Blue Mountain Alliance v. Energy Facility Siting , 353 Or. 465 ( 2013 )


Menu:
  • No. 18	                    April 18, 2013	465
    IN THE SUPREME COURT OF THE
    STATE OF OREGON
    In the Matter of the Request for Amendment #2
    of the Site Certificate for the Helix Wind Power Facility.
    THE BLUE MOUNTAIN ALLIANCE;
    Norm Kralman; Richard Jolly;
    Dave Price; Robin Severe;
    and Cindy Severe,
    Petitioners,
    v.
    ENERGY FACILITY SITING COUNCIL;
    and Site Certificate Holder Helix Windpower Facility, LLC,
    Respondents.
    (S060803)
    En Banc
    On judicial review from an order of the Energy Facility
    Siting Council.*
    Argued and submitted January 7, 2013.
    Daniel Kearns, Reeve Kearns PC, Portland, argued the
    cause and filed the brief for petitioners.
    Michael Casper, Assistant Attorney General, Salem,
    argued the cause for respondent Energy Facility Siting
    Council. Denise G. Fjordbeck, Attorney-in-Charge, Salem,
    filed the brief for respondent Energy Facility Siting Council.
    With her on the brief were Ellen F. Rosenblum, Attorney
    General, and Anna M. Joyce, Solicitor General.
    James N. Westwood, Stoel Rives LLP, Portland, filed the
    brief for respondent Helix Wind Power Facility LLP. With
    him on the brief were David E. Filippi and Elaine R. Albrich.
    Dina M. Dubson, Renewable Northwest Project, Portland,
    filed the brief for amici curiae Renewable Northwest Project
    and American Wind Energy Association. With her on the
    brief was Megan W. Decker.
    ______________
    * Appeal from a Final Order of the Energy Facility Siting Council dated
    August 24, 2012, W. Bryan Wolfe, Chair.
    466	           Blue Mountain Alliance v. Energy Facility Siting
    BALDWIN, J.
    The Final Order Denying a Contested Case Proceeding
    and Approving Amendment #2 of the Energy Facility Siting
    Council is affirmed.
    Energy facility site certificate holder applied for Amendment #2 to existing
    site certificate, seeking to extend the construction start and completion dates
    for a wind energy facility. Petitioners provided public comment requesting that
    Amendment #2 require compliance with a county ordinance adopted after the
    amendment application date, which required a two-mile setback between wind
    turbines and rural residences. The Energy Facility Siting Council issued a final
    order that declined to require compliance with the ordinance, denied petitioners’
    requests for a contested case proceeding, and approved the amendment. Held: (1)
    the council correctly characterized the ordinance as a land use regulation subject
    to consideration under ORS 469.504(1)(b)(A) and properly declined to consider
    the ordinance under that statute because it was not in effect on the Amendment
    #2 application date; (2) because the ordinance qualified as a land use regulation
    under ORS 469.504(1)(b)(A), the council correctly declined to require compliance
    with the ordinance under the “abide by local ordinances” clause of ORS 469.401(2);
    (3) the council did not abuse its discretion in declining to require compliance with
    the ordinance as a later-adopted law under ORS 469.401(2); and (4) the council did
    not err in denying petitioners requests for a contested case proceeding.
    The Final Order Denying a Contested Case Proceeding and Approving
    Amendment #2 of the Energy Facility Siting Council is affirmed.
    Cite as 353 Or 465 (2013)	467
    BALDWIN, J.
    This case challenges a final order of the Energy
    Facility Siting Council (council) approving an amended
    site certificate for construction of a wind energy facility.1
    The central question on review is whether, in approving
    the amended site certificate, the council correctly declined
    to require compliance with a recently adopted county
    ordinance requiring a two-mile setback between wind
    turbines and rural residences pursuant to ORS 469.401(2).
    For the reasons set out in this opinion, we conclude that
    the council did not err in not requiring compliance with
    the ordinance. We further conclude that the council did not
    err in denying petitioners’ requests for a contested case
    proceeding. We therefore affirm the council’s final order
    approving the amended site certificate.
    I.  FACTS AND BACKGROUND
    The following facts are taken from the council’s
    Final Order Denying a Contested Case Proceeding and
    Approving Amendment #2. In July 2009, the council issued a
    site certificate for the Helix Wind Power Facility, permitting
    up to 60 wind turbines covering 7,586 acres on private
    land in Umatilla County, northwest of Helix, Oregon. The
    site certificate holder is Helix Wind Power Facility LLC
    (Helix), also a respondent in this proceeding. The certificate
    included conditions to begin construction within three
    years and then complete construction within three years.
    The statutory process under which the council issued the
    original site certificate is generally described in Save Our
    Rural Oregon v. Energy Facility Siting, 339 Or 353, 356-57,
    121 P3d 1141 (2005). In June 2011, the council issued a final
    order approving Amendment #1, expanding the size of the
    facility to include 134 turbines, covering 20,613 acres.
    On February 3, 2012, Helix applied for Amendment
    #2, seeking to extend the construction start and completion
    dates by two years. In response, the Oregon Department
    of Energy (ODOE) posted public notice of the amendment
    1
    ORS 469.403(3) grants this court jurisdiction for judicial review of the
    council’s approval or rejection of a site certificate application or amendment; ORS
    469.405(1) additionally provides that judicial review of an amended site certificate
    shall be as provided in ORS 469.403.
    468	          Blue Mountain Alliance v. Energy Facility Siting
    request and sent notice to various other persons and entities,
    including a list of residential owners within two miles of
    the site boundary and a special advisory group consisting of
    the Umatilla County Board of Commissioners (board). The
    council received multiple comments, and Helix responded
    to those comments. Following internal analysis, ODOE
    issued a proposed order, together with public notice setting
    a deadline for public comments and requests for a contested
    case proceeding.
    In May 2012, the council held a listening session
    and received public comments. The council also received
    multiple written public comments and several requests for
    a contested case proceeding. Among other issues, public
    testimony and comments highlighted a Umatilla County
    ordinance—Ordinance 2012-04, adopted February 28,
    2012—that required a two-mile setback between wind
    turbines and rural residences. Petitioners contended that
    the ordinance had been adopted as a public health and
    safety measure and submitted materials intended to show
    that noise implications from turbines posed a “significant
    threat” to public health and safety and that a setback of
    less than two miles would not adequately protect against
    turbine noise. Petitioners requested that the council require
    the facility to comply with the ordinance.2
    In August 2012, ODOE staff presented a
    recommendation on Amendment #2 to the council (“ODOE
    staff report” or “report”). ODOE staff recommended that the
    council not incorporate Ordinance 2012-04 in its analysis
    whether the facility, with Amendment #2, complied with
    statewide planning goals under ORS 469.504(1) and also
    not require compliance with the ordinance in Amendment
    #2 under ORS 469.401(2). The report specifically treated
    Ordinance 2012-04 as a “land use regulation[  to be
    ]”
    2
    In 2011, the county had adopted a similar ordinance, which was appealed
    to the Land Use Board of Appeals (LUBA). LUBA remanded, and the county
    then updated the wording consistently with LUBA’s decision and adopted it as
    Ordinance 2012-04 in February 2012. Later in this opinion, we discuss the specific
    provisions of the original version of Ordinance 2012-04 and a revised, codified
    version dated August 16, 2012. For ease of reference throughout this opinion, we
    refer to “Ordinance 2012-04,” not to its codification.
    Cite as 353 Or 465 (2013)	469
    evaluated under ORS 469.504(1), instead of as a “public
    health and safety” measure to be evaluated under ORS
    469.401(2). The report additionally cited the council’s
    earlier approval of a smaller, 1/4-mile setback between wind
    turbines and residences in another, unrelated proceeding
    and an applicable noise-related “public health setback”
    with a distance that may exceed 1/4-mile, as adopted by the
    Oregon Department of Environmental Quality (ODEQ).3
    The report also observed that the council previously had
    determined that the facility complied with ODEQ noise
    regulations and that the time extension request did not
    implicate that finding. Finally, the report recommended
    that the council deny petitioners’ requests for a contested
    case proceeding under OAR 345-027-0070(7).
