issue of material fact sufficient to withstand the state’s claim that AWMS
    did not suffer a total taking.
    {¶ 48} We also reject the court of appeals’ conclusion that AWMS did not
    suffer a total taking because AWMS could have sublet its property to a third party.
    2019-Ohio-923, 
    132 N.E.3d 1151
    , at ¶ 16. The Federal Circuit addressed a similar
    17
    SUPREME COURT OF OHIO
    argument in Lost Tree Village Corp. v. United States, 
    787 F.3d 1111
    (Fed.Cir.2015). In that case, the government argued that an owner’s ability to sell
    an affected parcel of land constituted an economically beneficial use under Lucas.
    In rejecting that argument, the court explained that “[t]ypical economic uses enable
    a landowner to derive benefits from land ownership rather than requiring a
    landowner to sell the affected parcel.”
    Id. at
    1117. 
      By analogy, AWMS’s
    subletting the property, which would transfer away its right to directly use the
    property, also does not rise to the level of an economically beneficial use under
    Lucas. Moreover, any sublessee of the property would encounter the same problem
    as AWMS because it would inherit AWMS’s leasehold rights, which, as noted
    above, extend no further than saltwater-injection-well operations.
    {¶ 49} It is doubtful that AWMS’s subletting the property would even be a
    viable option here.     “[A] proposed ‘use’ requires a showing of reasonable
    probability that, at the time of the taking, the land was both physically adaptable for
    such use and that there was a need or demand for such use in the reasonably near
    future.” Bd. of Cty. Supervisors of Prince William Cty. v. United States, 
    276 F.3d 1359
    , 1365 (Fed.Cir.2002). The court of appeals observed that third parties had
    expressed interest in using AWMS’s property but that no agreement had been
    finalized. 2019-Ohio-923, 
    132 N.E.3d 1151
    , at ¶ 16. In support, it relied on the
    deposition testimony of Kilper, AWMS’s vice president, who explained that two
    potential buyers had contacted him and expressed interest in possibly buying out
    AWMS’s interest in the property. The record does not disclose the details of those
    conversations, but Kilper explained that at some point in the negotiations the
    potential buyers stopped returning AWMS’s telephone calls.             The evidence,
    therefore, does not show a legitimate demand for AWMS’s interest in the property.
    {¶ 50} The court of appeals also relied on the report of Andrew Adgate,
    ODNR’s underground-injection-control manager
    , id. at ¶ 17.
    In his report, Adgate
    suggested alternative ways in which AWMS could use the property. But because
    18
    January Term, 2020
    we conclude that Dr. Wade’s opinions in his report are enough to create a genuine
    issue of material fact regarding whether AWMS suffered a total taking, we need
    not consider the substance of Adgate’s report.
    2. The state’s nuisance defense
    {¶ 51} Under Lucas, even if a governmental regulation completely deprives
    an owner of all economically beneficial use of its property, just compensation is
    not required if the government can show that background principles of property and
    nuisance law proscribe the owner’s use of the property. 
    Lucas, 505 U.S. at 1029
    ,
    1017, 
    112 S. Ct. 2886
    , 
    120 L. Ed. 2d 798
    . To take an example from Lucas,
    the corporate owner of a nuclear generating plant [would not be
    entitled to just compensation] when it is directed to remove all
    improvements from its land upon discovery that the plant sits astride
    an earthquake fault. Such regulatory action may well have the effect
    of eliminating the land’s only economically productive use, but it
    does not proscribe a productive use that was previously permissible
    under relevant property and nuisance principles.
    Id. at
    1029-1030. 
       Courts have interpreted Lucas’s background-principles-of-
    property-and-nuisance-law passage as creating a defense that the government can
    raise in a regulatory-takings action. See, e.g., Rith Energy, Inc. v. United States,
    
    247 F.3d 1355
    , 1361 (Fed.Cir.2001); Palm Beach Isles Assocs. v. United States,
    
    231 F.3d 1354
    , 1357 (Fed.Cir.2000). We must consider whether, as AWMS argues,
    the state waived its nuisance defense.
    {¶ 52} “Unlike lack of subject matter jurisdiction, other affirmative
    defenses can be waived.” State ex rel. Jones v. Suster, 
    84 Ohio St. 3d 70
    , 77, 
    701 N.E.2d 1002
    (1998). “[I]t is well settled that ‘[a] party who fails to raise an
    argument in the court below waives his or her right to raise it here.’ ” (Second
    19
    SUPREME COURT OF OHIO
    bracket sic.) Niskanen v. Giant Eagle, Inc., 
    122 Ohio St. 3d 486
    , 2009-Ohio-3626,
    
    912 N.E.2d 595
    , ¶ 34, quoting State ex rel. Zollner v. Indus. Comm., 
    66 Ohio St. 3d 276
    , 278, 
    611 N.E.2d 830
    (1993).
    {¶ 53} AWMS argues that the state waived its nuisance defense because the
    state did not raise it in the court of appeals. The state’s second amended answer to
    AWMS’s complaint clearly sets forth the defense, but whether the state did so in
    its summary-judgment motion presents a closer question.
    {¶ 54} In its motion for summary judgment, the state briefly analogized the
    facts of this case to the hypothetical used by the court in Lucas in which the
    government could raise a nuisance defense in a situation in which a nuclear-power-
    generation plant sits astride an earthquake fault. In making that analogy, the state
    claimed that AWMS’s facility was located near “a previously unknown earthquake
    fault.”
    {¶ 55} At first blush, it would appear that the state did not waive its nuisance
    defense. The problem, however, is that Lucas requires a government-defendant to
    ground its nuisance defense in principles of its state’s property and nuisance law.
    
    Lucas, 505 U.S. at 1029-1030
    , 1017, 
    112 S. Ct. 2886
    , 
    120 L. Ed. 2d 798
    . Here, the
    state did not ground its nuisance defense in principles of Ohio property and
    nuisance law. We have held that waiver will apply when a litigant supplies no
    argument “regarding whether the relevant case law, applied to the facts of th[e]
    case, justifies a decision in [the litigant’s] favor.” Util. Serv. Partners, Inc. v. Pub.
    Util. Comm., 
    124 Ohio St. 3d 284
    , 2009-Ohio-6764, 
    921 N.E.2d 1038
    , ¶ 53. We
    find that principle dispositive here and hold that the state waived its nuisance
    defense for purposes of this appeal.
    {¶ 56} In summary, we conclude that there is a genuine issue of material
    fact concerning whether the state’s suspension of operations at well #2 deprived
    AWMS of all economically beneficial use of its leasehold. We further conclude
    that the state waived its nuisance defense. We therefore reverse the Eleventh
    20
    January Term, 2020
    District’s judgment granting summary judgment to the state on AWMS’s total-
    takings claim. On remand, the court of appeals must weigh the parties’ evidence
    relating to AWMS’s total-takings claim and disregard the state’s nuisance defense.
    D. Whether the division effected a partial taking
    {¶ 57} A regulation that prohibits less than all economically beneficial use
    of land falls outside of Lucas’ categorical rule and into Penn Cent.’s three-factor
    analysis. Palazzolo, 
    533 U.S. 606
    , 617, 
    121 S. Ct. 2448
    , 
    150 L. Ed. 2d 592
    . Under
    the framework of the Penn Cent. analysis, a court should consider “(1) the
    economic impact of the regulation on the claimant, (2) the extent to which the
    regulation has interfered with distinct investment-backed expectations, and (3) the
    character of the governmental action,” Shelly Materials, 
    115 Ohio St. 3d 337
    , 2007-
    Ohio-5022, 
    875 N.E.2d 59
    , at ¶ 19. “[T]he Penn Central inquiry turns in large part,
    albeit not exclusively, upon the magnitude of a regulation’s economic impact and
    the degree to which it interferes with legitimate property interests.” 
    Lingle, 544 U.S. at 540
    , 
    125 S. Ct. 2074
    , 
    161 L. Ed. 2d 876
    . “These essentially ad hoc, factual
    inquiries,” Penn 
    Cent., 438 U.S. at 123
    , 
    98 S. Ct. 2646
    , 
    57 L. Ed. 2d 631
    , account for
    the “particular circumstances of the case,” 767 Third Ave. Assocs. v. United States,
    
