Vandercar, L.L.C. v. Port of Greater Cincinnati Dev. Auth. , 2022 Ohio 3148 ( 2022 )


Menu:
  • [Cite as Vandercar, L.L.C. v. Port of Greater Cincinnati Dev. Auth., 
    2022-Ohio-3148
    .]
    IN THE COURT OF APPEALS
    FIRST APPELLATE DISTRICT OF OHIO
    HAMILTON COUNTY, OHIO
    VANDERCAR, LLC,                                  :          APPEAL NOS. C-210643
    C-210665
    Plaintiff-Appellee/Cross-                 :                       C-220130
    Appellant,                                           TRIAL NO. A-200900
    :
    vs.
    :              O P I N I O N.
    THE PORT OF GREATER
    CINCINNATI DEVELOPMENT                           :
    AUTHORITY,
    :
    Defendant-Appellant/Cross-
    Appellee.                                 :
    Civil Appeals From: Hamilton County Court of Common Pleas
    Judgments Appealed From Are: Affirmed in Part, Reversed in Part, and Cause
    Remanded
    Date of Judgment Entry on Appeal: September 9, 2022
    Taft Stettinius & Hollister LLP, W. Stuart Dornette, Russell S. Sayre and Beth A.
    Bryan, for Plaintiff-Appellee/Cross-Appellant,
    Calfee, Halter & Griswold LLP, Mitchell G. Blair, Matthew A. Chiricosta and David
    T. Bules, for Defendant-Appellant/Cross-Appellee.
    OHIO FIRST DISTRICT COURT OF APPEALS
    MYERS, Presiding Judge.
    {¶1}   The deterioration of the Millennium Hotel in downtown Cincinnati had
    long been an obstacle to the city’s efforts to attract convention business. In 2019,
    Vandercar, LLC, entered into a $36 million purchase contract with the hotel’s former
    owners in order to facilitate the redevelopment of the hotel “as a four-star (or better)
    convention center hotel.” Several months later, Vandercar assigned its interest in the
    contract to the Port of Greater Cincinnati Development Authority (“the Port”) in
    exchange for two potential fees totaling $7.5 million. The Port acquired the hotel
    property and paid Vandercar one of its potential fees, in the amount of $2.5 million.
    However, although demolition on the Millennium Hotel was completed in 2022, the
    dust has not yet settled on the parties’ dispute over the Port’s obligation to pay
    Vandercar the second fee of $5 million.
    {¶2}   Vandercar sued the Port for breach of contract and bad faith, claiming
    it was owed additional fees when the Port issued revenue bonds that included funds
    for demolition of the hotel and other activities that Vandercar claimed were for
    redevelopment. The trial court granted summary judgment in Vandercar’s favor on
    its breach-of-contract claim in the amount of $5 million, but denied its motion for
    prejudgment interest. The court granted the Port’s motion for partial judgment on
    the pleadings on Vandercar’s bad-faith claim. Both parties have appealed.
    {¶3}   Because we find that the contract is clear and unambiguous in requiring
    the Port to pay Vandercar its $5 million fee, we affirm the trial court’s grant of
    summary judgment in favor of Vandercar on its breach-of-contract claim.            And
    because prejudgment interest cannot be assessed against the Port as an arm of the
    state in the absence of statutory or contractual authority, we affirm the trial court’s
    denial of Vandercar’s motion for prejudgment interest. Finally, because Vandercar’s
    2
    OHIO FIRST DISTRICT COURT OF APPEALS
    bad-faith claim was subsumed in its breach-of-contract claim, we hold that the trial
    court properly dismissed the bad-faith claim as a separate, stand-alone cause of action.
    However, because we find that Vandercar has alleged that the Port acted in bad faith,
    we reverse the trial court’s granting of judgment on the pleadings as to the recovery of
    attorney fees and remand for further proceedings.
    Factual Background
    {¶4}    On July 1, 2019, Vandercar entered into a Purchase and Sale
    Agreement (“the Purchase Contract”) with Cincinnati S.I. Co., the owner of the
    Millennium Hotel, to purchase the property for $36 million. The Purchase Contract
    was amended on August 27, 2019, and on September 13, 2019.
    {¶5}   On October 4, 2019, Vandercar assigned its rights under the Purchase
    Contract to the Port in an Assignment and Assumption Agreement, and the parties
    entered into an Agreement Regarding Assignment (“the Agreement”). The Agreement
    provided:
    THIS AGREEMENT REGARDING ASSIGNMENT (the “Agreement”) is
    entered into effective as of the 4th day of October, 2019 (the “Effective
    Date”), by and between VANDERCAR, LLC, an Ohio limited liability
    company (“Vandercar”), and THE PORT OF GREATER CINCINNATI
    DEVELOPMENT AUTHORITY, a port authority and political
    subdivision and body corporate and politic duly organized and validly
    existing under the laws of the State of Ohio (“Port”), under the following
    circumstances:
    A. Vandercar is a party to that certain Purchase and Sale Agreement
    with Cincinnati S.I. Co., an Ohio limited partnership (“Seller”) dated as
    of July 1, 2019, as amended by that certain First Amendment to
    Purchase and Sale Agreement dated as of August 27, 2019, and as
    further amended by that Second Amendment to Purchase and Sale
    3
    OHIO FIRST DISTRICT COURT OF APPEALS
    Agreement dated as of September 13, 2019 (as so amended, and as may
    be further amended and/or supplemented from time to time, together,
    the “Contract”). A true, correct, and complete copy of the Contract is
    attached hereto as Exhibit A and incorporated herein.
    B. Under the Contract, among other things, Vandercar has agreed to
    purchase, and Seller has agreed to sell, certain Real Property (as such
    term is defined in the Contract)1 located in the City of Cincinnati,
    Hamilton County, Ohio, on which is located the Millennium Hotel
    Cincinnati.
    C. Port wishes to acquire the Real Property in order to redevelop, or
    cause to be redeveloped, the Real Property for a new hotel (the
    “Project”), which such acquisition of the Real Property may be financed
    with the proceeds of revenue bonds issued by the Port Authority (the
    “Property Acquisition Bonds”), and such redevelopment will be
    financed with the proceeds of revenue bonds issued by the Port
    Authority (the “Redevelopment Bonds”). The Property Acquisition
    Bonds and the Redevelopment Bonds may be issued at the same time as
    part of one issuance of bonds or, alternatively, may be issued on
    separate dates as determined by the Port.
    {¶6}    After setting forth certain obligations of the parties, the Agreement
    provided for certain payments to Vandercar. One of these was to occur upon the
    closing of the property (“Development Fee”), and another was to be paid upon the
    issuance of Redevelopment Bonds (“Redevelopment Fee”).                 Specifically, the
    Agreement provided in relevant part:
    1The “Real Property” referred to in the Agreement was defined in the July 1, 2019 Purchase
    Contract to include the Land and Improvements at the Millennium Hotel site.
    4
    OHIO FIRST DISTRICT COURT OF APPEALS
    D. Port desires to assume Vandercar’s rights and obligations under the
    Contract, and Vandercar desires to assign such rights and obligations to
    Port, subject, however, to the terms, conditions, and provisions of this
    Agreement.
