Lake States Engineering Corp. v. Lawrence Seaway Corp. , 15 Mich. App. 637 ( 1969 )


Menu:
  • 15 Mich. App. 637 (1969)
    167 N.W.2d 320

    LAKE STATES ENGINEERING CORPORATION
    v.
    LAWRENCE SEAWAY CORPORATION
    LAWRENCE SEAWAY CORPORATION
    v.
    UNITED STATES FIDELITY & GUARANTY COMPANY

    Docket Nos. 849, 850.

    Michigan Court of Appeals.

    Decided January 31, 1969.
    Application for leave to appeal filed February 21, 1969.

    *640 Merle R. Jenkins, for plaintiff.

    Arthur J. Hass, for defendant.

    Application for leave to appeal filed by defendant Lawrence Seaway Corporation and defendant United States Fidelity & Guaranty Company February 21, 1969.

    LEVIN, J.

    Lake States Engineering Corporation, an Illinois corporation, brought this action against Lawrence Seaway Corporation to recover damages for alleged breach of a building construction contract between Lake States, as subcontractor, and Lawrence, as general contractor. Lawrence counterclaimed for Lake States' alleged breach of the same contract. United States Fidelity & Guaranty Company was surety on Lake States' performance and payment bonds in favor of Lawrence.

    *641 The questions presented are:

    1) Is Lake States precluded from maintaining this action because of failure to have qualified to do business in Michigan?

    2) Even if Lake States cannot recover from Lawrence, may Lake States' surety, USF & G, recover from Lawrence the amounts USF & G pays labor and material claimants?

    3) Is Lawrence barred by its failure to have obtained a residential builder's license from recovering on its counterclaim against Lake States?

    The trial judge granted motions for accelerated and summary judgment dismissing the claims of all parties except that judgments totaling $92,217.67 were entered against Lake States and USF & G in favor of labor and material suppliers who were additional defendants. Lake States and USF & G appealed generally. Lawrence cross-appealed the dismissal of its claims against Lake States and USF & G. Neither Lake States nor USF & G have prosecuted their appeals against the labor and material suppliers.

    We affirm the judgment dismissing the claims of Lake States and USF & G and remand for trial on Lawrence's counterclaim.

    I.

    The contract, entered into in June or July, 1962, provided that Lake States would construct the foundation caissons for the Jeffersonian Apartments in Detroit. Lake States commenced performance. Before the dispute arose Lawrence had paid Lake States $252,810 of the $450,000 contract price.

    Lake States suspended work in November, 1962, after it failed in its attempts to get Lawrence to agree to pay additional amounts because of certain *642 subsurface conditions allegedly encountered by Lake States. Lake States claimed that Lawrence was obliged under the contract to pay more on that account. This Lawrence denied. Subsequently Lawrence hired another subcontractor to complete the caisson work.

    Lake States claims Lawrence owes it approximately $555,000. The amount of Lawrence's counterclaim, as stated in the counterclaim appended to Lawrence's answer, was $300,000.

    Section 95 of the Michigan general corporation act (MCLA § 450.95 [Stat Ann 1963 Rev § 21.96]) provides that "no foreign corporation shall be capable of making a valid contract in this state until it shall have fully complied with the requirements of the laws of this state with respect thereto, and at the time holds an unrevoked certificate to that effect."

    In June, 1962, Lawrence's president mailed the unsigned proposed form of contract from Detroit to Lake States in Chicago, Illinois. Lawrence's covering letter asked Lake States to sign the contract and added: "When the date of the contract is definitely determined, we will then sign the contracts and supply the dates for these contracts." Lake States signed in Chicago and later Lawrence signed in Detroit.

    Lake States claims the final acceptance of the contract occurred in Chicago, Illinois, when Lake States signed the contract, while Lawrence claims the contract did not become binding until it subsequently signed the contract in Detroit.

    The question of when and where the parties became contractually bound depends on their intention as manifested by their verbal statements and conduct in the light of all the circumstances.[1] The trial *643 judge did not make specific findings on that question. Furthermore, the question could not be decided without a trial hearing[2] and, thus, could not be decided on the record so far made. Accordingly, we may not affirm the trial judge on the ground that the contract was invalid under § 95 of the general corporation act. But that does not end our inquiry.

