Bacak v. Ventling , 2016 Ohio 4737 ( 2016 )


Menu:
  • [Cite as Bacak v. Ventling, 
    2016-Ohio-4737
    .]
    IN THE COURT OF APPEALS
    ELEVENTH APPELLATE DISTRICT
    TRUMBULL COUNTY, OHIO
    JOE BACAK, et al.,                             :      OPINION
    Cross-Appellees,              :
    CASE NO. 2015-T-0029
    - vs -                                 :
    TRUMBULL COUNTY BOARD OF                       :
    COMMISSIONERS, et al.,
    :
    Defendants,
    :
    GARY P. VENTLING,
    :
    Cross-Appellant.
    :
    Civil Appeal from the Trumbull County Court of Common Pleas, Case No. 2004 CV
    02140.
    Judgment: Affirmed.
    Frank R. Bodor, 157 Porter Street, N.E., Warren, OH 44483 (For Cross-Appellees).
    Thomas C. Nader, 5000 East Market Street, #33, Warren, OH 44484 (For Cross-
    Appellant).
    CYNTHIA WESTCOTT RICE, P.J.
    {¶1}     Cross-appellant, Gary Ventling (hereafter “appellant”), appeals the
    judgment of the Trumbull County Court of Common Pleas, following a trial to the
    magistrate, in favor of appellees, Joe Bacak, et al., and against appellant and the
    Trumbull County Board of Commissioners, declaring R.C. 307.73, regarding private
    contracts for the construction of sewer lines, to be unconstitutional. Appellant appealed
    the trial court’s finding that R.C. 307.73 is unconstitutional as applied to appellees;
    however, he did not appeal the trial court’s additional finding that the statute is
    unconstitutional on its face. At issue is whether the trial court’s declaration that R.C.
    307.73 is unconstitutional on its face includes the finding that the statute is
    unconstitutional as applied to appellees. Because we hold that it does, we affirm.
    {¶2}     Plaintiffs-appellees, Joe Bacak and some nine other individuals, are
    property owners and residents of Trumbull County, who formed an association known
    as “C.A.U.S.E.,” which stands for Citizens Against Unconstitutional Sewer Extensions.
    Appellees referred to themselves in the trial court as the “Sablecreek Plaintiffs” in order
    to distinguish themselves from other similarly-situated groups included in C.A.U.S.E.
    Appellees reside on St. Mary’s Drive in Mineral Ridge, Ohio, and were ordered by the
    Trumbull County Commissioners to tie into a new sewer extension on St. Mary’s Drive
    and to reimburse appellant, who constructed the extension, for the costs of its
    construction.
    {¶3}     In their Complaint, filed August 26, 2004, appellees requested declaratory
    judgment and injunctive relief against the commissioners and appellant, alleging that
    R.C. 307.73, which authorizes private sewer construction projects, is unconstitutional in
    that it violates procedural due process.
    {¶4}     The case proceeded to trial before the magistrate.     As fully explained
    below, the trial court entered judgment in favor of appellees and against the
    commissioners and appellant. The commissioners and appellant filed separate appeals
    in this court. Subsequently, the commissioners dismissed their appeal and appellant’s
    appeal is the only appeal remaining before us.
    2
    {¶5}   Appellees had previously installed septic systems to service their homes
    due to the unavailability of a sewer system in their area.
    {¶6}   On August 30, 2001, appellant, who lives on St. Mary’s Drive, and the
    commissioners entered a “Private Agreement for Extension of Sanitary Sewer” for the
    extension of a sanitary sewer on St. Mary’s Drive pursuant to R.C. 307.73.              On
    September 13, 2001, the commissioners enacted a resolution to enter said agreement.
    {¶7}   According to the agreement,          the   commissioners     gave   appellant
    permission to construct the sewer extension to his property. Appellant agreed to pay for
    the preparation of plans and specifications for the project and for construction of the
    sewer line. Further, the agreement provided that “[i]f and when any abutting property * *
    * desires to tap into or connect to said improvements, a connection charge will be
    charged the owner of said abutting property based on the pro rata costs as computed
    from the * * * cost statement which shall be reimbursed to [appellant] * * *.”