    1. Development Fee and Expenses in Connection with the Property
    Acquisition and the Contract.
    a. On the Closing Date of the acquisition of the Real Property, Port
    shall pay Vandercar:
    i.     a “Development Fee” of $2,500,000.00;
    ii.    An amount of $250,000.00 to reimburse Vandercar for
    its payment to the Seller of the Initial Deposit required
    under the Contract;
    iii.   An amount not to exceed $175,000.00 to reimburse
    Vandercar for the fees and expenses incurred by
    Vandercar in connection with the initial due diligence
    with respect to the Contract, such amount to be paid to be
    evidenced by invoices provided to the Port with sufficient
    detail as to the work performed; and
    iv.    An amount not to exceed $47,500.00 to reimburse
    Vandercar for the fees and expenses of Government
    Solutions in connection with the Contract.
    ***
    2.      Additional Vandercar Redevelopment Fee. The Port shall use
    commercially reasonable efforts to issue the Redevelopment Bonds
    within one year from the date of the closing of the purchase of the Real
    Property[.] * * * The Port shall not use or allow to be used any other
    method of financing the development of the Project unless such
    5
    OHIO FIRST DISTRICT COURT OF APPEALS
    financing causes and allows for the payment of the $5,000,000.00
    redevelopment fee described below. If the closing of the Redevelopment
    Bonds occurs within that one-year period (as may be extend (sic) due to
    force majeure event), on such date of closing of the Redevelopment
    Bonds[,] the Port shall pay Vandercar an additional amount of
    $5,000,000.00.
    (Emphasis sic.)
    {¶7}    On January 15, 2020, the Port adopted Resolution No. 2020-04 (“the
    January Resolution”), authorizing the issuance and sale of revenue bonds. The
    January Resolution provided:
    WHEREAS, the Port of Greater Cincinnati Development Authority (the
    “Port”), * * *, authorized and empowered * * * (1) to issue revenue bonds
    in one or more series for the purpose of financing costs of acquiring,
    constructing, installing, equipping or improving “port authority
    facilities,” as defined in Section 4582.21, Ohio Revised Code
    ***
    WHEREAS, pursuant to Board Resolution No. 2019-26 adopted on
    September 27, 2019, the Port entered into an Agreement Regarding
    Assignment dated as of October 4, 2019, with Vandercar, LLC
    (“Vandercar”), under which the Port accepted an assignment of
    Vandercar’s rights, interests and obligations under a Purchase and Sale
    Agreement dated as of July 1, 2019 (the “PSA”) with Cincinnati, S.I. Co.,
    as amended, and pursuant thereto, the Port intends to acquire and
    demolish2 (i) the Millennium Hotel, Cincinnati, Hamilton County, Ohio
    2We note that “acquire and demolish” does not modify the second phrase of this sentence and have
    interpreted the plain language to be: the Port intends (1) to acquire and demolish the Millennium
    Hotel and (ii) to evaluate the timing, scope and size of new convention facilities, including a new
    hotel. This is consistent with both parties’ arguments.
    6
    OHIO FIRST DISTRICT COURT OF APPEALS
    and certain other buildings and improvements located upon the Project
    Site (defined herein), and (ii) to evaluate the timing, scope and size of
    the construction of new convention facilities, including a new hotel, and
    an expansion of the convention center on all or a portion of the Project
    Site (collectively, the “Project”); and
    WHEREAS, upon advice from the Port’s staff, this Board has
    determined that it is necessary and proper and in the best interest of the
    Port to issue revenue bonds in one or more series in the maximum
    aggregate principal amount of $59,000,000 (“Bonds”) in anticipation
    of the issuance of additional revenue bonds to pay for the costs of the
    Project[.]
    {¶8}   The January Resolution then authorized the issuance of the bonds. In
    it, the Port agreed to use the bond proceeds to pay a portion of the Project’s costs. The
    Project is defined in the January Resolution as acquisition, demolition, and evaluation
    of the site.
    {¶9}   Specifically, the January Resolution provided:
    The Port will use the proceeds of the Bonds to pay a portion of the costs
    of the Project and pay or reimburse related costs, to pay certain costs of
    issuance of the Bonds, to make the capitalized interest deposit, if any,
    and to fund a debt service fund if required by the Original Purchaser.
    {¶10} On February 12, 2020, the Port adopted Resolution No. 2020-11 (“the
    February Resolution”) authorizing its president to enter into contracts for the
    remediation, demolition, and preconstruction at the Millennium Hotel site and for the
    development and construction of new convention facilities, including a convention
    center hotel, at the site. The February Resolution reiterated that the revenue bonds
    authorized by the January Resolution would be used to “pay the cost of acquiring the
    Project Site and demolishing the Millennium Hotel and evaluating the timing, scope
    7
    OHIO FIRST DISTRICT COURT OF APPEALS
    and size of the construction of new convention facilities, including a new hotel, and an
    expansion of the convention center[.]”
    {¶11} On February 13, 2020, the Port issued revenue bonds (“the February
    revenue bonds”) in the amount of $52.855 million, which were titled “Port of Greater
    Cincinnati Development Authority Revenue Bonds, Series 2020 (Convention Center
    Hotel Acquisition and Demolition Project).”
    {¶12} On February 14, 2020, the Port closed on its acquisition of the real
    property and paid Vandercar its $2.5 million Development Fee (plus expenses),
    pursuant to Paragraph D(4) of the Agreement.
    {¶13} On February 18, 2020, Vandercar submitted an invoice to the Port for
    the $5 million Additional Vandercar Redevelopment Fee described in Paragraph D(5)
    of the Agreement. In its letter accompanying the invoice, Vandercar asserted that the
    February revenue bonds were issued for purposes other than simply property
    acquisition and were Redevelopment Bonds issued within one year of closing, which
    triggered the Port’s obligation to pay Vandercar’s Redevelopment Fee.
    {¶14} On February 24, 2020, Vandercar sued the Port after it did not pay the
    Redevelopment Fee.
    Procedural History
    {¶15} In its complaint, Vandercar alleged two causes of action: breach of
    contract and bad faith. Vandercar alleged that the $52.855 million February revenue
    bonds issued by the Port included approximately $39 million to acquire the Project
    site and to pay Vandercar’s $2.5 million Development Fee, and the balance to begin
    redevelopment activities, including demolition of the Millennium Hotel. It alleged
    that the Port breached the Agreement when it failed to pay the $5 million
    Redevelopment Fee owed to Vandercar when the Port issued “Redevelopment Bonds,
    as defined under the Agreement,” as part of the February revenue bond issuance.
    Vandercar also alleged that the Port acted in bad faith by refusing to pay the
    8
    OHIO FIRST DISTRICT COURT OF APPEALS
    Redevelopment Fee and by structuring the bond issue to disguise the demolition and
    other redevelopment activity as something other than redevelopment.
