Jindal Builders & Restoration Corp. v. Cincinnati Metro. Hous. Auth. , 2020 Ohio 4043 ( 2020 )


Menu:
  • [Cite as Jindal Builders & Restoration Corp. v. Cincinnati Metro. Hous. Auth., 2020-Ohio-4043.]
    IN THE COURT OF APPEALS
    FIRST APPELLATE DISTRICT OF OHIO
    HAMILTON COUNTY, OHIO
    JINDAL BUILDERS & RESTORATION :                             APPEAL NO. C-190217
    CORP.,                                                      TRIAL NO. A-1704087
    :
    Plaintiff-Appellant,
    :                                 O P I N I O N.
    vs.
    :
    CINCINNATI    METROPOLITAN :
    HOUSING AUTHORITY,
    Defendant-Appellee.                          :
    Appeal From: Hamilton County Court of Common Pleas
    Judgment Appealed From Is: Affirmed in Part, Reversed in Part, and Cause Remanded
    Date of Judgment Entry on Appeal: August 12, 2020
    Lindhorst & Dreidame Co., LPA, Barry F. Fagel and Elizabeth M. Mahon, for Plaintiff-
    Appellant,
    Adams, Stepner, Woltermann & Dusing, PLLC, and Jeffrey C. Mando, for Defendant-
    Appellee.
    OHIO FIRST DISTRICT COURT OF APPEALS
    BERGERON, Judge.
    {¶1}   Delays in construction projects are one of the banes of existence. In this case,
    a contractor and owner fence over who bears the risk of loss for delay, and whether
    overhead costs are recoverable as damages under the contract at hand. Although the trial
    court denied the contractor any relief, we conclude that it erred by prohibiting overhead
    damages, but that only part of the time period sought by the contractor is ultimately
    recoverable. We therefore reverse in part and remand for further proceedings.
    I.
    {¶2}   To fully appreciate the dispute in this case, we begin with an overview of the
    Millvale North Development Project in Cincinnati. Originally, in 2014, defendant-appellee
    Cincinnati Metropolitan Housing Authority (“CMHA”) undertook a rehabilitation project
    for several public housing buildings in its Millvale North development, awarding the
    entirety of this project to a third-party contractor. However, the original contractor proved
    not up to the task and could not finish the entire project, prompting CMHA to divide the
    contract into two phases—leaving the original contractor on Phase I, but searching for
    another contractor to complete Phase II. According to CMHA, it planned to transfer Phase
    II residents into the Phase I units upon its completion, thereby vacating the Phase II units
    for rehabilitation.   But, unfortunately for CMHA, even after the division, the original
    contractor continued to struggle, leading CMHA to conclude that if you want something
    done right, do it yourself, and thus it terminated that contractor and deemed itself the
    general contractor of Phase I. In the meantime, CMHA hunted for a contractor for Phase II,
    ultimately landing on plaintiff-appellant Jindal Builders & Restoration, Corp., (“Jindal”) in
    December 2015.
    {¶3}   Two months later, in February 2016, Jindal and CMHA entered into a
    contract for “construction and comprehensive modernization services at CMHA’s Millvale
    2
    OHIO FIRST DISTRICT COURT OF APPEALS
    North Development – Phase II, Buildings[.]” Within this contract, CMHA delineated the
    various aspects of Jindal’s obligations, including job responsibilities, payment, and the
    period of performance, requiring Jindal to complete the project within 365 days from the
    date established in the notice to proceed. Notably, nowhere within the contract did CMHA
    condition Jindal’s start date on Phase II to the completion of Phase I units or mandate
    Phase II residents relocate to Phase I units.
    {¶4}   The contract also incorporated several of the federal trappings ordinary to a
    government construction contract, including the Housing and Urban Development (“HUD”)
    general conditions for construction contracts awarded by public housing agencies. Relevant
    to this appeal, section 30 of the general conditions allows a contractor to recover damages
    for delays caused solely by the government-contracting officer—this section punctuated with
    caveats addressed in more depth below. As will become apparent, this section assumes
    significance since, after the parties signed the contract, a series of delays occurred resulting
    in Jindal not starting work until months after the anticipated start date.
    {¶5}   In April 2016, just two months after signing the contract, CMHA issued a
    notice to proceed, advising Jindal to begin work on April 18, 2016, and fixing the completion
    date as July 26, 2017. But Jindal did not arrive at the Phase II work site, equipment in
    hand, on April 18, and CMHA contends that both parties understood July 26 to be the true
    start date. Consequently, April 18 came and went, with CMHA continuing to labor away on
    Phase I until July 9 when CMHA discovered significant vandalism at those units. According
    to CMHA, this threw a wrench in its plan, leaving the residents in Phase II unable to
    decamp to Phase I until CMHA repaired and completed the Phase I units.
    {¶6}   As July 26 approached, Jindal’s project manager, Jeff Reams, reached out to
    CMHA’s construction contract supervisor, Ronald Veley, on July 20 inquiring about the
    3
    OHIO FIRST DISTRICT COURT OF APPEALS
    relocation of the Phase II residents. Mr. Veley optimistically, yet vaguely, responded that he
    hoped to complete the other two buildings in Phase I by the next week, but failed to provide
    an anticipated start date for Phase II. A few weeks elapsed, with Jindal still awaiting the
    relocation of the Phase II residents and unable to begin its work. Growing ever more
    concerned, Mr. Reams reached out again to CMHA, underscoring the urgency: “We bid this
    project in early December 2015 with an anticipated spring 2016 start time and based our bid
    numbers on that time frame. As of today August 16, 2016 we are still waiting on a start date
    * * * causing time delays and extra cost to complete this project * * *. Please give us an
    update on when we can expect to start this project so we can plan accordingly.” Reinforcing
    this concern, Mr. Reams followed up on August 17 and 18, pleading with CMHA to provide a
    start date, but to no avail—CMHA ignored these outreaches.