    If, as we must now assume for the purpose of reviewing the judgment entered by the trial judge, the contract was made in Illinois, as Lake States claims, it was a lawful contract even though Lake States was not then qualified to do business in Michigan and the contract contemplated that Lake States would do acts in Michigan requiring qualification. Whitehead & Kales Co. v. Taan (1926), 233 Mich. 597, 600, 601; Westerlin & Campbell Co. v. Detroit Milling Co. (1925), 233 Mich. 384, 386.[3]

    Lawrence asserts that Lake States' actions in Michigan pursuant to the contract were nevertheless unlawful because Lake States was not qualified to do business in Michigan when it acted and, thus, even if the contract was valid, Lake States may not recover on such unlawful acts.

    Section 93 of the general corporation act (MCLA § 450.93 [Stat Ann 1963 Rev § 21.94]) provides that it is "unlawful" for an unqualified foreign corporation to carry on its business in this State. Lake *644 States conceded that it was doing business in Michigan and that it did not have a certificate authorizing it to do so as required by § 93.

    Among other cases, Lawrence cites Imperial Curtain Co. v. Jacob (1910), 163 Mich. 72. In that case the foreign corporation was not allowed to recover for services rendered in Michigan pursuant to a contract apparently made in Pennsylvania (p 77):

    "Even though it should be held that the contract was accepted in Philadelphia, we cannot see how this fact would make any difference in the disposition of the case. The statutes with reference to foreign corporations were not made merely for the purpose of preventing foreign corporations from coming into Michigan and making contracts here, but were passed principally for the purpose of preventing foreign corporations from carrying on their business in this State without subjecting themselves to certain liabilities and obligations. It was the prevention of work within the State that was aimed at, and it was for work and service in this State that this suit was brought, as appears by the record." (Emphasis supplied.)

    Also denying recovery, not because the contract was made in Michigan but because its performance by the unqualified foreign corporation constituted doing business in Michigan, are Nernst Lamp Co. v. Conrad (1911), 165 Mich. 604; General Highways System v. Dennis (1930), 251 Mich. 152; Decorators Supply Co. v. Chaussee (1920), 211 Mich. 302; Smilansky v. Mandel Bros. (1931), 254 Mich. 575; Columbus Services, Inc. v. Preferred Building Maintenance, Inc. (WD Mich, 1967), 270 F Supp 875, 879, 880; A.H. Andrews Co. v. Colonial Theatre Co. (ED Mich, 1922), 283 F 471. See, also, Watts Construction Company v. Joint Clutch & Gear Service, Inc. *645 (1949), 325 Mich. 548; Mathews Conveyer Co. v. Palmer-Bee Co. (CA 6, 1943), 135 F2d 73.

    RJA § 2021 (MCLA § 600.2021 [Stat Ann 1962 Rev § 27A.2021]) provides:

    "When, by the laws of this state, any act is forbidden to be done by any corporation, or by any association of individuals, without express authority by law, and such act was done by a foreign corporation, the foreign corporation shall not maintain any action founded upon such act, or upon any liability or obligation, express or implied, arising out of, or made or entered into in consideration of such act."

    In doing business in Michigan without having qualified to do so, Lake States, a foreign corporation, in the words of RJA § 2021, thereby did an "act * * * forbidden to be done * * * without express authority by law." Accordingly, it may "not maintain any action founded upon such act," the act of doing business in Michigan, or "upon any liability or obligation, express or implied, arising out of, or made or entered into in consideration of such act." Smilansky v. Mandel Bros., supra; Mathews Conveyer Co. v. Palmer-Bee Co., supra; Seamans v. Temple Co. (1895), 105 Mich. 400.

    Lake States' count against Lawrence for damages for breach of contract and its alternative count in quantum meruit are both "founded upon" Lake States' unlawful act of doing business in Michigan without having qualified to do so. Additionally, both the express and implied-in-law liability and obligation sought to be enforced against Lawrence is clamed by Lake States to arise out of such unlawful act and whatever liability or obligation Lawrence may owe Lake States was made or entered into in consideration of Lake States' unlawful act of doing business in Michigan. Thus, the clear and blunt *646 language of RJA § 2021 bars Lake States from maintaining this action.