    {¶16} After the Port filed its Answer, Vandercar moved for judgment on the
    pleadings, seeking judgment in its favor on both its breach-of-contract and bad-faith
    claims. Vandercar asked the court to award it $5 million in damages as well as its
    attorney fees. The trial court denied the motion, finding that genuine issues of
    material fact remained to be determined.
    {¶17} The Port then moved for partial judgment on the pleadings as to
    Vandercar’s bad-faith claim, arguing that the claim was not a legally cognizable, free-
    standing cause of action under Ohio law.
    {¶18} Before the court ruled on the Port’s motion, and following discovery,
    Vandercar moved for summary judgment on its breach-of-contract claim. Then the
    Port moved for summary judgment on both the breach-of-contract and bad-faith
    claims.     Both parties argued that the Agreement was clear and unambiguous.
    Vandercar argued that it was entitled to its $5 million Redevelopment Fee because the
    February      revenue   bonds   included   both   Property   Acquisition   Bonds   and
    Redevelopment Bonds. The Port argued that the February revenue bonds consisted
    only of Property Acquisition Bonds, and that it was not obligated to pay the
    Redevelopment Fee because it did not issue Redevelopment Bonds to construct a new
    hotel. In addition, the Port argued that Vandercar’s bad-faith claim failed as a matter
    of law because there was no evidence of bad faith.
    {¶19} The trial court heard arguments on the Port’s motion for partial
    judgment on the pleadings and on both motions for summary judgment. At the end
    of the hearing, the trial court orally announced its decision granting summary
    judgment in favor of Vandercar on its breach-of-contract claim and awarding
    Vandercar its $5 million Redevelopment Fee, denying the Port’s motion for summary
    judgment, and granting the Port’s motion for partial judgment on the pleadings as to
    9
    OHIO FIRST DISTRICT COURT OF APPEALS
    Vandercar’s bad-faith claim. Before the court issued a judgment entry, Vandercar filed
    a motion for prejudgment interest.
    {¶20} The trial court then issued a judgment entry disposing of the motions.
    In granting summary judgment in favor of Vandercar on its breach-of-contract claim,
    and denying summary judgment to the Port on that claim, the trial court stated:
    The Court finds that there is no disputed issue of material fact that the
    Port issued revenue bonds to acquire the property, and also redevelop
    the property by beginning demolition of the Millennium Hotel. As such,
    Vandercar is entitled to judgment as a matter of law on Count One of
    the Complaint. The $5-Million-Dollar Redevelopment Fee defined in
    the contract was triggered, and is owed.
    {¶21} The court rejected the Port’s contention that demolition of the
    Millennium Hotel “was paid for by issuance of Property Acquisition Bonds, which
    would not trigger the Redevelopment Fee.” The court explained that it considered no
    extrinsic evidence in reaching its decision, and it found that the language in the
    Agreement was unambiguous.           After looking to the dictionary definitions of
    “acquisition” and “redevelopment” to find the plain meaning of the terms used in the
    Agreement, the court stated:
    The Court reads acquisition to refer solely to the gaining possession of
    the property. The term Redevelopment would be applied to everything
    else after acquisition leading up to construction of a new hotel. This
    includes demolition of the previous building.
    {¶19} In dismissing Vandercar’s bad-faith claim, the court stated that,
    although it was clear that the parties disagreed as to whether the Redevelopment Fee
    was owed, “a dispute with regard to contract interpretation is not bad faith in this
    case.”
    10
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶20} After the court issued its judgment entry disposing of the motions, the
    Port appealed in the case numbered C-210643. Vandercar filed a cross-appeal in the
    case numbered C-210665, but asserted that the Port’s appeal was premature under
    App.R. 4(B)(2)(f) because Vandercar’s motion for prejudgment interest remained
    pending in the trial court.
    {¶21} This court stayed the appeals and remanded this case to the trial court
    to resolve the prejudgment-interest motion. The trial court denied the motion. The
    court found that prejudgment interest could not be levied upon the state in the absence
    of a statute requiring it. The court found that the Port was an arm or instrumentality
    of the state because it was created by, and its powers and authorities are defined by,
    the Revised Code. Because the court found that no statute required the imposition of
    prejudgment interest on an arm or instrumentality of the state, the court refused to
    award prejudgment interest against the Port.
    {¶22} Following the trial court’s denial of the motion for prejudgment
    interest, Vandercar filed the appeal in the case numbered C-220130.
    The Port’s Appeal
    {¶23} In two assignments of error, the Port challenges the trial court’s
    granting of summary judgment in Vandercar’s favor on the breach-of-contract claim
    and denying the Port’s summary-judgment motion on the same claim. The Port argues
    that it did not breach the Agreement with Vandercar by not paying the $5 million
    Redevelopment Fee. According to the Port, it did not issue Redevelopment Bonds that
    would trigger its obligation to pay the Redevelopment Fee, because the Agreement
    defined “Redevelopment Bonds” as revenue bonds issued to construct a new hotel.
    {¶24} We review a trial court’s ruling on a motion for summary judgment de
    novo. Grafton v. Ohio Edison Co., 
    77 Ohio St.3d 102
    , 105, 
    671 N.E.2d 241
     (1996).
    Summary judgment is appropriately granted when there exists no genuine issue of
    material fact, the party moving for summary judgment is entitled to judgment as a
    11
    OHIO FIRST DISTRICT COURT OF APPEALS
    matter of law, and the evidence, when viewed in favor of the nonmoving party, permits
    only one reasonable conclusion that is adverse to that party. State ex rel. Howard v.
    Ferreri, 
    70 Ohio St.3d 587
    , 589, 
    639 N.E.2d 1189
     (1994).
    {¶25} In interpreting a contract, our role is “to give effect to the intent of the
    parties to the agreement.” Motorists Mut. Ins. Co. v. Ironics, Inc., Slip Opinion No.
    
    2022-Ohio-841
    , ¶ 8, quoting Westfield Ins. Co. v. Galatis, 
    100 Ohio St.3d 216
    , 2003-
    Ohio-5849, 
    797 N.E.2d 1256
    , ¶ 11. We must “examine the contract as a whole and
    presume that the intent of the parties is reflected in the language of the contract.”
    Sunoco, Inc. (R&M) v. Toledo Edison Co., 
    129 Ohio St.3d 397
    , 
    2011-Ohio-2720
    , 
    953 N.E.2d 285
    , ¶ 37. Contract terms that are clear and unambiguous “should be applied
    as written.” Sutton Bank v. Progressive Polymers, L.L.C., 
    161 Ohio St.3d 387
    , 2020-
    Ohio-5101, 
    163 N.E.3d 546
    , ¶ 18. “[C]ommon words appearing in a written instrument
    will be given their ordinary meaning unless manifest absurdity results, or unless some
    other meaning is clearly evidenced from the face or overall contents of the
    instrument.” Id. at ¶ 15, quoting Alexander v. Buckeye Pipe Line Co., 
    53 Ohio St.2d 241
    , 
    374 N.E.2d 146
     (1978), paragraph two of the syllabus.
