City Electric Supply Co. v. Arch Insurance Co. , 481 Mass. 784 ( 2019 )


Menu:
  • NOTICE: All slip opinions and orders are subject to formal
    revision and are superseded by the advance sheets and bound
    volumes of the Official Reports. If you find a typographical
    error or other formal error, please notify the Reporter of
    Decisions, Supreme Judicial Court, John Adams Courthouse, 1
    Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
    1030; SJCReporter@sjc.state.ma.us
    SJC-12561
    CITY ELECTRIC SUPPLY COMPANY1   vs.   ARCH INSURANCE COMPANY.
    Norfolk.      November 8, 2018. - March 29, 2019.
    Present:   Gants, C.J., Gaziano, Lowy, Budd, Cypher, & Kafker,
    JJ.
    Mechanic's Lien. Bond.    Practice, Civil, Enforcement of
    liability on bond.   Statute, Construction.
    Civil action commenced in the Superior Court Department on
    August 17, 2016.
    The case was heard by Beverly J. Cannone, J., on a motion
    for summary judgment.
    The Supreme Judicial Court granted an application for
    direct appellate review.
    Thomas E. Day for the plaintiff.
    John W. DiNicola, II, for the defendant.
    GAZIANO, J.     In this case, we consider whether a claimant
    seeking to enforce a target lien bond by commencing a civil
    action pursuant to the mechanic's lien statute, G. L. c. 254,
    1   Doing business as Concord Electric Supply, Ltd.
    2
    § 14, must record an attested copy of the complaint in the
    registry of deeds.     We conclude that the lien statute contains
    no such requirement.     A party seeking to enforce a target lien
    bond, a bond which has the effect of dissolving a mechanic's
    lien that has been placed on a property, need not record a copy
    of a complaint in the registry of deeds as a condition precedent
    to enforcing the bond.
    1.   Background.    The essential facts are undisputed.   City
    Electric Supply Company, doing business as Concord Electric
    Supply, Ltd. (CES), supplied electrical materials for a
    construction project in Brookline to subcontractor Michael
    Franciosi, doing business as Electrical Professionals
    (Franciosi).   In June 2016, CES perfected a mechanic's lien on
    the Brookline property by recording a notice of contract in the
    Norfolk County registry of deeds pursuant to G. L. c. 254, § 4;
    the notice indicated that Franciosi owed CES $283,056.54.
    Months later, Franciosi filed a suggestion of bankruptcy in the
    Superior Court.
    On July 14, 2016, general contractor Tocci Building
    Corporation (Tocci) issued and recorded a "target lien bond,"2
    2 Both parties refer to a bond issued pursuant to G. L.
    c. 254, § 14, as a "target lien bond." The term "target lien
    bond" is not used in the language of G. L. c. 254, § 14.
    Nonetheless, as CES explains, a lien dissolution bond filed
    pursuant to G. L. c. 254, § 14, is "commonly referred to as a
    'target bond.'" We also previously have referred to a bond
    3
    pursuant to G. L. c. 254, § 14, in the amount of $283,056.54,
    the amount of the mechanic's lien that CES had created.     The
    target lien bond listed the defendant, Arch Insurance Company
    (Arch), as surety, and was recorded in the Norfolk County
    registry of deeds.
    In August, 2016, CES sought to enforce the target lien bond
    by filing a timely action against Franciosi and Arch in the
    Superior Court, pursuant to G. L. c. 254, § 14.    CES properly
    served Franciosi and Arch.     CES did not record a copy of its
    complaint in the registry of deeds within thirty days of
    commencement of the action.3
    In March, 2017, Arch moved for summary judgment pursuant to
    Mass. R. Civ. P. 56, 
    365 Mass. 824
     (1974); it argued that CES
    had failed to comply with G. L. c. 254.    Specifically, Arch
    alleged that CES had not recorded in the registry of deeds an
    attested copy of its complaint to enforce the target lien bond
    within thirty days of filing the complaint, as would have been
    required in a lien enforcement action under G. L. c. 254, § 5.