    On August 24, 2012, the council issued its final
    order approving Amendment #2 and incorporating the
    ODOE staff recommendations. Among other things, the
    final order (1) stated that the council had considered all
    public and reviewing agency comments and requests for a
    contested case proceeding; (2) determined that Ordinance
    2012-04 did not apply to the council’s determination
    whether the facility complied with statewide planning goals
    under ORS 469.504(1); (3) applied ODEQ noise control
    regulations as part of determining that the facility complied
    with administrative rules identified in the original project
    order; (4) adopted an ODOE staff recommendation to not
    require compliance with Ordinance 2012-04 under ORS
    469.401(2); (5) denied petitioners’ requests for a contested
    case proceeding because they had raised no significant
    issues of fact or law under OAR 345-027-0070(7); and
    (6) ultimately concluded that the facility complied with
    applicable siting statutes, council standards, and other
    applicable state statutes and administrative rules. The final
    order granted Helix’s time-extension request, subject to
    revisions set out in the order that are not at issue in this
    proceeding. Petitioners filed a petition for judicial review in
    this court. See ORS 469.405(1), ORS 469.403(3) (providing
    for such review).
    3
    See OAR 340-035-0035(1)(b)(B)(i) to (iii) (noise restrictions as to new
    industrial or commercial noise source generally and as to wind energy facilities).
    470	          Blue Mountain Alliance v. Energy Facility Siting
    II.  PARTIES’ ARGUMENTS
    To frame the parties’ arguments, we first set out the
    statutes at issue. In deciding whether to issue a site certificate
    or an amended site certificate, the council must make a
    series of determinations as to whether a preponderance of
    the evidence supports several conclusions. See ORS 469.503
    (so providing). One such determination is whether the
    facility complies with statewide planning goals under ORS
    469.503(4). ORS 469.504(1), in turn, establishes alternative
    means for the council to make that determination. See Save
    Our Rural Oregon, 339 Or at 366-69 (so explaining). The
    applicable alternative in this proceeding, set out in ORS
    469.504(1)(b)(A), provides:
    “(1)  A proposed facility shall be found in compliance
    with the statewide planning goals under ORS 469.503(4) if:
    “* * * * *
    “(b)  The Energy Facility Siting Council determines
    that:
    “(A)  The facility complies with applicable substantive
    criteria from the affected local government’s acknowledged
    comprehensive plan and land use regulations that are
    required by the statewide planning goals and in effect on
    the date the application is submitted, and with any Land
    Conservation and Development Commission administrative
    rules and goals and any land use statutes that apply directly
    to the facility under ORS 197.646[.]”
    (Emphasis added.) That same analysis, including the
    “application submission date” requirement, applies to
    amended site certificates, OAR 345-027-0070(10). Thus,
    the statute and the administrative rule establish a “goal-
    post” rule for consideration of criteria derived from the local
    government’s comprehensive plan and land use regulations
    in relation to compliance with statewide planning goals.
    That “goal-post” rule is based on the application date of
    the facility site certificate or an amended site certificate.
    Here, Ordinance 2012-04 was adopted 25 days after the
    Amendment #2 application date.
    Cite as 353 Or 465 (2013)	471
    The other statute at issue, ORS 469.401(2), sets out
    the required contents for a site certificate or an amended
    site certificate, once the council decides to issue it. That
    statute provides, in part:
    “The site certificate or amended site certificate shall
    contain conditions for the protection of the public health
    and safety, for the time for completion of construction, and
    to ensure compliance with the standards, statutes and rules
    described in ORS 469.501 and 469.503. The site certificate
    or amended site certificate shall require both parties to
    abide by local ordinances and state law and the rules of the
    council in effect on the date the site certificate or amended
    site certificate is executed, except that upon a clear showing
    of a significant threat to the public health, safety or the
    environment that requires application of later-adopted
    laws or rules, the council may require compliance with such
    later-adopted laws or rules.”
    (Emphasis added.) Under that statute, the council must
    require compliance with certain “local ordinances and
    state law and [council] rules” in effect on the date that
    the certificate is executed, and the council may require
    compliance with “later-adopted laws or rules” upon a clear
    showing of a “significant threat to the public health, safety
    or the environment” that requires application of the later-
    adopted law or rule. Here, Ordinance 2012-04 was adopted
    about six months before the council issued its final order
    approving Amendment #2; the amended site certificate
    has not yet been executed, pending this judicial review
    proceeding.
    The parties’ dispute requires that we construe
    the second statute, ORS 469.401(2)—specifically the two
    independent clauses in the second sentence4—and determine
    whether the council erred in not requiring compliance
    with Ordinance 2012-04 in Amendment #2. Petitioners
    contend that, notwithstanding ORS 469.504(1)(b)(A),
    Ordinance 2012-04 qualifies as a noise ordinance, bringing
    4
    For ease of reference in this opinion, we refer to the first clause of the second
    sentence of ORS 469.401(2) as the “abide by local ordinances” clause and to the
    second clause as the “later-adopted laws” clause.
    472	       Blue Mountain Alliance v. Energy Facility Siting
    it within the “public health and safety” concepts generally
    set out in ORS 469.401(2). Petitioners specifically argue
    that Ordinance 2012-04 falls within the scope of the “abide
    by local ordinances” clause and that the council therefore
    erred when it did not require compliance with the ordinance
    in Amendment #2. Alternatively, petitioners argue that
    Ordinance 2012-04 falls within the scope of the “later-adopted
    laws” clause, petitioners satisfied the “significant threat”
    threshold, and the council should have required compliance
    with the ordinance in the exercise of its discretion. Finally,
    petitioners contend that the council erred in denying their
    requests for a contested case proceeding, regarding the
    opportunity to demonstrate that the ordinance qualified
    as a public health and safety measure and that a setback
    of less than two miles posed a significant threat to public
    health and safety.
    The council and Helix instead begin the analysis
    with ORS 469.504(1)(b)(A), contending that Ordinance 2012-
    04 is a “land use regulation[  under that statute. Because
    ]”
    Ordinance 2012-04 was adopted after the Amendment
    #2 application date, the council and Helix assert that the
    council correctly concluded that the ordinance did not
    apply to the council’s evaluation of applicable substantive
    criteria under ORS 469.504(1)(b)(A), in determining facility
    compliance with statewide planning goals. Next, the council
    and Helix contend that any ordinance that qualifies as a
    “land use regulation[  under ORS 469.504(1)(b)(A) cannot
    ]”
    also be considered an ordinance to which the “abide by
    local ordinances” clause of ORS 469.401(2) applies. Helix
    adds that, if ORS 469.401(2) were construed to require
    Helix to comply with an ordinance that qualifies as a land
    use regulation that became effective after the application
    date, that result would conflict with ORS 469.504(1)(b)(A),
    which only requires consideration of land use regulations
    in effect as of the application date. The council and Helix
    further contend that the council did not err in declining to
    require compliance with Ordinance 2012-04 in Amendment
    #2 under the “later-adopted laws” clause of ORS 469.401(2)
    or in denying petitioners’ requests for a contested case
    proceeding.
    Cite as 353 Or 465 (2013)	473
    II.  FIRST ASSIGNMENT OF ERROR:
    ORS 469.401(2)—REQUIRED COMPLIANCE
    WITH LOCAL ORDINANCES IN EFFECT
    ON SITE CERTIFICATE EXECUTION DATE
    A.  Construction of “Abide by Local Ordinances” Clause of
    ORS 469.401(2)
    Before construing ORS 469.401(2), it is important
    to explain the operation of ORS 469.504(1)(b)(A). Again,
    that statute provides as follows:
    “(1)  A proposed facility shall be found in compliance
    with the statewide planning goals under ORS 469.503(4) if:
    “* * * * *
    “(b)  The Energy Facility Siting Council determines
    that:
    “(A)  The facility complies with applicable substantive
    criteria from the affected local government’s acknowledged
    comprehensive plan and land use regulations that are
    required by the statewide planning goals and in effect on
    the date the application is submitted, and with any Land
    Conservation and Development Commission administrative
    rules and goals and any land use statutes that apply directly
    to the facility under ORS 197.646[.]”
    (Emphasis added.) As noted earlier, the same process applies
    to amended site certificates, OAR 345-027-0070(10). In Save
    Our Rural Oregon, 339 Or at 361, this court explained the
    underlying purpose of ORS 469.504:
    “Oregon’s statewide land use planning goals, adopted
    by the Land Conservation and Development Commission
    (LCDC), set out broad objectives for land use planning in
    Oregon. Local governments implement those objectives in
    local comprehensive plans. ORS 197.225 to 197.250. ORS
    469.503(4) provides that the council may not issue a site
    certificate approving [a site certificate application] unless
    the proposed facility complies with the statewide planning
    goals. ORS 469.504, in turn, provides the guidelines for
    determining whether the [site certificate application]
    complies with those goals.”