    {¶8}   Appellant did not advertise for or take any bids on this project, as such is
    not required by R.C. 307.73. Instead, he hired the engineering firm of Lynn, Kittinger, &
    Noble to prepare the plans and specifications. He also hired Ady & Sons Construction
    to construct the sewer extension.
    {¶9}   Appellant began construction of the project on May 9, 2002.               He
    completed the sewer extension on November 13, 2002, and the Trumbull County
    Sanitary Engineer’s Office issued a certificate of completion on that date. One week
    later, on November 21, 2002, appellant submitted a cost statement to the Sanitary
    Engineer’s Office for approval. The original estimated cost of the project was $61,000,
    but the cost statement submitted by appellant was $103,460, which was $42,460, or
    41%, over the original estimate.
    3
    {¶10} Prior to completion of the project, neither the commissioners nor appellant
    ever sent any letters or other form of written notice to appellees notifying them of the
    existence of the private sewer extension agreement or that appellees would be
    responsible for paying their pro rata share of the cost. Rather, for the first time, on April
    7, 2004, 17 months after completion of the project, appellant filed a copy of the
    commissioners’ resolution to enter the private sewer extension agreement with the
    Trumbull County Auditor.
    {¶11} On December 13, 2003, the Trumbull County Health Department sent
    letters to appellees advising them that they were required to abandon their own septic
    systems and to tap into the new sewer extension. Appellees were also advised by
    these letters that when they tapped-in, they would have to pay to the county their total
    pro rata share of appellant’s costs for the sewer extension in one lump sum. However,
    the notice did not provide them with an exact or even an approximate amount of their
    cost.
    {¶12} Jay Walton, Senior Environmental Engineer with the Trumbull County
    Sanitary Engineer’s Office, testified he has the sole authority and discretion to approve
    the statement of costs submitted by individuals, such as appellant, with respect to
    private sewer construction projects. This includes reviewing the statement of costs and
    determining which, if any, of the submitted costs should be approved for reimbursement
    by the other abutting property owners. Walton’s decision is final and not subject to any
    objection, hearing, or appeal.    He testified that a property owner who tapped into the
    sewer extension would have to pay whatever amount he determined and would have no
    say in the matter.
    4
    {¶13} Walton found $29,281 of the $103,460 cost statement to be improper and
    approved the total cost of the sewer extension project as $74,179, which was still
    $14,000 over the original $61,000 cost estimate. The property owners on St. Mary’s
    Drive were never sent any notice as to the approved cost. The first time any owner
    would have discovered the cost of the tap-in would be when the property owner came to
    the Board of Health in response to the Board’s letter advising them that they were
    required to tap into the sewer extension and to pay their share of appellant’s costs.
    {¶14} Thomas Holloway, Trumbull County Sanitary Engineer at the time the
    subject project was approved, testified that, pursuant to R.C. 307.73, Walton has full
    discretion in determining the amount property owners who tap into a sewer extension
    will be required to pay. He said that whatever amount Walton determined the final cost
    to be, the property owner tapping into the extension is required to pay it and has no
    appeal from Walton’s decision. Under that procedure, the property owner is not given
    notice of the cost or an opportunity to object to it. He said there is an alternative
    procedure for a sewer construction project provided for at R.C. Chapter 6117. Under
    these provisions, the commissioners put the project out for bid and the improvement is
    ultimately paid for by an assessment. He said that, pursuant to Chapter 6117, the
    affected property owners are given notice of the preliminary assessment. Further, under
    that statute, property owners have the right to file objections, the right to a hearing, and
    the right to appeal the commissioners’ decision to the Probate Court.
