Ohio Fabricators, Inc. v. Aster Elements, Inc. , 2019 Ohio 3978 ( 2019 )


Menu:
  • [Cite as Ohio Fabricators, Inc. v. Aster Elements, Inc., 2019-Ohio-3978.]
    STATE OF OHIO                     )                         IN THE COURT OF APPEALS
    )ss:                      NINTH JUDICIAL DISTRICT
    COUNTY OF SUMMIT                  )
    OHIO FABRICATORS, INC.                                      C.A. No.        28934
    28911
    Appellant
    v.                                                  APPEAL FROM JUDGMENT
    ENTERED IN THE
    ASTER ELEMENTS, INC., et al.                                COURT OF COMMON PLEAS
    COUNTY OF SUMMIT, OHIO
    Appellees                                           CASE No.   CV-2016-04-1896
    DECISION AND JOURNAL ENTRY
    Dated: September 30, 2019
    TEODOSIO, Presiding Judge.
    {¶1}     Ohio Fabricators, Inc. (“Ohio Fabricators”) appeals the order of the Summit
    County Court of Common Pleas granting summary judgment in favor of Aster Elements, Inc.
    (“Aster”) and Travelers Casualty & Surety Company of America (“Travelers”). We reverse and
    remand.
    I.
    {¶2}     In October 2013, Ohio Fabricators entered into a subcontract agreement with
    Aster for the installation of exterior panels on a construction project for Cincinnati Children’s
    Hospital. The hierarchy of contractors began with the general contractor, Messer Construction,
    which hired the exterior general contractor, Pioneer Cladding and Glazing (“Pioneer”), which
    hired Aster as an exterior subcontractor. Aster subsequently hired Ohio Fabricators. Travelers
    issued a payment bond and a performance bond for Aster’s scope of the project, with Pioneer as
    the obligee and Aster as the principal.
    2
    {¶3}     In 2016, Ohio Fabricators commenced an action against Aster and Travelers,
    alleging multiple claims for breach of contract, detrimental reliance, and unjust enrichment.
    Both Aster and Travelers asserted several counterclaims against Ohio Fabricators. In November
    2017, upon motions for summary judgment filed by all parties, the trial court granted summary
    judgment in favor of Aster and Travelers on all five counts of Ohio Fabricators’ amended
    complaint; denied Ohio Fabricators’ motion for summary judgment as to Aster’s amended
    counterclaim and as to counts one and two of Travelers’ amended counterclaim; and granted
    summary judgment in favor of Ohio Fabricators on the third count of Travelers’ amended
    counterclaim.
    {¶4}     Ohio Fabricators’ now appeals, raising six assignments of error, which we have
    reordered for the purposes of our analysis.
    II.
    {¶5}     Appellate review of an award of summary judgment is de novo. Grafton v. Ohio
    Edison Co., 
    77 Ohio St. 3d 102
    , 105 (1996). Summary judgment is appropriate under Civ.R. 56
    when: (1) no genuine issue as to any material fact remains to be litigated; (2) the moving party is
    entitled to judgment as a matter of law; and (3) viewing the evidence most strongly in favor of
    the nonmoving party, reasonable minds can come to but one conclusion and that conclusion is
    adverse to the nonmoving party. Temple v. Wean United, Inc., 
    50 Ohio St. 2d 317
    , 327 (1977),
    citing Civ.R. 56(C). A court must view the facts in the light most favorable to the non-moving
    party and must resolve any doubt in favor of the non-moving party. Murphy v. Reynoldsburg, 
    65 Ohio St. 3d 356
    , 358–359 (1992). A trial court does not have the liberty to choose among
    reasonable inferences in the context of summary judgment, and all competing inferences and
    3
    questions of credibility must be resolved in the nonmoving party’s favor. Perez v. Scripps–
    Howard Broadcasting Co., 
    35 Ohio St. 3d 215
    , 218 (1988).
