Cuspide Properties, Ltd. v. Earl Mechanical Servs. , 2015 Ohio 5019 ( 2015 )


Menu:
  • [Cite as Cuspide Properties, Ltd. v. Earl Mechanical Servs., 
    2015-Ohio-5019
    .]
    IN THE COURT OF APPEALS OF OHIO
    SIXTH APPELLATE DISTRICT
    LUCAS COUNTY
    Cuspide Properties, Ltd.                                    Court of Appeals No. L-14-1253
    Appellee/Cross-Appellant                            Trial Court No. CI0200805503
    v.
    Earl Mechanical Services, Inc.
    Appellant/Cross-Appellee
    v.
    Huntington Bancshares Financial Corp.,
    et al.                                                      DECISION AND JUDGMENT
    Appellees                                           Decided: December 4, 2015
    *****
    Fritz A. Byers, for appellee/cross-appellant Cuspide Properties, Ltd.
    and appellee Community ISP, Inc.
    Erik G. Chappell and Julie A. Douglas, for appellant/cross-appellee.
    *****
    YARBROUGH, P.J.
    I. Introduction
    {¶ 1} This is an appeal from the Lucas County Court of Common Pleas.
    Appellant, Earl Mechanical Services, Inc., appeals the trial court’s grant of summary
    judgment to appellee/cross-appellant, Cuspide Properties, Ltd. (“Cuspide”), on Cuspide’s
    action to quiet title and liability in its slander of title action. Appellant appeals the trial
    court’s decision to grant summary judgment to Cuspide and appellee, Community ISP,
    Inc. (“CISP”), on all of appellant’s counterclaims. Cuspide cross-appeals the trial court’s
    grant of summary judgment to appellant on the element of damages for its slander of title
    action.
    A. Facts
    {¶ 2} This dispute began after appellant contracted with CISP to install air
    conditioning and condenser units on the property it leases from Cuspide. Appellant is
    owned by Jeffrey Earl and is a company providing construction services for commercial
    properties. Cuspide is owned by Jeffrey Klingshirn, who also serves as CEO of CISP.
    Dustin Wade serves as president of CISP. Appellee Huntington Bancshares Financial
    Corporation holds a mortgage on Cuspide’s property where CISP is located.
    {¶ 3} In early 2006, CISP decided to build and equip a data center on Cuspide’s
    property. Before the construction process, CISP purchased six air conditioning units and
    six condensers from an unrelated third party. CISP then began receiving quotes for the
    2.
    mechanical work needed to connect the air conditioning units and condensers and run
    pipes between the units and into the building. CISP spoke to several contractors and
    received estimates. One such estimate was more than $100,000. After speaking with
    Wade, appellant gave an estimate of $47,600. The parties eventually entered into a
    contract for $51,100. When asked about the large price difference between the bids, Earl
    stated it was due to the other contractor’s reliance on workers who belonged to labor
    unions.
    {¶ 4} The job was slated to be completed by early November 2006, so CISP could
    have an open house to promote their new data center. After the contract was signed, but
    before the work was completed, Earl informed Wade additional costs above the contract
    price were being accrued. The two then spoke to Klingshirn over the telephone about the
    extra costs. Some of these costs were associated with two changes to the project that
    were made by CISP. One change was installing the condenser units on the roof of the
    building rather than on concrete pads located in the back of the building. Wade testified
    in his deposition, he was told by appellant this change in location would not change the
    cost in the project.
    {¶ 5} The more significant change was the decision to change the system from a
    four pump system to a dual pump system produced by a company called Liebert. When
    CISP originally sought a quote from appellant, the estimate was based on each air
    conditioner and condenser having its own pump. However, after speaking with another
    potential contractor who suggested the dual pump system, CISP decided a dual pump
    3.
    system by Liebert should be installed. Wade then informed appellant of the requested
    changes and a new contract was drawn up.
    {¶ 6} The contract between the parties makes a notation in price for four pumps,
    which is what was originally agreed to between the parties. A few lines later, a line item
    for $3,500 is listed for “Add for Liebert 7 1/2 HP pump package.” Wade testified he
    believed that line item was referring to the dual pump system CISP wanted installed,
    including the labor and other costs associated with installing the system. This is
    supported by the change in estimates given to CISP by appellant. Appellant originally
    gave CISP an estimate for $47,600, but the contract between the parties was for $51,100.
    {¶ 7} Earl testified in his deposition that the line item was merely the price
    difference between the pumps and did not account for the extra work needed to actually
    install the different pump system. Several engineering drawings had to be made and the
    units had to be manifolded together for the system to operate correctly. He testified he
    was unaware until much later in the project what the extra costs of installing the new
    system would be.
    {¶ 8} The contract included a forum selection clause which required suit to be
    brought in Fulton County. The agreement required any changes in the scope of work to
    be in written change orders.
    {¶ 9} Toward the end of the project, Earl informed CISP and Wade extra costs
    were being incurred above the contract price. Wade and Klingshirn told Earl to continue
    his work, as the project needed to be completed on time and the company did not have
    4.
    enough time to hire a new contractor. Klingshirn told Earl he should continue work and
    the parties would negotiate the costs later. At the time of the conversation, appellant was
    unaware of the exact amount of the additional costs and told Wade he would have to
    make some calculations before he knew the exact amount.
