Hale Container Line, Inc. v. Houston Sea Packing Co. , 137 F.3d 1455 ( 1998 )


Menu:
  •                               United States Court of Appeals,
    Eleventh Circuit.
    Nos. 95-3201, 95-3296.
    HALE CONTAINER LINE, INC., Plaintiff-Counter-Defendant-Cross-Claimant-Appellee,
    Societe Guyanaise De Conseils Immobilers (SOGUCI), Plaintiff-Appellant,
    v.
    HOUSTON SEA PACKING CO., INC., Defendant-Cross-Defendant-Counterclaimant-
    Appellant,
    Meridian Ship Incorporated, Defendant-Cross-Defendant,
    Fabricated Products of Tampa, Inc., Defendant-Cross-Defendant-Cross Claimant,
    D&D Welding Fabrication, Defendant-Cross-Defendant-Cross Claimant,
    Project Logistics and Transportation, Inc., Tug "ALEXANDRA HALE" in rem, Barge
    "LIBERTY TRADER" in rem, Defendants-Appellees,
    National Cargo Bureau, Defendant-Cross-Claimant-Cross-Defendant,
    London Offshore Consultants, Inc., Defendant-Cross-Defendant.
    Hale Container Line, Inc., Plaintiff-Counterdefendant-Cross-Claimant,
    Societe Guyanaise De Conseils Immobilers (SOGUCI), Plaintiff-Appellee,
    v.
    Houston Sea Packing Co., Inc., Defendant-Cross-Defendant-Counterclaimant-Appellant,
    Meridian Ship Incorporated, Defendant-Cross-Defendant,
    Fabricated Products of Tampa, Inc., Defendant-Cross-Defendant-Cross-Claimant,
    D&D Welding Fabrication, Defendant-Cross-Defendant-Cross Claimant,
    Project Logistics and Transportation, Inc., Tug "ALEXANDRA HALE" in rem, Barge
    "LIBERTY TRADER" in rem, Defendants,
    National Cargo Bureau, Defendant-Cross-Claimant-Cross-Defendant,
    London Offshore Consultants, Inc., Defendant-Cross-Defendant.
    April 3, 1998.
    Appeals from the United States District Court for the Middle District of Florida. (No. 90-216-CIV-
    T-21A), Ralph W. Nimmons, Jr., Judge.
    Before HATCHETT, Chief Judge, BIRCH, Circuit Judge, and CLARK, Senior Circuit Judge.
    CLARK, Senior Circuit Judge:
    Defendant Houston Sea Packing Co., Inc. ("Houston") appeals the district court's judgments
    against it in favor of plaintiffs Hale Container Line, Inc. ("Hale") and Societe Guayanaise De
    Conseils Immobiliers ("SOGUCI"). SOGUCI cross-appeals from the judgment against it in favor
    of Hale, the National Cargo Bureau ("NCB"), and the Alexander Hale and Liberty Trader in rem,
    and the amount of damages it was awarded against Hale.
    I. BACKGROUND
    In July 1989, Jean Pierre Porry, a representative of SOGUCI, contracted with Project
    Logistics and Transportation, Inc. ("Project Logistics") to arrange for the transport of 210 mobile
    homes from Tampa, Florida, to French Guyana.1 A Project Logistics representative contacted Craig
    Firing of Meridian Shipping Inc. ("Meridian"), a shipping agency. Firing contacted Don Jones, the
    owner of Houston concerning the transportation of the mobile homes and the construction of a
    stanchion assembly to hold the homes during shipment.2 Jones gathered information to determine
    1
    SOGUCI had previously contracted with the European Space Agency to provide housing for
    workers constructing the Space Center in French Guyana. SOGUCI contracted with Florida
    Mercury to purchase the mobile homes from Fleetwood Homes. One of SOGUCI's principles,
    Michel Porry, asked his brother and maritime specialist Jean Pierre Porry to make the
    arrangements for the transportation of the mobile homes to French Guyana.
    2
    R2-99 at 3; R11-9, 11, 13-14.
    2
    the method and costs of transporting the homes, and contacted London Offshore, a marine surveying
    company that approved vessels for hauling cargo, to assist him. On July 31, 1989, Meridian and
    Houston entered into a "Conlinebooking" Liner Booking Note3 with Project Logistics for the
    shipment of 210 mobile homes on two voyages. The Booking Note named the "carrier" as
    "Meridian Ship/Houston Sea-Pack," the "merchant" or "shipper" as "Project Logistics and
    Transportation, Inc.," and the "vessel" as "Tug Barge(s) TBN." On August 4, 1989, Project Logistics
    and Florida Mercury Export, Inc.,4 as SOGUCI's representative, executed a Booking Note which
    named the "carrier" as "Project Logistics," the "merchant" or "shipper" as "Florida Mercury," and
    the "vessels" as "Tug: "Carol Hale' Barge: "Liberty Trader.' " Both booking notes gave the time
    for shipment as "September 1989."
    Houston contacted design engineer Arthur Tertyshny of Design Research for stress analysis
    of the stanchion system. Tertyshny provided drawings and calculations pertaining to a system
    containing three tiers of mobile homes.