    CES opposed the motion "on the grounds that suit on a lien bond
    issued pursuant to G. L. c. 254, § 14, as a "lien dissolution
    bond." See NES Rentals v. Maine Drilling & Blasting, Inc., 
    465 Mass. 856
    , 860 (2013).
    3 In January, 2017, CES ultimately recorded a copy of the
    complaint in the Norfolk County registry of deeds, after counsel
    for Arch contacted CES.
    4
    under [G. L. c. 254, § 14,] does not require an attested copy of
    the complaint to be recorded and Arch's interpretation of the
    lien bond requirement is erroneous."
    Following a hearing, a Superior Court judge allowed Arch's
    motion for summary judgment.    The judge reasoned that G. L.
    c. 254, § 14, must be read in conjunction with "the detailed and
    precise requirements of [§] 5, which dictate the procedures for
    a lien enforcement action."    As G. L. c. 254, § 5, requires that
    an attested copy of a complaint be recorded, the judge
    "reject[ed] [CES's] claim that because G. L. c. 254, § 14, is
    silent with respect to filing an attested copy of the complaint,
    it was excused from doing so within the thirty days of the
    commencement of the action as required by G. L. c. 254, § 5."
    CES filed a timely appeal.     We allowed CES's petition for direct
    appellate review.
    2.   Statutory scheme.     General Laws c. 254 "governs the
    creation, perfection, and dissolution of a mechanic's lien."
    National Lumber Co. v. United Cas. & Sur. Ins. Co., 
    440 Mass. 723
    , 726 (2004) (National Lumber II).    Because a perfected lien
    encumbers the property upon which it is placed, one purpose of
    G. L. c. 254 is "to ensure that a person searching the land
    records in a registry of deeds can determine with certainty
    whether or not title to a particular parcel of land is
    encumbered by a mechanic's lien."    National Lumber Co. v.
    5
    LeFrancois Constr. Corp., 
    430 Mass. 663
    , 668 (2000) (National
    Lumber I).   Another important "purpose of G. L. c. 254 is 'to
    provide security to contractors, subcontractors, laborers, and
    suppliers for the value of their services and goods provided for
    improving the owner's real estate.'"     Id., quoting Hammill-
    McCormick Assocs., Inc. v. New England Tel. & Tel. Co., 
    399 Mass. 541
    , 542-543 (1987).    "Because a mechanic's lien is purely
    a creation of statute, we have consistently required exact
    compliance with the statute in order to create, perfect, and
    enforce such a lien."    Golden v. General Bldrs. Supply LLC, 
    441 Mass. 652
    , 654 (2004).     At the same time, we have recognized
    that the mechanic's lien "statute is . . . intended to protect
    those who lawfully enhance the value of land by the expenditure
    upon it of material or labor."    Shaughnessy v. Isenberg, 
    213 Mass. 159
    , 161 (1912).
    General Laws. c. 254 also "provides for prevention of
    future liens and dissolution of existing liens by the giving of
    a [lien] bond, which benefits . . . anyone possessing an
    interest in that land . . . by furnishing means to keep his
    title free from liens and preventing the sale of the land to
    satisfy a lien" (quotation omitted).     NES Rentals v. Maine
    Drilling & Blasting, Inc., 
    465 Mass. 856
    , 860 (2013), citing
    G. L. c. 254, §§ 12, 14.     To do so, the statute establishes two
    distinct types of lien bonds:    "blanket" lien bonds that are
    6
    issued pursuant to G. L. c. 254, § 12, and "target" lien bonds
    that are issued under G. L. c. 254, § 14.     The filing of a
    blanket lien bond prevents a lien from attaching to a property.
    See G. L. c. 254, § 12.   See also J.W. DiNicola II & E.L. Hall,
    The Massachusetts Mechanic's Lien Law § 5.8.1, in Massachusetts
    Construction Law and Litigation (2d ed. 2018) ("Once filed, the
    [blanket lien] bond, by its terms, acts as a substitute for the
    real property.   The liens of subcontractors and vendors attach
    to the bond as an alternate form of security for the property").
    A target lien bond dissolves a lien that already has attached to
    a property.   See G. L. c. 254, § 14.