    48 F.3d 1575
    , 1580 (Fed.Cir.1995).
    1. Economic impact
    {¶ 58} Although the court of appeals did not consider the economic impact
    upon AWMS resulting from the state’s suspension of its operations at well #2, an
    established method of performing the economic-impact analysis involves
    “compar[ing] the value that has been taken from the property with the value that
    remains in the property.” Keystone Bituminous Coal Assn. v. DeBenedictis, 
    480 U.S. 470
    , 497, 
    107 S. Ct. 1232
    , 
    94 L. Ed. 2d 472
    (1987). This method is sometimes
    referred to as the “with and without” method. Eagle, “Economic Impact” in
    Regulatory Takings Law, 19 Hastings W.-Nw.J.Envtl.L. & Pol’y 407, 417-418, 420
    (2013) (“The usual approach to determine the impact of the regulation subtracts the
    21
    SUPREME COURT OF OHIO
    value of a parcel with the regulation in place from the value of the parcel without
    the regulation”).
    {¶ 59} Although there does not appear to be an exclusive method of
    comparing the value of property before and after a regulation, at least two
    approaches have been expressly endorsed. The first is the market-value approach,
    which compares the “market value of the property with and without the restrictions
    on the date that the restriction began.” Cienega Gardens v. United States, 
    503 F.3d 1266
    , 1282 (Fed.Cir.2007) (“Cienega Gardens II”). The second is the lost-net-
    income approach, which “compare[s] the lost net income due to the restriction
    (discounted to present value at the date the restriction was imposed) with the total
    net income without the restriction over the entire useful life of the property (again
    discounted to present value).” (Parenthesis sic.)
    Id. {¶ 60} AWMS’s
    expert witness, Dr. Wade, calculated the economic impact
    of the state’s regulation on AWMS under the with-and-without method using the
    lost-net-income approach. In Dr. Wade’s first calculation, he computed “the actual
    outcome caused by the shutdown of well #2.” In his second calculation, he
    computed “the expected outcome, which motivated [AWMS]’s investment in the
    leased property.” In each scenario, Dr. Wade used a discounted-cash-flow model
    to arrive at the net present value of AWMS’s property interest as of September 2014
    (when the suspension of operations at well #2 occurred) by looking backwards from
    June 2017 (the last date for which Dr. Wade had figures included on AWMS’s net-
    income statement from which to perform an analysis).
    {¶ 61} Regarding the first calculation, Dr. Wade computed a net loss of
    $6,119,275, and regarding the second calculation, he computed an expected net
    income of $14,475,770. Dr. Wade then computed the difference between those two
    numbers and determined that the economic impact upon AWMS was a loss of
    $20,595,045.    Finally, Dr. Wade compared the present value of AWMS’s
    investment ($6,076,043 as of September 2014) with the actual outcome (a net loss
    22
    January Term, 2020
    of $6,119,275 as of September 2014) and concluded that AWMS’s “continued
    ownership of the facilities through June 2017 incurred a loss of 101.5% of
    investment.” In his words, “the actual outcome does not recoup investment; no
    return on investment exists.”
    {¶ 62} The state’s expert witnesses agree that the lost-net-income approach
    is a valid method for computing economic impact. And they too performed a
    discounted-cash-flow analysis. But they concluded that the economic impact of the
    state’s suspension of operations at well #2 upon AWMS ranged from a low of
    $116,334 to a high of $359,374.
    {¶ 63} Again, the court of appeals did not consider the economic impact
    upon AWMS resulting from the state’s suspension of its operations at well #2.
    Given the significant numerical disparities in the results of the economic-impact
    analyses between AWMS’s and the state’s expert witnesses, we conclude that a
    genuine issue of material fact precluded the granting of summary judgment on the
    economic-impact factor under Penn Cent. We therefore reverse the Eleventh
    District’s judgment granting summary judgment to the state on AWMS’s partial-
    takings claim, remand to the court of appeals, and order it to weigh the parties’
    evidence concerning the economic-impact upon AWMS of the state’s suspension
    of operations at well #2.
    2. Reasonable investment-backed expectations
    {¶ 64} “The reasonable, investment-backed expectation analysis is
    designed to account for property owners’ expectation that the regulatory regime in
    existence at the time of their acquisition will remain in place, and that new, more
    restrictive legislation or regulations will not be adopted.” Love Terminal Partners,
    L.P. v. United States, 
    889 F.3d 1331
    , 1345 (Fed.Cir.2018). The Federal Circuit has
    developed three factors to guide a court when conducting that inquiry: “(1) whether
    the plaintiff operated in a ‘highly regulated industry;’ (2) whether the plaintiff was
    aware of the problem that spawned the regulation at the time it purchased the
    23
    SUPREME COURT OF OHIO
    allegedly taken property; and (3) whether the plaintiff could have ‘reasonably
    anticipated’ the possibility of such regulation in light of the ‘regulatory
    environment’ at the time of purchase.” Apollo Fuels, Inc. v. United States, 
    381 F.3d 1338
    , 1349 (Fed.Cir.2004), quoting Commonwealth Edison Co. v. United States,
    
