Hanuman Chalisa, L.L.C. v. Bomar Contracting, Inc. , 2022 Ohio 1111 ( 2022 )


Menu:
  • [Cite as Hanuman Chalisa, L.L.C. v. Bomar Contracting, Inc., 
    2022-Ohio-1111
    .]
    IN THE COURT OF APPEALS OF OHIO
    TENTH APPELLATE DISTRICT
    Hanuman Chalisa, LLC,                                :
    Plaintiff-Appellant,                 :                 No. 20AP-406
    (C.P.C. No. 17CV-5325)
    v.                                                   :
    (REGULAR CALENDAR)
    BoMar Contracting, Inc. et al.,                      :
    Defendants-Appellees.                :
    D E C I S I O N
    Rendered on March 31, 2022
    On brief: Sanjay K. Bhatt, for appellant. Argued: Sanjay K.
    Bhatt.
    On brief: Billmaier & Cuneo, LLC, and Jacob M.
    Lowenstein, for appellees. Argued: Jacob M. Lowenstein.
    APPEAL from the Franklin County Court of Common Pleas
    JAMISON, J.
    {¶ 1} Plaintiff-appellant, Hanuman Chalisa, LLC appeals from a judgment of the
    Franklin County Court of Common Pleas, in favor of defendants-appellees, BoMar
    Contracting, Inc. et al. ("BoMar"). For the reasons that follow, we reverse.
    I. FACTS AND PROCEDURAL HISTORY
    {¶ 2} On November 25, 2015, the parties executed a written agreement for the
    construction of a hotel in Columbus, Ohio. Appellant, Hanuman Chalisa, LLC, is identified
    as "Owner" in the contract documents and BoMar is identified as "Contractor." Robert L.
    Myers and Mary K. Grant, as guarantors of BoMar, executed personal guarantees
    respecting BoMar's work on the construction project.
    {¶ 3} The contract, drafted by Myers, incorporated an American Institute of
    Architects ("AIA"), form A101-2007, signed and initial by all parties, and an unsigned AIA
    No. 20AP-406                                                                              2
    form A201-2007, setting forth "General Conditions of Contract for Construction." The
    contract included a guaranteed maximum price of $5,172,701 and a "Cost Breakdown
    Worksheet."1 The Date of Commencement was to "be determined after a full set of
    documents have been received by owner's architect and when contractor records the notice
    of commencement * * *." According to the contract, the work was to be "[s]ubstantially
    complet[ed]" within 310 days of the "date of commencement." (Sept. 22, 2021 Pls. Ex. A at
    2-3.)
    {¶ 4} BoMar did not receive the final complete plans stamped by the City of
    Columbus until June 7, 2016. Accordingly, June 7, 2016, became the official date of
    commencement.
    {¶ 5} The contract required BoMar to submit payment applications on the
    prescribed AIA form. There is no dispute that the first ten pay applications were submitted
    and paid in a timely fashion. BoMar's eleventh pay application, submitted on or about
    October 10, 2016, identified work completed through September 25, 2016. The eleventh
    pay application was not approved or paid. Appellant, however, subsequently paid BoMar
    $150,000, and paid an additional sum of $386,461.73 directly to BoMar's subcontractors
    and materialmen. (Mar. 8, 2019 Stipulations at 2.)
    {¶ 6} By letter dated December 19, 2016, appellant terminated the contract
    effective December 27, 2016. The stated reason for the termination was alleged deficiencies
    and delays in BoMar's work.              As of the date of termination, BoMar had been paid
    $2,370,677.55, for work completed on the project.
    {¶ 7} On June 14, 2017, appellant filed a complaint against BoMar alleging breach
    of a construction contract and personal guarantee. According to appellant's complaint,
    BoMar breached the agreement by falling behind schedule, billing for work either not
    performed at all or not completed in accordance with BoMar's pay applications, permitting
    substandard work that was inconsistent with contract plans and specifications, requesting
    change orders for work within the original scope of work, and not engaging sufficient
    numbers of skilled workers to perform work in a proper manner. It is further alleged by
    appellant that BoMar failed to pay subcontractors and material suppliers, which resulted
    in the filing of mechanic's liens against the property.