    A mechanic's lien is created when a notice of contract is
    filed in the registry of deeds.     See G. L. c. 254, § 4; Tremont
    Tower Condominium, LLC v. George B.H. Macomber Co., 
    436 Mass. 677
    , 683 (2002) ("filing of the notice of contract is . . . the
    step that creates the lien in the first instance").    When a
    target lien bond is issued and recorded pursuant to G. L.
    c. 254, § 14, in a penal sum equal to a mechanic's lien that has
    been placed on a property, the mechanic's lien is dissolved and
    no longer encumbers the property.    See National Lumber II, 440
    Mass. at 729 ("the lien was dissolved when the [party] recorded
    [a company's] surety bond" in accordance with G. L. c. 254,
    § 14).   See also G. L. c. 254, § 14.    After a target lien bond
    is recorded pursuant to the terms and procedural requirements of
    7
    G. L. c. 254, § 14, a claimant becomes newly able to "recover on
    [its] claim for . . . labor and materials" by enforcing the
    target lien bond itself, as distinct from the then-dissolved
    mechanic's lien.    See G. L. c. 254, § 14.
    At the same time, statutory dissolution of a lien under
    G. L. c. 254, § 14, does not dissolve a claimant's ability to
    recover costs incurred "for labor or labor and materials that
    served as the basis of the lien."     NES Rentals, 465 Mass. at 865
    n.13.   A claimant seeking to enforce a target lien bond under
    G. L. c. 254, § 14, may recover, through a civil enforcement
    action, "to the extent that the claimant would have been able to
    recover" under the lien.    See NES Rentals, supra; G. L. c. 254,
    § 14.     In this way, G. L. c. 254, § 14, limits a claimant's
    ability to recover on a target lien bond to the amount of the
    claim that once formed the basis of the dissolved lien.        As a
    result, "[a] lien dissolution bond is inextricably connected to
    the underlying lien."     NES Rentals, supra.
    3.    Discussion.   As stated, this case concerns CES's
    efforts to enforce a target lien bond.     As it did in the
    Superior Court, CES argues that it was not required, pursuant to
    G. L. c. 254, § 14, to record a copy of the complaint in the
    registry of deeds within thirty days of commencing an action to
    enforce the bond.    Accordingly, CES argues that the allowance of
    Arch's motion for summary judgment was error.    We agree.
    8
    a.    Standard of review.    We review the allowance of a
    motion for summary judgment de novo.     See Miller v. Cotter, 
    448 Mass. 671
    , 676 (2007).    "Summary judgment is appropriate where
    there are no genuine issues of material fact and the moving
    party is entitled to judgment as a matter of law."     Twomey v.
    Middleborough, 
    468 Mass. 260
    , 267 (2014), citing Kourouvacilis
    v. General Motors Corp., 
    410 Mass. 706
    , 716 (1991); Mass. R.
    Civ. P. 56 (c), as amended, 
    436 Mass. 1404
     (2002).
    b.    Statutory interpretation.    "The starting point of our
    analysis is the language of the statute, 'the principal source
    of insight into Legislative purpose.'"     Simon v. State Examiners
    of Electricians, 
    395 Mass. 238
    , 242 (1985), quoting Commonwealth
    v. Lightfoot, 
    391 Mass. 718
    , 720 (1984).     "Where the language
    [of a statute] is plain and unambiguous, it is conclusive of the
    Legislature's purpose."    National Lumber II, 440 Mass. at 727,
    citing Pyle v. School Comm. of S. Hadley, 
    423 Mass. 283
    , 285
    (1996).
    i.    Statutory language.    The plain language of G. L.
    c. 254, § 14 -- the statutory provision pursuant to which CES
    commenced its civil action -- contains no requirement that a
    claimant must record an attested copy of a complaint in order to
    enforce a target lien bond.     This is in contrast to G. L.