    Under the first part of ORS 469.504(1)(b)(A), the
    council must determine that the facility complies with
    474	         Blue Mountain Alliance v. Energy Facility Siting
    substantive criteria—derived from the local government’s
    “acknowledged comprehensive plan and land use
    regulations”—that are (1) required by statewide planning
    goals; and (2) “in effect” on the certificate or amendment
    application date. In its final order, the council determined
    that the two-mile setback embodied in Ordinance 2012-
    04 was a “land use regulation[  that should be evaluated
    ]”
    under the “applicable substantive criteria” provision of ORS
    469.504(1)(b)(A). However, the council further determined
    that the ordinance was not “in effect” on the Amendment #2
    application date and therefore should not be included in the
    “applicable substantive criteria” used to determine whether
    the facility complied with the statewide planning goals.
    We agree with the council and Helix that the council was
    not required to consider the ordinance in its determination
    whether the facility complied with statewide planning goals
    because the ordinance was not “in effect” on the Amendment
    #2 application date. Petitioners do not appear to dispute that
    conclusion; instead, they principally rely on ORS 469.401(2),
    to which we now turn.
    Again, ORS 469.401(2) provides, in part:
    “The site certificate or amended site certificate shall
    contain conditions for the protection of the public health
    and safety, for the time for completion of construction,
    and to ensure compliance with the standards, statutes
    and rules described in ORS 469.501 and 469.503. The site
    certificate or amended site certificate shall require both
    parties to abide by local ordinances and state law and the
    rules of the council in effect on the date the site certificate or
    amended site certificate is executed, except that upon a clear
    showing of a significant threat to the public health, safety or
    the environment that requires application of later-adopted
    laws or rules, the council may require compliance with such
    later-adopted laws or rules.”
    (Emphasis added.) As noted earlier, petitioners rely on both
    clauses in the second sentence. Under the “abide by local
    ordinances” clause, they emphasize that Ordinance 2012-04
    is a local ordinance that was “in effect” on the Amendment
    #2 execution date and the council therefore erred in not
    requiring compliance with that ordinance; alternatively,
    under the “later-adopted laws” clause, the ordinance should
    Cite as 353 Or 465 (2013)	475
    be considered a “later-adopted law[  and the council, in
    ]”
    its discretion, should have required compliance with the
    ordinance.
    We review for error of law. See ORS 183.482(8)(a)
    (court must determine whether agency “has erroneously
    interpreted a provision of law”); ORS 469.403(6) (ORS
    183.482 applies to petition for judicial review of council’s
    approval or rejection of site certificate or amended site
    certificate application); see also Save Our Rural Oregon,
    339 Or at 360 (identifying statutory construction question
    as legal issue). To address petitioners’ contentions, we
    employ our method of statutory construction set out in
    State v. Gaines, 346 Or 160, 171-72, 206 P3d 1042 (2009), to
    ascertain the legislature’s intent. See also State v. Klein, 352
    Or 302, 309, 283 P3d 350 (2012) (when construing statutes,
    court reviews statutory text and context, including related
    statutes).
    We begin with the text of the “abide by local
    ordinances” clause of ORS 469.401(2), which provides:
    “The site certificate or amended site certificate shall
    require both parties to abide by local ordinances and state
    law and the rules of the council in effect on the date the site
    certificate or amended site certificate is executed[.]”
    That clause contains a timing trigger for requiring party
    compliance with local ordinances, state laws, and council
    rules: the site certificate must require compliance with
    ordinances “in effect” on the certificate execution date
    (with exceptions identified in the “later-adopted laws”
    clause), and Ordinance 2012-04 is presently “in effect”
    within that statutory meaning. See ORS 469.401(1) (after
    council approves site certificate or amended site certificate,
    council chairperson and applicant shall execute certificate
    with prescribed conditions; here, the site certificate with
    Amendment #2 has not yet executed, pending this judicial
    review proceeding). What is less clear, however, is the
    intended scope of the unmodified phrase, “local ordinances
    and state law and the rules of the council.” That is, although
    petitioners infer that the clause refers to ordinances, laws,
    and rules that pertain to “public health and safety” in effect
    on the execution date—and although other parts of the
    476	       Blue Mountain Alliance v. Energy Facility Siting
    statute also use those same modifying words—the clause
    contains no wording to that effect. The council and Helix
    do not dispute that the phrase “local ordinances” in the
    clause may include ordinances relating to public health and
    safety; they contend, however, that any “local ordinance”
    that is a “land use regulation[ ]” under ORS 469.504(1)(b)(A)
    is excluded from the intended scope of the “abide by local
    ordinances” clause. Simply stated, although the clause
    appears unambiguous on its face, the parties point to
    contextual clues to support their conflicting constructions.
    We first agree with the parties that, in referring
    to “local ordinances,” the legislature intended the “abide
    by local ordinances” clause of ORS 469.401(2) to generally
    extend to local ordinances that serve to protect public health
    and safety. By way of context, the next clause of that same
    sentence—which is more narrowly drawn than the first—
    provides a “later-adopted” exception for “laws or rules” that
    pose a significant threat “to the public health, safety,” or the
    environment. By setting out a subcategory of significant
    threat “to the public health [or] safety” that may justify
    application of “later-adopted” laws or rules, contrasted
    against laws or rules “in effect” on the certificate execution
    date, the “later-adopted laws” clause textually presumes
    that the preceding “abide by local ordinances” clause also
    extends to local ordinances, state law, and council rules that
    serve to protect public health and safety. A related statute,
    ORS 469.310, supports that construction, affirmatively
    stating as public policy that “the siting, construction and
    operation of energy facilities shall be accomplished in a
    manner consistent with protection of the public health and
    safety,” among other considerations. That is not to say that
    the phrase “abide by local ordinances and state law and the
    rules of the council” in ORS 469.401(2) is limited to local
    ordinances, state laws, and council rules that protect public
    health and safety; the context indisputably shows, however,
    that the legislature intended the scope of that phrase to
    extend to ordinances that protect public health and safety.
    Having construed the “abide by local ordinances”
    clause of ORS 469.401(2) as including—but not necessarily
    limited to—local ordinances, state laws, and council rules
    Cite as 353 Or 465 (2013)	477
    that protect public health and safety, we turn to other
    parts of ORS chapter 469 to assist our understanding of
    the scope of the term “local ordinances” in that clause. As
    explained below, several chapter components describing the
    site certificate application and approval process clarify the
    legislature’s intended meaning of that term as pertinent to
    our inquiry.
    As to the initial site certificate application process,
    ORS 469.330(1) requires an applicant to submit to the
    council a notice of intent to file a site certificate application.
    Following review of the notice and a public comment
    period, ODOE must issue a project order that establishes
    the “statutes, administrative rules, council standards,
    local ordinances, application requirements and study
    requirements for the site certificate application.” ORS
    469.330(3) (emphasis added). After the applicant files the
    initial site certificate application and at the conclusion of a
    mandatory contested case proceeding, the council must issue
    a final order approving or rejecting the application. ORS
    469.370(7). Under that statute, the council must base its
    approval on identified, council-adopted standards adopted
    under ORS 469.501 “and any additional statutes, rules or
    local ordinances determined to be applicable to the facility
    by the project order, as amended.” (Emphasis added.) See
    also generally ORS 469.503(3) (before issuing certificate,
    council must determine whether facility complies with state
    statutes and administrative rules identified in project order
    as applicable to site certificate issuance).
    Thus, the statutory scheme establishes that the
    process of drafting a project order and issuing a final
    order approving the site certificate application involves
    determining the “local ordinances” (and other provisions)
    that apply to the facility and with which an applicant must
    comply to obtain approval of its application. As part of that
    construct, ORS 469.401(2) logically is intended to require
    in the site certificate that the applicant comply with those
    same ordinances. Stated differently, given the statutory
    scheme, the reference in ORS 469.401(2) to “local ordinances
    and state law and the rules of the council in effect” on the
    certificate execution date logically refers to the ordinances,
    state law, and council rules that previously were determined
    478	       Blue Mountain Alliance v. Energy Facility Siting
    to apply to the facility in the course of developing the project
    order under ORS 469.330(3). See also ORS 469.401(2)
    (first sentence; site certificate must contain conditions to
    “ensure compliance with” statutes and rules described in
    ORS 469.503). Additionally, the phrase includes applicable
    ordinances, laws, and rules that may have become effective
    between the project order issuance date and the site
    certificate execution date—that is, provisions that, had they
    been in effect at the time that the project order issued, would
    have been included in that order under ORS 469.330(3). As
    previously discussed, those local ordinances, state laws, and
    rules may include—but are not limited to—public health
    and safety protections.