    RJA § 2021 explicitly covers implied liabilities or obligations as well as express liabilities or obligations. There is no room to construe it so as to make an exception for a liability or obligation the law implies, like the quasi-contractual recovery Lake States alternatively seeks.

    Furthermore, to engraft an exception for implied liabilities or obligations would be to emasculate the legislative policy reflected in RJA § 2021. It would be a rare case where recovery of amounts approximating, sometimes greater than, those denied recovery under the express contract could not be obtained quasi-contractually if we allow unqualified foreign corporations to ignore the contract and to recover on restitutionary theories whenever they are forbidden from recovering on the express contract.

    The prohibition against suit we now consider functions as a penalty. In that respect it differs from the statute of frauds which is designed to provide protection from imposition in certain kinds of transactions. We recognize that not infrequently in cases where a statute of frauds defense has been interposed courts have concluded that enforcement of the claim will not cause imposition and have allowed recovery by finding part performance taking the case out of the statute or invoking a restitutionary remedy; Vanderhoef v. Parker Brothers Company, Limited (1934), 267 Mich. 672, 681. The principles developed in those cases have no application where the prohibition, as the one here, is meant to apply without regard to whether the defendant has a meritorious defense, indeed even if he does not. See Cashin v. Pliter (1912), 168 Mich. 386, 391, 392.

    The legislature has deliberately decided to declare a forfeiture in the belief that the in terrorem effect *647 of such a forfeiture will tend to compel compliance with the statutory provisions requiring foreign corporations to register and pay taxes comparable to those imposed on domestic corporations. That being the legislative decision our duty is to enforce it even though in a given case the amount of the forfeiture may appear quantitatively or relatively large. Cf. Dawn Construction Co. v. Paris Home Builders, Inc. (1960), 360 Mich. 281, 285; Bilt-More Homes, Inc. v. French (1964), 373 Mich. 693.

    Nor does Lake States' compliance with Michigan's requirements after it committed all the acts upon which it declares in its complaint enable Lake States to maintain this action.[4] RJA § 2021 provides that an action may not be maintained based upon the commission of unlawful acts of the kind described in that section. Lake States' acts were of that kind. Lake States' subsequent qualification did not make those unlawful acts lawful.[5]

    *648 Lake States asserts that its contract with Lawrence was "executed" rather than "excutory" within the sense of Carolin Manufacturing Corporation v. George S. May, Inc. (1945), 312 Mich. 487, and Gill v. S.H.B. Corporation (1948), 322 Mich. 700. In those cases the party contracting with the foreign corporation failed in an attempt to declare the contract with the foreign corporation void after it had been fully performed by both parties. Lake States contends that Lawrence's termination of Lake States' employment under the contract after Lake States ceased work converted the contract from an executory to an executed one and thus, Lake States may recover under the cited cases.

    We need not decide the somewhat metaphysical question whether the contract then became executed *649 as to performance required of Lake States thereunder. The cited cases only preclude the assertion of the contract's infirmity by the other contracting party after such other contracting party has himself performed, i.e., when the contract is executed on both sides.

    In this case Lake States is complaining that Lawrence has not executed the performance (payment of money) Lake States claims Lawrence contracted to render. Lawrence chose to avail itself of the unlawfulness of Lake States' actions before the performance required of Lawrence was rendered. Since Lawrence has not rendered the performance for which Lake States brought this action, the policy which precludes rescission by one who has fully performed, who fails prior to performance to assert the unlawful nature of the foreign corporation's act, does not here apply.

    Lake States claims that when § 93a (making it a misdemeanor to violate § 93) was added in 1961 to the Michigan general corporation act,[6] RJA § 2021 ceased to apply to violators of § 93. The argument is that the criminal law penalties provided for in the 1961 enactment were intended to replace preexisting remedies.

    Apart from the fact that repeals by implication are not favored, we note that RJA § 2021, reenacting earlier legislation,[7] was passed subsequent to the law which added § 93a to the corporation act. We also note that it has not been Michigan's tradition to rely on criminal penalties in preference to civil *650 remedies to obtain compliance with corporate filing requirements. We read the 1961 legislature's intention to be the addition of still another sanction, not as eliminating by indirection the harsh but exceedingly effective RJA § 2021. Cf. Irvine & Meier v. Wienner (1920), 212 Mich. 199, 202; Reuter Hub & Spoke Co. v. Hicks (1914), 181 Mich. 250, 253; Dawn Construction Company v. Paris Home Builders, Inc., supra, p 285.

