Brown Plumbing & Heating, Inc v. Homeowner Construction Lien Recovery Fund , 442 Mich. 179 ( 1993 )


Menu:
  • 442 Mich. 179 (1993)
    500 N.W.2d 733

    BROWN PLUMBING & HEATING, INC
    v.
    HOMEOWNER CONSTRUCTION LIEN RECOVERY FUND

    Docket No. 92347, (Calendar No. 5).

    Supreme Court of Michigan.

    Argued December 8, 1992.
    Decided May 18, 1993.

    Richard D. Palmer for the plaintiff.

    Frank J. Kelley, Attorney General, Thomas L. Casey, Solicitor General, and Michael A. Lockman, Assistant Attorney General, for the defendant.

    *181 BRICKLEY, J.

    We granted leave to determine whether the "substantial compliance" provision, § 302, of the Construction Lien Act, MCL 570.1101 et seq.; MSA 26.316(101) et seq., applies to § 203(3)(h) of the act, which requires that one who seeks recovery from the Homeowner Construction Lien Recovery Fund establish that the person with whom the claimant contracted is licensed if required to be licensed.

    I

    The facts of this case are not in dispute. On April 14, 1987, plaintiff Brown Plumbing and Heating, Inc., a properly licensed plumbing and heating contractor, entered a written contract with Primus Energy Homes, a general contractor in the business of building homes, to provide plumbing labor and materials on a residential construction job. Primus fraudulently informed plaintiff that it was licensed and provided a license number belonging to a licensed, but unrelated, construction company, Mayflower Construction.[1] Plaintiff never asked to see the license or an identification card.

    When Primus became insolvent and failed to pay the subcontractors for the work completed, claims of lien were filed and foreclosure proceedings were begun on the property. The Homeowner Construction Lien Recovery Fund was named as a party. MCL 570.1203(4); MSA 26.316(203)(4). The homeowners filed an affidavit stating that they *182 paid Primus for the work completed, and thereby relieved themselves of liability. MCL 570.1203(1)(a); MSA 26.316(203)(1)(a).

    Plaintiff then resorted to seek payment through the Recovery Fund. MCL 570.1201 et seq.; MSA 26.316(201) et seq. The fund refused to pay plaintiff because of plaintiff's failure to show compliance with the prerequisites for recovery under the act, namely, that Primus was a licensed residential contractor as required under Michigan law.[2]

    Both the plaintiff and the fund filed motions for summary disposition. The trial court granted the plaintiff's motion, holding that the plaintiff had substantially complied with the act and, therefore, was entitled to recover from the fund.

    The fund appealed.[3] Noting that one of the dual purposes of the Construction Lien Act is to protect the rights of those who perform labor or provide materials for the improvement of real property, the Court of Appeals affirmed. The Court stated that because the act is remedial in nature, it *183 should be liberally interpreted in favor of lien claimants. As a result, the court held that substantial compliance with § 203(3)(h) is sufficient to permit recovery from the fund. 190 Mich. App. 709, 714; 476 NW2d 657 (1991). We granted leave to appeal, 440 Mich. 889 (1992), and we now reverse.

    II

    Section 302 of the act provides:

    This act is declared to be a remedial statute, and shall be liberally construed to secure the beneficial results, intents, and purposes of this act. Substantial compliance with the provisions of this act shall be sufficient for the validity of the construction liens provided for in this act, and to give jurisdiction to the court to enforce them. [Emphasis added.]

    We find this provision to be clear and unambiguous.[4] The express language provides that substantial compliance is only applicable in two aspects: 1) the perfection of the construction liens provided for in part 1, and 2) to give the court jurisdiction. Although the first sentence of the section states that the entire act is to be construed liberally, the language of the second sentence is qualified to apply in only the two instances described above and in no way suggests that substantial compliance is sufficient to collect from the fund.

    We find it persuasive that the Legislature provided express language demonstrating its intention that the substantial compliance language should apply only to part 1 of the act. Part 1 of the act *184 establishes the procedures to acquire an enforceable construction lien on a particular piece of property; in other words, part 1 establishes the procedures to acquire a "valid construction lien." Part 2 creates the Homeowner Construction Lien Recovery Fund and enumerates the requirements that must be established to collect from the fund. Therefore, by not referring to the fund or recovery from the fund, and only referencing "the validity of the construction liens," the actual language of § 302 expressly limits its application to part 1.

