Ohio Plumbing, Ltd. v. Fiorilli Constr., Inc. , 111 N.E.3d 763 ( 2018 )


Menu:
  • [Cite as Ohio Plumbing, Ltd. v. Fiorilli Constr., Inc., 
    2018-Ohio-1748
    .]
    Court of Appeals of Ohio
    EIGHTH APPELLATE DISTRICT
    COUNTY OF CUYAHOGA
    JOURNAL ENTRY AND OPINION
    No. 106242
    OHIO PLUMBING, LTD.
    PLAINTIFF-APPELLEE
    vs.
    FIORILLI CONSTRUCTION, INC.
    DEFENDANT-APPELLANT
    JUDGMENT:
    REVERSED; REMANDED
    Civil Appeal from the
    Cuyahoga County Court of Common Pleas
    Case No. CV-17-880991
    BEFORE: E.A. Gallagher, A.J., Stewart, J., and Celebrezze, J.
    RELEASED AND JOURNALIZED:                        May 3, 2018
    ATTORNEYS FOR APPELLANT
    Brian T. Winchester
    Patrick J. Gump
    McNeal, Schick, Archibald & Biro Co., L.P.A.
    123 West Prospect Avenue, Suite 250
    Cleveland, Ohio 44115
    ATTORNEY FOR APPELLEE
    David J. Horvath
    7100 E. Pleasant Valley Road, Suite 110
    Independence, Ohio 44131
    EILEEN A. GALLAGHER, A.J.:
    {¶1} Defendant-appellant Fiorilli Construction, Inc. (“Fiorilli”) appeals from the trial
    court’s decision denying its motion to stay pending arbitration. For the reasons that follow, we
    reverse the trial court.
    Factual and Procedural Background
    {¶2} In September 2016, Fiorilli, the contractor, contracted with plaintiff-appellee Ohio
    Plumbing, Ltd. (“Ohio Plumbing”), the subcontractor, to provide plumbing services in
    connection with the construction of a SteinMart discount department store in Bainbridge, Ohio
    (the “contract” or the “agreement”). The contract contains a dispute resolution provision, which
    sets forth a multistage dispute resolution process, including discussions between project
    managers, discussions between party executives, premediation and mediation.                       After
    non-binding dispute resolution attempts are concluded, “any dispute not resolved” is to be
    decided “by either arbitration or litigation * * * at Fiorilli Construction, Inc.’s sole discretion.”
    {¶3} Section 8.04(3) provides in relevant part:
    Binding Dispute Resolution: Upon the full conclusion of all good faith direct
    discussions, pre-mediation, and mediation attempts to resolve a dispute, any
    dispute not resolved shall be decided by either arbitration or litigation. Upon a
    failed mediation, the Subcontractor hereby expressly waives any and all rights to
    institute or pursue litigation, unless at the sole discretion of Fiorilli Construction,
    Inc., litigation is expressly determined in writing as the course of action for further
    dispute resolution proceedings.            Both Fiorilli Construction, Inc. and
    Subcontractor understand and agree that any such decision as to whether to have
    disputes decided by arbitration or litigation is at Fiorilli Construction, Inc.’s sole
    discretion and is a condition precedent to any legal or equitable proceedings being
    initiated under this Agreement.
    {¶4} On May 30, 2017, Ohio Plumbing filed a complaint against Fiorilli in the Cuyahoga
    County Court of Common Pleas, asserting claims of breach of contract and violation of the Ohio
    Prompt Payment Act, R.C. 4113.61, based on Fiorilli’s alleged failure to pay Ohio Plumbing for
    work performed under the agreement. Ohio Plumbing alleged that it had fully performed under
    the agreement, that it had obtained a final inspection approval of its work under the agreement
    and that Fiorilli had confirmed that Ohio Plumbing had completed its work and was due money
    under the agreement but that Fiorilli refused to pay Ohio Plumbing.       Ohio Plumbing sought to
    recover $5,337 it claimed it was due under the agreement, 18% interest per annum from the date
    Fiorilli received payment from the owner and attorney fees. Ohio Plumbing attached a copy of
    the agreement to its complaint.
    {¶5} On July 26, 2017, Fiorilli filed a motion for change of venue, attorney fees,
    dismissal and/or stay of proceedings pursuant to Civ.R. 3(C), Civ.R. 12(B) and R.C. 2711.02.
    Fiorilli claimed that venue was improper in Cuyahoga County because the agreement included a
    forum selection provision that stated that any litigation relating to the contract would be filed in
    Medina County, Ohio.     Fiorilli requested that the court transfer the case to the Medina County
    Court of Common Pleas and that it be awarded its attorney fees under Civ.R. 3(C)(2). It also
    requested that Ohio Plumbing’s complaint be dismissed or the action stayed under R.C.
    2711.02(B) pending arbitration of the parties’ dispute.
    {¶6} Ohio Plumbing opposed the motion. It argued that there was “nothing to arbitrate”
    under the agreement because — based on the allegations of its complaint — there was no
    “dispute” and the only issue to be litigated was “whether or not [Fiorilli] has paid [Ohio
    Plumbing] pursuant to the invoices that were submitted and approved by [Fiorilli].”                   Ohio
    Plumbing also argued the agreement was unconscionable and that the forum selection and
    dispute resolution provisions were, therefore, unenforceable.
    {¶7} On August 17, 2017, the trial court summarily denied Fiorilli’s motion.                Fiorilli
    appealed, raising the following assignment of error for review:
    The trial court erred in not enforcing a valid and irrevocable arbitration clause
    encompassed in a commercial contract between two commercial entities.1
    Law and Analysis
    {¶8} In its sole assignment of error, Fiorilli argues that the trial court erred in denying its
    motion to stay pending arbitration because the parties had a valid arbitration agreement and Ohio
    Plumbing’s claims were within the scope of the arbitration provision.           Ohio Plumbing responds
    that the trial court properly denied Fiorilli’s motion to stay because (1) Ohio Plumbing’s claims
    involve a payment issue that is not “suitable for arbitration”; (2) Fiorilli had not served a demand
    for arbitration or otherwise initiated arbitration proceedings prior to filing its motion to stay and
    (3) the arbitration clause is “so one-sided, draconian, and confusing,” it is unconscionable and
    unenforceable.
    Standard of Review
    1
    At this juncture, only the trial court’s denial of Fiorilli’s motion to stay pending arbitration is
    subject to appellate review, not the denial of its motion to dismiss or for change of venue. See R.C.
    2711.02(D); Helbling v. Lloyd Ward, P.C., 8th Dist. Cuyahoga No. 99991, 
    2014-Ohio-1513
    , ¶ 15-19
    (order denying motion to transfer venue was not a final, appealable order subject to immediate
    appeal).
    {¶9} The standard of review applicable to a trial court’s ruling on a motion to stay
    pending arbitration “depends upon ‘the type of questions raised challenging the applicability of
    the arbitration provision.’”   Wisniewski v. Marek Builders, Inc., 
    2017-Ohio-1035
    , 
    87 N.E.3d 696
    , ¶ 5 (8th Dist.), quoting Kaminsky v. New Horizons Computer Learning Ctr. of Cleveland,
    
