New England Etc. Co. v. Chicago Etc. Co. , 36 Cal. App. 584 ( 1918 )


Menu:
  • Plaintiff's assignor, one Carr, entered into a contract with the regents of the University of California to build a class-room at Davis, and sublet the portion of his contract to defendant Macdonald, taking a bond from defendant Surety Company for Macdonald's faithful performance of his contract. Macdonald abandoned the work, whereupon Carr proceeded to do it himself; but later, becoming financially embarrassed, was unable to finish the work, and the regents took it over, completed the job, and deducted the cost thereof, amounting to $1,409, from the money payable to Carr under his contract. On this state of facts plaintiff had judgment against defendant Surety Company for $750, the full amount of its bond. *Page 585

    But two points are presented on this appeal. The contract provided that in the event that Macdonald should delay the work Carr might prosecute it "if same is not done after three days' notice." It is claimed that Carr did not give this notice before proceeding with the work after Macdonald's abandonment, and that the surety was thereby relieved from liability. As was expressly held by this court in Bacigalupi v. Phoenix Bldg.etc. Co., 14 Cal.App. 632, 639, [112 P. 892], notice is unnecessary where the contractor entirely abandons thecontract, which the trial court expressly found to be the fact in the case at bar.

    Appellant's only other contention is that because Carr did not himself complete the work, he was not injured by Macdonald's failure to do the work. The owner did complete the work, at an actual and reasonable cost of $925.50, and as this amount was deducted from the amount to be paid to Carr on his contract, it is obvious that he was damaged to the extent of this deduction.

    The appeal in this case, as in another case appealed by the same defendant at this term of court, is obviously without merit, and we are satisfied that the same was taken for the purpose of delay. We are of the opinion that the judgment should be affirmed, and that the plaintiff should recover from the defendant Surety Company the sum of fifty dollars as damages for a frivolous appeal. It is therefore so ordered.

    Kerrigan, J., and Beasly, J., pro tem., concurred.

Document Info

Docket Number: Civ. No. 2175.

Citation Numbers: 172 P. 1122, 36 Cal. App. 584

Judges: ZOOK, J., <italic>pro tem.</italic> &#8212;

Filed Date: 3/26/1918

Precedential Status: Precedential

Modified Date: 1/12/2023