Zara Constr., Inc. v. Belcastro , 2022 Ohio 788 ( 2022 )


Menu:
  • [Cite as Zara Constr., Inc. v. Belcastro, 
    2022-Ohio-788
    .]
    COURT OF APPEALS
    RICHLAND COUNTY, OHIO
    FIFTH APPELLATE DISTRICT
    ZARA CONSTRUCTION, INC.,                            :       JUDGES:
    :       Hon. W. Scott Gwin, P.J.
    Plaintiff - Appellant                       :       Hon. Patricia A. Delaney, J.
    :       Hon. Craig R. Baldwin, J.
    -vs-                                                :
    :
    SCOTT BELCASTRO, et al.,                            :       Case No. 2021 CA 0039
    :
    Defendants - Appellees                      :       OPINION
    CHARACTER OF PROCEEDING:                                    Appeal from the Richland County
    Court of Common Pleas, Case No.
    2019 CV 0537 R
    JUDGMENT:                                                   Reversed and Remanded
    DATE OF JUDGMENT:                                           March 16, 2022
    APPEARANCES:
    For Plaintiff-Appellant                                     For Defendants-Appellees
    THOMAS L. ROSENDBERG                                        J. THOMAS NOCAR
    Roetzel & Andress LPA                                       JAMES A. KING
    41 S. High Street, 21st Floore                              Porter, Wright, Morris & Arthur LLP
    Columbus, Ohio 43215                                        41 S. High Street, 29th Floor
    Columbus, Ohio 43215
    BRIAN D. BREMER
    Roetzel & Andress LPA
    222 S. Main Street, Ste. 400
    Akron, Ohio 44308
    Richland County, Case No. 2021 CA 0039                                              2
    Baldwin, J.
    {¶1}    Zara Construction, Inc. is appealing the Richland County Court of Common
    Pleas decision granting appellees’ motion for directed verdict regarding Zara’s complaint
    to foreclose a mechanic’s lien and its claim for relief in quantum meruit or unjust
    enrichment. Appellees are Scott and Christine Belcastro.
    STATEMENT OF FACTS AND THE CASE
    {¶2}    Zara Construction, Inc. was started by Joseph Zara in 1992 as a general
    contracting business, primarily focusing on home construction, but also performing some
    light commercial work. Zara agreed to build a home designed by Scott and Christine
    Belcastro. The Belcastros provided plans for the home and, after multiple discussions the
    Belcastros agreed to have Zara complete some of the work. The Belcastros chose to
    serve as their own general contractor for several steps of the construction to reduce their
    costs. Parts of the project, including labor and materials for the footers and foundation,
    interior post and beam features and the spiral stair case, were completed by persons
    working under the supervision of the Belcastros.
    {¶3}    Zara drafted the contract and delivered it to the Belcastros for review on or
    before December 29, 2017.       The Belcastros reviewed the contract and requested
    changes before it was signed on February 15, 2018.
    {¶4}    Zara hired Stephen Marek to supervise a portion of the Belcastro project
    Zara was to complete and, at some point, the Belcastros hired Marek to perform work
    outside the parameters of the Zara Contract.
    {¶5}    Zara met with the Belcastros on several occasions to discuss the progress
    of the construction, work completed by the other contractors and change orders. The
    Richland County, Case No. 2021 CA 0039                                              3
    meetings became contentious and the relationship between the parties deteriorated. Zara
    and the Belcastros held each other responsible for delays and increased costs. Zara
    claimed that the project was delayed as a result of the use of multiple contractors and the
    Belcastros practice of reconsidering the plans in the midst of construction. The Belcastros
    delayed the installation of roofing while they considered a solar power system, but
    decided against that option due to the expense. Belcastros requested installation of floor
    drains in the garage, but Zara argued that they were not in the original plans and that a
    change order must be approved prior to their installation. Zara claimed that timbers
    installed by a third-party were not properly dried and caused delay in installation of
    drywall.
    {¶6}   The Belcastros were frustrated by their perception that they were misled
    about the cost of the home. They also considered Zara unresponsive to requests for
    information regarding change orders. Discussions regarding the direction of the project,
    arguments regarding what was required by the contract and the need for change orders
    grew heated during construction. The disagreements grew strident, and, in April 2019 the
    Belcastros issued a notice of termination.
    {¶7}   On April 2, 2019 the Belcastros delivered a letter to Zara claiming that Zara
    had defaulted and that the default must be cured within seven days. Zara did not respond
    and, on April 9, 2019 the Belcastros sent notice that the contract was terminated. Zara
    did no further work on the Belcastro home and the Belcastros completed the home with
    the help of other contractors.
    {¶8}   On May 6, 2019 Zara recorded an Affidavit of Lien stating that it had
    provided labor and materials for construction of the Belcastros’ home, that the last date
    Richland County, Case No. 2021 CA 0039                                                 4
    of work was April 9, 2019 and that Zara was owed $147,405.58 over and above all credits
    and set-offs. (Plaintiff’s Exhibit 4.) On June 20, 2019, Zara filed a second lien, identical
    to the first except for the following: “Zara Construction is currently owed the sum of
    $114,632.30 over and above all credits and set-offs for the work or materials described
    in Paragraph 2 above. This Amended Affidavit of Lien replaces the Affidavit of Lien filed
    with the County Recorder on May 6, 2019 for a different amount.” (Plaintiff’s Exhibit 5.)
    {¶9}    On July 23, 2019 Zara filed a complaint to foreclose the mechanic’s lien and
    included counts seeking compensation based upon theories of quantum meruit and unjust
    enrichment. On August 28, 2019, the Belcastros filed an answer and counterclaim
    containing    allegations   of    breach   of   contract,   slander   of   title,   breach   of
    bailment/conversion, unjust enrichment, negligence and a request for declaratory
    judgment. Zara filed its Reply to the counterclaim on September 12, 2019 and the matter
    was set for a jury trial.