    {¶15} The magistrate issued her decision on July 2, 2013, in favor of appellees
    and against appellant and the commissioners. The magistrate decided that R.C. 307.73
    is unconstitutional as applied in that it violated appellees’ procedural due process rights.
    The magistrate found that because appellees did not have proper notice under R.C.
    5
    307.73 and because appellees were required by Ohio Adm. Code 3701-29-02 to tie into
    the new sewer line, R.C. 307.73 is unconstitutional as applied to appellees and, thus,
    they were not required to pay the prorated cost of the sewer improvement project. The
    commissioners and appellant filed objections to the magistrate’s decision. The trial
    court, by its judgment filed on February 6, 2015, overruled the objections; modified the
    magistrate’s decision by also finding R.C. 307.73 to be unconstitutional on its face; and
    adopted the magistrate’s decision as modified.
    {¶16} The commissioners appealed the trial court’s judgment to this court on
    March 5, 2015. That appeal was assigned Case No. 2015-T-0019. On March 16, 2015,
    appellant filed a separate appeal, which was assigned Case No. 2015-T-0029. This
    court sua sponte consolidated the two appeals on April 17, 2015. On that same date,
    the commissioners filed a notice of dismissal of their appeal (Case No. 2015-T-0019).
    This court construed that notice as a motion to dismiss, and granted that motion on
    June 8, 2015. The dismissal of the commissioners’ appeal left only appellant’s appeal.
    {¶17} Appellant asserts six assignments of error. Because the third through
    sixth assigned errors are interrelated, they are considered together. They allege:
    {¶18} “[3.] The Trial Court’s Decision That Revised Code Section 307.73 is
    Unconstitutional as applied to the Sablecreek Plaintiffs is error.
    {¶19} “[4.] The Trial Court erred in finding that the Appellees did not have the
    Required Notice Pursuant to Revised Code Section 307.73.
    {¶20} “[5.] The Trial Court Erred in finding that Separate Sablecreek Plaintiffs
    Michael and Joanne Hanysh did not have constructive notice of the private extension
    agreement.
    6
    {¶21} “[6.]   The   Trial   Court   erred   in   concluding   that   the   Sablecreek
    Plaintiffs/Appellees did not have Actual Notice of the Ventling Private Extension
    Agreement.”
    {¶22} “On appeal, a trial court’s adoption of a magistrate’s decision will not be
    overruled unless the trial court abused its discretion in adopting the decision.” Brown v.
    Gabram, 11th Dist. Geuaga No. 2004-G-2605, 
    2005-Ohio-6416
    , ¶11. Accord In the
    Matter of Gibbs, 11th Dist. Lake No. 97-L-067, 
    1998 Ohio App. LEXIS 997
    , *12 (Mar.
    13, 1998) (an appellate review of the trial court’s decision under Civ.R. 53 is limited to a
    determination of whether the court abused its discretion in adopting the magistrate’s
    decision). The term “abuse of discretion” is one of art, “connoting judgment exercised by
    a court, which does not comport with reason or the record.” Gaul v. Gaul, 11th Dist.
    Ashtabula No. 2009-A-0011, 
    2010-Ohio-2156
    , ¶24, citing State v. Ferranto, 
    112 Ohio St. 667
    , 676-678 (1925).
    {¶23} R.C. 307.73, entitled, “Contract for private construction of * * * sewer
    lines,” provides that a board of county commissioners may, upon application by any
    individual or private entity, authorize such individual/entity to construct sewer lines
    under the board’s supervision.
    {¶24} R.C. 307.73 also provides that the board of commissioners shall collect
    and return to such individual/entity a prorated share of the cost of such improvement
    when such improvement is tapped into by a nonparticipant in the original cost, i.e., an
    abutting property owner who did not pay any part of the original cost. The prorated
    share is based on the front footage of improvement to the nonparticipant, and shall not
    exceed the amount the nonparticipant would have paid if he had participated in said
    project.