    {¶ 10} During the construction project, Wade was generally overseeing the
    project. Klingshirn delegated the responsibility to Wade to ensure that the project was
    completed and on time. Wade continually spoke with Klingshirn about the project. Both
    men had the right to sign checks to pay invoices, and Wade generally got approval from
    Klingshirn before paying any invoices. Earl directly dealt with Wade during the course
    of the project except for the one incident where he spoke with Klingshirn over the phone
    about the extra costs of the project.
    {¶ 11} Appellant completed the project in a time and manner that met the approval
    of CISP. Following the completion of the project, CISP paid appellant the balance of the
    contract which amounted to $25,500 based on an invoice from appellant. The bottom of
    this invoice stated extra work was still pending. CISP paid $15,520.97 in additional costs
    above the contracted price. Appellant then demanded an additional $47,491.97 which it
    claims is for the installation of the Liebert dual pump systems. In total, appellant asked
    CISP to pay $114,112.94 for a job which was originally contracted for $51,100. CISP
    refused to pay these extra costs. Consequently, appellant filed a mechanic’s lien against
    CISP’s lessee interest and Cuspide’s lessor interest on January 24, 2007.
    5.
    B. Procedural History
    {¶ 12} On February 21, 2008, CISP and Cuspide filed a complaint in Lucas
    County against appellant seeking to have the lien removed and other relief. Due to the
    forum selection clause in the contract, the case was transferred to Fulton County. CISP
    and Cuspide failed to pay the necessary filing fees and the case was dismissed.
    {¶ 13} On July 17, 2008, Cuspide filed a complaint against appellant seeking
    declaratory judgment, an order quieting Cuspide’s title by removing the mechanic’s lien,
    and damages for slander of title. Appellant moved to have the case dismissed so it could
    be brought in Fulton County on August 13, 2008. On November 24, 2008, the motion to
    dismiss was overruled, though the trial court required CISP to be involuntarily joined in
    the action or Cuspide would have to amend its complaint and remove its request for
    declaratory judgment. Cuspide filed an amended complaint on December 17, 2008,
    removing its request for declaratory judgment.
    {¶ 14} In response, appellant filed an answer and counterclaim. CISP and
    Huntington were then involuntarily joined by appellant’s counterclaim. The
    counterclaim asserted seven causes of action: breach of contract against CISP, breach of
    a modified contract against CISP and Cuspide, breach of a verbal contract against CISP
    and Cuspide, foreclosure of the mechanic’s lien, intentional and negligent
    misrepresentation against CISP and Cuspide, unjust enrichment against CISP and
    Cuspide, and abuse of process against CISP and Cuspide.
    6.
    {¶ 15} Following discovery, Cuspide moved for summary judgment as to its quiet
    title claim and the liability elements of its claim for slander of title. CISP and Cuspide
    both moved for summary judgment as to all counts of appellant’s counterclaim. Over the
    objection of CISP and Cuspide, and with leave of the court, appellant filed an amended
    counterclaim. The amended counterclaim included an agency theory between CISP and
    Cuspide which would make Cuspide liable on the contract between CISP and appellant.
    {¶ 16} Following the amendment, CISP and Cuspide renewed their motions for
    summary judgment. On April 20, 2012, the trial court granted summary judgment for
    Cuspide on its quiet title claim and the liability elements of its slander of title claim. The
    trial court granted summary judgment for CISP on most of appellant’s causes of action.
    On June 4, 2012, the trial court granted summary judgment for CISP on the remaining
    claims in the amended counterclaim. In this order, the trial court granted CISP fees and
    costs and asked CISP to enter evidence of their damages.
    {¶ 17} Appellant filed a request for findings of fact and conclusions of law as well
    as a motion for reconsideration of the June 4 order. The motion for reconsideration was
    granted on September 27, 2012, and the trial court determined fees should not have been
    granted. The trial court reserved determining the amount of fees to be awarded to the
    trier of fact. The motion for findings of fact and conclusions of law was ruled moot.
    {¶ 18} Appellant then moved for summary judgment as to Cuspide’s slander of
    title claim. The trial court granted appellant’s motion because Cuspide could not
    adequately prove its damages. Due to a fee sharing arrangement between Cuspide and
    7.
    CISP, Cuspide was unable to delineate which of its attorney fees were paid for its quiet
    title action and which were paid for its slander of title action. Cuspide was granted
    summary judgment as to all of appellant’s counterclaims on October 31, 2014.
    {¶ 19} Appellant now appeals the trial court’s grant of summary judgment for
    CISP and Cuspide on all counts of its amended counterclaim. Appellant also appeals the
    denial of its motion to dismiss and its motion for findings of fact and conclusions of law.
    Cuspide cross-appeals the granting of summary judgment for appellant on its slander of
    title claim on the issue of damages.
    C. Assignments of Error
    {¶ 20} Appellant presents five assignments of error for our review:
    [1.] The trial court erred when it denied appellant Earl Mechanical
    Services, Inc.’s motion to dismiss.
    [2.] The trial court erred when it granted Cuspide Properties, Inc.’s
    motion for summary judgment on its amended complaint.