    {¶6}    The Supreme Court of Ohio has set forth the nature of this burden-shifting
    paradigm:
    [A] party seeking summary judgment, on the ground that the nonmoving party
    cannot prove its case, bears the initial burden of informing the trial court of the
    basis for the motion, and identifying those portions of the record that demonstrate
    the absence of a genuine issue of material fact on the essential element(s) of the
    nonmoving party’s claims. The moving party cannot discharge its initial burden
    under Civ.R. 56 simply by making a conclusory assertion that the nonmoving
    party has no evidence to prove its case. Rather, the moving party must be able to
    specifically point to some evidence of the type listed in Civ.R. 56(C) which
    affirmatively demonstrates that the nonmoving party has no evidence to support
    the nonmoving party’s claims. If the moving party fails to satisfy its initial
    burden, the motion for summary judgment must be denied. However, if the
    moving party has satisfied its initial burden, the nonmoving party then has a
    reciprocal burden outlined in Civ.R. 56(E) to set forth specific facts showing that
    there is a genuine issue for trial and, if the nonmovant does not so respond,
    summary judgment, if appropriate, shall be entered against the nonmoving party.
    Dresher v. Burt, 
    75 Ohio St. 3d 280
    , 293 (1996).
    ASSIGNMENT OF ERROR TWO
    THE TRIAL COURT ERRED IN FINDING A PAY-IF-PAID CLAUSE
    APPLIED[.]
    {¶7}    In its second assignment of error, Ohio Fabricators argues the trial court erred in
    finding that a pay-if-paid clause was applicable to the project. We agree.
    {¶8}    In granting summary judgment on the amended complaint in favor of Aster and
    Travelers, the trial court found that because final payment had not been made to Aster, Aster was
    under no obligation to pay Ohio Fabricators for any outstanding payments because of the
    application of a pay-if-paid provision in the subcontract.
    {¶9}    Generally, there are two types of contractual provisions that establish the manner
    of payment from a general contractor to a subcontractor: pay-when-paid and pay-if-paid.
    4
    Transtar Elec., Inc. v. A.E.M. Elec. Servs. Corp., 
    140 Ohio St. 3d 193
    , 2014-Ohio-3095, ¶ 10. A
    pay-when-paid provision is an unconditional promise to pay the subcontractor that is not
    dependent upon the owner’s nonpayment.          
    Id. Alternatively, a
    pay-if-paid provision is a
    conditional promise to pay the subcontractor that is enforceable only if a condition precedent,
    such as the payment by the owner to the general contractor, occurs. 
    Id. at ¶
    11. Such a provision
    requires the general contractor to pay the subcontractor only if the general contractor is paid by
    the owner, therefore transferring the risk of nonpayment to the subcontractor. 
    Id. {¶10} In
    finding that a pay-if-paid clause was dispositive of Ohio Fabricators’ claims,
    the trial court relied upon Article 8.1.3 as contained in the General Conditions of the
    Subcontract, which provides:
    It is specifically understood and agreed that payment to the Subcontractor
    including any retention shall be made only after receipt of payment by Aster
    Elements, Inc. from the Owner, and such payment by Owner to Aster Elements,
    Inc. is a condition precedent to Aster Elements, Inc.’s obligation to pay the
    Subcontractor.
    Ohio Fabricators argue that the trial court erred in finding the pay-if-paid clause was applicable
    because it improperly interpreted the language of the provision in determining that it applied to
    Pioneer’s nonpayment of funds to Aster.
    {¶11} “When confronted with an issue of contract interpretation, our role is to give
    effect to the intent of the parties. We will examine the contract as a whole and presume that the
    intent of the parties is reflected in the language of the contract.” Sunoco, Inc. (R & M) v. Toledo
    Edison Co., 
    129 Ohio St. 3d 397
    , 2011–Ohio–2720, ¶ 37. “In addition, we will look to the plain
    and ordinary meaning of the language used in the contract unless another meaning is clearly
    apparent from the contents of the agreement. When the language of a written contract is clear, a
    court may look no further than the writing itself to find the intent of the parties.” 