    Lake States cites Rex Beach Pictures Co. v. Garson Productions (1920), 209 Mich. 692, where a nonqualified foreign corporation was permitted to replevy a motion picture film belonging to it. However, as pointed out by the Supreme Court in that case (p 707): "Plaintiff's [Rex Beach Pictures Co.] right to the possession of the property in question does not depend upon the void contract, but is rather in spite of, or notwithstanding such contract and the doing of business thereunder."[8] Here Lake States' right to recover depends on proof of the unlawful act of doing business in Michigan, not proof of ownership of property owned before it performed such unlawful act.

    Under part III of this opinion we remand for trial on Lawrence's counterclaim against Lake States. So as to avoid misunderstanding, Lake States may defend against Lawrence's counterclaim by asserting as an offset whatever claims Lake States may have against Lawrence even though Lake States is statutorily precluded from maintaining an action on such *651 claims or seeking an affirmative recovery based thereon. Since Lawrence has put in issue the entire relationship of the parties, Lake States must be allowed to use defensively whatever claims it has against Lawrence.[9]Cf. Milum v. Herz Brothers Water Well Drilling and Supply Company (1958), 74 Nev 309 (329 P2d 1068).

    II.

    The claim of the surety, USF & G, is that even though its principal, Lake States, is barred by the statute from recovering anything in our courts, it, USF & G, should be allowed as surety to recover from Lawrence the amounts it pays labor and material claimants.

    USF & G relies principally on rules of law developed in public construction contract cases. Since mechanic's liens cannot be filed against public property,[10] contractors for public structures are required to furnish bonds for the protection of labor and material suppliers. See, e.g., MCLA § 570.101 (Stat Ann 1953 Rev § 26.321); MCLA § 129.201 (Stat Ann Cum Supp § 5.2321[1]).

    *652 In Pearlman v. Reliance Insurance Co. (1962), 371 U.S. 132 (83 S. Ct. 232, 9 L. Ed. 2d 190), the surety prevailed against a bankrupt contractor's trustee in bankruptcy, a majority of the justices so holding on the ground that the surety was subrogated to the claims of laborers and materialmen against the funds retained by the government while the concurring justices put their concurrence on the ground that the surety stood in the shoes of the governmental authority itself.[11]

    However, in United States v. Munsey Trust Co. (1947), 332 U.S. 234 (67 S. Ct. 1599, 91 L. Ed. 2022) the United States was permitted, in preference to the claim of the contractor's surety who had paid unpaid laborers and materialmen, to set off against the funds which it had retained an amount due it from the defaulting contractor under another contract. In so holding the United States Supreme Court acknowledged that in earlier cases it had (p 240) "recognized the peculiarly equitable claim of those responsible for the physical completion of building contracts to be paid from available moneys ahead of others whose claims come from the advance of money. But in all those cases, the owner was a mere stakeholder and had no rights of its own to assert."

    We have already held that Lake States may not recover from Lawrence and, thus, Lawrence has no obligation to Lake States which will be recognized *653 by our courts as supporting an affirmative recovery against Lawrence.

    USF & G has cited no authority allowing a surety to recover for amounts the contractor could not recover.[12] In all the cases cited by USF & G, the one against whom recovery was sought was a stakeholder only and not a party to the controversy.

    The Jeffersonian Apartments could have been liened by the labor and material suppliers USF & G has paid or may pay. As a general proposition, labor and material suppliers of a subcontractor have no claim against the general contractor or owner.[13] The principles developed in the public construction contract sector might, nevertheless, properly be invoked in a case where the private property owner or general contractor holds an unpaid amount owing to an uncollectible subcontractor and the question is whether labor and material claimants of the uncollectible subcontractor who have not protected their mechanic's lien rights, or a surety paying such claimants, should be preferred over general creditors or assignees of the subcontractor.[14]

    It is apparent that the rules and principles of law urged upon us by USF & G developed as they did in cases where the real question was one of priority to moneys in the hands of the governmental authority or owner as between the surety and his contractor-principal's *654 receiver, assignee, or creditors who had no claim against the surety.