    c. 254, § 12, which explicitly requires a party seeking to
    enforce a blanket lien bond to record a copy of the complaint in
    9
    the registry of deeds.   See G. L. c. 254, § 12 ("An attested
    copy of the complaint shall be filed and recorded in the
    registry of deeds").   General Laws c. 254, § 14, instead,
    provides simply that "[a]ny person in interest may dissolve a
    lien under this chapter by recording . . . a bond of a surety
    company . . . in a penal sum equal to the amount of the lien
    sought to be dissolved; and that "[u]pon the recording of the
    bond, the lien shall be dissolved."   "Notice of the recording
    shall be given to the claimant by serving on the claimant a copy
    of the notice of recording together with a copy of the bond by
    an officer qualified to serve civil process or by delivering
    same to the claimant."   Id.   A claimant must commence a civil
    action to recover on a target lien bond "within ninety days
    after the later of the filing of the statement required by [§] 8
    or receipt of notice of recording of the bond."    Id.
    When interpreting the absence of language in an otherwise
    "detailed and precise [statute], we regard [an] omission as
    purposeful."   Leary v. Contributory Retirement Appeal Bd., 
    421 Mass. 344
    , 348 (1995).   General Laws c. 254 is detailed and
    precise; it sets forth a "comprehensive scheme" to govern
    mechanic's liens and lien bonds (citation omitted).      See Ng
    Bros. Constr., Inc. v. Cranney, 
    436 Mass. 638
    , 642 (2002)
    ("Individual sections of the statute delineate time requirements
    for creating, maintaining, and enforcing a lien").       General Laws
    10
    c. 254, § 14, itself establishes various procedural requirements
    for acquiring, recording, and enforcing a target lien bond.        See
    id.   "We do not read into the statute a provision which the
    Legislature did not see fit to put there, whether the omission
    came from inadvertence or of set purpose."     National Lumber II,
    440 Mass. at 727, quoting General Elec. Co. v. Department of
    Envtl. Protection, 
    429 Mass. 798
    , 803 (1999).    Indeed, we have
    long recognized that "statutes must be interpreted as enacted
    and statutory omissions cannot be supplied by the court."
    Modern Cont. Constr. Co. v. Lowell, 
    391 Mass. 829
    , 839–840
    (1984).   "Where language in certain provisions is noticeably
    absent from other provisions of the same statute, such as here,
    we have consistently held that the language should not be
    implied where it is not present."     National Lumber II, 440 Mass.
    at 728, quoting Hallet v. Contributory Retirement Appeal Bd.,
    
    431 Mass. 66
    , 69 (2000).
    By contrast, with regard to blanket lien bonds, G. L.
    c. 254, § 12, expressly requires that a complaint be recorded in
    the registry of deeds.     As discussed, a blanket lien bond issued
    pursuant to G. L. c. 254, § 12, does not dissolve a lien but,
    rather, prevents future liens from attaching to a property.
    Because a blanket lien bond is issued before the conclusion of a
    construction project, it may comprise only a "person's fair
    estimate of the contract sum."    See G. L. c. 254, § 12.   As a
    11
    result, subcontractors and suppliers conceivably might record
    notices of contract on a project in amounts greater than the
    amount of a blanket lien bond, such that the blanket lien bond
    may prove insufficient to protect the property from becoming
    subject to a lien.   Because a lien burdens the title of a
    property, potential purchasers and others retain an interest in
    knowing about suits to enforce blanket lien bonds that may fail
    to prevent liens from attaching to the property.
    Arch argues that, in light of this court's obligation to
    read G. L. c. 254, § 14, alongside G. L. c. 254, § 5, which
    requires recording of a complaint in the context of a lien
    enforcement action, a claimant must record a complaint in order
    to enforce a target lien bond.   As stated, G. L. c. 254, § 5,
    obliges a claimant seeking to enforce a lien to record an
    attested copy of its complaint "within thirty days of the
    commencement of the action, or such lien shall be dissolved."
    Thus, pursuant to G. L. c. 254, § 5, the recording of a
    complaint is one of several steps necessary to perfect a lien.
    See National Lumber I, 430 Mass. at 668.   Arch maintains that
    because G. L. c. 254, § 14, provides that the recording of a
    target lien bond does "not create any rights which the claimant
    would not have had, or impair any defense which the obligors
    would have had, in an action to enforce a lien," the recording
    requirement of G. L. c. 254, § 5, is transmuted into a
    12
    requirement that a claimant record its complaint in order to
    enforce a target lien bond issued under G. L. c. 254, § 14.      We
    do not agree.