    {¶7}   Nearly a month passed before Mr. Reams and Anil Jindal, president of Jindal,
    both simultaneously reached out to CMHA on September 12, begging for direction on when
    the Phase II units would be vacated so Jindal could begin its work and emphasizing the
    ramifications of this delay on Jindal’s billings and bond program. Again, based on the
    record before us, CMHA offered nothing but silence as to the project’s status. Finally, on
    October 17, CMHA informed Jindal that it vacated all Phase II units and Jindal therefore
    could commence work. However, because Jindal had yet to acquire necessary permits for
    the work, Jindal did not begin its work until November 10 (or November 17, a date later
    claimed by Jindal).
    {¶8}   With the Phase II project finally underway, Jindal submitted various change
    orders. The first of these arrived on December 2, 2016, with Jindal seeking an adjustment
    for additional costs for the upcoming winter months (i.e., December, January, and
    February) incurred because of the delay to the start of the project, which CMHA in turn
    4
    OHIO FIRST DISTRICT COURT OF APPEALS
    denied. Jindal accordingly revised and resubmitted another change order on April 11, 2017,
    this time pursuing, under section 30 of the contract, overhead damages suffered during the
    delay between April and November 2016. A few weeks later, on April 29, Jindal revised the
    change order one last time, seeking damages for the same time period in different amounts,
    but this achieved the same result—CMHA denied both requests. In the wake of CMHA’s
    denials, Jindal filed suit against CMHA, alleging breach of contract and seeking recovery for
    overhead damages incurred for the delay between April and November 2016. Despite the
    pending lawsuit, Jindal ultimately completed the rehabilitation of the Phase II units and
    performed the contract in full.
    {¶9}   At the two-day bench trial, Jindal’s breach-of-contract claim against CMHA
    centered upon section 30 of the contract, i.e., the suspension of work clause:
    (b) If the performance of all or any part of the work is, for an unreasonable
    period of time * * * delayed * * * (1) by an act of the Contracting Officer in the
    administration of this contract, or (2) by the Contracting Officer’s failure to
    act within the time specified (or within a reasonable time if not specified) in
    this contract an adjustment shall be made for any increase in the cost of
    performance of the contract (excluding profit) necessarily caused by such
    unreasonable * * * delay * * * and the contract modified in writing
    accordingly. However, no adjustment shall be made under this clause for any
    * * * delay * * * to the extent that performance would have been so * * *
    delayed * * * by any other cause[.]
    (c) A claim under this clause shall not be allowed (1) for any costs incurred
    more than 20 days before the Contractor shall have notified the Contracting
    Officer in writing of the act or failure to act involved * * * and (2) unless the
    5
    OHIO FIRST DISTRICT COURT OF APPEALS
    claim, in an amount stated, is asserted in writing as soon as practicable after
    the termination of the * * * delay * * * but not later than the date of final
    payment under the contract.
    No one really disputes that a delay occurred here—the question more is who bears
    responsibility.   According to Jindal, CMHA solely caused the delay between April and
    November 2016, and thus, because Jindal provided CMHA with the requisite notice,
    CMHA’s unreasonable delay entitled Jindal to overhead damages incurred while it awaited
    the start of work on Phase II.
    {¶10} To support its case, Jindal presented testimony from Mr. Reams and Mr.
    Jindal, detailing the reasons for and consequences of the delay. This permitted, according
    to Jindal, recovery of overhead damages nearing $300,000, with a CPA testifying to the
    appropriateness of this amount. To rebut this evidence, CMHA’s construction contract
    supervisor, Mr. Veley, and director of real estate and construction, Joseph Norton, insisted
    that CMHA notified Jindal at the signing of the notice to proceed that, contrary to the date
    on the notice, the start date would actually be July 26. Further, CMHA shifted blame,
    asserting Jindal’s failure to obtain the necessary permits, the vandalism to Phase I, and the
    delay in completion of Phase I instead occasioned the seven-month delay.
    {¶11} Upon considering both parties’ evidence, the trial court ultimately sided with
    CMHA, finding in favor of CMHA and entering judgment for it. Specifically, the court found
    that Jindal could not recover because (1) section 30(b) does not permit recovery of general
    overhead damages, (2) the cause of delay was not CMHA, but instead relocation issues and
    vandalism, as well as Jindal’s failure to obtain the necessary permits—the court deeming all
    this events outside of CMHA’s control—and (3) Jindal failed to deliver the appropriate
    notice in compliance with section 30(c).      Jindal now appeals, challenging in a single
    6
    OHIO FIRST DISTRICT COURT OF APPEALS
    assignment of error all these findings and conclusions. Accordingly, we address each of
    these challenges in turn.
    II.
    {¶12} On appeal, Jindal challenges the trial court’s interpretation of the contract
    and its findings of fact, each necessitating its own standard of review. See MRI Software,
    L.L.C. v. West Oaks Mall FL, L.L.C., 2018-Ohio-2190, 
    116 N.E.3d 694
    , ¶ 10 (8th Dist.)