    1   Due to approved change orders, the contract price at termination was $5,353,212.50.
    No. 20AP-406                                                                             3
    {¶ 8} On August 17, 2017, BoMar filed an answer to the complaint and a
    counterclaim alleging breach of contract, unjust enrichment, and quantum meruit.
    {¶ 9} The parties waived jury trial and on January 28, 2019, a magistrate
    conducted a two-day bench trial. One of the threshold issues at trial was whether appellant
    terminated the contract "for cause" or "for convenience," as those terms are used in the
    contract.
    {¶ 10} On January 8, 2020, the magistrate issued a decision in favor of BoMar on
    the complaint and the counterclaim. The magistrate found that appellant terminated the
    contract for convenience rather than for cause.       The magistrate then recommended
    judgment for BoMar in the total amount of $390,167.57.
    {¶ 11} On April 20, 2020, appellant timely filed objections to the magistrate's
    decision. On July 29, 2020, the trial court issued a decision and judgment entry overruling
    appellant's objections to the magistrate's decision and entering judgment for BoMar on the
    counterclaim in the total amount of $390,167.57.
    {¶ 12} Appellant timely appealed to this court from the July 29, 2020 judgment.
    II. ASSIGNMENTS OF ERROR
    {¶ 13} Appellant assigns the following as trial court error:
    [1.] The trial court erred when it found that the pre-printed
    AIA-201-2007 document, which form is commonly used
    throughout the construction industry, contained a
    "typographical error" and thereupon, modified the terms of the
    parties' agreement.
    [2.] The trial court erred in awarding Appellee BoMar 25%
    overhead and profit.
    [3.] The trial court erred in awarding 25% Profit on the
    outstanding invoices.
    III. STANDARD OF REVIEW
    {¶ 14} The interpretation and construction of a written contract are questions of
    law. Alexander v. Buckeye Pipeline Co., 
    53 Ohio St.2d 241
     (1978), paragraph one of the
    syllabus. Accordingly, "a de novo standard of review applies to matters of law, including
    the interpretation and construction of written contracts." Gatling Ohio, LLC v. Allegheny
    Energy Supply Co., LLC, 10th Dist. No. 17AP-188, 
    2018-Ohio-3636
    , ¶ 12, citing Long Beach
    No. 20AP-406                                                                                   4
    Assn. v. Jones, 
    82 Ohio St. 3d 574
     (1998). "Under the de novo standard, the court of appeals
    gives no deference to a trial court's interpretation of legal issues." 
    Id.,
     citing Holt v. State,
    10th Dist. No. 10AP-214, 
    2010-Ohio-6529
    , ¶ 9.
    IV. LEGAL ANALYSIS
    A. Assignments of Error
    1. Appellant's First Assignment of Error
    {¶ 15} In appellant's first assignment of error, appellant argues that the trial court
    erred, as a matter of law, when it found that the parties' agreement contained a
    typographical error. We disagree.
    {¶ 16} Pursuant to the parties' agreement, there are two methods the owner may
    employ to terminate the construction contract, termination for cause, pursuant to section
    14.1, and termination for convenience, pursuant to section 14.4.1 As previously noted, the
    trial court determined that appellant terminated the contract "for convenience" and that
    determination has not been challenged in this appeal. Section 14.1 provides as follows:
    § 14.4 TERMINATION BY THE OWNER FOR CONVENIENCE
    § 14.4.1 Notwithstanding any other provisions of the Contract
    Documents, the Owner may, at any time, and without cause,
    before or after the Notice to Proceed, terminate for
    convenience. * * *. The Owner shall pay the Contractor
    according to the terms of Section 13.1 of the Agreement and
    such payment shall be the Contractor's sole remedy under the
    Contract. Under no circumstances will the Contractor be
    entitled to anticipatory or unearned profits, consequential
    damages, or other damages of any sort as a result of a
    termination or partial termination of the Contract under this
    Section.
    (Emphasis added.) (Appellant's Brief at 16-17.)
    {¶ 17} Section 13.1 of the contract does not speak to damages in the event of a
    termination for convenience. In fact, section 13.1 does not speak directly to the issue of
    damages at all. Rather, section 13.1 merely provides that "[t]he Contract shall be governed
    by the law of the place where the Project is located." (Sept. 22, 2021 Pls. Ex. at 50.)
