Murphy Elevator Co., Inc. v. 11320 Chester L.L.C. , 110 N.E.3d 787 ( 2018 )


Menu:
  •          [Cite as Murphy Elevator Co., Inc. v. 11320 Chester L.L.C., 
    2018-Ohio-1362
    .]
    IN THE COURT OF APPEALS
    FIRST APPELLATE DISTRICT OF OHIO
    HAMILTON COUNTY, OHIO
    THE MURPHY ELEVATOR                               :          APPEAL NO. C-170251
    COMPANY, INC.,                                               TRIAL NO. A-1603623
    Plaintiff-Appellee,                       :              O P I N I O N.
    vs.
    :
    11320 CHESTER LLC, d.b.a. SPLASH
    CINCINNATI WATERPARK, f.k.a.
    COCO KEY HOTEL AND WATER                          :
    RESORT,
    Defendant-Appellant.                          :
    Civil Appeal From: Hamilton County Court of Common Pleas
    Judgment Appealed From Is:               Affirmed in Part, Reversed in Part, and Cause
    Remanded
    Date of Judgment Entry on Appeal: April 11, 2018
    Christopher R. Heekin Co. LLC and Christopher R. Heekin, for Plaintiff-Appellee,
    Repper-Pagan Law, Ltd., and Christopher J. Pagan, for Defendant-Appellant.
    OHIO FIRST DISTRICT COURT OF APPEALS
    MYERS, Presiding Judge.
    {¶1}       Defendant-appellant 11320 Chester LLC (“Chester”) has appealed
    from the trial court’s entry granting judgment in the amount of $13,626.14 to
    plaintiff-appellee The Murphy Elevator Company (“Murphy”) on Murphy’s claim for
    breach of contract.
    {¶2}   Because the trial court used the wrong measure of damages when
    calculating the damages owed to Murphy for the remaining months under the second
    year of the parties’ three-year contract, we reverse that portion of the trial court’s
    judgment. The judgment of the trial court is otherwise affirmed.
    Factual and Procedural Background
    {¶3}   Chester and Murphy entered into a contract for Murphy to perform
    maintenance services on certain elevators located in a hotel and waterpark owned by
    Chester. The contract commenced on August 1, 2014, and provided that it would
    continue for a period of three years.
    {¶4}   Chester was required to pay Murphy $4,000 per quarter for the first
    year of the contract. However, if Chester paid for an entire contract year up front, it
    was only required to pay $15,000 for the year. With respect to the price owed by
    Chester for the second and third years of the contract, the contract provided that the
    price “is subject to adjustment at the end of each year in which this agreement is in
    force. The following formula for adjustment will be used: not more than 3% of the
    current price.”
    {¶5}   The contract specified the exact services covered and stated that “[n]o
    work, service or liability, on the part of The Murphy Elevator Company other than
    that specifically mentioned herein is included or intended as a part of the contract.”
    2
    OHIO FIRST DISTRICT COURT OF APPEALS
    The contract further listed the hours and days during which services would be
    performed, and it provided that Chester would incur an additional charge for covered
    work performed outside of the specified days and times.
    {¶6}   Chester paid $15,000 up front for the first year of the contract. On
    July 1, 2015, Murphy submitted an invoice for the second year of the contract in the
    amount of $16,371. This amount was a three-percent increase to the price paid
    during the first year of the contract, plus sales tax. During the first and second years
    of the contract, Murphy submitted additional invoices to Chester for work performed
    that was outside the scope of the contract and for work covered under the contract
    that was performed outside of the contractually provided days and times.
    {¶7}   After paying for the first year of the contract up front, Chester made
    only two additional payments to Murphy. It made a payment of $168.13, which
    corresponded to an invoice for work that had been performed on a day or time not
    covered under the contract. And it made an additional payment of $8,500 on
    September 17, 2015.
    {¶8}   In June of 2016, Murphy sued Chester for breach of contract for
    Chester’s failure to pay the submitted invoices.       Murphy sought approximately
    $22,126 in damages.
    {¶9}   During a bench trial, Murphy’s Vice President of Administration Travis
    Carlisle testified regarding the unpaid invoices that Murphy had submitted to
    Chester. He explained that with respect to work that Murphy had performed that
    was not covered under the contract, Murphy billed Chester the rate it would charge
    for a technician’s regular time, holiday time, or overtime, depending on when the
    work was performed.      And for work covered under the contract but performed
    3
    OHIO FIRST DISTRICT COURT OF APPEALS
    outside of the contractually provided days and times, Carlisle stated that Murphy
    billed Chester the difference between a technician’s regular and overtime rates, as
    was provided for in the parties’ contract.
    {¶10} Carlisle explained the circumstances surrounding each invoice that
    had been submitted, including whether the work had been covered under the
    contract.   He conceded on cross-examination that Chester’s payment of $8,500
    should be applied to the amount invoiced for the second year of the contract.
    {¶11} Carlisle testified that Murphy had stopped performing under the
    contract in March of 2016 because of Chester’s nonpayment.           He additionally
    explained that Murphy generally receives a 33 percent profit margin on this type of
    service contract.
    {¶12} Vijaya Kumar Vemulapalli testified on behalf of Chester that neither he
    nor anyone else had requested that Murphy perform any services on weekends or
    during premium, noncovered time. He explained that prior to signing the contract
    with Murphy, he informed the company that he did not want to pay for services
    performed on the weekend. Vemulapalli testified that Murphy had told him that
    despite their standard contract language excluding weekends from coverage, it would
    not charge him for weekend service calls.
    {¶13} The trial court found that the parties’ contract covered only the days
    and times specified in the contract and that Murphy’s submitted invoices were valid.
    It voided the third year of the contract as a matter of equity, and it awarded Murphy
    $22,126.14 in damages.
    {¶14} Chester filed a motion for reconsideration. It argued that the trial
    court should have credited its payment of $8,500 towards the amount billed for the
    4
    OHIO FIRST DISTRICT COURT OF APPEALS
    second year of the parties’ contract, that the trial court should not have charged
    Chester premium rates for services performed outside the contract, and that Chester
    should not have been required to pay for the second half of the second year of the
    contract.
    {¶15} The trial court issued a modified judgment crediting Chester for the
    $8,500 payment and awarding Murphy $13,626.14 in damages.
    Billing Rates
