Technical Constr. Specialties v. Cooper , 2011 Ohio 5252 ( 2011 )


Menu:
  • [Cite as Technical Constr. Specialties v. Cooper, 
    2011-Ohio-5252
    .]
    Court of Appeals of Ohio
    EIGHTH APPELLATE DISTRICT
    COUNTY OF CUYAHOGA
    JOURNAL ENTRY AND OPINION
    No. 96021
    TECHNICAL CONSTRUCTION SPECIALTIES
    PLAINTIFF-APPELLANT
    vs.
    STEVE C. COOPER, ET AL.
    DEFENDANTS-APPELLEES
    JUDGMENT:
    AFFIRMED
    Civil Appeal from the
    Cuyahoga County Common Pleas Court
    Case No. CV-676571
    BEFORE:           Blackmon, P.J., Stewart, J., and Boyle, J.
    RELEASED AND JOURNALIZED:                                      October 13, 2011
    ATTORNEY FOR APPELLANT
    Daniel M. Walpole
    411 Quaker Square
    120 E. Mill Street
    Akron, Ohio 44308
    ATTORNEYS FOR APPELLEES
    Michael J. Murray
    Steven D. Shafron
    Berkman, Gordon, Murray & Devan
    55 Public Square
    Suite 2200
    Cleveland, Ohio 44113-1949
    PATRICIA ANN BLACKMON, P.J.:
    {¶ 1} Appellant Technical Construction Specialties (“TCS”) appeals the jury’s
    verdict awarding $14,876.45 in damages in its favor, arguing the award is inadequate.
    TCS assigns the following errors for our review:
    “I. The verdict awarding $14,876.45 in damages to TCS was against
    the manifest weight of the evidence, and that portion of the verdict
    must be reversed.”
    “II. The trial court abused its discretion when it denied TCS’s motion
    for a new trial as to the amount of damages the jury awarded.”
    “III.   The trial court abused its discretion when it denied TCS’s
    motion for a judgment notwithstanding the verdict as to damages.”
    {¶ 2} Having reviewed the record and pertinent law, we affirm the award of
    damages. The apposite facts follow.
    Facts
    {¶ 3} In   August     2004,    Entertainment    USA,   d.b.a.   Christie’s   Cabaret,
    (“Entertainment”) decided to renovate its nightclub located in Cleveland’s flats.
    {¶ 4} The new design eliminated the support beams inside the club, requiring the
    building to be supported by exterior pillars. Entertainment retained Summit Testing
    (“Summit”) to analyze the soil around the club and sought bids from various vendors to
    install the exterior supports.
    {¶ 5} On September 14, 2004, Entertainment’s president, Steve Cooper, signed a
    contract with Technical Construction Specialties, Inc., d.b.a. Atlas Piers N.E.O. (“TCS”)
    to install 45 helical piers to the depth of at least 45 feet below the existing grade. The
    agreed total cost for the work was $56,783.
    {¶ 6} Work began on Monday, November 8, 2004. After installing the first pier,
    TCS realized there was a problem because the pier went in at a depth of 86 feet, almost
    twice the depth that was projected. The president of TCS, Edward Sheeler, informed
    TCS’s project manager, David Rogers, of the problem. It was decided that TCS would
    install two more piers to form a triangular pattern to determine whether the depth of the
    first pier was limited to that one location.
    {¶ 7} David Rogers was not on site for the placement of the two other piers
    because he was needed at a site located in West Virginia. While Rogers was gone, TCS
    installed all of the stock it had on the job site to the depth of at least 80 feet. According
    to Sheeler, Rogers was aware TCS was continuing to drill, but did not tell TCS to stop.
    Rogers contends he did not know they continued to drill until he returned to the site on
    Wednesday, November 10, 2004, and TCS presented him with a change order in the
    amount of $51,000 for the purchase of more piers. This cost was in addition to the
    original contract price of $56,783.
    {¶ 8} Rogers notified Steve Cooper that TCS had done the triangulation, but had
    also installed all the piers even though they were going in at least 80 feet, thereby,
    doubling the cost of the project. Steve Cooper was outraged and refused to pay the
    additional cost, arguing TCS was not authorized to use all the stock it had on site once it
    was aware the depth was much deeper than anticipated.
    {¶ 9} As a result of the disagreement, Rogers scheduled a meeting for November
    16, 2004 to discuss the additional cost and possible ways to rectify the design problem.
    The meeting was attended by Sheeler, Rogers, a representative from Summit, structural
    engineers from Huffman & Associates, and Entertainment’s counsel. After the meeting,
    Sheeler sent Rogers a letter in which he recounted what had transpired at the meeting as
    follows:
    {¶ 10} “At that meeting, the man sitting next to you asked why we kept
    going when we knew that the pier depth was a problem. My response to you
    during our telephone conversation was that we did notify you that the first
    pier had run about 75'. I called you before the second pier was installed. I
    also told you that we were going to install the second pier to see if we hit the
    same depth and you agreed. The next day, on Tuesday morning, we installed
    two more piers around the building to create a triangle. At about 10:30 a.m.,
    I called you and told you that it seemed certain that all 45 piers would be
    going to 80+/-. You asked me for cost estimates, and I provided them to you
    over the phone, at that time and told you that I would be sending change
    orders out to you on Wednesday, so we pulled off the job at about noon. I
    am confident that we gave you any and all information as soon as possible.”
    {¶ 11} The letter does not indicate that Rogers authorized Sheeler to continue with
    the job. According to Rogers, he could not authorize Sheeler to continue without Steve
    Cooper agreeing to the change order.      Because Cooper refused to pay TCS, TCS
    removed all of its equipment including the piers it had installed. TCS then filed suit
    against Entertainment.
    {¶ 12} TCS requested $48,366 in contract damages and an additional $7,213 for
    costs it incurred removing its equipment and material from the site. The jury awarded
    TCS $14,876.45 in damages. Thereafter, TCS filed motions for a new trial and for
    judgment notwithstanding the verdict (“JNOV”), arguing that the jury’s award of
    damages was inadequate and against the manifest weight of the evidence. The trial court
    denied both motions.
    Inadequate Damages
    {¶ 13} We will address TCS’s assigned errors together as they all concern whether
    the jury’s verdict is supported by the evidence. TCS argues the verdict is against the
    manifest weight of the evidence and that the trial court erred by failing to grant its motion
    for a new trial or for JNOV.
    Standards of Review
    {¶ 14} In determining whether a verdict is against the manifest weight of the
    evidence, “[j]udgments supported by some competent, credible evidence going to all the
    essential elements of the case will not be reversed by a reviewing court as being against
    the manifest weight of the evidence.” C.E. Morris Co. v. Foley Const. Co. (1978), 
    54 Ohio St.2d 279
    , 280, 
    376 N.E.2d 578
    . When reviewing the sufficiency of the evidence
    in civil cases, the question is whether, after viewing the evidence in a light most favorable
    to the prevailing party, the judgment is supported by competent, credible evidence. 
    Id.
    Put more simply, the standard is “whether the verdict [is] one which could be reasonably
    reached from the evidence.” Hartford Cas. Ins. Co. v. Easley (1993), 
    90 Ohio App.3d 525
    , 
    630 N.E.2d 6
    . When engaging in this analysis, an appellate court must remember
    that the weight and credibility of the evidence are better determined by the trier of fact.
    