    7
    {¶25} R.C. 307.73 also provides that a copy of the commissioners’ resolution
    granting permission to construct sewer lines and authorizing the collection of a prorated
    share shall be filed by the applicant (here, appellant) with the county auditor, who shall
    keep an index of all such resolutions. The filing of such resolution constitutes
    constructive notice thereof. Significantly, R.C. 307.73 provides that “[n]o nonparticipant
    shall be required to pay the prorated share of the cost of such improvement permitted
    by resolution without such notice.”
    {¶26} Further, pursuant to R.C. 3701.34, the Ohio Department of Health is given
    the authority to establish sanitary sewer regulations of general application throughout
    the state.     Pursuant to this authority, the health department established a policy
    requiring the elimination of individual septic systems and connection to a sanitary
    sewerage system when such a system becomes accessible. Ohio Adm. Code 3701-29-
    02 provides:
    {¶27} (L) No household sewage disposal system shall be installed,
    maintained, or operated on property accessible to a sanitary
    sewerage system.
    {¶28} (M) Whenever a sanitary sewerage system becomes accessible to
    the property, a household sewage disposal system shall be
    abandoned and the house sewer directly connected to the
    sewerage system.
    {¶29} The Supreme Court of Ohio upheld the constitutionality of Ohio Adm.
    Code 3701-29-02 in DeMoise v. Dowell, 
    10 Ohio St.3d 92
     (1984). In DeMoise, the
    Court held that local health boards possess “the authority to require that whenever a
    sanitary sewerage system becomes accessible to a property, the household sewage
    disposal system shall be abandoned and the house sewer directly connected to the
    sewerage system.” 
    Id.
     at syllabus. The Court held the connection “requirement bears a
    8
    real and substantial relationship to the public health, is not unreasonable or arbitrary,
    and does not constitute a deprivation of due process of law.” 
    Id.
    {¶30} While the Ohio Supreme Court found Ohio Adm. Code 3701-29-02
    (requiring connection to an accessible public sewer) to be constitutional in DeMoise, the
    Court did not address the constitutionality of R.C. 307.73 (providing for private sewer
    construction agreements) in that case.
    {¶31} “It is well settled that an enactment of the General Assembly is entitled to
    a strong presumption of constitutionality.” State v. Cowan, 
    103 Ohio St.3d 144
    , 2004-
    Ohio-4777, ¶7. “Therefore, challenged legislation will not be invalidated unless the
    challenger establishes the unconstitutional nature of the statute beyond a reasonable
    doubt.” Cowan, supra.
    {¶32} There are two different ways of challenging a statute on constitutional
    grounds: 1) by arguing that it is unconstitutional on its face, or 2) by arguing that it is
    unconstitutional as applied to a particular set of facts. Cleveland Gear Co. v. Limbach,
    
    35 Ohio St.3d 229
    , 231 (1988). “An as applied challenge asserts that a statute is
    unconstitutional as applied to the challenger’s particular conduct.” Kruppa v. Warren,
    11th Dist. Trumbull No. 2009-T-0017, 
    2009-Ohio-4927
    , ¶12. In contrast, a facial
    challenge asserts the statute is unconstitutional in “all of its applications.” 
    Id.
    {¶33} The Supreme Court of Ohio in State v. Mateo, 
    57 Ohio St.3d 50
    , 52
    (1991), discussed the requirements of procedural due process, as follows:
    {¶34} The United States Supreme Court has stated that the essence of
    due process is notice and an opportunity to be heard: “For more
    than a century the central meaning of procedural due process has
    been clear: ‘Parties whose rights are to be affected are entitled to
    be heard; and in order that they may enjoy that right they must first
    be notified.’ * * * [Citations omitted.] It is equally fundamental that
    the right to notice and an opportunity to be heard ‘must be granted
    9
    at a meaningful time and in a meaningful manner.’ (Emphasis
    added.) Armstrong v. Manzo, 
    380 U.S. 545
    , 552 [1965].” Fuentes
    v. Shevin, 
    407 U.S. 67
    , 80 (1972). See also Mathews v. Eldridge,
    
    424 U.S. 319
    , 333 (1976). “As a general rule, due process requires
    that the government give notice and an opportunity to be heard
    before taking an individual’s liberty or property.” (Emphasis sic.)
