New Riegel Local School Dist. Bd. of Edn. v. Buehrer Group Architecture & Eng., Inc. (Slip Opinion) , 2019 Ohio 2851 ( 2019 )


Menu:
  • [Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as New
    Riegel Local School Dist. Bd. of Edn. v. Buehrer Group Architecture & Eng., Inc., Slip Opinion
    No. 2019-Ohio-2851.]
    NOTICE
    This slip opinion is subject to formal revision before it is published in an
    advance sheet of the Ohio Official Reports. Readers are requested to
    promptly notify the Reporter of Decisions, Supreme Court of Ohio, 65
    South Front Street, Columbus, Ohio 43215, of any typographical or other
    formal errors in the opinion, in order that corrections may be made before
    the opinion is published.
    SLIP OPINION NO. 2019-OHIO-2851
    NEW RIEGEL LOCAL SCHOOL DISTRICT BOARD OF EDUCATION, APPELLEE, v.
    BUEHRER GROUP ARCHITECTURE & ENGINEERING, INC., ET AL., APPELLANTS.
    [Until this opinion appears in the Ohio Official Reports advance sheets, it
    may be cited as New Riegel Local School Dist. Bd. of Edn. v. Buehrer Group
    Architecture & Eng., Inc., Slip Opinion No. 2019-Ohio-2851.]
    Contracts—Construction statute of repose, R.C. 2305.131—Court of appeals erred
    in reversing trial court’s dismissal of school district’s breach-of-contract
    claims as time-barred and in applying stare decisis to hold that current
    version of R.C. 2305.131 applies only to tort claims—Construction statute
    of repose is not limited to tort actions but also applies to contract actions
    that meet requirements of R.C. 2305.131—Court of appeals’ judgments
    reversed and causes remanded.
    (Nos. 2018-0189 and 2018-0213—Submitted March 5, 2019—Decided July 17,
    2019.)
    APPEALS from the Court of Appeals for Seneca County, No. 13-17-04, 2017-
    Ohio-8522, and Nos. 13-17-03 and 13-17-06, 2017-Ohio-8521.
    SUPREME COURT OF OHIO
    _____________________
    FRENCH, J.
    {¶ 1} These consolidated appeals ask whether Ohio’s construction statute
    of repose, R.C. 2305.131, applies to actions sounding in contract as well as to
    actions sounding in tort. We hold that R.C. 2305.131, as enacted in Am.Sub.S.B.
    No. 80, 150 Ohio Laws, Part V, 7915, 7937-7938, applies to any cause of action,
    whether sounding in tort or contract, so long as the cause of action meets the
    requirements of the statute.
    Facts and Procedural Background
    {¶ 2} These appeals arise from the design and construction of a public-
    school building (the “Project”) for the New Riegel Local School District. The
    Project, which was substantially completed and approved for occupancy in
    December 2002, was built as part of the Ohio Classroom Facilities Assistance
    Program, administered by the Ohio School Facilities Commission. Appellee, the
    New Riegel Local School District Board of Education (“New Riegel”), alleges that
    condensation, moisture intrusion, and other deficiencies exist in various areas of
    the Project, as a result of improper design and construction.
    {¶ 3} The Buehrer Group Architecture & Engineering contracted with New
    Riegel to provide design services for the Project; New Riegel alleges that the
    subsequently incorporated Buehrer Group Architecture & Engineering, Inc.
    (collectively, with the unincorporated entity, “the Buehrer Group”), adopted,
    benefited from, and provided services for New Riegel on the contract. Studer-
    Obringer, Inc., and Charles Construction Services, Inc., served as the general-trades
    contractor and the roofing contractor, respectively, on the Project, pursuant to
    contracts with the state; New Riegel was an intended beneficiary of those contracts.
    In January 2015, New Riegel served the Buehrer Group, Studer-Obringer, and
    Charles Construction with notices of claims regarding alleged defects in the school
    building. The Buehrer Group, Charles Construction, Studer-Obringer, and Ohio
    2
    January Term, 2019
    Farmers Insurance Company—the surety for Studer-Obringer and Charles
    Construction—are appellants here.
    {¶ 4} New Riegel filed this action in April 2015.1 New Riegel’s second
    amended complaint asserts claims against the Buehrer Group, the Estate of Huber
    H. Buehrer, Studer-Obringer, Charles Construction, American Buildings Company
    d.b.a. Architectural Metal Systems, and Ohio Farmers. As relevant here, New
    Riegel alleges claims for breach of contract against the Buehrer Group, Studer-
    Obringer, and Charles Construction; a claim for breach of express warranty against
    Charles Construction; and claims against Ohio Farmers on its surety bonds. It
    alleges that the Buehrer Group, Studer-Obringer, and Charles Construction “failed
    to provide [services or work] in conformance to the terms of” their contracts and
    that Studer-Obringer and Charles Construction failed to conform “with the requisite
    standard of care to perform in a workmanlike manner.” New Riegel alleges that as
    a result, it has incurred damages, including damages for “physical damage to
    property.”
    {¶ 5} In their answers and/or motions for judgment on the pleadings,
    appellants argued that the statute of repose in R.C. 2305.131 barred New Riegel’s
    claims because substantial completion of the Project occurred more than ten years
    before New Riegel filed its claims. The trial court granted appellants’ motions for
    judgment on the pleadings and dismissed as time-barred New Riegel’s breach-of-
    contract claims against the Buehrer Group, Studer-Obringer, and Charles
    Construction. The trial court also dismissed New Riegel’s claim against Ohio
    Farmers as surety for Studer-Obringer. Pursuant to Civ.R. 54(B), the trial court
    certified that there was no just reason for delay and that the judgment entries were
    final, appealable orders.
    1. The original complaint named the Ohio School Facilities Commission as an involuntary plaintiff,
    but New Riegel dropped the Ohio School Facilities Commission as an involuntary plaintiff when it
    filed its first amended complaint.
    3
    SUPREME COURT OF OHIO
    {¶ 6} The Third District Court of Appeals reversed the trial court’s
    judgment in two opinions containing nearly identical language. Although it stated
    that R.C. 2305.131, on its face, appeared to bar New Riegel’s breach-of-contract
    claims, the Third District determined that it was required to follow this court’s
    decision in Kocisko v. Charles Shutrump & Sons Co., 
    21 Ohio St. 3d 98
    , 
    488 N.E.2d 171
    (1986), and to hold that R.C. 2305.131 does not apply to claims for breach of
    contract. 2017-Ohio-8521, ¶ 11; 2017-Ohio-8522, ¶ 8. Having determined that
    R.C. 2305.131 does not apply to breach-of-contract claims, the Third District did
    not address New Riegel’s assignment of error arguing that R.C. 2305.131 does not
    bar its claims against Studer-Obringer and Charles Construction, because the state,
    with which those entities had contracted, is not subject to statutes of repose. 2017-
    Ohio-8521 at ¶ 14.
    {¶ 7} This court accepted and consolidated appellants’ discretionary
    appeals. 
    152 Ohio St. 3d 1478
    , 2018-Ohio-1990, 
    98 N.E.3d 293
    . Although phrased
    differently by different appellants, the accepted propositions of law essentially ask
    this court to hold (1) that R.C. 2305.131’s statute of repose applies to both tort and
    contract actions and (2) that stare decisis should not be applied when, as here, the
    General Assembly has repealed and replaced the statute construed in the precedent.
    Standard of Review
    {¶ 8} The trial court entered judgment on the pleadings for appellants
    pursuant to Civ.R. 12(C). Dismissal is appropriate under Civ.R. 12(C) when a court
    construes as true the material allegations in the complaint, along with all reasonable
    inferences to be drawn therefrom, and finds, beyond doubt, that the plaintiff can
    prove no set of facts that would entitle him to relief. State ex rel. Midwest Pride
    IV, Inc. v. Pontious, 
    75 Ohio St. 3d 565
    , 570, 
    664 N.E.2d 931
    (1996). Appellate
    review of a judgment on the pleadings involves only questions of law and is
    therefore de novo. Rayess v. Educational Comm. for Foreign Med. Graduates, 
    134 Ohio St. 3d 509
    , 2012-Ohio-5676, 
    983 N.E.2d 1267
    , ¶ 18. Similarly, questions of
    4
    January Term, 2019
    statutory construction constitute legal issues that we decide de novo on appeal. New
    York Frozen Foods, Inc. v. Bedford Hts. Income Tax Bd. of Rev., 
    150 Ohio St. 3d 386
    , 2016-Ohio-7582, 
    82 N.E.3d 1105
    , ¶ 8.
    Analysis
    {¶ 9} The overarching issue before this court is the meaning of the current
    version of R.C. 2305.131(A)(1), enacted as part of Am.Sub.S.B. No. 80, 150 Ohio
    Laws, Part V, 7915, and, particularly, whether the current statute applies to actions
    sounding in contract as well as to actions sounding in tort. In making that
    determination, we consider whether we are constrained by the doctrine of stare
    decisis. But before turning to the question of stare decisis, we briefly review the
    history of R.C. 2305.131.
    The evolution of R.C. 2305.131
    {¶ 10} The General Assembly first enacted R.C. 2305.131 in 1963.
    Am.S.B. No. 112, 130 Ohio Laws, Part I, 648. With the enactment of R.C.
    2305.131, Ohio joined the many states that had enacted construction statutes of
    repose in the late 1950s and early 1960s in response to the expansion of the
    common-law liability of architects and builders to third parties with whom they
    lacked privity of contract. Sedar v. Knowlton Constr. Co., 
    49 Ohio St. 3d 193
    , 195,
    
