State v. Karl R. Rohrer Assocs., Inc. , 104 N.E.3d 865 ( 2018 )


Menu:
  • [Cite as State v. Karl R. Rohrer Assocs., Inc., 
    2018-Ohio-65
    .]
    COURT OF APPEALS
    TUSCARAWAS COUNTY, OHIO
    FIFTH APPELLATE DISTRICT
    STATE OF OHIO, BY AND THROUGH                                JUDGES:
    JERRY WRAY, DIRECTOR,                                        Hon. W. Scott Gwin, P.J.
    OHIO DEPARTMENT OF                                           Hon. William B. Hoffman, J.
    TRANSPORTATION, ET AL.                                       Hon. Earle E. Wise, Jr., J.
    Plaintiff-Appellants                                 Case No. 2017AP030008
    -vs-
    OPINION
    KARL R. ROHRER ASSOCIATES, INC.
    Defendant-Appellee
    CHARACTER OF PROCEEDING:                                 Appeal from the Tuscarawas County
    Common Pleas Court, Case No.
    2015CV030118
    JUDGMENT:                                                Affirmed
    DATE OF JUDGMENT ENTRY:                                  January 8, 2018
    APPEARANCES:
    For Plaintiff-Appellants                                 For Defendant-Appellee
    MICHAEL DEWINE                                           BRIAN T. WINCHESTER
    Ohio Attorney General                                    PATRICK J. GUMP
    CRAIG D. BARCLAY                                         McNeal Schick Archibald & Biro Co., LPA
    WILLIAM C. BECKER                                        123 West Prospect Avenue, Suite 250
    Assistant Attorneys General                              Cleveland, OH 44115
    Court of Claims Defense Section
    150 E. Gay Street, 18th Floor                            For Amicus Curiae, AIA Ohio
    Columbus, OH 43215
    LUTHER L. LIGGETT, JR.
    Graff and McGovern LPA
    604 E. Rich Street
    Columbus, OH 43215
    Tuscarawas County, Case No. 2017AP030008                                                 2
    Hoffman, J.
    {¶1}   Appellants State of Ohio, by and through Jerry Wray, Director, Ohio
    Department of Transportation and Ohio Department of Administrative Services, n/k/a
    Ohio Facilities Construction Commission, appeal the directed verdict entered by the
    Tuscarawas County Common Pleas Court dismissing their breach of contract action
    against Appellee Karl R. Rohrer Associates Inc.
    STATEMENT OF THE FACTS AND CASE
    {¶2}   In 1992, and 1993, Appellee submitted two proposals to provide
    engineering services for the construction of the Ohio Department of Transportation
    (hereinafter “ODOT”) District 11 garage in New Philadelphia, Ohio. Appellee signed an
    agreement with the Ohio Department of Administrative Services (hereinafter “ODAS”) to
    provide design services related to structural engineering and related supervision for the
    construction of the garage. Structural designs for the project were provided by the State
    Architect’s Office (hereinafter “SAO”).
    {¶3}   In 1997, the SAO became aware of issues with the brick around five
    windows of the completed building. Appellee paid ODAS $68,000.00 to remediate the
    issue around the windows.
    {¶4}   Appellants later claimed all windows showed some degree of impermissible
    rotation of the steel supporting the brick, causing the brick around the windows to crumble
    and/or crack. Appellants further claimed the two-plus-story garage walls of the facility
    were not adequately supported. Appellants filed the instant action on March 3, 2015, for
    negligence, breach of contract, and declaratory judgment.
    Tuscarawas County, Case No. 2017AP030008                                                3
    {¶5}   On September 28, 2015, Appellee filed a motion for judgment on the
    pleadings, arguing Appellants’ complaint was barred by Ohio’s statute of repose, R.C.
    2305.131. The trial overruled the motion on December 31, 2015, finding R.C. 2305.131
    is generally worded and does not say it applies to the State, and Appellants were exempt
    from operation of the statute by the doctrine of nullum tempus.
    {¶6}   The case proceeded to jury trial on February 22 and 23, 2017. Prior to trial,
    Appellants dismissed their claims for negligence and for declaratory judgment.
    {¶7}   At the close of the presentation of Appellants’ case at trial, Appellee moved
    for directed verdict on various grounds, again arguing the action was barred by R.C.