    271 F.3d 1327
    , 1348 (Fed.Cir.2001).
    {¶ 65} Starting with the first factor—whether AWMS operated in a highly
    regulated industry—AWMS correctly notes that an entrant into a highly regulated
    field does not abandon all reasonable investment-backed expectations.              See
    Cienega Gardens 
    I, 331 F.3d at 1350
    . It is also true, however, that “reasonable
    investment-backed expectations are greatly reduced in a highly regulated field.”
    Branch v. United States, 
    69 F.3d 1571
    , 1581 (Fed.Cir.1995). And here, AWMS
    does not deny that it had entered a highly regulated industry—that of oil and gas.
    {¶ 66} Turning to the second factor—whether AWMS had been aware of
    the potential seismicity problem—AWMS admits to having known that induced
    seismicity could be an issue with its injection wells. However, we disagree with
    some of the state’s arguments concerning the problem-awareness factor because
    they focus on circumstances that arose after AWMS had acquired its leasehold on
    December 19, 2011. First, the state points to the seismic events that took place in
    Youngstown on December 24 and December 31, 2011, which prompted former
    Governor Kasich to impose a moratorium on certain injection activities. Second,
    the state emphasizes the September 2013 confidential offering memorandum that
    AWMS prepared for prospective investors in which AWMS acknowledged that
    governmental regulation of injection wells might increase, that its wells might
    induce a seismic event, and that such an event could cause a suspension of its
    injection operations. True, that evidence tends to show AWMS’s awareness that
    its operations might be suspended if its wells were to be determined to have induced
    seismic events. But it is the interestholder’s expectations at the time it acquired its
    24
    January Term, 2020
    interest that is determinative, not its expectations following an event occurring at
    some later point in time. See Apollo 
    Fuels, 381 F.3d at 1349
    .
    {¶ 67} At the time AWMS acquired its leasehold interest, AWMS could not
    have anticipated that the state would waver between a case-by-case approach and a
    statewide approach to addressing induced seismicity while rebuffing AWMS’s
    attempts to meet the state’s inchoate regulatory expectations. The parties do not
    dispute that at the time AWMS obtained its leasehold in December 2011, the
    division had not established its approach to managing induced seismicity. When
    the division first issued its suspension orders in September 2014, it put the onus on
    AWMS to “submit a written plan to the Division for evaluating the seismic
    concerns associated with the operation of” well #2. Although AWMS had not
    received direction from the division about what to include in the plan, AWMS
    nevertheless submitted a plan that included several proposals to establish certain
    controls over injections at well #2. The division rejected the plan as “generic and
    inadequate.”
    {¶ 68} During its appeal of the suspension order, AWMS met twice with
    the division in an attempt to understand the division’s regulatory position. At the
    first meeting in October 2014, the division stated that its statewide policy would
    not be ready for at least four to six more months and declined to address the
    circumstances of its suspension of AWMS’s operations. At the second meeting in
    February 2015, the division presented AWMS a single sheet of paper containing 14
    criteria that the division was considering for evaluating induced seismicity in its
    statewide policy. But the division also told AWMS that it would not implement a
    statewide policy for at least another eight months. A few days after the February
    2015 meeting, AWMS sought clarification on some of the division’s proposed
    criteria. Once again, the division failed to offer any direction or clarification.
    AWMS nevertheless submitted a plan to the division in early March 2015
    25
    SUPREME COURT OF OHIO
    addressing the division’s proposed criteria. The record does not indicate that the
    division responded.
    {¶ 69} AWMS got its answer in August 2015 when the commission issued
    its decision affirming the division’s suspension of operations of well #2. AWMS
    could not have reasonably anticipated when it acquired its leasehold interest that
    the state’s inconsistent regulatory approach or its lack of responsiveness to
    AWMS’s attempts at remediation would leave AWMS in limbo for years with an
    indefinite suspension of its operations.
    {¶ 70} AWMS has demonstrated a material issue of fact that the division’s
    suspension of operations at #2 interfered with AMWS’s reasonable investment-
    backed expectations. We therefore reverse the Eleventh District’s granting of
    summary judgment on this factor under Penn Cent.
    3. Character of the governmental action
    {¶ 71} The court of appeals began its analysis of the character-of-the-
    governmental-action factor under Penn Cent. as follows:
    In evaluating the character of the Suspension Order, we
    emphasize that the issue of the reasonableness of the Suspension
    Order has been fully litigated and the Tenth District’s opinion has
    preclusive effect on that point. * * * The character of the order has
    been deemed reasonable as a matter of law and that judgment was
    issued in an action between the same parties. Collateral estoppel
    therefore bars [AWMS] from challenging the reasonableness of the
    underlying order.
    2019-Ohio-923, 
    132 N.E.3d 1151
    , at ¶ 22. The court of appeals did not, however,
    cite any takings-related authority to support its application of the doctrine of
    collateral estoppel as a means of deciding the character-of-the-governmental-action
    26
    January Term, 2020
    inquiry. And neither party’s brief defends the court of appeals’ invocation of that
    doctrine. The parties’ silence is justified because the character of a governmental
    action is not determined by its lawfulness or propriety. See Norman v. United
    States, 
    63 Fed. Cl. 231
    , 285 (2004) (“the lawfulness or appropriateness of the
    governmental action is not akin to the character of the governmental action”).
    Applying this principle, we will analyze the character-of-the-governmental-action
    factor on its merits rather than recognize the court of appeals’ procedural bar.
    {¶ 72} Without attempting to provide an exhaustive list of the factors that
    courts have used to guide their character-of-the-governmental-action inquiries, we
    will focus on three factors emphasized by the parties. The first factor involves
    whether the interestholder has been impermissibly “singled out” by the government
    for unfavorable treatment, Sherman v. Chester, 
    752 F.3d 554
    , 565-565 (2d
    Cir.2014), or instead been permissibly included within a governmental program
    aimed at “adjusting the benefits and burdens of economic life to promote the
    common good,” Penn 
    Cent., 438 U.S. at 124
    , 
    98 S. Ct. 2646
    , 
    57 L. Ed. 2d 631
    . The
    second factor involves whether the regulation bears a “harm-preventing purpose.”
    Rose Acre Farms, Inc. v. United States, 
    559 F.3d 1260
    , 1281 (Fed.Cir.2009). And
    the third factor involves the extent to which regulatory delay accompanied the
    government’s decisionmaking process. State ex rel. Duncan v. Middlefield, 
    120 Ohio St. 3d 313
    , 2008-Ohio-6200, 
    898 N.E.2d 952
    , ¶ 19-20.
    {¶ 73} Turning to the first factor—whether the state impermissibly singled
    out AWMS for unfair treatment—AWMS claims that the division unfairly did so
    by suspending its operations at well #2 while not suspending operations at a
    seismicity-inducing well in Washington County (the “Long Run well”). The state’s
    expert witnesses agreed that the Long Run well contributed to seismicity in its
    surrounding area. And the division’s personnel do not dispute that the division
    contacted the operator of the Long Run well and asked it to reduce—rather than
    suspend—the well’s injection volumes in an effort to mitigate seismicity risks.
    27
    SUPREME COURT OF OHIO
    {¶ 74} The state argues, however, that there has been no unfair singling out
    of well #2 because the characteristics of well #2 and the Long Run well differ. First,
    the state asserts that the wells differ from a geological standpoint. The state stresses
    the proximity of the bottom of well #2 to a region known as the Precambrian
    basement, which consists of “igneous and metamorphic rocks that exist below the
    oldest sedimentary rock cover.” Ground Water Protection Council & Interstate Oil
    & Gas Compact Commission at 124. According to Simmers, the division’s chief,
    well injections near that region should be avoided. In Washington County, the
    separation between the bottom of the Long Run well’s injection zone and the
    Precambrian basement is just under a mile, which is a significant separation. Well
    #2, however, is drilled much deeper and bottoms out in an area located directly
    above the Precambrian basement.
    {¶ 75} AWMS agrees that the Long Run well and well #2 differ
    geologically. But it maintains that the significance of the differences have been
    overblown. The problem with AWMS’s argument in that regard, however, is that
    AWMS’s brief cites nothing from the record to support that view. See State ex rel.
    Coulverson v. Ohio Adult Parole Auth., 
    62 Ohio St. 3d 12
    , 14, 
    577 N.E.2d 352
    (1991) (holding that conclusory allegations are not sufficient to withstand summary
    judgment).
    {¶ 76} The state’s second basis for distinguishing the Long Run well from
    well #2 rests on the respective wells’ relative proximities to population centers. In
    support, the state points to a report prepared by one of its expert witnesses
    concluding that “the seismic risk in Trumbull and Washington Counties are at
    opposite ends of the spectrum” due to the differences in the “distribution and
    density of [the] population and structures” in those areas. AWMS responds that it
    is not the proximity of injection wells to population centers that should matter but
    rather the proximity of seismic events to population centers. Yet, AWMS fails to
    identify anything in the record that affirmatively negates the state’s emphasis on
    28
    January Term, 2020
    the wells’ proximity to population centers. And even if it had done so, there are
    still enough differences between well #2 and the Long Run well to persuade us that
    the state did not unfairly single out well #2.
    {¶ 77} Under the second character-of-the-governmental-action factor—
    whether governmental regulation bears a harm-preventing purpose—the character
    of a regulation will “weigh[] strongly against finding a taking” when the purpose
    of that regulation is to prevent harm to public health and safety. Rose Acre 
    Farms, 559 F.3d at 1281
    . “[I]n the context of the protection of public health and safety,
    ‘the private interest has traditionally been most confined and governments are given
    the greatest leeway to act without the need to compensate those affected by their
    actions.’ ”    Dimare Fresh, Inc. v. United States, 
    808 F.3d 1301
    , 1311
    (Fed.Cir.2015), quoting Rose Acre Farms at 1281-1282. In Rose Acre Farms, the
    federal circuit addressed a governmental action undertaken to limit the spread of
    salmonella bacteria in the chicken-egg market.
    Id. at
    1261. 
    In rejecting the
    plaintiff’s takings claim, the court gave considerable weight to the government’s
    harm-preventing purpose, explaining that human consumption of the “infected eggs
    could have caused serious illness and possibly even death.”
    Id. at
    1283.
    