    {¶ 18} In BoMar's proposed findings of fact and conclusions of law, BoMar argued
    that the parties' agreement contained a typographical error and that the reference to section
    13.1 in section 14.4.1 was mistaken. BoMar claimed that the parties intended section 14.4.1
    No. 20AP-406                                                                           5
    to read as follows: "The Owner shall pay the Contractor according to the terms of Section
    14.1.3." Section 14.1 reads in relevant part as follows:
    § 14.1 TERMINATION BY THE CONTRACTOR
    § 14.1.1 The Contract may terminate the Contract if the Work
    is stopped for a period of 60 consecutive days through no act
    or fault of the Contractor or a Subcontractor. * * *.
    § 14.1.2 The Contractor may terminate the Contract if, through
    no act or fault of the Contractor or a Subcontractor, * * *,
    repeated suspensions delays or interruptions of the entire
    Work by the Owner * * *.
    § 14.1.3 If one of the reasons described in Section 14.1.1 or
    14.1.2 exists, the Contractor may, upon fourteen (14) days'
    written notice to the Owner and Architect, terminate the
    Contract and recover from the Owner payments for Work
    executed, including reasonable overhead and profit and
    direct costs incurred by reason of such termination.
    (Emphasis added.) (Appellant's Brief at 16.)
    {¶ 19} The magistrate agreed with BoMar and found as follows:
    The Magistrate agrees with Defendants that reference to
    section 13.1 is a clear typographical error, as that section is
    inapplicable. Instead, Section 14.1 addresses how the
    contractor should be compensated when the contractor
    terminates the agreement for cause. Section 14.1.3 states, that
    the contractor shall be paid, "for Work executed, including
    reasonable overhead and profit, and direct costs incurred by
    reason of such termination."
    (Jan. 8, 2020 Mag. Decision at 27.)
    {¶ 20} The trial court agreed with the magistrate and adopted the magistrate's
    decision as its own. In so doing, the trial court offered the following analysis:
    Admittingly, as Plaintiff describes in this objection, this is
    initially confusing because the corrected typographical error
    results in being forced to analyze relief for Defendants under
    a section that is entitled "Termination by the Contractor"
    when the Agreement was technically terminated by the
    Owner. But, the Court must effect the logical meaning from
    the Agreement, and that meaning cannot be that Defendants
    would not be paid for the work it completed if Plaintiff
    terminated the Agreement for convenience. That would be a
    nonsensical result because it would allow the Owner to exceed
    the benefit of the bargain, which is not something the
    Contractor would rationally agree to. Courts are permitted to
    No. 20AP-406                                                                               6
    interpret a contract so as not to create a "manifest absurdity."
    See e.g., Olmstead v. Lumbermens Mut. Ins. Co., 
    22 Ohio St. 2d 212
    , 216. One common source of potential absurdity in a
    contract is a typographical error. As such, when courts
    encounter a typographical error, they may accord a
    reasonable interpretation when extrinsic evidence is not
    necessary to accord the provision meaning. See e.g., Triangle
    Props. v. Homewood Corp., 
    2013-Ohio-3926
    , ¶ 61.
    (July 29, 2020 Decision & Order Adopting Mag.'s Decision at 15.)
    {¶ 21} Here, the magistrate determined that the parties' agreement contained a
    typographical error in that the reference to section 13.1 in section 14.4.1 was mistaken.
    Accordingly, the magistrate reformed section 14.4.1 of the parties' agreement to read as
    follows: "The Owner shall pay the Contractor according to the terms of Section 14.1.3 of the
    Agreement and such payment shall be the Contractor's sole remedy under the Contract."
    {¶ 22} " 'Reformation is available where it is shown that the written instrument does
    not express the true agreement entered into between the contracting parties by reason of
    mistake common to them.' " Natl. City Real Estate Servs., L.L.C. v. Frazier, 4th Dist. No.