    2305.131. Tr. 445. The trial court directed a verdict as follows:
    Based upon evidence illicited [sic] by the Plaintiffs from Defendant’s
    principal, the Agreement was acknowledged, the Defendant stated that the
    work was performed, and the Defendant affirmed that it was paid upon
    completion of the work.
    Based upon the evidence presented by Plaintiffs’ expert, the claims
    for damage were proximately caused by inadequate design, regarding the
    standard of care for engineering.
    The Complaint, Pre-trial Statement, and finally, the evidence at trial,
    presented a claim in tort.     See Crowninshield/Old Town Cmty. Urban
    Redevelopment Corp. v. Campeon Roofing & Waterproofing, 1st Dist.
    Hamilton Nos. C-940731, C-940748, 1996 Ohio App. Lexis 1514 (Apr. 17,
    1996). The claims and opinions demonstrate a belief that the Defendant
    Tuscarawas County, Case No. 2017AP030008                                                  4
    failed in its rendering of services in the practice of a profession to exercise
    that degree of skill and learning normally applied by members of that
    profession in similar circumstances. See Illinois National Insurance Co., v.
    Wiles, Boyle, Burkholder & Bringardner Co., LPA, 10th Dist. Franklin No.
    10AP-290, 
    2010-Ohio-5872
    .
    Therefore, the Court found that the evidence presented in support of
    the breach of contract sounds in tort, and that the Plaintiffs failed to present
    any evidence that the Defendant breached the contract. Judgment Entry,
    February 28, 2017.
    {¶8}    From this entry Appellants prosecute their appeal, assigning as error:
    “THE TRIAL COURT ERRED IN GRANTING DEFENDANT’S
    MOTION FOR DIRECTED VERDICT AND FINDING THAT THE STATE OF
    OHIO’S CASE ‘SOUNDED IN TORT’ AND THAT THE STATE COULD
    ONLY SUE IN TORT DESPITE IT HAVING A CONTRACT WITH A
    DESIGN ENGINEER AND THEN GOING ON TO INCONSISTENTLY
    HOLD THAT THE STATE OF OHIO FAILED TO PROVE A BREACH OF
    CONTRACT CLAIM (AS THOUGH THE CASE ALSO ‘SOUNDED IN
    CONTRACT’).”
    {¶9}    Appellee assigns the following cross-assignments of error to the judgment
    of the trial court:
    Tuscarawas County, Case No. 2017AP030008                                   5
    “I.     THE TRIAL COURT ERRED IN DENYING DEFENDANT’S
    MOTION FOR JUDGMENT ON THE PLEADINGS, MOTION FOR
    RECONSIDERATION, AND MOTION FOR DIRECTED VERDICT THAT
    PLAINTIFFS’ CLAIMS WERE BARRED BY THE STATUTE OF REPOSE.
    “II.    THE TRIAL COURT ERRED IN DENYING DEFENDANT’S
    MOTION        FOR   DIRECTED   VERDICT   AS   TO   PLAINTIFF   OHIO
    DEPARTMENT OF TRANSPORTATION’S LACK OF CONTRACTUAL
    PRIVITY WITH THE DEFENDANT.
    “III.    THE TRIAL COURT ERRED IN DENYING DEFENDANT’S
    MOTION        FOR   DIRECTED   VERDICT   AS   TO   PLAINTIFF   OHIO
    DEPARTMENT OF ADMINISTRATIVE SERVICES’ LACK OF STANDING.
    “IV.     THE TRIAL COURT ERRED IN DENYING DEFENDANT’S
    MOTION FOR DIRECTED VERDICT AS THE PLAINTIFFS FAILED TO
    PRESENT EVIDENCE THAT IT SUBSTANTIALLY PERFORMED THE
    APPLICABLE CONTRACT.
    “V.     THE TRIAL COURT ERRED IN DENYING DEFENDANT’S
    MOTION FOR LEAVE TO FILE AN AMENDED ANSWER OR TO ALLOW
    ITS ANSWER TO CONFORM TO THE EVIDENCE.
    “VI. THE TRIAL COURT ERRED IN DENYING DEFENDANT’S
    MOTION FOR DIRECTED VERDICT AS PLAINTIFFS’ CLAIMS WERE
    BARRED BY THE DOCTRINE OF ACCORD AND SATISFACTION.
