Dynetics, Inc. and Subsidiaries v. United States , 121 Fed. Cl. 492 ( 2015 )


Menu:
  •        In the United States Court of Federal Claims
    No. 12-576T
    (E-Filed: May 31, 2015)
    )
    DYNETICS, INC. and SUBSIDIARIES,                     )   Cross-Motions for Partial
    )   Summary Judgment; RCFC 56(a);
    Plaintiff,                      )   I.R.C. § 41; Treasury Regulation
    )   §1.41-4A; Funded Research
    v.                                                   )   Exception
    )
    THE UNITED STATES,                                   )
    )
    Defendant.                      )
    )
    David M. Wooldridge, Birmingham, Ala., for plaintiff.
    Jason Bergmann, Trial Counsel, with whom were Caroline D. Ciraolo, Principal Deputy
    Assistant Attorney General; David I. Pincus, Chief, Court of Federal Claims Section,
    Mary M. Abate, Assistant Chief, Court of Federal Claims Section , Commercial
    Litigation Branch, Civil Division, United States Department of Justice, Washington,
    D.C., for defendant.
    OPINION and ORDER
    CAMPBELL-SMITH, Chief Judge
    This is a tax refund case. Dynetics, Inc. (Dynetics or plaintiff) is an engineering
    company headquartered in Huntsville, Alabama. Plaintiff filed amended tax returns for
    three tax periods seeking a refund based on certain research tax credits to which it claims
    entitlement under § 41 of the Internal Revenue Code (I.R.C.), which governs “Credit for
    increasing research activities.” I.R.C. § 41. Defendant, the Internal Revenue Service
    (IRS or defendant), disallowed plaintiff’s refund claims.
    On September 7, 2012, plaintiff timely filed its complaint in this court. While
    plaintiff’s complaint is based on tax refunds it claims for work performed on more than
    100 contracts, the parties have asked this court to evaluate plaintiff’s claims on only 7 of
    those contracts, which the parties refer to as sample contracts.
    While a taxpayer must establish a number of elements to qualify for a research tax
    credit under § 41, at this point in the case, the parties seek the court’s assistance with
    resolving their dispute on only one such element. Under § 41, a taxpayer may not claim a
    research tax credit if that research was “funded by any grant, contract, or otherwise by
    another person (or governmental entity).” I.R.C. § 41(d)(4)(H).
    Presently before the court are the parties’ fully briefed cross-motions for partial
    summary judgment on the funded research question, brought under Rule 56(a) of the
    Rules of the United States Court of Federal Claims (RCFC). The parties ask this court to
    determine whether the research performed by Dynetics under each of the seven sample
    contracts was “funded” under the governing Internal Revenue Code and Treasury
    regulations.
    After consideration of the parties’ briefing and evidentiary support, the court
    GRANTS defendant’s motion for partial summary judgment on the funded research
    question, and DENIES plaintiff’s cross-motion for partial summary judgment on the
    funded research question.
    I.     Background
    A.     Cross-Motions for Partial Summary Judgment
    Defendant filed a motion for partial summary judgment on the funded research
    question. Def.’s Mot., Aug. 7, 2014, ECF No. 35-1. Plaintiff filed its cross-motion for
    partial summary judgment on the funded-research question. Pl.’s Mot., Aug. 20, 2014,
    ECF No. 37-1. Defendant filed its response. Def.’s Resp., Sept. 26, 2014, ECF No. 40.
    Plaintiff filed a reply. Pl.’s Reply, Oct. 22, 2014, ECF No. 41.
    Defendant also filed various exhibits in support of its motion. Exs. 1.1 to 69, ECF
    Nos. 30-2 to 32.9. Plaintiff likewise supported its motion with both affidavits and
    exhibits. Exs. A to P, ECF No. 37-2.
    In reviewing the parties’ briefing, there were several questions on which the court
    felt it would benefit from additional explanation. Accordingly, on January 28, 2015, the
    court issued an order posing a number of questions to the parties, and requesting
    comment. Order Supp. Br., ECF No. 42.
    2
    On February 19, 2015, each party filed a supplemental brief in support of its
    motion for partial summary judgment. Pl.’s Supp. Br., ECF No. 45; Def.’s Supp. Br.,
    ECF No. 46. On February 26, 2015, each party filed a reply. Pl.’s Reply to Def.’s Supp.
    Br., ECF No. 47; Def.’s Reply to Pl.’s Supp. Br., ECF No. 48.
    The court is grateful to both parties for their supplemental briefing, which has
    been helpful in resolving their cross-motions.
    B.     Sample Contracts
    Each of the sample contracts is known by an alpha-numeric code assigned by
    Dynetics for internal contract management purposes. Like the parties, the court refers to
    each contract by this code.
    Dynetics was awarded the AF007 contract (contract no. F08630-03-C-0034) by
    the United States Air Force Research Laboratory, pursuant to which it was “to develop
    and test 14 tailkits capable of carrying 21,600 pound of ammunition for deployment at a
    specified target.” Ex. 12; Pl.’s Mot. 38. The AF007 contract was a cost-plus-fixed-fee
    contract. Id. at DYN 953.
    The AMS01 contract (subcontract no. 017-O2K1) was issued to Dynetics by
    Aviation & Missile Solutions, LLC (AMS) as a subcontract. Ex. 51, at DYN 7568.
    The prime contract was issued to AMS by the U.S. Army Aviation and Missile Command
    (AMCOM). Id. at DYN 7569. AMCOM is a specialized research and development
    command with the Army Research Development and Engineering Command. Pl.’s Mot.
    42. AMS is a joint venture between Dynetics and one other company, Camber. Id. at 43.
    The work performed by Dynetics under the AMS01 contract was performed on task
    orders issued as fixed-price-level-of-effort. Id. at 45-46; Def.’s Mot. 38. According to
    Dynetics, work on the AMS01 contract included “develop[ing] models and simulations to
    evaluate the effectiveness of missile defense systems, [as well as] developing technology
    and designing hardware that would enable the integration of applicable devices onto
    applicable platforms. [In addition, Dynetics] designed, analyzed, and tested warheads,
    fuzes, fuse systems, and technologies to integrate fuzes and warheads in constrained
    weapons systems.” Pl.’s Mot. 43.
    The AR005 contract (contract no. DAAH01-02-C0080) was issued to Dynetics by
    the U.S. Army Aviation & Missile Command. Ex. 27, at DYN 58336. The AR005
    contract included both fixed-price and cost-plus-fixed-fee line items. Id. at DYN 58339-
    41. As relevant to this motion, defendant objects only to expenses Dynetics claims under
    the cost-plus-fixed-fee line items. See Def.’s Mot. 27. According to Dynetics, its work
    3
    on the AR005 contract included developing “calibration shelters for Humvees that were
    deployed ‘in theater’” by the Army. Pl.’s Mot. 50. The purpose of this project was to
    “make it easier for soldiers to calibrate their equipment in the field rather than evacuating
    it for calibration.” Id.
    The BOE12 contract (contract no. 100267) was issued to Dynetics by The Boeing
    Company. Ex. 40, at DYN 41546. The BOE12 contract was a time-and-materials
    contract. See id. at DYN 41557-58. According to Dynetics, its work on the BOE12
    contract included “assisting in the development of a system to defend the United States
    against long-range (i.e., intercontinental) ballistic missile attacks.” Pl.’s Mot. 59.
    The NT001 contract (contract no. MDA908-99-D-0001) was issued to Dynetics by
    the Defense Intelligence Agency (DIA) Missile & Space Intelligence Center (MSIC). Ex.
    34, at DYN 8064. DIA is a combat support agency within the U.S. Department of
    Defense. The NT001 contract is a cost-plus-fixed-fee contract. Id. at DYN 8067.
    According to Dynetics, it was assigned tasks “associated with gaining an understanding
    [of] foreign missile systems and the United States’ capability of defending against threats
    posed by those foreign systems.” Pl.’s Mot. 64.
    The UAH01 contract (subcontract no. SUB2004-025) was issued to Dynetics by
    the University of Alabama, Huntsville (the University) as a subcontract. Ex. 18, at DYN
    1700. A cooperative agreement was issued to the University by the National Aeronautics
    and Space Administration (NASA)/Marshall Space Flight Center. Id. at DYN 1701.
    The UAH01 contract was a cost-plus-fixed-fee level-of-effort contract. Id. at DYN 1700.
    Under the UAH01 contract, Dynetics performed various tasks in support of the National
    Space Science & Technology Center. Pl.’s Mot. 70.
    The AR009 contract (contract no. DAAH01-02-C-R170) was issued to Dynetics
    by the U.S. Army Aviation & Missile Command. Ex. 47, at DYN 6933. The AR009
    contract was a fixed-price level-of-effort contract. Under the AR009 contract, Dynetics
    was asked to “design, develop, and test aerodynamic vehicles, including missiles,
    aviation systems, and targets [, and it] used aerodynamic engineering techniques to
    develop or design proposed missiles or analyze properties of proposed missiles.” Pl.’s
    Mot. 53 (internal citation omitted).
    II.    Legal Standards
    A.     Jurisdiction
    4
    The United States Court of Federal Claims shall have jurisdiction to render
    judgment upon any claim against the United States founded either upon the Constitution,
    or any Act of Congress or any regulation of an executive department, or upon any express
    or implied contract with the United States, or for liquidated or unliquidated damages in
    cases not sounding in tort. 
    28 U.S.C. § 1491
    (a)(1)(2012). This court has jurisdiction,
    concurrent with the district courts, over “[a]ny civil action against the United States for
    the recovery of any internal-revenue tax alleged to have been erroneously or illegally
    assessed or collected, or any penalty claimed to have been collected without authority or
    any sum alleged to have been excessive or in any manner wrongfully collected under the
    internal-revenue laws.” 
    28 U.S.C. § 1346
    (a)(1); see also Intersport Fashions West, Inc. v.
    United States, 
    84 Fed. Cl. 454
    , 456-57 (2008) (finding jurisdiction over tax refund claim).
    That the court has jurisdiction over plaintiff’s claim is undisputed.
    B.     Summary Judgment
    Summary judgment is appropriate “if the movant shows that there is no genuine
    dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
    RCFC 56(a); see Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 247-48 (1986); Celotex
    Corp. v. Catrett, 
    477 U.S. 317
    , 322-23 (1986). A genuine dispute is one that “may
    reasonably be resolved in favor of either party.” Liberty Lobby, 
    477 U.S. at 250
    .
    “As to materiality, the substantive law will identify which facts are material. Only
    disputes over facts that might affect the outcome of the suit under the governing law will
    properly preclude the entry of summary judgment.” 
    Id. at 248
    .
    The moving party carries the burden of establishing its entitlement to summary
    judgment. Celotex Corp., 
    477 U.S. at 322-23
    . Once that burden is met, the onus shifts to
    the non-movant to identify evidence demonstrating a dispute over a material fact that
    would allow a reasonable finder of fact to rule in its favor. Liberty Lobby, 
    477 U.S. at 256
    .
    In considering a motion for summary judgment, the court does not weigh each
    side’s evidence but, rather, must draw all inferences in the light most favorable to the
    nonmoving party. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 
    475 U.S. 574
    , 587-
    88 (1986). Where, as here, the parties have filed cross-motions for summary judgment,
    the court evaluates each motion on its own merits and makes all reasonable inferences
    against the party whose motion is under consideration. Marriot Int’l Resorts, L.P. v.
    United States, 
    586 F.3d 962
    , 968-69 (Fed. Cir. 2009). To the extent there exists a
    genuine issue of material fact, both motions must be denied. 
    Id. at 969
    .
    5
    The court evaluates the parties’ motions for partial summary judgment under these
    standards.
    C.     Tax Refund Claims
    It is well settled that in a tax refund case, like this one, there is a presumption of
    the correctness of the findings of the Commissioner of Internal Revenue. See, e.g.,
    Bubble Room, Inc. v. United States, 
    159 F.3d 553
    , 561 (Fed. Cir. 1998); Estate of
    Rubinstein v. United States, 
    119 Fed. Cl. 658
    , 667 (2015) (“[T]he assessment made by
    the [IRS] is presumed to be correct and this places an obligation on the taxpayer . . . to
    rebut a presumption of correctness.”) (quotation marks omitted).
    In a tax refund case, the ruling of the Commissioner of Internal
    Revenue is presumed correct. To rebut this presumption of correctness, the
    taxpayer must come forward with enough evidence to support a finding
    contrary to the Commissioner’s determination. In addition, the taxpayer has
    the burden of establishing entitlement to the specific refund amount claimed.
    Bubble Room, Inc., 159 F.3d at 561 (internal citations omitted). “[I]n a refund suit, a
    taxpayer has the burden of proving by a preponderance of the evidence that the
    assessment or determination is incorrect and the correct amount, if any, of tax.” Cook v.
    United States, 
    46 Fed. Cl. 110
    , 116 (2000) (citing Helvering v. Taylor, 
    293 U.S. 507
    ,
    515 (1935) (“[u]nquestionably the burden of proof is on the taxpayer”)).
    The court considers plaintiff’s claim in light of these burdens of proof.
    D.     Research Tax Credit
    The Internal Revenue Code specifies when a taxpayer may take a credit for
    “qualified research expenses (QREs).” I.R.C. § 41(a)-(b). Qualified research excludes
    “[a]ny research to the extent funded by any grant, contract, or otherwise by another
    person (or governmental entity).” I.R.C. § 41(d)(4)(H) (funded research exception).
    The regulations implementing § 41 similarly state that
    [q]ualified research does not include any research to the extent funded by
    any grant, contract, or otherwise by another (or governmental entity). To
    determine the extent to which research is so funded, § 1.41-4A(d) applies.
    6
    
    Treas. Reg. § 1.41-4
    (c)(9)). In turn, § 1.41-4A(d) further explains that research is funded
    under either of two circumstances. First, research is funded if the taxpayer receives
    payment that is not “contingent on the success of the research.” 
    Treas. Reg. § 1.41
    -
    4A(d)(1).
    Research does not constitute qualified research to the extent it is funded by
    any grant, contract, or otherwise by another person (including any
    governmental entity). All agreements (not only research contracts) entered
    into between the taxpayer performing the research and other persons shall be
    considered in determining the extent to which the research is funded.
    Amounts payable under any agreement that are contingent on the success of
    the research and thus considered to be paid for the product or result of the
    research (see § 1.41-2(e)(2)) are not treated as funding.
    