    17CA3585, 
    2018-Ohio-982
    , ¶ 27, quoting Wagner v. Natl. Fire Ins. Co., 
    132 Ohio St. 405
    ,
    412 (1937). "Reformation is an equitable remedy that allows a court to change the language
    in a contract where the parties' true intentions have not been expressed due to a 'mutual
    mistake'—meaning a common mistake by all the parties to the contract." Wells Fargo Bank
    Minnesota v. Mowery, 
    187 Ohio App.3d 268
    , 
    2010-Ohio-1650
     (4th Dist.). "[T]he remedy
    of reformation can be applicable even when a mistake has been caused by a unilateral
    drafting error." DeMuesy v. Haimbaugh, 10th Dist. No. 91AP-212, 
    1991 Ohio App. LEXIS 6407
     (Dec. 31, 1991), citing Snedegar v. Midwestern Indemn. Co., 
    44 Ohio App.3d 64
    (1988). The purpose of contract reformation is not to create a new contract between the
    parties; rather, the purpose of reformation is to make the writing conform to the real
    intention of the parties. Frazier at ¶ 27.
    {¶ 23} Appellant contends the trial court erred in reforming the parties' agreement
    because BoMar did not claim that section 14.4.1 contained a typographical error at trial,
    and no evidence was presented of the parties' intentions with regards to section 14.4.1. This
    court, however, has previously rejected the argument that a trial court is precluded from
    finding a typographical error in a written contract in the absence of extrinsic evidence to
    No. 20AP-406                                                                                7
    support the finding. See Triangle Properties, Inc. v. Homewood Corp., 10th Dist. No.
    12AP-933, 
    2013-Ohio-3926
    , ¶ 61 ("We find no error in the trial court's resolution of this
    issue purely as a matter of interpretation without the need to examine extrinsic evidence.
    The single reference to August 21, 2007 was a typographical error.")
    {¶ 24} In our view, the trial court adopted a reasonable interpretation of the parties'
    agreement in light of the obvious typographical error in section 14.1.1. Accordingly, we hold
    that the trial court did not err when it reformed section 14.1.1 of the parties' agreement to
    reflect the parties' true intentions.
    {¶ 25} Moreover, even if the trial court had erred when it reformed the parties'
    agreement, our review of Ohio common law supports the trial court's award of damages.
    Under Ohio law, damages for breach of contract are based either on the non-breaching
    party's expectation interest, reliance interest, or restitution interest.    Father's House
    International, Inc. v. Kurguz, 10th Dist. No. 15AP-1046, 
    2016-Ohio-5945
    , ¶ 22, citing
    Restatement of the Law 2d, Contracts, Section 344(c). Expectation damages vindicate the
    non-breaching party's "interest in having the benefit of his bargain." Restatement of the
    Law 2d, Contracts, Section 344(a). Expectation damages generally place the non-breaching
    party in the position it would have been in had the contract been fully performed. See
    Kurguz at ¶ 21-23; Alternatives Unlimited-Special, Inc. v. Ohio Dept. of Edn., 10th Dist.
    No. 12AP-647, 
    2013-Ohio-3890
    , ¶ 29. See also Restatement of the Law 2d, Contracts,
    Section 346, 347. Such damages include future lost profits. Alternatives Unlimited at ¶ 30,
    citing Doner v. Snapp, 
    98 Ohio App.3d 597
    , 601 (2d Dist.1994). The expectation interest
    is generally measured by "(a) the loss in value to the injured party cause[d] by the breaching
    party's failure or deficiency, plus (b) any other loss, including incidental or consequential
    loss, caused by the breach, less (c) any cost or other loss that the injured party avoided by
    not having to perform." Restatement of the Law 2d, Contracts, Section 347.
    {¶ 26} Conversely, restitution damages vindicate the non-breaching party's interest
    in recovering the benefit conferred on the other party. Kurguz at ¶ 24. "If a sum of money
    is awarded to protect a party's restitution interest, it may as justice requires be measured
    by either (a) the reasonable value to the other party of what he received in terms of what
    it would have cost him to obtain it from a person in the claimant's position, or (b) the
    No. 20AP-406                                                                                 8
    extent to which the other party's property has been increased in value or his other interests
    advanced." (Emphasis added.) Restatement of the Law 2d, Contracts, Section 371.