    The council and Helix urge that ORS 469.504(1)(b)(A)
    provides necessary context for the proper construction of
    the “abide by local ordinances” clause of ORS 469.401(2)—
    specifically, the intended scope of any local ordinance subject
    to a compliance requirement in the site certificate. As
    discussed earlier, ORS 469.504(1)(b)(A) refers to applicable
    substantive criteria—derived from the local government’s
    acknowledged comprehensive plan and “land use
    regulations” (emphasis added) in effect on the application
    date—that the council must consider in determining
    whether a facility complies with statewide planning goals.
    Essentially, the council and Helix argue that, because all
    applicable “land use regulations” fall within the scope of
    the council’s determination of goal compliance under ORS
    469.504(1)(b)(A), they cannot simultaneously fall within
    the scope of the “abide by local ordinances” clause of ORS
    469.401(2), relating to certificate requirements. That is, the
    council’s consideration of applicable “land use regulations”
    occurs at the point in time when the council determines
    whether a facility complies with statewide planning goals.
    By contrast, the council’s consideration of other, nonland use
    laws, rules, and ordinances extends to other points in the
    siting process. The legislature intended the two concepts to
    remain separate, the council and Helix argue, in large part
    because of their different “trigger” dates—the application
    date in ORS 469.504(1)(b)(A) for land use regulations, and
    the certificate execution date in ORS 469.401(2) for other
    local ordinances, state laws and council rules. Otherwise,
    Cite as 353 Or 465 (2013)	479
    the council could require compliance in a site certificate
    with a local “land use regulation[ ]” that was not in effect on
    the application date and that the council therefore had been
    precluded from considering for statewide planning goal
    compliance purposes under ORS 469.504(1)(b)(A).
    We have explained that ORS 469.504(1)(b)(A)
    and ORS 469.401(2) serve different purposes and apply at
    different stages of the site certificate application process,
    which arguably undercuts the council’s and Helix’s contention
    that the statutes must operate in harmony, particularly as to
    their trigger dates. At the same time, however, those varying
    purposes and applications provide some helpful statutory
    context. Notably, ORS 469.504(1)(b)(A) applies to the central
    determination whether an application for a site certificate
    or amendment should be approved or rejected. Only after
    the council has decided to approve the application does it
    determine the required contents of the certificate under
    ORS 469.401(2). The subordinate nature of the council’s
    determination of certificate contents under ORS 469.401(2),
    in relation to its central determination of application
    approval under ORS 469.504(1)(b)(A), suggests that the
    legislature intended ORS 469.401(2) to operate consistently
    with—and not to circumvent—ORS 469.504(1)(b)(A).
    See generally Davis v. Wasco IED, 286 Or 261, 272, 593 P2d
    1152 (1979) (“whenever possible the court should construe
    together statutes on the same subject as consistent with
    and in harmony with each other”). That, in turn, supports
    the council’s and Helix’s contention that the “abide by local
    ordinances”clause in ORS 469.401(2) excludes ordinances that
    qualify as “land use regulations” under ORS 469.504(1)(b)(A).
    Another part of ORS chapter 469 further supports
    that construction of ORS 469.401(2). ORS 469.503 requires
    that, in determining whether to issue a site certificate, the
    council must make a number of determinations about the
    facility. One such determination, as previously discussed, is
    whether the facility complies with statewide planning goals,
    ORS 469.503(4), pursuant to the alternative means provided
    in ORS 469.504(1). Another compliance determination is set
    out in subsection (3) of ORS 469.503, as follows:
    480	          Blue Mountain Alliance v. Energy Facility Siting
    “In order to issue a site certificate, the *  * [c]ouncil
    *
    shall determine that the preponderance of the evidence on
    the record supports the following conclusions:
    “* * * * *
    “(3)     Except as provided in ORS 469.504 for land use
    compliance * * *, the facility complies with all other Oregon
    statutes and administrative rules identified in the project
    order, as amended, as applicable to the issuance of a site
    certificate for the proposed facility. * * *”
    (Emphasis added.) That statute requires the council to
    determine that the facility complies with state statutes
    and rules previously determined to apply to the facility
    and therefore identified in the project order under ORS
    469.330(3). As previously discussed, the reference in the
    “abide by local ordinances” clause of ORS 469.401(2) to
    “local ordinances and state law and the rules of the council”
    in effect on the certificate execution date means those
    provisions previously identified in the project order under
    ORS 469.330(3), together with other applicable provisions
    that may have become effective between the project order
    issuance and certificate execution dates. That is, the same
    state statutes and rules identified in the project order
    under ORS 469.330(3) and therefore subject to certificate
    compliance requirements in ORS 469.401(2) also are
    subject to a facility compliance determination under ORS
    469.503(3).
    Significantly, in setting out that compliance
    determination requirement, ORS 469.503(3) expressly
    distinguishes state statutes and rules that pertain to “land
    use compliance” based on the application date under ORS
    469.504 from “all other Oregon statutes and administrative
    rules” previously identified in the project order. (Emphasis
    added.) Indeed, ORS 469.503(3) characterizes ORS 469.504—
    the statute that requires a compliance determination as to
    statewide planning goals that may include evaluation of
    the local government’s comprehensive plan and “land use
    regulations”—as a “land use compliance” statute. That
    characterization demonstrates a legislative intention that
    Cite as 353 Or 465 (2013)	481
    the council evaluate a provision of law or rule that qualifies
    as a “land use regulation[  only under ORS 469.504(1), as
    ]”
    part of the council’s statewide planning goal determination
    under ORS 469.503(4).5 By contrast, the legislature
    identified a separate category of “other” applicable provisions
    “identified in the project order” under ORS 469.330(3) that
    must be part of a separate compliance determination under
    ORS 469.503(3). And, as previously noted, the “abide by
    local ordinances” clause of ORS 469.401(2) in turn provides
    a mechanism for requiring compliance with such provisions
    (and similar provisions adopted after the project order but
    before execution of the site certificate) in the site certificate.6
    No aspect of the statutory context supports petitioners’
    competing construction.
    In light of the statutory context, we conclude that
    the requirement in ORS 469.401(2) that a site certificate
    or amended site certificate must require compliance with
    “local ordinances and state law and the rules of the council
    in effect on the date the site certificate or amended site
    certificate is executed” does not include any ordinance, law,
    or rule that is a “land use regulation[ ]”for purposes of ORS
    469.504(1)(b)(A).
    5
    In Save Our Rural Oregon v. Energy Facility Siting, 339 Or 353, 368, 121
    P3d 1141 (2005), this court explained that “the statewide land use planning goals
    establish broad policy objectives, while the applicable substantive criteria provide
    specific ways of implementing those objectives through local regulation.” (Internal
    quotations omitted.) Those “applicable substantive criteria,” in turn, are derived
    from the affected local government’s acknowledged comprehensive plan and land
    use regulations, ORS 469.504(1)(b).
    6
    We recognize that, in contrasting a “land use compliance” determination
    under ORS 469.504 against “other” facility compliance determinations, ORS
    469.503(3) does not refer to any “local ordinance” determined in the project order
    to apply to the facility. Compare ORS 469.330(3) (project order must establish “the
    statutes, administrative rules, council standards, local ordinances, application
    requirements and study requirements for the site certificate application” (emphasis
    added)); ORS 469.370(7) (council determination whether to issue final order must
    be based on standards adopted under ORS 469.501 “and any additional statutes,
    rules or local ordinances determined to be applicable to the facility by the project
    order, as amended” (emphasis added); ORS 469.401(2) (certificate must require
    compliance with “local ordinances and state law and the rules of the council”
    (emphasis added)). That lack of reference to local ordinances in ORS 469.503(3),
    however, does not diminish the import of that statute’s characterization of ORS
    469.504 as a “land use compliance” statute—as opposed to a category of “other,”
    nonland use statutes, rules, and ordinances—for purposes of our analysis.
