N. Park Retirement Community Ctr., Inc. v. Sovran Cos., Ltd. , 2011 Ohio 5179 ( 2011 )


Menu:
  • [Cite as N. Park Retirement Community Ctr., Inc. v. Sovran Cos., Ltd. , 
    2011-Ohio-5179
    .]
    Court of Appeals of Ohio
    EIGHTH APPELLATE DISTRICT
    COUNTY OF CUYAHOGA
    JOURNAL ENTRY AND OPINION
    No. 96376
    NORTH PARK RETIREMENT
    COMMUNITY CENTER, INC., ET AL.
    PLAINTIFFS-APPELLANTS
    vs.
    SOVRAN COMPANIES LTD.,
    ET AL.
    DEFENDANTS-APPELLEES
    JUDGMENT:
    AFFIRMED
    Civil Appeal from the
    Cuyahoga County Court of Common Pleas
    Case No. CV-736025
    BEFORE: Stewart, P.J., Cooney, J., and Rocco, J.
    RELEASED AND JOURNALIZED:                 October 6, 2011
    ATTORNEYS FOR APPELLANTS
    Timothy N. Toma
    Shannon M. McCormick
    Toma & Associates, L.P.A., Inc.
    33977 Chardon Road, Suite 100
    Willoughby Hills, OH 44094
    ATTORNEYS FOR APPELLEES
    John J. McHugh
    Brian C. Kalas
    Sarah A. Miller
    McHugh & McCarthy, Ltd.
    5580 Monroe Street
    Sylvania, OH 43560
    MELODY J. STEWART, P.J.:
    {¶ 1} Plaintiffs-appellants, North Park Retirement Community Center, Inc., J&R
    Health Associates, Inc., and John and Kimberly Coury (we shall refer to them collectively
    as “North Park” unless otherwise noted), appeal from an order that stayed proceedings
    and referred to arbitration a breach of contract complaint against defendants-appellees,
    Sovran Companies, Ltd. and William Sheehan. North Park argues that the court erred by
    finding its dispute with Sovran to be arbitrable because the dispute between the parties
    was unrelated to a prior agreement that contained an arbitration clause.
    I
    {¶ 2} As a preliminary matter, the parties both note that this court has issued
    conflicting opinions on the standard of review we employ when reviewing cases to
    determine whether the parties have agreed to arbitrate a dispute. In one line of cases, we
    have employed the de novo standard of review; while in another line of cases, we have
    employed the abuse of discretion standard of review.      Compare Shumaker v. Saks Inc.,
    
    163 Ohio App.3d 173
    , 
    2005-Ohio-4391
    , 
    837 N.E.2d 393
     (de novo review) with Sikes v.
    Ganley Pontiac Honda (Sept. 13, 2001), 8th Dist. No. 79015 (abuse of discretion review).
    Rather than resolve this conflict, panels of this court have decided to review the issue
    under both standards. See, e.g., GB AZ 1, L.L.C. v. Arizona Motors, L.L.C., 8th Dist. No.
    95502, 
    2011-Ohio-1808
    , ¶8; Bentley v. Cleveland Browns Football Co., L.L.C., 8th Dist.
    No. 95921, 
    2011-Ohio-3390
    , ¶13. This is an unacceptable course of action given that an
    appellate court is charged with stating the applicable law.
    {¶ 3} These cases do not conflict in the sense that they disagree on the correct
    standard of review; rather they involve different issues and therefore use different
    standards of review. For example, in Sikes, the issue was whether the court erred by
    staying the matter pending arbitration, so the panel applied the abuse of discretion
    standard to determine whether the stay was properly granted. Other cases raise issues in
    the context of the referral to arbitration, which is in essence a review of the contract to
    determine whether the dispute is contractually covered by an agreement to arbitrate, thus
    requiring the de novo standard of review applied to contract construction. See, e.g.,
    Vanyo v. Clear Channel Worldwide, 
    156 Ohio App.3d 706
    , 
    2004-Ohio-1793
    , 
    808 N.E.2d 482
    , ¶8. (“The issue of whether a controversy is arbitrable under the provisions of a
    written contract is a question of law for the trial court to decide.”)
    {¶ 4} The core issue in any dispute regarding the arbitrability of a matter is
    whether the parties agreed to arbitration. Arbitration is a creature of contract, see United
    Steelworkers v. Warrior & Gulf Navigation Co. (1960), 
    363 U.S. 574
    , 582, 
    80 S.Ct. 1347
    ,
    