    Tuscarawas County, Case No. 2017AP030008                                                   6
    “VII. THE TRIAL COURT ERRED IN DENYING DEFENDANT’S
    MOTION FOR DIRECTED VERDICT AS THE PLAINTIFFS FAILED TO
    PRESENT ANY EVIDENCE AS TO THE DIMINUTION IN VALUE OF THE
    SUBJECT PROPERTY.”
    Cross-Assignment I.
    {¶10} We address Appellee’s first cross-assignment of error first, as we find it
    dispositive of the entire appeal. Appellee argues the trial court erred in denying its motion
    for judgment on the pleadings, motion for reconsideration of its decision on the motion for
    judgment on the pleadings, and motion for directed verdict, asserting Appellants’ cause
    of action is barred by the statute of repose. We agree.
    {¶11} Civ. R. 12(C) provides, “After the pleadings are closed but within such time
    as not to delay the trial, any party may move for judgment on the pleadings.” The standard
    of review of the grant of a motion for judgment on the pleadings is the same as the
    standard of review for a Civ. R. 12(B)(6) motion. As the reviewing court, our review of a
    dismissal of a complaint based upon a judgment on the pleadings requires us to
    independently review the complaint and determine if the dismissal was appropriate. Rich
    v. Erie County Department of Human Resources, 
    106 Ohio App.3d 88
    , 91, 
    665 N.E.2d 278
     (1995). A reviewing court need not defer to the trial court's decision in such cases.
    
    Id.
    {¶12} A motion for a judgment on the pleadings, pursuant to Civ. R. 12(C),
    presents only questions of law. Peterson v. Teodosia, 
    34 Ohio St.2d 161
    , 165-166, 
    297 N.E.2d 113
     (1973). The determination of a motion under Civ. R. 12(C) is restricted solely
    Tuscarawas County, Case No. 2017AP030008                                                   7
    to the allegations in the pleadings and the nonmoving party is entitled to have all material
    allegations in the complaint, with all reasonable inferences to be drawn therefrom,
    construed in its favor. 
    Id.
     Evidence in any form cannot be considered. Conant v. Johnson,
    
    1 Ohio App.2d 133
    , 135, 
    204 N.E.2d 100
     (1964). In considering such a motion, one must
    look only to the face of the complaint. Nelson v. Pleasant, 
    73 Ohio App.3d 479
    , 
    597 N.E.2d 1137
     (1991).
    {¶13} A trial court's decision on a motion for directed verdict presents a question
    of law, which an appellate court reviews de novo. Groob v. Keybank, 
    108 Ohio St.3d 348
    ,
    2006–Ohio–1189, 
    843 N.E.2d 1170
    . Civil Rule 50 provides a motion for directed verdict
    may be made at the opening statement of the opponent, at the close of opponent's
    evidence, or at the close of all the evidence. Upon receiving the motion, the trial court
    must construe the evidence most strongly in favor of the party against whom the motion
    is directed. Civil Rule 50(A)(4). If the trial court finds on any determinative issue
    reasonable minds could come but to one conclusion on the evidence submitted, then the
    court shall sustain the motion and direct the verdict as to such issue. A directed verdict is
    appropriate where a plaintiff fails to present evidence from which reasonable minds could
    find in plaintiff's favor. See Hargrove v. Tanner, 
    66 Ohio App.3d 693
    , 
    586 N.E.2d 141
     (9th
    Dist. Summit 1990).
    {¶14} On September 28, 2015, Appellee filed a motion for judgment on the
    pleadings, arguing Appellants’ complaint was barred by Ohio’s statute of repose, R.C.
    2305.131. The trial overruled the motion on December 31, 2015, finding R.C. 2305.131
    is generally worded and does not say it applies to the State, and Appellants were exempt
    from operation of the statute by the doctrine of nullum tempus.
    Tuscarawas County, Case No. 2017AP030008                                                  8
    {¶15} At the close of the presentation of Appellants’ case at trial, Appellee moved
    for directed verdict, again arguing the action was barred by R.C. 2305.131. Tr. 445. The
    trial court granted directed verdict on other grounds.
