Jurgensen Co. v. Fairborn , 2015 Ohio 5478 ( 2015 )


Menu:
  •       [Cite as Jurgensen Co. v. Fairborn, 
    2015-Ohio-5478
    .]
    IN THE COURT OF APPEALS
    FIRST APPELLATE DISTRICT OF OHIO
    HAMILTON COUNTY, OHIO
    JOHN R. JURGENSEN COMPANY,                        :      APPEAL NO. C-140556
    TRIAL NO. A-0800003
    Plaintiff-Appellant,                         :
    vs.                                         :           O P I N I O N.
    CITY OF FAIRBORN, OHIO,                           :
    Defendant-Appellee.                          :
    Civil Appeal From: Hamilton County Court of Common Pleas
    Judgment Appealed From Is: Affirmed
    Date of Judgment Entry on Appeal: December 30, 2015
    Frantz Ward LLP, Andrew J. Natale and Nora E. Loftus, for Plaintiff-Appellant,
    Williams & Petro Co. LLC, John P. Petro and Susan S. R. Petro, for Defendant-
    Appellee.
    Please note: this case has been removed from the accelerated calendar.
    OHIO FIRST DISTRICT COURT OF APPEALS
    C UNNINGHAM , Presiding Judge.
    {¶1}    Plaintiff-appellant, the John R. Jurgensen Company, appeals from the
    trial court’s entry denying it summary judgment on its claims that defendant-
    appellee, the City of Fairborn, Ohio, had breached its road-improvement contract
    when it refused to pay Jurgensen an asphalt-binder price adjustment found in an
    Ohio   Department     of   Transportation    (“ODOT”)     construction   and   material
    specification. Because the parties’ agreement did not incorporate the asphalt-binder
    price adjustment and did not modify the express pricing and payment terms found
    elsewhere in the contract documents, we affirm the trial court’s judgment.
    {¶2}    In 2006, Fairborn sought bids for improvements to a number of its
    streets. It issued a proposal including 65 tasks for completion in what became
    known as the 2006 Street Program, Project Nos. 2502, 2601, 5104, and 5109. In
    April 2006, Jurgensen became the successful bidder. Its $1,106,881.80 bid was
    based in part on the general and project specifications and the bid and contract
    forms (“the contract documents”) that Fairborn had made available to each bidder.
    The contract documents included Fairborn Construction and Material Specification
    Item 400 which provided specific guidance on how some of the project tasks were to be
    performed. Because of the highly detailed nature of many construction specifications,
    the contract documents, including Fairborn Item 400, incorporated by reference the
    construction and material specifications promulgated by ODOT and required bidding
    contractors like Jurgensen to comply with them. The 2005 ODOT Construction and
    Material Specifications were in effect at the time of bidding.
    {¶3}    The price of asphalt is based largely on the price of oil, which can
    fluctuate widely. Many road contracts include an “asphalt binder price adjustment”
    to address this issue.     Although the contract documents for Fairborn’s road-
    improvement project did not include any specific reference to it, Jurgensen believed
    that the parties’ agreement included an asphalt-binder price adjustment as found in
    2
    OHIO FIRST DISTRICT COURT OF APPEALS
    ODOT Item 401.20. That provision required a project owner to equably adjust the
    contract price and pay the contractor for any increase in the price of asphalt between
    the time of its successful bid and the time that the asphalt is purchased and the work
    is performed. ODOT Item 401.20 provided detailed instructions for measuring and
    calculating any price adjustment.
    {¶4}    Jurgensen performed the asphalt work from August through
    November 2006. During the time between bidding and completion of the work, the
    price of asphalt increased significantly. At the completion of the project, Jurgensen
    submitted claims to Fairborn for additional compensation to reflect an asphalt-
    binder price adjustment of $92,395.66.