    {¶26} Where the terms in a contract are clear and unambiguous, courts
    “cannot in effect create a new contract by finding an intent not expressed in the clear
    language employed by the parties.” Alexander at 246. Where terms are not defined
    in the contract, courts rely upon dictionary definitions of the terms to determine their
    plain and ordinary meaning.      Id. at 247-248 (applying dictionary definitions of
    unambiguous contract terms); Mr. Pulpstone, LLC v. Shops on 58, LLC, 9th Dist.
    Lorain No. 21CA011718, 
    2021-Ohio-4467
    , ¶ 11; Sunoco at ¶ 38-39 (court looked to
    dictionary definitions of “arrangement” because the term was not defined in the
    parties’ agreement); Nationwide Mut. Fire Ins. Co. v. Guman Bros. Farm, 
    73 Ohio St.3d 107
    , 109, 
    652 N.E.2d 684
     (1995) (court applied Black’s Law Dictionary
    definition of “employee” where the term was not defined in parties’ contract).
    12
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶27} In this case, both parties assert that the Agreement’s terms are clear and
    unambiguous, and that the Agreement contemplated two types of revenue bonds:
    Property Acquisition Bonds and Redevelopment Bonds. They agree that, pursuant to
    Paragraph D(4) of the Agreement, the Port paid Vandercar’s $2.5 million
    Development Fee on the closing date of the acquisition of the Real Property. They
    disagree, however, on the meaning of the term “Redevelopment Bonds” in the
    Agreement and whether the February revenue bond issuance included Redevelopment
    Bonds.
    {¶28} The Port argues that the February revenue bonds were solely Property
    Acquisition Bonds, which it issued to finance acquisition, site studies, and demolition
    of the old Millennium Hotel. Vandercar argues that the February revenue bonds
    consisted of both Property Acquisition Bonds and Redevelopment Bonds. In support
    of their respective positions, both parties point to Paragraph C of the Agreement,
    which we set forth again:
    C. Port wishes to acquire the Real Property3 in order to redevelop, or
    cause to be redeveloped, the Real Property for a new hotel (the
    “Project”), which such acquisition of the Real Property may be financed
    with the proceeds of revenue bonds issued by the Port Authority (the
    “Property Acquisition Bonds”), and such redevelopment will be
    financed with the proceeds of revenue bonds issued by the Port
    Authority (the “Redevelopment Bonds”). The Property Acquisition
    Bonds and the Redevelopment Bonds may be issued at the same time as
    part of one issuance of bonds or, alternatively, may be issued on
    separate dates as determined by the Port.
    (Emphasis sic.)
    3The Real Property referred to in the Agreement was defined in the July 1, 2019 Purchase Contract
    to include the Land and Improvements at the Millennium Hotel site.
    13
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶29} The Agreement is clear and unambiguous. It provides for Property
    Acquisition Bonds to acquire the property and Redevelopment Bonds to redevelop the
    property. The only remaining question is whether demolition and site studies are part
    of “acquisition” or “redevelopment.”
    {¶30} Vandercar argues that “acquisition” means what it says, and does not
    include demolition. Rather, demolition and site studies are part of “redevelopment.”
    {¶31} The Port claims that demolition is part of acquisition, and not
    redevelopment. The Port contends that the only reasonable construction of “such
    redevelopment” in the context of the Agreement is “redevelop[ing] the Real Property
    for a new hotel”—the explicit antecedent in the first clause of the sentence. The Port
    contends that Redevelopment Bonds can only be those issued to finance “a new hotel,”
    and do not include bonds issued for acquisition, demolition of the old hotel, or other
    activities that do not result directly in “a new hotel.” The Port claims that nothing in
    Paragraph C prevented its use of Property Acquisition Bonds to finance both
    acquisition and what it calls “pre-development activities,” such as site studies and
    demolition, without triggering the Redevelopment Fee.
    {¶32} The Port also argues that the final sentence of Paragraph C means that
    the parties intended either one issuance of bonds to pay for everything from
    acquisition to new hotel construction, or two separate issuances of bonds in amounts
    sufficient to cover acquisition and construction of a new hotel, respectively. This
    sentence provided that “The Property Acquisition Bonds and the Redevelopment
    Bonds may be issued at the same time as part of one issuance of bonds or, alternatively,
    may be issued on separate dates as determined by the Port.” However, nothing in the
    final sentence limits the Port to a single issuance of Redevelopment Bonds. Under the
    clear language of the contract, the Port could issue Property Acquisition Bonds and
    Redevelopment Bonds “at the same time as part of one issuance of bonds,” or “on
    14
    OHIO FIRST DISTRICT COURT OF APPEALS
    separate dates.” So, as Vandercar correctly asserts, a single bond issuance could
    include only Property Acquisition Bonds, only Redevelopment Bonds, or some of each.
    {¶33} The Agreement did not define “acquisition” or “redevelopment,” and
    defined “Property Acquisition Bonds” only as bonds issued to acquire the Real
    Property and “Redevelopment Bonds” as those issued for redevelopment of the Real
    Property. Because the Agreement did not define the terms “Property Acquisition
    Bonds” or “Redevelopment Bonds” beyond this general description, we turn, as the
    trial court did, to dictionary definitions of the terms to determine their plain and
    ordinary meaning. The Agreement allowed the proceeds of Property Acquisition
    Bonds to finance “such acquisition of the Real Property.” The word “such” refers back
    to the opening clause’s reference to the Port’s wish to “acquire the Real Property.” The
    plain and ordinary meaning of “acquisition” is “[t]he gaining of possession or control
    over something; esp., the act of getting land, power, money, etc.” Black’s Law
    Dictionary (11th Ed.2019). Thus, the Property Acquisition Bonds are limited to the
    acquiring of the property and nothing more.
    {¶34} That leads us then to what is a Redevelopment Bond. The Agreement
    provided that the proceeds of Redevelopment Bonds were to be used to finance “such
    redevelopment,” referring to the introductory clause “Port wishes to acquire the Real
    Property in order to redevelop, or cause to be redeveloped, the Real Property for a new
    hotel[.]”   The plain and ordinary meaning of “Redevelopment” refers to
    “[r]ehabilitation of an urban-residential or commercial section that is subject to blight
    or in decline, esp. by erecting new buildings or renovating the old ones, often with
    public financing or tax-increment financing.” Black’s Law Dictionary (11th Ed.2019).
    {¶35}   Applying these dictionary definitions, we agree with the trial court
    that, as used in the Agreement, “acquisition” refers only to the Port’s gaining of
    possession or control of the Real Property.         We find that redevelopment and
    15
    OHIO FIRST DISTRICT COURT OF APPEALS
    rehabilitation include demolition, site studies, and the like. Thus, the revenue bonds
    were issued by the Port for both acquisition and redevelopment of the site.
    {¶36} Our conclusion is bolstered by the Port’s own description of the bonds.
    The issuance was described as “Convention Center Hotel Acquisition and Demolition
    Project.” The Port itself made a distinction between “Acquisition” and “Demolition.”
    And it also did so in the January Resolution where it used the separate terms of
    “acquisition” and “demolition.”