    {¶16} R.C. 2305.131, Ohio’s statute of repose, provides:
    (A)(1) Notwithstanding an otherwise applicable period of limitations
    specified in this chapter or in section 2125.02 of the Revised Code and
    except as otherwise provided in divisions (A)(2), (A)(3), (C), and (D) of this
    section, no cause of action to recover damages for bodily injury, an injury
    to real or personal property, or wrongful death that arises out of a defective
    and unsafe condition of an improvement to real property and no cause of
    action for contribution or indemnity for damages sustained as a result of
    bodily injury, an injury to real or personal property, or wrongful death that
    arises out of a defective and unsafe condition of an improvement to real
    property shall accrue against a person who performed services for the
    improvement to real property or a person who furnished the design,
    planning, supervision of construction, or construction of the improvement to
    real property later than ten years from the date of substantial completion of
    such improvement.
    (2) Notwithstanding an otherwise applicable period of limitations
    specified in this chapter or in section 2125.02 of the Revised Code, a
    claimant who discovers a defective and unsafe condition of an improvement
    to real property during the ten-year period specified in division (A)(1) of this
    Tuscarawas County, Case No. 2017AP030008                                              9
    section but less than two years prior to the expiration of that period may
    commence a civil action to recover damages as described in that division
    within two years from the date of the discovery of that defective and unsafe
    condition.
    (3) Notwithstanding an otherwise applicable period of limitations
    specified in this chapter or in section 2125.02 of the Revised Code, if a
    cause of action that arises out of a defective and unsafe condition of an
    improvement to real property accrues during the ten-year period specified
    in division (A)(1) of this section and the plaintiff cannot commence an action
    during that period due to a disability described in section 2305.16 of the
    Revised Code, the plaintiff may commence a civil action to recover
    damages as described in that division within two years from the removal of
    that disability.
    (B) Division (A) of this section does not apply to a civil action
    commenced against a person who is an owner of, tenant of, landlord of, or
    other person in possession and control of an improvement to real property
    and who is in actual possession and control of the improvement to real
    property at the time that the defective and unsafe condition of the
    improvement to real property constitutes the proximate cause of the bodily
    injury, injury to real or personal property, or wrongful death that is the
    subject matter of the civil action.
    (C) Division (A)(1) of this section is not available as an affirmative
    defense to a defendant in a civil action described in that division if the
    Tuscarawas County, Case No. 2017AP030008                                              10
    defendant engages in fraud in regard to furnishing the design, planning,
    supervision of construction, or construction of an improvement to real
    property or in regard to any relevant fact or other information that pertains
    to the act or omission constituting the alleged basis of the bodily injury,
    injury to real or personal property, or wrongful death or to the defective and
    unsafe condition of the improvement to real property.
    (D) Division (A)(1) of this section does not prohibit the
    commencement of a civil action for damages against a person who has
    expressly warranted or guaranteed an improvement to real property for a
    period longer than the period described in division (A)(1) of this section and
    whose warranty or guarantee has not expired as of the time of the alleged
    bodily injury, injury to real or personal property, or wrongful death in
    accordance with the terms of that warranty or guarantee.
    (E) This section does not create a new cause of action or substantive
    legal right against any person resulting from the design, planning,
    supervision of construction, or construction of an improvement to real
    property.
    (F) This section shall be considered to be purely remedial in
    operation and shall be applied in a remedial manner in any civil action
    commenced on or after the effective date of this section, in which this
    section is relevant, regardless of when the cause of action accrued and
    notwithstanding any other section of the Revised Code or prior rule of law
    Tuscarawas County, Case No. 2017AP030008                                                   11
    of this state, but shall not be construed to apply to any civil action pending
    prior to the effective date of this section.
    (G) As used in this section, “substantial completion” means the date
    the improvement to real property is first used by the owner or tenant of the
    real property or when the real property is first available for use after having
    the improvement completed in accordance with the contract or agreement
    covering the improvement, including any agreed changes to the contract or
    agreement, whichever occurs first.