    {¶10} The Belcastros moved for summary judgment on their claim that they were
    entitled to a declaratory judgment that Zara had violated the Home Construction Service
    Suppliers Act. (Counterclaim, Count II). The trial court granted that motion, found that
    Zara had committed several violations of the Act and ordered that damages would be
    determined at a hearing.         Zara also moved for summary judgment regarding the
    Belcastros’ claims for negligence and unjust enrichment, but that motion was denied.
    {¶11} The parties presented volumes of testimony and exhibits during a seven
    day jury trial, but Zara’s appeal involves a limited amount of the evidence that addressed
    the validity of the mechanic’s lien and whether the facts support a claim for quantum
    meruit or unjust enrichment.
    Richland County, Case No. 2021 CA 0039                                                  5
    MECHANIC’S LIEN
    {¶12} The dispute regarding the mechanic’s lien arose from Zara’s admission that
    the amount listed in the lien filed on May 6, 2019 was incorrect. Joseph Zara confirmed
    that “we put numbers from different things into that lien that shouldn't have been on there
    by accident.” (Trial Transcript, p. 72, lines 19-20). He confirmed that the correct amount
    of the lien was described in Exhibit 5, the amended lien, filed on June 20, 2019.
    {¶13} The parties also disputed the date of the last date of work toward completion
    of the Belcastro home. Joseph Zara’s affidavit listed the last day of work as April 9, 2019,
    though during the trial he could not recall “what is the last day we were on the job” in
    response to questions about working on the site. (Trial Transcript, p. 311, line 15). Zara
    did confirm that he was still working toward fulfilling the contract and finishing the home
    until termination on April 9, 2019. (Trial Transcript, p. 348, line 16 to p. 349, line 2).
    Stephen Marek, the project manager, confirmed that Zara was still soliciting contractor
    bids in furtherance of the project until April 9, 2019. (Trial Transcript, p. 479, lines 2-8).
    QUANTUM MERUIT/UNJUST ENRICHMENT
    {¶14} Zara claimed that it completed work prior to termination but had not received
    payment for those efforts. The Belcastros contended that no payment was due.
    {¶15} Payment for work completed was divided into four stages by the contract:
    “1/4 at Contract Initiation, 1/4 at Framing Dry In, 1/4 at Finished Drywall, 1/4 at Finish
    Final with Final Approved Inspection Occupancy Permit Issuance.” (Defendant’s Exhibit
    A, p. 1, paragraph two). The first two payments had been made and Zara was prepared
    to install the drywall when the Belcastros issued the notice of termination. Zara was
    Richland County, Case No. 2021 CA 0039                                              6
    prevented from completing the drywall, but had completed “things behind the walls” that
    must be finished before drywall is installed such as “electrical rough-in, plumbing rough-
    in, heating rough-in.” (Trial Transcript, p. 67, lines 1-9). An invoice for progress payment
    would have presumably included the charges for this work, but, because the Belcastros
    terminated the contract, the drywall was not installed and no invoice was issued. Zara
    was not paid for any of the work or materials completed after the second progress
    payment.
    {¶16} The Belcastros contended that because the contract was terminated prior
    to Zara completing the third benchmark for payment and issuing an invoice, they had no
    obligation to make payment to Zara pending completion of the home pursuant to
    paragraph 14(b) of the contract. The Belcastros did send the notices described in
    paragraph 14(b), first giving Zara notice that the Belcastros believed that Zara had
    defaulted and that they had seven days to cure the default and, when Zara did not
    respond to the letter, the Belcastros sent a second letter notifying them that the contract
    was terminated.    Relying on paragraph 14(b), the Belcastros then hired others to
    complete the home and, because they contend they paid out more than the unpaid
    balance owed to Zara under the written contract, they claimed that they were entitled to
    compensation.
    DIRECTED VERDICT
    {¶17} The Belcastros moved for a directed verdict regarding Zara’s claims at the
    close of Zara’s case, claiming that the lien was invalid as the amount was incorrect and
    no payment was due. They also claimed that Zara’s claim for quantum meruit or unjust
    enrichment must fail because paragraph 14(b) of the contract applied, and that recovery
    Richland County, Case No. 2021 CA 0039                                                7
    under the theories of quantum meruit or unjust enrichment is not available if an express
    contract provision applies.
    {¶18} The trial court granted the request for directed verdict. With regard to the
    mechanic’s lien, the trial court found that “the attestation that Plaintiff’s claims in the
    original affidavit were being brought "Pursuant to the contract" with the Defendant
    homeowners to be false, and the affidavit to be defective for that reason.” The trial court
    also found that “[p]laintiff’s attempt to amend its affidavit to state a revised amount due of
    $114,632.30 is prima facie evidence that affiant knowingly attested to an incorrect amount
    in its original affidavit, thus rendering it invalid,” and that Zara had failed to prove, by a
    preponderance of the evidence, that the last day of work was April 9, 2019. (Judgment
    Entry, p. 5, 6). With regard to the claim for unjust enrichment or quantum meruit, trial court
    found that paragraph 14(b) applied and that any amount due Zara would be calculated
    pursuant to that provision of the contract. The trial court concluded that because this
    express provision of the contract applied, Zara was prevented from pursuing a claim for
    unjust enrichment or quantum meruit.
    {¶19} The directed verdict disposed of Zara’s claims, but Belcastros counterclaim
    remained for the consideration of the jury. The Belcastros presented their case and, at
    the conclusion of the evidence, dismissed all but the slander of title and breach of contract
    claim. The jury was also asked to assess what damages, if any, the Belcastros suffered
    as a result of the violations of the HCSSA established prior to trial as a result of summary
    judgment.
    {¶20} The jury returned verdicts in favor of Zara on all counts, specifically finding
    in response to jury interrogatories that Zara did not breach the contract, that Zara did not
    Richland County, Case No. 2021 CA 0039                                             8
    commit slander of title and that the Belcastros were not entitled to damages for violation
    of the HCSSA.