    3
    In admiralty, a "liner" is a cargo operation that sails along fixed routes on a preannounced
    schedule. Grant Gilmore & Charles L. Black, Jr., The Law of Admiralty 13 (2nd ed.1975). A
    shipper reserves or "books" space on a liner for the cargo. Id.
    4
    Florida Mercury Export, Inc. was a U.S. corporation set up by Jacques Gallet, a Porry
    relative, to provide for the payment of the mobile homes and ocean freight in U.S. currency.
    3
    On August 28, 1989, Hale, as "Owner," and Houston, as "Charterer," executed a Time
    Charter5 in which Hale chartered the tug "Alexandra Hale" and barge "Liberty Trader" to Houston.
    The Time Charter provided for payment as follows:
    CHARTER HIRE PAYABLE: $100,000 wired to Owner's bank prior to departure from
    Baltimore. $150,000 wired to Owner's bank no later than 72 hours after departure from
    Tampa to South America on first and any successive trips, adjusted to projected charter hire
    to be earned.6
    The Time Charter provided:
    4. PAYMENT AND DEFAULT: In the event Charterer shall fail to pay hire or other money
    due hereunder, promptly on the date thereof, or fail to comply with any of the terms,
    provisions or conditions hereof, ... Owner shall have the option of terminating this agreement
    and Charterer shall forthwith surrender possession of said vessel to Charterer; ... and
    Charterer shall continue to remain liable for all sums then due hereunder, as well as for any
    and all other damages suffered by Owner.7
    * * * * * *
    12. LIENS: ... Owner shall have a lien on all cargoes and subfreights for all charter
    payments and general averages.8
    * * * * * *
    16. Owner and Charterer acknowledge that Charterer plans to add stanchions to the
    Liberty Trader. In consideration thereof, Charterer shall be fully responsible for, and fully
    indemnify Owner for, all claims, liability, costs, or expenses of any kinds, including attorney
    5
    "A time charter is a contract of affreightment to use a ship in order to ship goods for a
    specific period of time. The carrier makes the ship's capacity available to the time charterer for
    this purpose. The charterer bears the expenses connected with each voyage and pays hire to the
    carrier based upon the time the ship is under charter." Thomas J. Schoenbaum, 2 Admiralty and
    Maritime Law § 11-5 (2nd ed.1994). An "affreightment" is a contract with a ship-owner to hire a
    ship, or part of it, for the carriage of goods, and is generally in the form of either a charter-party
    or a bill of lading. Black's Law Dictionary 60 (6th ed.1990).
    6
    Pltf. Hale Trial Exh. 48 at 1.
    7
    Pltf. Hale Trial Exh. 48 at 3 ¶ 4.
    8
    Pltf. Hale Trial Exh. 48 at 4 ¶ 12.
    4
    fees, arising in any way or degree from addition of stanchions by Charterer to the Liberty
    Trader....9
    The Alexandra Hale and Liberty Trader arrived in Tampa, Florida on September 6, 1989.
    Pursuant to the Time Charter, Houston arranged for an inspection and survey of both vessels.
    Houston discovered that the Liberty Trader had a breakwater on the bow that would displace five
    mobile homes on the bottom bow tier. Houston then decided to construct a fourth tier at the aft end
    of the barge to accommodate the displaced mobile homes.10
    Pursuant to the Booking Note entered into between Houston and Project Logistics, Project
    Logistics was responsible for providing stevedoring services for the loading of the mobile homes
    onto the barge, securing and lashing the homes onto the stanchion system, and insuring that the nuts
    and bolts were securely fastened and tightened.11
    On September 18, 1989, James McElroy, Project Logistics representative, and Harry C.
    Anderson, Master of the M/V Alexandra Hale, executed a Liner Bill of Lading12 in Tampa, Florida,
    9
    Pltf. Hale Trial Exh. 48 at 6 ¶ 16; Deft. Houston Trial Exh. 1 at 6 ¶ 16.
    10
    Although Jones testified that he discussed this with Bill Lowe of London Offshore and
    engineer Tertyshny, Tertyshny stated that the decision to place the fourth tier was made "after he
    was out of it," and that if questioned about the possibility of adding a fourth tier, he would have
    changed his stress calculations.
    11
    The stanchions were built by, obtained from, delivered by, and pre-assembled by Fabricated
    Products of Tampa ("Fabricated Products"). The stanchions were welded to the barge by
    Fabricated Products, D & D Welding Fabrication, and a third night crew. Project Logistics
    employed Metro Stevedores to load and discharge the mobile homes from the barge, bolt, secure
    and lash the mobile homes to the stanchion system, and insure that the nuts and bolts were
    securely fastened and tightened; and employed other stevedores to discharge the mobile homes
    in French Guyana.
    12
    A Bill of Lading is a "document which is signed by the carrier or his agent acknowledging
    that goods have been shipped on board a specific vessel that is bound for a particular destination
    and stating the terms on which the goods are to be carried.... Each shipping line generally has its
    own form of bill of lading." 2 Schoenbaum, § 10-11 at 44 (2nd ed.1994).