    [3.] The trial court erred when it granted appellees Community ISP,
    Inc. and appellee Cuspide’s Properties, Inc.’s motions for summary
    judgment on appellant Earl Mechanical Services, Inc.’s amended
    counterclaims.
    [4.] The trial court erred when it ordered trier of fact to determine
    appropriateness of an award of fees and costs to appellee Community ISP,
    Inc. when no such award of fees and costs was ever requested by appellee
    8.
    Community ISP, Inc., nor is any award of fees and costs allowed under
    Ohio law.
    [5.] The trial court erred when it denied appellant Earl Mechanical
    Services, Inc.’s request for findings of fact and conclusions of law.
    {¶ 21} Cuspide brings one assignment of error for our review on its cross-appeal:
    [1.] The trial court erred in entering summary judgment for Earl on
    Cuspide’s slander-of-title claim.
    II. Analysis
    A. Motion to Dismiss
    {¶ 22} Appellant argues that its motion to dismiss should have been granted due to
    the forum selection clause in the contract between appellant and CISP. The trial court
    denied the motion because Cuspide was not a party to the contract that appellant is
    attempting to enforce. We agree.
    {¶ 23} A case can be involuntarily dismissed under Civ.R. 41(B)(1) when the
    plaintiff fails to prosecute or comply with a court order. Civ.R. 41(B)(1). The decision
    to grant a motion to dismiss is in the sound discretion of the trial court. Quonset Hut, Inc.
    v. Ford Motor Co., 
    80 Ohio St.3d 46
    , 47, 
    684 N.E.2d 319
     (1997), citing Jones v.
    Hartranft, 
    78 Ohio St.3d 368
    , 371, 
    678 N.E.2d 530
     (1997). An appellate court’s review
    is limited to determining if the trial court abused its discretion. 
    Id.
     “The term ‘abuse of
    discretion’ as it applies to a dismissal with prejudice for lack of prosecution implies an
    9.
    unreasonable attitude on the part of the court in granting [or denying] such motion.”
    Jones at 371, quoting Pembaur v. Leis, 
    1 Ohio St.3d 89
    , 91, 
    437 N.E.2d 1199
     (1982).
    {¶ 24} Appellant argues that Cuspide violated the trial court’s previous order to
    have the complaint filed by CISP and Cuspide moved to Fulton County when Cuspide
    filed the complaint underlying this appeal in Lucas County. However, there are several
    key differences between the two complaints. First, this suit was brought in the name of
    Cuspide only. The previous complaint, which was transferred to Fulton County, was
    filed by both Cuspide and CISP. Second, this suit originally did not entail the
    enforcement of the contract between appellant and CISP. Cuspide’s amended complaint
    does not involve a third-party beneficiary seeking to enforce the contract between CISP
    and appellant. Rather, Cuspide is seeking to quiet its title to the property. Finally,
    Cuspide was not a party to the contract between CISP and appellant and therefore is not
    bound by the forum selection cause contained within the contract. The trial court did not
    act with an unreasonable attitude when denying the motion to dismiss. Therefore, we
    find appellant’s first assignment of error not well-taken.
    B. Appellee Cuspide’s Claims
    1. Quiet Title
    {¶ 25} Appellant’s second assignment of error argues that genuine issues of
    material fact exist as to Cuspide’s claim to quiet the title on its property. Appellant
    argues that it had the right to enter a mechanic’s lien against Cuspide’s lessor interest in
    10.
    the Moffat Road property because CISP was acting as an agent of Cuspide when CISP
    entered into the contract with appellant.
    {¶ 26} Summary judgment decisions are reviewed by the appellate court de novo,
    using the same standard as the trial court. Lorain Natl. Bank v. Saratoga Apts., 
    61 Ohio App.3d 127
    , 129, 
    572 N.E.2d 198
     (9th Dist.1989). To succeed on a motion for summary
    judgment, a party must show (1) no genuine issues of material fact exist, (2) the moving
    party is entitled to judgment as a matter of law, and (3) reasonable minds can come to but
    one conclusion, when viewing the evidence most favorable to the nonmoving party, and
    that conclusion supports the moving party. Civ.R. 56(C). When a motion for summary
    judgment is made and supported, the opposing party then has the burden of setting forth
    specific facts showing there is a genuine issue for trial. Civ.R. 56(E).
    {¶ 27} A cloud on a title is a defect in title “that has a tendency even in the slight
    degree, to cast doubt upon the owner’s title, and to stand in the way of a full and free
    exercise of his ownership.” McClure v. Fischer Attached Homes, 
    145 Ohio Misc.2d 38
    ,
    
    2007-Ohio-7259
    , 
    882 N.E.2d 61
    , ¶ 13 (C.P.). An invalid lien creates the appearance that
    there is an encumbrance on one’s land where one does not exist. 
    Id.
    {¶ 28} An owner, co-owner, or lessee of real property can have a mechanic’s lien
    entered against their interest in real property if they fail to pay for work done to improve
    the property. R.C. 1311.02. In order to show a valid mechanic’s lien exists, a court must
    find that (1) a contract existed between the parties, (2) the contract provided for the labor
    or supplies to be delivered, (3) the labor or supplies were in furtherance of improvements
    11.
    to the property, and (4) the parties contracted for payment to be made due to the
    improvements. McClure at ¶ 15.