    The plaintiff argues that the placement of § 302 in part 3 is evidence that the Legislature intended that § 302 apply to the entire act. It is also possible that the Legislature, with the addition of the recovery fund and the repositioning of the sections that made up the previous act, did not consider the application of current § 302.[5] Where the Legislature placed § 302 may have been more a matter of utility. For example, in arranging the various provisions of a statute, particularly, as in this case, where former provisions become part of a greater statutory scheme, it is reasonable to put the substance of the statute in the beginning and place the interpretive provisions at the end.

    If § 302 would have appeared in part 1, it would be beyond the pale of argument to which part it applies. The fact that § 302 is not found in part 1 should not defeat the unambiguous language. We think that in this case, where it is a question of the actual language versus where the language appears, the actual language is paramount.

    The dissent indicates that parts 1 and 3 of the act borrow substantially from the former mechanics' lien act. In fact, "[v]irtually all of the sections *185 of the former mechanics' lien act are now contained within parts 1 and 3 of the Construction Lien Act." Post at 190. Part 2 was a new creation with the enactment of this statute. The dissent quotes the original version of the current § 302 from the mechanics' lien act of 1897. Post at 193. The fact that that section has remained essentially the same for almost a century demonstrates that its meaning has not changed. Because parts 1 and 3 are taken from the former mechanics' lien act, it is obvious that § 302 applies to those parts. The question is whether § 302 applies to part 2, which enumerates specific criteria for recovering from the fund. We think it can be argued with equal force that if the Legislature had intended to apply § 302 to the newly created part 2, it would have amended the language that has existed for nearly one hundred years to expressly provide for its new application.[6] The fact that the Legislature did not amend the language confirms that its meaning and application have not changed, and, therefore, § 302 only applies to parts 1 and 3.

    Because of our conclusion that the substantial compliance provision of § 302 does not apply to part 2, the question now becomes whether the decision by the Court of Appeals can be based on the first sentence of § 302. While we acknowledge that the liberal construction language of the first sentence applies to the entire act, we nonetheless find that liberality cannot and should not nullify a clear and unambiguous requirement.

    *186 We take notice of the actual language of § 203(3)(h):

    A person who seeks recovery from the fund shall establish all of the following: ... That the contractor or the subcontractor, with whom the person claiming the construction lien contracted with, is licensed if required by law to be licensed. [Emphasis added.]

    One cannot liberally construe this provision to provide relief to this particular plaintiff without destroying the meaning of the statute. There is nothing in the record to indicate that the general contractor was licensed at any time during the relationship between the parties. The provision does not say that the claimant shall take steps to determine if, or that he subjectively believe that, the other party is licensed.[7] Therefore, we hold that a liberal construction of § 203(3)(h) does not save the plaintiff's claim.

    III

    In conclusion, because part 2 of the act does not deal with the validity of construction liens, its provisions cannot be tested by a substantial compliance standard. Accordingly, we reverse the decision of the Court of Appeals.

    LEVIN, BOYLE, RILEY, and GRIFFIN, JJ., concurred with BRICKLEY, J.

    MALLETT, J.

    We dissent from the majority opinion *187 and would affirm the decision of the Court of Appeals. The majority holds that the substantial compliance language of § 302 applies only to the details for perfecting a construction lien under part 1 of the act and not to claims against the fund under part 2. As a result, complete adherence to the requirements set forth in § 203(3) is a condition precedent to recovery from the fund. We disagree.

    I

    Enacted in 1980, the Construction Lien Act seeks to achieve a dual protective purpose. It aspires to protect not only a lien claimant's right to payment for wages or materials, but also the landowner from multiple payments for the same services. Fischer-Flack, Inc v Churchfield, 180 Mich. App. 606; 447 NW2d 813 (1989). The preamble to the act sets forth its broadly defined purpose.

    AN ACT to establish, protect, and enforce by lien the rights of persons performing labor or providing material or equipment for the improvement of real property; to provide for certain defenses with respect thereto; to establish a homeowner construction lien recovery fund within the department of licensing and regulation; to provide for the powers and duties of certain state officers; to provide for the assessments of certain occupations; to prescribe penalties; and to repeal certain acts and parts of acts.

    Although a preamble is not to be considered authority for construing an act, it is useful for interpreting its purpose and scope. Malcolm v East Detroit, 437 Mich. 132, 143; 468 NW2d 479 (1991); 2A Singer, Sutherland Statutory Construction (5th ed), § 47.04, pp 145-150.