    551 N.E.2d 938
    (1990), overruled on other grounds, Brennaman v. R.M.I. Co., 
    70 Ohio St. 3d 460
    , 
    639 N.E.2d 425
    (1994), citing Hartford Fire Ins. Co. v. Lawrence,
    Dykes, Goodenberger, Bower & Clancy, 
    740 F.2d 1362
    , 1368 (6th Cir.1984);
    
    Kocisko, 21 Ohio St. 3d at 101
    , 
    488 N.E.2d 171
    (Wright, J., dissenting) (“Almost
    every state, including Ohio, enacted this type of statute, recognizing that architects
    and builders were exposed to liability for an indefinite time due to the longevity of
    buildings”); see also 2 Acret and Perrochet, Construction Litigation Handbook,
    Section 22:4, at 1249-1250 (2018-2019 Ed.2018).
    {¶ 11} A statute of repose is a statute that bars “any suit that is brought after
    a specified time since the defendant acted * * *, even if this period ends before the
    5
    SUPREME COURT OF OHIO
    plaintiff has suffered a resulting injury.” Black’s Law Dictionary 1637 (10th
    Ed.2014). The repose period begins to run “ ‘when a specific event occurs,
    regardless of whether a cause of action has accrued or whether any injury has
    resulted.’ ” 
    Id., quoting 54
    Corpus Juris Secundum, Limitations of Actions, Section
    4, at 20-21 (1987).
    {¶ 12} This court first addressed R.C. 2305.131 in Kocisko. The relevant
    version of the statute, enacted in 1971, stated:
    No action to recover damages for any injury to property, real
    or personal, or for bodily injury or wrongful death, arising out of the
    defective and unsafe condition of an improvement to real property,
    nor any action for contribution or indemnity for damages sustained
    as a result of said injury, shall be brought against any person
    performing services for or furnishing the design, planning,
    supervision of construction, or construction of such improvement to
    real property, more than ten years after the performance or
    furnishing of such services and construction. This limitation does
    not apply to actions against any person in actual possession and
    control as owner, tenant, or otherwise of the improvement at the time
    the defective and unsafe condition of such improvement constitutes
    the proximate cause of the injury or damage for which the action is
    brought.
    Am.S.B. No. 307, 134 Ohio Laws, Part I, 529, 530.
    {¶ 13} We noted in Kocisko that the 1971 version of R.C. 2305.131 applied
    only to “actions for injury to real or personal property, bodily injury, or wrongful
    death, ‘arising out of the defective and unsafe condition of an improvement to real
    property.’ ” 
    Kocisko, 21 Ohio St. 3d at 99
    , 
    488 N.E.2d 171
    , quoting Am.S.B. No.
    6
    January Term, 2019
    307, 134 Ohio Laws, Part I, at 530. We stated that the statutory language was
    “uniformly used to describe tortious conduct” and that the statute’s use of the terms
    “ ‘defective’ and ‘unsafe’ to describe the improvements at issue distinguish[ed] the
    actions contemplated within the statute from warranty or other contractual claims.”
    (Emphasis sic.) 
    Id. We therefore
    held that the 1971 version of R.C. 2305.131
    applied only to tort actions. 
    Id. at the
    syllabus.
    {¶ 14} In 1994, this court held that the 1971 version of R.C. 2305.131—the
    version at issue in Kocisko—violated the right to a remedy guaranteed by Article I,
    Section 16 of the Ohio Constitution because it deprived claimants of the right to
    sue before they knew or could have known about their injuries. 
    Brennaman, 70 Ohio St. 3d at 466-467
    , 
    639 N.E.2d 425
    , overruling Sedar, 
    49 Ohio St. 3d 193
    , 
    551 N.E.2d 938
    . Brennaman involved personal injuries that were incurred more than
    ten years after the defendants provided design and engineering services relating to
    the construction of a titanium metal plant. If applicable, the 1971 version of R.C.
    2305.131 would have barred the plaintiffs’ claims before they ever suffered an
    injury. We stated, “At a minimum, Section 16, Article I requires that the plaintiffs
    have a reasonable period of time to enter the courthouse to seek compensation after
    the accident.” 
    Id. at 466.
           {¶ 15} In 1996, partly in response to Brennaman, the General Assembly
    repealed the 1971 version of R.C. 2305.131 and enacted a new version of the
    statute, which began:
    (A)(1) Notwithstanding an otherwise applicable period of
    limitations specified in this chapter and except as otherwise
    provided in divisions (A)(2), (A)(3), (C), and (D) of this section, no
    cause of action to recover damages for an injury to real or personal
    property, bodily injury, or wrongful death that arises out of a
    defective and unsafe condition of an improvement to real property
    7
    SUPREME COURT OF OHIO
    * * * shall accrue against a person who performed services for the
    improvement to real property or a person who furnished the design,
    planning, supervision of construction, or construction of the
    improvement to real property later than fifteen years from the date
    of the performance of the services or the furnishing of the design,
    planning, supervision of construction, or construction.
    Am.Sub.H.B. No. 350 (“H.B. 350”), 146 Ohio Laws, Part II, 3867, 3917.
    {¶ 16} Whereas the 1971 version of R.C. 2305.131 precluded the
    commencement of an action, the H.B. 350 version of R.C. 2305.131 precluded the
    accrual of a cause of action. The General Assembly stated its understanding that
    the H.B. 350 version of R.C. 2305.131 would not violate the right to a remedy,
    because it did not deny a remedy to a claimant with a vested cause of action but
    instead precluded a cause of action from ever vesting. 
    Id. at Section
    5(E)(5), 146
    Ohio Laws, Part II, at 4022. But after this court held that H.B. 350 violated the
    Ohio Constitution’s single-subject rule, State ex rel. Ohio Academy of Trial
    Lawyers v. Sheward, 
    86 Ohio St. 3d 451
    , 
    715 N.E.2d 1062
    (1999), paragraph three
    of the syllabus, the General Assembly repealed R.C. 2305.131, “both as it results
    from and as it existed prior to its repeal and re-enactment by” H.B. 350. Sub.S.B.
    No. 108, Section 2.02(E), 149 Ohio Laws, Part I, 382, 499. The repeal took effect
    on July 6, 2001. 
    Id. at Section
    9, 149 Ohio Laws, Part I, at 511.
    {¶ 17} In 2004, the General Assembly enacted the current version of R.C.
    2305.131, which is substantially similar to the H.B. 350 version of the statute. It
    begins:
    (A)(1) Notwithstanding an otherwise applicable period of
    limitations specified in this chapter or in section 2125.02 of the
    Revised Code and except as otherwise provided in divisions (A)(2),
    8
    January Term, 2019
    (A)(3), (C), and (D) of this section, no cause of action to recover
    damages for bodily injury, an injury to real or personal property, or
    wrongful death that arises out of a defective and unsafe condition of
    an improvement to real property * * * shall accrue against a person
    who performed services for the improvement to real property or a
    person who furnished the design, planning, supervision of
    construction, or construction of the improvement to real property
    later than ten years from the date of substantial completion of such
    improvement.
    Am.Sub.S.B. No. 80, 150 Ohio Laws, Part V, at 7937-7938. The General Assembly
    recognized that the availability of evidence pertaining to an improvement to real
    property more than ten years after completion is problematic and that it is an
    unacceptable burden to require the maintenance of records and documentation
    pertaining to an improvement to real property for more than ten years after
    completion. 
    Id. at Section
    3(B)(3) and (4), 150 Ohio Laws, Part V, at 8029. It
    intended the current version of R.C. 2305.131 “to preclude the pitfalls of stale
    litigation.” 
    Id. at Section
    3(B)(5), 150 Ohio Laws, Part V, at 8029.
    Stare decisis
    {¶ 18} The Third District held that stare decisis required it to follow
    Kocisko and to hold that the current version of R.C. 2305.131, like the 1971 version
    of the statute, applies only to claims sounding in tort. 2017-Ohio-8521 at ¶ 11;
    2017-Ohio-8522 at ¶ 8. The doctrine of stare decisis requires a court to recognize
    and follow an established legal decision in subsequent cases in which the question
    of law is again in controversy. Clark v. Snapper Power Equip., Inc., 
    21 Ohio St. 3d 58
    , 60, 
    488 N.E.2d 138
    (1986). As a result, “[w]ell-reasoned opinions become
    controlling precedent, thus creating stability and predictability in our legal system.”
    9
    SUPREME COURT OF OHIO
    Westfield Ins. Co. v. Galatis, 
    100 Ohio St. 3d 216
    , 2003-Ohio-5849, 
    797 N.E.2d 1256
    , ¶ 1.
    {¶ 19} Considerations of stare decisis are particularly apt in the area of
    statutory construction because if the legislature disagrees with a court’s
    interpretation of a statute, it may amend the statute. Pearson v. Callahan, 
    555 U.S. 223
    , 233, 
    129 S. Ct. 808
    , 
    172 L. Ed. 2d 565
    (2009); Rocky River v. State Emp.
    Relations Bd., 
    43 Ohio St. 3d 1
    , 6, 
    539 N.E.2d 103
    (1989). But questions about the
    applicability of stare decisis arise when, as here, the legislature has amended a
    statute subsequent to a judicial interpretation of the statute. Appellants argue that
    stare decisis should not be applied here, because the General Assembly repealed
    the version of R.C. 2305.131 addressed in Kocisko and has enacted a substantially
    different version.
    {¶ 20} We do not apply stare decisis to strike down legislation merely
    because it is similar to a previous enactment that we found unconstitutional. Groch
    v. Gen. Motors Corp., 
    117 Ohio St. 3d 192
    , 2008-Ohio-546, 
    883 N.E.2d 377
    , ¶ 104.
    “To be covered by the blanket of stare decisis, the legislation must be phrased in
    language that is substantially the same as that which we have previously
    invalidated.” 
    Id., citing Arbino
    v. Johnson & Johnson, 
    116 Ohio St. 3d 468
    , 2007-
    Ohio-6948, 
    880 N.E.2d 420
    , ¶ 22-23. In Stetter v. R.J. Corman Derailment Servs.,
    L.L.C., 
    125 Ohio St. 3d 280
    , 2010-Ohio-1029, 
    927 N.E.2d 1092
    , ¶ 39, we conducted
    “a fresh review” of a statute that, despite a resemblance to previous legislation,
    differed from the prior statute “in significant and important ways.” See also State
    v. Bodyke, 
    126 Ohio St. 3d 266
    , 2010-Ohio-2424, 
    933 N.E.3d 753
    , ¶ 33 (lead
    opinion) (“as a threshold question, we must determine whether the statute and facts
    presented today are the same as those presented in precedent”).
    {¶ 21} New Riegel argues that Kocisko remains controlling because the
    1971 and the current versions of R.C. 2305.131 similarly define the actions to
    which they apply. The 1971 version of the statute applied to any “action to recover
    10
    January Term, 2019
    damages for any injury to property, real or personal, or for bodily injury or wrongful
    death, arising out of the defective and unsafe condition of an improvement to real
    property.” Am.Sub.S.B. No. 307, 134 Ohio Laws, Part I, at 530. The current
    version of the statute applies to any “cause of action to recover damages for bodily
    injury, an injury to real or personal property, or wrongful death that arises out of a
    defective and unsafe condition of an improvement to real property.”                R.C.
    2305.131(A)(1). But while the specific language defining the scope of the statute’s
    coverage has not substantially changed, we must now read that language in light of,
    and in a manner consistent with, the expanded, current version of the statute.
    {¶ 22} The current version of R.C. 2305.131 is sufficiently different from
    the 1971 version of the statute “ ‘to avoid the blanket application of stare decisis,’ ”
    Groch at ¶ 106, quoting Arbino at ¶ 24. Unlike the single-paragraph 1971 version
    of R.C. 2305.131, the current version of the statute consists of nine paragraphs,
    which set out exceptions to its application, situations that give rise to extensions of
    the repose period, and instructions that it be applied in a remedial manner in any
    civil action commenced on or after its effective date. The current version of R.C.
    2305.131, unlike the 1971 version, expressly refers to contract-law concepts,
    acknowledges that improvements to real property are generally designed and built
    pursuant to contract, and applies notwithstanding other general statutes of
    limitations, including those for contract actions. These substantial differences
    between the 1971 and the current versions of R.C. 2305.131 warrant “a fresh
    review” of the statute. Stetter at ¶ 39; see also McClure v. Alexander, 2d Dist.
    Greene No. 2007 CA 98, 2008-Ohio-1313, ¶ 53, quoting Groch at ¶ 106 (holding
    that the 1971 and the current versions of R.C. 2305.131 are “sufficiently different
    * * * ‘to avoid the blanket application of stare decisis’ ”). We therefore conclude
    that the Third District erred by applying the doctrine of stare decisis to hold that the
    current version of R.C. 2305.131 applies only to tort claims.
    11
    SUPREME COURT OF OHIO
    R.C. 2305.131 applies to both contract and tort claims
    {¶ 23} Now, freed from the constraints of Kocisko, we turn to the current
    version of R.C. 2305.131 to consider independently whether it applies to contract
    claims as well as to tort claims.
    {¶ 24} “The primary goal of statutory construction is to ascertain and give
    effect to the legislature’s intent in enacting the statute.” State v. Lowe, 112 Ohio
    St.3d 507, 2007-Ohio-606, 
    861 N.E.2d 512
    , ¶ 9. We read words and phrases in a
    statute according to rules of grammar and common usage and in the context of the
    whole statute. R.C. 1.42; Commerce & Industry Ins. Co. v. Toledo, 
    45 Ohio St. 3d 96
    , 102, 
    543 N.E.2d 1188
    (1989). And we presume that the General Assembly
    intended the entire statute to be effective. R.C. 1.47(B). We may look beyond the
    plain statutory language only when a definitive meaning remains elusive despite a
    thorough, objective examination of the language. Ohio Neighborhood Fin., Inc. v.
    Scott, 
    139 Ohio St. 3d 536
    , 2014-Ohio-2440, 
    13 N.E.3d 1115
    , ¶ 23, citing State v.
    Porterfield, 
    106 Ohio St. 3d 5
    , 2005-Ohio-3095, 
    829 N.E.2d 690
    , ¶ 11.
    {¶ 25} R.C. 2305.131(A)(1) applies to “cause[s] of action to recover
    damages for bodily injury, an injury to real or personal property, or wrongful death
    that arise[] out of a defective and unsafe condition of an improvement to real
    property.” Although this court stated in 
    Kocisko, 21 Ohio St. 3d at 99
    , 
    488 N.E.2d 171
    , that similar language in the 1971 version of R.C. 2305.131 was “uniformly
    used to describe tortious conduct,” that statement was shortsighted. More recently,
    for example, Ohio courts have recognized that a plaintiff, in appropriate
    circumstances, may seek damages for injury to property in an action for breach of
    contract. See, e.g., Landis v. William Fannin Builders, Inc., 2011-Ohio-1489, 
    951 N.E.2d 1078
    , ¶ 36-38 (10th Dist.) (applying rule governing damages for temporary
    injury to real property in breach-of-contract claim); Booth v. Duffy Homes, Inc.,
    