    Treas. Reg. § 1.41
    -4A(d)(1). Under § 1.41-4A(d)(1), if a taxpayer is paid for the results
    of the research regardless of whether those results are successful, the research is funded,
    and the taxpayer is ineligible for a tax credit. Alternatively, if payment is “contingent on
    the success of the research and thus considered to be paid for the product,” the research is
    not funded, and the taxpayer is eligible for the tax credit, assuming satisfaction of
    remaining § 41 requirements.
    Second, research is funded if the taxpayer performing research for another person
    or governmental entity “retains no substantial rights” in the research. 
    Treas. Reg. § 1.41
    -
    4A(d)(2).
    If a taxpayer performing research for another person retains no substantial
    rights in research under the agreement providing for the research, the
    research is treated as fully funded for purposes of section 41(d)(4)(H), and
    no expenses paid or incurred by the taxpayer in performing the research are
    qualified research expenses. For example, if the taxpayer performs research
    under an agreement that confers on another person the exclusive right to
    exploit the results of the research, the taxpayer is not performing qualified
    research because the research is treated as fully funded under this paragraph
    (d)(2). Incidental benefits to the taxpayer from performance of the research
    (for example, increased experience in a field of research) do not constitute
    substantial rights in the research.
    
    Treas. Reg. § 1.41
    -4A(d)(2).
    III.   Discussion – Whether Payment was Contingent on the Success of Research
    7
    Plaintiff makes a number of arguments in support of its position that the research it
    performed under each of the seven sample contracts was not funded, that is, it would be
    paid for the results of the research only if those results were successful.
    First, plaintiff argues that it had an established course of dealing with its
    contracting partner in each of six sample contracts, in which, regardless of the plain terms
    of each contract, it was expected to produce a successful result in order to receive
    payment. Next, plaintiff argues that each of the seven sample contracts included either an
    inspection clause or a warranty clause that expressly put Dynetics at financial risk of not
    being paid unless the results of its research were successful. Plaintiff relies most heavily
    on these two arguments.
    In addition, plaintiff argues that it faced certain risks if it failed to produce
    successful research, that termination clauses in each sample contract put it at risk of
    nonpayment, and that in the case of three sample contracts, the fact that the contract was
    initially issued as an undefinitized contract put it at risk.
    Defendant responds in opposition to each argument, insisting that under each
    sample contract, Dynetics would be paid regardless of whether its research was
    successful or not. In addition, defendant argues that Dynetics failed to retain substantial
    rights in the results of its research for two sample contracts. Accordingly, argues
    defendant, even if Dynetics was able to show that its research was not funded for these
    two contracts, Dynetics would still be ineligible for the tax credit. Plaintiff disagrees,
    insisting it did retain substantial rights in the results of the research for both sample
    contracts.
    The court considers plaintiff’s arguments in turn, and then defendant’s argument.
    A.     Course of Dealing
    Dynetics argues that a course of dealing existed between it and its contracting
    partner in each of six of the sample contracts at issue in this motion, through which it was
    obligated to deliver a particular result, not merely a number of hours of service or a level
    of effort.1
    1
    Dynetics makes no argument that a course of dealing existed for the UAH01
    contract. See Pl.’s Mot. 70-73 (offering no course of dealing argument for the UAH01
    contract); Pl.’s Reply 11-14 (making no argument that the UAH01 contract was
    ambiguous).
    8
    Dynetics understood, based on its long-term relationships with its customers
    that it had to successfully produce a product within the estimated cost to
    receive any payment in some cases and to secure future work under the
    contract in other cases. In both circumstances, Dynetics bore the financial
    risk of failed research.
    Pl.’s Mot. 22. In Dynetics’ view, under the course of dealing established with its
    contracting partners, each of the six sample contracts functioned as a fixed-price
    contract under which Dynetics was obligated to “produce a product,” and for
    which Dynetics would be paid a fixed price, regardless of its actual costs. See 
    id.
    Defendant argues first that plaintiff’s course of dealing argument is parol
    evidence. Def.’s Resp. 15-16. The court may only consider such evidence if the
    contracts are ambiguous. Def.’s Resp. 15-16. Defendant insists they are not. Def.’s
    Resp. 15-16.
    Second, defendant asserts that even if the court were to consider plaintiff’s
    argument, the evidence might reflect that Dynetics “had a unilateral policy that it would
    continue performing research, at its own expense, in order to generate the desired
    outcome, after the ceiling price of a contract or task order had been reached,” but such
    evidence falls well short of showing a “joint understanding” between Dynetics and its
    contracting partners. 
    Id. at 16-17
    .
    Defendant is correct as to both of its arguments.
    1.     Parol Evidence
    A party’s “attempt to vary the clear meaning of [a contract] in accordance with the
    parties’ course of dealing is improper under the parol evidence rule.” Alves v. United
    States, 
    133 F.3d 1454
    , 1459 (Fed. Cir. 1998) (internal quotation marks omitted).
    When construing a contract, a court first examines the plain meaning
    of its express terms. The parol evidence rule is a rule of substantive law that
    prohibits the use of external evidence to add to or otherwise modify the terms
    of a written agreement “in instances where the written agreement has been
    adopted by the parties as an expression of their final understanding. The rule
    thus renders inadmissible evidence introduced to modify, supplement, or
    interpret the terms of an integrated agreement. Evidence of the parties’
    course of dealing constitutes this kind of parol evidence that is prohibited by
    the rule. If the terms of a contract are clear and unambiguous, they must be
    9
    given their plain meaning—extrinsic evidence is inadmissible to interpret
    them.
    Barron Bancshares, Inc. v. United States, 
    366 F.3d 1360
    , 1375-76 (Fed. Cir. 2004)
    (emphasis added) (internal citations and quotation marks omitted).
    The Federal Circuit has described the circumstance in which a contract might be
    deemed ambiguous. “When a contract is susceptible to more than one reasonable
    interpretation, it contains an ambiguity. To show an ambiguity[,] it is not enough that the
    parties differ in their respective interpretations of a contract term. Rather, both
    interpretations must fall within a zone of reasonableness.” Metric Constructors, Inc. v.
    NASA, 
    169 F.3d 747
    , 751 (Fed. Cir. 1999) (internal citations and quotation marks
    omitted).
    Plaintiff initially made no argument that any of the six sample contracts were
    ambiguous. See Pl.’s Mot. 22-23. In its reply brief, plaintiff argued that, assuming
    contractual ambiguity was necessary for consideration of any course of dealing, each
    contract was in fact ambiguous. See Pl.’s Reply 10-14.
    Dynetics argues that during the briefing of this motion, the parties “have disagreed
    about the rights and obligations of Dynetics and the United States pursuant to these
    contracts . . . demonstrating that the contracts are unclear and ambiguous.” Pl.’s Reply
    11. Plaintiff is mistaken. The mere fact that the parties disagree is not evidence of
    contractual ambiguity. See Metric Constructors, Inc., 
    169 F.3d at 751
    .
    Plaintiff further argues that various contracts: (1) incorporate FAR provisions that
    rely on a term that is never defined (AF007, AMS01, NT001); (2) contain more than one
    inspection clause (AMS01 and AR009); (3) fail to include the appropriate inspection
    clause (AR005); or (4) were modified frequently by the parties, suggesting a lack of
    clarity (BOE12). See Pl.’s Reply 11-14.
    Regarding the “undefined terms,” Dynetics points to “best efforts” in various
    contracts, “allowable cost” in at least the AF007 and NT001 contracts, and the basis for
    invoice “approval” in at least the AMS01 contract. Even if the court were to assume that
    ambiguity in the contracts existed, it would be a patent ambiguity, because the terms
    about which plaintiff now complains are found in the FAR—the provisions of which are
    incorporated expressly in the contract. Under the patent ambiguity doctrine, contract
    ambiguities must be read in the government’s favor due to the contractor’s duty to
    inquire. Gen. Eng’g & Mach. Works v. O’Keefe, 
    991 F.2d 775
    , 781 (Fed. Cir. 1993).
    The Federal Circuit has made clear that “[a]lthough we do not wish to penalize a
    10
    contractor because of a contract that was poorly drafted by the government, the very fact
    that [a] contract is patently ambiguous places a burden on the contractor to seek
    clarification. . . . [If the contractor] failed to do so[,] it must . . . lose on its claim . . . .”
    Interstate Gen. Gov’t Contractors, Inc. v. Stone, 
    980 F.2d 1433
    , 1436 (Fed. Cir. 1992).
    Thus, even if a patent ambiguity existed, Dynetics could not benefit from it.
    Further, Dynetics makes no argument regarding how the terms it now considers
    ambiguous are relevant to the question of whether any of the six sample contracts
    required Dynetics to produce a particular product, rather than to provide hours of service
    or a level of effort. And if the allegedly ambiguous terms on which Dynetics asks the
    court to focus do not speak to the issue of what the contracts required Dynetics to do,
    plaintiff’s course of dealing argument is unavailing.
    Regarding the inspection clauses, as discussed infra Parts III.B.–F, Dynetics’
    arguments do not persuade either that the inspection clauses put it at financial risk, or that
    it was unclear which inspection clause applied to which contract. Moreover, even if
    multiple or missing inspection clauses caused ambiguity—as Dynetics’ claims—the
    ambiguity would be a patent ambiguity, and this fails to assist Dynetics. See Interstate
    Gen. Gov’t Contractors, Inc., 
    980 F.2d at 1436
    .
    That a contract is modified, as the BOE12 contract was many times, is not itself
    evidence of ambiguity. As plaintiff itself noted, “[t]he award of the [BOE12] contract did
    not authorize any work. Boeing would then modify the contract to add a new line item
    that would both allot funds and specify the work required to be done.” Pl.’s Mot. 59-60.
    Plaintiff makes no argument, nor could it, that the plain text of any of the six
    sample contracts was “susceptible to more than one reasonable meaning” as to whether
    Dynetics was responsible for delivering a particular result for the contracted price—as it
    would be in a fixed-price contract—or whether it was responsible only for delivering a
    certain number of hours of service or a certain level of effort—as it would be in the cost-
    reimbursement, time-and-materials, and fixed-price level-of-effort contracts at issue here.
    Plaintiff’s attempts to identify ambiguities are not convincing. Accordingly, in deciding
    the parties’ cross-motions for partial summary judgment, the court does not consider the
    parole evidence plaintiff seeks to introduce regarding its course of dealing with each of
    its six contracting partners.
    Nonetheless, the court is mindful that the sample contracts at issue in this motion
    are but a few of the contracts at issue in this matter. Solely for the purpose of providing
    the parties with information that might prove useful to them in resolving their remaining
    11
    disputes, the court addresses plaintiff’s course of dealing argument, including all
    evidence filed by Dynetics.2
    2.     Whether a Course of Dealing Existed Between Dynetics and its Contracting
    Partners
    Course of dealing relies on a “shared understanding” between the parties, which in
    certain situations can be used to clarify or supplement written contractual terms. See
    Sperry Flight Sys. Div. of Sperry Rand Corp. v. United States, 
    548 F.2d 915
    , 923 (Ct. Cl.
    1977) (“[A] course of dealing can supply an enforceable term to a contract (or may even
    supplement or qualify that contract) provided that the conduct which identifies that
    course of dealing can reasonably be construed as indicative of the parties’ intentions—a
    reflection of their joint or common understanding.”).
    Plaintiff’s evidence of a joint or common understanding is limited to affidavits,
    see Exs. B-I, six of which are provided by Dynetics’ employees. Defendant responds that
    “[f]or five of the contracts (AF007, AR005, BOE12, AR009, and AMS01), Dynetics
    presents evidence only of its own understanding of its commitments and obligations and
    no admissible evidence of the state of mind of the other contracting parties.”
    Review of each affidavit shows that defendant is correct, Dynetics either states its
    own unilateral contract management practices, or states its position on what it believes its
    contracting partner “understood.”
    To protect its reputation and demonstrate its commitment to providing
    desired results within its estimated costs, Dynetics would have taken any cost
    overruns out of its fee rather than ask the government for more money.
    2
    Plaintiff filed eight affidavits in support of its course of dealing argument. See
    Exs. B-I. Defendant objects to the court’s consideration of one affidavit in its entirety, as
    well as to specified paragraphs in the remaining affidavits. Def.’s Objections to Evidence
    Submitted by Plaintiff in Support of Its Cross-Motion for Partial Summary Judgment,
    ECF No. 40-1 (Def.’s Objs.); Supplemental Declaration of Jason Bergmann in
    Opposition to Plaintiff’s Cross-Motion for Summary Judgment, ECF No. 40-2. As the
    court does not consider plaintiff’s course of dealing argument in its resolution of the
    parties’ cross-motions, it is unnecessary to rule on defendant’s objections to plaintiff’s
    evidence. The parties should draw no inference as to the admissibility of plaintiff’s
    evidence from the mere fact that for the limited purpose of assisting the parties in
    resolving the remainder of their disputes, the court considers plaintiff’s evidence in its
    entirety.
    12
    Hug Aff. ¶ 19, Ex. E (AF007).
    Both Dynetics and the U.S. Army understood that Dynetics would rework
    any defective or unacceptable products produced under the AR005 contract
    at its own cost, regardless of whether the product was required by a fixed-
    price or cost-plus-fixed-fee CLIN.
    Williams Aff. ¶ 14, Ex. D (AR005).
    During our relationship with Boeing, we made Boeing aware of Dynetics’
    commitment to delivery [of] technically superior products within the cost
    estimates provided.
    Bendickson Aff. ¶ 25, Ex. I (BOE12).
    It was Dynetics’ practice to rework any defective or unacceptable work
    product required by the contract at its own cost, regardless of the terms of the
    contract. [The U.S. Army] was aware of Dynetics’ commitment to provide
    a technically superior product within the cost estimates, even if that meant
    reworking the product at its own cost.
    Walker Aff. ¶ 22, Ex. H (AR009).
    [I]t was Dynetics’ practice to finish any incomplete work or repair any
    deficient products at its own costs (regardless of whether Dynetics was
    technically obligated to do so under the contract), rather than risk losing
    future work under the Omnibus 2000 contract or any other contract with
    AMCOM.
    Miller Aff. ¶ 29, Ex. C (AMS01).
    It was Dynetics’ practice to rework defective or unacceptable deliverables at
    its own costs, regardless of whether the terms of the contract imposed this
    requirement on Dynetics.
    Nicaise Aff. ¶ 14, Ex. G (All contracts).
    Regarding the sixth contract, the NT001 contract with the Missile and Space
    Intelligence Center (MSIC), Dynetics filed affidavits from a current Dynetics employee
    13
    who was previously a MSIC employee, Patrick Keller, and a retired MSIC contracting
    officer, Steven Thomason. See Exs. B (Thomason) & F (Keller).
    Mr. Thomason affirms that he was the contracting officer for the NT001 contract
    during the relevant time period, July 1, 2002 through June 30, 2005. Thomason Aff. ¶ 4.
    Mr. Thomason provided statements regarding his management of the NT001 contract.
    In working with Dynetics on the [NT001] Contract, I made it clear
    that I expected all tasks to be completed within the amount listed in each
    delivery order and that I would not modify the delivery orders to allot
    additional funds if Dynetics was unable to complete the task within the funds
    originally allotted, barring some unforeseen circumstance that was outside of
    Dynetics’ control.
    Thomason Aff. ¶ 15.
    Dynetics also knew if a deliverable for a task was incomplete or
    defective[,] it was unacceptable. Furthermore, Dynetics was aware that I
    would expect the company to go back and rework any unacceptable
    deliverables at its own cost and that I would not authorize additional funds
    to rework a defective deliverable.
    