    United States v. 141st Street Corp., 
    911 F.2d 870
    , 874 (2d
    Cir.1990). * * * “Due process of law involves only the essential
    rights of notice, hearing or opportunity to be heard before a
    competent tribunal. * * *” State v. Luff, 
    117 Ohio St. 102
     (1927),
    paragraph four of the syllabus. See also State v. Edwards, 
    157 Ohio St. 175
    , 178 (1952), paragraph one of the syllabus.
    {¶35} The trial court, in addition to finding that R.C. 307.73 is facially
    unconstitutional, expressly found, at p. 11 of its judgment entry, that “R.C. 307.73, as
    applied under the facts of the Sablecreek Plaintiffs [i.e., appellees], is unconstitutional[.]”
    (Emphasis added.) Further, appellant does not challenge on appeal the trial court’s
    finding that R.C. 307.73 is facially unconstitutional.
    {¶36} Since appellant appeals only the trial court’s as-applied finding and does
    not appeal the court’s facial finding, the trial court’s conclusion that the statute is
    unconstitutional on its face stands. As such, the statute is unconstitutional in all of its
    applications, Kruppa, supra, including its application to appellees.
    {¶37} Because appellant did not appeal the trial court’s finding that R.C. 307.73
    is unconstitutional on its face, there is nothing for us to consider and we therefore
    uphold this finding. In any event, the trial court’s record fully supports this finding. The
    trial court demonstrated in its judgment the lack of procedural due process in R.C.
    307.73 by way of a chart. That graphic contrasted the lack of due process in R.C.
    307.73 with the multiple layers of due process in R.C. Chapter 6117, which sets forth an
    alternative method for constructing sewers by the county commissioners.                 Under
    Chapter 6117, the commissioners are authorized to construct sewers and to assess the
    10
    costs against the affected property owners.       The trial court noted that under R.C.
    6117.06, the sanitary engineer is required to prepare plans and cost estimates in a
    “tentative assessment” for “the information of property owners” prior to any levy. Notice
    must be mailed to all affected property owners prior to adoption of the resolution. The
    statute provides for objections to the project in general, the tentative assessment, and
    the physical boundaries. A hearing must then be held on any objections after notice to
    all affected property owners of the hearing, which includes details of the project.      A
    property owner can file objections up to five days after the hearing.          Under R.C.
    6117.09, a property owner can also appeal to the Probate Court.
    {¶38} In contrast to R.C. Chapter 6117, the trial court noted on its graphic that
    under R.C. 307.73, the filing of the commissioners’ resolution adopting a private sewer
    construction agreement with the county auditor constitutes constructive notice to
    affected property owners, but there is no time requirement as to when the resolution
    must be filed.   Further, pursuant to this statute, affected property owners are only
    entitled to notice of the resolution itself; the statute does not require that the total or
    even the estimated cost of the project be included in the notice. R.C. 307.73 does not
    require any oversight of the private contractor’s costs. Property owners are not entitled
    to review any costs and there is no provision for objections. There is no provision for
    any affected property owner to be heard or for any judicial review of the decision of the
    Sanitary Engineer’s Office regarding the amount abutting property owners must pay in
    order to reimburse the individual/private entity that constructed the sewer.
    {¶39} Thus, the trial court’s comparison demonstrates that R.C. 6117, et seq.,
    provides due process protections for affected property owners, while R.C. 307.73 is
    devoid of due process.