    This case presents no issue of priority between USF & G and other competing creditors of Lake States. Different policies and principles of law are here controlling. USF & G has not claimed that Lake States is uncollectible, that it will not be able to enforce its right of indemnification against Lake States as principal for whatever amount it has paid or shall pay under the bond. Irrespective of whether USF & G and Lake States are in fact collaborating as Lawrence charges, if, as we must assume absent a claim to the contrary, Lake States, the principal on the bond, is collectible, the effect of allowing its surety, USF & G, to recover from Lawrence would be to benefit Lake States since Lake States would to that extent be relieved of the payment of labor and material claims.

    Whatever equitable considerations might encourage us to recognize a remedy in favor of a surety whose principal is uncollectible against a fund still intact and owing, without regard to whether the principal may himself maintain an action to collect from the fund, do not apply where allowance of such a remedy would in fact subvert the policy of § 93 of the general corporation act and RJA § 2021 by reducing the sanction against a solvent foreign corporation.

    III.

    Lawrence's counterclaim for damages for breach of contract is defended by Lake States on the ground that Lawrence's failure to obtain a residential builder's license prevents it from maintaining any action on the contract (PA 1965, No 383 [MCLA § 338.1501, et seq., Stat Ann 1968 Cum Supp § 18.86(101), et seq.]).

    *655 Our examination of this statute convinces us that the policy and language of its sanction are different from those imposed by the general corporation act and RJA § 2021.

    Allowing anyone who deals with an unqualified foreign corporation to avail itself of the bar to suits by such corporation serves the public as a whole by providing a most effective deterrent to avoidance of State taxation and regulation of foreign corporations. The purpose of the residential builder's licensing law, on the other hand, is to serve a more limited portion of the public, namely, owners:

    "In order to safeguard and protect home owners and persons undertaking to become home owners, it shall be unlawful * * * for any person to engage in the business of or to act in the capacity of a residential builder * * * without having a license therefor." MCLA § 338.1501 (Stat Ann 1968 Cum Supp § 18.86 [101]).

    The policy of protecting the owner is reflected in the language adopted to express the scope of the disqualification on maintenance of suit which results from building without a license.[15] Section 16 of the statute provides:

    "No person engaged in the business or acting in the capacity of a residential builder and/or residential maintenance and alteration contractor may bring or maintain any action in any court of this state for the collection of compensation for the performance of any act or contract for which a license is required by this act without alleging and proving that he was duly licensed under this act at all times during the performance of such act or contract". MCLA § 338.1516 (Stat Ann 1968 Cum Supp § 18.86 [116]).

    *656 Thus, a nonlicensed builder may not maintain an action to recover "compensation for the performance of any act or contract for which a license is required." (Emphasis supplied.) Accordingly, a nonlicensed builder may not recover for his own performance.

    Lawrence's counterclaim does not seek recovery for Lawrence's performance. Lawrence rather seeks recovery against a subcontractor for the subcontractor's alleged nonperformance. Since Lawrence's counterclaim seeks recovery for nonperformance, not performance, the statutory limitation on suit by a nonlicensed builder does not bar the counterclaim.

    It is true that Lawrence's unlicensed building operations were unlawful. MCLA § 338.1501 (Stat Ann 1968 Cum Supp § 18.86[101]). Absent an express statutory provision like § 16 as to the effect of such unlawfulness on its contracts made during the period of noncompliance, we might well declare them voidable at the option of the other contracting party on the common-law principle expressed in Maurer v. Greening Nursery Co. (1917), 199 Mich. 522. But § 16 occupies the field. It states the extent to which one violating this statute is precluded from bringing suit. To invoke the principle expressed in the last cited case would be to give no significance to the legislature's choice of language and would be in effect to supersede § 16 altogether with the more comprehensive common-law sanction.

    As the Michigan Supreme Court observed in Cashin v. Pliter (1912), 168 Mich. 386, before a court declares applicable the common-law sanction invalidating contracts made in violation of law (pp 390, 391):

    "the court should carefully scrutinize the particular statute under advisement, for the purpose of *657 ascertaining, from the subject-matter and language used, the object for which it was enacted and the intent of its makers, to the end that such intent may be rendered effectual and the indicated purpose accomplished."