    {¶17} It is undisputed Appellants filed the instant action more than ten years after
    the building was substantially complete. Therefore, the only issue before us is whether
    the statute applies to Appellants’ breach of contract claim against Appellee.1
    {¶18} Appellants argue R.C. 2305.131 does not apply to breach of contract
    actions, citing Kocisko v. Charles Shutrump & Sons Co., 
    21 Ohio St. 3d 98
    , 
    488 N.E.2d 171
     (1986). In Kocisko the Ohio Supreme Court found a prior version of R.C. 2305.131
    applies only to actions which sound in tort. 
    Id.
     at syllabus. Actions in contract are
    governed by the fifteen-year statute of limitations set forth in R.C. 2305.06. 
    Id.
    {¶19} In so holding, the Ohio Supreme Court referred to the prior version of R.C.
    2305.131 as a ten-year statute of limitations. 
    Id. at 99
    , 488 N.E.2d at 172. The statute in
    effect at the time provided in pertinent part:
    1   Appellants’ claims for negligence and declaratory judgment were dismissed prior to trial.
    Tuscarawas County, Case No. 2017AP030008                                                    12
    No action to recover damages for any injury to property, real or
    personal, or for bodily injury or wrongful death, arising out of the defective
    and unsafe condition of an improvement to real property . . . shall be brought
    against any person performing services for or furnishing the design,
    planning, supervision of construction, or construction of such improvement
    to real property, more than ten years after the performance or furnishing of
    such services and construction (emphasis added).
    {¶20} The court concluded this ten-year statute of limitations did not apply to
    contract actions, which were governed by the fifteen-year statute of limitations found in
    R.C. 2305.06.
    {¶21} Further, the court in Kocisko found the complaint did not allege an injury to
    person or property arising out of a defective and unsafe improvement to real property.
    Rather, the plaintiff sought recovery for damages flowing from the installation of a leaky
    roof in breach of their various contracts. Id. Thus, while holding generally R.C. 2305.131
    did not apply to breach of contract actions, the court looked at the complaint to determine
    what type of injury the plaintiff alleged.
    {¶22} The dissenting justices found the plain language of the statute, stating “no
    actions” for certain types of injuries shall be brought more than ten years after the cause
    of action arose, did not distinguish between contract, tort, or other forms of actions. Id.
    at 100, 488 N.E.2d at 173. The dissenting opinion further looked to the intention of the
    legislature in adopting the statute to support its position the statute was not limited to tort
    actions:
    Tuscarawas County, Case No. 2017AP030008                                                   13
    The parties agree that R.C. 2305.131 was adopted to protect
    architects and builders when the demise of the privity of contract doctrine
    broadly extended their potential liability to third parties. Almost every state,
    including Ohio, enacted this type of statute, recognizing that architects and
    builders were exposed to liability for an indefinite time due to the longevity
    of buildings. Over such a long time, evidence becomes stale and intervening
    negligence could and does occur. I find unpersuasive the argument that the
    legislature would have passed such legislation intending it to apply only to
    tort claims but not to contract claims that allege the same type of injury. If
    the legislature intended to restrict the limitations period to a particular form
    of action, it could have done so explicitly. Id.
    {¶23} In Hedges v. Nationwide Mut. Ins. Co., 
    109 Ohio St.3d 70
    , 
    2006-Ohio-1926
    ,
    
    846 N.E.2d 16
    , ¶¶ 24-25 (2006), the Ohio Supreme Court held changes to the statutory
    language in the area of uninsured/underinsured motorist law cured the ambiguity that
    concerned the court in a prior case interpreting the statute, and therefore the prior holding
    of the court did not apply to the new version of the statute. In the instant case, the current
    statute is clearly not a statute of limitations as the Kocisko court characterized the prior
    version of R.C. 2305.131. Rather than limiting the time in which the action may be
    brought, the current statute prevents the cause of action from accruing after ten years
    has passed, stating “no cause of action shall accrue” later than ten years from the date
    the project was substantially completed.
    Tuscarawas County, Case No. 2017AP030008                                                  14
    {¶24} In addition, R.C. 2305.131 states:
    (F) This section shall be considered to be purely remedial in
    operation and shall be applied in a remedial manner in any civil action
    commenced on or after the effective date of this section, in which this
    section is relevant, regardless of when the cause of action accrued and
    notwithstanding any other section of the Revised Code or prior rule of law
    of this state, but shall not be construed to apply to any civil action pending
    prior to the effective date of this section (emphasis added).