           {¶ 78} In this case, the state presents a similar harm-prevention
    justification, arguing that the purpose behind the division’s suspension of
    operations at well #2 was to protect the public against the threat of earthquakes. A
    December 2017 report prepared by Simmers bears out this assertion. Simmers
    explained in his report that the “protect[ion] [of] public health and safety” was the
    purpose of the state’s suspension of operations at well #2. He further noted a strong
    correlation between the operations at well #2 and the seismic events that took place
    in the vicinity of well #2 on July 28, 2014, and August 31, 2014. And he concluded
    that the restarting of operations at well #2 would pose a continued threat of harm to
    public health and safety because the division has, since issuing the suspension
    order, obtained evidence that well #2 sits near a geological fault.
    29
    SUPREME COURT OF OHIO
    {¶ 79} AWMS does not challenge Simmers’s statement that the purpose of
    the suspension was to protect the public from harm—in fact, AWMS recognizes
    that preventing harm to the public is a laudable goal. Nor does AWMS challenge
    Simmers’s determination that its operations at well #2 correlated with the seismic
    events from 2014—two of AWMS’s expert witnesses concur in that determination.
    But AWMS does say in its merit brief that no one has determined that AWMS’s
    operations posed an “imminent threat” to public safety.          However, AWMS
    identifies no authority that requires a governmental actor to establish that there is
    an imminent threat of harm before the government implements a regulatory action
    to protect public health and safety.
    {¶ 80} The third and final character-of-the-governmental-action factor
    involves the extent to which delay accompanied the state’s decisionmaking process.
    Although “[a] requirement that a person obtain a permit before engaging in a certain
    use of his or her property does not itself ‘take’ the property in any sense,” United
    States v. Riverside Bayview Homes, Inc., 
    474 U.S. 121
    , 127, 
    106 S. Ct. 455
    , 
    88 L. Ed. 2d 419
    (1985), “a taking may occur by reason of ‘extraordinary delay in
    governmental decisionmaking,’ ” 
    Wyatt, 271 F.3d at 1097
    , quoting Tabb Lakes,
    Ltd. v. United States, 
    10 F.3d 796
    , 803 (Fed.Cir.1993). In deciding whether a delay
    is extraordinary, a court must weigh “all relevant factors,” Duncan, 
    120 Ohio St. 3d 313
    , 2008-Ohio-6200, 
    898 N.E.2d 952
    , at ¶ 20, including the length of the delay,
    Bass Ents. Prod. 
    Co., 381 F.3d at 366
    . Bad faith on the part of the government will
    influence the inquiry, as will any delay that the interestholder’s conduct caused.
    Duncan at ¶ 20. The “nature of the permitting process” and the “reasons for any
    delay” may also inform the analysis. Wyatt at 1098.
    {¶ 81} The party alleging a governmental taking must tie its claim of
    extraordinary delay to the government’s decisionmaking process, namely, the
    process by which the government reviews an interestholder’s formal request to use
    its property in a particular way. Duncan at ¶ 19-20. In Duncan, a case cited by
    30
    January Term, 2020
    AWMS in its merit brief, a landowner tied his claim of extraordinary delay to the
    government’s conduct in reviewing his zoning-permit applications. Duncan at
    ¶ 21 (addressing delays of six and nine months). In Byrd v. Hartsville, a case
    Duncan cites with approval, see Duncan at ¶ 19, a landowner similarly claimed to
    have suffered from extraordinary delay during the government’s review of his
    zoning petition, 
    365 S.C. 650
    , 660-662, 
    620 S.E.2d 76
    (2005) (addressing delays
    of two and eleven months). Although the plaintiffs in Duncan and Byrd did not
    succeed on their extraordinary-delay claims, the salient point for the purpose of our
    analysis is that the plaintiffs in those cases tied their claims to the manner in which
    the government conducted itself in reviewing their formal requests to use their
    property in a particular way.
    {¶ 82} Here, although it is a bit unclear, AWMS appears to allege
    extraordinary delay stemming from the division’s decision to delay, and then
    abandon, the implementation of its once-promised statewide policy on induced
    seismicity. But AWMS cites no authority supporting its argument that a claim of
    extraordinary delay will lie against the government for unduly delaying the
    implementation of a policy, as opposed to deciding an interestholder’s pending
    request to use its property in a certain way. And AWMS makes no claim that it is
    awaiting the division’s approval of its plans to restart well #2.
    {¶ 83} AWMS next alleges that the division has engaged in extraordinary
    delay based on the length of time that operations at well #2 have been suspended.
    But that argument is misplaced because it targets the consequences of the division’s
    decisionmaking process, not the decisionmaking process itself.
    {¶ 84} AWMS also alleges that the division has acted in bad faith. In
    support of that contention, AWMS points to an affidavit provided by Kilper, its
    vice president, in which he stated that he was told by a member of the division that
    “press and politics” (rather than science) was the real reason that the Long Run well
    had been permitted to operate and well #2 had not. But as explained above, there
    31
    SUPREME COURT OF OHIO
    is no genuine dispute that well #2 and the Long Run well differ in significant ways.
    Given these differences, AWMS’s allegations of bad faith are not “significantly
    probative.” Buckeye Union Ins. Co. v. Consol. Stores Corp., 
    68 Ohio App. 3d 19
    ,
    22, 
    587 N.E.2d 391
    (10th Dist.1990) (if evidence is “merely colorable” or not
    “significantly probative,” summary judgment may be entered).
    {¶ 85} If the crux of AWMS’s argument is that the division took too long
    to conduct its review of AWMS’s restart plan—again, AWMS’s argument
    regarding the division’s delay is a bit unclear—then the temporal scope of such
    reviews must be considered. AWMS is not clear on how it imputes value to a
    particular length of time. Approximately seven months—from September 2014 to
    March 2015—elapsed between the dates on which it submitted its first and second
    restart plans. And approximately 17 months—from March 2015 to August 2016—
    elapsed between the dates on which it submitted its second restart plan and filed its
    mandamus petition. Because the record does not show that the division ever
    formally rejected AWMS’s second restart plan, see also AWMS I, 2018-Ohio-3028,
    
    118 N.E.3d 385
    , at ¶ 8, in the absence of further guidance, we construe the filing of
    AWMS’s mandamus petition as setting the date upon which AWMS regarded the
    division as having effected a constructive denial of its plans. Even if we were to
    assume that the state acted in bad faith, AWMS cites no authority supporting its
    argument that delays of the lengths that occurred in this case are extraordinary
    under the circumstances. Further, delays of 45 months and longer have been
    deemed unextraordinary when, as here, complex regulatory schemes are involved.
    See, e.g., Bass Ents. Prod. 
    Co., 381 F.3d at 1363
    , 1366-1368 (45-month delay);
    