    Id. “Only when
                                                     5
    the language of a contract is unclear or ambiguous, or when the circumstances surrounding the
    agreement invest the language of the contract with a special meaning will extrinsic evidence be
    considered in an effort to give effect to the parties’ intentions.” Shifrin v. Forest City Ents., 
    64 Ohio St. 3d 635
    (1992), syllabus. The determination of whether a contract is ambiguous is a
    question of law that this Court reviews de novo. Salter v. Salter, 9th Dist. Summit No. 26440,
    2013–Ohio–559, ¶ 6, citing Hahn v. Hahn, 9th Dist. Medina No. 11CA0064–M, 2012–Ohio–
    2001, ¶ 9. See also Denman v. State Farm Ins. Co., 9th Dist. Lorain No. 05CA008744, 2006–
    Ohio–1308, ¶ 12.
    {¶12} The trial court is given great latitude in determining the meaning of ambiguous
    terms, including the intent of the parties and the equities involved. In re Dissolution of Marriage
    of Seders, 
    42 Ohio App. 3d 155
    , 156 (9th Dist.1987). However, the trial court must remain true
    to the guiding principle of contract interpretation: “[I]f the contract terms are clear and precise,
    the contract is not ambiguous and the trial court is not permitted to refer to any evidence outside
    of the contract itself, including the purported intentions of the parties.” Ryan v. Ryan, 9th Dist.
    Summit No. 19347, 
    1999 WL 980572
    , *1 (Oct. 27, 1999); see also Lawler v. Burt, 
    7 Ohio St. 340
    , 350-351 (1857). “Common words appearing in a written instrument will be given their
    ordinary meaning unless manifest absurdity results, or unless some other meaning is clearly
    evidenced from the face or overall contents of the instrument.” Alexander v. Buckeye Pipe Line
    Co., 
    53 Ohio St. 2d 241
    (1978), paragraph two of the syllabus.              Thus, if a contract is
    unambiguous, the language of the contract controls and “[i]ntentions not expressed in the writing
    are deemed to have no existence and may not be shown by parol evidence.” Aultman Hosp. Assn.
    v. Community Mut. Ins. Co., 
    46 Ohio St. 3d 51
    , 53 (1989).
    6
    {¶13} On the other hand, “[e]xtrinsic evidence is admissible to ascertain the intent of the
    parties when the contract is unclear or ambiguous, or when circumstances surrounding the
    agreement give the plain language special meaning.” Graham v. Drydock Coal Co., 76 Ohio
    St.3d 311, 313-314 (1996). Ambiguity refers to “the condition of admitting of two or more
    meanings, of being understood in more than one way, or of referring to two or more things at the
    same time[.]” Robinson v. Beck, 9th Dist. Summit No. 21094, 2003–Ohio–1286, ¶ 25, quoting
    Boulger v. Evans, 
    54 Ohio St. 2d 371
    , 378 (1978). Only if the terms of a contract may reasonably
    be understood in more than one sense can they be construed as ambiguous. Preferred Tax &
    Fin. Servs., Inc. v. Mark W. Boslett, Inc., CPA, 9th Dist. Summit No. 22801, 2006–Ohio–2690, ¶
    14.
    {¶14} In its judgment entry, the trial court stated that “[w]hether the subcontract
    contained the word “Owner,” as it does, or “Pioneer,” as Ohio [Fabricators] argues would be
    necessary, the contract language was not ambiguous and was fully understood by the signers.”
    Although the trial court concluded the language was not ambiguous, it improperly looked to
    extrinsic evidence to determine the intentions of the parties. Furthermore, despite stating the
    language was unambiguous, the trial court’s interpretation of the provision necessarily indicated
    it arrived at a definition of “Owner” outside of the plain and ordinary meaning of the word.