    {¶ 29} A mechanic’s lien only attaches to the interest for whom the improvement
    is made. Romito Bros. Elec. Const. Co. v. Frank A. Flannery, Inc., 
    40 Ohio St.2d 79
    , 81-
    82, 
    320 N.E.2d 294
     (1974). The lien will only attach to the lessee’s interest unless there
    was some relationship with the lessor. Mahoning Park Co. v. Warren Home Dev. Co.,
    
    109 Ohio St. 358
    , 365, 
    142 N.E. 883
     (1924). Generally, a person contracting to make
    improvements on real property is presumed to be an agent of the owner of the property
    unless that person is only a lessee of the property. R.C. 1311.10. Though an agency
    relationship is not presumed between a lessor and lessee, a lessor’s interest in property
    can be reached by a mechanic’s lien if the lessee is determined to be the agent of the
    lessor. See R.C. 1311.02. An agency relationship “exists only when one party exercises
    the right of control over the actions of another, and those actions are directed toward the
    attainment of an objective which the former seeks.” Hanson v. Kynast, 
    24 Ohio St.3d 171
    , 173, 
    494 N.E.2d 1091
     (1986).
    {¶ 30} Appellant has failed to show the existence of an agency relationship
    between CISP and Cuspide. Appellant claims CISP was an agent for Cuspide based
    mainly on the fact that Klingshirn is both CEO of CISP and owner of Cuspide. However,
    CISP is not an agent of Cuspide as CISP was never given any direct authority to act on
    behalf of Cuspide or to represent itself in that way.
    12.
    {¶ 31} CISP, Cuspide, or Klingshirn never held CISP out as an agent. Appellant
    only dealt with Klingshirn once during the entire process of the construction project.
    Appellant almost exclusively dealt with the president of CISP, Wade, during the project.
    Wade was solely an employee of CISP and did not represent himself in any other manner.
    The contract was signed between appellant and CISP. No mention of Cuspide or its
    business was made during the course of the parties’ negotiations. Wade signed the
    contract acting as the president of CISP. Appellant never dealt with Cuspide as an entity
    or Klingshirn while he was acting as the owner of Cuspide.
    {¶ 32} Appellant has failed to show that Klingshirn, acting as owner of Cuspide,
    exerted any control over CISP during the construction process. As the CEO of CISP,
    Klingshirn did participate in the construction project in determining which costs would be
    paid, and he had some discussion with the president about the project as it continued.
    However, appellant has failed to show how Cuspide exercised any judgment on the
    construction project other than by the mere fact that there is one corporate officer who is
    the same.
    {¶ 33} As there is no genuine issue of material fact about whether an agency
    relationship existed between CISP and Cuspide, and given that such a relationship is
    necessary to reach the lessor interest of Cuspide, we find appellant’s second assignment
    of error not well-taken.
    13.
    2. Slander of Title
    {¶ 34} Appellant and Cuspide appeal two of the trial court’s rulings on motions
    for summary judgment regarding Cuspide’s claim for slander of title. On May 1, 2012,
    the trial court awarded Cuspide summary judgment on the liability elements of its slander
    of title claim.
    {¶ 35} Following this order, both appellant and Cuspide filed competing motions
    for summary judgment on the issue of damages. The trial court granted appellant’s
    motion finding no genuine issues of material fact existed as to damages because Cuspide
    submitted insufficient evidence of its attorney fees. Specifically, Cuspide failed to
    indicate which causes of action the fees related to. Appellant appeals the trial court’s
    grant of summary judgment to Cuspide on the issue of liability, and Cuspide appeals the
    trial court’s grant of summary judgment on damages.
    {¶ 36} A slander of title claim can be “brought against any one who falsely and
    maliciously defames the property either real or personal, of another, and thereby causes
    him some special pecuniary damage or loss.” Green v. Lemarr, 
    139 Ohio App.3d 414
    ,
    430, 
    744 N.E.2d 212
     (2d Dist.2000). To prevail on a slander of title claim, the claimant
    must prove “(1) there was a publication of a slanderous statement disparaging claimant’s
    title; (2) the statement was false; (3) the statement was made with malice or made with
    reckless disregard of its falsity; and (4) the statement caused actual or special damages.”
    Green at 430-431.
    14.
    {¶ 37} In terms of a claim for slander of title, a person acts with malice when they
    act with reckless or wanton disregard of the rights of others. Consumer Food Industries,
    Inc. v. Fowkes, 
    81 Ohio App.3d 63
    , 72, 
    610 N.E.2d 463
     (9th Dist.1991). A person does
    not need to act out of personal hatred to act with malice in this context. 
    Id.
     “As a general
    rule, wrongfully recording an unfounded claim to the property of another constitutes
    slander of title.” McClure, 
    145 Ohio Misc.2d 38
    , 
    2007-Ohio-7259
    , at ¶ 21.
    {¶ 38} We find a slanderous statement disparaging Cuspide’s title was published
    when the mechanic’s lien was recorded by appellant. We find this statement was false, as
    no valid mechanic’s lien was in existence against Cuspide’s lessor interest. Further, the
    statement was a wrongful recording of an unfounded claim and thus constitutes a slander
    of title claim. We therefore find appellant’s second assignment of error not well-taken.