    To be sure, "[w]hen the meaning of a statute is brought
    into question, a court properly should read other sections and
    should construe them together" (citation omitted).    LeClair v.
    Norwell, 
    430 Mass. 328
    , 333 (1999).   As Arch correctly notes, we
    previously have indicated that, as with the provisions of any
    statute, G. L. c. 254, § 14, should be read together with other
    provisions of the lien statute.    See, e.g., NES Rentals, 465
    Mass. at 868 (referring to procedural requirements of G. L.
    c. 254, § 5, in construing G. L. c. 254, § 14).    At the same
    time, however, "[w]e do not 'interpret a statute so as to render
    it or any portion of it meaningless.'"    Volin v. Board of Pub.
    Accountancy, 
    422 Mass. 175
    , 179 (1996), quoting Adamowicz v.
    Ipswich, 
    395 Mass. 757
    , 760 (1985).
    General Laws c. 254, § 5, provides that dissolution of a
    lien is a consequence of a plaintiff's failure to record a
    complaint to enforce the lien.    In an action to enforce a target
    lien bond, however, the underlying lien already has been
    dissolved.   Therefore, to ascribe to Arch's interpretation would
    be to render the phrase "or such lien shall be dissolved," G. L.
    c. 254, § 5, unnecessary surplusage in the context of a target
    13
    lien bond enforcement action.4    "[T]he canon against surplusage
    is strongest when an interpretation would render superfluous
    another part of the same statutory scheme."    Marx v. General
    Revenue Corp., 
    568 U.S. 371
    , 386 (2013).
    ii.   Legislative history.   A review of the legislative
    history of G. L. c. 254 also supports our reading of the
    statute.   "A fundamental principle of statutory interpretation
    is that a statute must be interpreted according to the intent of
    the Legislature ascertained from all its words construed by the
    ordinary and approved usage of the language, considered in
    connection with the cause of its enactment, the mischief or
    imperfection to be remedied and the main object to be
    accomplished, to the end that the purpose of its framers may be
    effectuated" (quotation and citation omitted).    Harvard Crimson,
    Inc. v. President & Fellows of Harvard College, 
    445 Mass. 745
    ,
    749 (2006).
    The Legislature previously has considered and rejected
    language suggesting that G. L. c. 254, § 14, should be
    considered subject to all of the procedural requirements of
    4 We address today the narrow issue whether G. L. c. 254,
    § 14, requires that a claimant seeking to enforce a lien bond
    must record a copy of an attested complaint in the registry of
    deeds. We do not conclude that a lien bond "replace[s] the Lien
    Law in its entirety," as Arch suggests would be the result of a
    ruling against it, and, indeed, draw no conclusions with respect
    to any other procedural rights or defenses under G. L. c. 254,
    § 14.
    14
    G. L. c. 254, § 5.   In 1973, the Legislature amended G. L.
    c. 254, § 14, as part of an effort to bring the General Laws
    into conformity with the then newly adopted rules of civil
    procedure and rules of appellate procedure.   The year before,
    the Legislature had revised G. L. c. 254, § 14, to provide for a
    new cause of action to enforce target lien bonds, beyond the
    context of a suit under G. L. c. 254, § 5.    See St. 1972,
    c. 774, § 10.   Notwithstanding this then-recent adoption of the
    new cause of action, a 1973 Senate bill proposed the following
    language to bring G. L. c. 254, § 14, into conformity with the
    rules of civil procedure,
    "Section 14 of said chapter 254, as appearing in the
    Tercentenary Edition, is hereby amended by striking out the
    first sentence and inserting in place thereof the following
    sentence: In a civil action under section five, the court
    may, in its discretion, accept a bond, with sufficient
    surety or sureties, to dissolve the lien of any creditor or
    all liens, as to the whole or any part of the property, or
    any interest therein."