    *188 A

    The fundamental rules of statutory construction are instructive in determining the applicability of § 302. On several occasions, this Court has held that where the provisions of a statute are clear and unambiguous, they are to be applied as written. Gilroy v General Motors Corp (After Remand), 438 Mich. 330, 341; 475 NW2d 271 (1991); Selk v Detroit Plastic Products, 419 Mich. 1, 9; 345 NW2d 184 (1984). When construing statutory provisions, the court's task is to discover and effectuate the intent of the Legislature. The legislative intent is to be derived from the actual language of a statute, and when the language is clear and unambiguous, no further interpretation is necessary. Storey v Meijer, Inc, 431 Mich. 368; 429 NW2d 169 (1988). Where ambiguity exists, a court must give the statute a valid and reasonable construction that will reconcile any inconsistencies and give effect to all of its parts. Girard v Wagenmaker, 437 Mich. 231, 238; 470 NW2d 372 (1991); Aikens v Dep't of Conservation, 387 Mich. 495, 499; 198 NW2d 304 (1972). A court must also ascertain "the evil or mischief which it is designed to remedy, and will apply a reasonable construction which best accomplishes the statute's purpose." Pittsfield Charter Twp v Saline, 103 Mich. App. 99, 105; 302 NW2d 608 (1981). Remedial statutes are to be construed liberally in favor of the persons intended to be benefitted by the statute. Bierbusse v Farmers Ins Group, 84 Mich. App. 34, 37; 269 NW2d 297 (1978).

    With these precepts of statutory construction in mind, under the Construction Lien Act, a lien claimant such as plaintiff Brown Plumbing must establish several elements before recovering from *189 defendant fund.[1] Among the requirements is § 203(3)(h),[2] which provides:

    Subject to section 204,[[3]] a person who has recorded a claim of lien and who is precluded from recovering a construction lien under subsection (1) may recover from the fund the amount for which the lien is established. A person who seeks recovery from the fund shall establish all of the following:

    * * *

    (h) That the contractor or subcontractor, with whom the person claiming the construction lien contracted with, is licensed if required by law to be licensed.[[4]]

    Section 302 of the act provides a self-contained construction directive.

    This act is declared to be a remedial statute, and shall be liberally construed to secure the beneficial results, intents, and purposes of this act. Substantial compliance with the provisions of this act shall be sufficient for the validity of the construction liens provided for in this act, and to give jurisdiction to the court to enforce them. [Emphasis added.]

    *190 We are asked to ascertain whether the substantial compliance language of § 302 applies to § 203(3)(h) of the act.[5]

    B

    The Construction Lien Act is separated into three parts.[6] Parts 1 and 3 of the act borrow substantially from the former mechanics' lien act.[7] In fact, following the repeal of the mechanics' lien act, the Legislature provided a "disposition table" that indicates the corresponding sections in the Construction Lien Act. Virtually all of the sections of the former mechanics' lien act[8] are now contained within parts 1 and 3 of the Construction Lien Act. Thus, part 3 of the Construction Lien Act, including § 302, was a substantial part of the original mechanics' lien laws, which consisted of particularized procedures and qualifications for recovery of a lien.

    Part 2 of the act was an entirely new set of provisions at the time of the act's adoption in *191 1982. Part 2 established the defendant homeowner lien recovery fund and promulgated rules and procedures for its administration. The fund, financed by periodic assessments on various residential licensees, was created within the Department of Licensing and Regulation.[9] The fund created defenses against an action to foreclose a residential construction lien. Thus, while a construction lien may be entirely valid, homeowners may protect themselves from multiple payments by filing an affidavit indicating that they paid the contractor and cooperated with the department in the defense of the fund, and have not colluded with any other person to obtain payment from the fund.[10] More importantly for present purposes, defendant fund also provides a remedy for lien claimants who would otherwise be precluded from recovering a construction lien because of the homeowner's protection under the act.

    Given the imprecise language of § 302 and the unique statutory history of the act, it becomes quite difficult to discern the Legislature's intention from the plain language of the statute. Clearly, § 203(3)(h) was designed to protect the conscientious tradesmen from fraudulent contractors. In an attempt to achieve this purpose, this Court should apply a liberal construction to § 302 and find that it is applicable to part 2 of the act. If the Legislature intended that § 302 only apply to the procedures for perfecting a construction lien under part 1, then it would have placed § 302 in part 1 of the act or provided language expressly limiting the application of § 302 to part 1. We believe that the placement of § 302 in part 3 of the act was more *192 than "a matter of utility";[11] it was a deliberate, affirmative decision on the part of the Legislature, evidencing its intention that § 302 be applicable throughout the act, including part 2.