    Affirmed as to Lake States' and USF & G's appeal. Reversed and remanded for trial on Lawrence's counterclaim. Costs to Lawrence.

    LESINSKI, C.J., and J.H. GILLIS, J., concurred.

    NOTES

    [1] "If from a promise, or manifestation of intention, or from the circumstances existing at the time, the person to whom the promise or manifestation is addressed knows or has reason to know that the person making it does not intend it as an expression of his fixed purpose until he has given a further expression of assent, he has not made an offer." Restatement of the Law, Contracts, § 25, p 31. See, also, Simmons and Simmons Construction Co., Inc. v. Rea (1955), 155 Tex 353 (286 S.W.2d 415).

    [2] GCR 1963, 116.3, 117.2(3). See, also, committee comment to rule 116, particularly subdivision (4) reprinted as annotation, 1 Honigman & Hawkins, Michigan Court Rules Annotated (2d ed), p 324, and Durant v. Stahlin (1965), 375 Mich. 628, 644.

    [3] Lake States could have become domesticated between the making of the contract and its performance. Had it done so, its acts of performance in Michigan would have been entirely lawful. Whitehead & Kales Co. v. Taan (1926), 233 Mich. 597.

    [4] Lake States asserts Lawrence "terminated" the contract on December 14, 1962, and that Lake States qualified to do business in Michigan on December 24, 1962. This action was commenced January 29, 1963.

    [5] Section 95 of the general corporation act took substantially its present form with the enactment of PA 1907, No 310, § 6:

    "No foreign corporation subject to the provisions of this act, shall be capable of making a valid contract in this state until it shall have fully complied with the requirements of this act, and at the time holds an unrevoked certificate to that effect from the Secretary of State."

    The last clause in the section just quoted was added by the 1907 act, legislatively overruling (Despres, Bridges & Noel v. Zierleyn [1910], 163 Mich. 399) earlier interpretations of PA 1903, No 34 (Hastings Industrial Co. v. Moran [1906], 143 Mich. 679, 683) holding that the enforcement of such a contract is prohibited only until the corporation qualifies. Thus, under the statute as amended in 1907, subsequent compliance will not make valid a contract made in Michigan which, because of noncompliance, was invalid when made. Since qualification by a foreign corporation after contracting in Michigan will not relieve the Michigan contract of the invalidity which attached to it at the time of contracting, we think more harmonious a rule of law to the effect that qualification by a foreign corporation after commission of the unlawful acts sued upon (where the contract is a foreign-made contract) does not relieve those acts of their unlawfulness.

    Analogously, in Irvine & Meier v. Wienner (1920), 212 Mich. 199, the Court declared that the inhibition against enforcement of contracts made during the period of default in filing annual reports was intended by the legislature to be perpetual. Similarly, see, Industrial Coordinators, Inc. v. Artco, Inc. (1962), 366 Mich. 313, 316. While the statutory language (MCLA, § 450.87 [Stat Ann 1963 Rev § 21.87]) construed in the last-cited cases clearly required that result, the court in Irvine & Meier v. Wienner, supra, observed (p 202):

    "A glance at the former legislation on this subject discloses that the legislation has been steadily, for several years, growing more drastic. The obvious reason for this was to compel prompt filing of annual reports. With the legislature in this frame of mind when this legislation was passed, it is hardly conceivable that it intended only a temporary suspension of the right to enforce contracts, as that would be but mild punishment for its default."

    There is no policy in this State of allowing late filers to recover for acts committed during the period of delinquency. Cf. Bilt-More Homes, Inc. v. French, supra, construing residential builders contractor's licensing law; Irvine & Meier v. Wienner, supra; Despres, Bridges & Noel v. Zierleyn, supra.

    We have considered Peter & Burghard Stone Co. v. Carper (1930), 96 Ind App 554 (172 N.E. 319) (the dissenting opinion appears at page 600 of the official report but is not printed in the Northeastern reporter), and the decisions of other State courts cited by Lake States. We must adhere to Michigan's tradition of enforcing the various laws providing civil sanctions designed to achieve compliance with the corporate filing and payment of fees requirements, which laws were passed, no doubt, in recognition of the fact that the threat of fines and jail sentences had not proven and was not likely to prove effective.