    185 Ohio App. 3d 260
    , 2009-Ohio-6767, 
    923 N.E.2d 1175
    , ¶ 9, 13 (10th Dist.)
    12
    January Term, 2019
    (same); see also Bauman Chevrolet, Inc. v. Faust, 
    113 N.E.2d 769
    (Erie C.P.1953)
    (breach-of-contract claim sought damages for injury to personal property).
    {¶ 26} Reading the current version of R.C. 2305.131 as a whole, we
    conclude that Ohio’s construction statute of repose is not limited to tort actions but
    also applies to contract actions that meet the requirements of the statute. See State
    ex rel. Wray v. Karl R. Rohrer Assocs., Inc., 2018-Ohio-65, 
    104 N.E.3d 865
    , ¶ 30
    (5th Dist.) (“It matters not whether the action is brought in tort or contract, if the
    resultant damages are injury to property of the type set forth in R.C. 2305.131, the
    statute applies”).
    {¶ 27} R.C. 2305.131(A)(1) states that the repose period applies,
    “[n]otwithstanding an otherwise applicable period of limitations specified in this
    chapter.” R.C. Chapter 2305 includes statutes of limitations for contract claims,
    see R.C. 2305.06 and 2305.07, as well as for tort claims, see R.C. 2305.09 and
    2305.10. The uncodified language in Am.Sub.S.B. No. 80, Section 3(B)(1), 150
    Ohio Laws, Part V, at 8028-8029, confirms the General Assembly’s intention that
    the construction statute of repose “promote a greater interest than the interest
    underlying” not only the general tort statutes of limitations in R.C. 2305.09 and
    2305.10 but also the interest underlying “other general statutes of limitation
    prescribed by the Revised Code.”        Had the General Assembly intended the
    construction statute of repose to apply only to tort claims, it could have specified
    those statutes of limitations applicable to tort claims in the introductory phrase of
    R.C. 2305.131(A)(1).
    {¶ 28} Moreover, the General Assembly explicitly tied the commencement
    of the repose period to contractual performance. The ten-year repose period
    established in R.C. 2305.131(A)(1) begins to run upon “substantial completion” of
    an improvement. “Substantial completion” is defined as “the date the improvement
    to real property is first used by the owner or tenant of the real property or when the
    real property is first available for use after having the improvement completed in
    13
    SUPREME COURT OF OHIO
    accordance with the contract or agreement covering the improvement, including
    any agreed changes to the contract or agreement, whichever occurs first.”
    (Emphasis added.) R.C. 2305.131(G). By enacting that definition, the General
    Assembly acknowledged that a defendant in an action to which R.C. 2305.131
    applies—“a person who performed services for [an] improvement to real property
    or a person who furnished the design, planning, supervision of construction, or
    construction of [an] improvement to real property,” R.C. 2305.131(A)(1)—will
    generally operate pursuant to a contract.      New Riegel does not dispute that
    “substantial completion” is a contract term, and it acknowledges that the
    professionals listed in R.C. 2305.131 “always provide their services under
    contracts.”
    {¶ 29} Perhaps the most persuasive indication that the General Assembly
    did not intend generally to exclude contract actions from the construction statute of
    repose, however, is found in R.C. 2305.131(D), which specifically excludes from
    the application of the statute of repose “a civil action for damages against a person
    who has expressly warranted or guaranteed an improvement to real property for a
    period longer than” the ten-year repose period. Express warranty is a creature of
    contract. See Houston-Starr Co. v. Berea Brick & Tile Co., 
    197 F. Supp. 492
    , 499
    (N.D.Ohio 1961). And if R.C. 2305.131(A)(1) did not otherwise apply to a
    contractual warranty claim, the General Assembly would have had no reason to
    exclude warranty claims from the operation of the statute. We assume that the
    General Assembly does not use words or enact statutory provisions unnecessarily,
    and we avoid construing a statute in a way that would render a portion of the statute
    meaningless or inoperative. State v. Moore, 
    154 Ohio St. 3d 94
    , 2018-Ohio-3237,
    
