Moerman v. Prairie Rose Resources, Inc. , 371 Mont. 338 ( 2013 )


Menu:
  •                                                                                            August 27 2013
    DA 12-0666
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    
    2013 MT 241
    IRENE M. MOERMAN and JOHN H. MOERMAN,
    Plaintiffs and Appellants,
    v.
    PRAIRIE ROSE RESOURCES, INC.,
    a North Dakota Corporation,
    Defendant and Appellee.
    APPEAL FROM:            District Court of the Seventh Judicial District,
    In and For the County of Wibaux, Cause No. DV 11-11
    Honorable Richard A. Simonton, Presiding Judge
    COUNSEL OF RECORD:
    For Appellant:
    Brian D. Lee; Lee Law Office, P.C.; Shelby, Montana
    For Appellee:
    Albert R. Batterman; Batterman Law Offices, P.C.; Baker, Montana
    Submitted on Briefs: May 28, 2013
    Decided: August 27, 2013
    Filed:
    __________________________________________
    Clerk
    Justice Laurie McKinnon delivered the Opinion of the Court.
    ¶1     Irene and John Moerman appeal the judgment and order of the District Court for
    the Seventh Judicial District, Wibaux County, denying their claim that the oil and gas
    lease at issue in this case has expired or has been forfeited. We affirm.
    ¶2     We address the following issues on appeal:
    ¶3     1. Whether the District Court correctly concluded that the parties’ oil and gas
    lease remained in effect.
    ¶4     2. Whether the District Court was correct in awarding Prairie Rose Resources,
    Inc. (Prairie), its attorney fees.
    Factual and Procedural Background
    ¶5     Irene and John Moerman (the Moermans) lived on a ranch in Wibaux County,
    Montana, until 1995, when they sold the ranch to Jim Kane. John’s father, Anton
    Moerman, had acquired the ranch (which included both the surface and mineral estates
    with the exception of coal) via a land patent. The Moermans, who are now divorced,
    reserved for themselves life estates to the mineral rights on the ranch with the remainder
    to vest in their three children. The well in question was originally drilled almost thirty
    years ago, but was subsequently shut in and abandoned.
    ¶6     In 2006, Prairie, an oil and gas development company incorporated in North
    Dakota, leased the well from the Moermans, but failed to bring the well into production
    during the lease period. Consequently, the 2006 lease terminated. In June 2010, the
    2
    Moermans each1 signed a new Oil and Gas Lease with Prairie. These leases were for six
    months with the primary term of each lease from June 1, 2010, to December 1, 2010.
    Michael Gleason, Prairie’s president, paid the Moermans $32,000 for the leases.
    ¶7    The leases granted to Prairie the exclusive right to the oil and gas in the south half
    of Section 30, Township 18 North, Range 59 East, M.P.M., for exploration and
    development purposes. The leases required that Prairie pay the Moermans a royalty of
    one-eighth of all oil produced and saved from the leasehold premises. As to the term, the
    leases provided:
    It is agreed that this lease shall remain in force for a term ending
    December 1, 2010 and as long thereafter as oil or gas of whatsoever nature
    or kind is produced from said leased premises or on acreage pooled
    therewith, or drilling operations are continued as hereinafter provided. If,
    at the expiration of the primary term of this lease, oil or gas is not being
    produced on the leased premises or on acreage pooled therewith but Lessee
    is then engaged in drilling or re-working operations thereon, then this lease
    shall continue in force so long as operations are being continuously
    prosecuted on the leased premises or on acreage pooled therewith; and
    operations shall be considered to be continuously prosecuted if not more
    than one hundred eighty (180) days shall lapse between the completion or
    abandonment of one well and the beginning of operations for the drilling of
    a subsequent well. If after the discovery of oil or gas on said land or on
    acreage pooled therewith, the production thereof should cease from any
    cause after the primary term, this lease shall not terminate if Lessee
    commences additional drilling or re-working operations within one hundred
    eighty (180) days from the date of cessation of production or from date of
    completion of dry hole. If oil or gas shall be discovered and produced as a
    result of such operations at or after the expiration of the primary term of
    this lease, this lease shall continue in force so long as oil or gas is produced
    from the leased premises or on acreage pooled therewith.
    1
    Because the Moermans were divorced, two separate leases were executed; however, the
    terms of the leases are identical.