    5
    and Meridian, as agent, executed a Liner Bill of Lading in Baltimore, Maryland, for the first
    shipment of the mobile homes. Each Bill of Lading contained a General Paramount Clause,
    providing that the Carriage of Goods by Sea Act applied, and included a list of terms and conditions,
    including:
    5. The Scope of the Voyage.
    As the vessel is engaged in liner service the intended voyage shall not be limited to the direct
    route but shall be deemed to include any proceeding or returning to or stopping or slowing
    down at or off any ports or places for any reasonable purpose connected with service
    including maintenance of vessel and crew.
    * * * * * *
    9. Live Animals and Deck Cargo shall be carried subject to the Hague Rules ... with the
    exception that notwithstanding anything contained in Clause 19 the Carrier shall not be
    liable for any loss or damage resulting from any act, neglect or default of his servants in the
    management of such animals and deck cargo.
    * * * * * *
    13. Delay.
    The Carrier shall not be responsible for any loss sustained by the Merchant through delay
    of the goods unless caused by the Carrier's personal gross negligence....13
    The first shipment of homes departed on board the barge from Tampa on September 23,
    1989. However, after the vessels departed, the Tug began experiencing engine problems and had
    to return to Tampa for repairs. After the repairs were completed, the vessels again left Tampa.
    While en route to French Guyana, the Tug put into a port in Puerto Rico because one of its crew
    became ill, and later put into Martinique because of more engine problems. The Tug arrived in
    French Guyana on October 13, 1989. Upon arrival, it was noted that the stanchions and supports
    13
    Hale Trial Exhibits 49 and 85 at 2.
    6
    for the fourth tier of the last row of mobile homes had started to bend, causing some of the mobile
    homes to shift and sustain minor damage. Jones testified that the damage to the mobile homes was
    caused by shifting due to the bolts not being properly tightened by the stevedores or caused while
    the stevedores were unloading the homes. SOGUCI'S insurance underwriters' surveyor, Christian
    Renaux, reported that the damage was caused by the improper modification of the stanchion system,
    a failure to properly tighten the connecting bolts, and inadequate bracing of the structure due to
    welding of stanchions on the deck instead of plates on the deck. Renaux advised that the deformed
    stanchions should be replaced, and the mobile homes should be transported on only three levels.
    One of SOGUCI's owners, Michael Porry, testified that five mobile homes were damaged as a result
    of the first voyage, and were repaired quickly. Jean-Pierre Porry, another SOGUCI owner, testified
    that he never objected to the transport of the mobile homes in four, rather than three, tiers.
    A dispute arose between Houston and Hale concerning the amount of charter hire and other
    charges due arising from the first voyage.14
    Based on the insistence of its insurers, SOGUCI notified Houston and Project Logistics that
    it would require a survey of the vessels before departure on the second voyage. Houston
    subsequently hired NCB as surveyor to assure that the mobile homes were properly secured prior
    to the sailing of the vessels.15 NCB first viewed the barge when it was two-thirds loaded and
    14
    Although Houston had paid the $100,000.00 due according to the Time Charter prior to the
    departure of the tug and barge from Baltimore, Maryland, and had transferred $150,000.00 to
    Hale three days after the commencement of the first voyage, no further amounts had been paid.
    Hale claimed it was owed $129,405.05 upon the completion of the first voyage, but Houston
    disputed the amount. The parties agreed to compromise for $99,605.58.
    15
    Although NCB was initially asked to do a "trip and tow" survey as to the seaworthiness of
    the tug and the adequacy of the tug's towing gear, they declined to do so.
    7
    examined the tightness of the nuts and bolts and the securing of the lashing. NCB marine surveyor
    Arthur Evans Collins stated that, if the nuts and bolts were not tightened to the stanchion system,
    the system "would eventually work loose" causing possible damage to the mobile homes and
    bending to the system. NCB's surveyors examined the nuts, bolts, and lashing on the first tier
    physically, and on the other tiers visually. Their examination on the first tier revealed that some of
    the nuts and bolts were extremely loose. Their examination of the other tiers did not reveal whether
    or not the nuts were properly torqued, which would permit the nuts to back off the bolt. NCB's
    surveyors were not notified that the sailing of the barge was conditioned on the issuance of a trip and
    tow survey ordered by SOGUCI, and were not notified of Renaux's recommendations for the second
    voyage.
    On November 13, 1989, Project Logistics advised Houston that the stevedores had completed
    the loading, lashing, and securing of the mobile homes on the barge. Houston then advised Project
    Logistics that some of the nuts and bolts were loose. However, later that day, after the crew had
    rectified the loose nuts and bolts, NCB issued its document stating that all of the mobile home cargo
    was properly secured. The NCB document was accepted by SOGUCI and the vessels were
    permitted to sail.