    {¶15} The payment provision at issue provides that “[i]t is specifically understood and
    agreed that * * * payment by Owner to Aster Elements, Inc. is a condition precedent to Aster
    Elements, Inc.’s obligation to pay the Subcontractor.” In reviewing the subcontract, we conclude
    the term “Owner” is a common word to be given its ordinary meaning. It is not disputed that the
    owner of the property at the heart of this matter is Cincinnati Children’s Hospital. The term is
    used numerous times throughout the subcontract and there is nothing in its usage to suggest
    7
    another meaning, nor may the term be reasonably understood to have another meaning. We
    therefore conclude the language of the provision is unambiguous, and we look no further to
    determine the intent of the parties. As a result, there is no pay-if-paid provision in Article 8.1.3
    requiring payment by Pioneer to Aster as a condition precedent to Aster’s obligation to pay Ohio
    Fabricators.
    {¶16} While we acknowledge that Ohio Fabricators contends that Aster was not in
    privity with or paid by Cincinnati Children’s Hospital, we make no further determination of the
    applicability of the clause as to Cincinnati Children’s Hospital as that issue is not before us for
    review.
    {¶17} Ohio Fabricators’ second assignment of error is sustained.
    ASSIGNMENT OF ERROR FOUR
    THE TRIAL COURT ERRED IN GRANTING SUMMARY JUDGMENT TO
    THE BONDING COMPANY[.]
    {¶18} In its fourth assignment of error, Ohio Fabricators argues that the trial court erred
    in granting summary judgment in favor of Travelers. We agree.
    {¶19} In granting summary judgment, the trial court determined: “The evidence is
    undisputed that final payment has not been made to Aster, and Aster is under no obligation to
    pay Ohio [Fabricators] if in fact there are outstanding payments to be made. Therefore, as to
    Counts I and II of Ohio [Fabricators’] amended complaint, the court finds summary judgment in
    favor of Aster and Travelers to be appropriate and hereby grants the same.” The second count of
    the complaint alleged that Travelers had breached its obligation to pay Ohio Fabricators under
    the issued payment bonds.
    {¶20} The trial court provided no further analysis, as its decision to grant summary
    judgment in favor of Travelers hinged upon its determination of the applicability of the pay-if-
    8
    paid clause. As we have concluded that the pay-if-paid clause is inapplicable, we likewise
    sustain Ohio Fabricators’ fourth assignment of error.
    ASSIGNMENT OF ERROR FIVE
    THE TRIAL COURT ERRED IN DENYING PLAINTIFF’S MOTION FOR
    SUMMARY JUDGMENT[.]
    {¶21} In its fifth assignment of error, Ohio Fabricators argues the trial court erred in
    denying its motion for summary judgment.
    {¶22} The trial court granted summary judgment in favor of Aster and Travelers as to
    the claims of Ohio Fabricators. The trial court denied Ohio Fabricators’ motion for summary
    judgment as to Aster’s amended counterclaim and as to counts one and two of Travelers’
    amended counterclaim. In its subsequent order, the trial court revised its judgment to include
    Civ.R. 54(B) language stating “there is no just reason for delay.” The trial court stated that the
    addition of the language “render[ed] that order disposing of the plaintiff’s claims final and
    appealable as to those claims.” Appropriately, it makes no mention of the denial of summary
    judgment on the counterclaims being likewise rendered final and appealable.
    {¶23} When more than one claim for relief is presented in an action or when multiple
    parties are involved, the trial court may enter final judgment as to one or more but fewer than all
    of the claims or parties only upon an express determination that there is no just reason for delay
    pursuant to Civ.R. 54(B), however such a finding of no just reason for delay does not make
    appealable an otherwise non-appealable order. Rosenbaum v. Chronicle Telegram, 9th Dist.
    Lorain Nos. 01CA0079896 and 01CA007908, 2002-Ohio-7319, ¶ 12, citing Chef Italiano Corp.
    v. Kent State Univ., 
    44 Ohio St. 3d 86
    , 88 (1989).
    {¶24} Article IV, Section 3(B)(2), of the Ohio Constitution limits this Court’s appellate
    jurisdiction to the review of final judgments of lower courts. For a judgment to be final and
    9
    appealable, it must satisfy the requirements of R.C. 2505.02 and, if applicable, Civ.R. 54(B).