    {¶25} The statute itself sets forth the legislature’s intention it apply to any civil
    action in which it is relevant, regardless of any prior rule of law of this state, presumably
    including case law based on the prior version of the statute and/or any common law
    precedent.
    {¶26} Therefore, we find Kocisko is not binding authority on this Court in
    interpreting the current version of the statute.
    {¶27} The legislature set forth its purposes for reenactment of the statute of
    repose following the Ohio Supreme Court’s declaration the prior version was
    unconstitutional:
    In enacting section 2305.131 of the Revised Code in this act, it is the
    intent of the General Assembly to do all of the following:
    Tuscarawas County, Case No. 2017AP030008                                               15
    (1) To declare that the ten-year statute of repose prescribed by
    section 2305.131 of the Revised Code, as enacted by this act, is a specific
    provision intended to promote a greater interest than the interest underlying
    the general four-year statute of limitations prescribed by section 2305.09 of
    the Revised Code, the general two-year statute of limitations prescribed by
    section 2305.10 of the Revised Code, and other general statutes of
    limitation prescribed by the Revised Code;
    (2) To recognize that, subsequent to the completion of the
    construction of an improvement to real property, all of the following
    generally apply to the persons who provided services for the improvement
    or who furnished the design, planning, supervision of construction, or
    construction of the improvement:
    (a) They lack control over the improvement, the ability to make
    determinations with respect to the improvement, and the opportunity or
    responsibility to maintain or undertake the maintenance of                 the
    improvement;
    (b) They lack control over other forces, uses, and intervening causes
    that may cause stress, strain, or wear and tear to the improvement.
    (c) They have no right or opportunity to be made aware of, to
    evaluate the effect of, or to take action to overcome the effect of the forces,
    uses, and intervening causes described in division (E)(5)(b) of this section.
    (3) To recognize that, more than ten years after the completion of the
    construction of an improvement to real property, the availability of relevant
    Tuscarawas County, Case No. 2017AP030008                                              16
    evidence pertaining to the improvement and the availability of witnesses
    knowledgeable with respect to the improvement is problematic;
    (4) To recognize that maintaining records and other documentation
    pertaining to services provided for an improvement to real property or the
    design, planning, supervision of construction, or construction of an
    improvement to real property for a reasonable period of time is appropriate
    and to recognize that, because the useful life of an improvement to real
    property may be substantially longer than ten years after the completion of
    the construction of the improvement, it is an unacceptable burden to require
    the maintenance of those types of records and other documentation for a
    period in excess of ten years after that completion;
    (5) To declare that section 2305.131 of the Revised Code, as
    enacted by this act, strikes a rational balance between the rights of
    prospective claimants and the rights of design professionals, construction
    contractors, and construction subcontractors and to declare that the ten-
    year statute of repose prescribed in that section is a rational period of
    repose intended to preclude the pitfalls of stale litigation but not to affect
    civil actions against those in actual control and possession of an
    improvement to real property at the time that a defective and unsafe
    condition of that improvement causes an injury to real or personal property,
    bodily injury, or wrongful death. 2004 SB 80 § 3, eff. 4–7–05.
    Tuscarawas County, Case No. 2017AP030008                                                    17
    {¶28} We find the stated concerns underlying enactment of the statute apply to
    actions brought against design professionals for injury to person or property caused by a
    defective or unsafe improvement to real property, whether such action sounds in tort or
    contract.
    {¶29} In addition, the legislative history quoted above reflects an intent to promote
    a greater interest than the “four-year statute of limitations prescribed by section 2305.09
    of the Revised Code, the general two-year statute of limitations prescribed by section
    2305.10 of the Revised Code, and other general statutes of limitation prescribed by the
    Revised Code.” The inclusion of other statutes of limitations beyond R.C. 2305.09
    (certain torts) and R.C. 2305.10 (products liability) implies the statute applies to non-tort
    actions which allege the type of injury set forth in the statute.
    {¶30} It matters not whether the action is brought in tort or contract, if the resultant
    damages are injury to property of the type set forth in R.C. 2305.131, the statute applies.
    {¶31} In its complaint, Appellants state in their introduction:
    6. Defendant Rohrer failed to perform and otherwise breached its
    contract, breached its standard of care, failed to identify defective work for
    correction and otherwise failed to comply with the requirements of the
    Contract Documents.