    2016-Ohio-1468
    , 
    62 N.E.3d 1054
    , ¶ 12 (8th Dist.). Determinations as to whether a party has
    agreed to submit an issue to arbitration and whether an arbitration provision is unconscionable
    are reviewed de novo. McCaskey v. Sanford-Brown College, 8th Dist. Cuyahoga No. 97261,
    
    2012-Ohio-1543
    , ¶ 7-8. Under a de novo standard of review, we give no deference to the trial
    court’s decision.   Brownlee v. Cleveland Clinic Found., 8th Dist. Cuyahoga No. 97707,
    
    2012-Ohio-2212
    , ¶ 9.
    {¶10} An abuse of discretion standard applies to a determination that a party has waived
    its right to arbitrate a given dispute.   McCaskey at ¶ 7, citing Milling Away, L.L.C. v. UGP
    Properties, L.L.C., 8th Dist. Cuyahoga No. 95751, 
    2011-Ohio-1103
    , ¶ 8.               An abuse of
    discretion occurs where the trial court’s decision is unreasonable, arbitrary or unconscionable.
    Blakemore v. Blakemore, 
    5 Ohio St.3d 217
    , 219, 
    450 N.E.2d 1140
     (1983).
    {¶11} Ohio recognizes a “strong public policy” in favor of arbitration and the
    enforcement of arbitration provisions.       Hayes v. Oakridge Home, 
    122 Ohio St.3d 63
    ,
    
