Berkshire Environmental Action v. Tennessee Gas Pipeline Company , 851 F.3d 105 ( 2017 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 16-2100
    BERKSHIRE ENVIRONMENTAL ACTION TEAM, INC.; JEAN ATWATER-
    WILLIAMS; RONALD M. BERNARD; CATHY KRISTOFFERSON; CHERYL D.
    ROSE; IRVINE SOBELMAN; PAULA L. TERRASI; SUSAN K. THEBERGE;
    ROSEMARY WESSEL; KATHRYN R. EISEMAN; ARIEL S. ELAN; ELLIOT
    FRATKIN; MARTHA A. NATHAN; KENNETH HARTLAGE; RONALD R. COLER;
    JANE WINN; HEATHER MORRICAL,
    Petitioners,
    v.
    TENNESSEE GAS PIPELINE COMPANY, LLC; MASSACHUSETTS DEPARTMENT OF
    ENVIRONMENTAL PROTECTION,
    Respondents.
    PETITION FOR REVIEW OF AN ORDER OF
    THE MASSACHUSETTS DEPARTMENT OF ENVIRONMENTAL PROTECTION
    Before
    Kayatta, Circuit Judge,
    Souter, Associate Justice,*
    and Selya, Circuit Judge.
    Richard A. Kanoff, with whom Susan E. Stenger, Saqib Hossain,
    and Burns & Levinson LLP were on brief, for petitioners.
    Matthew Ireland, Assistant Attorney General, Environmental
    Protection Division, with whom Seth Schofield, Assistant Attorney
    General and Senior Appellate Counsel, Energy and Environment
    Bureau, Office of the Attorney General of Massachusetts, Maura
    Healey, Attorney General of Massachusetts, and Turner Smith,
    * Hon. David H. Souter, Associate Justice (Ret.) of the
    Supreme Court of the United States, sitting by designation.
    Assistant Attorney General, Environmental Protection Division,
    were on brief, for Massachusetts Department of Environmental
    Protection.
    James L. Messenger, with whom Brian J. Wall, Gordon Rees
    Scully Mansukhani, LLP, J. Curtis Moffatt, and Mosby G. Perrow
    were on brief, for Tennessee Gas Pipeline Company, LLC.
    March 15, 2017
    KAYATTA, Circuit Judge.           In this unusual petition for
    review arising out of a state administrative proceeding, the
    petitioners themselves argue that we lack jurisdiction to hear
    their complaints about what has transpired to date before the state
    agency.     Because the agency itself has not yet finally acted on
    the   matter     that   is   before    it   as    is    required      to   invoke    our
    jurisdiction under 15 U.S.C. § 717r(d)(1), we agree and dismiss
    the petition.
    I.     Background
    The Natural Gas Act ("NGA") requires a natural gas
    company to obtain from the Federal Energy Regulatory Commission
    ("FERC") a certificate of public convenience and necessity before
    it may construct new natural gas transportation facilities or
    expand    existing      ones.   15     U.S.C.     §    717f(c)(1)(A).         FERC    is
    responsible for coordinating all federal authorizations applicable
    to the process.           Id. § 717n(b)(1).             The NGA also expressly
    preserves the rights of states under the Coastal Zone Management
    Act of 1972, 
    16 U.S.C. §§ 1451
    –1466; the Clean Air Act, 
    42 U.S.C. §§ 7401
    –7671q; and the Clean Water Act ("CWA"), 
    33 U.S.C. §§ 1251
    –
    1388.     See 15 U.S.C. § 717b(d).          Under the CWA, any applicant for
    a federal license to construct or operate facilities that may
    result    in    discharge    into     navigable       waters   must    "provide      the
    licensing or permitting agency"--here, FERC--"a certification from
    the State in which the discharge originates or will originate."
    - 3 -
    
    33 U.S.C. § 1341
    (a)(1).               The state, in turn, must evaluate the
    proposed project's compliance with certain provisions of the CWA
    and set forth limitations and monitoring requirements "necessary
    to assure that any applicant for a Federal license or permit will
    comply" with the CWA "and with any other appropriate requirement
    of State law set forth in such certification."                      
    Id.