    {¶21} Zara appealed and submitted two assignments of error:
    {¶22} “I. THE TRIAL COURT IMPROPERLY ENTERED A DIRECTED VERDICT
    IN FAVOR OF DEFENDANTS-APPELLEES SCOTT AND CHRISTINE BELCASTRO ON
    ZARA CONSTRUCTION'S FORECLOSURE ON A MECHANIC'S LIEN CLAIM.”
    {¶23} “II. THE TRIAL COURT IMPROPERLY GRANTED A DIRECTED VERDICT
    TO DEFENDANTS-APPELLEES SCOTT AND CHRISTINE BELCASTRO ON THE
    CLAIMS OF UNJUST ENRICHMENT AND QUANTUM MERUIT IN THE COMPLAINT
    OF PLAINTIFF-APPELLANT ZARA CONSTRUCTION INC.”
    STANDARD OF REVIEW
    {¶24} “A motion for directed verdict raises a question of law because it examines
    the materiality of the evidence, as opposed to the conclusions to be drawn from the
    evidence.” Ruta v. Breckenridge-Remy Co., 
    69 Ohio St.2d 66
    , 69, 
    430 N.E.2d 935
     (1982).
    Thus, we review a trial court's ruling on a motion for directed verdict de novo. Goodyear
    Tire & Rubber Co. v. Aetna Cas. & Sur. Co., 
    95 Ohio St.3d 512
    , 
    2002-Ohio-2842
    , 
    769 N.E.2d 835
    , ¶ 4.
    {¶25} Under Civ.R. 50(A)(4), a motion for directed verdict can only be granted
    when, having construed the evidence most strongly in favor of the nonmoving party, the
    court concludes that reasonable minds could only reach one conclusion upon the
    evidence submitted and that conclusion is adverse to the nonmoving party. Conversely,
    the motion must be denied when there is substantial competent evidence supporting the
    position of the nonmoving party and reasonable minds might reach different conclusions.
    Richland County, Case No. 2021 CA 0039                                               9
    Hawkins v. Ivy, 
    50 Ohio St.2d 114
    , 115, 
    363 N.E.2d 367
     (1977). “The ‘reasonable minds’
    test mandated by Civ.R. 50(A)(4) requires the court to discern only whether there exists
    evidence of substantive probative value that favors the position of the nonmoving party.”
    Goodyear Tire & Rubber Co. v. Aetna Cas. & Sur. Co., 
    95 Ohio St.3d 512
    , 2002-Ohio-
    2842, 
    769 N.E.2d 835
    , ¶ 3. The nonmoving party “is entitled to have the trial court
    construe the evidence in support of its claim as truthful, giving it its most favorable
    interpretation, as well as having the benefit of all reasonable inferences drawn from that
    evidence.” Gibson v. Drainage Prods., Inc., 
    95 Ohio St.3d 171
    , 
    2002-Ohio-2008
    , 
    766 N.E.2d 982
    , ¶ 21, quoting Ruta v. Breckenridge-Remy Co., 
    69 Ohio St.2d 66
    , 68, 
    430 N.E.2d 935
     (1982). Accord Hargrove v. Tanner, 
    66 Ohio App.3d 693
    , 695, 
    586 N.E.2d 141
     (9th Dist. 1990). However, neither the weight of the evidence or the credibility of the
    witnesses are matters for the court's consideration under Civ.R. 50(A). Wagner v. Roche
    Laboratories, 
    77 Ohio St.3d 116
    , 119, 
    671 N.E.2d 252
     (1996), quoting Ruta at 68-69, 
    430 N.E.2d 935
    .
    MECHANIC’S LIEN
    {¶26} In its first assignment of error, Zara contends that the trial court improperly
    entered a directed verdict in favor of the Belcastros on Zara’s claim for foreclosure on its
    mechanic's lien. The trial court granted the motion for directed verdict after finding that
    the mechanic’s lien was invalid for three reasons: Zara’s reference to the contract as the
    source of the lien was false; Zara’s attempt “to amend its affidavit to state a revised
    amount due of $114,632.30 is prima facie evidence that affiant knowingly attested to an
    incorrect amount in its original affidavit;” and Zara “failed to meet its burden of proof by
    Richland County, Case No. 2021 CA 0039                                                  10
    a preponderance of the evidence that the last day of work performed on the Belcastro
    home was April 9, 2019.” (Judgment Entry, pp. 5-6).
    1311.06 INTERPRETATION
    {¶27} Our analysis of this assignment of error begins with a review of the
    requirements of R.C. 1311.06. The relevant language of that section describes the
    required content of a mechanic’s lien and the deadline for filing it with the county recorder
    in the county in which the improved property is located:
    Any person, or the person's agent, who wishes to avail self (sic) of
    sections 1311.01 to 1311.22 of the Revised Code, shall make and file for
    record in the office of the county recorder in the counties in which the
    improved property is located, an affidavit showing the amount due over and
    above all legal setoffs, a description of the property to be charged with the
    lien, the name and address of the person to or for whom the labor or work
    was performed or material was furnished, the name of the owner, part
    owner, or lessee, if known, the name and address of the lien claimant, and
    the first and last dates that the lien claimant performed any labor or work or
    furnished any material to the improvement giving rise to the claimant's lien.
    ***
    The affidavit shall be filed within one of the following periods:
    If the lien arises in connection with a one- or two-family dwelling or
    in connection with a residential unit of condominium property as defined in
    Chapter 5311. of the Revised Code, within sixty days from the date on which
    Richland County, Case No. 2021 CA 0039                                                   11
    the last labor or work was performed or material was furnished by the
    person claiming the lien * * *
    {¶28} The matter before us involves a single family dwelling, so Zara was
    obligated to file an affidavit within sixty days from the last date on which it performed labor
    or work or furnished material.
    {¶29} Revised Code 1311.06, on its face, provides direct instruction regarding the
    content and filing of a valid mechanic’s lien. The relevant caselaw and Revised Code
    regarding whether strict or substantial compliance with R.C. 1311.06 is required to create
    a valid mechanic’s lien that attaches to the subject property is far less clear.
