Mindlin v. O'Boyle , 283 Pa. 352 ( 1925 )


Menu:
  • Argued April 15, 1925. In our prior opinion in this case (278 Pa. 212), we approved the finding of the court below that defendants had broken their contract with plaintiffs, but reversed the judgment, and remitted the record with a procedendo, that additional testimony might be taken and the amount of damages legally ascertained. We did this because the contract, by which defendants agreed to sell coal to plaintiffs, provided for delivery "f. o. b. cars, mines," and the proofs failed to show that, after the breach, coal could not have been obtained at the mines; *Page 354 hence it was error, under that evidence, to measure the damages by the difference between the contract price and the market price elsewhere. On the return of the record, plaintiffs produced other testimony, but defendants did not, although the latter had personal knowledge touching the single point to be considered. Apparently they preferred to pick flaws in plaintiffs' proofs, — as of course they had the right to do, — perhaps because their testimony would have strengthened and not weakened plaintiffs' case. The court below found in favor of plaintiffs, and defendants again appealed.

    Their first complaint is that appellees had no right to prove the market value of coal at any other point than the mines, where it was to be delivered, and where primarily its cost was to be ascertained, because the statement of claim did not aver it could not be obtained there. This was, however, a matter of evidence, which could not properly be pleaded, since it would not have resulted in the concise statement required by statute: Electric Reduction Co. v. Colonial Steel Co., 276 Pa. 181. The averment that "through the failure of the defendants to deliver the coal as aforesaid, the plaintiffs were compelled to go in the market and buy the same kind of coal at a cost of $11 per short ton," was all plaintiffs were required to allege.

    It is also claimed that the court below erred in not allowing defendants to file additional exceptions, more than six months after the time permitted by the statute under which the case was tried. This was not error; to have allowed it probably would have been: Harris v. Mercur (No. 1), 202 Pa. 313.

    The other three assignments object: (1) to the finding of fact by the trial judge, that "during the period of breach plaintiffs could not obtain the coal for which they had contracted, at the place of delivery, or in any other available market nearer thereto than New York . . . . . . where they did obtain the coal for the current market price of $11 per ton"; (2) to his conclusion that, *Page 355 on the evidence produced, plaintiffs could recover more than nominal damages, and (3) to his assessing the amount of actual damages, in accordance with his finding quoted in clause (1). A determination of the first of these assignments adversely to appellants, necessarily carried with it, therefore, antagonistic decisions as to the other two. Hence, it is sufficient to say there was ample evidence (1) that the coal could not be bought at the mines from which it was to be delivered, or elsewhere in the anthracite coal regions (in which alone the character of coal contracted for was mined), unless plaintiffs would purchase also a quantity of the smaller sizes, which they were not obliged to do; and, also, (2) to sustain the trial judge's inference and conclusion as follows: "It is fair to assume that, if the coal could not be obtained in the immediate region of production, without the encumbrance of 'steam' sizes, its market price at any other place would only be affected by the cost of transportation thither, and New York City would enjoy at least equal advantage with any other market in that respect. In a word, during the period of breach, plaintiffs could not obtain the coal for which they had contracted, at the place of delivery, or in any other available market nearer thereto than New York City, which was also of course the most available for themselves, and where they did obtain the coal for the current price, $11 per ton delivered." In measuring the damages, he, therefore, considered that price, less the cost of transportation from the mines to the place of delivery in New York City (which was, as everybody knows, the greatest distributing center for coal shipped from the anthracite regions), as fixing the market value at the time of the breach. Under the facts found this was proper.

    The judgment of the court below is affirmed. *Page 356

Document Info

Citation Numbers: 129 A. 81, 283 Pa. 352

Judges: OPINION BY MR. JUSTICE SIMPSON, May 4, 1925:

Filed Date: 4/15/1925

Precedential Status: Precedential

Modified Date: 1/13/2023