    2009-Ohio-2054
    , 
    908 N.E.2d 408
    , ¶ 15; Taylor Bldg. Corp. of Am. v. Benfield, 
    117 Ohio St.3d 352
    , 
    2008-Ohio-938
    , 
    884 N.E.2d 12
    , ¶ 24; R.C. 2711.01(A).                A presumption favoring
    arbitration arises when the claim in dispute falls within the scope of the arbitration provision and
    courts must resolve any doubts in favor of arbitrability. See, e.g., Williams v. Aetna Fin. Co., 
    83 Ohio St.3d 464
    , 471, 
    700 N.E.2d 859
     (1998); Taylor Bldg. at ¶ 26; see also Council of Smaller
    Ents. v. Gates, McDonald & Co., 
    80 Ohio St.3d 661
    , 669, 
    687 N.E.2d 1352
     (1998) (arbitration
    provision should not be denied effect “‘unless it may be said with positive assurance that the
    arbitration clause is not susceptible of an interpretation that covers the asserted dispute’”),
    quoting Independence Bank v. Erin Mechanical, 
    49 Ohio App.3d 17
    , 18, 
    550 N.E.2d 198
     (8th
    Dist.1988).
    {¶12} R.C. 2711.02(B) provides:
    If any action is brought upon any issue referable to arbitration under an agreement
    in writing for arbitration, the court in which the action is pending, upon being
    satisfied that the issue involved in the action is referable to arbitration under an
    agreement in writing for arbitration, shall on application of one of the parties stay
    the trial of the action until the arbitration of the issue has been had in accordance
    with the agreement, provided the applicant for the stay is not in default in
    proceeding with arbitration.
    {¶13} Thus, R.C. 2711.02 requires a court to stay the trial of an action on application of
    one of the parties if (1) the action involves an issue referable to arbitration under a written
    arbitration agreement, (2) the court is satisfied the issue is referable to arbitration under the
    agreement and (3) the party seeking the stay is not in default in proceeding with arbitration.
    Eaton Corp. v. Allstate Ins. Co., 8th Dist. Cuyahoga No. 101654, 
    2015-Ohio-2034
    , ¶ 17.
    Arbitrability of Ohio Plumbing’s Claims
    {¶14} In this case, it is undisputed that the parties’ agreement contains a dispute
    resolution provision and that the dispute resolution provision includes an agreement to arbitrate,
    at Fiorilli’s discretion, “disputes under the Agreement.” Nevertheless, Ohio Plumbing contends
    that the claims raised in its complaint are not arbitrable because they involve only a single,
    “simple issue to be reconciled” — i.e., “payment for services rendered” — that is not “suitable
    for arbitration.”
    {¶15} Despite the presumption in favor of arbitration, a party cannot be compelled to
    arbitrate a dispute the party has not agreed to submit to arbitration. Council of Smaller Ents., 80
    Ohio St.3d at 665, 
    687 N.E.2d 1352
    . In deciding whether a dispute falls within the scope of an
    arbitration agreement, “‘[a] proper method of analysis * * * is to ask if an action could be
    maintained without reference to the contract or relationship at issue. If it could, it is likely outside
    the scope of the arbitration agreement.’” Alexander v. Wells Fargo Fin. Ohio 1, Inc., 
    122 Ohio St.3d 341
    , 
    2009-Ohio-2962
    , 
    911 N.E.2d 286
    , ¶ 24, quoting Fazio v. Lehman Bros., Inc., 
    340 F.3d 386
    , 395 (6th Cir.2003); see also Park Bldg. Condominium Assn. v. Howells & Howells
    Ents., L.L.C., 
    2017-Ohio-1561
    , 
    90 N.E.3d 131
    , ¶ 16 (8th Dist.).