    {¶ 39} We now turn to Cuspide’s cross-assignment of error, appealing the trial
    court’s decision to grant summary judgment to appellant on the damages element of its
    slander of title claim. The trial court granted summary judgment in part due to Cuspide’s
    failure to sufficiently prove its damages. Cuspide and CISP are both represented by the
    same counsel. By agreement, CISP is paying for the representation of both parties and
    Cuspide is reimbursing CISP a flat fee of $1,000 per month. The fees are not itemized or
    separated between Cuspide’s two causes of action.
    {¶ 40} A party may recover as special damages in a slander of title action attorney
    fees necessary to counteract a disparaging publication, but may not recover costs of
    litigation and attorney fees incurred to prosecute the slander of title action. Green, 139
    15.
    Ohio App.3d at 435, 
    744 N.E.2d 212
    . Costs and fees that were incurred removing a
    cloud of title are recoverable without a finding of bad faith whereas slander of title,
    attorney fees and costs may only be recovered if the other party acted in bad faith. 
    Id.
    {¶ 41} Cuspide argues the trial court erred when entering summary judgment
    against it because it was unable to specify which portion of the attorney’s fees were paid
    toward the quiet title action and which were paid toward prosecuting the slander of title
    action. If claims can be separated “into a claim for which fees are recoverable and a
    claim for which no fees are recoverable, the trial court must award fees only for the
    amount of time spent pursuing the claim for which fees may be awarded.” Bittner v. Tri-
    Cty. Toyota, Inc., 
    58 Ohio St.3d 143
    , 145, 
    569 N.E.2d 464
     (1991). However, there are
    instances where it is not always possible to divide the fees for distinct claims. Some
    claims will “involve a common core of facts or will be based on related legal theories”
    and therefore may be “difficult to divide the hours expended on a claim-by-claim basis.”
    Hensley v. Eckerhart, 
    461 U.S. 424
    , 435, 
    103 S.Ct. 1933
    , 
    76 L.Ed.2d 40
     (1983).
    {¶ 42} The quiet title action and the slander of title action involve a common core
    of facts and are based on the same legal theory that the mechanic’s lien was invalid. Both
    actions required proving the mechanic’s lien was wrongful and that CISP was not an
    agent of Cuspide. The slander of title action did not require any additional information
    above what was needed for the quiet title action. Therefore, the trial court erred when it
    granted summary judgment to appellant based on the inability of CISP to differentiate its
    16.
    attorney fees between its two claims and therefore reverse the granting of summary
    judgment to appellant. Cuspide’s cross-assignment of error is found well-taken.
    3. Appellant’s Counterclaims Against Cuspide
    {¶ 43} Several of appellant’s assignments of error and claims in its counterclaim
    are based on the contention that CISP was acting as an agent of Cuspide. Appellant
    argues that CISP was acting as an agent of Cuspide at the time of the contract for two
    reasons: (1) Cuspide leased the property to CISP and (2) Klingshirn is both owner of
    Cuspide and CEO of CISP. As stated above, we do not find a genuine issue of material
    fact demonstrating that CISP was acting as an agent of Cuspide, and therefore any
    arguments by appellant based on an agency theory are without merit. We therefore
    affirm the granting of summary judgment to Cuspide on all of appellant’s counterclaims.
    We now turn to appellant’s claims against CISP.
    C. Appellant’s Claims Against CISP
    {¶ 44} All of appellant’s claims against CISP were disposed of by the trial court
    by granting CISP’s motion for summary judgment.
    1. Oral Modification of Contract
    {¶ 45} In appellant’s third assignment of error, it argues that a modification to the
    written contract with CISP was made by oral agreement, which CISP then breached when
    it failed to pay the additional $47,491.97 appellant is seeking. A contract cannot be
    modified unilaterally, but rather must be mutually consented to by both parties. Fraher
    Transit, Inc. v. Aldi, Inc., 9th Dist. Summit No. 24133, 
    2009-Ohio-336
    , ¶ 12, quoting
    17.
    Nagle Heating & Air Conditioning Co. v. Heskett, 
    66 Ohio App.3d 547
    , 550, 
    585 N.E.2d 866
     (4th Dist.1990). A written contract may be amended if the oral amendment has the
    essential elements of a binding contract. Fraher, at ¶ 12. Verbal modification of an
    existing contract must rest on new consideration “or must have been so far executed or
    acted upon by the parties that a refusal to carry it out would operate as a fraud upon one
    of the parties.” 
    Id.
    {¶ 46} Here, appellant’s alleged oral modification fails for lack of consideration.
    Consideration is a bargained for exchange between parties. Brads v. First Baptist Church
    of Germantown, Ohio, 
    89 Ohio App.3d 328
    , 336, 
    624 N.E.2d 737
     (2d Dist.1993), citing
    Software Clearinghouse, Inc. v. Intrak, Inc., 
    66 Ohio App.3d 163
    , 175, 
    583 N.E.2d 1056
    (1st Dist.1990). Consideration can either be a detriment to the promisee or a benefit to
    the promisor. 
    Id.