    {¶ 27} In our view, section 14.4.1 of the parties' agreement limits a contractor's
    recovery to restitution damages. Expectation damages are not available to a contractor
    where the termination is for convenience rather than for cause. Here, the trial court
    awarded restitution damages to BoMar equal to the amount BoMar had been billed by its
    subcontractors for work executed prior to termination, plus overhead and profit. (Sept. 22,
    2021 Pls. Ex. at 4-6 and 19.) The trial court did not award damages to BoMar based on the
    future net profit BoMar would have earned had the agreement been fully performed.
    Accordingly, even if we were to find that the trial court erred when it determined that the
    reference to section 13.1 was a typographical error, and that BoMar's damages were to be
    determined in accordance with Ohio common law, the trial court limited BoMar's damages
    to restitution. Because BoMar's damages upon termination for convenience would have
    been the same had the trial court applied Ohio common law, appellant has not
    demonstrated prejudice.
    {¶ 28} For similar reasons, we find no merit in appellant's claim that section 14.4.1,
    "termination by owner for convenience," prohibits an award of profit to BoMar. Section
    14.4.1 provides in relevant part: "Under no circumstances will the Contractor be entitled
    to anticipatory or unearned profits, consequential damages, or other damages of any sort
    as a result of a termination or partial termination of the Contract under this Section."
    (Emphasis added.) In our view, the highlighted provision in section 14.4.1 prohibits a
    contractor from recovering expected or anticipated overhead and profit for work that it has
    yet to complete. BoMar's overhead and profit arising from work executed by BoMar's
    contractors prior to termination is not anticipatory or unearned. Thus, the trial court did
    not violate section 14.4.1 when it awarded damages to BoMar.
    {¶ 29} For the foregoing reasons we overrule appellant's first assignment of error.
    2. Appellant's Second Assignment of Error
    {¶ 30} In appellant's second assignment of error, appellant contends that the trial
    court erred when it awarded damages to BoMar based upon a finding that BoMar was
    entitled to a 25 percent mark-up for overhead and profit, rather than the 5 percent figure
    referenced in the Cost Breakdown Worksheet. We agree.
    No. 20AP-406                                                                               9
    {¶ 31} The parties submit the following stipulation relevant to the damages issue:
    3. The original contract price was $5,172,701.00. After taking
    into account all agreed to change orders that were approved
    as of the date of termination, the contract price at the time of
    termination was $5,353,212.50. At the time of termination,
    other change orders remained in dispute or had otherwise not
    been approved.
    4. Prior to BoMar's termination, [appellant] paid BoMar
    Contracting, Inc. a total of $2,370,677.55. Joint Exhibit A-1 is
    a list of the payment amounts and dates.
    5. After BoMar's termination, [appellant] paid a total of
    $386,461.73 to subcontractors or materialmen, for work
    performed, and materials supplied, while BoMar Contracting,
    Inc. served as the general contractor on the construction
    project.
    6. Between the beginning of the project and August 25, 2016,
    BoMar submitted 10 payment applications to [appellant]
    totaling $2,255,985.51.
    7. Between August 25, 2016 and the date of termination,
    BoMar submitted several different revisions of an 11th Pay
    Application to [appellant], but as of the date of termination,
    Pay Application 11 had not been approved.
    8. During the discussions relating to Pay Application 11,
    between Plaintiff, Defendant and Plaintiff's Lender, Liberty
    Bank, [appellant] made payments totaling $30,000 to
    BoMar's plumber, and a payment of $150,000.00 directly to
    BoMar towards the amount BoMar claimed was due on Pay
    Application 11.
    9. Between the period of time covered by Pay Application 10
    and BoMar's termination, BoMar received invoices from
    materialmen and subcontractors. Defendant's exhibits 3, 4, 5
    and 6 are ledgers listing the invoices received in September,
    October, November and December 2016, respectively.
    Plaintiff stipulates that for evidentiary purposes only, these
    ledgers are admissible summaries of the invoices received.
    Because Plaintiff made numerous payments to unpaid
    subcontractors and materialmen of Defendant after
    Defendant's contract was terminated (see Stipulation No. 5),
    Plaintiff cannot stipulate that these invoices have not been
    paid, or that Defendant has any obligation to pay those
    invoices which have never been paid.
    (Mar. 8, 2019 Stipulations at 1-2.)