    4 L.Ed.2d 1409
    , so we are guided by “the principle that a party can be forced to arbitrate
    only those issues it specifically has agreed to submit to arbitration[.]” First Options of
    Chicago, Inc. v. Kaplan (1995), 
    514 U.S. 938
    , 945, 
    115 S.Ct. 1920
    , 
    131 L.Ed.2d 985
    .
    This requires an examination of the agreement to arbitrate, which has always been
    considered a review as a “matter of law;” in other words, a de novo review.             See
    Alexander v. Buckeye Pipe Line Co. (1978), 
    53 Ohio St.2d 241
    , 
    374 N.E.2d 146
    ,
    paragraph one of the syllabus. If a court determines that the parties have agreed to
    arbitrate a dispute, it must refer the matter to arbitration. See R.C. 2711.03(A) (“upon
    being satisfied that the making of the agreement for arbitration or the failure to comply
    with the agreement is not in issue, the court shall make an order directing the parties to
    proceed to arbitration in accordance with the agreement”).
    {¶ 5} Once a court determines that the parties have agreed to arbitrate a dispute
    and has ordered the parties to proceed to arbitration, staying the action pending the
    outcome of arbitration is required. While courts typically have discretion to grant or
    deny general requests for stays, see State ex rel. Verhovec v. Mascio (1998), 
    81 Ohio St.3d 334
    , 336, 
    691 N.E.2d 282
    , R.C. 2711.02(B) removes this discretion in arbitration
    cases. That section states that the court, “upon being satisfied that the issue involved in
    the action is referable to arbitration under an agreement in writing for arbitration, shall on
    application of one of the parties stay the trial of the action until the arbitration of the issue
    has been had in accordance with the agreement, provided the applicant for the stay is not
    in default in proceeding with arbitration.” (Emphasis added.) The use of the word
    “shall” means that the court has no discretion and must comply with the statute. See
    State ex rel. Law Office Pub. Defender v. Rosencrans, 
    111 Ohio St.3d 338
    ,
    
    2006-Ohio-5793
    , 
    856 N.E.2d 250
    , ¶31 (the word “shall” establishes a mandatory duty
    while the word “should” requires the use of discretion and judgment).
    {¶ 6} R.C. 2711.02(A) is consistent with the Federal Arbitration Act, Section 3,
    Title 9, U.S.Code, which likewise states that the federal courts have no discretion to deny
    a stay if the issues raised are within the agreement to arbitrate. See Hornbeck Offshore
    Corp. v. Coastal Carriers Corp. (C.A.5, 1993), 
    981 F.2d 752
    , 754; United States v.
    Bankers Ins. Co. (C.A.4, 2001), 
    245 F.3d 315
    , 319.
    {¶ 7} That the court has no discretion to refuse to stay a matter that it has
    determined is subject to arbitration is logical.         Arbitration is ultimately a private
    agreement to avoid the courts — so if the parties have agreed to arbitrate a dispute, the
    court’s refusal to stay proceedings would in essence force the parties to submit to court
    proceedings to which they had agreed to avoid. It follows that appellate courts must
    review questions of arbitrability under the de novo standard of review applied to
    contracts. The abuse of discretion standard of review has no application in the context of
    the court deciding to stay proceedings pending the outcome of arbitration because a stay
    in such circumstances is mandatory, not discretionary.
    II
    {¶ 8} The substantive issue raised by North Park is whether the court erred by
    finding that it and Sovran agreed to arbitrate the present dispute.
    A
    {¶ 9} North Park operates a retirement and assisted living facility. In 2007, it
    sought to refinance its debt obligation with National City Bank, so it entered into a
    consulting agreement with Sovran, through Sovran’s principal Sheehan, in which Sovran
    would obtain the necessary financing in exchange for a fee. The consulting agreement
    contained an arbitration clause that stated:
    {¶ 10} “Any controversy arising out of this agreement, or out of the refusal by
    either party hereto to perform the whole or any part of this agreement that cannot be
    settled through negotiation, shall be settled by final and binding arbitration in accordance
    with the provisions of Chapter 2711 of the Ohio Revised Code.”
    {¶ 11} In 2009, Sovran notified North Park that it had secured funding in the form
    of a “sale/leaseback” in the amount of $4 million. It forwarded to North Park a letter
    agreement stating the terms of the funding, identified the assets being purchased, the
    terms of the lease, and other matters not related to this dispute. North Park paid Sovran a
    $40,000 underwriting fee for its work. North Park alleged that Sovran never obtained
    the funding and then refused to return the underwriting fee, prompting North Park to file
    this breach of contract action.
    B
    {¶ 12} North Park first argues that the current dispute between the parties was
    governed by the 2009 letter agreement detailing funding, not the 2007 consulting
    agreement.
    {¶ 13} In AT&T Technologies, Inc. v. Communications Workers of Am. (1986), 
    475 U.S. 643
    , 
    106 S.Ct. 1415
    , 
    89 L.Ed.2d 648
    , the Supreme Court described four basic
    principles that courts should use to determine whether a disputed issue is subject to
    arbitration: (1) arbitration is a matter of contract and a party cannot be required to
    submit to arbitration any dispute that he has not agreed to submit; (2) the question of
    arbitrability is an issue for judicial determination; (3) in deciding whether the parties have
    agreed to submit a particular grievance to arbitration, a court is not to rule on the potential
    merits of the underlying claims and must submit the matter if it arguably appears to be
    encompassed by the language in the written instrument, even if the claim itself appears
    frivolous; and (4) there is a presumption of arbitrability in the sense that an order to
    arbitrate the particular grievance should not be denied unless it may be said with positive
    assurance that the arbitration clause is not susceptible of an interpretation that covers the
    asserted dispute. 
    Id.,
     