    {¶5}    Fairborn refused to pay the adjustment. Fairborn also refused to
    release interest earned on the amounts retained from progress payments made to
    Jurgensen. See R.C. Chapter 153. Jurgensen brought suit seeking money damages
    and a declaration that Fairborn’s refusal to pay the asphalt-binder price adjustment
    and to pay interest had breached its duties under the contract documents.
    {¶6}    Fairborn answered and raised a counterclaim seeking $2,000 due for
    damage to a catch basin, along with a declaration that the price described in the
    winning bid—$1,106,881.80—was all the compensation due to Jurgensen.
    {¶7}    In December 2008, Jurgensen moved for summary judgment on its
    claims based on the affidavits of Peter W. Flora, its Dayton Division manager, and
    the contract documents.    Fairborn also moved for summary judgment on all of
    Jurgensen’s claims. Fairborn’s motion was supported by the affidavits of Michael A.
    Mayer, Fairborn’s city solicitor, and the attached documents.
    {¶8}    The trial court heard the arguments of counsel. On June 18, 2013, it
    journalized an entry denying Jurgensen’s motion for summary judgment on its
    breach-of-contract claims relating to the asphalt-binder price adjustment and
    granted Fairborn’s summary-judgment motion on those claims.           The trial court
    3
    OHIO FIRST DISTRICT COURT OF APPEALS
    denied Fairborn’s summary-judgment motion on Jurgensen’s retained-interest
    claim.
    {¶9}    The trial court then scheduled a trial date to resolve the remaining
    issues. Prior to trial, Jurgensen and Fairborn reached an agreement to dismiss
    Jurgensen’s interest claim and Fairborn’s property-damage counterclaim, and the
    parties submitted a proposed consent entry to the court. The trial court approved
    the entry. It journalized the entry on September 10, 2014, rendering its earlier
    summary-judgment ruling final and appealable. Jurgensen appealed.
    {¶10}   In two interrelated assignments of error, Jurgensen now asserts that
    the trial court erred in denying its motion for summary judgment and in granting, in
    part, Fairborn’s motion for summary judgment.          Civ.R. 56(A) makes summary
    judgment available to a party like Jurgensen, seeking to recover upon its own claim.
    See Capital Fin. Credit, LLC v. Mays, 
    191 Ohio App.3d 56
    , 
    2010-Ohio-4423
    , 
    944 N.E.2d 1184
    , ¶ 4 (1st Dist.). A party moving for summary judgment bears the burden
    of establishing that (1) no genuine issue of material fact remains to be litigated, (2)
    the moving party is entitled to summary judgment as a matter of law, and (3) it
    appears from the evidence, when viewed in a light most favorable to the nonmoving
    party, that reasonable minds can only come to a conclusion adverse to that party.
    See Civ.R. 56.
    {¶11}   The interpretation of clear, unambiguous contract terms is a question
    of law particularly appropriate for resolution by summary judgment. See Costanzo v.
    Nationwide Mut. Ins. Co., 
    161 Ohio App.3d 759
    , 
    2005-Ohio-3170
    , 
    832 N.E.2d 71
    , ¶
    19 (1st Dist.). If the language in a contract is clear and unambiguous, there is no
    issue of fact to be determined. See Physicians Anesthesia Serv. v. Burt, 1st Dist.
    Hamilton No. C-060761, 
    2007-Ohio-6871
    , ¶ 10. An appellate court reviews the trial
    court’s summary-judgment rulings de novo. See Comer v. Risko, 
    106 Ohio St.3d 185
    ,
    
    2005-Ohio-4559
    , 
    833 N.E.2d 712
    , ¶ 8.
    4
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶12}   Here, neither Jurgensen nor Fairborn has asserted that genuine
    issues of material fact remained for resolution. Both moved for summary judgment
    as a matter of law on Jurgensen’s claims. We have previously questioned the wisdom
    of resolving declaratory-judgment actions by summary judgment. But the parties’
    election to address the issues by cross-motions for summary judgment demonstrates
    that both sides believed that there was no genuine issue of material fact in dispute,
    and that the court was free to render a decision as a matter of law. E.g., Cincinnati
    v. Ohio Council 8, Am. Fedn. of State, Cty. & Mun. Emps., AFL-CIO, 
    93 Ohio App.3d 162
    , 164, 
    638 N.E.2d 94
     (1st Dist.1994).