    Houston was to receive payment from Project Logistics after the bill of lading was issued
    for the cargo. After the vessels sailed, Project Logistics refused to pay Houston the freight,
    demurrage and other charges due to it. On November 20, 1989, Houston required that SOGUCI
    make payment in the amount of $456,250.00. When SOGUCI did not pay, Houston instructed Hale
    8
    to return the tug and barge to the nearest U.S. port. Hale ignored Houston's instructions, unilaterally
    canceled the time charter, and entered into a separate agreement with Project Logistics.16
    On November 25, 1989, while the mobile homes were under the care, custody, and control
    of Hale and/or Project Logistics en route to French Guyana, the mobile homes on the fourth tier of
    the last row shifted. At Hale's instruction, the captain took the barge into Martinique. The shifting
    of the stanchions caused one mobile home to drop down on the mobile home below it, and to
    puncture a small hole in the roof. There was no other movement or damage to the mobile homes in
    the other rows. As a result of a dispute between Hale and SOGUCI concerning the manner in which
    the mobile homes would be transported to French Guyana, SOGUCI instituted legal proceedings
    against the vessels in Martinique. The vessels were held under arrest in Martinique from December
    8 until December 29, 1989. Fifteen mobile homes were off loaded and shipped to French Guyana
    on another vessel, and the vessels then sailed with the remaining mobile homes. The mobile homes
    arrived in French Guyana in January 1990, and were again inspected by Renaux. Renaux testified
    that all of the mobile homes sustained damage because the steel structures were loose and the
    stanchions were bent, and he observed many loose bolts after both voyages.
    In February 1990, Hale filed this complaint in admiralty against Houston, seeking its unpaid
    charter hire, fuel and lube oil expenses, indemnification for any sums due to the cargo claimant from
    SOGUCI's pending action in Martinique, payment for the $70,895.38 of expenses incurred during
    the emergency call at Fort de France, Martinique, and for lost profits in the amount of $100,000.00.
    16
    After the second voyage commenced, Hale advised Houston that it required payment of all
    sums due by November 16, 1989. Hale also advised Houston that if it failed to make timely
    payments, Hale intended to exercise its rights under the Time Charter and maritime law to
    withdraw the vessels from service and to lien subfreights.
    9
    It also sought indemnification for any sums due to the cargo claimant from the action pending in
    Martinique, damages for detention, loss of profit, port charges, pilotage, and stevedoring costs from
    Meridian, NCB, D & D Welding, and Fabricated Products. Houston counterclaimed against Hale
    for damages from Hale's breach of the charter agreement. NCB cross-claimed against Houston,
    Meridian, D & D Welding, and Fabricated Products for indemnification or contribution on the
    claims brought by Hale, and against Houston for breach of contract to recover its unpaid surveying
    fees. SOGUCI subsequently filed a complaint for $700,000.00 in damages to the shipment of
    mobile homes against Houston, NCB, London Offshore, Hale, and Project Logistics.17
    The case proceeded to a non-jury trial.18 Following the submission of post-trial briefs, the
    district court entered judgment for NCB, Hale, and the Alexandra Hale and Liberty Trader on
    SOGUCI's claims against them. It ruled against Hale on its claims against NCB and Houston for
    indemnity and contribution. It entered judgment for Hale against Houston on its charter party claim
    for $378,325.03 with interest, and "on each of Houston's claims against Hale." It entered judgment
    against NCB on its breach of contract claim against Houston. After Houston and SOGUCI
    submitted a stipulation as to the exchange rate, the district court granted judgment for SOGUCI on
    its claims against Houston for $337,049.52 with interest. Houston appealed, and SOGUCI
    17
    By stipulation, SOGUCI's action against London Offshore was dismissed.
    18
    Meridian was in Chapter 7 bankruptcy, and the case proceeded without its participation.
    Project logistics never entered an appearance and, based on the parties' tacit agreement that the
    case proceed to trial in the absence of Project Logistics, without any effort to default Project
    logistics, the district court found Project Logistics effectively dismissed. D & D Welding was
    dismissed as a party at the commencement of the trial, and summary judgment was granted
    against Hale on its claim against Fabricated Products. Hale and NCB's cross-claims against
    London Offshore were stricken, and NCB's cross-claims against Fabricated Products and D & D
    Welding were dismissed.
    10
    cross-appealed. Houston and SOGUCI timely filed appeals from the district court's judgment on all
    claims except SOGUCI's against Houston, our case no. 95-3201. After the district court entered
    judgment for SOGUCI against Houston, Houston and SOGUCI filed timely appeals, our case no.
    95-3296.
    II. DISCUSSION
    A. "Carriers" under COGSA
    Houston argues that the district court erred in finding that it was not a "carrier" or
    independent contractor of the carrier, Project Logistics, and thus entitled to the limitations under the
    Carriage of Goods by Sea Act ("COGSA").19 SOGUCI maintains that the district court erred in
    finding the vessels, in rem, "carriers" under COGSA.
    Under COGSA,20 "the carrier in relation to the loading, handling, stowage, carriage, custody,
    care, and discharge" of goods by sea is subjected to certain duties and entitled to certain rights.21
    The statute defines a carrier as "the owner or charterer who enters into a contract of carriage with
    a shipper."22 An owner may be a "carrier" either directly as the signor of a contract of carriage,
    indirectly by a charterer's authority to bind the owner by signing bills of lading as "for the master,"23
    19
    
    46 U.S.C. § 1300
     et seq.