    {¶37} If we were to adopt the Port’s position as to the meanings of “Property
    Acquisition Bonds” and “Redevelopment Bonds,” we would effectively be rewriting the
    parties’ agreement, which we will not do. See Beverage Holdings, L.L.C. v. 5701
    Lombardo, L.L.C., 
    159 Ohio St.3d 194
    , 
    2019-Ohio-4716
    , 
    150 N.E.3d 28
    , ¶ 25, quoting
    Foster Wheeler Enviresponse, Inc. v. Franklin Cty. Convention Facilities Auth., 
    78 Ohio St.3d 353
    , 362, 
    678 N.E.2d 519
     (1997) (“To the extent that [one of the parties]
    may be dissatisfied with the purchase price that resulted from the plain language
    agreed to by the parties, ‘[i]t is not the responsibility or function of this court to rewrite
    the parties’ contract in order to provide for a more equitable result’ ”).
    {¶38} We hold that the trial court properly entered summary judgment in
    favor of Vandercar on its breach-of-contract claim (and denied summary judgment to
    the Port on the same claim) because no genuine issue of fact remained—under the
    plain meaning of the terms used in the parties’ Agreement, the February revenue
    bonds included Redevelopment Bonds which triggered the Port’s obligation to pay
    Vandercar’s $5 million Redevelopment Fee. Therefore, we overrule the Port’s first and
    second assignments of error.
    Vandercar’s Appeal
    {¶39} In two assignments of error, Vandercar argues that the trial court erred
    by granting the Port’s Civ.R. 12(C) motion for judgment on the pleadings on its bad-
    16
    OHIO FIRST DISTRICT COURT OF APPEALS
    faith claim and by denying its motion for prejudgment interest on its award for the
    breach-of-contract claim.
    A.      Bad-Faith Claim
    {¶40} Dismissal on a Civ.R. 12(C) motion for judgment on the pleadings is
    proper when a court construes as true the material allegations in the complaint, along
    with all reasonable inferences to be drawn therefrom, and finds, beyond doubt, that
    the plaintiff can prove no set of facts that would entitle the plaintiff to relief. Reister
    v. Gardner, 
    164 Ohio St.3d 546
    , 
    2020-Ohio-5484
    , 
    174 N.E.3d 713
    , ¶ 17, citing State ex
    rel. Midwest Pride IV, Inc. v. Pontious, 
    75 Ohio St.3d 565
    , 570, 
    664 N.E.2d 931
     (1996).
    A Civ.R. 12(C) motion permits the court to consider the complaint and the answer in
    deciding whether the movant is entitled to judgment as a matter of law. State ex rel.
    Fire Rock, Ltd. v. Ohio Dept. of Commerce, 
    163 Ohio St.3d 277
    , 
    2021-Ohio-673
    , 
    169 N.E.3d 665
    , ¶ 6, citing Pontious at 569. We review a trial court’s ruling on a Civ.R.
    12(C) motion for judgment on the pleadings de novo. Reister at ¶ 17.
    {¶41} Vandercar alleged in its complaint that the Port was liable for
    Vandercar’s attorney fees because the Port acted in bad faith by refusing to pay the
    Redevelopment Fee and by structuring the February revenue bonds to make it appear
    that they were not issued for redevelopment to avoid having to pay the fee. Vandercar
    pled this as a separate cause of action in its complaint.
    {¶42} We address the bad-faith attorney-fee issue both as a separate cause of
    action and as a request to include an award of attorney fees as costs. As to the former,
    we affirm the trial court’s determination that no separate claim exists. But as to the
    latter, we return the case to the trial court.
    i. Bad Faith as a Separate Claim
    {¶43} Ohio recognizes that implied in every contract is a duty of good faith and
    fair dealing. Lucarell v. Nationwide Mut. Ins. Co., 
    152 Ohio St.3d 453
    , 
    2018-Ohio-15
    ,
    
    97 N.E.3d 458
    , ¶ 42. However, Ohio law is clear that it does not give rise to a stand-
    17
    OHIO FIRST DISTRICT COURT OF APPEALS
    alone claim. “[T]he duty of good faith and fair dealing does not stand alone from the
    contract but is a part of it.” Great Water Capital Partners, LLC v. Down-Lite
    Internatl., Inc., 1st Dist. Hamilton Nos. C-150015 and C-150023, 
    2015-Ohio-4877
    , ¶
    14. Therefore, a breach-of-contract claim subsumes an accompanying claim for the
    breach of the duty of good faith and fair dealing. Shertok v. Wallace Group Gen.
    Dentistry for Today, Inc., 1st Dist. Hamilton Nos. C-190457 and C-190464, 2020-
    Ohio-4369, ¶ 40. As a result, there is no independent cause of action for a breach of
    the duty of good faith separate from the underlying breach-of-contract claim. 
    Id.
    ii. Bad Faith as Basis for Award of Attorney Fees as Costs
    {¶44} But Vandercar does not simply claim that it is entitled to attorney fees
    under the doctrine of good faith and fair dealing. Rather, it relies on our decision in
    SST Bearing Corp. v. Twin City Fan Cos., 1st Dist. Hamilton No. C-110611, 2012-Ohio-
    2490, which permits the recovery of attorney fees in a breach-of-contract case where
    a plaintiff can establish bad faith by the breaching party.
    {¶45} Ohio courts generally follow the “American rule” with respect to
    attorney fees: “a prevailing party in a civil action may not recover attorney fees as part
    of the costs of litigation.” Wilborn v. Bank One Corp., 
    121 Ohio St.3d 546
    , 2009-Ohio-
    306, 
    906 N.E.2d 396
    , ¶ 7, citing Nottingdale Homeowners’ Assn., Inc. v. Darby, 
    33 Ohio St.3d 32
    , 33-34, 
    514 N.E.2d 702
     (1987), and State ex rel. Beebe v. Cowley, 
    116 Ohio St. 377
    , 382, 
    156 N.E. 214
     (1927). But there are three well-recognized exceptions
    to this rule: (1) where a statute specifically provides that a prevailing party may recover
    attorney fees; (2) where the parties’ contract provides for fee shifting; and (3) where
    there has been a finding of bad faith. SST Bearing at ¶ 28, citing Keal v. Day, 
    164 Ohio App.3d 21
    , 
    2005-Ohio-5551
    , 
    840 N.E.2d 1139
    , ¶ 5 (1st Dist.).
    {¶46} “A party seeking attorney fees based on the bad-faith exception to the
    American rule ‘must be the prevailing party in the litigation, and then must prove that
    his opponent acted in bad faith.’ ” Covenant Dove Holding Co., LLC v. Mariner Health
    18
    OHIO FIRST DISTRICT COURT OF APPEALS
    Care, Inc., 1st Dist. Hamilton No. C-120878, 
    2013-Ohio-3824
    , ¶ 7, quoting Strum v.