    {¶16} In its first assignment of error, Chester argues that the trial court erred
    in failing to enforce the clear and unambiguous terms of the contract to services
    performed outside the scope of the contract.
    {¶17} Where a contract’s terms are clear and unambiguous, interpretation of
    the contract is a matter of law. Ruehl v. Air/Pro, Inc., 1st Dist. Hamilton Nos. C-
    040339 and C-040350, 
    2005-Ohio-1184
    , ¶ 4. In such instances, this court conducts
    a de novo review. 
    Id.
     But where the terms of a contract are ambiguous, “the
    meaning of the words in the contract becomes a question of fact, and the trial court’s
    interpretation will not be overturned on appeal absent a showing that the court
    abused its discretion.”     Kelly Dewatering and Constr. Co. v. R.E. Holland
    Excavating, Inc., 1st Dist. Hamilton No. C-030019, 
    2003-Ohio-5670
    , ¶ 21.              A
    contract will be considered ambiguous where “its terms cannot be clearly determined
    from a reading of the entire contract or if its terms are susceptible to more than one
    reasonable interpretation.” 
    Id.
    {¶18} Chester first argues that a rate of $90 per hour should govern all
    charges for work performed outside of the contractually specified dates and times
    and for work that was not covered under the contract. It relies on the following
    5
    OHIO FIRST DISTRICT COURT OF APPEALS
    provision in the parties’ contract:    “If you request that the normal and regular
    examination, adjustments, and/or repairs be made at times other than the regular
    working hours as set forth above, then you agree to pay the difference between our
    regular and overtime billing rates.”    With respect to the difference in rates, the
    contract contained the following clause: “Rates for the year 2014: The difference
    between Straight and Overtime will be $90.00 per man hour.”
    {¶19} For covered services performed outside of the contractually specified
    dates and times, Murphy initially invoiced Chester at a rate of $90 per hour. But in
    two invoices in the year 2016, Murphy invoiced Chester at a rate 0f $126 per hour for
    such services. Carlisle addressed this discrepancy and explained that in 2016, the
    difference between regular and overtime rates had increased from $90 to $126 per
    hour.
    {¶20} Chester contends that the trial court erred in awarding Murphy
    judgment calculated at a rate of $126 per hour on these two invoices. But the
    contract language providing that Chester would owe the difference between a
    technician’s regular and overtime billing rates for this type of work was clear and
    unambiguous. The contract was equally clear that $90 was the difference between
    such rates in the year 2014. The trial court did not err in relying on Carlisle’s
    testimony and determining both that the difference in rates was $126 per hour in the
    year 2016 and that Chester was required to pay these two invoices as charged.
    {¶21} As to services performed that were not covered under the parties’
    contract, Murphy invoiced Chester at either a technician’s regular rate, holiday rate,
    or overtime rate, depending on when the services were performed. These rates
    ranged from $196 per hour to $362 per hour. Chester contends that Murphy could
    6
    OHIO FIRST DISTRICT COURT OF APPEALS
    only have charged a rate of $90 per hour (described as the difference between
    regular and overtime rates) for services not covered under the contract.
    {¶22} The contract clearly and unambiguously provided that only certain
    services were covered. And while the contract did not specify the exact hourly rate
    that Chester would be required to pay for services not covered, the only reasonable
    interpretation of the contract is that Chester would be charged Murphy’s standard
    rate for such services. Chester’s argument that Murphy was limited to charging a
    rate of $90 is meritless. The $90 amount specified in the contract was not an hourly
    rate otherwise charged by Murphy. Rather, it was the difference between the rates
    charged for a technician’s regular time and overtime. The trial court did not err in
    relying on Carlisle’s undisputed testimony and the submitted invoices to determine
    the rates that Murphy charged for a technician’s regular time, holiday time, and
    overtime, and in awarding Murphy judgment for services not contractually covered
    based on those rates.
    {¶23} Chester last argues under this assignment of error that the trial court
    erred in awarding judgment to Murphy on the invoice numbered 101382 because
    Murphy had failed to establish that Chester had requested the services charged in
    that invoice during a time not covered under the contract. The record belies this
    argument. With respect to the invoice numbered 101382, Carlisle testified that the
    service call had come in at night. He specifically stated, “[i]t certainly came in, in the
    evening at some point.” The trial court did not err in relying on Carlisle’s testimony
    and awarding Murphy the amount sought for overtime work in this invoice.
    7
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶24} Because the trial court did not err in awarding judgment on services
    that were performed outside the scope of the contract, we overrule Chester’s first
    assignment of error.
    Damages for Year Two of the Contract
    {¶25} In its second assignment of error, Chester argues that the trial court
    erred in awarding a judgment encompassing full payment under the second year of
    the contract.
    {¶26} Murphy invoiced Chester $16,371 for the second year of the contract.
    The trial court awarded Murphy judgment for this full amount, less Chester’s $8,500
    payment that Carlisle had conceded should be applied towards payment of the
    second year contract price.
    {¶27} Chester argues that because Murphy had stopped performing on the
    contract in March of 2016, the trial court erred in awarding Murphy the full amount
    invoiced for year two of the contract. It contends that Murphy is only entitled to
    damages on the months that it performed services during that contractual year.
    While we agree with Chester’s argument that the trial court erred in calculating the
    damages owed to Murphy for its services under year two of the contract, we disagree
    with Chester’s suggested measure of determining the correct amount of damages.
    {¶28} An award of damages should put the injured party in the same position
    it would have been in if there had been no breach. Evans Landscaping, Inc. v.
    Grubb, 1st Dist. Hamilton No. C-090139, 
    2009-Ohio-6645
    , ¶ 12. Here, had there
    been no breach, Murphy would have received the remainder of the amount invoiced
    on year two of the contract, less its expenses. Murphy therefore was entitled to
    damages in the amount of the lost profits that it would have received for the
    8
    OHIO FIRST DISTRICT COURT OF APPEALS
    remainder of year two of the contract. See Andrew v. Power Marketing Direct, Inc.,
    