    3
    ¶8      Prairie assigned the leases to PB Oil Company, LLP (PB Oil),2 an oilfield service
    company operating in the Sidney, Montana, area, subject to the reservation of a small
    overriding royalty interest. PB Oil then contracted with TOI Operating, Inc. (TOI) as the
    bonded contractor to bring the well into production.
    ¶9      Keith Carver, a petroleum engineer working for both PB Oil and TOI, worked to
    get the well into production. Carver testified that because of the high demand for drilling
    rigs, he was unable to get a “work-over rig” to the well site until November 2010. Carver
    further testified that he constructed a pad for the pump, installed the hardware and
    equipment necessary to produce oil at the site, and replaced the pumping unit. Carver
    testified that he started the well up on November 29, 2010, to make sure it would
    produce, but he had to leave the site early due to a blizzard. Carver returned to the site on
    December 1, 2010, but he was prevented from returning the following day due to the
    severe weather conditions.
    ¶10     On December 9, 2010, Carver again managed to get to the well to prepare the site
    for inspection by the Montana Board of Oil and Gas Conservation (BOGC).                  An
    inspector from BOGC visited the site on December 10 and 13, 2010. The inspector
    reported that the well was producing and that there was over seven feet of oil in the
    storage tanks. The BOGC referred to this well as the “Moerman 14-30.”
    ¶11     Gleason called John Moerman on December 10, 2010, to notify him that the well
    was producing. The record indicates that John Moerman failed to inform his ex-wife of
    2
    PB Oil was not a party to this action.
    4
    Gleason’s call. The record further indicates that John attempted to testify at trial, but due
    to health and memory issues, he was excused.
    ¶12    Gleason contracted with Shell Oil Corp. to purchase the oil from Moerman 14-30,
    but before the oil could be sold, Gleason was required to obtain a mineral title opinion to
    demonstrate clear title to the oil. Gleason contacted several attorneys throughout the
    latter part of 2010 and the early part of 2011, but because of the growth of the Bakken oil
    fields in North Dakota, there was a significant backlog in the production of title opinions.
    Gleason testified at the January 19, 2012 trial that he expected to have a completed title
    opinion by February 15, 2012, after which time he could begin selling the oil.
    ¶13    While Prairie was working to produce oil at Moerman 14-30 in the south half of
    Section 30, and to bring it to market, the Moermans leased the mineral rights to the north
    half of Section 30 to another company. Irene testified that because she had not received
    notice that Moerman 14-30 was producing, she assumed the leases with Prairie had
    expired in December 2010. Because Irene wished to lease the mineral rights to the south
    half of Section 30 to the same drilling company to which the Moermans had leased the
    mineral rights to the north half of Section 30, the Moermans’ attorney sent a letter to
    Prairie dated February 18, 2011, requesting that Prairie release those leases. Although
    Gleason later acknowledged that he had received the Moermans’ letter, he did not
    respond.
    ¶14    Gleason testified that the cost to Prairie and TOI to get Moerman 14-30 producing
    was approximately $150,000. In addition, Carver testified that if the well was leased out
    from under him, he would either have to plug the well or sell the well bore, all of which
    5
    would result in his incurring significant losses. Consequently, Prairie declined to cancel
    the leases.
    ¶15    On July 27, 2011, the Moermans filed a complaint for declaratory judgment
    claiming that their oil and gas leases with Prairie had expired.           The Moermans
    complained that they were unable to re-lease the premises unless Prairie’s lease was
    voided. Prairie counterclaimed for a declaration that the lease remained in effect, and
    alleged that the Moermans had breached the contract as well as the implied covenant of
    good faith and fair dealing.
    ¶16    A bench trial was held on January 19, 2012. On February 15, 2012, the District
    Court issued its Findings of Facts, Conclusions of Law, Judgment and Order wherein the
    court found the lease to be in full force and effect, and awarded Prairie its attorney fees
    and costs pursuant to § 82-1-202, MCA.         Notably, the court also pointed out that
    “Defendant should consider that with better communication between it and Plaintiffs, this
    action may not have been filed.” The Moermans appealed.