    11
    {¶40} The trial court found there are no circumstances in which the statute can
    provide procedural due process protections.        The court found there is no way to
    challenge appellant’s unreasonable charges as there are no meaningful due process
    rights built into R.C. 307.73 The court stated, “[T]he landowner in Trumbull County is
    getting nailed with unfounded and unreasonable charges because R.C. 307.73 simply
    does not provide the protection necessary to contest these matters. Additionally, the
    constructive notice requirement of R.C. 307.73 does not provide the landowner with
    sufficient information in a timely manner to know the actual costs to challenge any
    unreasonable costs that are charged.” The court stated: “R.C. 307.73, by providing no
    safeguards or even minimal due process, leaves innocent landowners with no choice
    but to tap in and pay whatever costs are charged or be criminally prosecuted by the
    Board of Health.” In addition, the trial court found “the lack of judicial oversight” is “a
    continuation of the affront to the right of due process present in R.C. 307.73.”
    {¶41} The trial court noted the total lack of procedural due process is best
    summed up by Jay Walton of the Trumbull County Sanitary Engineer’s Office. When
    asked as to how the taxpayers are to be “protected from a contractor who * * *
    overcharges in a case like this,” Walton answered, “Jeez. I don’t know what to say. I
    guess there is no protection.”
    {¶42} While the trial court’s facial finding includes the finding that R.C. 307.73 is
    unconstitutional as applied to appellees, the record supports such finding. Although
    R.C. 307.73 provides that the filing of the resolution with the county auditor constitutes
    constructive notice, here, the resolution was not filed by appellant with the county
    auditor until 17 months after completion of the sewer project.         Although appellant
    correctly argues that R.C. 307.73 does not provide an express time limit by which an
    12
    applicant must file a copy of the commissioners’ resolution, in order for the resolution to
    constitute constructive notice, it must pre-date the work for which the resolution is
    providing notice. Mateo, supra. Because appellant did not file the resolution until 17
    months after completion of the project, it was too late for appellees to effectively
    challenge the project or its costs. Thus, the “constructive notice” provided to appellees
    pursuant to R.C. 307.73 was not meaningful and did not satisfy procedural due process.
    {¶43} Moreover, R.C. 307.73 does not require that any reference to the cost of
    the project be included in the resolution, and appellees were not given any advance
    notice regarding the cost of the project, not even the original estimated cost of the
    project.   However, without such notice, appellees could not possibly have known
    whether there was any need for them to object to the project or to the costs submitted
    by appellant.
    {¶44} Appellant argues that because appellees, Michael Hanysh and Joanne
    Hanysh, bought their property in August 2004 (four months after appellant filed the
    commissioners’ resolution), the Hanyshes had constructive notice of the project.
    However, this argument misses the point. As successors in interest to the prior owners,
    the Hanyshes had the right to assert appellant’s failure to provide notice and an
    opportunity to be heard to their predecessors.
    {¶45} Next, appellant argues that even if appellees did not have constructive
    notice pursuant to R.C. 307.73, they had actual notice of the project because the sewer
    extension project would have required construction equipment to be near appellees’
    properties. In Edgar v. Hines, 
    35 Ohio App.3d 23
     (12th Dist.1987), the Twelfth District
    held that, “[a]lthough R.C. 307.73 provides that constructive notice, as set forth in the
    statute, is a prerequisite to obtaining reimbursement for private construction of a sewer
    13
    line, actual notice to the concerned property owners is also sufficient.” 
    Id.
     at paragraph
    three of the syllabus.      In Edgar, supra, the appellate court held that if the property
    owner had actual notice of the cost of construction of the sewer, constructive notice is
    not necessary. Id. at 25.
    {¶46} Appellant argues that because appellees were in a position to see this
    installation, they had actual notice of the project and, thus, constructive notice was not
    necessary.    However, the magistrate rejected this argument, finding that, although
    appellees had actual notice of the installation of the sewer extension near their homes,
    they did not have actual notice as to the required tie-in or the cost associated therewith.
    The magistrate also found that the newspaper articles referenced by appellant as
    evidence of actual notice merely addressed the residents’ objections to the general
    concept of sewer tie-in requirements and that these articles were not evidence that
    appellees had actual notice of the cost of the project.