    Id. ¶ 17
    .
    Dynetics relied on these paragraphs in the Thomason affidavit to argue that “even
    if the [NT001] contract were not ambiguous, the long-term course of dealing, which had
    been accepted by both parties, would supplement the contract by reflecting the parties’
    intent.” Pl.’s Reply 14. Dynetics is mistaken. If the NT001 contract is not ambiguous,
    the court may not consider parol evidence, including the parties’ alleged course of
    dealing. See. e.g., Barron Bancshares, 
    366 F.3d at 1375-76
    .
    Dynetics also failed to show that Mr. Thomason had the authority to make the
    types of changes to the NT001 contract that he asserts he made—that is, managing the
    contract effectively as a fixed-price contract, despite the fact that the express terms of the
    written contract provided for a cost-plus-fixed-fee contract.
    The NT001 contract expressly incorporated a Limitation of Cost clause. Ex. 34, at
    DYN 8099 ¶ I.75 (FAR 52.232-20 Limitation of Cost (Apr. 1984)). In relevant part,
    FAR 52.232-20 provides that,
    14
    [t]he Contractor is not obligated to continue performance under this contract
    (including actions under the Termination clause of this contract) or otherwise
    incur costs in excess of the estimated cost specified in the Schedule, until the
    Contracting Officer (i) notifies the Contractor in writing that the estimated
    cost has been increased and (ii) provides a revised estimated total cost of
    performing this contract.
    FAR 52.232-20(d)(2). Simply put, under the Limitation of Cost clause, if the allocated
    funds for the NT001 contract were exhausted, Dynetics was not obligated to continue
    work. Dynetics argues that, in effect, Mr. Thomason had the authority to disregard the
    plain language of the contract, as provided in the Limitation of Cost clause, and compel
    Dynetics to produce unfunded work. But Dynetics fails to show that Mr. Thomason had
    any such authority.
    In fact, the express terms of the NT001 contract show otherwise. The contractual
    terms indicate that such a change was outside of Mr. Thomason’s authority, and that
    changes to the contract were to be made by written order. The NT001 contract expressly
    incorporated a Changes clause enumerating the six type of changes a contracting officer,
    like Mr. Thomason, was authorized to make to the contract—by written order. See Ex.
    34, at DYN 8101 (incorporating FAR 52.243-2 Changes–Cost-Reimbursement (Aug.
    1987) – Alternate II). Those six changes were: (1) description of services to be
    performed; (2) time of performance; (3) place of performance; (4) drawings, designs, or
    specifications under certain circumstances; (5) method of shipment or packing of
    supplies; and (6) place of delivery. FAR 52.243-2 Alt. II.
    Nothing in the Changes clause could be read to authorize a contracting officer to
    make any change to the NT001 contract other than by “written order.” Furthermore,
    nothing in the Changes clause could be read to authorize a contracting officer to override
    the express terms of the contract and to change it from a cost-plus-fixed-fee contract to a
    fixed-price contract—by either written order or oral understanding. The changes to the
    NT001 contract for which Dynetics relies on Mr. Thomason’s affirmations are beyond
    his authority, as set forth in the Changes clause, and nothing in the record suggests that
    Mr. Thomason had authority over the NT001 contract beyond that provided in the
    Changes clause. See Thomason Aff. ¶¶ 7-8 (describing contracting officer duties and
    authority). In addition, nothing in the record suggests that Mr. Thomason, a former
    MSIC employee, had authority to present MSIC’s position on its management of the
    NT001 contract.
    Dynetics also filed an affidavit from Mr. Keller, who in his previous role as
    15
    MSIC Deputy Director was responsible for the overall execution of the MSIC’s mission.
    Keller Aff. ¶ 4. Mr. Keller affirmed that “his primary area of expertise is the technical
    aspects of the weapons systems involved in the [Defensive Systems Analysis] contracts.”
    Id. ¶ 5. Mr. Keller did not state that he had any personal knowledge about or
    involvement with the NT001 contract during his MSIC employment, or for that matter,
    during his current employment with Dynetics. The only mention of the NT001 contract
    by Mr. Keller was his statement that “Contract MDA908-99-D-0001 was one of DSA
    contracts awarded to Dynetics by MSIC. It was issued to Dynetics in 1999 and was
    given the project code NT001 by Dynetics.” Id. ¶ 6. While true, this statement provides
    no support for Dynetics’ assertions of a course of dealing under the NT001 contract.
    As defendant correctly points out, Dynetics has failed to provide the requisite
    evidence of any “joint understanding” between it and each of its contracting partners.
    Def.’s Resp. 16-17.
    3.     “All Agreements”
    Finally, Dynetics argues that the Treasury regulations “require” the court to
    consider the “agreements” it had with its contracting partners. See Pl.’s Reply 10.
    Dynetics insists:
    [T]he course of dealing and understandings with the government reflect
    agreements between Dynetics and the government with respect to the
    research and development done under the contracts. These “agreements” are
    required to be considered by the Treasury Regulations. 
    Treas. Reg. § 1.41
    -
    4A(d)(1) (“All agreements (not only research contracts) entered into between
    the taxpayer performing the research and other persons shall be considered
    in determining the extent to which the research is funded.”). Therefore, even
    if not permitted in the contract interpretation context, the course of dealing
    must be considered pursuant to the Treasury Regulations when determining
    the “funding” issue.
    