    Wyatt, 271 F.3d at 1098-1100
    (76-month delay).
    {¶ 86} In summary, we conclude that AWMS has not demonstrated that
    there is a genuine issue of material fact regarding whether the character of the
    division’s suspension order was to protect the public’s health and safety.
    32
    January Term, 2020
    4. Balancing the factors
    {¶ 87} In a typical partial-takings case, a reviewing court must balance the
    Penn Cent. factors to determine whether a partial taking has occurred. Reoforce,
    Inc. v. United States, 
    853 F.3d 1249
    , 1271 (Fed.Cir.2017). But genuine issues of
    material fact preclude us from performing that balancing exercise. We reverse the
    Eleventh District’s judgment granting summary judgment to the state on AWMS’s
    partial-takings claim. On remand, the court of appeals must weigh the parties’
    economic-impact evidence and determine in whose favor that factor falls. After
    doing so, the court of appeals must balance all three Penn Cent. factors to determine
    whether AWMS suffered a partial taking.
    IV. CONCLUSION
    {¶ 88} For the foregoing reasons, we hold that there is a genuine issue of
    material fact concerning whether the state’s suspension of AWMS’s operations at
    well #2 constituted a total taking by depriving AWMS of all economically
    beneficial use of its leasehold. We further conclude that the state waived its
    nuisance defense to AWMS’s total-takings claim.            We reverse the Eleventh
    District’s judgment granting summary judgment to the state on AWMS’s total-
    takings claim. On remand, the court of appeals must weigh the parties’ evidence
    relating to AWMS’s total-takings claim and disregard the state’s nuisance defense.
    {¶ 89} We also reverse the Eleventh District’s judgment granting summary
    judgment to the state on AWMS’s partial-takings claim. On remand, the court of
    appeals must weigh the parties’ evidence in accordance with this opinion and
    balance all three Penn Cent. factors to determine whether AWMS suffered a partial
    taking.
    Judgment reversed
    and cause remanded.
    O’CONNOR, C.J., and FRENCH and DEWINE, JJ., concur.
    KENNEDY, J., concurs in judgment only, with an opinion.
    33
    SUPREME COURT OF OHIO
    STEWART, J., concurs in judgment only.
    DONNELLY, J., dissents, with an opinion.
    _________________
    KENNEDY, J., concurring in judgment only.
    {¶ 90} Because I agree with the majority that there are genuine issues of
    material fact precluding the entry of summary judgment in favor of appellees, the
    Ohio Department of Natural Resources (“ODNR”); ODNR’s director, Mary Mertz;
    ODNR’s Division of Oil and Gas Resources Management (“the division”); and the
    division’s chief, Richard Simmers (collectively, “the state”), I concur in the court’s
    judgment to reverse the decision of the Eleventh District Court of Appeals.
    Appellants, AWMS Water Solutions, L.L.C.; AWMS Holdings, L.L.C.; and
    AWMS, Rt. 169, L.L.C. (collectively, “AWMS”), presented evidence that the
    state’s order closing AWMS’s saltwater-injection well effected a total or partial
    taking of its property sufficient to survive the state’s motion for summary judgment.
    Total-takings analysis
    {¶ 91} The threshold issue in a takings analysis is to define the property
    allegedly taken, and state law determines which individual rights constitute
    property, see State ex rel. New Wen, Inc. v. Marchbanks, 
    159 Ohio St. 3d 15
    , 2020-
    Ohio-63, 
    146 N.E.3d 545
    , ¶ 24. “An interest in real property is defined by the metes
    and bounds that describe its geographic dimensions and the term of years that
    describes the temporal aspect of the owner’s interest.” Tahoe-Sierra Preservation
    Council, Inc. v. Tahoe Regional Planning Agency, 
    535 U.S. 302
    , 331-332, 
    122 S. Ct. 1465
    , 
    152 L. Ed. 2d 517
    (2002). We have recognized, for example, that “[a] mineral
    estate may be considered the relevant parcel for a compensable regulatory taking if
    the mineral estate was purchased separately from the other interests in the real
    property.” State ex rel. Shelly Materials, Inc. v. Clark Cty. Bd. of Commrs., 
    115 Ohio St. 3d 337
    , 2007-Ohio-5022, 
    875 N.E.2d 59
    , ¶ 34.
    34
    January Term, 2020
    {¶ 92} The property interest at stake in this case is a narrow one: a leasehold
    right to operate Class II saltwater-injection wells on 5.2 acres of industrial property
    in Weathersfield Township, Trumbull County, Ohio. AWMS has invested millions
    of dollars to develop the facilities necessary to operate those wells, but it may use
    the property only for operations consistent with the limited property interest it
    owns. That is, AWMS cannot use the property to operate a fast-food restaurant or
    a car dealership or anything else exceeding the scope of the lease. Therefore, in
    determining whether the state’s order suspending AWMS’s operations at well #2
    constitutes a total or partial taking, the property allegedly taken is AWMS’s limited
    property right allowing it to operate saltwater-injection wells under its leasehold
    and the ancillary activities associated with that right.
    {¶ 93} In the United States Supreme Court’s seminal decision in
    Pennsylvania Coal Co. v. Mahon, 
    260 U.S. 393
    , 
    43 S. Ct. 158
    , 
    67 L. Ed. 322
    (1922),
    the claimant had sold the surface rights to particular parcels of property, but
    expressly reserved the right to remove the coal underneath those parcels. After the
    sale, Pennsylvania enacted a statute forbidding the mining of coal that causes the
    subsidence of any structure used as a human inhabitation unless, among other
    exceptions, the owner of the coal also owned the surface land.
    Id. at
    412-413. 
    The
    Supreme Court determined that the statute had made it “commercially
    impracticable” to mine the coal and had “very nearly the same effect for
    constitutional purposes as appropriating or destroying” the reservation of the
    mineral interest.
    Id. at
    414. The court therefore held that the statute effected a
    governmental taking of property.
    Id. at
    415-416.
    
           {¶ 94} Similarly, AWMS’s evidence established a triable issue regarding
    whether the state’s suspension order caused a total taking of AWMS’s property by
    depriving its leasehold of “all economically beneficial or productive use,” Lucas v.
    South Carolina Coastal Council, 
    505 U.S. 1003
    , 1015, 
    112 S. Ct. 2886
    , 
    120 L. Ed. 2d 798
    (1992). AWMS presented the report of its expert, Dr. William W. Wade, who
    35
    SUPREME COURT OF OHIO
    explained that AWMS had lost 99.4 percent of its investment by September 2015
    and 101.5 percent of its investment by June 2017. He therefore opined that it was
    not economically viable for AWMS to conduct saltwater-injection operations at
    well #1 if the suspension order remained in place for well #2. That evidence, if
    believed, is sufficient to establish that the suspension order was a total
    governmental taking of AWMS’s property because it completely deprived AWMS
    of all economically beneficial use of its leasehold interest, a limited property right
    allowing AWMS to operate saltwater-injection wells and to conduct the ancillary
    activities associated with the wells. See Lucas at 1015; Mahan at 414. A property
    right has no economic value if it can only be exercised at an economic loss.
    {¶ 95} Because Dr. Wade’s opinion created a genuine issue of material fact
    regarding whether AWMS had suffered a total taking of its property interest, it is
    unnecessary to consider other factual issues regarding whether AWMS’s leasehold
    retained some economic value because AWMS could continue other kinds of
    operations on the premises or because it could sell or sublet its interest. Those
    remain triable issues that should be considered by the court of appeals on remand;
    this court should not resolve factual disputes in the first instance when considering
    issues on appeal.
    Partial-takings analysis
    {¶ 96} Regarding AWMS’s partial-takings claim, I agree with the majority
    that there are genuine issues of material fact that precluded the entry of summary
    judgment in favor of the state. In determining whether a partial taking has occurred,
    we apply the analysis from Penn Cent. Transp. Co. v. New York City, 
    438 U.S. 104
    ,
    
