Harmon v. San Francisco & San Rafael Railroad , 86 Cal. 617 ( 1890 )


Menu:
  • Paterson, J.

    — This cause was heard in Bank, and the judgment and order were reversed, and the cause remanded for a new trial in May last. We are satisfied with the conclusion then reached herein.

    The evidence shows that “the work on the contract was completed on June 2, 1884.” We are asked to consider the evidence in the record on appeal in the case of Gordon Hardware Co. v. San Francisco & S. R. R. R. Co., post, p. 620, because that case and the one at bar were consolidated, by order of the court below, upon consent of counsel for the respective parties; but this we cannot do. The plaintiff in each case was defeated in the court below, and each one moved separately for a new trial, the grounds of which were peculiar to the respective cases; separate bills of exceptions were prepared and filed, separate appeals were taken, and each case was presented in this court on its own record.

    Respondent claims that the claim filed by plaintiff, and upon which this action is based, must have included material for which no lien could be maintained, because the plaintiff testified that of the lumber he furnished “ there was used $1,159.13 worth in the building of temporary houses,” and $577 paid on the lumber for freight *619and cartage. It does not clearly appear whether there was extra material included in the claim of lien, or an erroneous statement as to the value; and as the claim filed contained no articles except such as are the subject of lien, we cannot see that a lien for so much lumber, etc., as was actually used in the construction of the road, should be defeated by reason of this testimony. The bare fact that the plaintiff had filed for too much lumber, or set too high a price on it, would not, in the absence of fraud, defeat his right to recover.

    Whatever may be the rule in ordinary cases, where the material-man furnishes materials to several independent contractors, we do not think it was necessary for the plaintiff to segregate the amounts in the claim which he filed. Hawley was the only person with whom the company had to settle. The latter was liable only for the balance of the contract price held by it. It was in no way interested in the question how much had been furnished McDonald before the assignment. Hawley had simply stepped into McDonald’s shoes, with the knowledge and consent of the company, and had assumed all liabilities. There was but one contract on the part of the defendant. On final settlement, McDonald was entitled to nothing, and we are unable to see how the company could be prejudiced by the failure to designate the amount furnished to each. No question of priority is involved herein. Where a statute required a claimant to state from whom the debt was due, it was held that a mistake in the name of the contractor would not defeat' the lien, if it appeared that the owner was not harmed by the error. (Putnam v. Ross, 46 Mo. 337.) In the case at bar, the proof segregates the amount furnished to Hawley from that which was furnished to McDonald, so that no injury could possibly result.

    We think that the court erred in rejecting the notice of lien. Other points made by the respondent need not be specially noticed.

    *620If the facts shown by the evidence of the plaintiff are true, he is entitled to have his lien declared good, to an amount not exceeding the amount of the contract price in the hands of the company at the time the notice of lien was filed.

    Judgment and order reversed, and cause remanded for a new trial.

    McFarland, J., Sharpstein, J., Fox, J., Thornton, J., and Beatty, C. J., concurred.

Document Info

Docket Number: No. 12017

Citation Numbers: 86 Cal. 617

Judges: Paterson

Filed Date: 12/8/1890

Precedential Status: Precedential

Modified Date: 1/12/2023