    Id.
     But, Dynetics is mistaken; the Treasury regulations require no such thing. First,
    Dynetics assumes what it seeks to prove, in particular, that it had an “agreement” with
    any of the six contracting partners for which it has pressed this argument. Second, the
    agreement contemplated in the Treasury regulation is not present here. The term
    “agreement” is defined in the FAR, which governs government contracts like those at
    issue here. An “agreement” is defined as a “written instrument of understanding,” that is
    “not a contract.” FAR 16.702(a), 16.703(a). Clearly, the reference to “agreements” in
    16
    the Treasury regulations does not encompass what Dynetics asserts is a course of dealing
    between it and its contracting partners.
    For all these reasons, if any of the six sample contracts were ambiguous, which
    they are not, see supra Part III.A.1., and the court considered plaintiff’s affidavits in their
    entirety, a question on which it makes no decision, see supra note 2, plaintiff’s evidence
    would still fail to show a joint understanding that would support a finding that a course of
    dealing existed between Dynetics and any of its contracting partners in the AF007,
    AR005, NT001, BOE12, AR009, or AMS01 contracts.
    B.     Inspection Clauses – AF007 and NT001 Contracts
    Incorporated into the AF007 contract as the inspection clause is FAR 52.246-8
    Inspection of Research and Development–Cost-Reimbursement (May 2001). Ex. 12, at
    DYN 957. Dynetics argues that this inspection clause is like one at issue in the contract
    discussed in Fairchild Industries, Inc. v. United States, 
    71 F.3d 868
    , 873 (Fed. Cir. 1996).
    Given the similar inspection clauses, Dynetics urges that its contract is like the contract in
    Fairchild, which the Federal Circuit found “demonstrate[d] the shift of risk to the
    contractor.” Pl.’s Mot. 41 (citing Fairchild, 
    71 F.3d at 873
    ).
    Dynetics is mistaken in its reading of Fairchild. The flaw in Dynetics’ position is
    that it assumes the Federal Circuit based its decision on the incorporated inspection
    clause alone. The appellate court did not. Rather, it clearly based its decision on the text
    of the contract, as well as on the inspection, rejection, and payment clauses incorporated
    into the contract. Fairchild, 
    71 F.3d at 871
     (“The . . . contract provided that the Air Force
    was obligated to pay for the research only if Fairchild produced results that met the
    contract specifications, in accordance with certain provisions of the Defense Acquisition
    Regulations (DAR).”).
    The contract between Fairchild and the Air Force called for Fairchild to produce
    two prototype aircraft, according to a “contract [that] contained over 1,000 pages of
    technical specifications that required Fairchild to meet specific design, construction,
    quality, and performance standards.” Fairchild, 
    71 F.3d at 870
    . The contract included
    express language by which Fairchild accepted responsibility for producing the prototype
    aircraft, known as a Next Generation Trainer (NGT). According to the contract, “[t]he
    contractor hereby accepts Total System Responsibility for the NGT System,” with “total
    system responsibility” defined as the
    responsibility for the installation and integration of the NGT system
    elements, i.e., its systems, subsystems, components, support equipment, and
    17
    software/data; including the responsibility for undertaking any and all actions
    necessary to assure that the total system will meet all requirements as defined
    in the system specification . . . as identified in . . . this contract.
    Fairchild, 
    71 F.3d at 871
     (emphasis added). Thus according to the contract language,
    Fairchild explicitly accepted responsibility for doing whatever was necessary to produce
    prototype aircraft in compliance with the contract specifications. See Fairchild, 
    71 F.3d at 870
    . Unlike the contractor in Fairchild, Dynetics makes no assertion that it expressly
    accepted contractual responsibility for producing any product.
    The Federal Circuit in Fairchild also relied on two DAR provisions that were
    incorporated into the contract: one governing inspection and rejection, DAR 7-302.4,
    and the other covering payments, DAR 7-302.2.3 “If the work was deemed unacceptable,
    the Air Force could either (1) reject the work, (2) require Fairchild to correct the work at
    its own expense, or (3) accept the work subject to an equitable price reduction.”
    Fairchild, 
    71 F.3d at
    870 (citing DAR 7-302.4 (1976)). Fairchild would be paid for
    “work product delivered and accepted.” Fairchild, 
    71 F.3d at
    870 (citing DAR 7-302.2
    (1976)).
    The Fairchild inspection clause, which included rejection language, is
    included below.
    (a) All work under this contract shall be subject to inspection and test by
    the Government, to the extent practicable, at all times (including the period
    of performance) and places, and in any event prior to acceptance. . . .
    (b) The Government may reject any work that is defective or otherwise
    not in conformity with the requirements of this contract. If the Contractor
    fails or is unable to correct or to replace such work within the delivery
    schedule or such later time as the Contracting Officer may authorize, the
    Contracting Officer may accept such work at a reduction in price which is
    equitable under the circumstances.
    3
    The Defense Acquisition Regulations (DAR) were included as Title 32 of the
    Code of Federal Regulations until April 1, 1984. See FMC Corp. v. United States, 
    853 F.2d 882
    , 884 n.2 (Fed. Cir. 1988). Thus, the cited DAR are available as 
    32 C.F.R. § 7
    -
    302.4 and 
    32 C.F.R. § 7-302.2
    .
    18
    DAR 7-302.4 (a)-(b) (emphasis added).
    The relevant portion of FAR 52.246-8, the inspection clause incorporated into the
    AF007 contract—on which Dynetics relies, is as follows: “The Government has the right
    to inspect and test all work called for by the contract, to the extent practicable at all
    places and times, including the period of performance, and in any event before
    acceptance.” FAR 52.246-8(c). Dynetics is correct that the inspection language in FAR
    52.246-8(c) is like that found in DAR 7-302.4(a), the provision at issue in the Fairchild
    case. But the rejection language found in DAR 7-302.4(b) is wholly absent from FAR
    52.246-8, and Dynetics makes no assertion that such language was incorporated
    independently into the AF007 contract.
    Finally, the payments clause in the Fairchild contract provided that “[t]he
    Contractor shall be paid . . . [at] the prices stipulated herein for work delivered or
    rendered and accepted . . . .” DAR 7-302.2.
    The payments clause incorporated in the AF007 contract is FAR 52.216-7
    Allowable Cost and Payment (Dec. 2002). See Ex. 12, at DYN 964. Dynetics makes no
    argument that the payments clause in the AF007 contract included similar language to the
    payment clause in Fairchild that limited payment to work that the government
    “accepted.” Nor is such language apparent in a review of FAR 52.216-7.
    The Federal Circuit found that Fairchild was entitled to the research credit,
    because “[t]he contract explicitly placed solely on Fairchild the risk of failure of every
    line item . . . . The items to be produced were not commodities: all required research,
    development, and testing, to meet complex contract specifications.” Fairchild, 
    71 F.3d at 873
    . The same cannot be said of the AF007 contract. Dynetics did not bear such risk.
    Notwithstanding Dynetics’ arguments to the contrary, any similarity between the
    AF007 contract and the contract in Fairchild is limited to the inspection clause. The
    AF007 contract included no language that directed Dynetics to accept responsibility for
    producing a product. The AF007 contract did not include rejection language; nor did it
    limit payment to work the government accepted. The limited similarity between the
    inspection clauses does not support a finding that the AF007 contract was like the
    contract in Fairchild. Throughout its arguments based on the various inspection clauses
    relevant to the sample contracts, Dynetics has attempted to liken the sample contracts to
    the contract in Fairchild. For the same reasons discussed herein, none of the sample
    contracts are like the contract in Fairchild.
    19
    Dynetics adds that it was put at financial risk by the plain text of certain other
    provisions in FAR 52.246-8, insisting that
    FAR § 52.246-8 gives the government the right [to] require replacement or
    correction of “work not meeting contract requirements.” FAR § 52.246-8(f).
    Furthermore, if the contractor fails to proceed with “reasonable promptness
    to perform required replacement or correction, the Government may (i) [b]y
    contract or otherwise, perform the replacement or correction, [and] charge
    the Contractor any increased cost.” FAR § 52.246-8(g)(1).
    Pl.’s Mot. 41. But, Dynetics has not fully considered the FAR provision on which it
    relies.
    FAR 52.246-8(f) provides that
    [a]t any time during contract performance . . . the Government may require
    the Contractor to replace or correct work not meeting contract requirements.
    . . . Except as otherwise provided in paragraph (h) below, the cost of
    replacement or correction shall be determined as specified in the Allowable
    Cost and Payment clause, [FAR 52.216-7] but no additional fee shall be paid.
    FAR 52.246-8(f).
    A review of FAR 52.216-7, the payments clause incorporated into the AF007
    contract, shows that reimbursable costs include those “for items or services purchased
    directly for the contract.” FAR 52.216-7(b)(1)(i). There is no mention of excluding costs
    incurred to replace or correct work not meeting standards. As defendant correctly points
    out, while the contractor will be paid “no additional fee” for replacement or correction,
    “the denial of a ‘fee’ merely limits the contractor’s profit for the corrective work, but it
    does not preclude the contractor from recovering its costs.” Def.’s Resp. 11. Dynetics
    makes no assertion that in replacing or correcting its work it would not be paid. Nor does
    the language of FAR 52.246-8(f) support such a position.
    Under FAR 52.246-8(g), the government may charge the contractor for “increased
    cost” if the government has to perform the replacement or correction. FAR 52.246-
    8(g)(1)(i). However, as Dynetics correctly states, the government may only do so “[i]f
    the Contractor fails to proceed with reasonable promptness to perform required
    replacement or correction.” Id. Dynetics could be at financial risk under FAR 52.246-
    8(g)(1), but only if it “fails to proceed with reasonable promptness” to make the
    replacement or correction. FAR 52.246-8(g)(1). And, this risk is not attributable to the
    20
    failure of the research, which is the sole risk relevant to the tax credit. See 
    Treas. Reg. § 1.41
    -4A(d)(1) (“Amounts payable under any agreement that are contingent on the success
    of the research and thus considered to be paid for the product or result of the research . . .
    are not treated as funding.”).
    Dynetics’ arguments that FAR 52.246-8, as incorporated into the AF007 contract,
    put it at financial risk are unpersuasive.
    The NT001 contract incorporated FAR 52.246-5 Inspection of Services–Cost-
    Reimbursement (Apr. 1984). Ex. 34, at DYN 8075. The inspection language in FAR
    52.246-5(c) is identical to that in the inspection clause incorporated into the AF007
    contract, FAR 52.246-8(c), with the exception that FAR 52.246-5(c) provides for the
    inspection of “services,” rather than “work.”
    As it did with the AF007 contract, Dynetics argues that the inspection language in
    the NT001 contract, which incorporates FAR 52.246-5(c), is similar to that in DAR 7-
    302.4(a) and puts it at the same risk as in Fairchild. Pl.’s Mot. 68. But, as previously
    discussed, any similarity in the inspection language of FAR 52.246-5(c) and DAR 7-
    302.4(a), without more, is insufficient to put Dynetics at financial risk.
    C.     Inspection Clauses – AR009 and AMS01 Contracts
    The AR009 contract expressly incorporated two different clauses for inspection of
    research and development; one pertained to fixed-price contracts (FAR 52.246-7) and the
    other to cost-reimbursement contracts (FAR 52.246-8). Ex. 47, DYN 6946. The AR009
    contract is a firm-fixed-price, level-of-effort contract (FFP-LOE) for labor costs. See 
    id.
    at DYN 6954.
    The AMS01 contract expressly incorporated four different inspection clauses,
    respectively for fixed-price contracts (FAR 52.246-4), cost-reimbursement contracts
    (FAR 52.246-5), time-and-material and labor-hour contracts (FAR 52.246-6) and
    research and development contracts (short form) (FAR 52.246-9). See Ex. 51, at DYN
    7579. Plaintiff explained that multiple inspection clauses were included in the AMS01
    contract because the contract permitted “fixed rate[], fixed-price and/or cost plus fixed
    fee task orders.” Pl.’s Supp. Br. 17 (quoting Ex. 51, at DYN 7570). The parties agree
    that there are only five task orders at issue under the AMS01 contract, and all are FFP-
    LOE. Pl.’s Mot. 45-46 (“Each task order was issued on a fixed-price level of effort
    21
    basis.”);4 Def.’s Mot. 38 (“The five task orders provided for work on a fixed-rate level-
    of-effort basis.”).
    In arguing that it was put at financial risk by the inspection clause contained in
    each contract, Dynetics relied only on the fixed-price inspection clauses. See Pl.’s Mot.
    58 (FAR 52.246-7 under AR009); 
    Id. at 49
     (FAR 52.246-4 under AMS01). But, plaintiff
    did not explain how it could be at financial risk under any inspection clause, given the
    definition of a FFP-LOE contract provided in the FAR:
    A firm-fixed-price, level-of-effort term contract is suitable for investigation
    or study in a specific research and development area. The product of the
    contract is usually a report showing the results achieved through application
    of the required level of effort. However, payment is based on the effort
    expended rather than on the results achieved.
    FAR 16.207-2 Firm-Fixed-Price, Level-of-Effort Term Contracts – Application
    (emphasis added). The court asked the parties to reconcile arguments based on the fixed-
    price inspection clauses with the definition of a FFP-LOE contract provided in FAR
    16.207-2. See Order Supp. Br. 4-5.
    Dynetics responded that “in the case of both the AR009 and AMS01 contracts, the
    government defined deliverables that were expected as a pre-requisite to payment.” Pl.’s
    Supp. Br. 14-15. While acknowledging that “in theory” a contractor could satisfy FFP-
    LOE contract requirements by providing a specified level of effort, Pl.’s Supp. Br. 14,
    Dynetics argued that the AR009 and AMS01 contracts were not “typical” FFP-LOE
    contracts. Pl.’s Reply to Def.’s Supp. Br. 10. Rather, in Dynetics’ view, both contracts
    “appear to be hybrids, calculating a fixed price based on effort, but requiring delivery of
    specified items as a condition for payment.” 
    Id.
    As an example of deliverables, Dynetics points to Technical Directive Order 8
    (TDO 8) issued under the AR009 contract, which required Dynetics to “develop and
    deliver a long list of hardware items.” Pl.’s Supp. Br. 15 (citing Ex. 48, at DYN 62475).
    Review of TDO 8 shows that Dynetics is correct. TDO 8 required Dynetics’ effort on
    “Flight Hardware Fabrication” in support of “several flight tests to demonstrate
    4
    In its supplemental briefing, Dynetics seems to argue the task orders were fixed
    price, rather than firm-fixed-price, level-of-effort. See Pl.’s Supp. Br. 17-18. The record
    is clear, however, that the five task orders were firm-fixed-price, level-of-effort, with the
    government purchasing a specified number of labor hours. See Ex. 52, at 64293 (Task
    Order 27); Ex. 53, at DYN 64342 (Task Order 34); Ex.54 at DYN 64555 (Task Order
    53); Ex. 55 at DYN 65341 (Task Order 60); Ex. 56 at DYN 65373 (Task Order 64).
    22
    hypervelocity performance.” Ex. 48, at DYN 62475. Dynetics was required to “fabricate
    to print . . . hardware items in accordance with the design drawings provided . . . .” 
    Id.
    A list of twenty different hardware items, in various quantities, followed. 
    Id.
     at DYN
    62475-76.
    According to Dynetics, “[s]eeking specified deliverables is directly contrary to the
    applicable uses of [a] FFP-LOE [contract] under the FAR, which states that this contract
    form may only be used where ‘the work cannot otherwise be clearly defined.”’ Pl.’s
    Supp. Br. 15 (quoting FAR 16.207-3(a)). Plaintiff is mistaken, however, in its reliance
    on this provision of the FAR.
    The AR009 contract is a research & development contract. Ex. 47, at DYN 6933
    item 15 (“Kind of Contract: Research and Development Contract”). As used in FAR Part
    35 (Research and Development Contracting), the term “development” means
    the systematic use of scientific and technical knowledge in the design,
    development, testing, or evaluation of a potential new product or service (or
    of an improvement in an existing product or service) to meet specific
    performance requirements or objectives. It includes the functions of design
    engineering, prototyping, and engineering testing. . . .
    FAR 35.001. Part 35 of the FAR governing “contracting methods and contract type”
    provides that a FFP-LOE contract “may be useful for,” inter alia, “developing system
    design concepts.” FAR 35.006(d) (citing FAR 16.207, Firm-Fixed-Price, Level-of-Effort
    term contracts). Thus, a FFP-LOE contract is contemplated for development, and
    development includes prototyping and engineering testing, all of which require
    production of hardware. Contrary to Dynetics’ assertion, a specific deliverable does not
    contravene the FAR provisions governing FFP-LOE contracts.
    Dynetics adds that under the AMS01 contract, the government “likewise sought
    specific deliverables.” Pl.’s Supp. Br. 17. Unlike in its argument for the AR009 contract,
    Dynetics provided no specific examples from the task orders in the record. Regardless,
    for the reasons explained above, any argument based on the mere requirement of a
    deliverable would be insufficient to show that the AMS01 contract was other than a FFP-
    LOE contract.
    Dynetics also argued that both contracts seemingly functioned as hybrid contracts
    because the government permitted Dynetics to “vary its hours ‘by plus or minus 10%
    provided the total price for that specific [Technical Directive Order] option exercise is
    not exceeded.”’ 
    Id.
     at 16 (citing Ex. 47, at DYN 6949). Dynetics reasons that “[i]f the
    23
    government was just buying the ‘effort’ there would be no reason to vary the hours,
    because hours would be all that Dynetics was providing.” 
    Id.
    Review of the AR009 contract shows that the government specified the labor mix
    for each option, including the specific positions and the number of hours for each
    position. See Ex. 48, at DYN 6947. For example, an option would specify a certain
    number of hours of program manager time, senior engineer time, engineer time, etc. 
    Id.
    As Dynetics correctly points out, the government allowed it to shift time from one
    position to another, for example by using more engineer time but less senior engineer
    time, provided it did not exceed the total dollar amount contracted for that option. 
    Id.
     at
    DYN 6949. The government simply allowed Dynetics some flexibility and discretion in
    the labor mix of the “effort” it provided. Contrary to Dynetics’ assertion, nothing in this
    labor mix flexibility shows the government was buying anything other than a level of
    effort.
    Dynetics relied on a case from the U.S. Department of Agriculture Board of
    Contract Appeals (Board). In its briefing, Dynetics argued that the Board considered a
    contract “similar” to the AR009 and AMS01 contracts, and agreed “to treat the contract
    as firm-fixed-price, despite the contractor’s claim that it understood the contract to be
    fixed-price, level of effort.” Pl.’s Supp. Br. 18-19 (citing In re Mangi Envtl. Grp., Inc.,
    AGBCA Nos. 2005-101-1, 2005-102-1, 2005-103-1, 
    06-1 BCA ¶ 33,233
     (Mar. 7, 2006)).
    In that case, the contractor attempts to argue—during a dispute over costs it
    incurred above the contract amount—that because it had understood the contract to be
    FFP-LOE, not fixed-price, it was entitled to recover payment for its costs above the
    contracted dollar amount. Mangi, Fact 22. The Board found that the contract was firm-
    fixed-price; that is what the contract expressly stated, and during the bidding process, the
    contractor had acknowledged as much, in writing. Accordingly, this board case provides
    Dynetics with no support.
    Plaintiff has not shown that either the AR009 or AMS01 contract was anything
    other than a firm-fixed-price, level-of-effort contract. As plaintiff correctly
    acknowledged, in such a contract, the contractor only needs to provide a certain level of
    effort in order to be paid for its work. See Pl.’s Reply to Def.’s Supp. Br. 10. Dynetics
    has not shown that it was put at financial risk by the terms of any inspection clause
    incorporated into either the AR009 or AMS01 contract.
    D.     Inspection Clause – AR005 Contract
    24
    The AR005 contract includes three different line items, fixed price, cost-plus-
    fixed-fee and cost-reimbursement. The fixed-price line items provided for hardware
    production, the cost-plus-fixed-fee line items covered a specified number of hours of
    engineering services, and the cost-reimbursement line items supported travel and other
    direct expenses. (The latter two are referred to collectively as cost-reimbursement line
    items.) See, e.g., Ex. 27, at DYN 58339-42.
    Defendant objects only to expenses under the cost-reimbursement line items; it
    makes no objection to expenses under the fixed-price line items. Def.’s Mot. 27.
    According to defendant, Dynetics claimed QREs for wages in various amounts for each
    of the three tax years at issue in this motion, and these are the expenses for which
    defendant argues Dynetics may not take a tax credit under the AR005 contract. See 
    id.
    The AR005 contract incorporated only one inspection clause—FAR 52.246-2
    Inspection of Supplies–Fixed-Price (Aug. 1996). See Ex. 27, at DYN 58356. Defendant
    acknowledges that the absence of an inspection clause for the cost-reimbursement line
    items was an “oversight,” Def.’s Reply to Pl.’s Supp. Br. 9, likely attributable to the fact
    that the initial undefinitized AR005 letter contract expressed the intent of the Army to
    enter a fixed-price contract, which included no line items for engineering services, see
    Ex. 26, at DYN 36187-90. Regardless of the reason, it is apparent that the AR005
    contract includes both fixed-price and cost-reimbursement line items, while including
    only a fixed-price inspection clause. The parties disagree on the consequence of this
    oversight. Defendant has correctly described each party’s position as follows:
    Defendant contends that the fixed-price clauses apply by their terms only to
    the fixed-price CLINs, and the Court should read certain mandatory but
    omitted cost-reimbursement FAR clauses into the contract under the
    Christian doctrine.5 Disagreeing, Dynetics suggests that the Court must
    apply the specific fixed-price clauses in the AR005 Contract both to the
    fixed-price and cost reimbursement CLINs.
    Def.’s Reply to Pl.’s Supp. Br. 9 (footnote added).
    5
    “Under the Christian doctrine, a court may insert a clause into a government
    contract by operation of law if that clause is required under applicable federal
    administrative regulations.” Def.’s Resp. 4-5 (quoting Gen. Eng’g & Mach. Works v.
    O’Keefe, 
    991 F.2d 775
    , 779 (Fed. Cir. 1993); see also G.L. Christian & Assocs. v. United
    States, 
    160 Ct. Cl. 1
    , 12 (1963) (holding that “there was a legal requirement that the
    plaintiff’s contract contain the standard termination clause and the contract must be read
    as if it did”)).
    25
    The court first considers plaintiff’s argument that FAR 52.246-2 applies to the
    expenses for which it seek a tax credit, wages for engineering services. FAR 52.246-2
    governs the inspection of “supplies,” which “includes but is not limited to raw materials,
    components, intermediate assemblies, end products, and lots of supplies.” FAR 52.246-
    2(a). Dynetics failed to offer an explanation as to how wages for engineering services
    could fall within the definition of supplies provided in FAR 52.246-2.
    Rather, Dynetics’ approach was to argue that, notwithstanding that the line items
    in the AR005 contract were labeled expressly “cost plus fixed fee” e.g., Ex. 27, at DYN
    58340, the contract as a whole was a firm-fixed-price contract, and thus the fixed-price
    inspection clause, FAR 52.246-2, must apply to every line item. See Pl.’s Supp. Br. 9
    (“Because [FAR 52.246-2] is the only [inspection] clause specifically incorporated into
    the contract, it is relevant to the question of whether all of the work performed under the
    AR005 contract is funded. . . . ”); Pl.’s Reply to Def.’s Supp. Br. 4 (“The AR005 contract
    is designated by the government as “Firm-Fixed-Price”, notwithstanding the fact that
    certain CLINs are paid on a cost reimbursement basis.) (internal citation omitted).
    In support of this argument, Dynetics points to the first page of the AR005
    contract, which is a form contract, Standard Form 30 (SF 30). See Pl.’s Reply to Def.’s
    Supp. Br. 4 (citing Ex. 27, at DYN 58336). Item 1 on the first page of that contract is a
    small box labeled “Contract ID Code,” below which are the typed words “Firm-Fixed-
    Price.” Ex. 27, at 58336. In effect, Dynetics argues that the words typed into Item 1 state
    what type of contract the AR005 contract is. Review of the SF 30, and its instructions,
    shows that Dynetics is mistaken.
    The SF 30 and its instructions are available in the FAR. See FAR 53.301-30
    (Standard Form 30, Amendment of Solicitation/Modification of Contract). The following
    instruction is provided for SF 30 Item 1: “Item 1 (Contract ID Code). Insert the contract
    type identification code that appears in the title block of the contract being modified.”6
    Thus, the term “firm fixed price” describes the “contract being modified,” that is
    the earlier undefinitized letter contract, Ex. 26, not the definitized AR005 contract at
    issue in this motion, Ex. 27. That the undefinitized letter contract was a firm-fixed-price
    contract is undisputed. It is also irrelevant to this motion, as that contract included no
    line items for engineering services, the only disputed expenses in this motion.
    6
    A copy of the form is also available on the General Services Administration
    (GSA) website. GSA, http://www.gsa.gov/portal/forms/download/116158 (search “SF
    30”) (last visited May 22, 2015).
    26
    Dynetics has failed to show either that the AR005 contract was a fixed-price
    contract, or that the wage expenses for which it seeks a tax credit were supplies which
    could fall within the fixed-price inspection clause, FAR 52.246-2, as incorporated in the
    AR005 contract. Accordingly, it is unnecessary to consider defendant’s alternative
    argument that the court should incorporate certain FAR provisions in the AR005 contract
    as a matter of law under the Christian doctrine.
    E.     Warranty Clause – BOE12 Contract
    Dynetics asserts it was put at financial risk under the Rejection, Warranty for
    Services, and Warranty for Materials paragraphs of the Boeing Company General
    Provisions for Labor Hour/Time & Material Contracts (GP3). See Pl.’s Mot. 63-64
    (citing Pl.’s Ex. L ¶ 9 (Rejection), ¶ 11 (Warranty for Services), and ¶ 12 (Warranty for
    Materials)). The GP3 is expressly incorporated into the BOE12 contract. See Ex. 40, at
    DYN 41546, 41557-58.
    Dynetics argues it was at financial risk because Boeing could reject
    nonconforming services, and could either require Dynetics to reperform at its own
    expense, or could obtain replacement services and charge Dynetics the cost for doing so.
    See Pl.’s Mot 63 (citing Pl.’s Ex. L ¶¶ 9(a), 9(b), 11). Likewise, Dynetics argues that it
    was responsible for correcting or replacing nonconforming materials at its own expense.
    See 
    id.
     (citing Pl.’s Ex. L ¶ 12).
    The relevant clauses of the GP3 are included below.
    REJECTION
    a. If Seller [Dynetics] delivers nonconforming Services, Buyer [Boeing] may
    require Seller to promptly correct or replace the nonconforming Services.
    Redelivery to Buyer of any corrected or replaced Services shall be at Seller’s
    expense, limited to Seller’s hourly rate as set forth in this contract, excluding
    that portion of the rate attributable to profit.
    b. In addition Buyer may (i) correct the nonconforming Services or (ii) obtain
    replacement Services from another source at Seller’s expense.
    Pl.’s Ex. L ¶ 9(a)-(b).
    WARRANTY FOR SERVICES. Seller warrants that all Services performed
    hereunder shall be performed by employees or agents of Seller who are
    experienced and skilled in their profession and in accordance with industry
    27
    standards. Seller further warrants that all Services performed under this
    contract, at the time of acceptance, shall be free from defects in workmanship
    and conform to the requirements of this contract. Buyer shall give written
    notice of any defect or nonconformance to Seller within one year from the
    date of acceptance by Buyer. [“First provision”] Buyer may, at its option,
    either (a) require correction or reperformance of any defective or
    nonconforming Services, or (b) make an equitable adjustment in the price of
    this contract. If Seller is required to correct or reperform the Services, such
    correction or reperformance shall be at Seller’s expense. Any Services
    corrected or reperformed shall be subject to this article to the same extent as
    work initially performed. [“Second provision”] If Seller fails or refuses to
    correct or reperform, Buyer may correct or replace with similar Services and
    charge Seller for any cost to Buyer, or make an equitable adjustment in the
    price of this contract.
    