    20
    
    46 U.S.C. §§ 1300-1315
    .
    21
    
    46 U.S.C. § 1302
    .
    22
    
    46 U.S.C. § 1301
    (a).
    23
    Matter of Intercontinental Properties Management, S.A., 
    604 F.2d 254
    , 258 n. 3 (4th
    Cir.1979); EAC Timberlane v. Pisces, Ltd., 
    745 F.2d 715
    , 719 (1st Cir.1984); Pacific
    Employers Insurance Company v. M/V Gloria, 
    767 F.2d 229
    , 235-236 (5th Cir.1985); J. Gerber
    & Co., Inc. v. M/V Inagua Tania, 
    828 F.Supp. 458
    , 460-461 (S.D.Tex.1992) (absent bills of
    lading showing contractual relationship between owner and shipper and evidence that the
    charterer had actual or apparent authority to bind the owner, owner is not a "carrier" subject to
    11
    or otherwise has some privity of contract with the shipper.24 A charterer may be a "carrier" as
    established by the vessel's charter, its acts of accepting and loading goods into containers owned by
    the charterer, and issuance of the bill of lading.25 More than one party may be a carrier, and where
    the owner has not completely relinquished possession, command and navigation of the ship to the
    charterer, both the owner and charterer may be held jointly liable.26 A vessel is a "carrier," and thus
    liable under COGSA, where (1) the ship transported and discharged the cargo; (2) the bill of lading
    was issued "for the master;" (3) no contractual relationship existed which absolved the ship and its
    owner from liability for the cargo.27 The COGSA defenses and protections may be extended to the
    carrier's agents and contractors by an express provision, a "Himalaya clause," in the bill of lading.28
    liability); Otto Wolff Handelsgesellschaft v. Sheridan Transportation Company, 
    800 F.Supp. 1359
    , 1362-1363 (E.D.Va.1992).
    24
    EAC Timberlane, 745 F.2d at 719.
    25
    Yeramex International v. S.S. Tendo, 
    595 F.2d 943
    , 946-947 (4th Cir.1979); Demsey &
    Associates v. Steamship Sea Star, 
    461 F.2d 1009
    , 1014 (2nd Cir.1972); Joo Seng Hong Kong
    Co., Ltd. v. S.S. Unibulkfir, 
    483 F.Supp. 43
    , 45-47 (S.D.N.Y.1979); Trans-Amazonica Iquitos,
    S.A. v. Georgia S.S. Co., 
    335 F.Supp. 935
    , 937-938 (S.D.Ga.1971).
    26
    Trans-Amazonica Iquitos, S.A., 335 F.Supp. at 940-941 (S.D.Ga.1971); J. Gerber & Co.,
    
    828 F.Supp. at 460
    .
    27
    Industria Nacional Del Papel, CA. v. M/V "Albert F,", 
    730 F.2d 622
    , 624 (11th Cir.), cert.
    denied, 
    469 U.S. 1037
    , 
    105 S.Ct. 515
    , 
    83 L.Ed.2d 404
     (1984); Compagnie De Navigation
    Fraissinet & Cyprien Fabre, S.A. v. Mondial United Corporation, 
    316 F.2d 163
    , 172-173 (5th
    Cir.1963); Otto Wolff Handelsgesellschaft, 
    800 F.Supp. at 1362-1363
    .
    28
    Certain Underwriters at Lloyds' v. Barber Blue Sea Line, 
    675 F.2d 266
    , 269 (11th
    Cir.1982); Generali v. D'Amico, 
    766 F.2d 485
    , 487-488 (11th Cir.1985); Taisho Marine & Fire
    Insurance Co., Ltd. v. Vessel "Gladiolus", 
    762 F.2d 1364
    , 1367 (9th Cir.1985) (whether an entity
    is the intended beneficiary of a Himalaya clause is determined by the contractual relationship
    between the entity and the carrier, and the natures of services performed compared with the
    carrier's responsibilities); Agrico Chemical Company v. S/S Atlantic Forest, 
    620 F.2d 487
    , 489
    n. 1 (5th Cir.1980); Almacen Boyaca CIA, LTDA v. Gran Golfo Express, 
    771 F.Supp. 354
    , 356
    (S.D.Fla.1991); Agrico Chemical Co. v. SS Atlantic Forest, 
    459 F.Supp. 638
    , 647
    12
    In considering the COGSA limitation of liability, this court construes Himalaya clauses
    strictly limiting their application to the intended beneficiaries.29 The clause must express the
    understanding of the contracting parties through language expressing a clear intent to extend the
    benefits to a well-defined class of readily identifiable persons.30 A reference to a class of persons
    such as "agents" and "independent contractors" clearly indicates that the contract includes all
    persons engaged by the carrier to perform the functions and duties of the carrier within the scope
    of the carriage contract, and no further clarity, such as enumeration of the parties, is necessary.31
    To determine whether a party is an independent contractor referenced in a Himalaya clause, a court
    should (1) compare the nature of the services provided by the party with the carrier's responsibilities
    under the bill of lading or contract of carriage,32 and (2) consider whether the independent
    contractor's duty had been fulfilled at the time when the liability was incurred.33 Further, a
    contractor will be entitled to the benefits of a Himalaya clause where there is a manifest consent by
    the carrier that the contractor shall act on its behalf and subject to its control, and consent by the
    contractor to so act.34
    (E.D.La.1978)(carrier may not insulate itself from liability by use of independent contractors).