    Strum, 
    63 Ohio St.3d 671
    , 675, 
    590 N.E.2d 1214
     (1991). “Bad faith” generally implies
    “a dishonest purpose, moral obliquity, conscious wrongdoing, breach of a known duty
    due to ulterior motive, ill will comparable to fraud, or an actual intent to mislead or
    deceive another.” Id. at ¶ 7. Although an award of attorney fees may be granted in a
    contract action upon a finding by the trial court of bad-faith conduct, a trial court errs
    by awarding attorney fees where it has made no finding of bad faith. Id. at ¶ 8; Wright
    v. Fleming, 1st Dist. Hamilton No. C-070121, 
    2008-Ohio-1435
    , ¶ 5. We emphasize
    that an award of attorney fees is generally not available in contract actions and will be
    warranted only in an exceptional case.
    {¶47} In SST Bearing, we held that the trial court was within its discretion to
    award attorney fees in a breach-of-contract action when it made an explicit finding
    that the breaching party acted in bad faith. In that case, the trial court found that the
    buyer had used the seller’s price to obtain leverage with other competitors, had tried
    to obtain trade-secret information from the seller, had canceled the entire contract
    with the seller prior to testing any of the seller’s products and had canceled orders for
    products for which the buyer could find no fault, and refused to give the seller an
    opportunity to cure any potential defects. SST Bearing, 1st Dist. Hamilton No. C-
    110611, 
    2012-Ohio-2490
    , at ¶ 29.
    {¶48} Thereafter, we granted the buyer’s motion to certify a conflict between
    our decision and the decisions of two other appellate districts on the following
    question:
    The “American Rule” does not permit the prevailing party to recover
    attorneys[] fees in the absence of a statutory authorization. Does Ohio
    recognize an exception to the American Rule for “bad faith” breach of
    contract in absence of an award of punitive damages?
    19
    OHIO FIRST DISTRICT COURT OF APPEALS
    The buyer appealed to the Supreme Court of Ohio, which declined jurisdiction.
    SST Bearing Corp. v. Twin City Fan Cos., Ltd., 
    133 Ohio St.3d 1413
    , 
    2012-Ohio-4650
    ,
    
    975 N.E.2d 1031
    . On review of the order certifying a conflict, the Supreme Court
    “determined that no conflict exists,” and dismissed the matter. SST Bearing Corp. v.
    Twin City Fan Cos., Ltd., 
    133 Ohio St.3d 1408
    , 
    2012-Ohio-4650
    , 
    975 N.E.2d 1027
    . The
    Supreme Court denied a subsequent motion for reconsideration. SST Bearing Corp.
    v. Twin City Fan Cos., Ltd., 
    133 Ohio St.3d 1494
    , 
    2012-Ohio-5459
    , 
    978 N.E.2d 912
    .
    {¶49} In examining Ohio law in a contract action where the plaintiffs’
    complaints included counts seeking attorney fees based on the defendant’s bad-faith
    conduct, the United States District Court for the Southern District of Ohio explained
    the difference between a stand-alone claim and a recovery of attorney fees for bad-
    faith conduct. In Avis Rent a Car Sys., LLC v. City of Dayton, S.D.Ohio Nos. 3:12-cv-
    399 and 3:12-cv-405, 
    2013 U.S. Dist. LEXIS 119597
    , *7-8 (Aug. 22, 2013) (“Avis I”),
    the court stated:
    [I]n breach of contract cases, Ohio courts that award attorneys’ fees
    after a showing of bad faith conduct do so as an award of costs to the
    prevailing party, not as an element of damages. [(citing SST Bearing
    and Columbus Med. Equip. Co. v. Watters, 
    13 Ohio App.3d 149
    , 
    468 N.E.2d 343
     (10th Dist.1983)] * * * Even though the Plaintiffs have pled
    a separate count for attorneys’ fees based on allegations of bad faith
    conduct, such a claim is not cognizable under Ohio law as a free-
    standing cause of action, as “good faith is part of a contract claim and
    does not stand alone.” Lakota Local Sch. Dist. v. Brickner, 
    108 Ohio App.3d 637
    , 
    671 N.E.2d 578
    , 584 (Ohio Ct. App. 1996). Thus, the issue
    of whether to award attorneys’ fees to Plaintiffs is entirely appropriate
    to award post-judgment, or even post-appeal, after a complete and final
    resolution of the merits of their case.
    20
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶50} The court noted that before it entered summary judgment in favor of the
    plaintiffs on their motions for summary judgment on their contract claims, the
    plaintiffs had amended their complaints to include counts seeking attorney fees, based
    on alleged “bad faith” conduct by the defendant. Id. at *3-4. Because Ohio does not
    recognize a stand-alone cause of action for bad faith in a contract claim, the court
    dismissed the bad-faith counts in the plaintiffs’ complaints and ordered the plaintiffs
    to file postjudgment motions for attorney fees to preserve their rights to request
    attorney fees, should the court’s summary-judgment rulings be affirmed. Id. at *10-
    11.
    {¶51} Then the plaintiffs filed their motions for attorney fees, the defendant
    appealed the court’s decision, and the Sixth Circuit Court of Appeals affirmed the
    decision. See Avis Rent A Car Sys., LLC v. City of Dayton, S.D.Ohio No. 3:12-cv-399,
    
    2015 U.S. Dist. LEXIS 129516
    , *16 (Sept. 25, 2015) (“Avis II”). Thereafter, the district
    court addressed the plaintiffs’ motions for attorney fees, applying Ohio law. Id. at *17.
    {¶52} The defendant argued that the court should deny the motions for
    attorney fees because the Supreme Court of Ohio had never held that attorney fees are
    recoverable for a bad-faith breach of contract. Id. at *22. However, the district court
    “believe[d] that the Ohio Supreme Court would recognize the exception to the
    American Rule for attorneys’ fees based on bad-faith conduct giving rise to a breach-
    of-contract claim” for several reasons. Id.
    {¶53} First, the district court pointed to our decision in SST Bearing and other
    Ohio decisions affirming such awards in contract cases where no tort or punitive
    damages provided the basis for attorney fees. See id. at *25-32, citing SST Bearing,
    1st Dist. Hamilton No. C-110611, 
    2012-Ohio-2490
    ; Dodson v. Maines, 6th Dist.
    Sandusky No. S-11-012, 
    2012-Ohio-2548
     (upholding award of attorney fees for bad-
    faith conduct in an unjust-enrichment action sounding in contract); Hall v. Frantz,
    9th Dist. Summit No. 19630, 
    2000 Ohio App. LEXIS 2186
     (May 24, 2000) (upholding
    21
    OHIO FIRST DISTRICT COURT OF APPEALS
    attorney-fee award for bad-faith conduct in an action to enforce a settlement
    agreement); and LEH Properties, Inc. v. Pheasant Run Assn., 9th Dist. Lorain No.
    10CA009780, 
    2011-Ohio-516
     (affirming attorney-fee award for a party’s bad-faith
    noncompliance with a settlement agreement).
    {¶54} Second, the district court viewed as persuasive the Supreme Court of
    Ohio’s determination that our decision in SST Bearing was not in conflict with
    decisions of other appellate districts. Avis II at *32-34. The court stated that the ruling
    “provide[d] an addition reason to believe that [the Supreme Court of Ohio] might
    recognize the exception to the American Rule affirmed in that case.” Id. at *34.