    {¶16} In this case, the arbitration clause is broad, applying to any “disputes under the
    Agreement.” Ohio Plumbing’s claims for breach of contract and violation of the Ohio Prompt
    Payment Act are based on the services Ohio Plumbing provided under the agreement and could
    not be maintained “‘without reference to the contract or relationship at issue.’” Alexander at ¶
    24, quoting Fazio at 395. Ohio Plumbing’s right to the $5,337 it seeks to recover in this action
    arises out of the agreement.     Simply because Ohio Plumbing has alleged in its complaint that
    “[d]efendant agrees it owes this money,” does not mean, as Ohio Plumbing contends, that there is
    “nothing to arbitrate.” Fiorilli’s failure to pay Ohio Plumbing the sums it claims are due is a
    “dispute”     Because Ohio Plumbing’s claims involve a “dispute under the [a]greement,” they
    are within the scope of the arbitration provision.2
    Whether any conditions precedent to arbitration have been satisfied or waived is a matter for
    2
    the arbitrator. See, e.g., Council of Smaller Ents. at 665 (“‘Once it is determined * * * that the
    parties are obligated to submit the subject matter of a dispute to arbitration, “procedural” questions
    Default in Proceeding with Arbitration
    {¶17} Ohio Plumbing also contends that its claims are not referable to arbitration under
    R.C. 2711.02(B) because Fiorilli did not serve Ohio Plumbing with a formal demand for
    arbitration or initiate arbitration proceedings prior to filing its motion to stay and, therefore, is “in
    default in proceeding with arbitration” under R.C. 2711.02(B).
    {¶18} “Default” is “‘the omission or failure to perform a legal or contractual duty.’” PS
    Commercial Play, LLC v. Harp Contrs., Inc., 2d Dist. Montgomery No. 27253, 
    2017-Ohio-4011
    ,
    ¶ 17, quoting Black’s Law Dictionary 376 (5th Ed.1979). A party who waives its right to
    arbitrate is “in default in proceeding with arbitration.” M84 Lumber Co. v. O.C.H. Constr.,
    LLC, 
    2015-Ohio-4149
    , 
    44 N.E.3d 961
    , ¶ 16; see also Ponyicki v. Monterey Homes, 8th Dist.
    Cuyahoga No. 65549, 
    1994 Ohio App. LEXIS 2158
    , *10 (May 19, 1994), citng Mills v.
    Jaguar-Cleveland Motors, Inc., 
    69 Ohio App.2d 111
    , 113, 
    430 N.E.2d 965
     (8th Dist.1980). In
    order to waive the right to arbitrate, a party must know they have the right to arbitrate and act
    inconsistently with that right. See, e.g., M84 Lumber at ¶ 16; Am. Gen. Fin. v. Griffin, 8th Dist.
    Cuyahoga No. 99088, 
    2013-Ohio-2909
    , ¶ 17. For example, where a party does not promptly
    raise an arbitration provision before the trial court, the party may waive its right to arbitrate a
    dispute.   See, e.g., Cantie v. Hillside Plaza, 8th Dist. Cuyahoga No. 99850, 
    2014-Ohio-822
    , ¶
    11-16.
    {¶19} As this court explained in Capital One Bank (USA), N.A. v. Rotman, 8th Dist.
    Cuyahoga No. 96891, 
    2012-Ohio-480
    , there is no requirement under R.C. 2711.02(B) that a
    which grow out of the dispute and bear on its final disposition would be left to the arbitrator.’”),
    quoting John Wiley & Sons, Inc. v. Livingston, 
    376 U.S. 543
    , 556-557, 
    84 S.Ct. 909
    , 
    11 L.Ed.2d 898
    (1964); see also Bd. of Library Trustees v. Ozanne Constr. Co., 
    100 Ohio App.3d 26
    , 30, 
    651 N.E.2d 1356
     (8th Dist. 1995); Blanchard Valley Health Sys. v. Canterbury Holdings, Inc., 3d Dist. Hancock
    No. 5-12-08, 