    (“Appellate review of a mixed question of fact and law requires an appellate court to give
    deference to a trial court’s factual findings if they are supported by competent, credible
    evidence, and to independently review whether the trial court properly applied the law to
    the facts.”). As to Jindal’s assertions that the court erred in its interpretation of section 30,
    this constitutes a matter of law, which we review de novo. See Ignazio v. Clear Channel
    Broadcasting, Inc., 
    113 Ohio St. 3d 276
    , 2007-Ohio-1947, 
    865 N.E.2d 18
    , ¶ 19 (“But the
    interpretation of a contract is a matter of law that we review de novo.”); Western and
    Southern Life Ins. Co. v. Bank of New York Mellon, 2019-Ohio-388, 
    129 N.E.3d 1085
    , ¶ 6
    (1st Dist.) (“This court reviews the interpretation of a contract de novo.”).
    {¶13} But as to Jindal’s challenges to the court’s factual findings, we instead
    “presume that the findings of the trier of fact are correct,” given the court’s opportunity to
    view the witnesses and observe their demeanor. Lehigh Gas-Ohio L.L.C. v. Cincy Oil Queen
    City, L.L.C., 1st Dist. Hamilton No. C-130127, 2014-Ohio-2799, ¶ 44; see Tidewater Fin. Co.
    v. Cowns, 
    197 Ohio App. 3d 548
    , 2011-Ohio-6720, 
    968 N.E.2d 59
    , ¶ 11 (1st Dist.), quoting
    Lucero v. Ohio Dept. of Rehab. & Corr., 10th Dist. Franklin No. 11AP-288, 2011-Ohio-6388,
    ¶ 16, quoting Seasons Coal Co., Inc. v. City of Cleveland, 
    10 Ohio St. 3d 77
    , 80, 
    461 N.E.2d 1273
    (1984) (“ ‘In an appeal from a bench trial, a reviewing court must presume that the
    factual findings of the trial judge are correct because the trial judge had an opportunity “to
    7
    OHIO FIRST DISTRICT COURT OF APPEALS
    view the witnesses and observe their demeanor, gestures and voice inflections, and use
    these observations in weighing the credibility of the proffered testimony.” ’ ”). Accordingly,
    we afford due deference to the court as the finder of fact, evaluating whether “some
    competent and credible evidence” supports the court’s findings. MRI Software at ¶ 12 (“A
    reviewing court must, therefore, accord due deference to the credibility determinations
    made by the fact finder.”); see Roark v. Rydell, 
    174 Ohio App. 3d 186
    , 2007-Ohio-6873, 
    881 N.E.2d 333
    , ¶ 54 (1st Dist.) (“Our review of the trial court’s factual determinations is highly
    deferential.”).
    III.
    A.
    {¶14} We begin with Jindal’s assertion that the court improperly interpreted section
    30 to prohibit recovery of general overhead costs, which we review de novo. See Ignazio at
    ¶ 19. Jindal contends that section 30(b) entitles it to recover damages in the form of
    overhead costs arising out of the delay that increased the overall cost of performance, not
    just actual work done, as the trial court found.
    {¶15} As in any contractual dispute, our “primary objective is to ascertain and give
    effect to the parties’ intent,” searching the language the parties selected for clues. Wal-Mart
    Realty Co. v. Tri-County Commons Assocs., LLC, 1st Dist. Hamilton No. C-160747, 2017-
    Ohio-9280, ¶ 10. And the parties here elected to incorporate HUD’s general conditions for
    construction contracts, i.e., form HUD-5370, section 30 that we quoted above.
    {¶16} Specifically, section 30(b) permits a contractor to recover for “any increase in
    the cost of performance of the contract (excluding profit),” if the contractor’s performance
    of all or any part of the work is, for an unreasonable period of time, delayed by the
    contracting officer’s act or failure to act. Stated differently, if a contractor incurs increased
    8
    OHIO FIRST DISTRICT COURT OF APPEALS
    costs by virtue of an act or failure to act by the contracting officer that effectively delays the
    contractor’s ability to perform the contract, then section 30 permits recovery of those
    additional costs. See George Sollitt Const. Co. v. United States, 
    64 Fed. Cl. 229
    , 236-237
    (2005) (finding that “[i]f the contractor suffers increased costs because of government
    action or inaction which effectively suspends the contractor’s progress on contract work,
    [the suspension of work] clause may provide a remedy.”). Notably, section 30(b) explicitly
    excludes “profit” from its scope, barring a contractor from recuperating lost profit arising
    out of the contracting-officer-caused delay. See Maki v. United States, 13 Cl.Ct. 779, 783
    (1987) (interpreting an identical suspension of work clause to “expressly exclude[] claims
    for lost ‘profit.’ ”). Consequently, under section 30, a contractor may seek recovery for
    additional costs to its performance directly stemming from the contracting-officer-caused
    delay, as long as that additional cost is not profit.
    {¶17} And this makes sense, as it is well-established that when performing a
    contract, a contractor incurs not only direct costs, but also indirect costs. See Complete
    Gen. Constr. Co. v. Ohio Dept. of Transp., 
    94 Ohio St. 3d 54
    , 57, 
    760 N.E.2d 364
    (2002)
    (explaining “construction projects incorporate two different kinds of costs,” specifically
    direct and indirect costs).      As to the former, direct costs include expenses “directly
    attributable to the performance of a specific contract”—i.e., equipment expenses,
    construction wages, etc. Nicon, Inc. v. United States, 
    331 F.3d 878
    , 882 (Fed.Cir.2003); see
    Complete Gen. at 57. By contrast, indirect costs consist of expenses generally involved in
    running a business, and thereby not attributable to any one project—overhead expenses the
    most significant indirect cost among them. See J & H Reinforcing & Structural Erectors,
    Inc. v. Ohio School Facilities Comm., 10th Dist. Franklin No. 12AP-588, 2013-Ohio-3827, ¶
    100, citing Complete Gen. at 57; Altmayer v. Johnson, 
    79 F.3d 1129
    , 1132 (Fed.Cir.1996)
    9
    OHIO FIRST DISTRICT COURT OF APPEALS
    (“Home office overhead costs are those that are expended for the benefit of the whole
    business, which by their nature cannot be attributed or charged to any particular contract.”).