    No. 20AP-406                                                                              10
    {¶ 32} Appellant relies on the Cost Breakdown Worksheet in support of its claim
    that the parties agreement limits BoMar's overhead and profit margin to five percent. The
    Cost Breakdown Worksheet is attached to the Contract as exhibit 1 and incorporated into
    the parties' agreement pursuant to section 4.3.
    {¶ 33} At oral argument, BoMar's counsel conceded that a five percent margin for
    overhead and profit was an agreed upon margin for purposes of the original contract price.
    BoMar maintains, however, that the five percent figure was subject to change and that the
    five percent margin did not apply to any work executed pursuant to changes ordered.
    {¶ 34} In Ohio Water Dev. Auth. v. W. Reserve Water Dist., 
    149 Ohio App.3d 155
    ,
    
    2002-Ohio-4393
     (10th Dist.), this court set forth the relevant law of contract interpretation
    as follows:
    The interpretation of a written contract is a matter of law to
    be determined by the court. Alexander v. Buckeye Pipe Line
    Co. (1977), 
    49 Ohio St.2d 158
    , 
    3 Ohio Op. 3d 174
    , 
    359 N.E.2d 702
    , paragraph one of the syllabus. The paramount objective
    in construing such a written agreement is to ascertain the
    parties' intent. Aultman Hosp. Assn. v. Community Mut. Ins.
    Co. (1989), 
    46 Ohio St.3d 51
    , 53, 
    544 N.E.2d 920
    . The
    agreement must be given a just and reasonable construction
    which carries out the intent of the parties as evidenced by the
    contractual language. Skivolocki v. East Ohio Gas Co. (1974),
    
    38 Ohio St.2d 244
    , 
    67 Ohio Op. 2d 321
    , 
    313 N.E.2d 374
    ,
    paragraph one of the syllabus. The parties' intent is presumed
    to reside solely within the language employed in the
    agreement. Kelly v. Medical Life Ins. Co. (1987), 
    31 Ohio St.3d 130
    , 
    31 Ohio B. 289
    , 
    509 N.E.2d 411
    , paragraph one of the
    syllabus. Words and phrases appearing in a contract which are
    not specifically defined therein should be given their common,
    ordinary, and usual meaning. Monsler v. Cincinnati Cas. Co.
    (1991), 
    74 Ohio App.3d 321
    , 329, 
    598 N.E.2d 1203
    . It is of
    course well-settled that the fact that parties may adopt
    conflicting interpretations of a contract between them, while
    involved in litigation, will not create ambiguity or a basis for
    unreasonable interpretation of the language and original
    intent of the parties where no such ambiguity should
    reasonably be found. Steward v. Champion International
    Corp. (C.A.11, 1993), 
    987 F.2d 732
    , 734. The question of
    whether ambiguity or uncertainty in the language of a
    contract requires resort to extrinsic evidence to ascertain the
    intent of the parties is a question of law for the court. Latina
    No. 20AP-406                                                                              11
    v. Woodpath Development Co. (1991), 
    57 Ohio St.3d 212
    , 214,
    
    567 N.E.2d 262
    .
    Id. at ¶ 25.
    {¶ 35} At trial, BoMar maintained that the parties did not intend the 5 percent limit
    for overhead and profit to apply to all of BoMar's work on the project. BoMar produced
    testimonial evidence at trial in order to establish that a 25 percent margin for overhead and
    profit was contemplated by the parties. Appellant counters that, absent ambiguity in the
    relevant contract language, the trial court was precluded from considering extrinsic
    evidence of the parties' intent.
    {¶ 36} BoMar relied on defendant's Exhibit 19 and the testimony of bookkeeper,
    Marie Arnold, in support of the damage's calculation. Defendant's Exhibit 19 shows that
    BoMar lost overhead and profit as a result of contract termination in the total amount of as
    $178,000. According to Arnold, the loss was calculated by adding a 25 percent markup for
    overhead and profit to the invoices submitted by BoMar's contractors for the work reflected
    on pay application number 11. When Arnold was asked about the 25 percent margin at trial
    she testified as follows:
    Q. Okay. Going back to Exhibit 19, the next line down is the
    $713,057.07. That is the total of the four months that are listed
    slightly to the left of that figure; correct?