    {¶13}    To prevail on its claims, Jurgensen would have to establish the
    existence of a contract, performance on its part, breach of a duty by Fairborn, and its
    own damage or loss. See Brunsman v. W. Hills Country Club, 
    151 Ohio App.3d 718
    ,
    
    2003-Ohio-891
    , 
    785 N.E.2d 794
    , ¶ 11 (1st Dist.).
    {¶14}   The touchstone of contract interpretation is to give effect to the intent
    of the parties as evidenced by the actual language of the contract. See Transtar Elec.
    v. A.E.M. Elec. Servs. Corp., 
    140 Ohio St.3d 193
    , 
    2014-Ohio-3095
    , 
    16 N.E.3d 645
    , ¶
    9, citing Skivolocki v. E. Ohio Gas Co., 
    38 Ohio St.2d 244
    , 
    313 N.E.2d 374
     (1974),
    paragraph one of the syllabus. We must apply clear and unambiguous contract
    provisions without regard to the relative advantages gained or hardships suffered by
    the parties. See Hope Academy. Broadway Campus v. White Hat Mgmt., L.L.C.,
    Slip Op. No. 
    2015-Ohio-3716
    , ¶ 36, citing Dugan & Meyers Constr. Co., Inc. v. Ohio
    Dept. of Adm. Servs., 
    113 Ohio St.3d 226
    , 
    2007-Ohio-1687
    , 
    864 N.E.2d 68
    , ¶ 29.
    {¶15}   Both parties maintain that the contract documents are clear and
    unambiguous. See Burt, 1st Dist. Hamilton No. C-060761, 
    2007-Ohio-6871
    , at ¶ 10.
    Jurgensen, however, argues that Fairborn breached the agreement when it refused to
    pay the asphalt-binder price adjustment. Jurgensen maintains that the contract
    documents’ reference to ODOT Item 401 incorporated the asphalt-binder price
    5
    OHIO FIRST DISTRICT COURT OF APPEALS
    adjustment described in ODOT Item 401.20, that Fairborn’s own provisions did not
    modify the asphalt-binder price adjustment, and that Jurgensen reasonably
    understood that, as was the custom in its trade, the contract included an implied
    term for price adjustment when it submitted its bid and signed the contract.
    {¶16}   In response, Fairborn argues that the parties’ contract documents did
    not incorporate the asphalt-binder price adjustment. Fairborn argues that those
    ODOT items referred to by the contract documents merely established specifications
    for the work to be performed and did not modify the express pricing and payment
    terms found elsewhere in the contract documents.
    {¶17}   ODOT Item 401.20—the asphalt-binder price adjustment—is not
    referenced in any of the contract documents. The first page of Fairborn’s General
    Provisions states that the “specifications for this project shall conform to the City of
    Fairborn Construction and Material Specifications and Standard Drawings * * *.”
    But if the Fairborn specifications “do not cover a particular item, the latest edition of
    the Construction and Material Specifications as published by the Ohio Department of
    Transportation shall have precedence.”      Jurgensen argues that since Fairborn’s
    construction and material specifications did not provide for an asphalt-binder price
    adjustment, every provision in ODOT Item 401, including the asphalt-binder price
    adjustment, “shall have precedence” and thus apply to the project.
    {¶18}   More specifically, in Fairborn’s proposal seeking bidders, seven of the
    65 project tasks identified specifications for the work by reference to ODOT Item 448
    and to Fairborn Item 400.        Jurgensen’s approved bid schedule quoted prices
    pursuant to these tasks.       Jurgensen contends that because Fairborn’s own
    construction specifications referenced ODOT Item 401, each provision of that item
    was incorporated into the parties’ agreement, including the asphalt-binder price
    adjustment.