    Because overhead costs include expenses such as salaries of executive or administrative
    personnel, general insurance, rent, interest on loans, etc., contractors generally spread
    overhead costs “proportionally across ongoing projects.” City of Cincinnati v. Triton Servs.,
    Inc., 2019-Ohio-3108, 
    140 N.E.3d 1249
    , ¶ 53 (1st Dist.); see Charles G. Williams Const., Inc.
    v. White, 
    271 F.3d 1055
    , 1058 (Fed.Cir.2001), quoting West v. All State Boiler, Inc., 
    146 F.3d 1368
    , 1372 (Fed.Cir.1998) (“ ‘A contractor recovers its indirect costs by allocating them on a
    proportionate basis among all of its contracts.”). Consequently, “[w]hen a delay occurs on a
    particular construction project, that particular project ceases to carry its weight in regard to
    running the business, which can result in damages to the contractor.” Complete Gen. at 57.
    In other words, a delay can render the contractor’s overhead costs unabsorbed, with the
    billings for that project failing to cover its apportioned amount. See Triton Servs. at ¶ 53
    (“When an owner-caused delay substantially diminishes a project’s cash flow, the
    contractor’s fixed overhead costs are not absorbed by the delayed project[.]”); Nicon at 882,
    quoting C.B.C. Ents., Inc. v. United States, 
    978 F.2d 669
    , 671 (Fed.Cir.1992) (“[W]hen the
    government causes a delay or suspension of performance, this ‘decreases the stream of
    direct costs against which to assess a percentage rate for reimbursement.’ ”).
    {¶18} Contemplating this problem, both Ohio and federal courts generally permit
    contractors to recover general overhead costs arising out of a government-caused delay. See
    All State Boiler at 1370 (interpreting an identical suspension of work clause to allow the
    contractor to recover unabsorbed overhead costs resulting from the government-caused
    delay); Complete Gen. at 57 (discerning the appropriate formula to apply when calculating
    damages for overhead costs incurred but unabsorbed due to the government-caused delay);
    10
    OHIO FIRST DISTRICT COURT OF APPEALS
    Wood Elec., Inc. v. Ohio Facilities Constr. Comm., 2017-Ohio-2743, 
    90 N.E.3d 371
    , ¶ 36
    (10th Dist.) (affirming the court’s application of the HOOP formula to calculate the
    contractor’s home office overhead damages arising out of the government-caused delay);
    Stockton E. Water Dist. v. United States, 
    109 Fed. Cl. 760
    , 799 (2013) (“Courts also have
    awarded damages for overhead expenses when the Government imposed a delay or
    suspension of the contract work and thereby interrupted or reduced the contractor’s stream
    of income.”).
    {¶19} With this backdrop in mind, we turn to the contract at hand, observing no
    prohibition in section 30 for recovery of overhead damages. In fact, the plain language bars
    only one type of damages from its purview, specifically “profit.” Given the ubiquity of
    overhead costs in the construction industry and the well-chronicled case law on this point, it
    seems more than reasonable to conclude that if the parties intended to limit recovery of
    overhead costs, the language would reflect as much. See Dellagnese Const. Co. v. Nicholas,
    9th Dist. Summit No. 22951, 2006-Ohio-4350, ¶ 12 (“By expressing these specific
    limitations on appellee’s recovery, the parties impliedly excluded other limitations.”).
    {¶20} Bolstering this point, other provisions within the contract contemplate such
    distinctions between direct costs, indirect costs, and profit.       For instance, section 29,
    governing change orders, similarly permits equitable adjustments to the contract,
    delineating the expenses within its purview: “The Contractor’s written proposal for
    equitable adjustment shall be submitted in the form of a lump sum proposal supported with
    an itemized breakdown of all increases and decreases in the contract in at least the following
    details: (1) Direct Costs * * * (2) Indirect Costs * * * (3) Profit[.]” In light of section 29, we
    conclude that the parties certainly appreciated the distinctions between recoverable
    expenses, and therefore intended to exclude only “profit,” not indirect costs (such as
    11
    OHIO FIRST DISTRICT COURT OF APPEALS
    overhead), from section 30’s scope. Accordingly, we read section 30 to allow recovery of
    overhead damages, as long as the contractor meets the additional requirements nestled in
    the suspension of work clause (i.e., causation and timely notice). We thus find that the trial
    court erred in interpreting section 30 to the contrary.
    B.