    {¶55} Finally, the district court pointed to the Supreme Court of Ohio’s
    decision in State ex rel. Chapnick v. East Cleveland City School Dist., 
    93 Ohio St.3d 449
    , 
    755 N.E.2d 883
     (2001), which could “be read to implicitly assume that the
    plaintiff might have been entitled to attorneys’ fees based on bad faith” where “the
    conduct in question occurred entirely before he filed suit.” Avis II at *34-35.
    {¶56} In following our prior decision in SST Bearing, we also agree with the
    district court’s analysis in Avis II. We hold that in an exceptional case, a party may
    recover attorney fees if it can establish bad faith on the part of the breaching party.
    And the bad faith need not involve only conduct occurring during litigation. See 
    id.
     It
    can involve conduct giving rise to a party’s claim. See SST Bearing, 1st Dist. Hamilton
    No. C-110611, 
    2012-Ohio-2490
    , at ¶ 29; Cleveland Fire Fighters, Local 93 of the
    I.A.F.F. v. City of Cleveland, 8th Dist. Cuyahoga No. 109136, 
    2020-Ohio-4751
    , ¶ 37
    (finding no abuse of discretion in trial court’s denial of attorney fees upon its finding
    that defendant did not act in bad faith). “If a trial court makes a finding that the losing
    party had acted in bad faith, and if that finding is supported by the record, an award
    of attorney fees is warranted.” Covenant Dove, 1st Dist. Hamilton No. C-120878,
    
    2013-Ohio-3824
    , at ¶ 7. Again, we note that this will generally not be available in a
    breach-of-contract action.
    22
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶57} In this case, the trial court determined on the face of the complaint that
    “there is no indication of bad faith in the present action.” However, taking the
    allegations of the complaint as true, we cannot conclude that there is no set of facts
    under which Vandercar could recover. We thus sustain Vandercar’s first assignment
    of error, reverse the trial court’s decision in this regard, and return this matter to the
    court for a determination of whether the Port acted in bad faith.
    B.    Prejudgment Interest
    {¶58} In its second assignment of error, Vandercar argues that the trial court
    erred by denying its motion for prejudgment interest. It asserts that prejudgment
    interest is mandated by R.C. 1343.03(A), and that the trial court erred by finding that
    prejudgment interest could not be imposed upon the Port because it was an arm or
    instrumentality of the state.
    {¶59} Generally, a party granted judgment on an underlying contract claim is
    entitled to prejudgment interest as a matter of law, pursuant to R.C. 1343.03(A).
    Ronald J. Solomon, D.D.S., Inc. v. Davisson, 
    2018-Ohio-2011
    , 
    113 N.E.3d 1003
    , ¶ 7
    (1st Dist.). R.C. 1343.03(A) provides:
    In cases other than those provided for in sections 1343.01 and 1343.02
    of the Revised Code, when money becomes due and payable upon any
    bond, bill, note, or other instrument of writing, upon any book account,
    upon any settlement between parties, upon all verbal contracts entered
    into, and upon all judgments, decrees, and orders of any judicial
    tribunal for the payment of money arising out of tortious conduct or a
    contract or other transaction, the creditor is entitled to interest at the
    rate per annum determined pursuant to section 5703.47 of the Revised
    Code, unless a written contract provides a different rate of interest in
    relation to the money that becomes due and payable, in which case the
    creditor is entitled to interest at the rate provided in that contract.
    23
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶60} Nevertheless, R.C. 1343.03(A) does not require the payment of
    prejudgment interest by an arm or instrumentality of the state in a contract action.
    See Beifuss v. Westerville Bd. of Edn., 
    37 Ohio St.3d 187
    , 190, 
    525 N.E.2d 20
     (1988)
    (in the absence of statutory authority, a public school board cannot be held liable for
    prejudgment interest on damages assessed in a contract action). As the Supreme
    Court of Ohio explained in Beifuss, “[i]t is well-established that ‘[i]n the absence of a
    statute requiring it, or a promise to pay it, interest cannot be adjudged against the state
    for delay in the payment of money.’ ”4 Id. at 188-189, quoting State ex rel. Parrott v.
    Bd. of Pub. Works, 
    36 Ohio St. 409
     (1881), paragraph four of the syllabus. The court
    held that this “interest rule” applied “to public school boards as it has been applied to
    the state and its agencies.” Id. at 189.
    {¶61} The Beifuss court stated that it refused “to abandon our long-standing
    rule in contract actions that, in the absence of a statute requiring it, or a promise to
    pay it, interest cannot be assessed against the state for delay in the payment of money.”
    (Emphasis sic.) Id. at 190. The court noted that in its prior cases, “we refused to
    abandon the interest rule despite the fact that prejudgment interest was allowable in
    cases filed against the state in the Court of Claims under R.C. 2743.18.” Id. at 190,
    citing State ex rel. Home Care Pharmacy, Inc. v. Creasy, 
    67 Ohio St.2d 342
    , 
    423 N.E.2d 482
     (1981), and State ex rel. Montrie Nursing Home v. Creasy, 
    5 Ohio St.3d 124
    , 
    449 N.E.2d 763
     (1983). In construing R.C. 1343.03(A), the court determined that
    the statutory provision did not “clearly express any intention of the legislature to
    assess prejudgment interest against a public school board in this type of action.” Id.
    at fn. 1.; State ex rel. Stacy v. Batavia Local School Dist. Bd. of Edn., 
    105 Ohio St.3d 476
    , 
    2005-Ohio-2974
    , 
    829 N.E.2d 298
    , ¶ 62. The court found that any expansion of a
    4 We note that a rule that the state is not liable for prejudgment interest in a case where it has
    delayed payment (i.e., slow pay) makes sense due to the bureaucracy and paperwork that may be
    involved when the state makes payment. The cases, however, go well beyond simply delayed
    payments and included, as did Beifuss, cases where the state disclaims liability altogether.
    24
    OHIO FIRST DISTRICT COURT OF APPEALS
    public school board’s contractual liability to allow prejudgment interest “should be
    created through clearly expressed legislation by the General Assembly or by the parties
    themselves at the bargaining table.” Id. at 190.
    {¶62} The court held that a public school board is an arm of the state because
    its duties and powers are defined extensively in R.C. Title 33 and it is “ultimately
    managed and controlled by the dictates of the General Assembly.” Id. at 189, quoting
    Thaxton v. Medina City Bd. of Edn., 
    21 Ohio St.3d 56
    , 57, 
    488 N.E.2d 136
     (1986). The
    court held that a public school board was not liable for the payment of prejudgment
    interest on an award of back pay because there was no statute or contractual provision
    requiring it. Id. at 190.
    {¶63} The Supreme Court has also declined to award prejudgment interest on
    an employee’s award of back pay against a county sheriff’s department. See State ex
    rel. Carver v. Hull, 
    70 Ohio St.3d 570
    , 579, 
    639 N.E.2d 1175
     (1994). In Carver, the
    Supreme Court rejected the employee’s argument that she was entitled to prejudgment
    interest on an award of back pay under R.C. 1343.03(A), because the provision “d[id]
    not specifically establish that a county can be held liable for interest on a judgment at
    all, much less for prejudgment interest.” Id. at fn. 3.