    29
    Certain Underwriters at Lloyds', 675 F.2d at 268.
    30
    Id. at 269-270.
    31
    Id.
    32
    Taisho Marine & Fire Insurance Co., 762 F.2d at 1367.
    33
    Hiram Walker & Sons, Inc. v. Kirk Line, 
    877 F.2d 1508
    , 1516 (11th Cir.1989).
    34
    Grace Line, Inc. v. Todd Shipyards Corporation, 
    500 F.2d 361
    , 373 (9th Cir.1974).
    13
    As the district court noted, COGSA governed the carriage of the mobile homes from Tampa
    to French Guyana by virtue of clauses incorporated in the bills of lading. Each bill of lading
    contained a "Clause Paramount" which provided that COGSA applied to the carriage of the cargo,
    a "Clause 9" which provided that deck cargo shall be carried subject to COGSA's provisions, and
    a "Clause 19" which provided for a Himalaya clause extension of the rights provided to the carrier
    to agents, servants, and independent contractors of the carrier.
    The district court found that the vessels, in rem, qualified as carriers under COGSA because
    they (1) transported and discharged the cargo of the mobile homes, and (2) the master of each
    voyage, by transporting the cargo, ratified the bills of lading. It found that Project Logistics was also
    a carrier as it signed both bills of lading, booked the cargo through its booking note with SOGUCI,
    hired the stevedores to load and discharge the cargo, received payment from the shipper, SOGUCI,
    and disbursed payment to other parties. However, it concluded that Houston was neither an agent
    nor independent contractor of Project Logistics. It noted that Houston was not directly employed
    by Project Logistics, did not receive payment for its services from Project Logistics, had no
    contractual relationship with Project Logistics, and was not rendered an agent by Project Logistics
    as Project Logistics did not consent to have Houston act on its behalf. Although the July 31, 1989
    booking note listed "Meridian Ship/Houston Sea-Pack" as the carrier, the district court noted that
    Houston's representative, Don Jones, was neither a party to the contract nor signed the booking note.
    The evidence supports the district court's finding that Houston was not a "carrier" entitled
    to COGSA benefits. Houston was neither an agent nor contractor of shipper Project Logistics.
    Houston was contacted by a representative of Meridian Shipping, Inc., and Houston and Meridian
    proposed a shipping plan to Project Logistics. The July 31, 1989, and August 4, 1989, Booking
    14
    Notes were executed, respectively, by representatives of Project Logistics and Meridian naming
    "Meridian Ship/Houston Sea-Pack" as the carrier and Project Logistics as the merchant, and by
    representatives of Project Logistics and Florida Mercury naming Project Logistics as the carrier.
    Neither Houston nor its representative were a party to the July 31, 1989 contract.
    On August 28, 1989, representatives of Houston and Hale executed a Time Charter in which
    Hale chartered the vessels Alexandra Hale and Liberty Trader to Houston. On September 18, 1989,
    a representative of Project Logistics and Harry C. Anderson, Master of the M/V Alexandra Hale,
    executed a Bill of Lading listing SOGUCI as the shipper and consignee, and the Liberty Trader as
    the vessel. Meridian, as Houston's agent, executed a separate Bill of Lading for the first shipment
    of mobile homes.
    On November 13, 1989, a representative of Project Logistics executed a Bill of Lading for
    the second shipment of mobile homes, listing SOGUCI as the shipper and consignee, and the vessel
    as Liberty Trader; Meridian, as Houston's agent, executed a Bill of Lading for the shipment of
    mobile homes. On November 16, 1989, Project Logistics' representative executed a corrected Bill
    of Lading for the second shipment of mobile homes, listing SOGUCI as the shipper and consignee,
    and Liberty Trader as the vessel. There was no evidence presented that showed that Project
    Logistics entered into a contract of carriage or bill of lading with Houston, consented to have
    Houston act on its behalf as an agent, or was in privity with Houston. Project Logistics signed both
    bills of lading, booked the cargo through its booking note with SOGUCI, hired the stevedores to
    load and discharge the cargo, received payment from the shipper, and disbursed the funds to other
    parties.