    2012-Ohio-5134
    , ¶ 22-25.
    defendant must initiate arbitration proceedings before it can seek a stay of litigation pending
    arbitration:
    Nothing in [R.C. 2711.02(B)] imposes a requirement that a party must initiate
    arbitration before seeking a stay. * * * [T]he statute clearly reflects that a party
    need only file a motion to have the proceedings stayed when “the action is
    referable to arbitration under an agreement in writing for arbitration.” R.C.
    2711.02(B).
    * * * Case law instructs that where a matter is subject to arbitration, “[t]he burden
    is on the plaintiff to commence the arbitration action, and the parties are obliged
    to cooperate and respond in a timely manner.” Sexton v. Kidder, Peabody & Co.,
    Inc., 8th Dist. Cuyahoga No. 74833, 
    1999 Ohio App. LEXIS 3972
     (Aug. 24,
    1999). See also Kessinger v. SR83 Hotel Partners, LLC, 5th Dist. Ashland No.
    04-CA-83, 
    2005-Ohio-4110
    , ¶ 17; Johnson v. E. Bay Kia, Inc., S.D.Ala. No.
    08-00656-CG-B, 
    2009 U.S. Dist. LEXIS 30906
    , *1 (Apr. 2, 2009). Indeed, it
    would be nonsensical to require a defendant to commence arbitration of a claim
    against himself. Thus, where a defendant properly exercises a right to
    arbitration, it is incumbent upon the plaintiff to pursue its claims in arbitration
    once a stay of the action is granted.
    Id. at ¶ 8-9; see also Featherstone v. Merrill Lynch, Pierce, Fenner & Smith, Inc., 
    159 Ohio App.3d 27
    , 
    2004-Ohio-5953
    , 
    822 N.E.2d 841
    , ¶ 8 (9th Dist.) (“[A] party cannot be in default in
    proceeding with arbitration where it has no duty to commence arbitration. Only an aggrieved
    party may demand arbitration. It defies logic to insist that an uninjured party, who may or may
    not know that another party believes it has been wronged, must institute arbitration proceedings
    against that allegedly aggrieved party in order to preserve its right to arbitrate.”).
    {¶20} Additionally, there is no such requirement in the parties’ agreement.        Under the
    terms of the parties’ agreement, Ohio Plumbing waived its right to litigate any dispute unless
    Fiorilli agreed in writing to resolve the dispute by litigation.            Further, binding dispute
    resolution, be it litigation or arbitration, was to occur only after efforts at nonbinding dispute
    resolution failed.   There is nothing in the record to suggest that the parties participated in any of
    the “direct discussions, pre-mediation, and mediation attempts” that were to precede “binding
    dispute resolution” under the terms of the agreement.
    {¶21} In this case, it cannot be said that Fiorilli acted inconsistently with its right to
    arbitrate. Fiorilli’s “opportunity to either waive or invoke its right arbitration” occurred after
    Ohio Plumbing filed its complaint.    Harsco Corp. v. Crane Carrier Co., 
    122 Ohio App.3d 406
    ,
    412-413, 
    701 N.E.2d 1040
     (3d Dist.1997). To invoke its right to arbitration, Fiorilli needed to
    file a motion to stay the litigation until the parties’ dispute was arbitrated in accordance with the
    agreement. R.C. 2711.02(B).       That is precisely what Fiorilli did.   Prior to filing its answer,
    Fiorilli promptly filed a motion to stay the proceedings pending arbitration. Based on the record
    before us, there is no reasonable basis upon which the trial court could have determined that
    Fiorilli was in default in proceeding with arbitration at the time it filed its motion for stay