    6
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶19}     But closer scrutiny of those portions of Fairborn Item 400 referencing
    ODOT Item 401 reveals that they provide only a description of the manner in which
    the project items are to be performed. See S. A. Ruebel & Co. v. Morr, 
    95 Ohio App. 433
    , 439, 
    120 N.E.2d 605
     (1st Dist.1953) (defining the term “specification,” as used
    in road-improvement contracts, as a specific and detailed description of the thing to
    be furnished or the work to be done); see also Danis Clarkco Landfill Co. v. Clark
    Cty. Solid Waste Mgt. Dist., 
    73 Ohio St.3d 590
    , 600, 
    653 N.E.2d 646
     (1995).
    {¶20}     Fairborn    Item   400 references ODOT         specifications for the
    construction of “asphalt concrete surface course[s] placed on an asphalt concrete
    leveling course and/or intermediate course[s] as specified herein.”            The item
    identifies which ODOT specifications apply to the construction and provides as
    follows:
    Plant mix bituminous pavements shall meet the requirements of
    ODOT Item 401, Asphalt Concrete Pavements – General; Asphalt
    Concrete Mixing Plants shall meet the requirements of ODOT Item
    401 and the asphalt concrete surface and [I]ntermediate courses shall
    meet the requirements of ODOT Item 448, Type 1 or 2, PG 64-22, of
    the latest edition of the Ohio Department of Transportation
    ‘Construction and Material Specifications.’
    (Emphasis added.)
    {¶21}     Other sections of Fairborn Item 400 direct that “bituminous plant
    mixtures” should only be placed under dry and temperate conditions. The references
    to ODOT Item 401 are made solely in the context of how bituminous mix and asphalt
    concrete pavements are to be prepared and used. These provisions describe how the
    work is to be performed and make no mention of payment adjustments.                The
    language of Fairborn Item 400 clearly references Jurgensen’s contractual obligation
    7
    OHIO FIRST DISTRICT COURT OF APPEALS
    to satisfactorily complete asphalt concrete paving in accordance with ODOT material
    specifications. It does not establish a right of Jurgensen to receive escalating prices
    for materials.
    {¶22}     Moreover, there are no references at all to ODOT Item 401 in the
    payment terms separately identified in Fairborn Item 400.            Section 4(A), titled
    “PAYMENT,” provides,
    The quantities, measured as provided above, will be paid for at the
    contract price for each of the particular pay items listed below that are
    shown in the bid schedule, which price and payment shall be full
    compensation for furnishing all material and for all labor, equipment,
    tools and incidentals necessary to complete the item.
    (Emphasis added.)
    {¶23}     The bid-schedule price was $1,106,881.80.         Thus, by its express
    terms, Fairborn’s Item 400 mandates only that asphalt plants, bituminous mixes,
    and intermediate courses employed in the project comply with the material
    specifications of ODOT Items 401, 402, and 448. It imposed no duty on Fairborn,
    and no part of Item 400 subjected Fairborn to any obligation to pay a price
    adjustment.
    {¶24}     Nowhere else in the contract documents is there any express
    incorporation of any ODOT item establishing Fairborn’s obligation to pay the
    asphalt-binder price adjustment. For example, Jurgensen’s bid proposal, signed by
    its vice president, does not state that its proposed prices relied upon the existence of
    the price adjustment. Instead, its bid states that Jurgensen would “accept from
    [Fairborn] as full payment for the completion of each specified item and any
    required maintenance thereof as hereinafter provided, the price quoted for each item
    of work completed.”