    {¶21} Although overhead damages are indeed recoverable under section 30, Jindal’s
    journey is not yet complete, with section 30 necessitating that it clear two more hurdles
    before recovering—causation and timely notice. Regarding causation, section 30 does not
    permit a contractor to obtain overhead damages for just any delay, but specifically one that
    the contracting officer solely caused. Consequently, because Jindal seeks overhead damages
    stemming from a series of delays between April and November 2016, each delay must
    necessarily arise out of the action or inaction of CMHA. Underscoring that point, section
    30(b) explains, “[h]owever, no adjustment shall be made under this clause for any
    suspension, delay, or interruption to the extent that performance would have been so
    suspended, delayed, or interrupted by any other cause, including the fault or negligence of
    the Contractor[.]” Based on the plain language of section 30(b), a contractor may only
    recover for costs under this provision if the contracting officer is the sole cause of the
    delay—with concurrent delay occasioned by the negligence or fault of the contractor or
    another barring relief. See MW Builders, Inc. v. United States, 
    134 Fed. Cl. 469
    , 508 (2017),
    quoting (Emphasis sic.) Triax-Pacific v. Stone, 
    958 F.2d 351
    , 354 (Fed.Cir.1992) (reasoning
    an identical suspension of work clause requires the contracting officer be “ ‘the sole
    proximate cause of the contractor’s additional loss, and the contractor would not have been
    delayed for any other reason during that period.’ ”). Consequently, “even if the government
    has caused an unreasonable delay to contract work, that delay will not be compensable if the
    12
    OHIO FIRST DISTRICT COURT OF APPEALS
    contractor, or some other factor not chargeable to the government, has caused a delay
    concurrent with the government-caused delay.” George Sollitt Const. 
    Co., 64 Fed. Cl. at 238
    ;
    see MW Builders at 508 (“[T]he contractor may not recover, if there is a concurrent delay
    caused by the contractor or some other third party.”).
    {¶22} Here, the trial court concluded that section 30 “only allows for recovery of
    delay damages which are directly caused by CMHA[.]” Applying this provision of the
    contract, the court then attributed the delay to “vandalism and relocation issues and Jindal’s
    failure to serve permits, all of which were outside of CMHA’s control,” which thus excused
    CMHA of responsibility. On appeal, Jindal challenges several of the trial court’s findings
    concerning causation. Specifically, Jindal contends the trial court erred when it found that
    (1) July 26, 2016, not April 18, was the actual start date, (2) Jindal was unprepared to begin
    work on April 18, (3) the contract conditioned the commencement of Phase II on the
    completion of Phase I, and (4) the delay between April and November was not caused by
    CMHA. For ease in addressing these challenges, we divide the delay into three separate
    periods: (1) April 18 to July 26, (2) July 27 to October 17, and (3) October 18 to November
    10, and consider each accordingly.
    1.
    {¶23} We turn first to the period between April 18 and July 26. According to Jindal,
    the triggering event for the seven-month delay occurred in April 2016, when CMHA issued
    its notice to proceed, advising Jindal to commence work on April 18, but CMHA failed to
    relocate the residents from the Phase II units. Disagreeing, the trial court identified July 26
    as the start date, meaning that no delay existed between April and July that would enable
    Jindal to recover. In light of the competent, credible evidence supporting this finding, we
    agree. See MRI Software, 2018-Ohio-2190, 
    116 N.E.3d 694
    , at ¶ 10.
    13
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶24} At trial, CMHA’s director of real estate and construction, Mr. Norton,
    maintained Jindal understood that the start date was July 26, testifying CMHA “told [Mr.]
    Jindal at that signing of the Notice to Proceed that he would not be starting until July.”
    Following suit, CMHA’s construction contract supervisor, Mr. Veley, testified that, not only
    did CMHA inform Jindal of the July start date, but the notice to proceed reflected as much.
    Specifically, Mr. Veley clarified that, although the notice declared April 18 as the start date,
    the notice also established July 26, 2017, (i.e., 465 days after April 18) as the completion
    date. Accordingly, because the contract contemplated completion within 365 days from the
    date advised in the notice to proceed, Mr. Veley explained, CMHA added a hundred days to
    the April 18 date (i.e., July 26) to allow 365 days for Jindal to complete the project—
    otherwise April 18, 2017, would have been the completion date reflected in the notice to
    proceed (instead of July 26, 2017). The parties thus understood this delay and agreed to it
    contractually.
    {¶25} While Jindal counters with protestations that its officers lacked any memory
    of CMHA informing it of the July start date, Mr. Reams conceded that not only did Jindal
    fail to show up on April 18 with equipment ready to break ground, but between April and
    May it also never mustered any complaints about this “delay.” Mr. Jindal echoed the point,
    acknowledging that Jindal issued no complaints the first few months (i.e., April, May, and
    June) regarding its inability to begin work on April 18 or shortly thereafter.             This
    nonchalance about the delay in April, May, and June reinforces the conclusion that Jindal
    did not truly believe April 18 was the start date for its work on the Phase II units, all of
    which comports with the contractual time period contained in the agreement. Bolstering
    this point, Jindal also failed to tender the requisite notice as to this April to July period
    pursuant to section 30(c)(1). In fact, as discussed in more depth below, Jindal’s first written
    14
    OHIO FIRST DISTRICT COURT OF APPEALS
    notification did not arrive until mid-August, well beyond the 20-day period beginning on
    April 18 when Jindal would have first discovered its inability to commence work.
    {¶26} In light of the above, competent, credible evidence supported the trial court’s
    finding that July 26 was the actual start date, not April 18. We accordingly conclude Jindal
    cannot recover any overhead damages for the period between April 18 and July 26.
    2.
    {¶27} As to the second interval, July 27 to October 17, we reach a different
    conclusion. Premised on a July 26 start date (as explained above), Jindal’s work on Phase II
    nevertheless did not commence on this date. Siding with CMHA, the trial court blamed
    vandalism and relocation issues, as well as Jindal’s failure to obtain permits, for this delay,
    deeming these issues “outside of CMHA’s control.” In doing so, the trial court found that
    the “[r]enovation and rehabilitation of the Phase I units needed to be completed first so that
    tenants in the Phase II units could be moved into them while the Phase II units were being
    renovated,” and that the “vandalism of the Phase I units prevented CMHA from releasing
    Jindal to start work on the Phase II units[.]”