    111 N.E.3d 1146
    , ¶ 13, citing State ex rel. Myers v. Spencer Twp. Rural School
    Dist. Bd. of Edn., 
    95 Ohio St. 367
    , 373, 
    116 N.E. 516
    (1917).
    {¶ 30} Reading R.C. 2305.131 as a whole and in a manner that gives effect
    to all provisions of the statute, we conclude that Ohio’s construction statute of
    14
    January Term, 2019
    repose applies to all causes of action, whether sounding in tort or contract, that seek
    “to recover damages for bodily injury, an injury to real or personal property, or
    wrongful death that arise[] out of a defective and unsafe condition of an
    improvement to real property * * * against a person who performed services for the
    improvement to real property or a person who furnished the design, planning,
    supervision of construction, or construction of the improvement to real property.”
    This reading of the statute is consistent with the General Assembly’s stated
    intention to protect defendants from having to defend against stale claims, see
    Am.Sub.S.B. No. 80, Section 3(B)(3) through (5), 150 Ohio Laws, Part V, at 8029,
    the perils of which are the same whether the underlying claim is based in contract
    or tort.
    Whether R.C. 2305.131 bars New Riegel’s claims is not before this court
    {¶ 31} In an argument that goes beyond either proposition of law that this
    court accepted, New Riegel argues that even if R.C. 2305.131 is applicable, the
    statute does not bar its claims, which accrued within ten years after substantial
    completion of the Project, because R.C. 2305.131(A)(1) does not limit
    commencement of an action once a claim has accrued. According to New Riegel,
    the 15-year statute of limitations for contract actions begins to run once a cause of
    action accrues within the repose period and R.C. 2305.131(A)(1) does not shorten
    the time to file an action on an accrued claim. In the court of appeals, New Riegel
    argued that R.C. 2305.131 will never bar a breach-of-contract claim because such
    a claim accrues, necessarily within the repose period, when the breach occurs, i.e.,
    when an architect publishes a defective design or when defective construction is
    performed. But the court of appeals did not address that argument.
    {¶ 32} We do not decide the effect on these cases of our holding that R.C.
    2305.131 applies to any cause of action, including a contract claim, that falls within
    the scope of R.C. 2305.131(A)(1), because that issue is beyond the scope of the
    15
    SUPREME COURT OF OHIO
    propositions of law that we accepted and because neither the trial court nor the court
    of appeals addressed it.
    Conclusion
    {¶ 33} For these reasons, we reverse the judgments of the Third District
    Court of Appeals and remand these cases to that court to address New Riegel’s
    remaining arguments.
    Judgments reversed
    and causes remanded.
    O’CONNOR, C.J., and FISCHER and DONNELLY, JJ., concur.
    KENNEDY, J., concurs in part and dissents in part, with an opinion joined by
    DEWINE, J.
    STEWART, J., dissents, with an opinion.
    _________________
    KENNEDY, J., concurring in part and dissenting in part.
    {¶ 34} Because R.C. 2305.131 applies to all causes of action for damages
    arising out of the defective and unsafe condition of an improvement brought against
    a person who furnished the design, planning, supervision of construction, or
    construction of that improvement, and because breach of contract is a cause of
    action, e.g., Lucarell v. Nationwide Mut. Ins. Co., 
    152 Ohio St. 3d 453
    , 2018-Ohio-
    15, 
    97 N.E.3d 458
    , ¶ 41, I concur in the court’s judgment to the extent that it
    reverses the judgments of the Third District Court of Appeals.
    {¶ 35} I write separately, however, to address the assertion that R.C.
    2305.131(A)(1) does not bar commencement of an action once a claim has accrued.
    Appellee, the New Riegel Local School District Board of Education, contends that
    the General Assembly intended R.C. 2305.131(A)(1) to apply only to causes of
    action sounding in tort, reasoning that “when a written contract exists related to the
    design or construction of an improvement to real property, the statute of repose
    would sit wholly impotent.” According to the school board, a breach-of-contract
    16
    January Term, 2019
    claim can never be limited by the construction statute of repose because such a
    claim will always accrue before the ten-year period expires, and for this reason, the
    school board maintains that “[i]t makes no sense to say that the General Assembly
    intended” R.C. 2305.131(A)(1) to apply to breach-of-contract claims.
    {¶ 36} Contrary to the majority’s analysis, this statutory-construction
    argument responds directly to the propositions of law that we accepted for review.
    We cannot decide the issue presented in this case without addressing the school
    board’s argument. Moreover, an appellee such as the school board can defend a
    judgment of the court of appeals with arguments that were not passed on by that
    court, see O’Toole v. Denihan, 
    118 Ohio St. 3d 374
    , 2008-Ohio-2574, 
    889 N.E.2d 505
    , ¶ 94, and “ ‘[r]eviewing courts are not authorized to reverse a correct judgment
    on the basis that some or all of the lower court’s reasons are erroneous,’ ” Goudlock
    v. Voorhies, 
    119 Ohio St. 3d 398
    , 2008-Ohio-4787, 
    894 N.E.2d 692
    , ¶ 12, quoting
    State ex rel. McGrath v. Ohio Adult Parole Auth., 
    100 Ohio St. 3d 72
    , 2003-Ohio-
    5062, 
    796 N.E.2d 526
    , ¶ 8. The school board’s argument is therefore properly
    before this court, and reaching it is necessary to decide this case. This court’s
    remand of the case does nothing more than add further delay in resolving this
    matter.
    {¶ 37} In Oaktree Condominium Assn., Inc. v. Hallmark Bldg. Co., 
    139 Ohio St. 3d 264
    , 2014-Ohio-1937, 
    11 N.E.3d 266
    , we considered whether the
    application of R.C. 2305.131 to the plaintiff violated the Ohio Constitution’s
    prohibition on retroactive laws. The cause of action had accrued prior to the
    enactment of the statute but was commenced more than ten years after construction
    had been completed. We recognized that R.C. 2305.131 was a statutory bar to the
    claim, because “[b]y its plain language, the real-property-construction statute of
    repose, which became effective on April 7, 2005, applies to civil actions
    commenced after the effective date of the statute regardless of when the cause of
    action accrued.” (Emphasis added.) 
    Id. at ¶
    8. And we noted that “[b]ecause [the
    17
    SUPREME COURT OF OHIO
    plaintiff’s] cause of action accrued and vested before the April 7, 2005 effective
    date of R.C. 2305.131, the retroactive application of the statute of repose would
    take away [its] substantive right and conflict with Article II, Section 28 of the Ohio
    Constitution.” 
    Id. at ¶
    12. We therefore understood that the statute of repose bars
    causes of action that had accrued but were not commenced prior to the running of
    the ten-year period.
    {¶ 38} The school board nonetheless asks us to construe the phrase “no
    cause of action * * * shall accrue,” R.C. 2305.131(A)(1), to exempt causes of
    actions that did in fact accrue during the ten-year repose period. It reasons that had
    the General Assembly intended R.C. 2305.131 to be a true statute of repose, it
    would have provided that no cause of action “shall be commenced” after ten years.
    {¶ 39} However, we may not read individual words of a statute in isolation;
    rather, we are obligated “to evaluate a statute ‘as a whole and giv[e] such
    interpretation as will give effect to every word and clause in it. No part should be
    treated as superfluous unless that is manifestly required, and the court should avoid
    that construction which renders a provision meaningless or inoperative.’ ” Boley v.
    Goodyear Tire & Rubber Co., 
    125 Ohio St. 3d 510
    , 2010-Ohio-2550, 
    929 N.E.2d 448
    , ¶ 21, quoting State ex rel. Myers v. Spencer Twp. Rural School Dist. Bd. of
    Edn. 
    95 Ohio St. 367
    , 373, 
    116 N.E. 516
    (1917). “ ‘ “[S]ignificance and effect
    should, if possible, be accorded to every word, phrase, sentence and part of an
    act.” ’ ” 
    Id., quoting Weaver
    v. Edwin Shaw Hosp., 
    104 Ohio St. 3d 390
    , 2004-
    Ohio-6549, 
    819 N.E.2d 1079
    , ¶ 13, quoting Wachendorf v. Shaver, 
    149 Ohio St. 231
    , 
    78 N.E.2d 370
    (1948), paragraph five of the syllabus.
    {¶ 40} Construing R.C. 2305.131 as applying only to causes of action that
    accrue after the ten-year repose period has expired would render large swaths of the
    statute wholly superfluous. For example, R.C. 2305.131(A)(2) creates a discovery-
    rule exception to the statute of repose:
    18
    January Term, 2019
    Notwithstanding an otherwise applicable period of
    limitations specified in this chapter or in section 2125.02 of the
    Revised Code, a claimant who discovers a defective and unsafe
    condition of an improvement to real property during the ten-year