    Id. ¶ 11
     (annotation added).
    WARRANTY FOR MATERIALS
    (a). . . . Buyer may, at its option, either (i) return for credit or refund or (ii)
    require prompt correction or replacement of the defective or nonconforming
    materials. Return to Seller of defective or nonconforming materials and
    redelivery to Buyer of corrected or replaced materials shall be at Seller’s
    expense.
    
    Id. ¶ 12
    .
    1.     Paragraph 9(a) of the Rejection Clause and the “First Provision” of the
    Paragraph 11 Warranty for Services Clause
    Review of paragraph 9(a) shows that while Dynetics is correct that Boeing may
    require it to “correct or replace the nonconforming [s]ervices,” it is incorrect that
    Dynetics would be at financial risk in doing so. Dynetics relies on the term “seller’s
    expense,” in paragraph 9(a). See Pl.’s Mot. 63 (“Boeing could reject nonconforming
    services and require Dynetics . . . to “correct[] or replace[] Services . . . at Seller’s
    expense.”) (quoting Pl.’s Ex. L ¶ 9(a)). But Dynetics omits mention of the fact that this
    term is defined as “limited to Seller’s hourly rate as set forth in this contract, excluding
    that portion of the rate attributable to profit.”
    28
    Thus when called upon by Boeing to correct or replace nonconforming services,
    Dynetics is first paid its full hourly rate for producing the initial nonconforming services,
    and is then paid its costs for reperforming those services, with the exception of its profit.
    This is like the inspection clause in the AF007 contract, FAR 52.246-8(f). See supra Part
    III.B. As discussed therein, the omission of further profit for reperforming
    nonconforming services is not the type of risk contemplated under the Treasury
    regulation. Dynetics was not at financial risk under the plain text of paragraph 9(a).
    In considering Dynetics’ arguments under paragraph 11, it is apparent that the first
    provision in that Warranty for Services clause addresses the same point as paragraph 9(a)
    of the Rejection clause, that is Boeing’s rights in the face of Dynetics’ delivery of
    nonperforming services. Reviewing the relevant sentences side-by-side is helpful in
    appreciating the similarity.
    Reperformance Requirement
    Rejection –                           Warranty for Services –
    Paragraph 9(a)                      Paragraph 11 “First provision”
    If Seller delivers nonconforming Services, Buyer may . . . (a) require correction or
    Buyer may require Seller to promptly          reperformance of any defective or
    correct or replace the nonconforming          nonconforming Services . . . . If Seller is
    Services. Redelivery to Buyer of any          required to correct or reperform the
    corrected or replaced Services shall be at    Services, such correction or
    Seller’s expense, limited to Seller’s hourly reperformance shall be at Seller’s expense.
    rate as set forth in this contract, excluding Any Services corrected or reperformed
    that portion of the rate attributable to      shall be subject to this article to the same
    profit.                                       extent as work initially performed.
    Pl.’s Ex. L ¶¶ 9(a), 11. The only real difference between paragraphs 9(a) and 11 is
    the definition of “seller’s expense.” Paragraph 11 fails to include the dependent
    clause “limited to Seller’s hourly rate as set forth in this contract, excluding that
    portion of the rate attributable to profit.” In reading paragraph 11, the question is
    whether the term “seller’s expense” should be read to include the definition set
    forth in paragraph 9(a).7
    7
    The court asked the parties to comment on the definition of seller’s expense in
    paragraph 9(a), and whether this definition would apply in paragraph 11, and whether
    Dynetics would be at financial risk under this definition. Order for Supp. Br. 4.
    Dynetics’ response was limited to stating that it understood that any reference to “Seller”
    was a reference to Dynetics, followed by a repetition of its course of dealing argument.
    See Pl.’s Supp. Br. 13.
    29
    “[T]he rule of thumb [is] that a term generally means the same thing each time it is
    used,” which is known as the presumption of consistent usage. United States v.
    Castleman, 
    134 S. Ct. 1405
    , 1417 (2014). However, “the presumption of consistent
    usage readily yields to context, and a statutory term—even one defined in the statute—
    may take on distinct [characteristics] from association with distinct statutory objects
    calling for different implementation strategies. Utility Air Regulatory Grp. v. E.P.A., 
    134 S. Ct. 2427
    , 2441 (2014) (internal quotation marks omitted).
    “The words of a contract are deemed to have their ordinary meaning appropriate to
    the subject matter, unless a special or unusual meaning of a particular term or usage was
    intended, and was so understood by the parties.” Lockheed Martin IR Imaging Sys., Inc.
    v. West, 
    108 F.3d 319
    , 322 (Fed. Cir. 1997). “Under general rules of contract law we are
    to interpret provisions of a contract so as to make them consistent.” Abraham v.
    Rockwell Int’l Corp., 
    326 F.3d 1242
    , 1251 (Fed. Cir. 2003). “[A]n agreement is not to be
    read in a way that places its provisions in conflict, when it is reasonable to read the
    provisions in harmony . . . . [T]he provisions must be read together in order to implement
    the substance and purpose of the entire agreement.” Air-Sea Forwarders, Inc. v. United
    States, 
    166 F.3d 1170
    , 1172 (Fed. Cir. 1999). “A reasonable interpretation must assure
    that no contract provision is made inconsistent, superfluous, or redundant.” Medlin
    Const. Group, Ltd. v. Harvey, 
    449 F.3d 1195
    , 1200 (Fed. Cir. 2006) (internal quotation
    marks omitted).
    To read the term “seller’s expense” in paragraph 11 without the paragraph 9(a)
    definition would mean that under paragraph 11, Dynetics must reperform at its own
    expense, which is directly at odds with the plain text of paragraph 9(a), which states that
    when reperforming, Dynetics will be paid its “hourly rate” (less its profit).
    As both paragraphs 9(a) and 11 address the same point, under the presumption of
    consistent usage, the court would read the definition for seller’s expense provided in
    paragraph 9(a) into paragraph 11. Reading the paragraph 9(a) definition of seller’s
    expense into paragraph 11 also would permit the court to interpret the contract provisions
    consistently, without placing the two provisions in conflict with one another. See
    Abraham, 
    326 F.3d at 1251
    ; Air-Sea Forwarders, Inc., 
    166 F.3d at 1172
    . The converse,
    reading the term seller’s expense in paragraph 9(a) as it is written in paragraph 11, would
    render the dependent clause in paragraph 9(a) superfluous, making such an interpretation
    unreasonable. See Medlin Const. Group, Ltd., 
    449 F.3d at 1200
    .
    For these reasons, the court interprets the term “seller’s expense” in paragraph 11
    to have the same meaning as in paragraph 9(a), that is Dynetics would be paid its “hourly
    rate as set forth in this contract, excluding that portion of the rate attributable to profit.”
    30
    Under this reading, as discussed earlier, Dynetics was not at financial risk when called
    upon to reperform nonconforming services.
    2.     Paragraph 9(b) of the Rejection Clause and the “Second Provision” of the
    Paragraph 11 Warranty for Services Clause
    We turn now to Dynetics’ assertions of financial risk under paragraphs 9(b) and
    11. It is apparent that both paragraphs address the same points, Boeing’s rights to correct
    nonconforming services or replace those services with a contractor other than Dynetics.
    Comparison of the two sentences side-by-side, however, reveals a significant difference.
    Boeing’s Ability to Charge Dynetics for Replacement Services
    Rejection –                            Warranty for Services –
    Paragraph 9 (b)                      Paragraph 11 “Second provision”
    In addition Buyer may (i) correct the        If Seller fails or refuses to correct or
    nonconforming Services or (ii) obtain        reperform, Buyer may correct or replace with
    replacement Services from another source at  similar Services and charge Seller for any cost
    Seller’s expense.                            to Buyer, or make an equitable adjustment in
    the price of this contract.
    Pl.’s Ex. L ¶¶ 9(b), 11. In both paragraphs 9(b) and 11, Boeing has the right to charge
    Dynetics the cost of any replacement services it procured from another contractor. Id. ¶
    9(b) (“Buyer may . . . obtain replacement Services from another source at Seller’s
    expense.”); Id. ¶ 11 (“If Seller fails or refuses to correct or reperform, Buyer may . . .
    replace with similar Services and charge Seller for any cost to Buyer.”). In paragraph
    9(b), Boeing may resort to this option at any time. Id. ¶ 9(b). In paragraph 11, however,
    Boeing may do so only “[i]f [s]eller fails or refuses to correct or reperform.” Id. ¶ 11.
    “When a contract is susceptible to more than one reasonable interpretation, it
    contains an ambiguity. To show an ambiguity[,] it is not enough that the parties differ in
    their respective interpretations of a contract term. Rather, both interpretations must fall
    within a zone of reasonableness.” Metric Constructors, Inc., 
    169 F.3d at 751
     (internal
    citations and quotation marks omitted).
    The plain text of paragraphs 9(b) and 11 are ambiguous as to when Boeing could
    charge Dynetics for its cost in securing replacement services—at any time, or only if
    Dynetics fails or refuses to correct or reperform. The GP3 as a whole provides no further
    information on this point. Either interpretation is within a zone of reasonableness. See
    Metric Constructors, Inc., 
    169 F.3d at 751
    .
    31
    Under the doctrine of contra proferentem, any ambiguity in the BOE12 contract is
    to be construed against the drafter. See LAI Svcs., Inc. v. Gates, 
    573 F.3d 1306
    , 1315
    (Fed. Cir. 2009). The BOE12 contract, including the GP3, was drafted by Boeing. A
    review of the texts clearly indicates that paragraph 11 is in Dynetics’ interest, and against
    Boeing’s interest, because it limits the circumstances in which Boeing can go outside the
    contract to secure replacement services at Dynetics’ expense. For this reason, the court
    resolves the ambiguity between paragraphs 9(b) and 11 by reading the GP3 to permit
    Boeing to charge Dynetics for similar services it obtains as set forth in paragraph 11, “[i]f
    Seller fails or refuses to correct or reperform.”
    In arguing that it was put at financial risk under paragraph 11, Dynetics overlooks
    the portion of paragraph 11 that limits Boeing’s right to charge Dynetics for replacement
    services only to when it first “fails or refuses to correct or reperform.” See Pl.’s Mot. 63
    (“The warranty clauses of the General Provisions gave Boeing the right to request
    correction or performance of defective or nonconforming services at the Seller’s expense
    . . . .”) (citing Pl.’s Ex. L ¶ 11). While Dynetics is at risk under paragraph 11, this risk
    results not from the failure of its research, but rather from any lack of response to a
    rejection of its nonperforming services—that is, by either its failure or refusal to correct
    or reperform. See Pl.’s Ex. L ¶ 11. This is not the risk contemplated by the Treasury
    regulation, which is limited to the failure of the research. See infra Part III.G.
    3.     Paragraph 12
    Finally, Dynetics claims it is at risk under paragraph 12, under which it provided
    Boeing with a warranty for materials. It is unclear, however, how risk under paragraph
    12, if such risk exists, is relevant to this motion. According to defendant, Dynetics
    claims only wages as the expenses for which it seeks a tax credit. See Def.’s Mot. 33.
    Dynetics says nothing to the contrary in its own motion. See id. at 58-64. If Dynetics
    seeks a tax credit only for wages, it is unclear how a warranty for materials would be
    relevant to the question of whether Dynetics was at financial risk in its research, for
    which it incurred only expenses for wages. Dynetics says nothing on this point.
    Having considered Dynetics’ arguments based on paragraphs 9(a), 9(b), 11 and 12
    of the GP3, the court finds Dynetics’s arguments that it was put at financial risk under the
    warranty and rejection clauses of the BOE12 contract to be unpersuasive.
    F.     Inspection Clause – UAH01 Contract
    The warranty clause in the UAH01 contract is set forth in the contract itself; there
    are no relevant incorporated FAR provisions. See Ex. 18, at DYN 1707 ¶ 1. Dynetics
    32
    argues that “[w]hile the UAH01 contract did not include any inspection provisions,8 the
    warranty provision, as governed by Alabama law, gave UAH a right to recover the price
    paid if the work delivered did not conform to the requirements of the contract.” Pl.’s
    Reply 8 (quotation marks omitted) (footnote added).
    The warranty clause on which Dynetics relies is included below in its entirety.
    Standard of Performance. All services rendered by the Contractor and its
    employees, agents, or representatives in performance of this Contract shall
    conform to the highest standards of workmanship for the type of work
    involved. Each of the Contractor’s employees performing services under this
    Contract shall be well qualified for the services he or she is performing. The
    Contractor warrants to the University that all work performed shall: (a)
    conform in all respects to all requirements of this Contract; (b) be free from
    all defects in materials and workmanship; and (c) be free from all defects in
    design and be fit for its intended purposes.
    Ex. 18, at DYN 1707 ¶ 1. Notably, the warranty clause includes no rejection or
    reperformance provisions. In arguing it was at financial risk, Dynetics also relied on
    certain Alabama state statutes:
    Failing to deliver work meeting [the warranty clause] requirements gives rise
    to a cause of action to seek return of funds already paid. 
    Ala. Code § 7-2
    -
    711 (where seller fails to deliver goods as warranted, buyer may, in addition
    to other remedies, cancel contract and recover the price that has paid); Ala.
    Code. § 7-2-714; Massey-Ferguson, Inc. v. Laird, 
    432 So. 2d 1259
     (Ala.
    1983) (damages for breach of express warranty include the difference in
    value between the goods as warranted and value as delivered plus incidental
    and consequential damages).
    Pl.’s Mot. 71. In Massey-Ferguson, the Supreme Court of Alabama relied on section 7-2-
    714 of the Alabama code in its calculation of damages for breach of warranty. Massey-
    Ferguson, Inc., 
    432 So. 2d at 1264
    .
    8
    The UAH01 contract did include an inspection provision. “Inspection. The
    University, through its authorized representatives, shall have the right at all reasonable
    times to inspect or otherwise evaluate the work performed or being performed by the
    Contractor.” Ex. 18, at DYN 1707 ¶ 2. Nothing in the text of the inspection clause puts
    Dynetics at financial risk.
    33
    Under Lockheed Martin, any determination of risk must be made solely on the
    “research agreement” between the parties, with no consideration of any external statute
    not expressly incorporated in that agreement. Lockheed Martin Corp. v. United States,
    