    {¶30} Revised Code 1311.22, captioned “Liberal Construction” states that
    substantial compliance with the elements of 1311.06 is sufficient for the validity of the
    lien:
    Sections 1311.01 to 1311.22 of the Revised Code are to be
    construed liberally to secure the beneficial results, intents, and purposes
    thereof; and a substantial compliance with those sections is sufficient for
    the validity of the liens under those sections, provided for and to give
    jurisdiction to the court to enforce the same.
    {¶31} A version of this statute has been in effect since 1917 as noted by Park v.
    Williamson Heater Co., 
    28 Ohio Dec. 141
    , 149 (Ohio Com.Pl.1917), aff'd, (1st Dist.
    Hamilton May 20, 1918):
    Section 8323-8 G. C. provides as follows:
    “This act is hereby declared to be a remedial statute and to be construed
    liberally to secure the beneficial result, intent, and purposes thereof; and a
    Richland County, Case No. 2021 CA 0039                                                    12
    substantial compliance with its several provisions shall be sufficient for the
    validity of the lien or liens hereinbefore provided for and to give jurisdiction
    to the court to enforce the same.”
    {¶32} Further suggesting a liberal application of R.C. 1311.06, Chapter 1311 has
    been deemed remedial: “The mechanics' lien statutes are remedial legislation, designed
    to protect the wage earner, furnisher of materials, and contractor whose work, goods, and
    skill create the structures to which the lien in part attaches.” Wayne Bldg. & Loan Co. of
    Wooster v. Yarborough, 
    11 Ohio St.2d 195
    , 217–18, 
    228 N.E.2d 841
     (1967).                       The
    legislature has acted to insure that remedial statutes are construed liberally:
    Remedial laws and all proceedings under them shall be liberally
    construed in order to promote their object and assist the parties in obtaining
    justice. The rule of the common law that statutes in derogation of the
    common law must be strictly construed has no application to remedial laws;
    but this section does not require a liberal construction of laws affecting
    personal liberty, relating to amercement, or of a penal nature.
    R.C. 1.11.
    {¶33} While this caselaw and Revised Code language suggests a liberal
    interpretation of R.C. 1311.06 where substantial compliance with the Code is sufficient to
    establish the validity of a mechanic’s lien, the Supreme Court of Ohio’s decisions mandate
    a different conclusion:
    Notwithstanding the statutory provision for liberal construction of the
    mechanics lien law the Supreme Court of Ohio held that these statutes were
    in derogation of common law and must be strictly construed with respect to
    Richland County, Case No. 2021 CA 0039                                                  13
    compliance with the statutory steps to obtain the lien and liberally construed
    after the lien attached. Robert V. Clapp Co. v. Fox, 
    124 Ohio St. 331
    , 
    178 N.E. 586
    ; C. C. Constance & Sons v. Lay, 
    122 Ohio St. 468
    , 
    172 N.E. 283
    .
    In Miller v. Kyle, 
    85 Ohio St. 186
    , 193, 
    97 N.E. 372
    , the Supreme Court, in
    construing the Negotiable Instruments Act, said ‘That statutes in derogation
    of the common law shall not by construction receive a meaning beyond that
    of the terms which they employ.’ Id. 195, 
    97 N.E. 373
    .”
    In re Summit Hardware, Inc., 
    302 F.2d 397
    , 401 (6th Cir.1962).
    {¶34} The strict construction requirement was reaffirmed the Supreme Court of
    Ohio in C.C. Constance & Sons v. Lay, 
    122 Ohio St. 468
    , 469, 
    172 N.E. 283
    , 283–84
    (1930) and Robert V. Clapp Co. v. Fox, 
    124 Ohio St. 331
    , 333–35, 
    178 N.E. 586
    , 587–
    88, 
    10 Ohio Law Abs. 701
     (1931) and it is regularly revisited, but still creates confusion:
    This issue has been repeatedly addressed by the Ohio Courts,
    however, the law is still a bit vague. The principal question that has plagued
    the courts is whether the mechanics lien statutes are to be treated as
    remedial and therefore are to be construed liberally, or whether they are to
    be strictly construed as being in derogation of the common law. (See
    discussion 36 Ohio Jurisprudence 2d Mechanics' Liens s 14.) The Supreme
    Court of Ohio indicates that neither of these broad rules is satisfactory, for
    the statutes must be strictly construed in some respects and liberally
    construed in others. Furthermore, this Court must follow the construction
    given by the Supreme Court of Ohio in determining the validity of the
    mechanic's lien in question.
    Richland County, Case No. 2021 CA 0039                                                  14
    In re Johnson, Inc., 
    19 B.R. 706
    , 707 (Bankr. N.D. Ohio 1982) on reconsideration,
    
    21 B.R. 90
     (Bankr. N.D. Ohio 1982).
    {¶35} Justice Herbert questioned the accuracy and applicability of the strict/liberal
    interpretation dichotomy in Gebhart v. United States, 
    172 Ohio St. 200
    , 212–15, 
    174 N.E.2d 615
    , 623–24 (1961):
    Although we agree with the decision in the Clapp case, we question
    the necessity of paragraph one of the syllabus in that case, which states:
    ‘Mechanics' lien statutes create rights in derogation of the *213
    common law and should therefore be strictly construed as to question (sic)
    whether a lien attaches, but their procedural and remedial provisions should
    be liberally construed, after the lien has been created.’
    The rule stated in 36 Ohio Jurisprudence (2d), 445 and 512, Sections
    14 and 68, seems to be taken from this paragraph of the syllabus in the
    Clapp case and yet it seems by its very statement to raise other questions.
    When does a lien attach and what remains to be construed liberally after
    the lien has been created? Although this distinction between strict and
    liberal construction seems to have come down over the years, the writer
    questions its accuracy and applicability today. It is never contended that
    Section 1311.14, Revised Code, the last sentence of which provides, ‘this
    section shall, as to mortgages contemplated by this section, control over all
    other sections of the Revised Code relating to said mechanic's,
    materialmen's, contractor's, subcontractor's, laborer's, and all liens that can
    be had under sections 1311.01 to 1311.68, inclusive, of the Revised Code,
    Richland County, Case No. 2021 CA 0039                                                   15
    and shall be liberally construed in favor of such mortgagees, a substantial
    compliance by such mortgagees being sufficient,’ is in derogation of the
    common law.