    482	       Blue Mountain Alliance v. Energy Facility Siting
    B.  Ordinance 2012-04—“Land Use Regulation[ ]” or “Public
    Health and Safety” Ordinance
    We turn to whether the council properly
    characterized the two-mile setback contained in Ordinance
    2012-04 as a “land use regulation[  subject to analysis
    ]”
    under ORS 469.504(1)(b)(A) or whether it should have
    treated the ordinance as a nonland use ordinance requiring
    compliance under the “abide by local ordinances” clause
    of ORS 469.401(2). We review the council’s determination
    for any error of law. See Rubalcaba v. Nagaki Farms, Inc.,
    333 Or 614, 619, 43 P3d 1106 (2002) (agency determination
    whether subject of applicable legal standard qualifies under
    that standard is conclusion of law, not finding of fact); Woody
    v. Waibel, 276 Or 189, 192 n 3, 554 P2d 492 (1976) (same;
    distinguishing when assessing question of law may involve
    predicate question of fact).
    Ordinance 2012-04 was adopted as an amendment
    to the Umatilla County Code of Ordinances, as a new
    provision in the Development Code (UCDC, chapters 150-
    153 of the Umatilla County Code of Ordinances), UCDC
    section 152.616(HHH)(6)(a). That ordinance, as adopted on
    February 28, 2012, provided:
    “§ 152.616  STANDARDS FOR REVIEW OF CONDI-
    TIONAL USES AND LAND USE DECISIONS.
    “(HHH) Commercial Wind Power Generation Facility.
    “(6)  Standards/Criteria of Approval The following
    requirements and restrictions apply to the siting of a Wind
    Power Generation Facility:
    “[(a)]  Setbacks. The minimum setback shall be a
    distance of not less than the following:
    “(1)  From a turbine tower to a city urban growth
    boundary (UGB) shall be two miles. The measurement of
    the setback is from the centerline of a turbine tower to the
    edge of the UGB that was adopted by the city as of the date
    the application was deemed complete.
    “(2)  From a turbine tower to land zoned Unincorporated
    Community (UC) shall be 1 mile.
    Cite as 353 Or 465 (2013)	483
    “(3)  From a turbine tower to a rural residence shall
    be 2 miles. For purposes of this section, a ‘rural residence’
    is defined as a legal, conforming dwelling existing on the
    parcel at the time an application is deemed complete. The
    measurement of the setback is from the centerline of the
    turbine tower to the centerpoint of the residence.”
    See Ordinance No 2012-04, http://www.co.umatilla.or.us/
    planning/ordinances/Ordinance _2012-04.pdf (last accessed
    Apr 9, 2013) (italics in original). A revised version of the
    UCDC dated August 16, 2012—eight days before the council
    issued the final order at issue in this case—contains an
    expanded version of Ordinance 2012-04, still codified as
    UCDC section 152.616(HHH)(6)(a).7 The expanded version
    includes the provisions set out above, with revised and
    additional text in subsection (6)(a)(3) that does not affect
    our analysis here. The revised version contains additional
    subsections to section (6)(a) that provide, in part:
    “(4)  A Wind Power Generation Facility applicant may
    apply for and receive an adjustment for a reduced distance
    between a turbine tower and a rural residence under the
    following approval criteria. The adjustment application
    shall be submitted on a form provided by the County and
    signed by the rural residence landowner.
    “(i)  The adjustment will not significantly detract from
    the livability of the subject rural residence. This standard is
    satisfied if applicable [O]DEQ noise standards are satisfied,
    there is no significant adverse impact to property access and
    traffic conditions, and other evidence demonstrates that the
    residence remains suitable for peaceful enjoyment or, such
    impacts to the livability of the rural residence resulting from
    the adjustment are mitigated to the extent practical; and
    “(ii) All other requirements of the Wind Power
    Generation Facility application remain satisfied.
    “(5)  An adjustment application under this section
    shall be processed as a Land Use Decision concurrently
    7
    We take judicial notice of the undisputed contents of the revised version
    of Ordinance 2012-04 dated August 16, 2012, as well as other aspects of the
    Code of Umatilla County. Only the original version of Ordinance 2012-04 and an
    interim, revised version dated March 13, 2012, are contained in the record of this
    proceeding.
    484	          Blue Mountain Alliance v. Energy Facility Siting
    with the Wind Power Generation Facility application. For
    applications subject to Energy Facility Siting Council *  *
    *
    jurisdiction, an adjustment application shall be included
    as the applicable substantive criteria evaluated by [the
    council] when granting or denying an application for a Site
    Certificate.
    “* * * * *
    “(9)  The turbine/towers shall be of a size and design
    to help reduce noise or other detrimental effects. At a
    minimum, the Wind Power Generation Facility shall be
    designed and operated within the limits of noise standard(s)
    established by the State of Oregon. A credible noise study
    may be required to verify that noise impacts in all wind
    directions are in compliance with the State noise standard.”
    See http://www.co.umatilla.or.us/planning/pdf/Umatilla_
    County_Development_Code.pdf, 310-11 (last accessed
    Apr 9, 2013) (emphases added).
    In text and context, Ordinance 2012-04 bears the
    characteristics of a “land use regulation[  consistently
    ],”
    with the legislature’s use of that term in ORS 469.504(1)
    (b)(A). The ordinance was adopted as an amendment
    to the county’s Development Code, maintained by the
    county’s Department of Land Use Planning. As written,
    the ordinance operates as a “siting” restriction. Revised
    subsection (6)(a)(4) permits a setback of less than two miles
    if approved through an adjustment application process;
    significantly, revised subsection (6)(a)(5) provides that such
    an adjustment application shall be processed as a “Land
    Use Decision” and that such applications “shall be included
    as the applicable substantive criteria” that the council
    evaluates in determining whether the facility complies
    with statewide planning goals under ORS 469.504(1). By
    contrast, subsection (6)(a)(4)(i) designates ODEQ noise
    regulations as providing applicable “noise standards” by
    which to measure an approved adjustment application, and
    subsection (6)(a)(9) establishes a “minimum” noise standard
    for wind energy facilities consistently with statewide noise
    standards—that is, those adopted by ODEQ. Ordinance
    2012-04 does not itself establish any noise standard that
    may justify treating the ordinance as a “public health and
    Cite as 353 Or 465 (2013)	485
    safety” measure, as opposed to a “land use regulation[  8
    ].”
    In sum, the foregoing evaluation supports the council’s
    conclusion that the ordinance is a “land use regulation[ ]”
    for purposes of ORS 469.504(1)(b)(A).
    In arguing to the contrary, petitioners rely, in part,
    on the “purpose” statement in Chapter 152 of the UCDC,
    which expressly refers to the promotion of public health
    and safety. That statement, codified as UCDC § 152.002,
    provides:
    “The intent of purpose of this chapter is to promote the
    public health, safety and general welfare and to carry out
    the County Comprehensive Plan, the provisions of ORS
    Chapters 92 and 215 and the Statewide Planning Goals
    adopted pursuant to ORS Chapter 197. This chapter is
    to establish use zones and regulations governing the
    development and use of land within portions of the county;
    to provide regulations governing non-conforming uses
    and structures; to establish and provide for the collection
    of fees; to provide to the administration of this chapter
    and for the officials whose duty it shall be to enforce the
    provisions thereof; to provide penalties for the violations of
    this chapter; to provide for conflicts with other ordinances
    or regulations; and provide classifications and uniform
    standards for the division of land and the installation of
    related improvements in portions of the unincorporated
    area of the county.”
    See http://www.co.umatilla.or.us/planning/pdf/Umatilla_
    County_Development_Code.pdf, 12 (last accessed Apr 9,
    2013). As can be seen, the statement identifies several
    purposes of chapter 152, not just the promotion of public
    health, safety, and general welfare—which, arguably, is an
    inextricable component of most land use regulations. Notably,
    the identified purposes include carrying out the county’s
    comprehensive plan, state law pertaining to subdivisions
    and partitions (ORS chapter 92), state law pertaining to
    county planning, zoning, and housing codes (ORS chapter
    215), and the statewide planning goals adopted pursuant to
    ORS chapter 197. Further, the statement primarily describes
    8
    Compare Code of Umatilla County, Chapter 96 (“Noise Control Ordinance,”
    Ordinance 99-07) (setting out, among other things, restrictions on noise levels), see
    http://www.co.umatilla.or.us/deptwebs/codes/96.pdf (last accessed Apr 9, 2013)).