    Chef Italiano at 88. The denial of a motion for summary judgment does not determine the action
    and prevent a judgment, and thus generally does not constitute a final appealable order under
    R.C. 2505.02. Celebrezze v. Netzley, 
    51 Ohio St. 3d 89
    , 90 (1990). A trial court’s Civ.R. 54(B)
    certification cannot make a non-final order appealable, because the requirements of both R.C.
    2505.02 and Civ.R. 54(B) must be satisfied to permit appellate review. Noble v. Colwell, 
    44 Ohio St. 3d 92
    , 96 (1989).
    {¶25} The trial court certified only the disposition of Ohio Fabricators’ claims as being
    final and appealable pursuant to Civ.R. 54(B), it did not likewise certify the remaining
    counterclaims. Moreover, the trial court’s finding that there was no just reason for delay did not
    make appealable other portions of the order that were otherwise non-appealable.               See
    MacFarland v. Niekamp, Weisensell, Mutersbaugh & Mastrantonio, LLP, 9th Dist. Summit No.
    28462, 2017-Ohio-8394, ¶ 35. Accordingly, those aspects of the trial court’s order that denied
    motions for summary judgment are not final or appealable.
    {¶26} Ohio Fabricators’ fifth assignment of error is therefore overruled.
    ASSIGNMENT OF ERROR ONE
    THE TRIAL COURT ERRED IN FINDING THAT A CONTRACTOR WAS
    THE OWNER[.]
    ASSIGNMENT OF ERROR THREE
    THE TRIAL COURT ERRED IN GRANTING SUMMARY JUDGMENT IN
    FAVOR OF THE DEFENDANTS[.]
    ASSIGNMENT OF ERROR SIX
    THE TRIAL COURT ERRED IN DENYING PLAINTIFF’S MOTION TO
    VACATE[.]
    10
    {¶27} In its first assignment of error, Ohio Fabricators argues that the trial court erred in
    finding Pioneer to be the “Owner.” In its third assignment of error, Ohio Fabricators argues the
    trial court erred in granting summary judgment in favor of the defendants because there were a
    series of disputed issues of material fact. In its sixth assignment of error, Ohio Fabricators
    argues the trial court erred in denying its motion to vacate under Civ.R. 60(B).
    {¶28} We decline to reach the merits of these arguments as our resolution of Ohio
    Fabricators’ second assignment of error has rendered them moot. See App.R. 12(A)(1)(c).
    III.
    {¶29} Ohio Fabricators’ second and fourth assignments of error are sustained. The fifth
    assignment of error is overruled. The first, third, and sixth assignments of error have been
    rendered moot. The judgment of the Summit County Court of Common Pleas is reversed and
    remanded for further proceedings consistent with this opinion.
    Judgment reversed
    and remanded.
    There were reasonable grounds for this appeal.
    We order that a special mandate issue out of this Court, directing the Court of Common
    Pleas, County of Summit, State of Ohio, to carry this judgment into execution. A certified copy
    of this journal entry shall constitute the mandate, pursuant to App.R. 27.
    Immediately upon the filing hereof, this document shall constitute the journal entry of
    judgment, and it shall be file stamped by the Clerk of the Court of Appeals at which time the
    period for review shall begin to run. App.R. 22(C). The Clerk of the Court of Appeals is
    11
    instructed to mail a notice of entry of this judgment to the parties and to make a notation of the
    mailing in the docket, pursuant to App.R. 30.
    Costs taxed to Appellees.
    THOMAS A. TEODOSIO
    FOR THE COURT
    HENSAL, J.
    CALLAHAN, J.
    CONCUR.
    APPEARANCES:
    MICHAEL R. STAVNICKY, Attorney at Law, for Appellant.
    TIMOTHY FITZGERALD, Attorney at Law, for Appellee.
    ALAN TORRANCE, Attorney at Law, for Appellee.
    

Document Info

Docket Number: 28934, 28911

Citation Numbers: 2019 Ohio 3978

Judges: Teodosio

Filed Date: 9/30/2019

Precedential Status: Precedential

Modified Date: 10/9/2019