    {¶36} In 1993, the Supreme Court of Ohio reaffirmed the strict construction
    requirement without addressing Justice Herbert’s concerns:
    In Robert V. Clapp Co. v. Fox (1931), 
    124 Ohio St. 331
    , 
    178 N.E. 586
    , paragraph one of the syllabus, this court held: “Mechanics' lien statutes
    create rights in derogation of the common law and should therefore be
    strictly construed as to question whether a lien attaches, **1031 but their
    procedural and remedial provisions should be liberally construed, after the
    lien has been created.” See, also, C.C. Constance & Sons v. Lay (1930),
    
    122 Ohio St. 468
    , 469, 
    172 N.E. 283
    , 283 (The statutory steps to establish
    a mechanic's lien must be followed, “and in that respect the law is strictly
    construed and applied.”).
    Crock Constr. Co. v. Stanley Miller Const. Co., 
    66 Ohio St.3d 588
    , 592, 
    613 N.E.2d 1027
    , 1030–31 (1993).
    {¶37} The language compelling strict construction is clear, but the decision of the
    Sixth District Court of Appeals preserves uncertainty regarding application of the rule.
    The Sixth District reviewed several cases it characterized as applying a strict construction
    and others applying a liberal construction and held that an obvious error regarding the
    year the work was performed did not invalidate the affidavit:
    Here, appellant's affidavit set forth all of the information required by
    R.C. 1311.06, although there was a clerical error with the year that the work
    Richland County, Case No. 2021 CA 0039                                                16
    was performed. The affidavit was signed by appellant's president on
    February 10, 2012, and was filed on February 17, 2012, yet the dates when
    the work was first and last performed were set forth as May 6, 2012 and
    December 15, 2012. Clearly, the work could not have been performed and
    completed after the affidavit was signed and filed. There was no dispute
    about when the work was performed. Given that R.C. 1311.22 provides that
    substantial compliance with the mechanic's lien statutes is sufficient for a
    valid lien and it is evident that appellant's affidavit is in substantial
    compliance with the requirements of R.C. 1311.06, we find that appellant's
    mechanic's lien is valid.
    Burroughs Framing Specialists, Inc. v. 505 W. Main St., L.L.C., 6th Dist. No. OT-14-001,
    
    2014-Ohio-3961
    , 
    18 N.E.3d 1253
    , ¶ 31.
    {¶38} The Second District Court of Appeals found that Burroughs “directly
    conflicts with the decisions of this Court” and concluded that an error in the date that the
    last work was completed could not be corrected by a later affidavit. SRS Distrib., Inc. v.
    Axis All., LLC, 2nd Dist. No. 28607, 
    2020-Ohio-1529
    , 
    153 N.E.3d 953
    , appeal not allowed
    sub nom. SRS Distrib., Inc. v. Axis All., L.L.C., 
    159 Ohio St.3d 1476
    , 
    2020-Ohio-4045
    ,
    
    150 N.E.3d 967
    , ¶ 21-24.
    {¶39} The cases cited by Burroughs highlight confusion or recalcitrance regarding
    the application of a strict construction analysis of compliance with R.C. 1311.06 in the
    context of the precedent and Revised Code Sections that permit substantial compliance.
    Nevertheless, we are unable to ignore the mandate issued by the Supreme Court of Ohio
    Richland County, Case No. 2021 CA 0039                                                   17
    regarding strict construction of the requirements and will endeavor to restrict our analysis
    to the plain language of R.C. 1311.06 to determine the validity of Zara’s mechanic’s lien.
    AMOUNT OF LIEN
    {¶40} Zara Construction filed a lien with a specific amount and later filed what it
    described as an amended lien with a different, lower amount. The trial court found that
    “Plaintiffs attempt to amend its affidavit to state a revised amount due of $114,632.30 is
    prima facie evidence that affiant knowingly attested to an incorrect amount in its original
    affidavit, thus rendering it invalid.” In support of the trial court, the Belcastros cite to Busy
    Bee Restoration, Inc. v. A-A Blue Print Co. Summit C.P. No. CV 2013063056, 
    2014 Ohio Misc. LEXIS 24449
     but that case is factually distinguishable and the holding insufficiently
    broad to apply to this case. In Busy Bee, the lienholder attempted to file a lien “to secure
    payment for services that have not been rendered.” Busy Bee at *33. Because R.C.
    1311.06 permits liens only for “labor or work or furnished any material to the improvement
    giving rise to the claimant's lien” the lien in Busy Bee was invalid regardless of the amount,
    so that holding is not instructive.
    {¶41} Revised Code 1311.06 requires that a potential lien claimant make and file
    “an affidavit showing the amount due over and above all legal setoffs.” The statute
    contains no requirement that the amount be agreed upon by the parties, nor does it
    contain any instruction or limitations regarding how the amount may be calculated. A
    dispute over the amount due is not unexpected and may be a part of every case involving
    a mechanic’s lien, but we do not agree that dispute serves to invalidate the lien.