    475 U.S. at 648-650
    , 
    106 S.Ct. 1415
     (internal quotations and
    citations omitted).
    {¶ 14} North Park’s complaint alleges that Sovran “failed to obtain the
    $4,000,000.00 for financing as required by the agreement, therefore failing to fulfill the
    requirements of the sale/leaseback agreement.” While this breach of contract action is
    grounded on a violation of the 2009 letter agreement for financing, it is plain that North
    Park’s claim also implicates the 2007 consulting agreement that required Sovran to
    “arrang[e] appropriate financing.” North Park’s claim certainly invokes the arbitration
    clause of the 2007 consulting agreement that encompasses “any controversy” arising out
    of Sovran’s failure to perform “the whole or any part” of the agreement to arrange
    financing. This is so because Sovran’s obligation to North Park was to arrange financing
    in accordance with the 2007 consulting agreement. It can be argued that the 2009 letter
    agreement was the fruit of the 2007 consulting agreement and that Sovran was at all
    events bound by its obligation to provide financing.           At the very least, the two
    agreements were sufficiently related to each other to fall within the very wide ambit of the
    arbitration provision.   Because we cannot say with positive assurance that Sovran’s
    failure to obtain financing is not encompassed within the arbitration clause of the 2007
    consulting agreement, we find that the court did not err by referring the matter to
    arbitration.
    {¶ 15} For the same reasons, we reject North Park’s argument that the court’s
    decision to refer the matter to arbitration compels it to arbitrate that which it did not agree
    to arbitrate because the 2009 letter agreement did not contain an arbitration clause. The
    claim that Sovran breached the 2009 letter agreement by failing to provide financing
    bears a sufficient nexus to its obligation to obtain financing in accordance with the terms
    of the 2007 consulting agreement.
    C
    {¶ 16} North Park next claims that it is not bound by the arbitration agreement in
    the 2007 consulting agreement because that contract was signed by different parties from
    those who signed the 2009 letter agreement. The 2007 consulting agreement was signed
    by John P. Coury on behalf of Sovereign Health and North Park Retirement Community
    Center, Inc., and also signed by John Coury individually. The 2009 letter agreement was
    signed by John Coury individually and by Kimberly Coury in her individual capacity and
    on behalf of J&R Healthcare Associates, Sovereign Healthcare Services, and North Park
    Care Center. North Park argues that John Coury was the only signatory of the 2009 letter
    agreement to sign the 2007 consulting agreement, so neither Kimberly Coury nor J&R
    Healthcare were bound by it.
    {¶ 17} Because agreements to arbitrate are matters of contract, a person who was
    not   a   party   to   an   arbitration   agreement   cannot   be   forced   to   arbitrate.
    Cleveland-Akron-Canton Advertising Coop. v. Physician’s Weight Loss Ctrs. of Am., Inc.,
    