    [6] CLS 1961, § 450.93 (Stat Ann 1961 Cum Supp § 21.94); PA 1961, No 122 (MCLA, § 450.93a [Stat Ann 1963 Rev § 21.94(1)]).

    [7] See CL 1948, § 612.19 and earlier enactments going back to RS 1846, ch 116, § 2.

    There has been no change in substance and little change in the verbiage of RJA § 2021 since it first appeared in the revised statutes of 1846.

    [8] Similarly, see John J. Gamalski Hardware, Inc. v. Wayne County Sheriff (1941), 298 Mich. 662 (136 A.L.R. 1155); Benton Harbor Federation of Women's Clubs v. Nelson (1942), 301 Mich. 465; Woman's Relief Corps No. 1 Michigan v. South Haven City and Township Library Board (1945), 313 Mich. 85, 92, and In re Petitions of Auditor General (1952), 333 Mich. 700, 705, 706, where the Supreme Court allowed corporations delinquent in filing annual reports to maintain suits to vindicate their asserted interest in property held or claimed by another.

    [9] While Lake States' pretrial statement asserted that there was an inconsistency between Lawrence's claim that the contract between Lawrence and Lake States is invalid under § 95 of the general corporation act because made in Michigan and its counterclaim for damages under that contract, this contention has not been pursued in its briefs filed with our Court.

    Lawrence's counterclaim for breach of contract of necessity proceeds in affirmance of the contract. As previously mentioned we have decided this case on the assumption that the contract between Lake States and Lawrence was valid even though Lake States' actions in its performance violated § 93 of the general corporation act.

    In all events it is clear that when Lawrence filed its counterclaim it did not mean thereby to waive its affirmative defense that Lake States may not enforce the contract. Lawrence's assertion of the counterclaim no more waived the affirmative defense than did its assertion of the affirmative defense preclude the counterclaim. See GCR 1963, 111.9(2).

    [10] Knapp v. Swaney (1885), 56 Mich. 345; 36 Am Jur, Mechanics' Liens, § 16, p 27.

    [11] The United States Supreme Court has ruled that the surety's rights in funds retained by the governmental authority are superior to those of assignees or general creditors of the contractor where the surety completes the contract (Prairie State Bank v. United States [1896], 164 U.S. 227 [17 S. Ct. 142, 41 L. Ed. 412]) or pays those who complete it (Henningsen v. U.S. Fidelity & Guaranty Co. [1908], 208 U.S. 404 [28 S. Ct. 389, 52 L. Ed. 547]). See, also, National Surety Corporation v. United States (Ct Cls, 1955), 133 F Supp 381, 383, 384.

    Michigan cases applying these principles are Fidelity & Casualty Co. v. Livingston (1926), 234 Mich. 375, and City of Detroit v. Fidelity & Deposit Co. of Maryland (1927), 240 Mich. 213.

    [12] See Knapp v. Swaney (1885), 56 Mich. 345, 348, holding that a surety can claim nothing under a contract which the principal could not have claimed.

    [13] A crossclaim was filed against one of the owners of the Jeffersonian Apartments but the portion of the record furnished us does not show whether the claim was filed by Lake States or USF & G or both, or its nature.

    [14] It appears from Prairie State Bank v. United States (1896), 164 U.S. 227 (17 S. Ct. 142, 41 L. Ed. 412), and other authorities (see, e.g., Sandusky Grain Co. v. Borden's Condensed Milk Co. [1921], 214 Mich. 306, 314 et seq.; 17 Am Jur 2d, Contractor's Bonds, §§ 39-42, pp 220-222) that the equitable principles involved are not necessarily to be confined to public construction contract cases.

    [15] Cf. Beznos v. Borisoff (1954), 339 Mich. 12.

Document Info

Docket Number: Docket 849, 850

Citation Numbers: 167 N.W.2d 320, 15 Mich. App. 637

Judges: Gillis, Lesinski, Levin

Filed Date: 2/21/1969

Precedential Status: Precedential

Modified Date: 8/25/2023