    210 F.3d 1366
     (Fed. Cir. 2000). In Lockheed Martin, the Federal Circuit considered the
    question of whether entitlement to the tax credit—which requires the taxpayer to show
    both that it was put at financial risk by conducting the research and that it retained
    substantial rights in that research—could be shown by reliance on a statute outside the
    contract. 
    Id. at 1370
    . The appellate court held that it could not.
    We similarly reject the argument that the determination whether
    Lockheed Martin retained “substantial rights” to its research can be found by
    reference to export control laws and top secret classifications; they are also
    irrelevant because they are outside of the research agreements. The
    determination whether Lockheed Martin retained “substantial rights” must
    be made by reference to the . . . contracts alone. The regulation’s focus on
    the taxpayer’s right under the research agreements makes it clear that the
    determination whether the taxpayer had the right to use the results of its
    research without paying for that right must be determined by reference to the
    research agreements.
    
    Id. at 1375-76
    . The companion Treasury regulation governing whether the taxpayer is at
    financial risk likewise focuses on the taxpayer’s right under the research agreements.
    Research does not constitute qualified research to the extent it is funded by
    any grant, contract, or otherwise by another person (including any
    governmental entity). All agreements (not only research contracts) entered
    into between the taxpayer performing the research and other persons shall be
    considered in determining the extent to which the research is funded.
    
    Treas. Reg. § 1.41
    -4A(d)(1) (emphasis added).
    Dynetics points to no part of the UAH contract incorporating the Alabama state
    statutes on which it relies to argue that it faced financial risk. Under Lockheed Martin,
    the court is precluded from considering the impact of any statute outside of the UAH01
    contract in determining whether Dynetics was at financial risk under the UAH01
    contract. Dynetics made no argument that it was subject to financial risk under the plain
    text of the warranty provision, and a review of the UAH01 contract fails to show that it
    was.
    G.     Business Risk Arguments
    34
    Dynetics argues that it was put at financial risk by the uncertain nature of the
    work, by the fact that it had to invest in staffing and resources with no commitment from
    the government to pay those costs, and by the incremental orders placed under the
    contracts. Pl.’s Mot. 32-37.
    Dynetics argues that for at least four contracts—specifically, AR009, AMS01,
    BOE12 and NT001—it was “uncertain” about the “nature of the work,” as the contracts
    included “extremely broad statements of work that identified a wide range of work
    Dynetics would be required to perform.” 
    Id. at 32
    . Dynetics argues that “[b]ecause the
    exact nature of the work could not always be described – or could not be described in a
    manner to fully disclose all necessary information, Dynetics bore the risk that it would be
    unable to complete the work within the price proposed, or at all.” 
    Id. at 33
    .
    Next, Dynetics argues that under the contracts, it was “required to incur the costs
    associated with developing and maintaining the staffing and resources necessary to
    support the work contemplated by the contract, but the government was not obligated to
    issue more than a minimal amount of work under the contract.” 
    Id. at 34-35
    . Dynetics
    complains that it bore the risk of its efforts and investments, while the “government had
    no obligation to continue to use those resources if the research was unsuccessful.” 
    Id.
    Dynetics further argues that six of the sample contracts (all but the AF007
    contract) “contemplated an uncertain amount of work at the time the contract was
    funded,” as certain contracts were Indefinite Delivery Indefinite Quantity (IDIQ), while
    others “used options or modifications to order the vast majority of the work contemplated
    by the contract.” 
    Id.
     Dynetics asserts that it faced a financial risk because “[i]f the
    research Dynetics performed under the initial tasks in these contracts was unsuccessful,
    the government could have declined to issue any further work under the contract without
    incurring any additional liability to Dynetics.” 
    Id.
    Defendant collectively characterizes these risks as business risks or economic
    risks, none of which, it asserts, are the type of financial risk contemplated by the Treasury
    regulation. Def.’s Resp. 23-25. In support of its position, defendant points to both the
    relevant Treasury regulation, and the Federal Circuit’s interpretation thereof in Fairchild.
    As provided in the Treasury regulation governing qualified research, “[a]mounts
    payable under any agreement that are contingent on the success of the research and thus
    considered to be paid for the product or result of the research . . . are not treated as
    funding.” 
    Treas. Reg. § 1.41
    -4A(d)(1).
    35
    As the Federal Circuit has explained,
    [t]he inquiry turns on who bears the research costs upon failure, not on
    whether the researcher is likely to succeed in performing the project. When
    payment is contingent on performance, such as the successful research and
    development of a new product or process, the researcher [Dynetics] bears the
    risk of failure.
    Fairchild, 
    71 F.3d at 873
    .
    It is clear that none of plaintiff’s arguments suggest a circumstance under which it
    will not be paid for the results of unsuccessful research. As this is the only financial risk
    considered by the Treasury regulation in determining whether expenses are funded, that
    is the only risk relevant in this motion. Plaintiff’s assertions of any other risk are
    irrelevant to the court’s resolution of this motion.
    H.     Termination Clauses
    Plaintiff also argues it was at risk from the FAR termination clauses incorporated
    into each sample contract. Pl.’s Mot. 37. “In all cases, the government could terminate
    the contract for convenience, and the government’s liability would be capped to work
    done under the contract for convenience, and the government’s liability would be capped
    to work done under the contract and certain unwinding costs.” 
    Id.
     (citing FAR 52.249-1
    to 52.249-7). Dynetics argues it was at risk because if the government terminated the
    contract for convenience, it “would still be left with the costs and expenses arising from
    developing the capabilities to do the full amount of work contemplated by the contract.”
    
    Id.
    Although it argued otherwise, Dynetics was not put at financial risk by the terms
    of any FAR termination clause. As an example, FAR 52.249-6 Termination Cost-
    Reimbursement (Sept. 1996) is incorporated into the AF007 contract. Ex. 12, at DYN
    965. Under this termination clause, a contractor is entitled to receive all reimbursable
    costs, together with reasonable costs of settlement of the terminated work. FAR 52. 249-
    6(h) (1)-(3). In addition, the contractor is entitled to receive a portion of the fee payable
    under the contract, which in the case of a termination for convenience, is “equal to the
    percentage of completion of work contemplated under the contract.” FAR 52. 249-
    6(h)(4).
    Thus, if the government terminated a contract for convenience, the contractor
    would receive all reimbursable costs for the work it had performed, together with a
    36
    comparable portion of its fee. While it is true that Dynetics would not have the
    opportunity to earn its full fee, the loss of an opportunity for profit is not the type of
    financial risk contemplated in the Treasury regulation. See 
    Treas. Reg. § 1.41
    -4A(d)(1).
    The court further observes that in Fairchild, the Federal Circuit held that the
    contractor was put at financial risk under the terms of its contract where the government
    had in fact terminated Fairchild’s contract for convenience, prior to the completion of the
    contract. Fairchild, 
    71 F.3d at 871
     (“Fairchild and the Air Force agreed to termination for
    convenience terms,” after Congress cancelled funding for the program.). Yet, even
    though the contract in Fairchild included a termination clause and the government
    actually did terminate the contract, there was no discussion in the Fairchild case about the
    contractor’s financial risk resulting from the termination clause. Thus, Dynetics’
    assertions are without meaningful support.
    I.     Undefinitized Contracts
    The government initially issued three sample contracts as undefinitized contracts,
    which Dynetics argues put it at risk. See Pl.’s Mot. 39-40 (AF007); 51 (AR005); 60
    (BOE12). Because Dynetics did not explain how such a contract put it at risk, the court
    asked Dynetics to provide supplemental briefing on this point. Order Supp. Br. 2.
    Dynetics offered several arguments in response. First, Dynetics asserts that an
    undefinitized contract is incomplete, and may lack relevant provisions, “such as price,
    terms of payment, and inspection and acceptance rights and obligations.” Pl.’s Supp. Br.
    3. Dynetics did not, however, indicate that any of the sample contracts at issue in this
    motion lacked these relevant provisions.
    Second, relying on case law, Dynetics asserts that an undefinitized contract may
    be unenforceable and thereby leave it at risk of nonpayment. 
    Id.
     at 3-4 (citing Trauma
    Servs. Group Ltd. v. United States, 
    33 Fed. Cl. 426
     (1995)). But, the agreement in
    Trauma Services, on which Dynetics based its assertions, was a memorandum of
    agreement (MOA), not a contract. Trauma Servs., 33 Fed. Cl. at 430-31. That a MOA
    may be unenforceable is irrelevant to whether Dynetics was at risk here under either the
    AF007 or BOE12 undefinitized contract.
    The government responds that Dynetics was not at risk under any of the three
    sample contracts. For the AF007 contract, the undefinitized contract included FAR
    52.216-07 Allowable Cost and Payment (Dec. 2002), Ex. 12, at DYN 964, which
    provided that “[t]he Government will make payments to the Contractor when requested
    as work progresses.” FAR 52.216-7(a)(1). Contrary to Dynetics’ assertion that
    37
    undefinitized contracts may be incomplete, the AF007 included two pages of FAR
    clauses. Ex. 12, at DYN 964-65.
    With respect to the BOE12 contract, defendant correctly pointed out that the
    undefinitized contract provided for payment to Dynetics in the event of contract
    termination. Def.’s Reply to Pl.’s Supp. Br. 6-7 (citing Ex. 39, at DYN 41532).
    In the event that a definitive subcontract is not executed because of the
    inability of the parties hereto to agree upon the provisions of a definitive
    subcontract, the Buyer, [Boeing], at its sole discretion, may terminate this
    letter contract in accordance with the provision entitled “Termination for
    Convenience,” and shall pay the Subcontractor [Dynetics] in accordance
    therewith subject to the limitations contained herein, but with no allowance
    for profit.
    Ex. 39, at DYN 41532 ¶ 7. Dynetics’ only risk here was the possibility that it might not
    earn a profit. Again, that is not the risk contemplated by the Treasury regulation. See
    