    486	           Blue Mountain Alliance v. Energy Facility Siting
    the contents of Chapter 152 by using wording that can be
    characterized as relating to “land use” and not to “public
    health and safety.” Indeed, in its original final order approving
    the initial site certificate, the council drew the “applicable
    substantive criteria from the affected local government’s
    acknowledged comprehensive plan and land use regulations”
    under ORS 469.504(1)(b)(A) largely from various sections
    of UCDC Chapter 152. In short, the “purpose” statement
    cuts against petitioners’ contention that Ordinance 2012-04
    is a “public health and safety” measure subject to the
    “abide by local ordinances” clause of ORS 469.401(2),
    rather than a “land use regulation[  as the legislature
    ]”
    intended that term to apply in ORS 469.504(1)(b)(A).
    Petitioners are correct that one effect of Ordinance
    2012-04 may be a positive impact on public health and safety,
    given that an increased distance between wind turbines and
    rural residences potentially lessens any health or safety
    hazards that arguably may flow from turbine installation.
    The same could be said, however, for any number of land
    use restrictions—for example, a restriction that prohibits
    development in a flood plain may bear the characteristics of
    a “land use regulation[ ],” while at the same time having the
    effect of protecting public health and safety.9 The fact that
    such a restriction may operate to benefit public health and
    safety, however, does not diminish its qualification under
    the legislature’s express category of “land use regulations[ ]”
    for purposes of ORS chapter 469. That same logic applies
    to Ordinance 2012-04: As is clear from the text of the
    ordinance, the context of its adoption as part of the county’s
    Development Code, and the UCDC purpose statement, the
    ordinance qualifies—under the legislative category of “land
    use regulations” identified in ORS 469.504(1)(b)(A)—as
    9
    We also acknowledge that the legislature has determined, in other statutory
    contexts, that a “land use” regulation simultaneously may relate to “public
    health and safety.” See, e.g., ORS 197.723(5)(a) (statute establishing process for
    designating regionally significant industrial areas; one particular subsection does
    not apply to any “land use regulation that is necessary *  * [t]o protect public
    *
    health or safety”). Indeed, as noted earlier, ORS 469.310 requires that “the siting,
    construction and operation of energy facilities shall be accomplished in a manner
    consistent with protection of the public health and safety,” which demonstrates
    that the legislature intended that public health and safety considerations be part
    of the siting decision for an energy facility.
    Cite as 353 Or 465 (2013)	487
    a “land use regulation[  pertaining to the siting of wind
    ]”
    turbines.10
    C.  Council’s Application of ORS 469.504(1)(b(A) and
    “Abide by Local Ordinances” Clause of ORS 469.401(2)
    in its Final Order
    We turn to the council’s application of the statutes
    at issue in its final order approving Amendment #2. First,
    the council applied ORS 469.504(1)(b)(A) and determined
    that it was precluded from including Ordinance 12-04 as
    part of the “applicable substantive criteria” to consider in
    making a land-use compliance determination, because
    the ordinance was not “in effect” on the Amendment #2
    application date. As previously explained, we agree with the
    council that (1) Ordinance 2012-04 qualifies as a “land use
    regulation[  within the meaning of ORS 469.504(1)(b)(A);
    ]”
    and, (2) because the ordinance was not “in effect” on the
    Amendment #2 application date, it should not be considered
    as part of the substantive criteria assessment set out
    under that statute. The council did not err in applying ORS
    469.504(1)(b)(A) in that manner.
    Next, the council made a series of compliance
    determinations applying various public health and
    safety council-adopted standards, state statutes, and
    administrative rules to Amendment #2. For example, the
    council determined that, under ORS 469.503(1), the facility
    complied with council-adopted standards identified in ORS
    469.501, including standards for the design, construction,
    and operation of the wind turbines, to avoid endangering
    public safety and to include adequate safety devices and
    10
    Petitioners also cite Oregon statutes and administrative rules that pertain
    to noise regulations, specifically, ORS 467.010 (declared policy that state has
    interest in controlling noise emission pollution and that protection program should
    be initiated) and OAR 340-035-0005 (ODEQ rule; state public policy to provide
    coordinated statewide noise control program, to facilitate cooperation among
    state and local governmental units in that regard, and to develop progressive and
    cooperative noise-control program). In petitioners’ view, in linking noise prevention
    with public health, those provisions support construing Ordinance 2012-04 as
    a “public health and safety” ordinance subject to the “abide by local ordinances”
    clause of ORS 469.401(2). The existence of those express public policies, however,
    do not support characterizing Ordinance 2012-04—which, by its terms, was written
    and adopted as a land-use regulation and therefore subject to consideration under
    ORS 469.504(1)(b)(A)—as a public health and safety measure in the manner that
    petitioners contend.
    488	       Blue Mountain Alliance v. Energy Facility Siting
    testing procedures. The council noted in that regard
    that several related site certificate conditions, expressly
    included in the original final order approving the initial
    site certificate, were necessary to “ensure public safety.”
    See ORS 469.503(1) (before issuing site certificate, council
    must determine that preponderance of evidence supports
    conclusion that facility complies with council-adopted
    standards under ORS 469.501); ORS 469.501(1) (council
    shall adopt standards for energy facility siting, construction,
    operation, and retirement, including standards addressing
    structural, financial, environmental, and public health and
    safety concerns; council has adopted those standards as
    administrative rules); ORS 469.401(2) (site certificate shall
    contain conditions for, among other things, “protection of the
    public health and safety”). The council further determined
    under ORS 469.503(3) that the facility, with Amendment
    #2, would comply with “all other Oregon statutes and
    administrative rules identified in the project order,” including
    ODEQ noise regulations, subject to site certificate conditions
    already identified in the original final order. Then, as to the
    requirement in ORS 469.310 that the council ensure that
    the siting, construction, and operation of energy facilities “be
    accomplished in a manner consistent with protection of the
    public health and safety,” the council identified previously
    imposed “public health and safety” conditions addressing fire
    protection, magnetic fields, and coordination with the Public
    Utilities Commission regarding electrical transmission
    line design. As to all those described components, the
    council determined that nothing in Amendment #2 would
    alter the earlier compliance findings from its original
    final order approving the initial site certificate, so long as
    previously imposed conditions continued to apply. We set
    out the foregoing determinations—which petitioners do not
    dispute—as an illustration of the council’s assessment and
    application of various “public health and safety” standards,
    rules, and site certificate conditions to Amendment #2.
    We turn to the council’s application of the “abide
    by local ordinances” clause of ORS 469.401(2). The council
    expressly stated that “the site certificate holder is subject to
    all applicable conditions and requirements contained in the
    rules of the Council and in local ordinances and state law
    Cite as 353 Or 465 (2013)	489
    in effect on the date the amended site certificate is executed.”
    (Emphasis added.) In that part of its final order, the council
    did not mention Ordinance 2012-04; however, the council
    previously had considered and rejected application of the
    ordinance in determining whether the facility complied with
    statewide planning goals under ORS 469.504(1)(b)(A) and
    had incorporated an ODOE staff recommendation that it not
    apply the ordinance under the “abide by local ordinances”
    clause of ORS 469.401(2). As do the parties, we infer that
    the council concluded that the proper characterization
    of Ordinance 2012-04 as a “land-use regulation[  subject
    ]”
    to evaluation under ORS 469.504(1)(b)(A) precluded its
    application under the “abide by local ordinances” clause of
    ORS 469.401(2).
    In light of our statutory analysis and review of the
    council’s legal evaluation of Ordinance 2012-04, we conclude
    that the council did not err in its application of the “abide
    by local ordinances” clause of ORS 469.401(2). As discussed,
    the council correctly characterized Ordinance 2012-04 as
    a “land use regulation[  under ORS 469.504(1)(b)(A) and
    ]”
    correctly concluded that the effective date of the ordinance
    precluded its consideration under that statute. Because the
    council accurately characterized Ordinance 2012-04 as a
    “land use regulation[  it also correctly concluded that the
    ],”
    ordinance did not fall within the scope of the “abide by local
    ordinances” clause of ORS 469.401(2).