    {¶42} In Warne v. Bamfield, 5th Dist. Guernsey No. 2005-CA-33, 
    2006-Ohio-850
    ,
    ¶ 19, we found that a lien was still valid and sufficiently explicit when the lienholder “did
    Richland County, Case No. 2021 CA 0039                                              18
    not estimate the value of the credits and setoffs”. In that case, as in the case now before
    us, “[t]he value of the [appellant’s] work and [appellee’s] credits and setoffs” were in
    dispute. The amount described in the lien in Warne was higher than the amount admitted
    as due during trial. We acknowledge that the amounts involved in the case before us
    differs significantly from the amounts in Warne, but as the principals are the same, we
    find that we must reach the same conclusion in this case. Accord In re Qualstan Corp.,
    
    303 B.R. 149
    , 156–57 (“NCB cites to no authority which would invalidate a lien of
    asserting a smaller amount than what is actually owed. * * * This Court will not invalidate
    the lien of Conie or question its veracity because it stated a smaller amount.”); Regency
    Centre Dev. Co. v. Constr. Dimensions, Inc., 8th Dist. Cuyahoga No. 81171, 2003-Ohio-
    5067, ¶ 64 ( “That the amount of a lien is undetermined does not mean the lien is invalid,
    no more than the fact that the amount stated in an affidavit is in excess of the correct
    amount would render an affidavit invalid.”); Tucker Construction, Inc. v. Kitchen (March
    1, 1995), Summit App. No. 16636, *3 (“On the contrary, the Ohio Supreme Court has held
    that a mechanic's lien in an amount in excess of the actual amount due is not, for that
    reason, rendered invalid.”) Thompson Thrift Construction v. Lynn, 5th Dist. No. 16 CAE
    10 0044, 
    2017-Ohio-1530
    , 
    89 N.E.3d 249
    , ¶¶ 78-79 (“Courts have held that a lien is not
    invalidated if the stated amount is incorrect when the lienholder testifies to the amount of
    the lien.”); Thomas v. Huesman, 
    10 Ohio St. 152
    , 158–59 (1859) (“The fact of the amount
    claimed to remain due upon the account being stated at $951.05, when in fact there
    appears to have been only $891.53, very obviously can be no objection to the goodness
    of the account to secure a lien for the amount actually due. That the greater includes the
    less is a conclusive answer to this objection.”)
    Richland County, Case No. 2021 CA 0039                                               19
    {¶43} We find that Zara included an amount due in compliance with R. C. 1311.06
    and the fact that amount was later lowered by the sworn testimony of the lienholder does
    not serve to invalidate Zara’s lien.
    COMPUTATION OF AMOUNT DUE
    {¶44} The trial court attacks the computation of the amount due as well,
    contending that the statement in the affidavit that the amount was calculated per the
    contract was not true and that falsehood invalidates the affidavit.
    {¶45} As we have noted, the affidavit need only show the amount due over and
    above all legal set offs. Revised Code 1311.06 contains no requirement that the affiant
    describe how the amount was calculated and we find that the inclusion of such language
    is surplusage and does not serve to invalidate the lien. We acknowledge that this issue
    may have an impact on the calculation of the amount due, credits owed or other financial
    issues, but we do not agree that it will serve to invalidate the lien. Zara’s lien must arise
    from an express or implied contract, but R.C. 1311.06 does not require that Zara describe
    the source of the lien within the affidavit creating the lien.
    {¶46} The trial court limits its analysis of the source of the mechanic’s lien to the
    written contract, but Zara has claimed compensation under implied contracts through the
    theories of unjust enrichment and quantum meruit. We have held that “[a] subcontractor
    can file a mechanic's lien to secure payment for work or labor or material in furtherance
    of any improvement undertaken by virtue of a contract, express or implied. R.C. 1311.02.”
    Thompson Thrift Construction v. Lynn, 5th Dist. No. 16 CAE 10 0044, 
    2017-Ohio-1530
    ,
    
    89 N.E.3d 249
    , ¶ 65.
    Richland County, Case No. 2021 CA 0039                                                  20
    {¶47} Zara may rely on work performed pursuant to an express or implied contract
    to calculate its lien, and Chapter 1311 does not impose a requirement upon a lienholder
    to calculate a lien pursuant to the terms of a written contract to create a lien that satisfies
    the elements of R.C. 1311.06.
    {¶48} The trial court’s reliance upon the assertion that the claims were brought
    pursuant to the contract with the homeowners and its implication that the lien must be
    based upon labor and materials provided pursuant to a written, express contract is
    erroneous as the Revised Code contains no such requirement.
    LAST DAY OF WORK
    {¶49} Zara was obligated to state in its affidavit “the first and last dates that the
    lien claimant performed any labor or work or furnished any material to the improvement
    giving rise to the claimant's lien” and that affidavit must be recorded within sixty days of
    the last day the lien claimant performed work or furnished material to establish a valid
    lien. (R.C. 1311.06) Zara’s first affidavit states that the last date of work was April 9, 2019.
    The trial court found that “Plaintiff failed to meet its burden of proof by a preponderance
    of the evidence that the last day of work performed on the Belcastro home was April 9,
    2019.” (Judgment Entry, April 21, 2020, p. 6).
    {¶50} The trial court’s reference to a preponderance of the evidence “was an
    improper standard for the trial court to use because this requires a higher degree of proof
    and consideration of the weight of the evidence which is improper in addressing a motion
    for directed verdict.” (Citations omitted.) Lorenz v. Young, 5th Dist. Tuscarawas No. 2005
    AP 06 0046, 
    2005-Ohio-6190
    , ¶ 28. Instead, the trial court was required to construe the
    evidence most strongly in favor of Zara and, before granting a directed verdict, conclude
    Richland County, Case No. 2021 CA 0039                                                  21
    that reasonable minds could only reach one conclusion upon the evidence submitted and
    that conclusion was adverse to Zara.
    {¶51} The trial court contends that the last day of work was revealed by Stephen
    Marek who testified:
    Q. In fact, after that framing inspection, no other work was performed by
    Zara Construction. Correct?
    A. I think that's true.
    Q. Right. So Zara's last day of work was March 29th, 2019, when that
    framing inspection was completed. Right?
    A. That's probably true.
    Transcript, p. 455, lines 6-11.
    {¶52} However, Marek later testified on redirect that Zara was still working on the
    project on April 9, 2019:
    Q. So you indicated something about March 29th, 2019, the last day of work
    on site. Up until April 9th, 2019, or between that time frame, March 29, 2019,
    and April 9, 2019, do you have knowledge as to what Joe was doing in
    furtherance of the project from his office?