    184 Ohio App.3d 805
    , 
    2009-Ohio-5699
    , 
    922 N.E.2d 1012
    , ¶14. Nonetheless, in some
    circumstances non-signatories to contracts can be contractually bound by ordinary
    contract and agency principles. Short v. Resource Title Agency, Inc., 8th Dist. No.
    95839, 
    2011-Ohio-1577
    , at ¶14.
    {¶ 18} The 2007 consulting agreement was signed by John Coury as a
    representative of North Park and Sovereign Healthcare. The arbitration provision of that
    agreement made it binding on “the heirs, executors, administrators, legal representatives,
    successors, and assigns of the respective parties.” Kimberly Coury signed the 2009 letter
    agreement both individually and on behalf of North Park Care Center, Sovereign
    Healthcare Services, and J&R Healthcare.             The amended complaint states that J&R
    Health Associates, Inc. 1 does business as “Sovereign Healthcare.” By signing in her
    corporate capacity, Kimberly Coury is a “representative” of those companies as
    contemplated by the arbitration provision of the 2007 consulting agreement.
    {¶ 19} Moreover, an affidavit submitted by Sheehan states that Sovran “was
    introduced to Sovereign Healthcare as the ‘family entity for several retirement
    communities in Northeast Ohio operated by the John Coury, Jr. family.’” Sovereign is the
    registered trade name of J&R Healthcare as alleged in the amended complaint. This fact
    is supported by evidence showing that Kimberly Coury filed the application for the
    Sovereign trade name with the secretary of state on a form that listed her as J&R
    Healthcare’s “authorized representative.” We thus find the record gives every indication
    that these companies and individuals are so affiliated and otherwise intertwined that the
    For reasons that are unexplained, the amended complaint is styled “J&R Health Associates,
    1
    Inc.,” the 2009 letter agreement refers to “J and R Health Associates, Inc.” and is signed by Kimberly
    Coury on behalf of “J&R Healthcare Associates, Inc.” Appellant’s brief refers to “J&R Healthcare
    Associates.” Neither party claims that there is a material difference among the names, so we refer to
    the entity as “J&R Healthcare” as expressed in the briefs.
    court did not err as a matter of law by making J&R Healthcare and Kimberly Coury
    parties to the arbitration.
    III
    {¶ 20} North Park next claims that the court erred by referring the matter to
    arbitration when Sovran only sought to stay the proceedings. We summarily reject this
    argument. While it is true that Sovran filed a “motion to stay,” that motion not only
    sought a stay, but asked the court “to refer any such disputes to final and binding
    arbitration in accordance with the provisions of Chapter 2711 of the Ohio Revised Code.”
    This sufficiently requested that the action not only be stayed, but that the court refer it to
    arbitration.
    IV
    {¶ 21} Finally, North Park argues that the court erred by referring the matter to
    arbitration without first conducting an evidentiary hearing.
    {¶ 22} R.C. 2711.03(B) states that upon receiving a request to refer a matter to
    arbitration, the court “shall hear” the parties and refer the matter upon being satisfied the
    making of the agreement to arbitrate or the failure to comply with arbitration is in issue.
    We have held that the R.C. 2711.03(B) mandate for a hearing does not necessarily require
    a full evidentiary hearing on the issues if the issues are sufficiently briefed for
    presentation to the court. See Panzica Constr. Co. v. Zaremba, Inc., 8th Dist. No. 95103,
    
    2011-Ohio-620
    , ¶37.
    {¶ 23} The court granted North Park’s request for a hearing and scheduled a date
    for that hearing, but the record does not indicate that a hearing went forward as
    scheduled. Sovran maintains that the parties met with the court on the day scheduled for
    a hearing and “engaged in a meaningful confrontation” with the court that lasted for
    several hours, with each side given an opportunity to present their respective positions of
    the issues. North Park does not dispute Sovran’s claim that the parties met with the
    court, but continues to insist that it was entitled to a full evidentiary hearing.
    {¶ 24} Regardless of whether the parties met with the court, we find that the issues
    were sufficiently fleshed out by the parties’ submissions to the court that the matter could
    be heard on briefs without the need of a full evidentiary hearing. North Park makes no
    argument that it had evidence to present to the court that it could not present in briefing,
    nor does it maintain that it wished to raise new arguments in addition to those previously
    presented to the court. Of course, if the parties did meet with the court, albeit informally
    in chambers as suggested by Sovran, that fact reinforces our conclusion that North Park
    was given a full and fair opportunity to present its case for denying Sovran’s motion to
    refer the matter to arbitration. With no error remotely manifest, we find that the court
    did not err by failing to hold a full evidentiary hearing on the motion to refer the case to
    arbitration.
    Judgment affirmed.
    It is ordered that appellees recover of appellants their costs herein taxed.
    The court finds there were reasonable grounds for this appeal.
    It is ordered that a special mandate issue out of this court directing the Cuyahoga
    County Court of Common Pleas to carry this judgment into execution.
    A certified copy of this entry shall constitute the mandate pursuant to Rule 27 of
    the Rules of Appellate Procedure.
    MELODY J. STEWART, PRESIDING JUDGE
    KENNETH A. ROCCO, J., CONCURS;
    COLLEEN CONWAY COONEY, J., CONCURS
    IN JUDGMENT ONLY