    Id.
    {¶ 15} A motion for new trial is governed by Civ.R. 59. TCS’s motion was based
    on Civ.R. 59(A)(4), which provides that a trial court may grant a new trial based upon
    excessive or inadequate damages. The motion was also based on Civ.R. 59(A)(6), which
    allows a new trial where the judgment was not sustained by the weight of the evidence.
    {¶ 16} The determination of whether or not to grant a new trial is within the
    discretion of the trial court and will not be reversed absent an abuse of discretion. Pena
    v. N.E. Ohio Emergency Affiliates, Inc. (1995), 
    108 Ohio App.3d 96
    , 103, 
    670 N.E.2d 268
    , citing Verbon v. Pennese (1982), 
    7 Ohio App.3d 182
    , 184, 
    454 N.E.2d 976
    . A
    motion for a new trial is reviewed differently at the appellate level than at the trial level; a
    reviewing court must view the evidence in a light most favorable to the trial court’s
    decision, rather than in favor of the nonmoving party. Jenkins v. Krieger (1981), 
    67 Ohio St.2d 314
    , 
    423 N.E.2d 856
    . This court does not weigh the evidence in reviewing a
    decision on a motion for a new trial.           Mannion v. Sandel, 
    91 Ohio St.3d 318
    ,
    
    2001-Ohio-47
    , 
    744 N.E.2d 759
    .
    {¶ 17} The standard of review for a JNOV motion is the same as that for a directed
    verdict. Construing the evidence most strongly in favor of the party against whom the
    motion is directed, the motion must be overruled unless reasonable minds could reach no
    other conclusion but that, under the applicable law, the movant is entitled to judgment in
    his favor. Civ.R. 50; D.O. Summers Cleaners & Shirt Laundry Co., Inc. (1998), 
    81 Ohio St.3d 677
    , 679, 
    693 N.E.2d 271
    .
    {¶ 18} Additionally, the assessment of damages is generally within the purview of
    the jury. Moskovitz v. Mt. Sinai Med. Ctr. (1994), 
    69 Ohio St.3d 638
    , 655, 
    635 N.E.2d 331
    ; Weidner v. Blazic (1994), 
    98 Ohio App.3d 321
    , 334, 
    648 N.E.2d 565
    . The jury’s
    verdict will not be disturbed absent an affirmative showing of passion or prejudice.
    Moskovitz at 655. Passion or prejudice is shown where the jury’s assessment of damages
    is so overwhelmingly disproportionate as to shock reasonable sensibilities. Pena at 104.
    “The mere size of the verdict is insufficient to establish proof of passion or prejudice.”
    