    A. Okay. Between -- I'm sorry. Give me the dates again.
    Q. March 29, 2019, and April 9, 2019. April 9th was the date of the
    termination letter.
    Q. Do you know what Zara was doing from his office in furtherance of trying
    to make progress on the project?
    Richland County, Case No. 2021 CA 0039                                                   22
    A. I think he was still looking for -- yeah, to continue on soliciting
    subcontractor bids, yeah.
    Q. Okay. So he was still -- was he still working in furtherance of the project?
    A. I believe so, yes.
    Trial Transcript, p. 478, line 18 to p. 479, line 8.
    {¶53} Joseph Zara also confirmed that he was working toward completion of the
    home until April 9, 2019:
    Q. That's all I wanted to ask you about that. Let's talk about these liens for
    a minute. Up until the time of April 9th, 2019, when you received the notice
    of termination, whether you were on site or off site, as a company, were you
    still working on the project?
    A. Yes. We worked on the site, but yes.
    Q. Okay. So, like, what kind of activities would you be doing between, like,
    the end of March and April 9th?
    A. Retrieval and searching for documents, paperwork that was being
    requested.
    Q. Would you be working with your subs to get them going?
    A. Yes.
    Q. Before you got this notice of termination, are you trying to continue to
    purchase material, serve the customer, coordinate with your subs?
    A. Yes, absolutely. We did not stop working towards fulfilling the contract
    and finishing that house until termination.
    Trial Transcript, p. 348, line 10 to p. 349, line 2.
    Richland County, Case No. 2021 CA 0039                                                 23
    {¶54} Revised Code 1311.06 contains no requirement that the labor or work in
    furtherance of the project occur at the construction site, but only that the affidavit contain
    the last date of work performed. We find that Zara satisfied that requirement and that the
    record contains evidence that April 9th was the last date work was performed in
    furtherance of the project sufficient to withstand the motion for directed verdict.
    {¶55} Finally, we note that the trial court included a finding in its judgment entry
    that creates confusion regarding its decision with regard to the last date of work
    requirement of R.C. 1311.06.       Though the trial court concluded that Zara failed to
    establish that April 9th was the last date of work by a preponderance of the evidence,
    earlier in the entry the trial court found that “the original mechanic's lien was timely filed,
    but is otherwise invalid and did not attach to the property* * * .” (Judgment Entry, April 21,
    2020, p. 4). The trial court’s conclusion that there was insufficient proof of the last date of
    work suggests that it found that the lien was not timely filed, but that ruling would conflict
    with its prior statement. Because we have found that the record contains sufficient
    evidence to establish that April 9th was the last day of work, at least in the context of a
    motion for directed verdict, this conflict is of no consequence to our decision but may play
    a role in any future analysis.
    {¶56} After a review of the record, we find sufficient evidence to support a
    conclusion that Zara’s first affidavit satisfied the requirements of R.C. 1311.06. The
    parties conceded that this affidavit was filed timely and the Belcastros do not contend that
    it failed to contain a description of the property to be charged with the lien; the name and
    address of the person to or for whom the labor or work was performed or material was
    furnished; the name of the owner, part owner, or lessee, if known; and the name and
    Richland County, Case No. 2021 CA 0039                                                  24
    address of the lien claimant. We find that the affidavit contained a valid statement of the
    amount due over and above all legal setoffs and that assertion was not invalidated by a
    failure to describe the underlying calculations that produced that number. Further, we
    find that the face of the affidavit does not show that it was filed outside the sixty-day
    statutory time period allowed for perfecting a mechanics lien and that the filing of an
    amended lien does not invalidate the initial lien as the first lien contains all of the required
    information.
    {¶57} We recognize that the material assertions of the affidavit are contested by
    the parties, but we find that the information presented by Zara at trial regarding the lien
    were sufficient to survive a motion for directed verdict attacking the validity of the lien.
    We find that “there is substantial competent evidence supporting the position of the
    nonmoving party and reasonable minds might reach different conclusions” so we find that
    the trial court’s grant of a directed verdict on this issue was in error. Hawkins v. Ivy, 
    50 Ohio St.2d 114
    , 115, 
    363 N.E.2d 367
     (1977).
    {¶58} Zara’s first assignment of error is well taken and granted.
    II.
    QUANTUM MERUIT/UNJUST ENRICHMENT
    {¶59} In its second assignment of error, Zara claims the trial court improperly
    granted a directed verdict the Belcastro on the claims of unjust enrichment and quantum
    meruit.
    {¶60} Unjust enrichment and quantum meruit are doctrines “derived from the
    natural law of equity” and share the same essential elements. Maghie & Savage, Inc. v.
    P.J. Dick, Inc., 10th Dist. No. 08AP–487, 
    2009-Ohio-2164
    , 
    2009 WL 1263965
    , ¶ 33. A
    Richland County, Case No. 2021 CA 0039                                               25
    party seeking relief under either doctrine must show: (1) a benefit conferred by a plaintiff
    upon a defendant; (2) knowledge by the defendant of the benefit; and (3) retention of the
    benefit by the defendant under circumstances where it would be unjust to do so without
    payment. A N Bros. Corp. v. Total Quality Logistics, L.L.C., 12th Dist. No. CA2015-02-
    021, 
    2016-Ohio-549
    , 
    59 N.E.3d 758
    , ¶ 42.
    {¶61} “The doctrines differ with respect to the calculation of damages—damages
    for unjust enrichment are ‘the amount the defendant benefited,’ while damages for
    quantum meruit are ‘the measure of the **1040 value of the plaintiff's services, less any
    damages suffered by the other party.’ U.S. Health Practices, Inc. v. Byron Blake, M.D.,
    Inc. (Mar. 22, 2001), 10th Dist. No. 00AP–1002, 
    2001 WL 277291
    .” Meyer v. Chieffo, 10th
    Dist. No. 10AP-683, 
    193 Ohio App.3d 51
    , 
    2011-Ohio-1670
    , 
    950 N.E.2d 1027
    , ¶ 37.