    {¶28} Jindal mounts two challenges to the court’s conclusions concerning this
    second period—the first contesting the court’s determination that the commencement of
    Phase II was contingent upon the completion of Phase I, and the second, challenging the
    court’s finding that the vandalism and relocation issues were out of CMHA’s control.
    Turning to the former, Jindal asserts that nowhere in the contract does a provision exist
    conditioning the start of Phase II on the completion of Phase I. And we agree. One can
    search the contract in vain for any language conditioning Jindal’s work on the Phase II units
    on Phase I’s completion or on CMHA relocating the Phase II residents specifically to the
    15
    OHIO FIRST DISTRICT COURT OF APPEALS
    Phase I units. CMHA certainly could have baked this condition into the contract, but it did
    not—and its efforts to reallocate the risk of loss at this juncture fall short.
    {¶29} Reinforcing the point, other than some testimony from CMHA regarding an
    obscure “plan,” the record is devoid of any evidence that Phase II’s commencement was
    contingent on Phase I’s competition (reflecting the contractual absence as well). Nor was
    this something of which CMHA should have been unaware—it served as the general
    contractor for Phase I. Absent a carve-out in the contract, no reason exists why Jindal
    should have understood that Phase I served as a type of prerequisite to launch Phase II. To
    the extent that the trial court interpreted the contract to require that renovation of “the
    Phase I units needed to be completed first so that tenants in the Phase II units could be
    moved into them,” we find that it erred.
    {¶30} This brings us to Jindal’s second challenge in regard to the July to October
    delay period—the court’s conclusion that CMHA was not the sole cause of the delay.
    Ordinarily, vandalism would seem to fall into the “any other cause” category under section
    30, and therefore absolve CMHA of responsibility for the delay. See Section 30(b) of the
    contract (“However, no adjustment shall be made under this clause for any * * * delay * * *
    to the extent that performance would have been so * * * delayed * * * by any other
    cause[.]”); MW 
    Builders, 134 Fed. Cl. at 508
    , quoting (Emphasis sic.) 
    Triax-Pacific, 958 F.2d at 354
    (“[A] contractor may recover for an unreasonable delay, if the Government is ‘the sole
    proximate cause of the contractor’s additional loss, and the contractor would not have been
    delayed for any other reason during that period.’ ”). But here, the vandalism did not occur
    to Jindal’s contractually designated project, the Phase II units, but instead to a wholly
    separate project, the Phase I units. We would likely reach a different result if vandalism
    damaged Phase II and prevented construction there from going forward. Nevertheless, the
    16
    OHIO FIRST DISTRICT COURT OF APPEALS
    damage to the Phase I units cannot shield CMHA from fault in failing to relocate the Phase
    II residents here when, as discussed above, Phase I’s completion held no bearing on Jindal’s
    work on Phase II.
    {¶31} Nor may CMHA seek to shift any blame for this delay to Jindal’s failure to
    obtain permits. At trial, both of CMHA’s employees conceded that relocation and vandalism
    caused the delay between July and October, with Mr. Norton admitting that the relocation
    of the Phase II residents and the vandalism to Phase I were “the only cause of delay,” at least
    until CMHA released the Phase II units to Jindal on October 17. Further, both Mr. Norton
    and Mr. Veley agreed that Jindal’s failure to obtain the necessary permits did not cause this
    period of delay. And Mr. Norton conceded that “CMHA [was] in control of the relocation,”
    thereby recognizing CMHA’s responsibility in relocating the Phase II residents. Needless to
    say, even if Jindal had the permits in hand, CMHA would not have allowed it to commence
    work prior to October 17.
    {¶32} Therefore, we conclude that the court below erred when it determined that
    the vandalism to the Phase I units and the relocation of the Phase II residents fell “outside
    of CMHA’s control” and that Jindal’s failure to obtain permits caused the delay—at least
    with respect to this July to October period. Based on an application of the contract at hand
    to the facts of this case, we see no other cause “concurrent with the government-caused
    delay.” See George Sollitt Const. 
    Co., 64 Fed. Cl. at 238
    (“[E]ven if the government has
    caused an unreasonable delay to contract work, that delay will not be compensable if the
    contractor, or some other factor not chargeable to the government, has caused a delay
    concurrent with the government-caused delay.”). We accordingly find that CMHA’s failure
    to relocate the Phase II residents in order to enable Jindal to commence work solely caused
    the delay between July 27 and October 17. Therefore, Jindal may recover for overhead
    17
    OHIO FIRST DISTRICT COURT OF APPEALS
    damages incurred for this period pursuant to section 30 of the contract if it provided
    suitable notice (which we will address below).
    3.
    {¶33} As to the third temporal period (between October 18 and November 10), we
    find that Jindal bears at least some responsibility for this delay. As noted above, on October
    17, CMHA released the Phase II units to Jindal to begin construction. But Jindal had yet to
    acquire the necessary permits for it to commence work. It did not acquire these permits
    until November 2, which prevented it from commencing work before November 10.
    Obtaining the permits fell on Jindal’s shoulders, with the specifications in the contract
    designating this duty to the contractor. Further, at trial, Mr. Jindal admitted as much,
    conceding that the contract directed Jindal to acquire the permits and that CMHA would
    then reimburse Jindal for these costs. The delay between October and November was
    accordingly “the fault or negligence of” Jindal, not some act or failure to act by CMHA, thus
    barring Jindal from recovering overhead damages during this period under section 30 of the
    contract. See Section 30 of the contract (“However, no adjustment shall be made under this
    clause for any * * * delay * * * to the extent that performance would have been so * * *
    delayed * * * by any other cause, including the fault or negligence of the Contractor[.]”).