    IV.  SECOND ASSIGNMENT OF ERROR:
    ORS 469.401(2)—“LATER-ADOPTED” LAWS OR RULES
    We turn to petitioners’ second assignment of error,
    under the “later-adopted laws” clause of ORS 469.401(2),
    which provides:
    “The site certificate or amended site certificate shall
    require both parties to abide by local ordinances and state
    law and the rules of the council in effect on the date the
    site certificate or amended site certificate is executed,
    except that upon a clear showing of a significant threat to
    the public health, safety or the environment that requires
    application of later-adopted laws or rules, the council may
    require compliance with such later-adopted laws or rules.”
    490	           Blue Mountain Alliance v. Energy Facility Siting
    (Emphasis added.) Relying on the ODOE staff report, the
    council in its final order declined to require compliance with
    Ordinance 2012-04 as a “later-adopted law[          ]”under ORS
    469.401(2). Petitioners assert that the ordinance qualifies
    as a “later-adopted law[  that they presented substantial
    ],”
    evidence to satisfy the “significant threat” requirement,
    and that the council abused its discretion when it failed to
    require compliance with the ordinance in Amendment #2.
    Before turning to the merits, we address three
    preliminary considerations. First, the parties do not appear
    to dispute that the words “later-adopted laws or rules”
    in ORS 469.401(2) mean laws or rules adopted after the
    execution date of either the site certificate or an amended
    site certificate, as applicable.11 Here, the county adopted
    Ordinance 2012-04 before the council issued its final order
    approving Amendment #2 and before the execution date
    for Amendment #2—indeed, that amended site certificate
    has not yet been executed, pending the outcome of this
    proceeding. In the context of this assignment of error, then,
    petitioners appear to treat the execution date for either the
    initial site certificate or for Amendment #1—which both
    predated adoption of Ordinance 2012-04—as the operative
    trigger date that justifies treatment of the ordinance as a
    “later-adopted law[ ].” That is, unlike their first assignment of
    error—which exclusively focuses on the statutorily required
    contents of Amendment #2—this assignment alternatively
    contends that Amendment #2 should address the changed
    circumstance of the county’s adoption of Ordinance 2012-04
    after the execution date for either the original site certificate
    or Amendment #1.
    Second, we note that OAR 345-027-0090 provides
    a process for requesting that the council require facility
    compliance with later-adopted laws or rules under
    the “significant threat” requirement set out in ORS
    469.401(2). Such a process was not initiated here; instead,
    petitioners raised (and continue to raise) their “later-
    adopted” contentions in the context of challenging Helix’s
    Amendment #2 application. Although the council and Helix
    11
    By contrast, the preceding “abide by local ordinances” clause of ORS
    469.401(2) unequivocally applies to local ordinances, state law, and council rules in
    effect on the execution date.
    Cite as 353 Or 465 (2013)	491
    disagree with petitioners on the merits, they do not argue
    that petitioners should have raised this challenge through
    the process established in OAR 345-027-0090.
    Third, in disagreeing with petitioners on the merits,
    the council and Helix do not appear to dispute petitioners’
    assumption that a local ordinance may qualify under the
    “later-adopted laws or rules” clause of ORS 469.401(2)
    (emphasis added). As a matter of statutory interpretation,
    we agree with that construction. At first blush, the more
    precise wording of the preceding “abide by local ordinances”
    clause—which requires inclusion in the site certificate of
    compliance conditions as to “local ordinances and state law
    and the rules of the council” in effect on the execution date
    (emphasis added)—coupled with the lack of reference to
    “local ordinances” in the “later-adopted laws” clause, could
    be read to suggest that “later-adopted” laws include state
    laws but exclude local ordinances. However, other aspects
    of the statutory scheme suggest that “later-adopted laws”
    include local ordinances. For example, subsection (3) of ORS
    469.401 provides, in part:
    “(3)  *  * After the site certificate or amended site
    *
    certificate is issued, the only issue to be decided in an
    administrative or judicial review of a state agency or local
    government permit for which compliance with governing
    law was considered and determined in the site certificate
    or amended site certificate proceeding shall be whether the
    permit is consistent with the terms of the site certificate or
    amended site certificate. * * *”
    That subsection of ORS 469.401 uses the words “governing
    law” to refer to the collective body of ordinances, state law,
    and rules that are subject to site certificate compliance
    requirement terms under subsection (2). That reference
    in turn suggests that the similarly broad “later-adopted
    laws” clause of subsection (2) incorporates local ordinances,
    as well. By contrast, ORS chapter 469 consistently refers
    to categories of applicable state law as “statutes” or “state
    laws,” instead of using the broader term, “laws.” See ORS
    469.503(3) (in determining facility compliance with “Oregon
    statutes and administrative rules identified in the project
    order,” if council identifies related conflicting certificate
    conditions, council may resolve conflict but may not waive
    492	       Blue Mountain Alliance v. Energy Facility Siting
    “any applicable state statute” (emphases added)); ORS
    469.504(3) (similar waiver provision; refers to “applicable
    statutes and state administrative rules” (emphasis added));
    ORS 469.401(2) (refers to compliance with future-adopted
    “applicable state and federal laws” to extent required under
    state agency statutes and rules (emphasis added)). In light
    of that statutory context, we agree with all parties that
    “later-adopted laws” referred to in ORS 469.401(2) may
    include local ordinances.
    We turn to petitioners’ contention on the merits.
    As noted, under ORS 469.401(2), the council “may” require
    compliance with a “later-adopted law[  upon a clear
    ]”
    showing of a significant threat to the public health, safety,
    or the environment that requires application of such a law.
    Because the council’s determination under that clause is
    discretionary, we review the council’s decision to not require
    compliance with Ordinance 2012-04 as a “later-adopted
    law[  for abuse of discretion. See ORS 183.482(8)(b)(A)
    ]”
    (court shall remand if it finds agency’s exercise of discretion
    to be outside range of discretion delegated to agency by law).
    In its final order approving Amendment #2, the
    council incorporated by reference factual findings from both
    the original final order approving the initial site certificate
    and the final order approving Amendment #1 that the
    facility would comply with ODEQ noise regulations, subject
    to identified site certificate conditions. The council further
    concluded that, subject to those same site certificate
    conditions, the facility would comply with applicable
    ODEQ regulations under Amendment #2. The council did
    not specifically analyze petitioners’ contentions under the
    “later-adopted laws” clause of ORS 469.401(2) in its final
    order; instead, the order incorporated the ODOE staff report
    analysis by reference.
    The ODOE staff report recommended that the
    council decline to find that a setback of less than two miles
    posed a significant threat to public health and safety.
    First, the report explained that the council previously
    had determined—in an unrelated proceeding—that a 1/4
    mile setback was sufficient and that the council since had
    applied that smaller setback to other wind energy facilities.
    Cite as 353 Or 465 (2013)	493
    Second, the report explained that ODEQ noise regulations
    established a “public health setback” that may exceed 1/4
    mile depending on certain circumstances and that the
    council applied those regulations to all energy facilities.
    The report therefore recommended that the council follow
    its own previously established 1/4-mile setback or a setback
    that otherwise complied with ODEQ regulations, whichever
    was greater. The report further noted that the council
    expressly had declined to adopt a two-mile setback when the
    same question had been raised in proceedings challenging
    Amendment #1 the previous year; as noted, both the original
    final order and the final order approving Amendment #1
    had concluded that (with identified conditions in place)
    the facility would comply with ODEQ noise regulations.
    By incorporating the ODOE staff report by reference, the
    council implicitly declined to require compliance with
    Ordinance 2012-04 in Amendment #2 as a “later-adopted
    law[ ].”
    In challenging that decision, petitioners argue that
    the council discounted their supporting documentation
    demonstrating the adverse public health effects of wind
    turbine noise and that the council failed to evaluate whether
    petitioners had made a sufficient “significant threat” showing,
    so as to justify requiring compliance with Ordinance 2012-04
    as a “later-adopted law[ ] under ORS 469.401(2). Petitioners
    are correct that, in its assessment of the “significant threat”
    question, the council expressly focused on its own precedent
    and, in particular, the applicable ODEQ regulations,
    rather than on petitioners’ arguments and documentation.
    However, after viewing the relevant final order components
    as a whole, we understand the council to have declined
    to require compliance with Ordinance 2012-04 because
    the applicable ODEQ regulations and council precedent
    countered petitioners’ proffered “significant threat” showing.
    We conclude that the council did not abuse
    its discretion in declining to require compliance with
    Ordinance 2012-04 in Amendment #2 as a “later-adopted
    law[  under ORS 469.401(2). As part of issuing both
    ]”
    its original final order and its final order approving
    Amendment #1, the council previously had determined
    494	          Blue Mountain Alliance v. Energy Facility Siting
    that the facility was subject to the ODEQ noise regulations
    and that the facility would comply with those regulations.