    A statutory provision should be read in its entirety and in connection with the rest of the statute, and each provision of an act is to be read with reference to every other provision so as to produce an harmonious whole. In re Forfeiture of $5,264, 432 Mich. 242, 251; 439 NW2d 246 (1989); Detroit v Detroit Police Officers Ass'n, 408 Mich. 410, 481; 294 NW2d 68 (1980). In other words, due consideration must be given to all sections to produce an harmonious and consistent enactment of the entire statute. Preston v Dep't of Treasury, 190 Mich. App. 491; 476 NW2d 455 (1991). Reading the Construction Lien Act in its entirety, it is clear that § 302 should be made applicable to the requirements for collection from the fund, including § 203(3)(h).[12]

    The defendant urges this Court to consider a line of cases that illustrate the development of the substantial compliance doctrine.[13] Contrary to the defendant's assertions, substantial compliance is not a judicially created doctrine. In the mechanics' lien act of 1897,[14] the original version of the current § 302 appears in § 27.

    *193 This act is hereby declared to be a remedial statute and to be construed liberally to secure the beneficial results, intents and purposes thereof; and a substantial compliance with its several provisions shall be sufficient for the validity of the lien or liens hereinbefore provided for, and to give jurisdiction to the courts to enforce the same. [1897 PA 143.]

    Thus, the doctrine has existed in this state for nearly a century and has played an essential role in the development of property lien laws.

    We decline to follow the cases proffered by the defendant which involve the then-existent residential builders act,[15] not the Construction Lien Act or its predecessor. The theory behind a licensure requirement is deterrence. In those cases, recovery was being sought by an unlicensed contractor. By denying a claim to an unlicensed contractor, the Legislature sought to discourage unlicensed entities from engaging in residential construction. Deterrence would not be achieved by denying plaintiff Brown Plumbing recovery from the fund pursuant to the Construction Lien Act. Brown Plumbing was fully licensed and contributed to the fund, but was denied recovery because of Primus Energy Homes' lack of licensure. Should the Legislature determine that strict and not substantial compliance with § 203(3)(h) shall be required in the future, that change can be easily made.

    Accordingly, we would affirm the decision of the Court of Appeals that the trial court properly granted plaintiff's motion for summary disposition pursuant to MCR 2.116(C)(9) and (10). On the basis of the rules of statutory construction, and the remedial nature of the Construction Lien Act, we believe it is sufficient for a lien claimant to substantially *194 comply with § 203(3)(h) in order to recover from the Homeowner Construction Lien Recovery Fund.

    CAVANAGH, C.J., concurred with MALLETT, J.

    NOTES

    [1] Cruz Ortiz, a co-owner of Primus, misrepresented to the homeowners that he had a builder's license and used the license number belonging to Mayflower Construction to obtain building permits for the job. Leonard Ortiz, the other co-owner, filed sworn statements with a bank, alleging that Mayflower was the general contractor. Additionally, Cruz and Leonard Ortiz misrepresented themselves to others as "Primus Energy Homes in association with Mayflower Construction, Builder's License # 43237...."

    [2] Residential builders are required to be licensed before they may provide services. MCL 339.601(1); MSA 18.425(601)(1); MCL 339.2401(a); MSA 18.425(2401)(a).

    The specific prerequisites to recover from the fund are found in § 203(3), which provides in part:

    Subject to section 204, a person who has recorded a claim of lien and who is precluded from recovering a construction lien under subsection (1) may recover from the fund the amount for which the lien is established. A person who seeks recovery from the fund shall establish all of the following:

    * * *

    (h) That the contractor or the subcontractor, with whom the person claiming the construction lien contracted with, is licensed if required by law to be licensed. [MCL 570.203(3)(h); MSA 26.316(203)(3)(h).]

    [3] We note the defendant did not preserve the issue whether there was substantial compliance with the requirements for reimbursement from the lien recovery fund, in spite of the fact that the general contractor was not licensed as required by § 203(3)(h). Thus, we do not address this issue.