     § 1341(d).      A
    condition imposed under the state's certification "shall become a
    condition     on    any     Federal     license      or    permit     subject    to    the
    provisions of this section."                Id.
    On July 31, 2014, Tennessee Gas Pipeline Company, LLC
    ("Tennessee Gas") applied to FERC for a certificate of public
    convenience        and    necessity,        which   FERC     eventually       issued    in
    March 2016 subject to, among other things, filing of proof that
    Tennessee Gas has received "all applicable authorizations required
    under federal law (or evidence of waiver thereof)."                       In pursuit of
    one    such    authorization          (or    waiver       thereof),      Tennessee     Gas
    submitted     an    application        to    the    Massachusetts        Department    of
    Environmental            Protection     ("MassDEP")          for      water      quality
    certification on June 30, 2015.               On June 29, 2016, after almost a
    full   year    during       which   interested        citizens     and    environmental
    organizations            (including     Petitioners)          participated        in     a
    nontestimonial notice-and-comment process, Tennessee Gas received
    conditional certification for its proposed project in a letter
    - 4 -
    from the Western Regional Office of MassDEP signed by Wetlands
    Program Chief David Cameron.
    The   letter   contained    over     forty    conditions     to    the
    project's    approval,     including    a    condition--"Condition          15"--
    forbidding Tennessee Gas from conducting any "work subject to this
    Certification,     including   the     cutting    of     trees,"    until     "the
    expiration of the Appeal Period set forth below and any appeal
    proceedings that may result from an appeal."                 The conditional
    certification also described the appeal process, explaining that
    "[c]ertain persons shall have a right to request an adjudicatory
    hearing concerning certifications by the Department," including
    "[a]ny person aggrieved by this certification who has submitted
    written comments during the public comment period."                In accordance
    with Massachusetts regulations on the subject, the conditional
    certification provided that any person who wished to appeal was
    required to submit a Notice of Claim for Adjudicatory Hearing
    within twenty-one days of the certification's issuance.
    Petitioners took advantage of this provision, filing a
    Notice of Claim for Adjudicatory Hearing on July 20, 2016.                     In
    response, Tennessee Gas opposed Petitioners' request for a hearing
    and sought a stay of further administrative proceedings, claiming
    that once the agency had issued a conditional water quality
    certification, the state's involvement in the process was at an
    end, with any further review to be pursued through a petition to
    - 5 -
    this court.      Petitioners disagreed, as did MassDEP, which denied
    Tennessee Gas's request for a stay and moved forward, scheduling
    a final decision to be issued by April 3, 2017.                 In early August
    2016, Tennessee Gas filed suit in the District of Massachusetts
    seeking    to     bar     MassDEP    from     engaging   in    further      review.
    Petitioners, in turn, hedged their bets.             They filed the petition
    now before us in order to preserve some review of the June 29
    conditional      water     quality    certification      in    the    event    that
    Tennessee Gas was correct.            At the same time, they asked us to
    reject their petition on the grounds that Tennessee Gas is not
    correct; that is to say, they claim that our review is premature
    until MassDEP completes its adjudicatory process.
    II.     Discussion
    A.
    We begin with the language of the statute that grants us
    the jurisdiction putatively invoked by this petition.                       We have
    exclusive jurisdiction "over any civil action for the review of an
    order or action of a . . . State administrative agency acting
    pursuant to Federal law [in ruling on an application, as pertinent
    here,     for    a   water    quality       certification     under    
    33 U.S.C. § 1341
    (a)(1)]." 15 U.S.C. § 717r(d)(1). In a literal sense, state
    agencies repeatedly take "action" in connection with applications
    for   water     quality    certifications.        They   docket      applications,
    review them, and express opinions about them.                 We see no reason,
    - 6 -
    though, to think that Congress wanted us to exercise immediate
    review over such preliminary and numerous steps that state agencies
    may take in processing an application before they actually act in
    the more relevant and consequential sense of granting or denying
    it.