    98 S. Ct. 2646
    , 
    57 L. Ed. 2d 631
    (1978). We have noted that the analysis involves an
    an ad hoc, factual inquiry that requires the examination of the
    following three factors to determine whether a regulatory taking
    occurred in cases in which there is no physical invasion and the
    36
    January Term, 2020
    regulation deprives the property of less than 100 percent of its
    economically viable use: (1) the economic impact of the regulation
    on the claimant, (2) the extent to which the regulation has interfered
    with distinct investment-backed expectations, and (3) the character
    of the governmental action.
    Shelly Materials, 
    115 Ohio St. 3d 337
    , 2007-Ohio-5022, 
    875 N.E.2d 59
    , at ¶ 19.
    {¶ 97} Regarding the first prong of the Penn Cent. test—the economic
    impact of the regulation—AWMS presented Dr. Wade’s expert opinion that the
    economic impact of the suspension order on AWMS was a loss of $20,595,045 and
    the elimination of any return on investment. The state’s experts calculated the
    economic impact as ranging between $116,334 and $359,374. Accordingly, there
    is a significant factual dispute regarding the scope of the economic impact that
    AWMS suffered. Without resolving this factual dispute, the court of appeals had
    no basis to determine what weight, if any, to give the economic impact of the
    regulation on AWMS’s property. Simply assuming that this factor weighed in
    AWMS’s favor, as the court of appeals did here, is no substitute. There is a
    difference between assuming that this factor weighed in AWMS’s favor and finding
    that the suspension order has cost AWMS tens of millions of dollars.
    {¶ 98} The majority therefore correctly determines that there are genuine
    issues of material fact regarding the economic impact of the regulation that
    precluded the court of appeals from granting summary judgment to the state.
    {¶ 99} The second prong of the Penn Cent. test requires us to evaluate the
    reasonableness of the property owner’s distinct investment-backed expectations. In
    investing millions of dollars to construct saltwater-injection wells, AWMS had a
    reasonable expectation that it would be able to conduct its operations if it complied
    with the statutes enacted by the General Assembly and the rules promulgated by
    the division. It was also more than reasonable for AWMS to expect that it would
    37
    SUPREME COURT OF OHIO
    be able to continue saltwater-injection operations as long as it obeyed the terms of
    its permits. That is, AWMS had the right to expect that the state would adhere to
    the principle that “the government itself is subject to rules of law, and cannot
    disregard the law, or remake it to suit itself without heeding those procedures
    specified by law.” Cooper v. Gwinn, 
    171 W. Va. 245
    , 250, 
    298 S.E.2d 781
    (1981).
    {¶ 100} The state might be correct when it calls AWMS’s investment “a
    calculated investment risk.” However, that calculation was based on AWMS’s
    expectations that the division would adhere to Ohio’s statutes and rules and
    AWMS’s permit conditions as written, which would allow AWMS’s continued
    operation of its well if the terms of its permits were not violated. AWMS could
    reasonably rely on R.C. 1509.04(A) and (C), which allow saltwater-injection
    operations to be suspended when there is a violation of a statute, administrative
    rule, or condition of the permit, but only if (1) the operator has violated an order
    finding a material and substantial violation or (2) continued operation “presents an
    imminent danger to the health or safety of the public or that results in or is likely to
    result in immediate substantial damage to the natural resources of this state.” And
    AWMS could rely on the fact that neither the Revised Code nor the division’s
    administrative rules include specific provisions regulating induced seismicity. And
    to the extent that Ohio law permits the division to include conditions regarding
    induced seismicity in a permit, AWMS could rely on the fact that its permits did
    not contain express language empowering the division to suspend its operations due
    to a seismic event of a specific magnitude.
    {¶ 101} The division and AWMS were both aware of the concerns that
    saltwater-injection operations could induce seismicity prior to the division’s issuing
    AWMS its permits, but the division nonetheless issued the permits for AWMS to
    construct two wells, without reserving its authority to suspend AWMS’s operations
    if the wells caused a particular amount of seismic activity. The Supreme Court of
    the United States has recognized that that such approval “can lead to the fruition of
    38
    January Term, 2020
    a number of expectancies embodied in the concept of ‘property’—expectancies
    that, if sufficiently important, the Government must condemn and pay for before it
    takes over the management of the landowner’s property.” Kaiser Aetna v. United
    States, 
    444 U.S. 164
    , 179, 
    100 S. Ct. 383
    , 
    62 L. Ed. 2d 332
    (1979). And there have
    been no relevant changes to Ohio’s regulatory scheme that should preclude
    AWMS’s continued reliance on the division’s approval.
    {¶ 102} Based on these facts, a factfinder could conclude that the state’s
    suspension order interferes with AWMS’s distinct investment-based expectations
    and that those expectations were reasonable.
    {¶ 103} In reviewing this second prong of the Penn Cent. test, the majority
    focuses on “the state’s inconsistent regulatory approach” and “its lack of
    responsiveness to AWMS’s attempts at remediation.” Majority opinion at ¶ 69.
    But that evidence should not be considered solely under the second prong of the
    Penn Cent. test, because it is also relevant in determining the character of the
    governmental regulation, which is the third prong of the Penn Cent. test. The third
    prong recognizes that there can be a range of governmental action that can affect
    property rights, from the physical invasion of property, to a regulation that “merely
    affects property interests through ‘some public program adjusting the benefits and
    burdens of economic life to promote the common good,’ ” Lingle v. Chevron
    U.S.A. Inc., 
    544 U.S. 528
    , 539, 
    125 S. Ct. 2074
    , 
    161 L. Ed. 2d 876
    (2005), quoting
    Penn 
    Cent., 438 U.S. at 124
    , 
    98 S. Ct. 2646
    , 
    57 L. Ed. 2d 631
    . The focus should
    appropriately be on “the degree to which [the regulation] interferes with legitimate
    property interests,”
    id. at 540,
    and draw on the understanding that the right to use
    property “is subject to the reasonable exercise of state authority, including the
    enforcement of valid zoning and land-use restrictions,” Palazzolo v. Rhode Island,
    