    {¶64} In White v. Summit Cty. Dept. of Human Servs., 9th Dist. Summit Nos.
    23740 and 23741, 
    2008-Ohio-176
    , the Ninth District followed the approach taken by
    the Beifuss court and determined that a county department of job and family services,
    like a public school board, is an arm of the state because it is “ultimately managed and
    controlled by the dictates of the General Assembly.” White at ¶ 14, quoting Beifuss, 37
    Ohio St.3d at 189, 
    525 N.E.2d 20
    . The court noted that the county department was
    created under R.C. Chapter 329, which extensively detailed the department’s duties
    and powers. Id. at ¶ 13. The court held that prejudgment interest may not accrue
    against the department in the absence of a statute authorizing it. Id. at ¶ 14.
    25
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶65} And in State ex rel. Mendez v. Pub. School Emp. Retirement Sys., 10th
    Dist. Franklin No. 88AP-458, 
    1989 Ohio App. LEXIS 1934
    , *10-11 (May 23, 1989), the
    Tenth District held that a school employees retirement board, which was a creature of
    statute and could act only in accordance with its enabling statutory scheme, was an
    instrumentality of the state. The court held that no general statute, including R.C.
    1343.03, provided for interest to be ordered against the state in actions other than
    those brought in the Court of Claims, and therefore, prejudgment interest could not
    be assessed against the retirement board. Id. at *12-13.
    {¶66} As relevant here, a port authority is a political subdivision of the state of
    Ohio created under R.C. Chapter 4582. State ex rel. Toledo Blade Co. v. Toledo-Lucas
    Cty. Port Auth., 
    121 Ohio St.3d 537
    , 
    2009-Ohio-1767
    , 
    905 N.E.2d 1221
    , ¶ 11. R.C.
    4582.21(A) defines a “port authority” as “a body corporate and politic created pursuant
    to the authority of section 4582.22 of the Revised Code.” R.C. 4582.22, in turn,
    provides that port authorities exercise essential governmental functions of the state.
    That statute provides in relevant part:
    A port authority created pursuant to this section is a body corporate and
    politic which may sue and be sued, plead and be impleaded, and has the
    powers and jurisdiction enumerated in sections 4582.21 to 4582.59 of
    the Revised Code. The exercise by such port authority of the powers
    conferred upon it shall be considered to be essential governmental
    functions of this state, but no port authority is immune from liability by
    reason thereof.
    R.C. 4582.22(A). A port authority’s powers are detailed in R.C. 4582.31(A)(1)-(27).
    {¶67} Like the public school board in Beifuss, the county department of
    human services in White, and the retirement board in Mendez, a port authority is an
    arm of the state because it is a creature of statute and its powers are extensively
    detailed by statute. Therefore, a port authority cannot be held liable for prejudgment
    26
    OHIO FIRST DISTRICT COURT OF APPEALS
    interest on damages assessed in a contract action in the absence of a statutory or
    contractual provision requiring it. See Beifuss, 37 Ohio St.3d at 188-189, 
    525 N.E.2d 20
    . And R.C. 1343.03(A), relied on by Vandercar, does not provide statutory authority
    to assess prejudgment interest against the state or an arm of the state in a contract
    action. See Beifuss at 190; Mendez at *12-13.
    {¶68} Vandercar seizes on the last clause of the last sentence of the statutory
    provision in R.C. 4582.22(A)—“no port authority is immune from liability by reason
    of” its performance of “essential governmental functions”—and argues that “when the
    General Assembly created this new form of public entity, it gave port authorities
    governmental powers but denied them any form of sovereign immunity.” (Emphasis
    deleted.) Contrary to Vandercar’s assertion, however, the Port never claimed that it
    was entitled to total sovereign immunity from Vandercar’s contract claim. Instead,
    the Port relied on the well-established interest rule, reiterated in Beifuss, that the state
    is not liable for prejudgment interest in the absence of a statute requiring it or a
    promise to pay it.
    {¶69} Moreover, unlike R.C. 2743.18(A), which provides a statutory right to
    prejudgment interest in suits against the state brought in the Court of Claims
    (“[p]rejudgment interest shall be allowed with respect to any civil action on which a
    judgment or determination is rendered against the state”), R.C. 4582.22(A) makes no
    mention of prejudgment interest. As the Supreme Court held long ago, “The state is
    not bound by the terms of a general statute, unless it be so expressly enacted.” State
    ex rel. Parrott v. Bd. of Pub. Works, 
    36 Ohio St. 409
     (1881), paragraph three of the
    syllabus.
    {¶70} Rather, like the Supreme Court’s description of R.C. 1343.03(A), the
    cited clause from R.C. 4582.22(A) does “not clearly express any intention of the
    legislature to assess prejudgment interest” against an arm of the state. See Beifuss, 37
    Ohio St.3d at 191, fn. 1, 
    525 N.E.2d 20
    . Therefore, we decline to read into the phrase
    27
    OHIO FIRST DISTRICT COURT OF APPEALS
    “no port authority is immune from liability by reason [of its governmental functions]”
    a statutory requirement to assess prejudgment interest against a port authority. See
    In re Icebreaker Windpower, Inc., Slip Opinion No. 
    2022-Ohio-2742
    , ¶ 56 (“We may
    not add words to a statute to achieve a desired construction.”). If the legislature
    intended to assess prejudgment interest against a port authority in a contract action,
    it could have done so.
    {¶71} In the absence of statutory authority allowing prejudgment interest to
    be assessed against the Port in this action, or an agreement by the parties to pay it, we
    hold that prejudgment interest cannot be assessed against it on the contract award
    because it is an arm of the state. Therefore, we hold that the trial court properly denied
    Vandercar’s motion for prejudgment interest.          We overrule Vandercar’s second
    assignment of error.
    Conclusion
    {¶72} In summary, we hold that the trial court properly granted summary
    judgment in favor of Vandercar, and denied summary judgment in favor of the Port,
    on Vandercar’s breach-of-contract claim.        We hold that the trial court properly
    dismissed Vandercar’s bad-faith claim as a stand-alone claim and denied its motion
    for prejudgment interest. We hold, however, that the trial court erred in granting
    judgment on the pleadings as to Vandercar’s claimed entitlement to attorney fees as a
    result of claimed bad faith on the part of the Port. Therefore, we affirm the trial court’s
    entry of summary judgment in favor of Vandercar on its breach-of-contract claim and
    its entry denying prejudgment interest. We reverse the trial court’s judgment on the
    pleadings on Vandercar’s bad-faith claim and remand the matter to the trial court for
    a determination of whether the Port acted in bad faith, and, if so, whether an award of
    attorney fees in favor of Vandercar is warranted.
    Judgment accordingly.
    28
    OHIO FIRST DISTRICT COURT OF APPEALS
    BERGERON and BOCK, JJ., concur.
    Please note:
    The court has recorded its own entry this date.
    29