    Pushing back on this common sense conclusion, Tennessee
    Gas points to the fact that § 717r(d)(1) employs the term "action,"
    bereft of the modifier "final."            This contrasts with, for example,
    the text employed in the Administrative Procedure Act ("APA"), 
    5 U.S.C. § 704
     ("Agency action made reviewable by statute and final
    agency action for which there is no other adequate remedy in a
    court are subject to judicial review."), and with the text of 15
    U.S.C. § 717r(b), which permits judicial review of FERC orders
    only   after    FERC's    denial      of    an    application     for     rehearing.
    Therefore,     reasons    Tennessee        Gas,   we    should    infer    that,   by
    authorizing our review of state agency action, Congress did not
    limit such review to final agency action.
    Such a negative inference might have interpretative
    force in dealing with some other subject matter.                   See generally,
    e.g., Barnhart v. Sigmon Coal Co., 
    534 U.S. 439
    , 452 (2002)
    (articulating    the     rule    of   statutory        construction     that   courts
    should   typically     infer     that      Congress     intends   differences      in
    statutory      language     to        effect      differences      in      statutory
    application).    Here, though, the subject matter is judicial review
    - 7 -
    of agency action, which review Congress creates in the context of
    a long-standing and well-settled "strong presumption . . . that
    judicial review will be available only when agency action becomes
    final."    Bell v. New Jersey, 
    461 U.S. 773
    , 778 (1973) (citing FPC
    v. Metro. Edison Co., 
    304 U.S. 375
    , 383-85 (1938)).            To say that
    silence on the subject implies no requirement of finality would be
    to recognize this "strong presumption" only when it is of little
    benefit.
    It is also unclear that Congress's reference to FERC's
    internal review process in § 717r(b), coupled with the lack of a
    similar reference in § 717r(d)(1) to the internal review processes
    of state agencies, even raises the inference that Tennessee Gas
    claims.     Rather,   there   is   a   more   plausible   explanation    for
    Congress's decision to write the statute this way:              unlike the
    FERC procedures described in § 717r(b), which are the same for any
    applicant proposing a project in any state or states, the state
    procedures giving rise to orders reviewable under § 717r(d)(1) may
    (and   undoubtedly     do)    vary     widely    from     jurisdiction    to
    jurisdiction.     Thus, whereas it is reasonable to interpret a
    reference to FERC's rehearing process as a signal that final agency
    action is required under § 717r(b), it does not make sense to draw
    the negative inference that the lack of a reference in § 717r(d)(1)
    to the variegated internal review mechanisms deployed by state
    agencies sends the opposite signal.             Simply put, the text of
    - 8 -
    § 717r(d)(1), on its own or read alongside § 717r(b), does not
    rebut the strong presumption that judicial review is available
    only following final agency action.
    Further       reinforcement        for     the   strong   presumption
    restricting review until an agency has taken final action resides
    in Congress's numerous efforts to prevent states from unreasonably
    delaying the performance of their reserved roles in connection
    with natural gas projects.          In connection with any permit required
    by federal law, § 717r(d)(2) authorizes the United States Court of
    Appeals for the District of Columbia to issue injunctive relief
    when a state agency "fail[s] to act" on such a permit in accordance
    with a schedule established by FERC.                 Where the permit is a water
    quality certification required by 
    33 U.S.C. § 1341
    (a)(1), a state
    waives its right in connection with a FERC application if it "fails
    or   refuses   to   act    on   a   request     for    certification,   within   a
    reasonable period of time (which shall not exceed one year) after
    receipt of such request.”           
    Id.
       The very fact that Congress has
    granted us the unusual ability to review directly (and on an
    expedited basis, 15 U.S.C. § 712r(d)(5)) action by a state agency
    can itself be seen as further evidence that Congress sought to
    reduce the potential for the use of delay to block natural gas
    projects.      Certainly        nothing   in    the     legislative   history    of
    § 717r(d)(1) belies that perception.             See Islander E. Pipeline Co.
    v. Conn. Dep't of Envtl. Prot., 
    482 F.3d 79
    , 85 (2d Cir. 2006)
    - 9 -
    ("[A]pplicants . . . were encountering difficulty proceeding with
    natural gas projects that depended on obtaining state agency
    permits." (citing Regional Energy Reliability and Security:                 DOE
    Authorization to Energize the Cross Sound Cable:               Hearing Before
    the H. Subcomm. on Energy & Air Quality, 108th Cong. 8 (2004)
    (statement of Rep. Barton), and Natural Gas Symposium:              Symposium
    Before the S. Comm. on Energy & Nat. Res., 109th Cong. 41 (2005)
    (statement of Mark Robinson, Director, Office of Energy Projects,
    FERC))).     A Congress that placed so much emphasis upon avoiding
    delay in the adjudication of requests for certification of this
    type would not likely have intended to authorize the delay that
    interlocutory reviews of every state agency action, final or not,
    would inevitably engender.