    pending arbitration.
    Unconscionability
    {¶22} Ohio Plumbing also contends that the arbitration provision is unconscionable and
    that the trial court, therefore, properly denied Fiorilli’s motion to stay pending arbitration,
    because the arbitration provision is unenforceable.
    {¶23} An arbitration provision is not enforceable if it is unconscionable. See, e.g.,
    Hedeen v. Autos Direct Online, Inc., 
    2014-Ohio-4200
    , 
    19 N.E.3d 957
    , ¶ 26 (8th Dist.) (“[A]n
    arbitration provision may be held unenforceable on grounds that exist at law or in equity for the
    revocation of any contract. * * * Unconscionability is such a reason.”), citing Hayes, 
    122 Ohio St.3d 63
    , 
    2009-Ohio-2054
    , 
    908 N.E.2d 408
    , at ¶ 15, 19; Handler v. Southerland Custom
    Builders, Inc., 8th Dist. Cuyahoga No. 86956, 
    2006-Ohio-4371
    , ¶ 11 (“An arbitration clause that
    is deemed unconscionable is unenforceable as a matter of law.”).            Whether an arbitration
    provision is unconscionable is a question of law.     Id. at ¶ 8; Ins. Co. of N. Am. v. Automatic
    Sprinkler Corp., 
    67 Ohio St.2d 91
    , 98, 
    423 N.E.2d 151
     (1981).
    {¶24}   Unconscionability     embodies     two    separate   concepts:   (1)   substantive
    unconscionability, i.e., unfair and unreasonable contract terms and (2) procedural
    unconscionability, i.e., an absence of meaningful choice on the part of one of the parties.
    Taylor Bldg., 
    117 Ohio St.3d 352
    , 
    2008-Ohio-938
    , 
    884 N.E.2d 12
    , at ¶ 33. The party asserting
    the unconscionability of a contract must prove that the agreement is both procedurally and
    substantively unconscionable. Hayes at ¶ 30 (“A party challenging an arbitration agreement
    must prove a quantum of both procedural and substantive unconscionability.”); Taylor Bldg. at ¶
    33; see also Murea v. Pulte Group, Inc., 8th Dist. Cuyahoga No. 100127, 
    2014-Ohio-398
    , ¶ 11
    (“[T]hese two concepts create a two-prong conjunctive test for unconscionability [that] * * * is
    not satisfied if one of the requirements is not met.”).   Ohio Plumbing has not met its burden in
    this case.
    {¶25} “Substantive unconscionability pertains to the contract itself, without any
    consideration of the individual contracting parties, and requires a determination of whether the
    contract terms are commercially reasonable in the context of the transaction involved.’”    Vasil
    v. Pulte Homes of Ohio, L.L.C., 8th Dist. Cuyahoga No. 102212, 
    2015-Ohio-2407
    , ¶ 17, quoting
    Wallace v. Ganley Auto Group, 8th Dist. Cuyahoga No. 95081, 
    2011-Ohio-2909
    , ¶ 21.
    Procedural unconscionability involves factors bearing on the relative bargaining position of the
    contracting parties, such as age, education, intelligence, business acumen and experience,
    bargaining power, who drafted the contract, whether the terms were explained to the weaker
    party and whether alterations in the printed terms were possible. See, e.g., Vasil at ¶ 17; Taylor
    Bldg. at ¶ 43; Hayes at ¶ 23. No single factor, in and of itself, determines whether a contract is
    procedurally unconscionable; the totality of the circumstances must be considered. Murea at ¶
    12, citing Hayes at ¶ 29-30. The “crucial question” is whether each party to the contract had a
    reasonable opportunity to understand the terms of the contract.   Lake Ridge Academy v. Carney,
    