    Treas. Reg. § 1.41
    -4A(d)(1).
    While the AR005 contract was an undefinitized contract initially, none of the
    expenses for which Dynetics claims a tax credit were incurred under that undefinitized
    contract. Dynetics claims expenses only for wages incurred under the cost-plus-fixed-fee
    contract line items for engineering services included in the later definitized contract. See
    Def.’s Mot. 27; Ex. 27, at DYN 58340. Those line items were not included in the
    undefinitized contract. Ex. 26, at DYN 36189-90. As Dynetics’ expenses were incurred
    under the definitized contract, it is under that contract that it must show it was at risk.
    See 
    Treas. Reg. § 1.41
    -4A(d)(1) (“Amounts payable under any agreement that are
    contingent on the success of the research and thus considered to be paid for the product or
    result of the research . . . are not treated as funding.”) (emphasis added). Dynetics has
    failed to do so here.
    IV.    Discussion – Whether Dynetics Retained Substantial Rights in the Results
    of the Research
    Defendant argues that because Dynetics did not retain substantial rights in the
    results of the research under the UAH01 and NT001 contracts, it may not take a tax credit
    for its incurred expenses under either contract. Def.’s Mot. 40-42.
    As provided in the relevant Treasury regulation,
    38
    [i]f a taxpayer performing research for another person retains no substantial
    rights in research under the agreement providing for the research, the
    research is treated as fully funded for purposes of section 41(d)(4)(H), and
    no expenses paid or incurred by the taxpayer in performing the research are
    qualified research expenses.
    
    Treas. Reg. § 1.41
    -4A(d)(2);9 see also Lockheed Martin Corp., 
    210 F.3d at 1374-75
     (“If
    the taxpayer does not have the right to use or exploit the results of the research, its
    expenditures are not entitled to the tax credit . . . regardless [of] whether the taxpayer
    receives some “incidental benefit” such as increased experience.”) (emphasis added).
    A.     UAH01 Contract
    Defendant makes two arguments in support of its position that Dynetics did not
    retain substantial rights in the results of its research for the University. Def.’s Mot. 41.
    First, defendant points to the plain language of the contract, under which it argues that
    Dynetics assigned “all rights in the results of its work” to the University. 
    Id.
     (citing Ex.
    18, at DYN 1709). Defendant also argues that Dynetics’ work under the UAH01 contract
    was a “work for hire,” thus Dynetics retained no rights in that work. 
    Id.
     Defendant first
    relies on paragraph 24 of the UAH01 contract.
    24. Patents.10 (a) [1st sentence] All rights, title, and interest in and to
    inventions or other intellectual property rights conceived or reduced to
    practice in the course of performance of the work called for by this Contract
    are hereby vested in the University. [2d sentence] The contractor agrees to
    promptly disclose to the University, in a format acceptable to the University,
    9
    Further, “[a] taxpayer does not retain substantial rights in the research if the
    taxpayer must pay for the right to use the results of the research,” 
    Treas. Reg. § 1.41
    -
    4A(d)(3). The question of payment for the right to use the results of the research is not
    an issue in this matter.
    10
    The “Construction Rules” included in the UAH01 contract provide that “[t]he
    captions and headings in this Contract are for purposes of convenience and reference
    only, and the words contained therein shall have no substantive effect and shall in no way
    be held to explain, modify, or amplify the meaning of the sections and provisions of this
    Contract to which they pertain.” Ex. 18, at 1711 ¶ 39(a). Further, “[t]he language in all
    parts of this contract shall in all cases be simply construed according to its fair meaning
    and not strictly for or against any party.” Ex. 18, at 1711 ¶ 39(d). Neither party
    commented on the heading “Patents” in paragraph 24. According to the contract’s
    Construction Rules, the court does not consider it when evaluating Dynetics’ rights.
    39
    any potentially patentable idea or concept conceived or reduced to practice
    in the course of performance of the work called for by this Contract.
    Ex. 18, at DYN 1709 ¶ 24(a) (annotation added).
    Dynetics replies that while it may not have retained substantial rights in all its
    work for the University, it retained substantial rights in certain work, specifically all
    “non-patentable technology.” Pl.’s Mot. 72 (“Therefore, to the extent the research and
    development activities undertaken in connection with the UAH contract result in products
    or knowledge that is not patentable, rights to those products and solutions remain with
    Dynetics.”). Dynetics points to Exhibit C to the UAH01 contract, the “NASA Grantee
    New Technology Summary Report,” through which NASA requires any contractor, like
    the University, or subcontractor, like Dynetics, to “report new technology” to it. Ex. 18,
    at DYN 1705. Exhibit C provides that new technology “may be either patentable or non-
    patentable,” and that NASA does not require the disclosure of “non-patentable new
    technology.” Ex. 18, at DYN 1705.
    Dynetics asserts that its work under the UAH01 contract—solving equations and
    developing simulations to describe the deep space environment—is not patentable. Pl.’s
    Mot. 72 (citing In re Bilski, 
    545 F.3d 943
     (Fed. Cir. 2008) aff’d, Bilski v. Kappos, 
    561 U.S. 593
     (2010)). Patentable inventions include “new and useful process, machine,
    manufacture, or composition of matter,” 
    35 U.S.C. § 101
    , none of which, argues
    Dynetics, would include the products and solutions it developed under the UAH01
    contract. Pl.’s Mot. 72. Given that the results of the research under the UAH01 contract
    were non-patentable, and that NASA did not require the disclosure of non-patentable new
    technology, Dynetics concludes that such technical products and solutions as it ultimately
    developed fell outside the second sentence in paragraph 24, and thus it retains substantial
    rights in that technology. Pl.’s Mot. 72.
    Defendant responds that Dynetics overlooks the first sentence of paragraph 24,
    which “more broadly ‘vests in the University’ not just patentable ‘inventions’ but also
    any ‘other intellectual property rights,’ such as the copyright in the computer code written
    by Dynetics.” Def.’s Resp. 28. Dynetics offered no reply to this argument. See Pl.’s
    Reply 19-20.
    The Copyright Act defines a “computer program” as “a set of statements or
    instructions to be used directly or indirectly in a computer in order to bring about a
    certain result.” 
    17 U.S.C. § 101
    . “A computer program is a form of literary work, and
    thus is copyrightable.” Greenberg v. National Geographic Soc., 
    533 F.3d 1244
    , 1262 n.6
    40
    (11th Cir. 2008).11 The owner of a copyright enjoys a number of exclusive rights under
    the Copyright Act. See, e.g., Cambridge Univ. Press v. Patton, 
    769 F.3d 1232
    , 1242 n.5
    (11th Cir. 2014) (citing 
    17 U.S.C. § 501
    (a)).
    Even if Dynetics is correct that the results of the research on the UAH01 contract
    were non-patentable technology, under the first sentence of paragraph 24, any other
    intellectual property rights in those results, like copyright protections, would vest in the
    University.
    Dynetics bears the burden of showing it had substantial rights in the results of the
    research. See Bubble Room, Inc., 159 F.3d at 561. In the face of paragraph 24, Dynetics
    would have to show that the results of the research on the UAH01 contract fell entirely
    outside the broad category of rights vested in the University—other intellectual property
    rights conceived or reduced to practice in the course of performance of the work.
    According to Dynetics’ own description of its work on the UAH01 contract—solving
    equations and developing simulations to describe the deep space environment, Pl.’s Mot.
    72—all its work fell within the protection of paragraph 24.
    Considering the plain text of the UAH01 contract, and the work Dynetics
    performed for the University, Dynetics has not carried its burden to show that it retained
    substantial rights in that work. The court finds that Dynetics did not retain substantial
    rights in the results of the research under the UAH01 contract.
    As defendant has prevailed on its contractual argument, it is unnecessary to reach
    defendant’s alternate work for hire argument.
    B.     NT001 Contract
    With regard to the NT001 contract, defendant asks this court to consider Dynetics’
    work under only one task order, Task Order 169. See Def.’s Mot. 42 n.15; Def.’s Resp.
    29. According to defendant, the government issued Dynetics approximately 260 task
    orders under the NT001 contract, however, defendant believes the parties can use this
    11
    Copyright issues are not assigned exclusively to the Federal Circuit. See 
    28 U.S.C. § 1295
     (2012). “When the questions on appeal involve law and precedent on
    subjects not exclusively assigned to the Federal Circuit, the court applies the law which
    would be applied by the regional circuit.” Atari Games Corp. v. Nintendo of Am., Inc.,
    