    Standard of Review
    ¶17    This Court reviews the findings of fact of a district court sitting without a jury to
    determine if the court’s findings are clearly erroneous. Varano v. Hicks, 
    2012 MT 195
    ,
    ¶ 7, 
    366 Mont. 171
    , 
    285 P.3d 592
     (citing Olsen v. Milner, 
    2012 MT 88
    , ¶ 16, 
    364 Mont. 523
    , 
    276 P.3d 934
    ). We review a district court’s conclusions of law to determine whether
    the court’s interpretation of the law is correct. Somont Oil Co., Inc. v. A. & G. Drilling,
    Inc., 
    2002 MT 141
    , ¶ 14, 
    310 Mont. 221
    , 
    49 P.3d 598
     (Somont I), overruled on other
    grounds by Johnson v. Costco Wholesale, 
    2007 MT 43
    , 
    336 Mont. 105
    , 
    152 P.3d 727
    6
    (citing Carbon County v. Union Reserve Coal Co., 
    271 Mont. 459
    , 469, 
    898 P.2d 680
    ,
    686 (1995)).
    ¶18    In addition, our standard of review of a trial court’s order granting or denying
    attorney fees and costs is whether the court abused its discretion. Somont Oil Co., Inc. v.
    A. & G. Drilling, Inc., 
    2006 MT 90
    , ¶ 25, 
    332 Mont. 56
    , 
    137 P.3d 536
     (Somont II),
    overruled on other grounds by Johnson v. Costco Wholesale, 
    2007 MT 43
    , 
    336 Mont. 105
    , 
    152 P.3d 727
     (citing Gullett v. Van Dyke Const. Co., 
    2005 MT 105
    , ¶ 12, 
    327 Mont. 30
    , 
    111 P.3d 220
    ).
    Issue 1.
    ¶19    Whether the District Court correctly concluded that the parties’ oil and gas lease
    remained in effect.
    ¶20    The Moermans contend that the undisputed evidence demonstrates that the
    Moerman 14-30 well did not produce oil until after the expiration of the primary term of
    the lease. The Moermans also contend that even if Moerman 14-30 had produced oil in
    sufficient quantities to extend the lease beyond the primary term, Prairie failed to prove
    that the five-month cessation of production in 2011 was authorized under the temporary
    cessation of production doctrine. Consequently, the Moermans argue that based on either
    of these scenarios, the lease automatically terminated and they are entitled to an order
    declaring the same.
    ¶21    Prairie contends that the uncontroverted evidence indicates that Prairie had at all
    times acted with diligence in establishing oil production, and that the lease remained in
    effect because the Moerman 14-30 well did produce oil prior to the expiration of the
    7
    primary lease term. Prairie also contends that under the lease, a cessation of production
    of less than 180 days would not terminate the lease, and since there has not been a
    cessation of production for longer than 180 days, Prairie is entitled to continue to operate
    the well.
    ¶22    In construing an oil and gas lease, courts generally apply the rules of contract
    interpretation. Sandtana, Inc. v. Wallin Ranch Co., 
    2003 MT 329
    , ¶ 26, 
    318 Mont. 369
    ,
    
    80 P.3d 1224
    . In doing so, we have stated that the “ ‘intention of the parties is to be
    pursued if possible,’ ” and that this intention “ ‘is to be gathered from the entire
    agreement, not from particular words or phrases or disjointed or particular parts of it . . . .
    The contract must be viewed from beginning to end, and all its terms must pass in
    review; for one clause may modify, limit or illuminate the other.’ ” Sandtana, ¶ 26
    (quoting Federal Land Bank v. Texaco, Inc., 
    250 Mont. 471
    , 474, 
    820 P.2d 1269
    , 1271
    (1991); Lee v. Lee Gold Mining Co., 
    71 Mont. 592
    , 599, 
    230 P. 1091
    , 1093 (1924)).
    “It is well established that a court, in interpreting a written instrument, will
    not isolate certain phrases of that instrument in order to garner the intent of
    the parties, but will grasp the instrument by its four corners and in light of
    the entire instrument, ascertain the paramount and guiding intention of the
    parties.”
    Sandtana, ¶ 26 (quoting Federal Land Bank, 250 Mont. at 474-75, 
    820 P.2d at 1271
    ;
    Steen v. Rustad, 
    132 Mont. 96
    , 102, 
    313 P.2d 1014
    , 1018 (1957)).
    ¶23    Because oil and gas leases deal with property of a highly speculative nature, “the
    protection of the interests of the lessor is considered of paramount importance.”
    Stanolind Oil & Gas Co. v. Guertzgen, 
    100 F.2d 299
    , 300 (9th Cir. 1938). Thus, we
    construe oil and gas leases liberally in favor of the lessor and strictly against the lessee.