    15
    Houston claims that the district court failed to consider SOGUCI's stipulation that "Project
    Logistics contracted with Houston to design a stanchion support system to carry 110 mobile homes
    per voyage on the deck of the barge."35 It also claims that the district court failed to consider that
    the provided tug, barge and stanchion system were fundamental to the performance of the contract
    for ocean carriage of the cargo from Tampa to Guyana, and that written agreements were entered
    into between Project Logistics and Houston, specifically the July 31, 1989 Liner Booking Note
    signed by representatives of "Meridian Ship/Houston Sea Pack" and Project Logistics stating that
    the carrier is "Meridian Ship/Houston Sea" and the merchant or shipper is Project Logistics; the
    August 4, 1989 communication from George Mandeville of Project Logistics to Don Jones of
    Houston indicating agreement of certain loading and support requirements to be provided by
    Houston; the August 7, 1989 communication from Don Jones of Houston agreeing to conditions
    set forth in Project Logistics' August 4 transmittal; and the August 8, 1989 agreement signed by
    representatives from Project Logistics, "Meridian Ship/Houston Sea Pack," and Houston Sea-
    Packing.
    The evidence showed that Houston was originally contacted by Meridian concerning the
    methods and costs of transporting the mobile homes and the construction of a stanchion system. In
    July 1989, Meridian and Houston entered into a booking note with Project Logistics for the shipment
    of the mobile homes; this booking note showed Meridian Ship/Houston Sea Pack as the "carrier"
    or "owner" but indicated that the vessel was to be named later. However, the July 1989 booking
    note was replaced by the August 4, 1989 booking note which was signed by Project Logistics and
    Florida Mercury and which named the vessels.
    35
    R2-104 at 2 ¶ 6; R2-99 at 3 ¶ A.
    16
    The September 18, 1989 bill of lading showed SOGUCI as the consignee or shipper, and was
    signed by a representative of the carrier, Project Logistics, and by the Master of the M/V Alexandra
    Hale, Harry C. Anderson. The November 13, 1989 bill of lading showed SOGUCI as the consignee
    or shipper, and was signed by a representative of the carrier, Project Logistics. Houston, however,
    did not issue either bill of lading. Houston, by virtue of the "Conlinebooking" Liner Booking Note
    it entered into with Project Logistics, was not responsible for the loading of the mobile homes onto
    the barge, securing and lashing the homes onto the stanchion system, or insuring that the nuts and
    bolts were securely fastened and tightened.
    Houston argues that its carrier status was determined by the district court's finding that
    "pursuant to the time charter between Hale and Houston, the Master of the vessels signed the bills
    of lading on behalf of Houston, rather than Hale" or, alternatively, that by sailing the vessels with
    the mobile homes on board, Houston impliedly ratified the bills of lading. However, Houston
    mischaracterizes the district court's findings.
    In considering the vessels' "carrier" status, the district court noted the qualifications for a
    vessel, in rem, to qualify as a carrier, and found that the vessels met those requirements because a
    "master's" sailing of the vessel with cargo aboard constitutes a ratification of the bill of lading. The
    district court made no findings as to Houston's implicit ratification of the bills of lading.
    In considering Hale's "carrier" status, the district court found that:
    [n]o Hale representative signed the November 13, 1989 bill of lading. Although Captain
    Anderson signed the September 18, 1989 bill of lading, he did so without actual or apparent
    authority to bind Hale as the vessels' owner. The time charter between Hale and Houston
    defined the respective duties of each party ... and provided that the captain would serve
    under the orders and directions of the charterer, Houston, with respect to employment and
    agency. The time charterer further provided that the charterer's agent would sign bills of
    lading in place of the captain. Captain Anderson, therefore, signed the bill of lading in
    17
    contravention of the time charter. Moreover, any authority conferred on Captain Anderson
    to sign the bills of lading flowed from Houston as a principal to the Captain as its agent....36
    The district court did not find that the Master signed the bills of lading on behalf of Houston,
    but only that he did so without actual or apparent authority, and any of his authority would have
    flowed from Houston under the time charter. Similarly, as the district court noted in denying Hale's
    "carrier" status claim, Houston neither booked the cargo nor hired stevedores to load the cargo on
    the vessel, and did not receive any payment directly from the shipper, SOGUCI.
    The district court's conclusions that the vessels in rem were carriers and that Houston was
    not a carrier are correct.
    B. Liability under COGSA
    SOGUCI maintains that the district court erred in finding that the vessels were entitled to the
    $500 per package limitation of liability under COGSA. It contends that the district court improperly
    found that the vessel's captain exercised due diligence in loading and stowing the cargo on the
    second voyage, and that the vessels were not liable for the costs of discharging and transhipping the
    fifteen mobile homes off-loaded in Martinique. It maintains that the vessels were not entitled to the
    COGSA limitation on liability because they did not give SOGUCI an opportunity to declare a higher
    value per package.
    Under COGSA, a shipper establishes a prima facie case by proving that the carrier received
    the cargo in good condition, but unloaded it in damaged condition at its destination.37 Once the
    36
    R2-257 at 22.