    897 F.2d 1572
    , 1575 (Fed. Cir. 1990). As this contract was performed in the state of
    Alabama, which sits within the Eleventh Circuit, the court consults Eleventh Circuit law
    on copyright issues.
    41
    court’s resolution of the substantial rights question for Task Order 169 to resolve the
    same question for the remaining task orders.12 Def.’s Mot. 42 n.15. Accordingly, the
    court considers only the question of whether Dynetics retained substantial rights to the
    results of the research performed under Task Order 169 on the NT001 contract, and
    offers no opinion on whether Dynetics retained substantial rights to the results of the
    research on any other task order issued under the NT001 contract.
    Defendant describes Dynetics’ work on the NT001 contract as “highly classified
    intelligence research on foreign weapons systems.” Def.’s Resp. 29. In performing its
    work on the NT001 contract, “Dynetics was required to comply with military security
    requirements in accordance with DD Form 254, which classified the contract as ‘Top
    Secret.”’ Def.’s Mot. 41; Ex. 34, at DYN 8125 item 1.
    The parties disagree on whether the security requirements in DD Form 254 had
    any effect on Dynetics’ right to use the results of the research, including the allocation of
    intellectual property rights between Dynetics and the government.
    1.     Contract Provisions
    a.     DD Form 254 Security Requirements for Intelligence Information
    The DD Form 254 is the Department of Defense Contract Security Classification
    Specification, and is Attachment no. 2 to the NT001 contract. Ex. 34, at DYN 8125; Ex.
    34, at 8089 (Section J List of Attachments). It is a two-page form, and in the case of the
    NT001 contract, includes four additional, individually-typed “continuation sheets” that
    include twenty-nine enumerated paragraphs providing further information about security
    guidance and security requirements. 
    Id.
     at DYN 8125-30. Further, paragraph 6 on
    continuation sheet page 2, itself incorporates a separate two-page attachment, Attachment
    no. 1, which includes an additional eleven enumerated paragraphs regarding the security
    requirements for intelligence information. See 
    id.
     at DYN 8127 ¶ 6, 8131-32.
    12
    In its reply, Dynetics interpreted defendant’s argument as challenging whether
    Dynetics retained substantial rights in the results of the research only under Task Order
    169, but not for work under any other task order. See Pl.’s Reply 19. This is an
    inaccurate characterization of defendant’s argument. Defendant clearly stated that it
    limited its argument to Task Order 169 only “for the purpose of this motion.” Def.’s
    Mot. 42 n.15.
    42
    As provided in DD Form 254, Dynetics had access to intelligence information that
    was SCI (Special Compartmented Information13) and non-SCI (top secret). See 
    id.
     at
    DYN 8125 items 10(e)(1), (2). Patrick Keller, a Dynetics employee knowledgeable
    about the NT001 contract, testified about the distinctions among intelligence information
    classifications. See Keller dep. 58:6-59:15, Dec. 12, 2013, Ex. 64.
    [SCI] means that it has to be protected with much greater care than –
    if secret information is lost, it causes bad damage. . . . Secret, bad; top secret,
    really, really bad; SCI; exceptional, extreme, grave, bad, serious
    compromise. So you have the SCI caveat that means that it is more tightly
    controlled than just regular top secret information . . . .
    Id. at 58:16-59:1.
    b.     Task Order 169
    Task Order 169 called for Dynetics to provide services in support of a “classified
    foreign air-defense system” known internally as “Vorlon.” Def.’s Mot. 42. “The task
    order employed Dynetics to prepare engineering drawings of the missile and to describe
    the key physical and operational characteristics of certain sections of the missile in a
    technical report.” Def’s Supp. Br. 7. According to Mr. Keller, Task Order 169 called for
    Dynetics to perform an initial characterization of a foreign air defense system, which
    involved analyzing hardware—a missile nose section and a control section. Keller Dep.
    95:4-15, Dec. 12, 2013, Ex. 64.
    Review of the task order itself shows that the Statement of Work described two
    tasks, which required Dynetics to conduct analyses, prepare engineering drawings in both
    hardcopy and softcopy (software) formats, identify key characteristics of specified
    sections of a missile, perform laboratory tests, and document its findings in a report. Ex.
    35, at DYN 9925. Dynetics’ work on Task Order 169 required deliverables of
    engineering drawings and a technical report. Id. at DYN 9926.
    2.     Discussion
    a.     Right to Use or Exploit the Results of the Research
    13
    The DD Form 254 refers alternately to Sensitive Compartmented Information, Ex.
    34, at DYN 8125 item 10(e)(1), and Special Compartmented Information, Ex. 34, at
    DYN 8128 ¶ 16. The terms are used interchangeably.
    43
    Defendant argues that the intelligence information—either SCI or top secret—
    Dynetics used in performing Task Order 169 permeated the results of that research, to the
    point that the security requirements in the DD Form 254 prevented Dynetics from using
    those results, just as the same security requirements prevented Dynetics from using the
    intelligence information itself. See Def.’s Mot. 41-42; Def.’s Resp. 29 (“Because one
    cannot segregate the results of Dynetics’ work on that task order from the ‘Top Secret’ or
    ‘SCI’ material that Dynetics was retained to characterize, Dynetics can have no right to
    ‘use or exploit the results of the research.”’); Def.’s Supp. Br. 8 (“[The DD Form 254]
    provisions eliminate any right that Dynetics might otherwise possess to use or exploit the
    results of its work on Task Order 169, because classified “intelligence information”
    permeated such work.”).
    As defendant points out in its supplemental briefing, the DD Form 254 places a
    number of limits on use of intelligence information. See id. at 7-8. A sampling of
    security restrictions includes the following.
    Intelligence materials generated by your organization may be reproduced
    without written permission exclusively for this contract.
    Ex. 34, at DYN 8131 ¶ 4.
    No authorization is granted to release intelligence material to any activity,
    employee, or other person not directly engaged in providing services under
    the contract unless specific written authorization for such release is received
    from DIA/MSIC. This prohibition precludes release without authority to
    another contractor (including a subcontractor), Government Agency, private
    individual, or organization.
    Id. at DYN 8131 ¶ 8 (emphasis added).
    Upon completion of this contract, all materials provided to the contractor will
    be returned to the Government unless written exception is provided to the
    contractor. Materials generated by the contractor may be returned or
    destroyed as directed.
    Id. at DYN 8128 ¶ 10 (emphasis added).
    All materials provided to the contractor under this contract are for the
    exclusive use of this contract.
    44
    Id. at DYN 8128 ¶ 12.
    In the face of these significant security restrictions, Dynetics makes several
    arguments that it nonetheless retained the right to use the results of the research on Task
    Order 169. Pl.’s Reply 19. First, Dynetics points to “skills and advancements” it
    developed while working on Task Order 169.
    [A]ny capabilities developed in the analysis of the Vorlon system, such as
    advancements in preparing engineering drawings or improving the method
    of identifying radio frequency, could be reused in subsequent work
    performed by Dynetics because those skills and advancements are not
    necessarily particular to the specific classified weapons system.
    Id.
    The governing Treasury regulation provides that “[i]ncidental benefits to the
    taxpayer from performance of the research (for example, increased experience in a field
    of research) do not constitute substantial rights in the research.”). 
    Treas. Reg. § 1.41
    -
    4A(d)(2). It is unclear how the accumulation of “skills and advancements” would be
    other than an “incidental benefit,” and Dynetics is silent on this point.
    Next, Dynetics asserts that it can “use its research results from Task Order 169 in
    performing work for other intelligence agencies following authorization from MSIC.”
    Pl.’s Reply 19 (emphasis added) (citing Ex. 34, at DYN 8130 ¶ 22); see also Pl.’s Supp.
    Br. 11 (“Dynetics retains the rights in the products it develops (including those products
    with intelligence information) for purposes of performing work pursuant to contracts with
    MSIC or any other government agency (or private company) provided that MSIC agrees
    to the transfer of such information.”) (citing Ex. 34, at DYN 8132 ¶ 11) (emphasis
    added).
    Dynetics does not address the obvious question of how it could have substantial
    rights in the results of the research, if it needed the government’s “authorization” to use
    those results. Nor do the particular DD Form 254 paragraphs cited by Dynetics in its
    assertion of a right to use—paragraphs 11 and 22—provide it with support.
    The contractor will not reproduce any SCI related material without written
    permission from the [Contract Monitor]/[Special Security Officer]. When
    such permission has been granted, the contractor will control and account for
    such reproduction in the same manner as pertains to originals.
    45
    Ex. 34, at 8130 ¶ 22. Dynetics offers no explanation how, if it did receive permission to
    reproduce “SCI related material,” it could “use its research results from Task Order 169
    in performing work for other intelligence agencies,” as it asserts it can, Pl.’s Reply 19,
    and still comply with the requirement in paragraph 22 that it “control and account for
    such reproduction in the same manner as pertains to originals.” If Dynetics performed
    work for another intelligence agency, it would cease to have control over that work, and
    would be unable to comply with the security requirement in paragraph 22.
    DD Form 254 attachment no. 1 paragraph 11 governs intelligence material, SCI
    and non-SCI, and is included below.
    Upon expiration of the contract, all substantive collateral intelligence
    materials released to your company will be returned to the issuing agency for
    disposition. In the event the contract is extended or a new similar contract
    requiring the released data is initiated, it is the responsibility of the contract
    monitor to effect an extension or document transfer with the [Defense
    Intelligence Agency/Missile and Space Intelligence Center] [Special
    Security Officer].
    Ex. 34, at DYN 8132 attach no. 1 ¶ 11 (emphasis added). Paragraph 11 refers to either an
    extension of the existing contract or the initiation of a new similar contract with MSIC.
    Nothing in paragraph 11 could be read to suggest that Dynetics had the right to use the
    results of the research, containing intelligence material, in performing work for “any
    other government agency (or private company),” as Dynetics asserts it could. See Pl.’s
    Supp. Br. 11.
    In its supplemental briefing, Dynetics asserts that the security requirements in
    Attachment 1 do not preclude it from using “the models, analyses, software
    enhancements, or testing components developed under the NT001 contract in future
    contracts,” as the intelligence material it used or generated “in many cases is severable
    from the models and systems developed under the contract.” 
    Id.
     Dynetics’ argument was
    not specific to Task Order 169, but rather spoke generally about its work under the
    NT001 contract. 
    Id.
    Defendant responds that Dynetics produced no “models, analyses, software
    enhancements, or testing components” under Task Order 169, and thus its assertion of
    severability is irrelevant to this motion.14 See Def.’s Reply to Pl.’s Supp. Br. 13.
    14
    Defendant acknowledges that “the degree of integration of Dynetics’ work product
    with the intelligence information it concerned” will vary among the remaining task
    46
    Finally, Dynetics argues that in Lockheed Martin, the Federal Circuit rejected the
    position that security classifications, like those found in DD Form 254, can deprive a
    contractor of substantial rights in the results of the research. See Pl.’s Reply to Def.’s
    Supp. Br. 5 (citing Lockheed Martin, 
    210 F.3d at 1375
    ). Dynetics is mistaken in its
    understanding of the Federal Circuit’s holding.
    The government argued that Lockheed Martin lacked substantial rights in its
    research because, inter alia, “top secret security provisions and export control laws . . .
    restricted sales of products resulting from Lockheed Martin’s research.” Lockheed
    Martin, 
    210 F.3d at 1373
    . The trial court found that Lockheed Martin lacked substantial
    rights in the results of the research for a number of reasons, including that it “had to seek
    prior approval from the State Department before entering into licensing agreements or
    discussing with other customers technical information not in the public domain,” and that
    “particular statutory provisions restricted Lockheed Martin’s exports.” Lockheed Martin,
    
    210 F.3d at 1370
    .
    On appeal, the Federal Circuit found that the export control laws and security
    classifications upon which the trial court based its decision were outside the research
    agreements, and thus irrelevant to the substantial rights determination. Lockheed Martin,
    
    210 F.3d at 1375-76
    . The Federal Circuit was clear that a determination of whether the
    contractor retained substantial rights “must be made by reference to the [relevant]
    contracts alone.” Lockheed Martin, 
    210 F.3d at 1376
    ; see also 
    Treas. Reg. § 1.41
    -
    4A(d)(2) (“If a taxpayer performing research for another person retains no substantial
    rights in research under the agreement providing for the research, the research is treated
    as fully funded . . . .”) (emphasis added).
    As discussed supra Part III.B.1.a, the DD Form 254 is clearly part of the NT001
    contract. As the decision in Lockheed Martin had nothing to do with the security
    classifications themselves, this decision provides Dynetics with no support.
    Dynetics has the burden to show that it has substantial rights in its research.
    Although Dynetics has offered a number of arguments in furtherance of its claim that it
    had the requisite substantial rights to the results of the research, the arguments are
    unpersuasive. The security requirements simply leave Dynetics with no right to use
    results that contained intelligence information, without government authorization. See,
    e.g., Ex. 34, at DYN 8130 ¶ 22); Id. at DYN 8132 ¶ 11). Even with authorization,
    Dynetics would not have had the right to freely transfer results with intelligence
    orders, and that plaintiff’s severability argument could be relevant in considering
    substantial right under other task orders. Def.’s Reply to Pl.’s Supp. Br. 13.
    47
    information. See e.g., Ex. 34, at 8130 ¶ 22. Although Dynetics advanced a severability
    argument, it is highly unlikely that this was feasible for Task Order 169 considering the
    work required.
    b.     Intellectual Property Rights
    Dynetics also argues that the DD Form 254 is unrelated to the allocation between
    it and the government of the intellectual property rights in the produced research results.
    See Pl.’s Mot. 69. In its supplemental briefing, Dynetics urged that it retained intellectual
    property rights in its research under FAR 52.227-11 Patent Rights—Retention by the
    Contractor (June 1997), which was incorporated in the NT001 contract by reference.
    Pl.’s Reply to Def.’s Supp. Br. 5 n.4 (citing Ex. 34, at DYN 8098).
    Dynetics is correct that the NT001 contract does incorporate FAR 52.227-11. That
    provision in relevant part provides that “[t]he Contractor may retain the entire right, title,
    and interest throughout the world to each subject invention subject to the provisions of
    this clause . . . .” FAR 52.227-11(b). An “invention” is defined as “any invention or
    discovery which is or may be patentable,” FAR 52.227-11(a)(1), and a “subject
    invention” is defined as “any invention of the contractor conceived or first actually
    reduced to practice in the performance of work under this contract . . . ,” FAR 52.227-
    11(a)(6).
    Dynetics avers that the language of FAR 52.227-11 is “almost identical” to the
    language in the patent rights clause incorporated in each contract in Lockheed Martin,
    “which the Federal Circuit found conveyed substantial rights to the contractor.” Pl.’s
    Reply to Def.’s Supp. Br. 5 n.4 (citing Lockheed Martin, 
    210 F.3d at 1377-78
    ).
    Again, Dynetics is correct. The patent rights clause in Lockheed Martin stated
    that “[t]he Contractor may retain the entire right, title, and interest throughout the world
    or any country thereof in and to each Subject Invention disclosed [ ], subject to the rights
    obtained by the Government in paragraph (c) of this clause,” Lockheed Martin, 
    210 F.3d at 1378
    , and this language is almost identical to FAR 52.227-11, as stated above. The
    Federal Circuit characterized this rights clause as giving Lockheed Martin the “the right
    to make and use patented inventions or to exclude unauthorized third parties from
    making, using, or selling such inventions.” 
    Id. at 1377
    .
    That said, while FAR 52.227-11 does provide that Dynetics retains patent rights, it
    does not vest—as Dynetics asserts—all “intellectual property rights” in Dynetics; rather
    it provides rights only to “subject inventions.” Dynetics makes no argument that the
    results of the research under Task Order 169—engineering drawings and a technical
    48
    report, Ex. 35, at DYN 9926—are patentable. And unless the research results for which
    it claims it has substantial rights are patentable, the rights provided by FAR 52.227-11 are
    irrelevant to the consideration of substantial rights in those research results.
    For all the reasons stated, Dynetics has not carried its burden to show that it
    retained substantial rights in its work on Task Order 169 under the NT001 contract. The
    court finds that Dynetics did not retain substantial rights in the results of the research on
    Task Order 169 under the NT001 contract.
    V.     Conclusion
    For all the reasons discussed herein, the court GRANTS defendant’s motion for
    partial summary judgment on the funded research question, and DENIES plaintiff’s
    cross-motion for partial summary judgment on the funded research question.
    The parties are directed to file a joint status report by Tuesday, June 30, 2015,
    informing the court how they would like to proceed in this matter.
    IT IS SO ORDERED.
    s/ Patricia E. Campbell-Smith
    PATRICIA E. CAMPBELL-SMITH
    Chief Judge
    49
    

Document Info

Docket Number: 12-576

Citation Numbers: 121 Fed. Cl. 492

Judges: Patricia E. Campbell-Smith

Filed Date: 5/31/2015

Precedential Status: Precedential

Modified Date: 1/13/2023

Authorities (24)

Massey-Ferguson, Inc. v. Laird , 432 So. 2d 1259 ( 1983 )

Cambridge University Press v. Patton , 769 F.3d 1232 ( 2014 )

LAI Services, Inc. v. Gates , 573 F.3d 1306 ( 2009 )

barron-bancshares-inc-william-j-oestreicher-michael-v-masterson , 366 F.3d 1360 ( 2004 )

Medlin Construction Group, Ltd. v. Harvey , 449 F.3d 1195 ( 2006 )

Metric Constructors, Inc. v. National Aeronautics and Space ... , 169 F.3d 747 ( 1999 )

Fmc Corporation v. United States , 853 F.2d 882 ( 1988 )

Interstate General Government Contractors, Inc. v. Michael ... , 980 F.2d 1433 ( 1992 )

General Engineering & MacHine Works v. Sean C. O'keefe, ... , 991 F.2d 775 ( 1993 )

Spencer Abraham, Secretary of Energy v. Rockwell ... , 326 F.3d 1242 ( 2003 )

lockheed-martin-corporation-as-successor-to-martin-marietta-corporation , 210 F.3d 1366 ( 2000 )

Atari Games Corporation and Tengen, Inc., Plaintiffs/cross-... , 897 F.2d 1572 ( 1990 )

In Re Bilski , 545 F.3d 943 ( 2008 )

Maynard Alves v. United States , 133 F.3d 1454 ( 1998 )

Helvering v. Taylor , 55 S. Ct. 287 ( 1935 )

Lockheed Martin Ir Imaging Systems, Inc. v. Togo D. West, ... , 108 F.3d 319 ( 1997 )

Fairchild Industries, Incorporated v. United States , 71 F.3d 868 ( 1996 )

Air-Sea Forwarders, Inc. v. United States , 166 F.3d 1170 ( 1999 )

Matsushita Electric Industrial Co., Ltd. v. Zenith Radio ... , 106 S. Ct. 1348 ( 1986 )

Anderson v. Liberty Lobby, Inc. , 106 S. Ct. 2505 ( 1986 )

View All Authorities »