    533 U.S. 606
    , 627, 
    121 S. Ct. 2448
    , 
    150 L. Ed. 2d 592
    (2001). Our task here is to
    determine where on the continuum of governmental action the state’s suspension
    order on AWMS fell.
    39
    SUPREME COURT OF OHIO
    {¶ 104} Contrary to the majority’s reasoning, there are genuine issues of
    material fact that must be resolved before the third prong of Penn Cent. test may be
    balanced against the first two factors. AWMS presented evidence establishing that
    the division’s suspension order had neither been intended to promote public safety
    nor supported by science, but that it was imposed because of “press and politics.”
    AWMS supports that claim by pointing to situations involving other saltwater-
    injection wells that had been permitted to continue their operations notwithstanding
    concerns about their inducing seismicity, including one that had been permitted to
    inject saltwater at reduced volumes rather than have its operations suspended.
    AWMS points to the division’s delay in reviewing its plan for restarting its
    operations, a plan that sought to mitigate potential seismic activity through
    operational adjustments that had been successfully used with other wells. That is,
    “the state’s inconsistent regulatory approach” and “its lack of responsiveness to
    AWMS’s attempts at remediation” that have left “AWMS in limbo for years with
    an indefinite suspension of its operations,” majority opinion at ¶ 69, support
    AWMS’s assertion that the suspension order is “not * * * a broadly applied
    regulation to prevent or limit an existing threat to public safety or welfare[,]” but
    rather requires one injection-well operator to solely bear the burden of “a problem
    that is shared by its peers.”
    {¶ 105} This evidence establishes a factual dispute regarding the character
    of the state’s regulation of AWMS’s operations and whether the state’s purpose is
    to protect the environment and public safety or whether this “particular exercise of
    the State’s regulatory power is so unreasonable or onerous as to compel
    compensation,” Palazzolo at 627.
    {¶ 106} For these reasons, I agree with the majority that there are genuine
    issues of material fact precluding the entry of summary judgment on AWMS’s
    total-takings and partial-takings claims.
    _________________
    40
    January Term, 2020
    DONNELLY, J., dissenting.
    {¶ 107} I would hold that appellants, AWMS Water Solutions, L.L.C.;
    AWMS Holdings, L.L.C.; and AWMS, Rt. 169, L.L.C. (collectively, “AWMS”),
    suffered neither a total nor a partial regulatory taking, and thus I would affirm the
    judgment of the Eleventh District Court of Appeals. Accordingly, I respectfully
    dissent.
    Total-takings analysis
    {¶ 108} I start my regulatory-takings analysis where the majority does, by
    considering AWMS’s total-takings claim against the backdrop of the United States
    Supreme Court’s decision in Lucas v. South Carolina Coastal Council, 
    505 U.S. 1003
    , 
    112 S. Ct. 2886
    , 
    120 L. Ed. 2d 798
    (1992). In that case, the property owner
    bought beachfront property for the purpose of developing it into single-family
    residences.
    Id. at
    1006-1007.      Later, the South Carolina legislature enacted
    legislation forbidding the owner from erecting any permanent habitable structures
    on the property, rendering the property “valueless.”
    Id. at
    1007. 
    The Supreme
    Court of South Carolina determined that the legislation had not effected a
    governmental taking of the owner’s property because the legislation’s purpose was
    to preserve beaches as a public resource.
    Id. at
    1009-1010.
    {¶ 109} The United States Supreme Court reversed, determining that the
    legislation’s purpose had no place in a takings analysis. The Supreme Court held
    that “when the owner of real property has been called upon to sacrifice all
    economically beneficial uses in the name of the common good, that is, to leave his
    property economically idle, he has suffered a taking,”
    id. at 1019,
    unless the state
    can show that the owner’s “proscribed use interests were not part of his title to begin
    with,”
    id. at 1027.
    The court explained that when a regulation deprives land of any
    “economically beneficial or productive options for its use—typically, as here, by
    requiring land to be left substantially in its natural state,” the regulation carries with
    41
    SUPREME COURT OF OHIO
    it a “heightened risk that private property is being pressed into some form of public
    service under the guise of mitigating serious public harm.”
    Id. at
    1018.
    {¶ 110} The facts presented in this case are a far cry from those involved in
    Lucas. Appellees, the Ohio Department of Natural Resources (“ODNR”); ODNR’s
    director, Mary Mertz; ODNR’s Division of Oil and Gas Resources Management
    (“the division”); and the division’s chief, Richard Simmers (collectively, “the
    state”), did not force AWMS to render its property economically idle by leaving it
    to its natural state. AWMS continued to use well #1 after the division suspended
    operations at well #2. In fact, before AWMS voluntarily decided to shut down its
    operations at well #1, it had generated hundreds of thousands of dollars in revenue
    from its use. And as the court of appeals noted, even after well #2’s suspension,
    AWMS “still processed, stored, recycled, treated, and disposed of brine” on the
    property. 2019-Ohio-923, 
    132 N.E.3d 1151
    , ¶ 15.
    {¶ 111} Given that the property was, and still could be, used for income-
    producing purposes, I am puzzled by the majority’s decision to remand the cause
    to the court of appeals for further weighing of the evidence. The majority points to
    the parties’ competing economic-impact evidence, explaining that there is a
    genuine issue of material fact about whether the division’s suspension of operations
    at well #2 left AWMS’ leasehold valueless. True, the parties’ experts offered
    sharply divergent opinions on how far AWMS undershot its original revenue goals
    and why.    The majority correctly notes that the “complete elimination of a
    property’s value” is the “determinative factor” under the analysis espoused in a
    Lucas. Majority opinion at ¶ 43, quoting Lingle v. Chevron, U.S.A., Inc., 
    544 U.S. 528
    , 539, 
    125 S. Ct. 2074
    , 
    161 L. Ed. 2d 876
    (2005). But from a regulatory-takings
    perspective, I fail to see how a property could ever be characterized as valueless
    when the property is capable of being put to the economically beneficial uses
    discussed above. As Lucas itself makes clear, a property’s usage informs its value.
    See 
    Lucas, 505 U.S. at 1019
    , 1027, 
    112 S. Ct. 2886
    , 
    120 L. Ed. 2d 798
    .
    42
    January Term, 2020
    {¶ 112} Indeed, we interpreted the reasoning in Lucas in precisely that way
    in State ex rel. Shelly Materials, Inc. v. Clark Cty. Bd. of Commrs., 
    115 Ohio St. 3d 337
    , 2007-Ohio-5022, 
    875 N.E.2d 59
    . In that case, a local zoning board had denied
    a company’s request for a permit to mine sand and gravel deposits located below
    the surface of the company’s property.
    Id. at
    ¶ 4. The company eventually
    responded by filing a total-takings claim.
    Id. at
    ¶ 14. In one part of our decision,
    we framed the takings question as turning on whether the government had deprived
    the owner of all economically beneficial use of the property.
    Id. at
    ¶ 18. In another
    part of our decision, we framed the question as whether the company had suffered
    a “ ‘complete elimination of [the property’s] value.’ ”
    Id. at
    ¶ 22, 
    quoting Lingle at
    539. We ultimately rejected the company’s argument that the government’s denial
    of the permit destroyed “all economic value associated with its property,”
    determining instead that “there are other potential uses available for th[e] land.”
    (Emphasis added.) Shelly Materials at ¶ 39. We noted that the property could be
    used for agriculture purposes or developed into residential lots.
    Id. at
    ¶ 3.
    