    {¶62} In the absence of fraud, illegality, or bad faith, however, a plaintiff may not
    recover in quantum meruit when an express contract governs the parties' obligations.
    Aultman Hosp. Ass'n v. Community Mut. Ins. Co., 
    46 Ohio St.3d 51
    , 55, 
    544 N.E.2d 920
    (1989). Likewise, when competent parties contract, and no fraud or illegality is involved,
    unjust enrichment cannot be claimed. Ullmann v. May, 
    147 Ohio St. 468
    , 476, 
    72 N.E.2d 63
     (1947). “The law does not recognize the coexistence of a quasi contract and an
    express contract covering the same subject.” Williams v. Goodyear Aircraft Corp., 
    84 Ohio App. 113
    , 117, 
    85 N.E.2d 601
    , 604 (9th Dist.1948).
    {¶63} The written contract between Zara and the Belcastros called for payments
    to be made “on the basis of an application for payment submitted to the order by the
    contractor as the work progresses.” (Defendants Exhibit A, contract, page 1, paragraph
    three). The contract provided that those payments were to be made as follows “1/4 at
    Richland County, Case No. 2021 CA 0039                                              26
    Contract Initiation, 1/4 at Framing Dry In, 1/4 at Finished Drywall, ¼ at Finish Final with
    Final Approved Inspection Occupancy Permit Issuance.” (Id. at page 1, paragraph two).
    In the case before us, it is uncontested that the second progress payment had been made
    in response to an application by Zara and that Zara had begun work for the next stage of
    construction. Prior to completion the relationship between the parties degenerated to the
    point that the Belcastros decided to terminate the contract pursuant to paragraph 14(b)
    of the contract. The Belcastros delivered a notice of termination to Zara and, shortly
    thereafter, Zara ceased all work on the project.
    {¶64} Zara claims it provided materials and labor toward the completion of the
    project after the second progress payment for which it has not been paid. Zara claims it
    pursued an action under quantum meruit or unjust enrichment because the written
    contract terms do not address how the contractor may recover payment for work done in
    between progress payments when the owner terminates the contract. The Belcastros did
    not contend the work was not completed, but only that no payment was owed as the
    written contract provides a solution.
    {¶65} The trial court granted a directed verdict to the Belcastros on this claim
    based upon its reading of paragraph 14(b) of the contract. The trial court claimed that
    provision was unambiguous and provided a solution to the current factual situation. That
    section states:
    Owner's Termination. The owner may, on one week's notice to the
    contractor terminate this contract before the termination date hereof, and
    without prejudice to any other remedy he may have, when the contractor
    defaults in performance of any provision herein, or fails to carry out the
    Richland County, Case No. 2021 CA 0039                                                  27
    construction in accordance with the provisions of the contract documents.
    On such termination the owner may take possession of the worksite and all
    materials, equipment, tools, and machinery thereon, and finish the work in
    whatever way he deems expedient. lithe unpaid balance of the contract sum
    at the time of such termination exceeds the expense of finishing the work,
    the owner will pay such excess to the contractor. If the expenses of finishing
    the work exceeds the unpaid balance at the time of termination the
    contractor agrees to pay the difference to the owner. On such default by the
    contractor, the owner may elect not to terminate the contract, and in such
    event he may make good the deficiency in which the default consists, and
    deduct the costs from the progress payment due to the contactor.
    {¶66} The trial court’s analysis of the issue concludes with the following:
    In order to avail itself of the quantum meruit and/or unjust enrichment
    theories of recovery Plaintiff attempts to argue that the express contract that
    Plaintiff drafted is silent on what should happen when the contract is
    terminated by the owner between two payment milestones. The Court finds
    this theory of relief disingenuous, as paragraph 14 of the contract expressly
    provides the means to calculate a fair payment under just such a scenario.
    Also important to the court's decision is the long accepted tenet in
    contract interpretation that, if there are ambiguities in a contract, the
    document will be strictly construed against the party who drafted it or
    selected its language. Plaintiff Zara Construction, Inc. drafted the contract
    in dispute in this matter. If Plaintiff finds the contract ambiguous as to the
    Richland County, Case No. 2021 CA 0039                                               28
    correct procedure for calculating damages where the owner terminated the
    contract between payment milestones, it has no one but itself to blame. The
    Court finds no such ambiguity.
    {¶67} While the trial court does not specifically cite section (b) of paragraph
    fourteen of the contract, that is the only section that describes the consequences of a
    contract terminated by the owner.
    {¶68} Paragraph 14(b) applies to circumstances where the “contractor defaults in
    the performance of any provision herein, or fails to carry out construction in accordance
    with the provisions of the contract documents.” The plain language of paragraph 14(b)
    requires proof of the delivery of the requisite notice and a finding that Zara defaulted
    before the Belcastros could successfully terminate the contract and complete
    construction.
    {¶69} The trial court did not find that Zara was in default or that it breached any
    part of the contract before it issued a directed verdict. Instead, the Belcastros’ allegation
    that Zara breached the contract was presented to the jury. The jury returned a verdict in
    favor of Zara finding that it had not breached the contract. These facts lead us to the
    conclusion that the trial court’s holding that paragraph 14(b) of the contract addressed the
    circumstances presented to it was error, because the record contains no finding that Zara
    defaulted, an unambiguous requirement of that section of the contract. Further, we hold
    that the record contains sufficient evidence to present a question to the jury regarding
    whether Zara was entitled to damages under a theory of either unjust enrichment or
    quantum meruit as it is uncontested that Zara provided labor and materials after the third
    Richland County, Case No. 2021 CA 0039                                              29
    payment for which it has not received payment and the contract contains no express or
    implied provision addressing compensation for those services or materials.
    {¶70} Zara’s second assignment of error is well taken and granted.
    {¶71} The decision of the Richland County Court of Common Pleas is reversed
    and this matter is remanded to the trial court for further proceedings consistent with this
    opinion.
    By: Baldwin, J.
    Gwin, P.J. and
    Delaney, J. concur.