    [4] The dissent points out that legislative intent must be derived from the actual language of a statute, and when the language is clear and unambiguous, no further interpretation is necessary. Post at 188. (Citing Storey v Meijer, Inc, 431 Mich. 368, 376; 429 NW2d 169 [1988].)

    [5] The recovery fund was not part of this statute's predecessor, the former mechanics' lien act. Part 2 of the current act was a new addition with the enactment of this statute in 1982.

    [6] The dissent states:

    If the Legislature intended that § 302 only apply to the procedures for perfecting a construction lien under part 1, then it would have placed § 302 in part 1 of the act or provided language expressly limiting the application of § 302 to part 1. [Post at 191.]

    [7] Some provisions of the act do lend themselves to a liberal construction, particularly where there is a question of degree. The following sections provide an example: § 203(1)(c) (cooperating in the defense of the fund), § 203(3)(a) (entitled to a construction lien), § 203(3)(e) (not colluding to obtain payment from the fund), and § 203(3)(g) (making a reasonable effort to obtain payment from the contractor or subcontractor).

    [1] See MCL 570.1203(3); MSA 26.316(203)(3).

    [2] MCL 570.1203(3)(h); MSA 26.316(203)(3)(h).

    [3] Section 204, MCL 570.1204; MSA 26.316(204), provides:

    The department shall not pay out of the fund to subcontractors, suppliers, and laborers more than $75,000.00 per residential structure. When it appears that the amount claimed from the fund, with respect to a residential structure, will exceed $75,000.00, the department may delay payment until the total amount to be paid can be ascertained. If the total amount payable to subcontractors, suppliers, and laborers exceeds $75,000.00, they shall be paid their proportional shares of that amount.

    [4] See MCL 339.601; MSA 18.425(601), MCL 339.2401; MSA 18.425(2401), and MCL 339.2403; MSA 18.425(2403).

    [5] There is disagreement concerning whether the term "substantial compliance" is ambiguous in nature. See Fischer-Flack v Churchfield, supra at 611 (the phrase "substantial compliance" is ambiguous). Cf. Norcross Co v Turner-Fisher Associates, 165 Mich. App. 170; 418 NW2d 418 (1987) (the language of § 302 is clear and unambiguous). However, this Court is not called upon today to extrapolate the term "substantial compliance" or determine whether the plaintiff's actions conform to that term's definition.

    [6] Part 1 of the act, MCL 570.1101-570.1128; MSA 26.316(101)-26.316(128), establishes detailed procedures and guidelines for the filing and recovery of construction liens. Part 2 of the act, MCL 570.1201-570.1207; MSA 26.316(201)-26.316(207), creates and provides procedures for recovery under the homeowner construction lien recovery fund. Part 3 of the act, MCL 570.1301-570.1305; MSA 26.316(301)-26.316(305), sets forth the act's application and construction.

    [7] MCL 570.1-570.30; MSA 26.281-26.310, repealed by 1980 PA 497, § 303.

    [8] The inconsequential exceptions that did not become a part of the Construction Lien Act are MCL 570.2; MSA 26.282 (liens upon land held jointly by husband and wife); MCL 570.4a; MSA 26.284(1) (false statements made by contractor with intent to defraud); MCL 570.28; MSA 26.308 (notice of proceedings by publication).

    [9] The Department of Licensing and Regulation is now known as the Bureau of Occupational and Professional Regulation. See Executive Order No. 1991-9.

    [10] MCL 570.1203(1); MSA 26.316(203)(1).

    [11] Ante at 184.

    [12] Admittedly, there is an inherent difficulty in requiring a subcontractor to substantially comply with a statutory provision that requires the licensure of another party. However, this Court is not called upon today to determine the standard for substantial compliance with § 203(3)(h). There may, in fact, be adequate safeguards in place within the statute to remedy any difficulty in application.

    [13] Michigan Roofing & Sheet Metal, Inc v Dufty Rd Properties, 90 Mich. App. 732; 282 NW2d 809 (1979), vacated and remanded 409 Mich. 887; 295 NW2d 230 (1980), (On Remand) 100 Mich. App. 577; 298 NW2d 923 (1980), lv den 412 Mich. 872 (1981); Bernard F Hoste v Kortz, 117 Mich. App. 448; 324 NW2d 46 (1982); Superior American Homes v Fry, 130 Mich. App. 379; 343 NW2d 561 (1983).

    [14] 1897 PA 143.

    [15] MCL 338.1501 et seq.; MSA 18.86(101) et seq.