    Tennessee   Gas   contends   that   finding   a    final    agency
    action requirement in § 717r(d)(1) nevertheless puts us at odds
    with the Second Circuit's decision in Islander East.                    In that
    decision, the court did not dismiss the case sua sponte for lack
    of subject matter jurisdiction even though, Tennessee Gas says,
    the state agency had not taken final action.         Therefore, Tennessee
    Gas reasons, the Second Circuit must have construed § 717r(d)(1)
    to confer subject matter jurisdiction to review non-final agency
    action.    See Tenn. Gas Pipeline Co. v. Del. Riverkeeper Network,
    
    921 F. Supp. 2d 381
    , 392–93 (M.D. Pa. 2013) (articulating this
    argument).    We think it a stretch, however, to draw so sweeping an
    - 10 -
    inference from a court's rendering of a decision on the merits
    where the question of subject matter jurisdiction was not squarely
    before or even addressed by the court.               The Second Circuit in
    Islander East evidenced no awareness that it might be reviewing an
    incomplete state agency action, as opposed to a completed state
    agency action for which state court review was not yet exhausted.
    See Islander East, 
    482 F.3d at
    88 n.7.            We therefore find little
    if any persuasive force in Tennessee Gas's reliance on that
    decision.
    Tennessee     Gas   also    appears    to    argue    that   reading
    § 717r(d)(1) to permit judicial review of only a state agency's
    "final action" would be tantamount to imposing an exhaustion of
    administrative remedies requirement where one is not provided by
    the statute.      In that vein, the company urges us to adopt the
    reasoning    of   other    courts      that   have      found    exhaustion   of
    administrative remedies unnecessary to trigger the exclusive and
    original jurisdiction of a United States Circuit Court of Appeals
    under § 717r(d)(1).        See, e.g., AES Sparrows Point LNG, LLC v.
    Wilson, 
    589 F.3d 721
    , 727 (4th Cir. 2009); Islander East, 
    482 F.3d at
    88 n.7; Del. Riverkeeper, 921 F. Supp. 2d at 391–92.
    We disagree with Tennessee Gas's premise.              Finding that
    a statute requires final agency action is different from finding
    that   it   requires    exhaustion.       "[T]he     judicial      doctrine   of
    exhaustion of administrative remedies is conceptually distinct
    - 11 -
    from the doctrine of finality":           whereas exhaustion "refers to
    administrative and judicial procedures by which an injured party
    may seek review of an adverse decision and obtain a remedy if the
    decision is found to be unlawful or otherwise inappropriate,"
    finality "is concerned with whether the initial decisionmaker has
    arrived at a definitive position on the issue that inflicts an
    actual, concrete injury."       Darby v. Cisneros, 
    509 U.S. 137
    , 144
    (1993) (second and third quotations quoting Williamson Cty. Reg'l
    Planning Comm'n v. Hamilton Bank of Johnson City, 
    473 U.S. 172
    ,
    193 (1985)).    Each of the courts Tennessee Gas asks us to join was
    tasked with determining whether § 717r(d)(1) barred either a
    second, separate state agency or a state court from reviewing a
    state agency's final decision granting, conditioning, or denying
    a water quality certification.       We, by contrast, are faced with
    the question whether a single agency must render a final decision
    before   a    United   States   Circuit    Court   of   Appeals   may   take
    jurisdiction to analyze whether the decision was sound.
    We therefore conclude that there is ample reason to stick
    to the strong presumption restricting our review to final agency
    action of a type that is customarily subject to judicial review.
    B.
    The foregoing brings us to Tennessee Gas's alternative,
    and principal, argument:        that the June 29, 2016, letter from
    MassDEP constituted final agency action granting its application,
    - 12 -
    albeit with conditions. Under this view, the continuing proceeding
    at MassDEP is in the nature of the type of appellate review that
    falls within the exclusive province of this court.