    66 Ohio St.3d 376
    , 383, 
    613 N.E.2d 183
     (1993).
    {¶26} Ohio Plumbing asserts that the arbitration clause is substantively unconscionable
    because it requires Ohio Plumbing to “waive[] [its] rights to litigation” and is part of a
    “confusing,” “lengthy,” “costly” and “oppressive” multi-stage dispute resolution “labryinth” that
    has a “chilling effect” on small claims.      Ohio Plumbing also asserts that the arbitration
    provision is procedurally unconscionable because the agreement was an “adhesion contract,”
    there was an “utter lack of bargaining power or ability to negotiate” on its part and the contract
    was not subject to review by Ohio Plumbing’s counsel.
    {¶27} The potential cost or burden of arbitration, in and of itself, is not sufficient to
    render an arbitration provision commercially unreasonable or otherwise unenforceable. See,
    e.g., English v. Cornell Quality Tools, Co., 9th Dist. Summit No. 22578, 
    2005-Ohio-6983
    , ¶ 18;
    McCaskey, 
    2012-Ohio-1543
    , at ¶ 32, 34 (observing that unconscionability requires “specific and
    individualized evidence that arbitration costs were unduly burdensome to the party opposing
    [arbitration]” and that “[w]ithout some evidence that a party would be precluded from bringing a
    claim, the cost of arbitration, standing alone, is not a justifiable reason to find
    unconscionability”).   Likewise, inequality of bargaining power or that a contract is preprinted
    and the arbitration clause is a required term, without more, “fails to demonstrate the
    unconscionability of the arbitration clause.” Taylor Bldg. at ¶ 44-45.
    {¶28} This case involves a contract between two commercial parties.               Here, a
    commercial transaction took place in which Ohio Plumbing agreed to perform certain plumbing
    services as a subcontractor for Fiorilli on the SteinMart project. The cases upon which Ohio
    Plumbing relies in support of its claim that the arbitration provision is unenforceable on
    unconscionability grounds involve the enforcement of arbitration provisions against consumers
    who purchased needed goods or services from a commercial entity, see, e.g., Eagle v. Fred
    Martin Motor Co., 
    157 Ohio App.3d 150
    , 
    2004-Ohio-829
    , 
    809 N.E.2d 1161
     (9th Dist.), and
    Williams v. Aetna Fin. Co., 
    83 Ohio St.3d 464
    , 
    700 N.E.2d 859
     (1998), or employees asserting
    discrimination claims, see, e.g., Post v. ProCare Auto Serv. Solutions, 8th Dist. Cuyahoga No.
    87646, 
    2007-Ohio-2106
    . As such they are distinguishable.
    {¶29} There is no evidence in the record supporting Ohio Plumbing’s allegations of
    procedural unconscionability or regarding any other facts and circumstances relevant to the issue.
    Ohio Plumbing did not submit any evidence (by way of affidavit or otherwise) to support its
    allegations of unconscionability and did not request that the trial court conduct a hearing on the
    issue. The only evidence in the record is the agreement itself. Pursuant to the agreement, the
    total amount Ohio Plumbing was to receive for the work it performed under the agreement was
    $36,000, of which Ohio Plumbing contends $5,337 has not been paid. The provision at issue
    appears in section VIII of the agreement, which is titled in bold capital letters, “DISPUTE
    RESOLUTION.” Although the agreement appears to have been drafted by Fiorilli, each page of
    the agreement, including the pages setting forth the dispute resolution procedure, was initialed by
    a representative of Ohio Plumbing.         Accordingly, the dispute resolution procedure and
    arbitration provision could have hardly been a surprise to Ohio Plumbing. “Anyone entering
    into a commercial contract has the burden of assuring themselves of what they are taking part
    in.” English at ¶ 28.    Certainly, Ohio Plumbing could have sought legal advice before entering
    into the agreement with Fiorilli.
    {¶30} Because Ohio Plumbing did not offer any evidence of procedural unconscionability
    (or allege any specific facts that, if proven, could establish procedural unconscionability under
    the totality of the circumstances here), it “cannot establish both prongs of the conjunctive
    two-part unconscionability test” and the trial court could not have properly denied Fiorilli’s
    motion to stay pending arbitration on grounds of unconscionability.               See, e.g., Murea,
    