    {¶47} Significantly, appellant concedes that any knowledge appellees acquired
    took place after the commissioners’ resolution approving the sewer extension was
    adopted and after construction of the project had already begun. There is no evidence
    in this record that, before the project was approved by the commissioners and
    construction had begun, appellees knew (1) of the sewer extension agreement between
    the commissioners and appellant, (2) the commissioners’ resolution approving that
    agreement, (3) the cost of the project, or (4) appellees’ pro rata share of the costs.
    Thus, the presence of construction equipment did not provide actual notice of the cost
    of the project.
    {¶48} Further, the magistrate found that the lack of procedural due process in
    R.C. 307.73 prevented appellees from being able to assert legitimate challenges to
    14
    unreasonable costs submitted by appellant for reimbursement. From the original cost
    statement submitted by appellant in the amount of $103,460, Walton determined that
    several of the cost items (totaling $29,281) were obviously improper and subtracted
    them, including a $10,573 charge for unsubstantiated “miscellaneous” items; $15,975 in
    interest charged by appellant’s engineering firm, Ady & Sons, due to appellant’s failure
    to timely pay that firm’s bills on the project; and $2,555 for charges that were
    attributable to appellant’s own home.       Further, the magistrate found the fact that
    appellant sought reimbursement for such obviously improper charges made the other
    charges in his bill all the more suspect.
    {¶49} The magistrate also found that many other costs were improper and
    unreasonable and should have been – but were not - subtracted by Walton from the
    $74,179 final approved cost of the project. These included an unexplained $12,000
    charge for rock excavation; $6,960 in attorney fees (which appellant was ordered to pay
    a non-party who successfully sued appellant in an unrelated action for trespass on his
    property); $2,985 (which was assessed against appellant personally in that trespass
    action for his failure to comply with the settlement agreement requiring appellant to
    repair the damage he caused to the plaintiff’s property); and $7,500 in attorney fees
    (which appellant’s own attorney charged him for defending him in that trespass action).
    The court found it was improper and unreasonable for appellant to pass these cost
    items on to the taxpayers and for the Sanitary Engineer’s Office to approve these costs
    without appropriate review and oversight. In addition, the magistrate found the invoice
    submitted by appellant’s construction firm in the amount of $46,759, which was nearly
    double their original proposal with no legitimate substantiation, was unreasonable. The
    magistrate found that Walton essentially approved any cost submitted by appellant’s
    15
    construction firm without requiring any documentation to show the cost was reasonable
    or necessary.
    {¶50} The trial court was appalled at the near complete lack of oversight by the
    Sanitary Engineer’s Office through its agent, Walton, of appellant’s statement of costs.
    Walton admitted he approved obviously suspect cost items without requiring any
    substantiation or explanation.    He even approved costs that were unrelated to the
    project and costs that were caused by appellant’s improper conduct. Incredibly, Walton
    said he still planned to charge the taxpayers several substantial cost items submitted by
    appellant even after Walton acknowledged they were improper and wrong.
    {¶51} To make matters worse, although the sewer extension agreement
    required appellant to provide a “certified notarized cost statement” within 90 days of
    completion of the project, he never certified the accuracy of his cost statement. After
    the project was completed, Walton wrote two letters to appellant in May and June 2003,
    demanding the certification. Walton told appellant that without the certification, the
    sewer extension agreement would become void and he would lose his right to any
    reimbursement. Despite these demands and warnings, appellant never provided the
    required certification.   Even more incredible, Walton said he ultimately decided to
    overlook this omission and to simply pass the charges on to the taxpayers without the
    certification.
    {¶52} We therefore uphold the trial court’s finding that R.C. 307.73 is
    unconstitutional on its face. Since appellant did not appeal that finding, his argument
    that the trial court erred in finding R.C. 307.73 unconstitutional as applied lacks merit.
    {¶53} Appellant’s third, fourth, fifth, and sixth assignments of error are overruled.