     A promise to do what one is already bound to do is not sufficient
    consideration for a new contract. Shannon v. Univeral Mtge. & Discount Co., 
    116 Ohio St. 609
    , 621, 
    157 N.E.2d 478
     (1927). During Earl’s conversation with Wade and
    Klingshirn, appellant promised to complete the job it was already contractually obligated
    to complete. Appellant claims that continuing to work on the project despite the
    mounting costs serves as consideration for the new agreement between the parties. This
    is an incorrect claim, however, because threatening to breach a contract and then
    continuing to fulfill one’s obligations does not serve as new consideration. The mere fact
    that the job cost appellant more than it originally bid does not constitute new
    consideration to sustain the oral modification of the written agreement. We therefore find
    18.
    no genuine issues of material fact exist as to the verbal modification of the written
    agreement between appellant and CISP. Accordingly, we find appellant’s modification
    argument not well-taken.
    2. Breach of New Verbal Contract
    {¶ 47} Appellant argues in the alternative that a new verbal contract was created
    during the conversation between Earl, Wade, and Klingshirn. A contract is a promise or
    a set of promises that can be enforced when one person fails to fulfill the promise.
    Kostelnik v. Helper, 
    96 Ohio St.3d 1
    , 
    2005-Ohio-2985
    , 
    770 N.E.2d 58
    , ¶ 16, citing
    Pawlowski v. Pawlowski, 
    83 Ohio App.3d 794
    , 798-799, 
    615 N.E.2d 1071
     (10th
    Dist.1992). A contract consists of an offer, acceptance, and consideration. 
    Id.,
     citing
    Perimuter Printing Co. v. Strome, Inc., 
    436 F.Supp. 409
    , 411 (N.D.Ohio 1976).
    Consideration is the bargained for legal benefit or detriment. 
    Id.
     “A meeting of the
    minds as to the essential terms of the contract is a requirement to enforcing the contract.”
    
    Id.,
     citing Episcopal Retirement Homes, Inc. v. Ohio Dept. of Indus. Relations, 
    61 Ohio St.3d 366
    , 369, 
    575 N.E.2d 134
     (1991). “Terms of an oral contract may be determined
    from words, deeds, acts, and silence of the parties.” Id. at ¶ 15, citing Rutledge v.
    Hoffman, 
    81 Ohio App. 85
    , 
    75 N.E.2d 608
     (1st Dist.1947), paragraph one of the syllabus.
    {¶ 48} Appellant claims that the conversation between Earl, Wade, and Klingshirn
    created a new verbal contract for the extra costs of the project. During the conversation
    with Wade and Klingshirn, Earl stated that there were mounting costs above the contract
    price. Wade and Klingshirn stated that the project needed to be completed as there was a
    19.
    deadline and that the parties would sit down and figure out the total price afterward. This
    conversation took place several months after the contract between the parties was signed.
    Within this conversation, Earl only promised to complete the project he was already
    contractually obligated to complete. He merely told Wade and Klingshirn it was going to
    cost him more than he originally budgeted. Wade and Klingshirn promised to negotiate
    the extra costs following the project.
    {¶ 49} Appellant’s argument regarding the formation of a new contract fails
    because this “new” contract is not supported by consideration. A promise to complete an
    already existing obligation does not constitute consideration to support a contract.
    Shannon, 116 Ohio St. at 621, 
    157 N.E.2d 478
    . Here, all appellant promised in this
    conversation was to complete the project the parties had already agreed it would
    complete. Its only option at the point when it realized the costs would be too high would
    be to breach the contract and cut any potential losses. As there was no consideration to
    support this alleged new agreement, appellant’s argument is not well-taken.
    {¶ 50} Furthermore, the alleged contract fails as there was no meeting of the
    minds as to the essential terms of the contract between the parties. Earl told Wade and
    Klingshirn that he would have to get back to them as to the actual costs of the project.
    No terms to the “contract” were ever discussed thereafter until CISP received an invoice
    doubling the amount originally agreed upon. As there is no genuine issue of material fact
    as to whether a new verbal contract existed, we affirm the trial court’s decision to grant
    CISP summary judgment on appellant’s breach of contract claim.
    20.
    3. Foreclosure of Mechanic’s Lien
    {¶ 51} Appellant appeals the granting of summary judgment to CISP on the
    foreclosure of the mechanic’s lien placed on CISP’s lessee interest. The Ohio Revised
    Code allows anyone who performs labor on real property for improvements to the
    property to place a lien thereon to secure payment for the labor or materials expended to
    make those improvements. R.C. 1311.02. The work or material must be “undertaken by
    virtue of a contract, express or implied.” 
    Id.
     As noted above, appellant has failed to
    establish the existence of a contract for the additional costs it is seeking. Nonetheless, it
    argues that the additional costs could still be recovered under a mechanic’s lien because
    the costs constituted extra work.
    {¶ 52} The Ohio Mechanic’s Lien Act does not require a signed change order for a
    contractor to recover under the Act. Midwest Curtainwalls, Inc. v. Pinnacle 701, LLC,
    8th Dist. Cuyahoga No. 92269, 
    2009-Ohio-3740
    , ¶ 61. Also, “Ohio law has been clear
    for over one hundred years that when a subcontractor performs extra work on an
    improvement to real property, it may include such extra work in its lien claim.” 