    2014-Ohio-398
    , ¶ 12-14.
    {¶31} Based on the record before us, the trial court erred in denying Fiorilli’s motion to
    stay proceedings pending arbitration. Fiorilli’s assignment of error is sustained. We reverse
    the trial court’s judgment and remand the case to the trial court with instructions to stay litigation
    pending arbitration.
    {¶32} Judgment reversed; remanded.
    It is ordered that appellant recover from appellee the costs herein taxed.
    The court finds there were reasonable grounds for this appeal.
    It is ordered that a special mandate issue out of this court directing the Cuyahoga County
    Court of Common Pleas to carry this judgment into execution.
    A certified copy of this entry shall constitute the mandate pursuant to
    Rule 27 of the Rules of Appellate Procedure.
    ____________________________________________________
    EILEEN A. GALLAGHER, ADMINISTRATIVE JUDGE
    MELODY J. STEWART, J., and
    FRANK D. CELEBREZZE, JR., J., CONCUR
    

Document Info

Docket Number: 106242

Citation Numbers: 2018 Ohio 1748, 111 N.E.3d 763

Judges: Gallagher

Filed Date: 5/3/2018

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (18)

robert-fazio-v-lehman-brothers-inc-lehman-brothers-holdings-inc-sg , 340 F.3d 386 ( 2003 )

Brownlee v. Cleveland Clinic Found. , 2012 Ohio 2212 ( 2012 )

PS Commercial Play, L.L.C. v. Harp Contrs., Inc. , 2017 Ohio 4011 ( 2017 )

Kaminsky v. New Horizons Computer Learning Ctr. of Cleveland , 2016 Ohio 1468 ( 2016 )

Helbling v. Ward , 2014 Ohio 1513 ( 2014 )

Cantie v. Hillside Plaza , 2014 Ohio 822 ( 2014 )

Murea v. Pulte Group, Inc. , 2014 Ohio 398 ( 2014 )

Am. Gen. Fin. v. Griffin , 2013 Ohio 2909 ( 2013 )

Caskey v. Sanford-Brown College , 2012 Ohio 1543 ( 2012 )

Capital One Bank (USA) N.A. v. Rotman , 2012 Ohio 480 ( 2012 )

Eagle v. Fred Martin Motor Co. , 157 Ohio App. 3d 150 ( 2004 )

Bd. of Library Trustees v. Ozanne Constr. , 100 Ohio App. 3d 26 ( 1995 )

Featherstone v. Merrill Lynch, Pierce , 159 Ohio App. 3d 27 ( 2004 )

Wisniewshi v. Marek Builders, Inc. , 2017 Ohio 1035 ( 2017 )

Wallace v. Ganley Auto Group , 2011 Ohio 2909 ( 2011 )

Blanchard Valley Health Sys. v. Canterbury Holdings, Inc. , 2012 Ohio 5134 ( 2012 )

Hedeen v. Autos Direct Online, Inc. , 2014 Ohio 4200 ( 2014 )

John Wiley & Sons, Inc. v. Livingston , 84 S. Ct. 909 ( 1964 )

View All Authorities »