    8
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶25}   Payment terms identified in express contract provisions prevail over
    general statements regarding the use of gap-filling specifications found elsewhere in
    the document terms. See Marusa v. Erie Ins. Co., 
    136 Ohio St.3d 118
    , 2013-Ohio-
    1957, 
    991 N.E.2d 232
    , ¶ 14; see also Gibbons-Grable Co. v. Gilbane Bldg. Co., 
    34 Ohio App.3d 170
    , 175, 
    517 N.E.2d 559
     (8th Dist.1986). The fact that the referenced
    ODOT items were “important to the proper construction of asphalt pavements” in no
    way subjected Fairborn to cost-allocation terms where the contract documents
    elsewhere made express provision for prices and payment.
    {¶26}    But even if we were to agree that ODOT Item 401.20 had been
    incorporated into the parties’ contract, Jurgensen could not prevail. The clear and
    unambiguous text of Item 401.20 does not impose any duty upon Fairborn to pay a
    price adjustment. Item 401.20 provides simply that “[a]ny contract item specifying
    asphalt concrete is eligible for a price adjustment, if the Department’s asphalt binder
    index shows the price for asphalt binders has increased or decreased in excess of 5
    percent and the adjustment is more than $100 for any individual item.” (Emphasis
    added.)
    {¶27}   Each of the seven remaining paragraphs of the item describes the
    manner in which the adjustment is to be computed. The item imposes obligations
    only on “the [Ohio] Department [of Transportation].”          The term “Contractor”
    appears only once in the remaining text. Nowhere in the item is any obligation
    imposed on an “Owner,” in general, or Fairborn, in particular.
    {¶28}   Where contract language states simply that a “contract item * * * is
    eligible” for a price adjustment, additional language imposing an obligation on the
    contracting authority to pay the adjustment is required to modify otherwise express
    and unambiguous payment terms and to make the item enforceable. See Morr, 95
    Ohio App. at 440, 
    120 N.E.2d 605
    . In the absence of an express modification of the
    9
    OHIO FIRST DISTRICT COURT OF APPEALS
    payment terms of the contract, Fairborn was obligated to pay only the full amount of
    Jurgensen’s accepted bid price.
    {¶29}   Finally, Jurgensen maintains that under the “usage of trade” doctrine,
    the asphalt-binder price adjustment was effectively made part of the contract terms.
    Through its Dayton Division managers’ affidavits, Jurgensen argues that it
    understood the asphalt-binder price adjustment to be part of the contract because, in
    its prior work, when a public entity employed ODOT specifications for asphalt items,
    the public entity had honored requests for price adjustments. The express terms of a
    contract generally prevail over custom or “usage of trade,” a practice or method of
    dealing so regularly observed as to justify an expectation that it will be observed in
    the transaction in question. See Camargo Cadillac Co. v. Garfield Ent., Inc., 
    3 Ohio App.3d 435
    , 
    445 N.E.2d 1141
     (1st Dist.1982). But evidence of a usage of trade
    existing at the time of contract may be employed to clarify disputed contract
    language only if each party knows or has reason to know of the usage. E.g., Dana
    Partners, LLC v. Koivisto Constructors & Erectors, Inc., 11th Dist. Trumbull No.
    2011-T-0029, 
    2012-Ohio-6294
    , ¶ 27. The existence and scope of a usage of trade
    generally presents a factual issue. See, e.g., R.C. 1301.303. Jurgensen acknowledges
    that it did not, by the means identified in Civ.R. 56, introduce evidence of the terms
    of its other contracts, or of Fairborn’s knowledge of these dealings with other
    entities.
    {¶30}   Here, from the evidence before the trial court, when construed most
    strongly in favor of Jurgensen, we conclude from the clear and unambiguous
    language of the contract documents that Fairborn had no duty to pay the asphalt-
    binder price adjustment, and therefore, it did not breach a contracted-for duty when
    it refused to pay the adjustment. The first and second assignments of error are
    overruled.
    {¶31}   The trial court’s judgment is affirmed.
    10
    OHIO FIRST DISTRICT COURT OF APPEALS
    Judgment affirmed.
    FISCHER and STAUTBERG, JJ., concur.
    Please note:
    The court has recorded its own entry on the date of the release of this opinion.
    11