    period specified in division (A)(1) of this section but less than two
    years prior to the expiration of that period may commence a civil
    action to recover damages as described in that division within two
    years from the date of the discovery of that defective and unsafe
    condition.
    Similarly, R.C. 2305.131(A)(3) includes an exception to the statute of repose for
    plaintiffs “within the age of minority or of unsound mind” pursuant to R.C.
    2305.16:
    Notwithstanding an otherwise applicable period of
    limitations specified in this chapter or in section 2125.02 of the
    Revised Code, if a cause of action that arises out of a defective and
    unsafe condition of an improvement to real property accrues during
    the ten-year period specified in division (A)(1) of this section and
    the plaintiff cannot commence an action during that period due to a
    disability described in section 2305.16 of the Revised Code, the
    plaintiff may commence a civil action to recover damages as
    described in that division within two years from the removal of that
    disability.
    {¶ 41} Construing the statute of repose as not applying to causes of action
    that accrued within the ten-year repose period renders these two exceptions
    meaningless and inoperative. As the Fifth District Court of Appeals has explained,
    19
    SUPREME COURT OF OHIO
    under that interpretation, R.C. 2305.131(A)(2) “would have no effect on any
    claimant because once a claimant’s cause of action accrued, the statute of repose
    would no longer apply and the statute of limitations would apply.” Tuslaw Local
    School Dist. Bd. of Edn. v. CT Taylor Co., Inc., 5th Dist. Stark No. 2018CA00099,
    2019-Ohio-1731, __ N.E.3d __, ¶ 25.           The same reasoning applies to R.C.
    2305.131(A)(3).
    {¶ 42} Moreover, in uncodified law, the General Assembly repeatedly
    described R.C. 2305.131 as a statute of repose.          It explained that although
    “[s]tatutes of repose are vital instruments that provide time limits, closure, and
    peace of mind to potential parties of lawsuits,” Ohio had stood virtually alone in
    failing to “adopt[] statutes of repose to protect architects, engineers, and
    constructors of improvements to real property from lawsuits arising after a specific
    number of years after completion of an improvement to real property.”
    Am.Sub.S.B. No. 80, Section 3(A), 150 Ohio Laws, Part V, 7915, 8026-8027. The
    legislature acted to remedy that failing and eliminate the “unacceptable burden” of
    requiring architects, engineers, and constructors of improvements to real property
    to maintain insurance against liability, retain documents and records, and preserve
    evidence throughout the useful life of the improvement, explaining that “the ten-
    year statute of repose prescribed in [R.C. 2305.131(A)(1)] is a rational period of
    repose intended to preclude the pitfalls of stale litigation.” 
    Id. at 8027-8029.
    And
    it declared that R.C. 2305.131 was intended “to promote a greater interest than the
    interest underlying * * * other general statutes of limitation prescribed by the
    Revised Code.” 
    Id. at 8028-8029.
           {¶ 43} It is therefore manifest that the General Assembly understood R.C.
    2305.131 to be a true statute of repose, i.e., one that bars accrued claims as well as
    those that have not yet vested. See Antoon v. Cleveland Clinic Found., 148 Ohio
    St.3d 483, 2016-Ohio-7432, 
    71 N.E.3d 974
    , ¶ 16. As the United States Supreme
    Court has explained, a statute of repose is akin to a discharge in bankruptcy;
    20
    January Term, 2019
    because it is a “cutoff” or absolute bar to liability that “puts an outer limit on the
    right to bring a civil action,” application of a statute of repose does not depend on
    whether the cause of action has accrued. CTS Corp. v. Waldburger, 
    573 U.S. 1
    , 8-
    9, 
    134 S. Ct. 2175
    , 
    189 L. Ed. 2d 62
    (2014). It extinguishes liability regardless. 
    Id. {¶ 44}
    The plain language of R.C. 2305.131(A), read in its entirety,
    extinguishes liability for injuries arising out of a defective and unsafe condition of
    an improvement brought against a person who designed, planned, supervised, or
    constructed that improvement after ten years from its substantial completion,
    subject to the time extensions established in subdivisions (A)(2) and (A)(3) of that
    statute. Uncodified law and our caselaw support this conclusion. Because the
    school board brought this breach-of-contract action more than ten years after the
    substantial completion of its school building, the trial court correctly dismissed the
    breach-of-contract claims as time-barred. For this reason, I would reverse the
    judgments of the court of appeals and reinstate the judgments of the trial court.
    DeWine, J., concurs in the foregoing opinion.
    _________________
    STEWART, J.
    {¶ 45} I respectfully dissent from the majority’s holding that R.C.
    2305.131(A)(1), Ohio’s construction statute of repose, applies to contract actions.
    R.C. 2305.131(A)(1) has not been changed in any significant way since this court
    interpreted it in Kocisko v. Charles Shutrump & Sons Co., 
    21 Ohio St. 3d 98
    , 
    488 N.E.2d 171
    (1986), syllabus, to apply “only to actions which sound in tort.” We
    should reaffirm Kocisko and leave it to the General Assembly to amend the statute
    to provide that it applies to contract actions, if that truly is the General Assembly’s
    intent.
    {¶ 46} The majority concedes that the current version of R.C.
    2305.131(A)(1) contains language “similar” to the version of the statute that we
    construed in Kocisko. Majority opinion at ¶ 25. That is an understatement: the
    21
    SUPREME COURT OF OHIO
    version we construed in Kocisko applied to “action[s] to recover damages for any
    injury to property, real or personal, or for bodily injury or wrongful death,” Am.S.B.
    No. 307, 134 Ohio Laws, Part I, 529, 530, while the current version of the statute
    applies to “action[s] to recover damages for bodily injury, an injury to real or
    personal property, or wrongful death,” R.C. 2305.131(A)(1). The same words are
    used but merely reordered, with no effect on the meaning of the statute.
    {¶ 47} After we held in Kocisko that former R.C. 2305.131(A)(1) applied
    only to tort actions and that “[a]ctions in contract continue to be governed by the
    fifteen-year statute of limitations found in R.C. 2305.06,” Kocisko at syllabus, the
    General Assembly could easily have amended R.C. 2305.131(A)(1) to add
    “contract actions” to the actions listed in that provision if that had been its intent
    when initially enacting the statute.2 But subsequently, despite twice amending
    other parts of the statute, the General Assembly chose not to supersede Kocisko by
    adding contract actions to the actions listed in R.C. 2305.131(A)(1).
    {¶ 48} Under the rules that the General Assembly enacted to guide courts
    when interpreting statutes, we are constrained to construe the amendments to R.C.
    2305.131(A)(1) that did not expand the statute’s applicability as “intended to be a
    continuation of the prior statute and not a new enactment, so far as it is the same as
    the prior statute,” R.C. 1.54. “By the rules of construction of statutes, if a statute is
    2. Notably, a number of states have enacted construction statutes of repose that explicitly apply to
    contract actions. See, e.g., 735 Ill.Comp.Stat. 5/13-214(a) (“Actions based upon tort, contract or
    otherwise against any person for an act or omission of such person in the design, planning,
    supervision, observation or management of construction, or construction of an improvement to real
    property * * *”); Ind.Code Ann. 32-30-1-5(d) (applying to actions, “whether based upon contract,
    tort, nuisance, or another legal remedy,” for any deficiency in design or construction of an
    improvement to real property or “an injury to real or personal property arising out of a deficiency”);
    N.J.Stat.Ann. 2A:14-1.1(a) (applying to any action, “whether in contract, in tort, or otherwise,” for
    “any deficiency in the design, planning, surveying, supervision or construction of an improvement
    to real property, or for any injury to property, real or personal, or for an injury to the person, or for
    bodily injury or wrongful death”); Colo.Rev.Stat. 13-80-104(1)(c) (statute of repose for design and
    construction claims applies to “any and all actions in tort, contract, indemnity, or contribution, or
    other actions for the recovery of damages”).
    22
    January Term, 2019
    amended in certain particulars, after the same has been interpreted and defined by
    the courts, without change in other respects, it will be presumed that the Legislature
    was satisfied with the court’s interpretation upon these features which were
    unchanged, but that the amended portions were intended to be excepted from the
    operation of the court’s decision.” Spitzer v. Stillings, 
    109 Ohio St. 297
    , 305, 
    142 N.E. 365
    (1924); see also State v. Hassler, 
    115 Ohio St. 3d 322
    , 2007-Ohio-4947,
    