    2012-Ohio-4371
    , 
    978 N.E.2d 974
    , ¶ 66 (10th Dist.) (lost profits may be recovered in
    an action for breach of contract where “(1) profits were within the contemplation of
    the parties at the time the contract was made; (2) the loss of profits was the probable
    result of the breach of contract; and (3) the profits are not too remote or
    speculative.”).
    {¶29} Carlisle testified that Murphy generally receives a 33 percent profit
    margin on a service contract.        But rather than award Murphy its lost profits
    encompassing 33 percent of the amount owed by Chester for the remaining months
    of year two of the contract, the trial court awarded Murphy the gross revenue it
    would have received for the services covered under year two of the contract. This
    was in error.
    {¶30} We sustain Chester’s second assignment of error, and we vacate the
    portion of the trial court’s judgment awarding Murphy full payment on the amount
    invoiced for year two of the contract. This cause is remanded for the trial court to
    calculate the lost profits on the remaining months of the second year of the contract
    and to award Murphy damages in that amount. The judgment of the trial court is
    otherwise affirmed.
    Judgment affirmed in part, reversed in part, and cause remanded.
    MILLER and DETERS, JJ., concur.
    Please note:
    The court has recorded its own entry on the date of the release of this opinion.
    9
    

Document Info

Docket Number: C-170251

Citation Numbers: 2018 Ohio 1362, 110 N.E.3d 787

Judges: Myers

Filed Date: 4/11/2018

Precedential Status: Precedential

Modified Date: 1/12/2023