    A. Yes.
    Q. Okay. Now, the next line applies an overhead and profit of
    25 percent to that figure. Do you see where I'm referring?
    A. Yes.
    Q. Is 25 percent an industry standard number for overhead
    and profit?
    A. That is what we always customarily billed.
    (Jan. 29, 2019 Tr. Vol. 2 at 566-67.)
    {¶ 37} The magistrate found that a 25 percent margin for profit and overhead was
    reasonable in light of the industry standard:
    Defendants' witnesses established damages at trial. BoMar
    submitted that it is owed for its direct costs from September
    through termination in December of 2016, plus reasonable
    profit and overhead. Both Ms. Arnold and Mr. Myers testified
    that a 25% markup for profit and overhead is standard in the
    No. 20AP-406                                                                                             12
    industry and customarily billed. No other witness presented
    evidence to the contrary. Therefore, as is set forth in
    Defendants' Ex 19, the total owed to plaintiff for the project is
    $3,147,306.85. Against this, the parties have stipulated that
    plaintiff should be credited $2,757,139.28, leaving a balance
    owed to the defendant of $390,167.57.
    (Jan. 8, 2020 Mag.'s Decision at 27.)
    {¶ 38} The trial court adopted the magistrate's findings of fact and conclusions of
    law as its own. Based largely on Arnold's testimony, and the absence of rebuttal evidence,
    the trial court found that the parties agreed to a 25 percent margin for overhead and profit.
    {¶ 39} We do not read Arnold's testimony as broadly as the magistrate and the trial
    court. In our view, Arnold testified only that she customarily adds 25 percent to the invoices
    submitted by BoMar's subcontractors to account for overhead and profit. Her testimony
    does not establish an industry standard.2 Moreover, "[w]hen the terms in a contract are
    unambiguous, courts will not in effect create a new contract by finding an intent not
    expressed in the clear language employed by the parties." Shifrin v. Forest City Enter., Inc.,
    
    64 Ohio St.3d 635
    , 638 (1992), citing Alexander v. Buckeye Pipeline Co., 
    53 Ohio St.2d 241
    ,
    246 (1978). It is "[o]nly when the language of a contract is unclear or ambiguous, or when
    the circumstances surrounding the agreement invest the language of the contract with a
    special meaning will extrinsic evidence be considered in an effort to give effect to the parties'
    intentions." Shifrin at 638, citing Kelly v. Med. Life Ins. Co., 
    31 Ohio St.3d 130
     (1987).
    {¶ 40} In adopting the magistrate's decision, the trial court reasoned that the parties
    did not intend the five percent margin for overhead and profit to apply to the numerous
    and extensive modifications to the work that occurred during construction. We find no
    such intent expressed in the parties' agreement. In fact, section 7.3.8 specifically addresses
    the manner of payment to a contractor where the parties cannot agree on change order
    pricing. That section of the agreement contains several blank spaces where the parties are
    prompted to insert the contractor's margin for overhead and profit. The parties did not
    insert any figures in those blank spaces. Had the parties intended to provide a greater
    margin for overhead and profit when BoMar executed work pursuant to a change directive,
    2Appellant argues alternatively that Arnold was not competent to offer testimony as to the industry standard
    for overhead and profit. Having determined that Arnold offered no such testimony, appellant's competency
    argument is moot.
    No. 20AP-406                                                                                13
    the parties would certainly have provided for a different rate in section 7.3.8. Rather than
    doing so, the parties left the space designated for overhead and profit blank. In the absence
    of a contrary expression of the parties' intent in the written agreement, a five percent
    margin for overhead and profit applied to all work performed on the project.
    {¶ 41} Moreover, section 1.1 of the General Provisions to the parties' agreement
    provides the method by which the parties' may modify the original agreement as follows:
    "A Modification is (1) a written amendment to the Contract signed by both parties, (2) a
    Change Order, (3) a Construction Change Directive or (4) a written order for a minor
    change in the Work issued by the Architect." (Sept. 22, 2021 Pls. Ex. at 11.) Accordingly,
    the contract provides that any subsequent modification to the agreed upon margin for
    overhead and profit must be in writing.