    875 N.E.2d 46
    , ¶ 16 (despite amending statute eight times, legislature showed no
    intent to supersede judicial interpretation of statute). We recently noted this
    proposition in Wayt v. DHSC, L.L.C., 
    155 Ohio St. 3d 401
    , 2018-Ohio-4822, 
    122 N.E.3d 92
    , ¶ 23, in which we presumed that the legislature had been aware of a
    prior decision of this court and “could easily have drafted the statute to prevent the
    holding from that case from affecting the outcome of this case” by adding a single
    term to an existing statute. The same reasoning applies here. The General
    Assembly is presumed to have been aware of our decision in Kocisko, and its failure
    to add contract actions to the actions listed in R.C. 2305.131(A)(1) shows that it
    has been content to let the statute stand as we previously interpreted it.
    {¶ 49} Finding no support for its interpretation of R.C. 2305.131(A)(1) in
    the text of that provision, the majority maintains that the General Assembly
    nonetheless intended to include contract actions within the scope of the construction
    statute of repose because the current statute contains “contract-law concepts.”
    Majority opinion at ¶ 22. Exactly what contract-law “concepts” are incorporated
    into the statute is unclear.    The word “contract”—followed by its synonym,
    “agreement”—appears only twice in R.C. 2305.131, both times in division (G):
    As used in this section, “substantial completion” means the
    date the improvement to real property is first used by the owner or
    tenant of the real property or when the real property is first available
    for use after having the improvement completed in accordance with
    23
    SUPREME COURT OF OHIO
    the contract or agreement covering the improvement, including any
    agreed changes to the contract or agreement, whichever occurs first.
    {¶ 50} The “substantial completion” of a contract or agreement to construct
    an improvement to property triggers the initiation of the repose period. R.C.
    2305.131(A)(1). It has nothing to do with the actual cause of action for “bodily
    injury, an injury to real or personal property, or wrongful death that arises out of a
    defective and unsafe condition of an improvement to real property,” 
    id. As this
    court noted in Kocisko, language relating to injury or wrongful death is “uniformly
    used to describe tortious 
    conduct.” 21 Ohio St. 3d at 99
    , 
    488 N.E.2d 171
    . None of
    these injuries encompass contract claims.
    {¶ 51} The majority suggests that a party may seek damages for injury to
    property in a contract action but cites no authority from this court in support of that
    proposition. The breach-of-contract claims brought in this action sought economic
    damages—that is, the benefit of the bargain had the school building been designed
    and constructed according to applicable state standards. The “economic loss”
    doctrine states that when parties are in privity of contract and one party allegedly
    suffers purely economic damages as a result of an alleged breach of that contract,
    that party’s exclusive remedy is in the law of contracts and no action is cognizable
    in tort. Chemtrol Adhesives, Inc. v. Am. Mfrs. Mut. Ins. Co., 
    42 Ohio St. 3d 40
    , 45,
    