    {¶34} In sum, we conclude that Jindal cannot recover overhead damages for the
    first period between April 18 and July 26, since no delay occurred during this time, nor can
    it recover for the third interval between October 18 and November 10, as Jindal caused the
    delay for this period. This leaves the delay between July 27 and October 17 the only
    compensable period, as long as Jindal satisfied the notice requirements contained within
    section 30(c).
    18
    OHIO FIRST DISTRICT COURT OF APPEALS
    C.
    {¶35} This brings us to the last hurdle Jindal must clear in order to recover
    overhead damages for the period of delay between July 27 and October 17—timely notice as
    outlined in section 30(c). Pursuant to section 30(c), a claim is not allowed
    (1) for any costs incurred more than 20 days before the Contractor shall
    have notified the Contracting Officer in writing of the act or failure to act
    involved (but this requirement shall not apply as to a claim resulting from
    a suspension order); and, (2) unless the claim, in an amount stated, is
    asserted in writing as soon as practicable after the termination of the * * *
    delay * * * but not later than the date of final payment under the contract.
    {¶36} Although the parties debate whether this clause imposes two conjunctive
    requirements or disjunctive ones, the plain language settles this dispute, with section 30(c)
    obligating the contractor to comply with two separate notice requirements for timely filing
    its claim, as the case law confirms. See Hoel-Steffen Constr. Co. v. United States, 
    197 Ct. Cl. 561
    , 
    456 F.2d 760
    , 766 (1972) (holding that, because the board failed “to heed the different
    nature of the two separate notice requirements in the suspension clause,” it ultimately erred
    when it found the contractor failed to timely submit its claim for the government-caused
    delay within the 20-day period). As to the first requirement, set forth in section 30(c)(1),
    the contractor cannot recover for costs incurred more than 20 days before the contractor
    should have notified the contracting officer in writing of the act or failure to act involved.
    Stated differently, once the contractor knows of the contracting officer’s act or failure to act
    causing delay, section 30(c)(1) demands written notification to the contracting officer within
    20 days. Consequently, section 30(c)(1) aims to place the contracting officer on notice that
    a condition exists that is delaying the contractor’s performance, which then enables it to
    19
    OHIO FIRST DISTRICT COURT OF APPEALS
    remedy the situation. See
    id. (interpreting a nearly
    identical suspension of work clause
    mandating notice within 20 days to be directed “only at notification to the defendant ‘of the
    act or failure to act involved.’ ”).
    {¶37} On the other hand, section 30(c)(2) endeavors to quantify the contractor’s
    claim, requiring the contractor to provide a “written monetary claim” detailing the costs
    incurred. See
    id. (“The latter of
    the two is that there must be a written monetary claim ‘in an
    amount stated * * * as soon as practicable after the termination of such suspension, delay, or
    interruption[.]’ * * * The other notice specification * * * is not directed at the presentation of
    a monetary claim in connection with the suspension clause, but only at notification to the
    defendant ‘of the act or failure to act involved.’ ”). Notably, the contractor need not tender
    this “written monetary claim” within 20 days of experiencing the increased costs, but
    instead “as soon as practicable after the termination of” the delay.
    {¶38} Interpreting section 30(c), the trial court here ultimately found that, because
    Jindal did not provide a written request for delay damages until December 2, 2016, section
    30(c) barred Jindal from recovering any reimbursement for delay damages incurred.
    However, in doing so, the trial court conflated the two notice requirements, subjecting
    Jindal’s “written monetary claim” to the 20-day requirement specified in section 30(c)(1).
    See Hoel-Steffen at 766 (finding the board erroneously transformed the 20-day notice
    requirement “into a provision for the filing by the contractor of a specific monetary claim
    under the suspension clause within 20 days of experiencing the increased costs.”). But, as
    discussed above, Jindal needed only to submit written notification (not a full claim
    delineating costs incurred) within 20 days from when it should have notified CMHA of the
    outset of the delay. And this makes sense—the purpose of the first provision is to place the
    contracting officer on notice in order to ameliorate any damage, and it would be unrealistic
    20
    OHIO FIRST DISTRICT COURT OF APPEALS
    to expect the contractor to completely itemize all of its damages on such short notice
    (particularly when the harm might be on-going).
    {¶39} Upon review of the record, we find that Jindal satisfied the notice
    requirements for the period between July 27 and October 17. As established above, July 26
    represented the actual start date for Phase II.         Jindal satisfied the 20-day notice
    requirement by sending various emails in mid-August notifying CMHA of Jindal’s inability
    to begin work on Phase II and warning of the increased costs that would be incurred from
    this delay. Without receiving adequate responses from CMHA, Jindal continued to pepper
    it with notices of Jindal’s objections to the delay and the specter of damages resulting from
    the delay throughout September.
    {¶40} This constitutes sufficient written notice to CMHA under section 30(c). Once
    Jindal notified CMHA of this delay, CMHA had the ability to try to mitigate any damages
    and to try to resolve the delay. See 
    Hoel-Steffen, 456 F.2d at 766
    (“[The] inquiry is simply
    whether the contractor put the [g]overnment on notice of the government conduct
    complained about, so that the procurement officials could begin to collect data on the
    asserted increase in cost, and could also evaluate the desirability of continuing the delay-
    causing conduct.”); K-Con Bldg. Systems, Inc. v. United States, 
    114 Fed. Cl. 595
    , 605 (2014),
    quoting Calfon Constr., Inc. v. United States, 18 Cl.Ct. 426, 438 (1989) (discussing the
    purpose of the written notification requirement is to inform the government contracting
    officer “ ‘before such time that the Government would suffer if not apprised of the facts.’ ”).