    7. Said breaches of contract and negligence included but were not
    limited to: failure to design, advise, and properly monitor construction of
    brick and steel lintels over long-span window openings, forty-five in all,
    causing window displacement, and corresponding cracking of brick with
    Tuscarawas County, Case No. 2017AP030008                                                18
    related leakage; failure to design, advise and properly monitor construction
    of walls and footer/foundation throughout, especially in high wall areas – all
    violating basic engineering standards.
    {¶32} In its prayer for relief for breach of contract, Appellants’ complaint states:
    14. As a direct and proximate result of Rohrer’s breach of contract,
    ODOT has incurred and will incur additional costs and damages to repair
    and replace defective and non-complying structural design, workmanship,
    and materials in an amount in excess of $1.5 million plus prejudgment
    interest, and other compensatory and consequential damages in an amount
    to be proven at trial.
    {¶33} Appellants’ claim for negligence sets forth a nearly-identical prayer for
    damages:
    17. As a direct and proximate result of the negligence of Defendant
    Rohrer, the Plaintiffs have incurred and will incur additional costs and
    damages to repair and replace defective and non-complying designs, work
    and materials in an amount in excess of $1.5 million, plus prejudgment
    interest, and other compensatory and consequential damages, to be proven
    at trial.
    Tuscarawas County, Case No. 2017AP030008                                                       19
    {¶34} We find the instant action is an action for damages to property caused by
    defective design to an improvement to real property, and as such R.C. 2305.131 applies.
    {¶35} The trial court found R.C. 2305.131 did not apply to Appellants based on
    the maxim nullum tempus occurrit regi (time does not run against the king). Based on the
    doctrine of nullum tempus, the state of Ohio is not subject to general requirements of
    statutes of limitations unless the statute in question has specifically included the
    government.     State, Dept. of Transp. v. Sullivan, 
    38 Ohio St.3d 137
    , 139, 
    527 N.E.2d 798
    , 799 (1988). We reiterate the present version is not a statute of limitations but rather
    a declaration of when a cause of action no longer exists. One reason for the vitality of
    the doctrine in a time when royal privilege no longer exists is found in the public policy of
    preserving the public rights, revenues, and property from injury and loss from the
    negligence of public officials in failing to bring suit in a timely fashion. 
    Id.
     The rule is
    justified on the basis the same active vigilance cannot be expected of the State as
    characterizes a private person in protecting his or her own rights. 
    Id.,
     citing Heddleston
    v. Hendricks, 
    52 Ohio St. 460
    , 465, 
    40 N.E. 408
    , 409 (1895).
    {¶36} The trial court relied on City of Chicago ex rel. Scachitti v. Prudential
    Securities, Inc., 
    332 Ill. App. 3d 353
    , 
    772 N.E.2d 906
     (2002). In that case, the Illinois
    court first undertook an analysis of the application of nullum tempus to the statute of
    limitations, as in Illinois the test for its applicability is whether the right the State seeks to
    assert is a right belonging to the general public, or whether it belongs only to the
    government or a small subsection of the public at large. Id. at 361. After determining the
    right was one belonging to the general public and the statute of limitations did not apply
    based on the doctrine of nullum tempus, the court then found the statute of repose also
    Tuscarawas County, Case No. 2017AP030008                                                 20
    did not bar the action, citing People v. Asbestospray Corp., 
    247 Ill. App. 3d 258
    , 
    616 N.E.2d 652
     (1993).
    {¶37} In Asbestospray, the court concluded despite differences between the two,
    statutes of repose are essentially time limitations and therefore subject to the doctrine of
    nullum tempus, citing cases from the states of Washington and North Carolina. Id. at
    262. However, the Illinois statute in question in Asbestospray differed from the Ohio
    statute. Unlike R.C. 2305.131 which prevents the cause of action from accruing, the
    Illinois statute provides no product liability action based on strict liability “shall be
    commenced except within the applicable limitations period and, in any event, within 12
    years from the date of first sale….” Id. at 260.