    537 N.E.2d 624
    (1989). “ ‘When the promisee’s injury consists merely of the loss
    of his bargain, no tort claim arises because the duty of the promisor to fulfill the
    term of the bargain arises only from the contract.’ ” 
    Id., quoting Battista
    v. Lebanon
    Trotting Assn., 
    538 F.2d 111
    , 117 (6th Cir.1976). Here, the plaintiff-school district
    did not allege that the defendants engaged in any tortious conduct that caused
    24
    January Term, 2019
    “injury to property.”3 The claims asserted in this case are purely contractual and
    outside the scope of the statute of repose.
    {¶ 52} Although the majority asserts that Kocisko was “shortsighted,”
    majority opinion at ¶ 25, Kocisko is consistent with decisions construing similar
    statutes of repose in other states. The Michigan Supreme Court considered a
    similarly worded construction statute of repose—former Mich.Comp.Laws
    600.5839(1) (“[n]o person may maintain any action to recover damages for injury
    to property, real or personal, or for bodily injury or wrongful death, arising out of
    the defective and unsafe condition of an improvement to real property”)—and held
    that that statute did “not apply to a claim against an engineer or contractor for a
    defect in an improvement when the nature and origin of the claim is the breach of
    a contract.” Miller-Davis Co. v. Ahrens Constr., Inc., 
    489 Mich. 355
    , 370, 
    802 N.W.2d 33
    (2011). The court quoted with approval the reasoning that a lower court
    provided in support of this conclusion in a prior case:
    “[T]his statute was enacted primarily to limit the engineers’ and
    architects’ exposure to litigation by injured third persons as
    evidenced by the legislation’s timing and relation to case law. * * *
    If there is no causal connection between the defective condition and
    the injury, the provision does not apply. Similarly, where the suit is
    for deficiencies in the improvement itself, the injury is the defective
    condition, hence, the injury does not ‘arise out of’ the defective
    condition, but, rather, it is the condition. Therefore, claims for
    deficiencies in the improvement itself do not come within the scope
    of this special statute of limitation.”
    3. Of course, there are torts involving real property; for example, trespass to property, vandalism,
    and nuisance.
    25
    SUPREME COURT OF OHIO
    
    Id. at 369-370,
    quoting Marysville v. Pate, Hirn & Bogue, Inc., 154 Mich.App. 655,
    660, 
    397 N.W.2d 859
    (1986).
    {¶ 53} And in Fid. & Deposit Co. of Maryland v. Bristol Steel & Iron
    Works, Inc., 
    722 F.2d 1160
    (4th Cir.1983), the United States Court of Appeals for
    the Fourth Circuit construed Va.Code 8.01-250, which, like R.C. 2305.131(A)(1),
    applies to actions “for any injury to property, real or personal, or for bodily injury
    or wrongful death.” The Fourth Circuit held, like this court in Kocisko, that “the
    statute, by its express terms, is restricted in its application to what are in effect tort
    actions to recover for ‘injury’ to property or persons and not to actions in contract”).
    