    {¶ 42} Here, BoMar introduced testimony that, if believed, contradicted the plain
    language of the parties' agreement with regards to the contractor's margin for overhead and
    profit. The trial court, in awarding damages to BoMar, relied on this testimony, disregarded
    the language in the contract, and applied a 25 percent profit margin. In so doing, the trial
    court impermissibly created a new contract by finding an intent not expressed in the
    language employed by the parties. Shifrin at 638. Accordingly, we hold that the trial court
    erred, as a matter of law, when it determined that the parties orally agreed to apply a 25
    percent margin for overhead, rather the five percent set out in the parties' agreement.
    {¶ 43} We acknowledge that BoMar's margin for overhead and profit could have
    been addressed more conspicuously in the parties' agreement.              Nevertheless, "[i]n
    interpreting a contract, we are required, if possible, to give effect to every provision of the
    contract." Sunoco, Inc. v. Toledo Edison Co., 
    129 Ohio St.3d 397
    , 408 (2011). Here, the
    contractor's margin for overhead and profit is set forth in the contract documents and there
    is no ambiguity or uncertainty as to five percent margin for overhead and profit.
    Consequently, there was no reason to consider evidence outside the written agreement to
    discern the parties' intent, and no need for appellant to rebut any such evidence.
    {¶ 44} BoMar argues that because section 14.1.3 permits an award of "reasonable
    overhead and profit," the trial court was permitted to look outside the contract to determine
    what was reasonable. As previously discussed, because BoMar's margin for overhead and
    profit is set forth in the parties' agreement, the trial court had no reason to look beyond the
    No. 20AP-406                                                                               14
    four corners of the written agreement to determine reasonable overhead and profit.
    BoMar's argument erroneously assumes that the five percent margin for overhead and
    profit agreed to by the partiers is not reasonable. This court, however, "will not rewrite the
    contract simply to relieve [a party] of what he perceives as a bad bargain." Hodge v. Prater,
    10th Dist. No. 13AP-838, 
    2014-Ohio-3152
    , ¶ 18, citing Impressions Bldg., LLC v. Heart
    Specialists of Ohio, Inc., 10th Dist. No. 06AP-275, 
    2006-Ohio-4719
    , ¶ 9, citing Ervin v.
    Garner, 
    25 Ohio St.2d 231
    , 239-40 (1971). For the foregoing reasons, appellant's second
    assignment of error is sustained.
    3. Appellant's Third Assignment of Error
    {¶ 45} In appellant's third assignment of error, appellant argues that the trial court
    erred when it awarded BoMar 25 percent profit on outstanding invoices. We disagree.
    {¶ 46} The trial court determined that appellant terminated the contract for
    convenience, not for cause. On the date of termination, pay application 11 had been
    submitted to appellant by BoMar, but it had not yet been approved. BoMar had not yet
    made payment to the subcontractors for the work reflected in pay application 11.
    {¶ 47} The trial court adjusted the damages awarded to BoMar to account for the
    direct payments appellant made to BoMar's subcontractors after termination. However,
    because the termination was for convenience, appellant's direct payments to BoMar's
    subcontractors for work executed prior to the termination did not relieve appellant of the
    contractual obligation to pay BoMar profit it had earned. BoMar was entitled to restitution
    damages for executed work.
    {¶ 48} Nevertheless, consistent with our ruling on appellant's second assignment of
    error, we hold that the trial court erred when it added 25 percent margin for overhead and
    profit rather than the 5 percent set forth in the parties' agreement. Accordingly, we sustain
    appellant's third assignment of error in part and overrule it in part.
    V. CONCLUSION
    {¶ 49} Having overruled appellant's first assignment of error but having sustained
    appellant's second assignment of error and appellant's third assignments of error, in part,
    we affirm the judgment of the Franklin County Court of Common Pleas, in part and reverse
    in part, and remand the matter for further proceedings consistent with this decision.
    Judgment affirmed in part and reversed in part.
    No. 20AP-406                                           15
    SADLER and BEATTY BLUNT, JJ., concur.
    

Document Info

Docket Number: 20AP-406

Citation Numbers: 2022 Ohio 1111

Judges: Jamison

Filed Date: 3/31/2022

Precedential Status: Precedential

Modified Date: 4/1/2022