           {¶ 113} Other authorities support this understanding of Lucas. According
    to a leading treatise on regulatory takings, “[t]he tenor of Lucas * * * continually
    reinforces the idea that ‘property’ consists of rights to use resources.” (Emphasis
    sic.) 1 Eagle, Regulatory Takings, Section 7-3(b)(5) (2018). While recognizing
    that the concept of value does appear in Lucas, the treatise explains that Lucas’s
    discussion of value “is coupled with economically beneficial use.”
    Id. This coupling arises
    from the fact that “[a] large component of property, and of its value,
    is the right to receive streams of income in the future.”
    Id. at
    Section 7-3(b)(6).
    {¶ 114} The same treatise further observes that the United States Court of
    Appeals for the Federal Circuit “has repeatedly found that a categorical taking is
    measured by complete deprivation of use, not value.”
    Id. at
    Section 7-3(b)(5). The
    United States Courts of Appeals for the Ninth and Fourth Circuits have applied
    Lucas’s rule in a similar way. See, e.g., Del Monte Dunes at Monterey, Ltd. v.
    43
    SUPREME COURT OF OHIO
    Monterey, 
    95 F.3d 1422
    , 1433 (9th Cir.1996) (“our focus is primarily on use, not
    value”), aff’d on other grounds, 
    526 U.S. 687
    , 
    119 S. Ct. 1624
    , 
    143 L. Ed. 2d 882
    (1999); Front Royal and Warren Cty. Indus. Park Corp. v. Front Royal, 
    135 F.3d 275
    , 286 (4th Cir.1998) (rejecting the claimant’s total-takings claim under Lucas
    because the claimant had not been denied “the right to use its property”).
    {¶ 115} Today’s decision creates friction with those authorities and does
    little to bring certainty to Ohio litigants, other than ensuring that their litigation
    costs will rise. The majority’s holding will now make it necessary for litigants to
    pay an expert to prepare an economic-impact statement to prosecute (or defend
    against) a total-takings claim brought under Lucas. Nor is the majority’s decision
    today likely to simplify matters for Ohio courts considering a total-takings claim.
    Rather than requiring courts to consider, as Lucas instructs, whether an owner has
    been forced to render his or her property economically idle by leaving it to its
    natural state (a simple enough inquiry), the courts will now be expected to sift
    through dense economic analyses and determine which litigant’s expert produced
    the more probative report. Nothing in Lucas requires that we leave these important
    questions of constitutional dimension in the hands of economists and corporate-
    strategy analysts.
    {¶ 116} The upshot of the majority’s decision today is that Ohio taxpayers
    might now be forced to bear the financial fallout of an inherently risky business
    venture.   Justice Holmes warned of such dangers long ago, observing that
    “[g]overnment hardly could go on if to some extent values incident to property
    could not be diminished without paying for every such change in the general law.”
    Pennsylvania Coal Co. v. Mahon, 
    260 U.S. 393
    , 413, 
    43 S. Ct. 158
    , 
    67 L. Ed. 322
    (1922). I fear that the majority’s decision today has lost sight of that principle.
    Partial-takings analysis
    {¶ 117} I turn now to the majority’s analysis of AWMS’s partial-takings
    claim and the factors to be applied to that claim derived from Penn Cent. Transp.
    44
    January Term, 2020
    Co. v. New York City, 
    438 U.S. 104
    , 
    98 S. Ct. 2646
    , 
    57 L. Ed. 2d 631
    (1978).
    Although I agree with the majority’s analysis of the factor in Penn Cent. examining
    the character of the governmental action and its conclusion that there is a genuine
    issue of material fact concerning the economic-impact factor, I would resolve the
    Penn Cent. inquiry solely on the basis of the reasonable-investment-backed-
    expectations factor.
    {¶ 118} I agree with a good portion of the majority’s analysis of the facts of
    this case under Penn Cent.’s reasonable-investment-backed-expectations factor.
    As the majority correctly points out, the government’s regulation of induced
    seismicity is an issue of enormous complexity. But, as the Federal Circuit noted in
    Good v. United States, we have a “growing consciousness of and sensitivity toward
    environmental issues,” with the result here being that AWMS “must * * * have
    been aware that standards could change to [its] detriment, and that regulatory
    approval could become harder to get.” 
    189 F.3d 1355
    , 1363 (Fed.Cir.1999). Given
    the added threat to public health and safety or damage to the environment arising
    from human-induced earthquakes, the majority properly finds that the balance of
    the investment-backed-expectations factor tips in the state’s favor.
    {¶ 119} Unlike the majority, however, I would go a step further and
    conclude that the balance tips decisively in the state’s favor, thus obviating the need
    to address the other Penn Cent. factors. That is precisely the approach that the
    Federal Circuit applied in Good when it held that “the government is entitled to
    summary judgment on a regulatory takings claim where the plaintiffs lacked
    reasonable, investment-backed expectations, even where the challenged
    government action ‘substantially reduc[ed] the value of plaintiff’s property.’ ”
    (Brackets sic.) Good at 1363, quoting Avenal v. United States, 
    100 F.3d 933
    , 937
    (Fed.Cir.1996). The Ninth Circuit Court of Appeals has applied a similar approach.
    See Guggenheim v. Goleta, 
    638 F.3d 1111
    , 1120 (9th Cir.2010) (according
    45
    SUPREME COURT OF OHIO
    dispositive status to its conclusion on the inquiry into reasonable investment-
    backed expectations).
    {¶ 120} The majority declines to accord controlling significance to the
    investment-backed-expectations factor. I find it problematic that while the majority
    has applied a large swath of the Federal Circuit’s takings jurisprudence in this case,
    it has chosen not to apply it, as the Federal Circuit did in Good, to conclusively
    resolve the Penn Cent. analysis on the basis of the expectations factor. I do not find
    the majority’s piecemeal approach to be particularly helpful. In order to better
    ensure predictability and uniformity in our takings jurisprudence, the majority
    should follow the approach taken by the Federal Circuit in Good.
    {¶ 121} More importantly, I find it problematic that the majority focuses on
    AWMS’s expectations at the time it obtained its leasehold—rather than at the time
    of its investment. An analysis of a claimant’s reasonable investment-backed
    expectations should necessarily involve consideration of the claimant’s
    expectations formed at the time of its investment. When an interest in real property
    is relevant in a takings case, the economic investment and the price of acquiring the
    property interest are normally one and the same. See, e.g., Love Terminal Partners,
    L.P. v. United States, 
    889 F.3d 1331
    , 1337, 1346 (Fed.Cir.2018) (claimant’s
    investment was $6.5 million spent to acquire the property interest). Not so here.
    {¶ 122} When AWMS obtained its leasehold in December 2011, its only
    “investment” was its promise to pay the lessor a 5 percent royalty on any revenue
    eventually derived from each well from brine disposal. AWMS’s actual investment
    occurred, as AWMS itself states, when it spent millions of dollars “constructing a
    state-of-the-art disposal [f]acility on the leasehold.” The actual investment did not
    start to take place until September 2013, long after the series of earthquakes that
    occurred in Youngstown, Ohio in December 2011, long after the division took the
    “Northstar #1” well out of operation for causing the earthquakes, and long after the
    statewide moratorium had been imposed on certain well-injection activities so that
    46
    January Term, 2020
    the division could study induced seismicity. At the time that AWMS’s actual
    investment occurred, AWMS explicitly acknowledged in its “confidential offering
    memorandum” that it knew that the government’s regulation of injection wells
    could increase in scope and complexity due to growing industry awareness, that
    AWMS’s wells could cause a seismic event similar to the events that had occurred
    in Youngstown, and that a seismic event caused by AWMS’s wells could lead to
    the suspension of its injection operations.
    {¶ 123} All three factors in the reasonable-expectations analysis weigh
    heavily in the state’s favor: AWMS operates in a highly regulated industry, it was
    aware that induced earthquakes had caused state regulation of an injection well in
    its property’s vicinity by the time of its investment, and it expressly anticipated the
    possibility of such regulation of its own wells at the time of its investment. See
    Apollo Fuels, Inc. v. United States, 
    381 F.3d 1338
    , 1349 (Fed.Cir.2004). Contrary
    to the majority’s conclusion, AWMS was absolutely forewarned that the division
    would regulate injection-well-induced earthquakes in the way that the division did.
    {¶ 124} Accordingly, after the division ordered AWMS to temporarily
    suspend its operations at well #2 due to the likelihood that AWMS’s operations had
    caused multiple earthquakes, the court of appeals correctly held that the suspension
    did not cause AWMS to suffer a total or partial regulatory taking. I therefore dissent
    and would affirm the judgment of the Eleventh District Court of Appeals.
    _________________
    Brouse McDowell, L.P.A., Matthew G. Vansuch, and Kyle A. Shelton, for
    appellants.
    Dave Yost, Attorney General, Samuel C. Peterson, Deputy Solicitor
    General, and Brett A. Kravitz and W. Scott Myers, Assistant Attorneys General,
    for appellees.
    _________________
    47
    

Document Info

Docket Number: 2019-0493

Citation Numbers: 2020 Ohio 4509

Judges: Fischer, J.

Filed Date: 9/23/2020

Precedential Status: Precedential

Modified Date: 9/23/2020

Authorities (35)

767 Third Avenue Associates and Sage Realty Corporation v. ... , 48 F.3d 1575 ( 1995 )

front-royal-and-warren-county-industrial-park-corporation-a-virginia , 135 F.3d 275 ( 1998 )

Tabb Lakes, Ltd. v. United States , 10 F.3d 796 ( 1993 )

Appolo Fuels, Inc. v. United States , 381 F.3d 1338 ( 2004 )

Commonwealth Edison Company v. United States , 271 F.3d 1327 ( 2001 )

Del Monte Dunes at Monterey, Ltd. v. City of Monterey, Del ... , 95 F.3d 1422 ( 1996 )

Rith Energy, Inc. v. United States , 247 F.3d 1355 ( 2001 )

Lloyd A. Good, Jr. v. United States , 189 F.3d 1355 ( 1999 )

Board of County Supervisors of Prince William County, ... , 276 F.3d 1359 ( 2002 )

Helen L. Cooley, William O. Cooley, and the 7c Company v. ... , 324 F.3d 1297 ( 2003 )

Dr. Ben Branch, Trustee of Bank of New England Corporation, ... , 69 F.3d 1571 ( 1996 )

palm-beach-isles-associates-a-florida-partnership-martin-slifka , 231 F.3d 1354 ( 2000 )

cienega-gardens-claremont-village-commons-covina-west-apartments-del-amo , 331 F.3d 1319 ( 2003 )

anne-d-wyatt-eastern-minerals-international-inc-van-buren-minerals , 271 F.3d 1090 ( 2001 )

Byrd v. City of Hartsville , 365 S.C. 650 ( 2005 )

Robert E. Morris and Carol L. Morris v. United States , 392 F.3d 1372 ( 2004 )

Albert J. Avenal, Jr., and 129 Similarly Situated v. United ... , 100 F.3d 933 ( 1996 )

Cienega Gardens v. United States , 503 F.3d 1266 ( 2007 )

Rose Acre Farms, Inc. v. United States , 559 F.3d 1260 ( 2009 )

Buckeye Union Ins. v. Consol. Stores , 68 Ohio App. 3d 19 ( 1990 )

View All Authorities »