    {¶38} We find the City of Chicago case unpersuasive in the instant appeal. The
    Illinois statutory language is more similar to a statute of limitations than the language in
    the Ohio statute. Further, Illinois requires consideration of whether the government is
    engaged in a public function prior to applying the doctrine of nullum tempus. Ohio has no
    such requirement, and thus application of the doctrine to the statute of repose would
    provide a sweeping application to all actions brought by the State. Unlike City of Chicago
    where the right asserted belonged to the general public, we find the right asserted here
    belongs to the government.2 In addition, we note a split of authority among states as to
    the applicability of the doctrine to statutes of repose. See, e.g, Com. v. Owens-Corning
    Fiberglass Corp., 
    238 Va. 595
    , 
    385 S.E.2d 865
     (1989); Altoona Area School Dist. v.
    2 In City of Chicago, the action was brought to recover overcharges incurred by yield
    burning on the part of the defendants in advanced-refunding of city bonds. The court held
    the recovery of $1.4 million in overcharges benefitted the general public. 
    772 N.E.2d at 918
    .
    Tuscarawas County, Case No. 2017AP030008                                                21
    Campbell, 152 Pa. Cmwlth. 131, 
    618 A.2d 1129
     (1992); Shasta View Irrigation Dist. v.
    Amoco Chemicals Corp. 
    329 Or. 151
    , 
    986 P.2d 536
     (1999).
    {¶39} We find the trial court erred in finding the doctrine of nullum tempus barred
    application of the statute of repose against the State. The doctrine nullum tempus occurrit
    regi translates “time does not run against the king.” Because the statute of repose
    prevents a cause of action from accruing, application of the doctrine to the statute of
    repose would not stop time from running against the king, but rather would give the king
    a cause of action where otherwise one would not exist. The Supreme Court of Oregon
    held in Shasta View, supra, at 164:
    ORS 30.905(1), by contrast, reflects a legislative judgment that an
    injury occurring eight years after a defective product first enters the stream
    of commerce is not legally cognizable because, after that time, all claims
    are extinguished. Sealey, 309 Or. at 392, 
    788 P.2d 435
    . Unlike a statute of
    limitations, the eight-year ultimate repose period prescribed by that statute
    begins to run on the date on which a product first is purchased for use or
    consumption, not on the date on which a purchaser knows or should have
    known of an injury caused by the product. The eight-year statute of ultimate
    repose runs whether or not a public official or any other plaintiff fails to
    assert a claim in a timely manner. The public policy for exempting
    governments from statutes of limitations therefore does not apply to statutes
    of ultimate repose. That is so, because the expiration of ultimate repose
    Tuscarawas County, Case No. 2017AP030008                                                   22
    periods extinguishes all claims irrespective of whether the injured plaintiff
    was negligent in failing to assert claims in a timely manner.
    {¶40} As in Oregon, the policy underlying the continued application of nullum
    tempus in Ohio is premised on protecting the public interest from the negligence of public
    officials who fail to bring a claim in a timely fashion. Sullivan, supra. Such underpinning
    does not apply to R.C. 2305.131, which extinguishes all claims ten years after completion
    of the project irrespective of whether the plaintiff has filed a complaint in a timely manner.
    {¶41} Further, the language of the statute specifically states it applies
    notwithstanding common law to the contrary:
    (F) This section shall be considered to be purely remedial in
    operation and shall be applied in a remedial manner in any civil action
    commenced on or after the effective date of this section, in which this
    section is relevant, regardless of when the cause of action accrued and
    notwithstanding any other section of the Revised Code or prior rule of law
    of this state, but shall not be construed to apply to any civil action pending
    prior to the effective date of this section. R.C. 2305.131(F) (emphasis
    added).
    {¶42} The language of the statute itself suggests the doctrine of nullum tempus,
    a “prior rule of law of this state,” shall not prevent application of the statute.
    Tuscarawas County, Case No. 2017AP030008                                            23
    {¶43} For the foregoing reasons, we find the instant action, filed more than ten
    years after substantial completion of the project, is barred by R.C. 2305.131.     The
    assignment of error is sustained.
    {¶44} The assignment of error on direct appeal and the remaining cross-
    assignments of error are rendered moot by our disposition of the first cross-assignment
    of error.
    {¶45} The judgment of the Tuscarawas County Common Pleas Court is affirmed.
    By: Hoffman, J.
    Gwin, P.J. and
    Wise, Earle, J. concur