    1973 Senate Doc. No. 11, at 190.   The proposed language
    referenced an outdated version of the mechanic's lien statute,
    and was dropped from the final act as adopted, thereby rejecting
    any reference to G. L. c. 254, § 5.   See St. 1973, c. 1114,
    § 320 ("The last sentence of section 14 of said chapter 254, as
    appearing in section 10 of chapter 774 of the acts of 1972, is
    hereby amended by striking out the words 'petition in equity
    filed' and inserting in place thereof the words:   -- civil
    15
    action commenced").    "Where the Legislature has deleted . . .
    language, apparently purposefully, the current version of the
    statute cannot be interpreted to include the rejected
    requirement.    Reading in language that the Legislature chose to
    remove . . . violates basic principles of statutory construction
    and impermissibly interferes with the legislative function."
    Aids Support Group of Cape Cod, Inc. v. Barnstable, 
    477 Mass. 296
    , 303 (2017), quoting Commonwealth v. Porges, 
    460 Mass. 525
    ,
    530 (2011).
    Arch's reliance on Valentine Lumber & Supply Co. v.
    Thibeault, 
    336 Mass. 411
     (1957) (Valentine Lumber), in support
    of its argument that recording of the complaint was required is
    misplaced.5    In Valentine Lumber, supra at 412-413, this court
    concluded that a claimant's failure to record a complaint
    (called a "subpoena") to enforce a target lien bond precluded
    the claimant from recovering under the mechanic's lien statute.
    Under the statutory scheme in existence when Valentine Lumber
    5 We recognize, as Arch argues, that many entities,
    including the general contractor and other subcontractors, may
    have an interest in knowledge of a target lien bond enforcement
    action; as they are not interested parties to the lawsuit, they
    will not receive notice through timely service of process. For
    example, here CES provided Franciosi and Arch -- the two named
    parties in its enforcement action -- with notice of its claim on
    the target lien bond. Tocci, the general contractor, however,
    who was not a party to the action, did not receive such notice,
    and under the terms of the statute, CES was not obligated to
    provide it. Any resolution of this issue, however, is for the
    Legislature.
    16
    was decided, G. L. c. 254, § 5, expressly mandated that, where a
    plaintiff sought to enforce a target lien bond, a copy of the
    complaint (subpoena) had to be recorded.   See Valentine Lumber,
    supra at 413 ("the failure to record the subpoena was an
    omission to do something required in mandatory language by the
    statute, and there is nothing in the statute which excuses
    compliance with its provisions"); St. 1915, c. 292, §§ 4, 9.     As
    discussed, after this court's decision in Valentine Lumber,
    supra, the Legislature created within G. L. c. 254, § 14, an
    independent action to enforce target lien bonds in which it
    included no express recording requirement.   See St. 1972 c. 774,
    § 10.
    Under the terms of the mechanic's lien statute in effect
    since 1972, "[o]nce a bond is recorded in accordance with § 14,
    the lien is dissolved on the record, and any concern about
    uncertainty of title arising from that lien is eliminated."     NES
    Rentals, 465 Mass. at 869.   Thus, recording a complaint to
    enforce a target lien bond would not support the goal of
    "ensur[ing] that a person searching the land records in a
    registry of deeds can determine with certainty whether or not
    title to a particular parcel of land is encumbered by a
    mechanic's lien."6   National Lumber I, 430 Mass. at 668.
    6 Arch argues that "it is standard practice in the industry
    for lien claimants to record attested copies of complaints
    17
    4.   Conclusion.   The order allowing summary judgment is
    vacated and set aside, and the matter is remanded to the
    Superior Court for further proceedings.
    So ordered.
    against target lien bond sureties." We do not read G. L.
    c. 254, § 14, to preclude interested entities from filing
    attested copies of complaints to enforce target lien bonds in
    the registry of deeds; we merely interpret the statutory text
    not to mandate such recording. While industry "practice may be
    helpful in discerning the Legislature's intent," Tremont Tower
    Condominium, LLC, 436 Mass. at 688, "[a]n industry practice,
    standing alone, does not necessarily dictate our construction of
    a statute." Id. at 687-688.