    8
    Clawson v. Berklund, 
    188 Mont. 48
    , 53, 
    610 P.2d 1168
    , 1171 (1980). And, while
    forfeitures are not favored in other areas of the law, forfeitures of oil and gas leases are
    favored “to prevent lands being burdened by profitless and unworked leases.” Fey v.
    A. A. Oil Corp., 
    129 Mont. 300
    , 316, 
    285 P.2d 578
    , 586 (1955); see also Christian v.
    A. A. Oil Corp., 
    161 Mont. 420
    , 425, 
    506 P.2d 1369
    , 1372 (1973).
    ¶24    In this case, the Moermans contend that there was no oil production prior to
    December 1, 2010, thus the lease automatically terminated on that date. The Moermans
    also contend that assuming the lease did not terminate on December 1, 2010, it would
    have terminated by May 2011, because there was a cessation of production in paying
    quantities between December 2010, and May 2011. We have several problems with the
    Moermans’ arguments.
    ¶25    First, regarding the Moermans’ contention that the well did not produce oil prior to
    December 1, 2010, thereby terminating the lease, the Moermans have not provided any
    evidence to refute Prairie’s contention that oil was produced prior to the December 1,
    2010 deadline. Keith Carver, the petroleum engineer who worked the well for PB Oil
    and TOI, testified as follows:
    A. . . . At 11/29 we started the well up to make sure it would
    produce, and we left the well site early, shutting the well down because of a
    blizzard. And then we didn’t go up there until after—into December and
    actually establish production with the well.
    Q. But you continued operations up to and through December 1st?
    A. Yes.
    The Moermans interpret Carver’s statement that they “established production” into
    December, to mean that no oil was produced on November 29, 2010, when Carver started
    9
    up the well. However, the District Court determined that Carver’s statement meant that
    some oil was produced from the well on November 29, 2010. The inference drawn by the
    District Court is correct since “established production” implies starting up the pump and
    seeing it produce oil. In addition, Carver also testified that he was at the well site on
    December 1, 2010.      His testimony that they “didn’t go up there until after—into
    December and actually establish production with the well” could also be interpreted to
    mean that they established production on December 1, 2010, the last day of the primary
    term of the lease.
    ¶26    Second, contrary to the Moermans’ contentions, the lease clearly states that the
    production of oil is not the only thing that will prevent the lease from terminating on
    December 1, 2010. Rather, the lease states that it “shall remain in force for a term ending
    December 1, 2010 and as long thereafter as oil or gas of whatsoever nature or kind is
    produced from said leased premises . . . or drilling operations are continued as
    hereinafter provided.” (Emphasis added.) The lease goes on to state that “[i]f, at the
    expiration of the primary term of this lease, oil or gas is not being produced on the leased
    premises . . . but Lessee is then engaged in drilling or re-working operations thereon,
    then this lease shall continue in force so long as operations are being continuously
    prosecuted on the leased premises . . . . (Emphasis added.)
    ¶27    In this case, Carver was actively engaged in re-working operations at the well both
    before and after December 1, 2010. Carver moved a work-over rig to the site, engineered
    the well to produce, constructed a pad for the pump, installed the hardware and
    equipment necessary to produce oil at the site, and replaced the pumping unit. Carver
    10
    started the unit pumping on November 29, 2010, but was forced off the site by a blizzard.
    In addition, service records indicate that Carver plowed the well out on December 1,
    2010, but he was precluded from getting to the site the next day due to the harsh weather.
    Carver successfully got to the site and produced the well again for a state inspector on
    December 9 and 10, 2010.
    ¶28    Third, the Moermans cite this Court’s decision in Somont I for the proposition that
    “the cessation of production in paying quantities” will trigger the automatic termination
    of a lease. See Somont I, ¶ 26. Thus, they maintain that the cessation of production at
    Moerman 14-30 for the five months from December 2010, to May 2011, terminated their
    lease with Prairie.
    ¶29    We stated in Somont I that “once a plaintiff establishes that an oil and gas lease
    has halted production, the burden shifts to the defendant to prove that the cessation was
    temporary and not permanent. A temporary cessation in production will not trigger an
    automatic termination of the lease,” but “[a] cessation in production will only be deemed
    temporary when it is caused by a sudden stoppage of the well or a mechanical breakdown
    of the equipment used in connection with the well, or the like.” Somont I, ¶¶ 28, 33.