    16
    {¶54} Appellant’s first and second assigned errors are related and thus
    considered together. They allege:
    {¶55} “[1.] The Trial Court’s Order that Appellees have the right to tap into the
    Sablecreek Sanitary Sewer Line at no cost is an unconstitutional taking.
    {¶56} “[2.] The Appropriate Remedy to be awarded Appellees is that the
    Sablecreek Sanitary Sewer Lines Are Not Available and that Appellees Are Not
    Required to Tap into the Sanitary Sewer Lines.”
    {¶57} The Ohio Constitution states that “private property shall ever be held
    inviolate, but subservient to the public welfare. * * * Where private property shall be
    taken for public use, a compensation therefore shall first be made in money * * * and
    such compensation shall be assessed by a jury * * *.” State ex rel. OTR v. City of
    Columbus, 
    76 Ohio St.3d 203
    , 206 (1996), quoting Section 19, Article I, Ohio
    Constitution. A taking occurs when a landowner experiences a substantial or
    unreasonable interference with property. OTR, supra. That interference may involve an
    actual physical taking of real property or it may include the deprivation of an intangible
    interest in the premises. Id.
    {¶58} Appellant argues the trial court’s judgment interfered with his property right
    to reimbursement in the sewer extension agreement, resulting in a taking. In support,
    he cites Stop The Beach Renourishment v. Florida Dept. of Environmental Protection,
    
    560 U.S. 702
     (2010). However, his reliance on this case is misplaced. In Stop the
    Beach, the Supreme Court stated, “The takings clause only protects property rights as
    they are established under state law * * *.” Stop The Beach at 732. Appellant’s claimed
    property right to reimbursement is based on a statute that violates procedural due
    17
    process.    Because R.C. 307.73 is unconstitutional, appellant’s taking claim fails
    because it is not based on a valid state law.
    {¶59} In any event, even if R.C. 307.73 was constitutional, it provides that
    property owners who tap into the sewer line are not required to pay the prorated share
    of the cost of the project if the applicant fails to provide constructive notice of the
    project. Thus, constructive notice is a prerequisite to reimbursement. Edgar, supra, at
    paragraph three of the syllabus. Since appellant did not file the commissioners’ 2001
    resolution until April 2004, 17 months after the project was completed, appellant failed
    to give the affected property owners constructive notice at a meaningful time and he is
    not entitled to reimbursement.
    {¶60} Further, appellant argues that, to avoid a taking, the trial court should have
    declared the sewer extension to be unavailable and, this way, appellees would have
    been allowed to disconnect from the sewer. However, the remedy appellant seeks
    would have required the trial court to find that the sewer line is not physically available
    to appellees when, in fact, it is. Moreover, appellant’s proposed remedy would violate
    Ohio Adm. Code 3701-29-02, which requires that when a sanitary sewerage system
    becomes accessible to the property, the house must abandon the household sewage
    system and be connected to the sanitary sewerage system.            Moreover, appellant’s
    proposed remedy would impliedly overrule the Ohio Supreme Court’s decision in
    DeMoise, supra. As noted above, the Ohio Supreme Court in that case held that when
    a public sewer system is available to a property owner, he must abandon his personal
    sewer system and connect to the public system. There is no dispute in this record that
    construction of the sewer extension made it available to appellees and thus appellees
    are legally bound to tie into it. However, as a result of the due process violations
    18
    discussed herein, the trial court did not abuse its discretion in adopting the magistrate’s
    decision that appellees were entitled to tie into the sewer system at no cost.
    {¶61} Appellant’s first and second assignments of error are overruled.
    {¶62} For the reasons stated in this opinion, the assignments of error lack merit
    and are overruled. It is the order and judgment of this court that the judgment of the
    Trumbull County Court of Common Pleas is affirmed.
    DIANE V. GRENDELL, J.,
    COLLEEN MARY O’TOOLE, J.,
    concur.
    19