    In succinctly addressing petitioners’ contentions in this
    Amendment #2 proceeding, the council continued to apply
    its earlier analysis from the Amendment #1 proceeding and
    determined that its own precedent, facility compliance with
    ODEQ regulations, and previously imposed site certificate
    conditions effectively negated petitioners’ “significant
    threat” contentions. The council’s reliance on the ODEQ
    regulations as part of assessing petitioners’ “significant
    threat” contention fell within its statutory authority under
    ORS 469.401(2).12 It follows that its ultimate determination
    that the “later-adopted laws” clause of that statute did not
    require compliance with Ordinance 2012-04 also fell within
    its authority.
    V.  THIRD ASSIGNMENT OF ERROR:
    OAR 345-027-0070(7)—CONTESTED CASE
    PROCEEDING
    Petitioners’ final assignment of error is that the
    council erred in denying their requests for a contested
    case proceeding. They rely on OAR 345-027-0070(7), which
    provides, in part:
    “To determine that an issue justifies a contested case
    proceeding under section (8),[13] the Council must find that
    the request raises a significant issue of fact or law that may
    affect the Council’s determination that the facility, with the
    change proposed by the amendment, meets an applicable
    standard. If the Council finds that the request would not
    affect the Council’s determination if the alleged facts were
    found to be true but that those facts could affect a site
    certificate condition, the Council may deny the request and
    may adopt appropriate conditions. * * *”
    12
    And, even if the council had determined that petitioners had established a
    “significant threat,” it nonetheless had discretion under ORS 469.401(2) whether
    to treat Ordinance 2012-04 as a “later-adopted law[ ].”
    13
    OAR 345-027-0070(8) provides, in part, that the council “shall determine
    whether any issue identified in a request for a contested case proceeding justifies
    a contested case proceeding[.]” See also OAR 345-027-0070(6) (any person may ask
    council to hold contested case proceeding on proposed order; written request must
    include description of contested issues and statement of facts believed to be at
    issue).
    Cite as 353 Or 465 (2013)	495
    (Emphasis added.) Petitioners focus on the “significant
    issue of fact or law” component, arguing that their legal
    and factual submissions to the council as to the proper
    application of ORS 469.401(2) and Ordinance 2012-04, and
    the noise impact of wind turbines on public health and
    safety, satisfied that component. Petitioners additionally
    contend that a contested case proceeding would have
    provided them the opportunity to further develop their legal
    analysis and more persuasively establish that a setback
    of less than two miles would create a “significant threat”
    to public health and safety under the second clause of the
    second sentence of ORS 469.401(2). As to the “applicable
    standard” component of OAR 345-027-0070(7), petitioners
    characterize the alternative 1/4-mile setback and ODEQ
    regulations as insufficient alternative “standards” to the
    two-mile setback required in Ordinance 2012-04; they also
    characterize their proffered construction of ORS 469.401(2)
    as a “standard” that applied to the council’s determination
    under OAR 345-027-0070(7).
    OAR 345-027-0070(7) requires that petitioners raise
    “a significant issue of fact or law” and also that the issue
    must be one that may affect the council’s determination
    that the facility, with the proposed amendment, would
    “meet[  an applicable standard.” (Emphasis added.) In the
    ]
    context of OAR chapter 345, the phrase “meets an applicable
    standard” in OAR 345-027-0070(7) has a particular meaning.
    ORS 469.501 requires the council to adopt “standards
    for the siting, construction, operation and retirement of
    [energy] facilities,” and the council has done so.14 As part
    of the site certificate application process, the council must
    determine that the facility complies with those council-
    adopted standards, ORS 469.503(1), just as it also must
    determine whether the facility complies with statewide
    planning goals, ORS 469.503(4), and whether it complies
    14
    See OAR 345-022-0010 - 345-022-0120 (setting out standards relating to
    applicant’s organizational expertise; facility structure; soil protection; land use
    (including compliance with statewide planning goals); protected areas; retirement
    and financial assurance; fish and wildlife habitat; threatened and endangered
    species; scenic resources; historic, cultural, and archaeological resources;
    recreation; public services; and waste minimization); OAR 345-024-0010 - 345-024-
    0720 (setting out specific standards for siting facilities, including wind facilities,
    transmission lines, and facilities that emit carbon dioxide).
    496	       Blue Mountain Alliance v. Energy Facility Siting
    with other state statutes and rules identified in the project
    order, ORS 469.503(3). Thus, the question under OAR 345-
    027-0070(7) is whether the council erred in determining
    that petitioners raised no significant issue of fact or law
    that may have affected the council’s determination under
    ORS 469.503(1) that the facility, with Amendment #2, would
    meet an applicable council-adopted standard arising under
    ORS 469.501.
    Here, the council’s determination under OAR
    XXX-XX-XXXX(7) was summary in nature but incorporated
    by reference extensive discussion from the ODOE staff
    report. That report analyzed petitioners’ contentions under
    the second sentence of ORS 469.401(2) and recommended
    that the council reach the same determinations that we
    now have affirmed: (1) Ordinance 2012-04 qualifies as a
    “land use regulation[  under ORS 469.504(1)(b)(A) and
    ]”
    therefore should not be considered under the “abide by local
    ordinances” clause of ORS 469.401(2); and (2) in light of
    applicable council precedent, the ODEQ noise regulations,
    and the related procedural background as to this site
    certificate, the council should decline to require compliance
    with Ordinance 2012-04 as a “later-adopted law[       ]”under
    ORS 469.401(2). Significantly, the report also reiterated that
    the final order approving Amendment #1 had determined
    that the two-mile setback did not apply to any of the
    council’s “compliance” determinations under ORS 469.503—
    including compliance with council-adopted standards under
    ORS 469.503(1)—and that Amendment #2 raised no new
    facts or circumstances that justified altering the council’s
    earlier ORS 469.503 compliance determinations. The report
    expressly recommended that the council find that petitioners
    had not satisfied the threshold requirements under OAR
    345-027-0070(7). By incorporating the ODOE staff report by
    reference, the council adopted the staff analysis and made
    the recommended determination.
    We conclude that the council did not err in rejecting
    petitioners’ requests for a contested case proceeding. The
    council determined that petitioners’ legal and factual
    claims—even to the extent that they may have raised
    “significant issue[s] of fact or law” in the abstract—did not
    Cite as 353 Or 465 (2013)	497
    raise any significant issue or fact or law that may have
    affected the council’s determination under ORS 469.503(1)
    that the facility “meets an applicable standard” under OAR
    XXX-XX-XXXX(7); instead, petitioners focused on the council’s
    application of the second sentence of ORS 469.401(2),
    regarding amended site certificate contents. The council’s
    determination was permissible, given the narrow wording
    of OAR XXX-XX-XXXX(7). See Don’t Waste Oregon Com. v.
    Energy Facility Siting, 320 Or 132, 142, 881 P2d 119 (1994)
    (where council’s plausible interpretation of own rule cannot
    be shown to be inconsistent with wording of rule, context,
    or any other source of law, no basis exists for this court to
    conclude that council interpreted rule “erroneously”).
    VI. CONCLUSION
    To summarize, we conclude that (1) the council correctly
    characterized Ordinance 2012-04 as a “land use regulation[ ]”
    subject to consideration under ORS 469.504(1)(b)(A)
    and properly declined to consider the ordinance under that
    statute because it was not “in effect” on the Amendment
    #2 application date; (2) because the ordinance qualified as
    a “land use regulation[  under ORS 469.504(1)(b)(A), the
    ]”
    council correctly declined to require compliance with the
    ordinance under the “abide by local ordinances” clause of
    ORS 469.401(2); (3) the council did not abuse its discretion
    in declining to require compliance with the ordinance as
    a “later-adopted law[  and (4) the council did not err in
    ]”;
    denying petitioners’ requests for a contested case proceeding.
    We therefore affirm the council’s final order approving
    Amendment #2.
    The Final Order Denying a Contested Case
    Proceeding and Approving Amendment #2 of the Energy
    Facility Siting Council is affirmed.
    

Document Info

Docket Number: S060803

Citation Numbers: 353 Or. 465, 300 P.3d 1203

Filed Date: 4/18/2013

Precedential Status: Precedential

Modified Date: 1/13/2023