    ¶30    However, we also stated in Somont I, that this does not hold true in every case, but
    only “in most oil and gas leases operating pursuant to the conditions of the secondary
    term.” Somont I, ¶ 26 (emphasis added). Under the terms of the lease at issue in this
    case, the secondary term allows for a cessation of production “from any cause” not just
    for “a sudden stoppage of the well or a mechanical breakdown,” provided that the
    cessation of production is less than 180 days:
    11
    If after the discovery of oil or gas on said land . . . the production thereof
    should cease from any cause after the primary term, this lease shall not
    terminate if Lessee commences additional drilling or re-working operations
    within one hundred eighty (180) days from the date of cessation of
    production or from date of completion of dry hole. [Emphasis added.]
    ¶31    We further held in Somont I, that “[t]he diligent lessee who takes immediate steps
    to rectify a sudden halt in production will not lose his or her investment” during such a
    temporary stoppage. Somont I, ¶ 32.
    “The test for determining whether there was sufficient production or
    whether the lessee was acting with reasonable diligence in producing and
    marketing the gas from the leased lands is the diligence which would be
    exercised by the ordinary prudent operator having regard to the interests of
    both lessor and lessee. This is a question of fact that will depend upon the
    facts and circumstances of each case.”
    Somont I, ¶ 27 (quoting Christian, 161 Mont. at 427-28, 
    506 P.2d at 1373
    ).
    ¶32    In this case, Gleason testified that he had contracted with Shell Oil Corp. to
    purchase the oil from Moerman 14-30, but before the oil can be sold, he has to obtain a
    mineral title opinion to demonstrate that he has clear title to the oil. Gleason further
    testified that he began contacting attorneys to get a title opinion beginning in September
    2010, but because of the growth of the Bakken oil fields in North Dakota, there is a
    significant backlog in the production of title opinions. Gleason also testified that once
    this legal hurdle is overcome and they can start selling the oil, the well should initially
    produce 17 to 20 barrels of oil per day which will stabilize at 12 to 14 barrels per day,
    and at $100 per barrel, that will be a profitable amount.
    ¶33    Based on the foregoing, we hold that the District Court correctly concluded that
    the parties’ oil and gas leases to the Moerman 14-30 well remained in effect.
    12
    Issue 2.
    ¶34    Whether the District Court was correct in awarding Prairie its attorney fees.
    ¶35    The District Court awarded Prairie its attorney fees under § 82-1-202(1), MCA,
    because the Moermans failed to establish that the lease to the Moerman 14-30 well had
    been forfeited. Section 82-1-202(1), MCA, provides:
    If the lessee or assignee of a lease neglects or refuses to execute a
    release as provided by this part, the owner of the leased premises may sue
    in any court of competent jurisdiction to obtain the release, and in that
    action the owner may also recover from the lessee or the lessee’s successor
    or assigns the sum of $100 as damages, all costs, together with reasonable
    attorney fees for preparing and prosecuting the suit, and any additional
    damages that the evidence in the case warrants. . . . If in the action the
    plaintiff fails to establish the forfeiture of the lease, attorney fees must be
    allowed to the lessee or assignee of the lease. Issues in regard to attorney
    fees must be determined in the same manner as other issues in those
    actions. [Emphasis added.]
    ¶36    As we indicated previously in this Opinion, we review a trial court’s order
    granting or denying attorney fees and costs to determine whether the trial court abused its
    discretion. Somont II, ¶ 25 (citing Gullett, ¶ 12). Finding no abuse of discretion in this
    case, we hold that because the Moermans failed to establish that the leases in question in
    this case had been forfeited, Prairie’s attorney fees in defending this action are
    recoverable under § 82-1-202, MCA.
    ¶37    In addition, in its response brief on appeal, Prairie requested that it be awarded its
    attorney fees incurred on appeal.     The Moermans did not refute Prairie’s argument
    regarding attorney fees on appeal as the Moermans declined to file a reply brief.
    Consequently, we conclude that pursuant to § 82-1-202, MCA, Prairie is also entitled to
    13
    its attorney fees on appeal, and we remand to the District Court for a determination of
    those fees.
    ¶38    Affirmed.
    /S/ LAURIE McKINNON
    We Concur:
    /S/ MICHAEL E WHEAT
    /S/ PATRICIA COTTER
    /S/ BRIAN MORRIS
    /S/ JIM RICE
    14