    An agency action is "final" only where it "represents
    the    culmination     of   the    agency's    decisionmaking        process   and
    conclusively determines the rights and obligations of the parties
    with respect to the matters at issue."                Rhode Island v. EPA, 
    378 F.3d 19
    , 23 (1st Cir. 2004); cf. Bennett v. Spear, 
    520 U.S. 154
    ,
    177–78 (1997) (holding that "final agency action" under the APA,
    
    5 U.S.C. § 704
    , must be "the 'consummation' of the agency's
    decisionmaking process," "must not be of a merely tentative or
    interlocutory nature," and "must be one by which 'rights or
    obligations     have    been       determined,'       or     from   which   'legal
    consequences will flow'" (first quoting Chi. & S. Air Lines, Inc.
    v. Waterman S.S. Corp., 
    333 U.S. 103
    , 113 (1948); and then quoting
    Port    of   Bos.    Marine       Terminal    Ass'n     v.    Rederiaktiebolaget
    Transatlantic, 
    400 U.S. 62
    , 71 (1970))).
    In form, there is something to Tennessee Gas's argument
    that the June 29 letter constituted final agency action.                       The
    MassDEP officials did issue a formal document that states "the
    Department grants a Water Quality Certification . . . subject to
    the following conditions . . . necessary to maintain water quality,
    to minimize impact . . . and to ensure compliance with appropriate
    state law."    The regulations (and the certification itself) refer
    - 13 -
    to the adjudicatory hearing following an application for water
    quality certification as an "appeal."           See, e.g., 310 Mass. Code
    Regs. § 1.01(1)(c) ("Adjudicatory Appeal or Appeal means the
    portion of an adjudicatory proceeding initiated by filing a notice
    of claim with the Department and concluded by a final decision.");
    314 Mass. Code Regs. § 9.09(1)(e) (referring to "the appeal period"
    and final decisions following "an appeal"); id. § 9.10 (describing,
    in a provision entitled "Appeals," the process of filing a notice
    of claim and engaging in an adjudicatory hearing).                Where no
    adjudicatory hearing is sought and the certification is not further
    challenged in court, a water quality certification has the force
    and effect of law.    See id. § 9.11 ("Failure to comply with . . .
    a 401 Water Quality Certification . . . shall be enforced [under
    regulatory    provisions    concerning    administrative    penalties].").
    And the regulations neither refer to water quality certifications
    as   "preliminary"   or    "proposed"    nor   require   certifications   or
    denials to include those words.
    The substance of the Massachusetts regulatory regime,
    however, shows the contrary:       an initial letter granting a water
    quality certification subject to Condition 15, either before the
    twenty-one day window to request a hearing has lapsed or after a
    timely notice of claim is filed, is not a final agency action.
    Three aspects of the water quality certification that MassDEP
    - 14 -
    issued in this case and the regulatory regime that gave rise to it
    lead us to this conclusion.
    First, Massachusetts law makes clear that Tennessee
    Gas's application seeking a determination of its rights in the
    form of a water quality certification initiated a single, unitary
    proceeding, an essential part of which is the opportunity (of which
    petitioners    have   availed   themselves)    to   have    an   adjudicatory
    hearing.    Under Massachusetts law, "a proceeding before an agency
    in which the legal rights, duties or privileges of specifically
    named persons are required by constitutional right or by any
    provision of the General Laws to be determined after opportunity
    for an agency hearing" is an "[a]djudicatory proceeding."               Mass.
    Gen. Laws ch. 30A, § 1(1).      MassDEP regulations, in turn, provide
    that   an    adjudicatory   proceeding     "means    a     proceeding   under
    [chapter 0A] that may culminate in an adjudicatory hearing and the
    Commissioner's issuance of a final decision." 310 Mass. Code Regs.
    § 1.01(c).    Those same regulations also define such a hearing as
    one in which "parties may present evidence on issues of fact, and
    argument on issues of law and fact prior to the Commissioner's
    issuance of a final decision."       Id.      No party disputes that, in
    the present context, such a presentation of evidence and arguments
    occurs after the issuance of a conditional certification, not
    before.