    Accordingly, we find that Jindal sufficiently notified CMHA under section 30(c)(1) of the
    contract.
    {¶41} Turning to the latter requirement under section 30(c)(2), Jindal also needed
    to provide CMHA with a written monetary claim “as soon as practicable” after the
    21
    OHIO FIRST DISTRICT COURT OF APPEALS
    termination of the delay, but “not later than the date of final payment under the contract.”
    As noted by the trial court, on December 2, 2016, Jindal submitted its first written monetary
    claim describing increased costs stemming from the delay.            But this filing concerned
    increased expenses for future months, rather than the unabsorbed overhead costs that form
    the basis of this appeal. In fact, it was not until April 11, 2017, that Jindal provided a written
    claim quantifying the unabsorbed overhead costs arising out of delay between April 18 and
    November 10, 2016.
    {¶42} Although this notice came five months after Jindal commenced work, based
    on the facts of this case, we find that Jindal tendered CMHA its written claim for overhead
    damages “as soon as practicable” after the termination of the delay pursuant to section
    30(c)(2), especially in light of Jindal’s hiring a CPA to calculate the overhead damages for
    the relevant period. See 
    Hoel-Steffen, 456 F.2d at 766
    (finding the contractor’s $150,000
    claim submitted a little over eight months after the termination of the delay satisfied the “as
    soon as practicable” requirement). Certainly, it tendered this claim well in advance of “final
    payment.” Therefore, because Jindal satisfied the pair of notice requirements in regards to
    the delay period between July 27 and October 17, we find the trial court erred in concluding
    Jindal’s claim was untimely under section 30(c).
    D.
    {¶43} Based on the above, we hold that Jindal may recover for overhead damages
    stemming from the CMHA-caused delay between July 27 and October 17, and accordingly
    remand the cause for the trial court to determine the amount of Jindal’s overhead damages.
    As to how to calculate these overhead damages, we leave that to the able discretion of the
    trial court below, as Ohio courts do not compel any particular approach.
    22
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶44} On the one hand, Ohio courts, including the Ohio Supreme Court, have
    gravitated towards the Eichleay formula to calculate unabsorbed overhead costs arising out
    of government-caused delay. See Triton Servs., 2019-Ohio-3108, 
    140 N.E.3d 1249
    , at ¶ 54,
    quoting Complete 
    Gen., 94 Ohio St. 3d at 55
    , 
    760 N.E.2d 364
    (“[Eichleay] is ‘the most well-
    known formula for calculating unabsorbed overhead’ costs arising out of government-
    caused delay.”). Originally established in the context of federal government construction
    contracts, the Eichleay formula “creates a per diem rate for overhead costs attributable to a
    single project, multiplying that rate by the number of days of delay to arrive at a total home
    office overhead award.” (Emphasis sic.) Complete Gen. at 58, citing Wickham Contracting
    Co., Inc. v. Fischer, 
    12 F.3d 1574
    , 1577 (Fed.Cir.1994), fn. 3. The Eichleay formula also
    carries two substantive prerequisites: the contractor must demonstrate that (1) it was on
    standby, and (2) it was unable to take on other work during this standby period.
    Id. at 58;
    All State 
    Boiler, 146 F.3d at 1373-1375
    .
    {¶45} However, as this court emphasized in Triton Services, the Eichleay formula is
    but one way to determine unabsorbed home-office-overhead damages. See Triton Servs. at
    ¶ 54; Complete Gen. at 61 (“We find today that the Eichleay formula is one way of
    determining unabsorbed home office overhead damages in public construction delay
    cases.”). Consequently, a trial court maintains discretion in calculating overhead damages
    resulting from government-caused delay, with the Eichleay formula but one arrow in its
    quiver. See J & H Reinforcing, 10th Dist. Franklin No. 12AP-588, 2013-Ohio-3827, at ¶ 106
    (holding the “Eichleay formula is discretionary,” and thus “the referee acted within its
    discretion in applying a formula other than the Eichleay formula in calculating home office
    overhead damages.”); Wood Elec., 2017-Ohio-2743, 
    90 N.E.3d 371
    , at ¶ 36 (affirming the
    trial court’s use of the HOOP formula when calculating overhead damages caused by delays
    23
    OHIO FIRST DISTRICT COURT OF APPEALS
    and finding no error in the trial court’s failure to require proof of the Complete Gen. factors
    prior to considering the HOOP method). We leave it to the trial court below on remand to
    calculate, within its discretion, Jindal’s overhead damages arising out of the period of delay
    between July 27 and October 17 if the parties prove unable to stipulate to the amount.
    IV.
    {¶46} For the forgoing reasons, we affirm in part and reverse in part the judgment
    rendered in favor of CMHA, and we remand the matter to the trial court. Specifically, we
    affirm the portion of the trial court’s judgment that found Jindal could not recover for
    overhead damages for the April 18 to July 26 and October 18 to November 10 periods, and
    we accordingly overrule Jindal’s single assignment of error in this respect. However, we
    reverse the court’s conclusion that Jindal could not recover overhead damages for the
    period of delay between July 27 and October 17, and therefore, we sustain Jindal’s sole
    assignment of error in part. Therefore, in light of our disposition, we remand the cause for
    the trial court to calculate the overhead damages arising out of the CMHA-caused delay
    between July 27 and October 17.
    Judgment accordingly.
    MYERS, P. J., and WINKLER, J., concur.
    Please note:
    The court has recorded its entry on the date of the release of this opinion
    24