    Id.,
    citing Dunn & Witt v. Rankin & Co., 
    27 Ohio St. 132
     (1875). A party’s verbal
    instructions to change the project outside what was included in the specifications creates
    a “constructive change order” and allows for additional recovery of costs. 
    Id.
    {¶ 53} Here, despite appellant’s contention, the original specifications were not
    changed from the contract. Appellant did not provide any extra work or materials to the
    project with CISP. Rather appellant’s contract with CISP was to install the air
    21.
    conditioning and condenser units along with two dual pumps for the units. Appellant was
    aware of the change to the dual pump system before entering the contract as there is a
    notation on the contract for the price of the pumps. The Liebert dual pump system was
    more complicated than the single pump system that was originally discussed by the
    parties, but the contract clearly states that the price quote was for the Liebert system
    installation. As the mechanic’s lien for the additional amounts was not based on a
    contract and did not constitute extra work provided by appellant, we find that the trial
    court properly extinguished appellant’s mechanic lien on CISP’s lessee interest in the
    property.
    4. Intentional Misrepresentation
    {¶ 54} Appellant also alleges that the trial court erred when it granted summary
    judgment for CISP on its claims of intentional and negligent misrepresentation. To
    succeed on an intentional misrepresentation claim, a party must show (1) a representation
    was made; (2) was material to the transaction at hand; (3) was knowingly false, or was
    made with such utter disregard and recklessness as to whether it is true or false that
    knowledge may be inferred; (4) with the intent of misleading another party into relying
    on it; (5) justifiable reliance on the representation; and (6) a resulting injury proximately
    caused by the reliance. Burr v. Bd. of Cty. Commrs. of Stark Cty., 
    23 Ohio St.3d 69
    , 73,
    491 NE.2d 1101 (1986), quoting Cohen v. Lamko, 
    10 Ohio St.3d 167
    , 169, 
    462 N.E.2d 407
     (1984).
    22.
    {¶ 55} Appellant argues that during the conversation between Earl, Wade, and
    Klingshirn, Wade and Klingshirn made intentional misrepresentations to Earl about
    paying the additional costs of the project. During the conversation, Earl warned that
    extra costs were mounting on the project. Klingshirn responded by asking Earl to
    continue with the project and stated that the two companies would agree on costs after the
    work was completed. Appellant now claims that this was a misrepresentation because
    Wade, Klingshirn, and CISP had no intention of ever paying the extra costs. We
    disagree.
    {¶ 56} A misrepresentation must be a fact rather than a promise. RAE Assocs.,
    Inc. v. Nexus Communications, Inc., 
    2015-Ohio-2166
    , 
    36 N.E.3d 757
    , ¶ 16. “‘Fraud is
    generally predicated on a misrepresentation relating to a past or existing fact, and not on
    promises or representations relating to future actions or conduct.’” 
    Id.,
     quoting Krukrubo
    v. Fifth Third Bank, 10th Dist. No. 09AP-933, 
    2010-Ohio-1691
    , ¶ 9. An exception to this
    rule exists, however, where an individual makes a promise concerning a future action,
    occurrence, or conduct, and at the time of the promise, the individual has no intention of
    keeping the promise. 
    Id.,
     quoting Williams v. Edwards, 
    129 Ohio App.3d 116
    , 124, 
    717 N.E.2d 368
     (1st Dist.1989). The fact that the promise was later unfulfilled is not enough
    to meet the burden of proving a misrepresentation in this manner. Wall v. Firelands
    Radiology, Inc., 
    106 Ohio App.3d 313
    , 328, 
    666 N.E.2d 235
     (6th Dist.1995), citing
    Lightning Lube, Inc. v. Witco Corp., 
    4 F.3d 1153
    , 1186 (3d Cir.1993).
    23.
    {¶ 57} The record does not contain any evidence CISP had no intention of paying
    any additional amounts to appellant at the time the discussion between Earl, Wade, and
    Klingshirn took place. CISP has actually paid almost $16,000 above the contract price
    for additional expenses incurred by appellant. When viewing the evidence most
    favorable to appellant, we cannot find a genuine issue of material fact as to the claim of
    intentional misrepresentation.
    5. Negligent Misrepresentation
    {¶ 58} Appellant’s claim for negligent misrepresentation also fails. A negligent
    misrepresentation occurs when (1) one, in the course of his or her employment, or in a
    transaction in which he or she has a pecuniary interest; (2) supplies false information to
    others in their business transactions; (3) another party justifiably relies on the
    information; (4) if he or she fails to exercise reasonable care or competence in obtaining
    or communicating the information. Martin v. Ohio State Univ. Found., 
    139 Ohio App.3d 89
    , 103, 
    742 N.E.2d 1198
     (10th Dist.2000), citing Delman v. Cleveland Hts., 
    41 Ohio St.3d 1
    , 4, 
    534 N.E.2d 835
     (1986). An affirmative false statement must be made for a
    negligent misrepresentation to be found. 
    Id.,
     citing Textron Fin. Corp. v. Nationwide
    Mut. Ins. Co., 
    115 Ohio App.3d 137
    , 149, 
    684 N.E.2d 1261
     (9th Dist.1996).