    - 15 -
    Second, the review to be provided in the adjudicatory
    hearing is a review of Tennessee Gas's application, rather than a
    review of a prior agency decision.         MassDEP accords no deference
    to the preliminary findings included in the certification, see
    Conservation Comm'n of Falmouth v. Pacheco, 
    733 N.E.2d 127
    , 130
    (Mass. App. Ct. 2000), and the regulations expressly provide that
    the agency may even consider "new substantive issues arising from
    material changes to the scope or impact of the activity and not
    apparent at the time of public notice" from persons who did not
    participate in the notice-and-comment process, 314 Mass. Code
    Regs. § 9.10(1).   When a notice of claim is timely filed following
    the issuance of a water quality certification, the agency's review
    of the proposed project continues more or less as though no
    decision has been rendered at all.
    Third, the manner in which Massachusetts has chosen to
    structure its internal agency decision-making strikes us as hardly
    unusual or contrived.    It allows for unopposed actions to proceed
    to finality without the time and expense of full-blown adjudicatory
    proceedings,   while    preserving   the    parties'   rights   to   such
    proceedings when sought.    With the taking of evidence and de novo
    consideration, it bears the hallmarks of decision-making by expert
    administrative agencies rather than those of judicial review.        Its
    chief drawback, as demonstrated here, is its duration.          Congress,
    though, has addressed the matter of delay directly, see 15 U.S.C.
    - 16 -
    § 717r(d)(2); 
    33 U.S.C. § 1341
    (a)(1),1 and by divesting states of
    their customary review of state agency orders and opinions in this
    field, see 15 U.S.C. § 717r(d)(1).                We see no indication that
    Congress otherwise intended to dictate how (as opposed to how
    quickly) MassDEP conducts its internal decision-making before
    finally acting.        See 
    33 U.S.C. § 1251
    (b) ("It is the policy of the
    Congress       to    recognize,     preserve,     and       protect   the   primary
    responsibilities and rights of States to prevent, reduce, and
    eliminate      pollution,     [and]   to   plan       the   development     and   use
    (including restoration, preservation, and enhancement) of land and
    water resources . . . ."); United States v. Cooper, 
    482 F.3d 658
    ,
    667 (4th Cir. 2007) ("In the CWA, Congress expressed its respect
    for states' role through a scheme of cooperative federalism that
    enables states to 'implement . . . permit programs' like [the one
    at issue here.]"); S. Ohio Coal Co. v. Office of Surface Mining,
    Reclamation & Enf't, Dep't of Interior, 
    20 F.3d 1418
    , 1427 (6th
    Cir.       1994)    ("[T]he   CWA   sets   up     a    system    of   'cooperative
    1
    Our consideration of the jurisdictional issue posed by this
    case leaves us with no occasion to consider whether, because
    MassDEP did not finally act on Tennessee Gas's application within
    one year, the requirement that Tennessee Gas obtain a water quality
    certification from the Commonwealth of Massachusetts has been
    waived. See 
    33 U.S.C. § 1341
    (a)(1). Nor have we considered the
    potential relevance of 15 U.S.C. § 717r(d)(2) (granting the D.C.
    Circuit "original and exclusive jurisdiction over any civil action
    for the review" of a state agency's "alleged failure to act . . .
    to issue, condition, or deny any permit required under Federal
    law" for a facility subject to NGA § 717f).
    - 17 -
    federalism,' in which states may choose to be primarily responsible
    for   running    federally-approved          programs.");     cf.     Dominion
    Transmission, Inc. v. Summers, 
    723 F.3d 238
    , 240 (D.C. Cir. 2013)
    (noting   that   the   NGA    "expressly      does   not   preempt"   certain
    environmental    protection    laws    like    the   Clean   Air    Act   that
    contemplate a robust role for states).
    III.   Conclusion
    There is, as yet, no order or action of MassDEP in
    connection with Tennessee Gas's application for a water quality
    certification that we may review under 15 U.S.C. § 717r(d)(1).             We
    therefore dismiss the petition for review for lack of subject
    matter jurisdiction.    Each party shall bear its own costs.
    - 18 -