    Id.
    Analysis
    {¶ 19} The contested issue in this trial was whether TCS had authority to proceed
    to install the remaining piers once it discovered the piers installed in the triangle
    formation was at a depth of at least 80 feet, which was almost twice the depth projected.
    TCS contends that Sheeler’s discussions with Roger and Roger’s failure to issue a stop
    work order, gave it the authority to proceed. However, the jury could have easily
    concluded that TCS should not be awarded damages beyond the triangulation and
    subsequent removal of the piers installed up to and including the triangulation because it
    was not authorized to proceed with the project once the triangulation showed the depth
    would be a problem at the entire site.
    {¶ 20} David Rogers testified that after the first pier went in at the depth of 86 feet
    he discussed the problem with Entertainment President Steve Cooper. They agreed that a
    triangulation of the area should be done to determine the extent of the problem. Rogers
    testified that if the depth was going to be a problem throughout the design, they would
    then have the opportunity to create another design. Entertainment, however, never had
    the opportunity to discuss another design because TCS continued to install the entire
    stock of piers at the additional depth. In fact, by the time Rogers was given the change
    order, TCS had installed 15 additional piers.
    {¶ 21} Although Sheeler of TCS contends he notified Rogers of the depth problem
    after the triangulation was performed, there is no evidence Rogers gave him permission to
    continue. According to Sheeler, Rogers told him to give him an estimate of how much it
    would cost to do the project at the additional depth. However, the jury could have
    concluded this was not permission from Cooper to proceed. In fact, Rogers testified that
    Sheeler was aware that Rogers was only the project manager, not the owner, and only had
    permission to authorize day to day issues, not material changes. Any material changes
    had to be submitted to Cooper for approval. According to Rogers, he did not receive the
    new estimate until he was given a change order request for the additional $51,000 in
    material. This was after TCS had installed the additional piers.
    {¶ 22} TCS also claims the contract authorized it to proceed to install the piers
    because there was a provision in the contract quoting the cost of additional piers should
    they be required. However, it was within the jury’s discretion to determine whether this
    provision applied to material changes that would result in doubling the costs of the
    contract or only applied to the occasional use of additional piers in completing the project.
    Moreover, if this provision is read to apply to even material changes to the contract,
    there would have been no need to perform the triangulation as the contract would have
    obligated Entertainment to allow TCS to continue with the project regardless of the
    additional cost.
    {¶ 23} Based on this evidence, we conclude the jury could have reasonably
    determined that although Entertainment breached the contract by not paying TCS, TCS
    was not entitled to all the damages it claimed. There is no dispute that Entertainment
    authorized TCS to preform the triangulation; therefore, TCS should be paid for that work
    and possibly the cost for removing those piers. Unfortunately, because no special
    interrogatories were submitted to the jury, we are unable to conclusively determine what
    figures the jury used to calculate the damages. “Proper jury interrogatories lead to
    ‘findings of such a character as will test the correctness of the general verdict returned
    and enable the court to determine as a matter of law whether such verdict shall stand.’”
    Bobb Forest Products, Inc. v. Morbark Industries, Inc., 
    151 Ohio App.3d 63
    ,
    
    2002-Ohio-5370
    , 
    783 N.E.2d 560
    , citing Freeman v. Norfolk & W. Ry. Co. (1994), 
    69 Ohio St.3d 611
    , 613-614, 
    635 N.E.2d 310
    .          However, based on the evidence, the
    $14,876.45 could be reasonably calculated from the evidence presented and was not
    based upon passion or prejudice.
    {¶ 24} Thus, we conclude the court did not abuse its discretion in denying TCS’s
    motions and the jury verdict was not against the manifest weight of the evidence.
    Accordingly, TCS’s three assigned errors are overruled.
    Judgment affirmed.
    It is ordered that appellees recover from appellant their costs herein taxed.
    The court finds there were reasonable grounds for this appeal.
    It is ordered that a special mandate be sent to said court to carry this judgment into
    execution.
    A certified copy of this entry shall constitute the mandate pursuant to Rule 27 of
    the Rules of Appellate Procedure.
    PATRICIA ANN BLACKMON, PRESIDING JUDGE
    MELODY J. STEWART, J., and
    MARY J. BOYLE, J., CONCUR
    

Document Info

Docket Number: 96021

Citation Numbers: 2011 Ohio 5252

Judges: Blackmon

Filed Date: 10/13/2011

Precedential Status: Precedential

Modified Date: 10/30/2014