    {¶ 59} No genuine issues of material fact exist about whether CISP supplied false
    information to appellant during their transactions. When viewing the evidence in a light
    most favorable to appellant, the record does not reflect any false statement made by CISP
    or its agents during the course of the construction project. Once again, appellant claims
    24.
    that Wade and Klingshirn made false statements about payment of the additional costs of
    the project. However, the record does not show that these statements were false. CISP
    paid more money than the contract requires, albeit not double the contract price as
    appellant argues it is entitled to. Some discussion about actual costs of the project as well
    as the amounts CISP was willing to pay also occurred which is all CISP promised to do.
    We therefore find appellant’s negligent misrepresentation argument not well-taken.
    6. Unjust Enrichment
    {¶ 60} Appellant also appeals the granting of CISP’s motion for summary
    judgment on its unjust enrichment claim. Unjust enrichment occurs when “(1) a benefit
    is conferred by a plaintiff upon a defendant; (2) knowledge by the defendant of that
    benefit; and (3) retention of the benefit by the defendant under circumstances where it
    would be unjust to do so without payment.” Hambleton v. R.G. Barry Corp., 
    12 Ohio St.3d 179
    , 183, 
    465 N.E.2d 1298
     (1984). However, when two competent parties contract,
    and no fraud or illegality is involved, unjust enrichment cannot be claimed. Ullmann v.
    May, 
    147 Ohio St. 468
    , 476, 
    72 N.E.2d 63
     (1947). “That the terms of the agreement
    appear (and may work out to be) harsh may be admitted, but unless there is fraud or other
    unlawfulness involved, courts are powerless to save a competent person from the effects
    of his own voluntary agreement.” 
    Id.
     As long as the terms of the agreement are plain
    and unambiguous, the court will not correct the agreement between the parties, even if
    the contract terms are a hardship on one of the parties. Id.
    25.
    {¶ 61} The trial court correctly granted summary judgment in favor of CISP on the
    unjust enrichment claim as the parties voluntarily entered into a contractual agreement,
    and appellant does not claim any fraud or illegality in the contract. Further, both parties
    were competent at the time the contract was made. Appellant signed a contract for much
    less than its costs would be, but it had to at least be aware that the costs would be higher
    than it anticipated when Wade asked why its bid was about one-half the costs of another
    construction company. Though it may be a hardship on appellant, it made a voluntary
    agreement that must be enforced. We therefore affirm the trial court’s ruling and find no
    genuine issues of material fact exist to support appellant’s claim for unjust enrichment.
    Appellant’s third assignment of error is found not well-taken in its entirety.
    7. Findings of Fact and Conclusion of Law and
    Determination of Fees by Trier of Fact
    {¶ 62} We combine appellant’s fourth and fifth assignments of error for review.
    We agree with the trial court’s finding that appellant’s motion for findings of fact and
    conclusions of law was moot, as the trial court had vacated the earlier order granting fees
    to CISP. When questions of fact are determined by the court, a party may ask within
    seven days for the court’s findings of fact and conclusions of law. Civ.R. 52.
    {¶ 63} Here, the trial court denied appellant’s motion for findings of fact and
    conclusions of law because the motion was moot. In the trial court’s June 4 order
    granting summary judgment to CISP on appellant’s counterclaims, the trial court granted
    fees to CISP. CISP never sought these fees in any motion. Appellant then made a
    26.
    motion for reconsideration and for findings of fact and conclusions of law. The trial
    court granted appellant’s motion for reconsideration and vacated its previous order
    granting fees to CISP. In the same order, the trial court found appellant’s motion for
    findings of fact and conclusions of law to be moot as the previous order was vacated.
    The trial court also stated in this order that any fees would be determined by the trier of
    fact. Appellant argues that no fees should be granted and therefore asks for findings of
    fact as to why the trial court stated that fees would be determined by the trier of fact.
    {¶ 64} No attorney fees have been assessed in this case and the trial court did not
    order fees to be assessed, but merely stated that if they were to be charged against
    appellant, the fees would be determined by the trier of fact. There has not been a final
    order granting CISP any fees with regard to appellant’s counterclaims. Thus, the motion
    for findings of fact and conclusions of law is still moot. Accordingly, appellant’s fourth
    and fifth assignments of error are not well-taken.
    II. Conclusion
    {¶ 65} In light of the foregoing, the judgment of the Lucas County Court of
    Common Pleas is affirmed, in part, and reversed, in part. We remand to the trial court for
    determination of whether Cuspide has proven damages in its slander of title action. Costs
    shall be assessed to appellant pursuant to App.R. 24.
    Judgment affirmed, in part,
    and reversed, in part.
    27.
    Cuspide Properties, Ltd. v.
    Earl Mechanical Servs.
    C.A. No. L-14-1253
    A certified copy of this entry shall constitute the mandate pursuant to App.R. 27.
    See also 6th Dist.Loc.App.R. 4.
    Mark L. Pietrykowski, J.                       _______________________________
    JUDGE
    Arlene Singer, J.
    _______________________________
    Stephen A. Yarbrough, P.J.                                 JUDGE
    CONCUR.
    _______________________________
    JUDGE
    This decision is subject to further editing by the Supreme Court of
    Ohio’s Reporter of Decisions. Parties interested in viewing the final reported
    version are advised to visit the Ohio Supreme Court’s web site at:
    http://www.sconet.state.oh.us/rod/newpdf/?source=6.
    28.