    Id. at 1162.
    These decisions show that Kocisko is not an outlier.
    {¶ 54} We have acknowledged the General Assembly’s prerogative, as the
    “ ‘ “ultimate arbiter of public policy,” ’ ” to “refine[] Ohio’s tort law to meet the
    needs of our citizens.” Groch v. Gen. Motors Corp., 
    117 Ohio St. 3d 192
    , 2008-
    Ohio-546, 
    883 N.E.2d 377
    , ¶ 102, quoting Arbino v. Johnson & Johnson, 116 Ohio
    St.3d 468, 2007-Ohio-6948, 
    880 N.E.2d 420
    , ¶ 21, quoting State ex rel. Cincinnati
    Enquirer, Div. of Gannett Satellite Information Network v. Dupuis, 
    98 Ohio St. 3d 126
    , 2002-Ohio-7041, 
    781 N.E.2d 163
    , ¶ 21. In the years following Kocisko, the
    General Assembly could easily have added contract actions to R.C.
    2305.131(A)(1)’s list of actions to which the statute applies, but it has chosen not
    to. We therefore must assume that the General Assembly is content with this
    court’s interpretation of the statute in Kocisko. A Virginia court reached the same
    conclusion in construing Va.Code 8.01-250, reasoning that the legislature had
    “presumably been aware of the Fourth Circuit’s construction of the statute, and it
    has not amended it”:
    Had the General Assembly intended § 8.01-250 to apply to
    actions for breach of contract, it could have added “breach of
    contract” to the enumerated actions in the statute or it could have
    26
    January Term, 2019
    omitted the words “to recover for any injury to property, real or
    personal, or for bodily injury or wrongful death.” It did neither.
    Inclusio unius est exclusio alterius.
    BurgerBusters, Inc. v. Ratley Constr. Co., Inc., 45 Va.Cir. 133, 135 (1998), citing
    Fid. & Deposit Co. at 1162.
    {¶ 55} Indeed, in Minnesota, a former version of that state’s construction
    statute of repose, Minn.Stat. 541.051(1), much like R.C. 2305.131(A)(1), applied
    to “action[s] to recover damages for any injury to property, real or personal, or for
    bodily injury or wrongful death.” The Minnesota Supreme Court construed that
    statute as applying only to tort actions. Kittson Cty. v. Wells, Denbrook & Assocs.,
    Inc., 
    308 Minn. 237
    , 241, 
    241 N.W.2d 799
    (1976). In the wake of that decision,
    the Minnesota legislature did what our General Assembly has not done—it
    amended Minnesota’s construction statute of repose to cover “action[s] by any
    person in contract, tort, or otherwise.” Minn.Stat. 541.051(1); see Lietz v. N. States
    Power Co., 
    718 N.W.2d 865
    , 871 (Minn.2006).
    {¶ 56} The General Assembly has the power to adopt a statute of repose and
    define the parameters of that law. We should not take it upon ourselves to do that
    which the legislature has chosen not to do. I would conclude that given the absence
    of any amendment to supersede our holding in Kocisko, R.C. 2305.131(A)(1)
    applies only to tort actions. I would therefore reject both propositions of law and
    affirm the judgments of the court of appeals.
    _________________
    Bricker & Eckler, L.L.P., Christopher L. McCloskey, Tarik M. Kershah,
    and Bryan M. Smeenk, for appellee.
    Gallagher Sharp, L.L.P., P. Kohl Schneider, and Richard C.O. Rezie, for
    appellant Charles Construction Services, Inc.
    27
    SUPREME COURT OF OHIO
    Frantz Ward, L.L.P., Marc A. Sanchez, Michael J. Frantz Jr., and Allison
    Taller Reich, for appellant Ohio Farmers Insurance Company.
    Ritter, Robinson, McCready & James, Ltd., Shannon J. George, and
    Matthew T. Davis, for appellant Studer-Obringer, Inc.
    McNeal, Schick, Archibald & Biro Co., L.P.A., Brian T. Winchester, and
    Patrick J. Gump, for appellants Buehrer Group Architecture & Engineering, Inc.,
    Estate of Huber H. Buehrer, and Buehrer Group Architecture & Engineering.
    Singerman, Mills, Desberg & Kauntz Co., L.P.A, Michael R. Stavnicky,
    and Stephen L. Byron, urging affirmance for amici curiae County Commissioners
    Association of Ohio, Ohio Municipal League, Ohio Township Association, Erie
    County, and Ohio School Boards Association.
    Paul W. Flowers Co., L.P.A., Paul W. Flowers, and Louis E. Grube, urging
    affirmance for amicus curiae Ohio Association for Justice.
    Murray & Murray Co., L.P.A., Dennis E. Murray Sr., Charles M. Murray,
    and Donna J. Evans, urging affirmance for amicus curiae Timothy Betton.
    Graff and McGovern, L.P.A., and Luther L. Liggett Jr., urging reversal for
    amici curiae AIA Ohio and Ohio Society of Professional Engineers.
    Vorys, Sater, Seymour & Pease, L.L.P., Natalia Steele, and Thomas E.
    Szykowny, urging reversal for amici curiae Ohio Insurance Institute, Ohio
    Manufacturers’ Association, Ohio Chamber of Commerce, Ohio Chapter of the
    National Federation of Independent Business, and Surety & Fidelity Association of
    America.
    Harpst, Ross & Becker Co., L.L.C., Todd A. Harpst, and Joseph R.
    Spoonster, urging reversal for amicus curiae Subcontractors Association of
    Northeast Ohio.
    McDonald Hopkins, L.L.C., Peter D. Welin, Jason R. Harley, and John A.
    Gambill, urging reversal for amici curiae Associated General Contractors of Ohio;
    Allied Construction Industries (Cincinnati AGC); Associated General Contractors
    28
    January Term, 2019
    of Ohio, Akron; Builders Association of Eastern Ohio & Western Pennsylvania
    (AGC Youngstown); Central Ohio AGC; Associated General Contractors,
    Cleveland; Associated General Contractors of Northwest Ohio (Toledo AGC);
    West Central Ohio AGC (Dayton AGC); and Ohio Contractors Association.
    Koehler Fitzgerald, L.L.C., and Timothy J. Fitzgerald, urging reversal for
    amicus curiae Ohio Association of Civil Trial Attorneys.
    _________________
    29
    

Document Info

Docket Number: 2018-0189 and 2018-0213

Citation Numbers: 2019 Ohio 2851

Judges: French, J.

Filed Date: 7/17/2019

Precedential Status: Precedential

Modified Date: 7/17/2019

Cited By (17)

Maternal Grandmother v. Hamilton Cty. Dept. of Job & Family ... , 2021 Ohio 4096 ( 2021 )

Reister v. Gardner (Slip Opinion) , 2020 Ohio 5484 ( 2020 )

Gault v. Medina Cty. Court of Common Pleas Clerk , 2022 Ohio 3955 ( 2022 )

Gerritsen v. State Med. Bd. of Ohio , 2023 Ohio 943 ( 2023 )

State v. Chears , 2022 Ohio 861 ( 2022 )

Ewing v. UC Health , 2022 Ohio 2560 ( 2022 )

State ex rel. Betton v. Burgess & Niple, Inc. , 2023 Ohio 740 ( 2023 )

Rowe v. Hoist & Crane Serv. Group, Inc. , 2022 Ohio 3130 ( 2022 )

Everhart v. Coshocton Cty. Mem. Hosp. , 2022 Ohio 629 ( 2022 )

Mundy v. Golightly , 2022 Ohio 83 ( 2022 )

Acorn Dev., L.L.C. v. Sanson Co. , 2022 Ohio 2576 ( 2022 )

Cincinnati v. Rennick , 2022 Ohio 1110 ( 2022 )

Three-C Body Shops, Inc. v. Francois , 2020 Ohio 4710 ( 2020 )

Acorn Development, L.L.C. v. Sanson Co. , 2022 Ohio 2576 ( 2022 )

Grayson v. Cleveland Clinic Found. , 2022 Ohio 1668 ( 2022 )

Emanuel's, L.L.C. v. Restore Marietta, Inc. , 2023 Ohio 147 ( 2023 )

Everhart v. Merrick Mfg. II, L.L.C. , 2022 Ohio 4626 ( 2022 )

View All Citing Opinions »