    37
    Sony Magnetic Products Inc. of America v. Merivienti O/Y, 
    863 F.2d 1537
    , 1539 (11th
    Cir.1989); M. Golodetz Export Corp. v. S/S Lake Anja, 
    751 F.2d 1103
    , 1109 (2nd Cir.), cert.
    denied, 
    471 U.S. 1117
    , 
    105 S.Ct. 2361
    , 
    86 L.Ed.2d 261
     (1985) (the shipper is not required to
    prove that the carrier was at fault or how the damage might have occurred); Westinghouse
    18
    shipper presents a prima facie case, the burden shifts to the carrier to prove that it either exercised
    due diligence to prevent damage to the cargo by handling, stowing, and carrying the cargo in a
    seaworthy ship, or that the harm resulted from an "uncontrollable" cause of loss as statutorily
    defined.38 The determination of whether due diligence and proximate cause are matters of fact, and
    this court will not overturn the district court's findings on these issues absent a finding that the
    findings are clearly erroneous.39 This court may not reverse the district court's findings on the
    evidence if they are plausible in light of the record viewed in its entirety, even if we would have
    weighed the evidence differently and arrived at a contrary conclusion.40 Independent surveyor
    reports and testing can be considered as "very strong evidence of due diligence."41
    The duty to load, stow, and discharge cargo in the carriage of goods under a time charter is
    on the ship and its owner.42 Use of stevedores to load and discharge the cargo does not relieve the
    Electric Corporation v. M/V "Leslie Lykes", 
    734 F.2d 199
    , 206 (5th Cir.), cert. denied, 
    469 U.S. 1077
    , 
    105 S.Ct. 577
    , 
    83 L.Ed.2d 516
     (1984); Terman Foods, Inc. v. Omega Lines, 
    707 F.2d 1225
    , 1227 (11th Cir.1983); Blasser Brothers, Inc. v. Northern Pan-American Line, 
    628 F.2d 376
    , 381 (5th Cir.1980).
    38
    Sony Magnetic Products Inc. of America, 863 F.2d at 1539; Westinghouse Electric Corp.,
    734 F.2d at 206; Terman Foods, Inc., 707 F.2d. at 1227; Blasser Brothers, Inc. v. Northern
    Pan-American Line, 628 F.2d at 382-383; 
    46 U.S.C. § 1304
    (2).
    39
    Fireman's Fund Insurance Companies v. M/V Vignes, 
    794 F.2d 1552
    , 1555 (11th Cir.1986).
    40
    
    Id.
    41
    
    Id. at 1556
    .
    42
    Associated Metals & Minerals Corp. v. M/V Arktis Sky, 
    978 F.2d 47
    , 50 (2nd Cir.1992);
    United States v. Lykes Bros. S.S. Co., Inc., 
    511 F.2d 218
    , 224 (5th Cir.1975); Nichimen Co. v.
    M.V. Farland, 
    462 F.2d 319
    , 330 (2nd Cir.1972); Demsey & Associates, Inc., 461 F.2d at 1014
    (operation under a charter does not affect the liability of the vessel); Agrico Chemical Company,
    
    459 F.Supp. 638
    , 647 (E.D.La.1978), aff'd, 
    620 F.2d 487
    , 489 (5th Cir.1980)(a carrier may not
    insulate itself from liability by use of independent contractors, servants, or agents).
    19
    ship and her owner of responsibility for any consequent cargo damage.43 However, a shipper may
    contract with another party to exercise control over the loading and unloading of the cargo, and
    liability will be found by determining who controlled the loading and storage.44
    The doctrine of deviation provides that, when a ship deviates from the contract of carriage
    or varies the conduct in the carriage of goods, increasing the risk of shipment of the goods, COGSA
    does not apply because the bill of lading, which acts as the contract of carriage, is nullified.45 The
    doctrine of deviation has been applied sparingly for geographical departures and unauthorized
    on-deck stowage.46 Where a ship leaves port badly stowed or unseaworthy, courts have held that
    the ship did not deviate in seeking a port of refuge.47 Also, a ship's master is empowered to exercise
    his good faith judgment during his command where the safety of the crew, vessel and cargo are
    concerned.48
    43
    Id..
    44
    Sumitomo Corporation of America v. M/V "Sie Kim", 
    632 F.Supp. 824
    , 836-837
    (S.D.N.Y.1985).
    45
    Unimac Co., Inc. v. C.F. Ocean Service, Inc., 
    43 F.3d 1434
    , 1437 (11th Cir.1995); Spartus
    Corporation v. S/S Yafo, 
    590 F.2d 1310
    , 1313-1314 (5th Cir.1979), quoting G.W. Sheldon & Co.
    v. Hamburg Amerikanische Packetfahrt-Actien-Gesellschaft, 
    28 F.2d 249
    , 251 (3rd Cir.1928)(a
    deviation may include "carrying the cargo on the deck of the ship contrary to custom and without
    the consent of the shipper" or "failure to deliver the goods at the port named in the bill of
    lading").
    46
    Unimac Co., Inc., 
    43 F.3d at 1437
    .
    47
    The Malcolm Baxter, Jr., 
    20 F.2d 304
    , 305-306 (2nd Cir.1927), aff'd, 
    277 U.S. 323
    , 
    48 S.Ct. 516
    , 
    72 L.Ed. 901
     (1928) (distinguishing between a voluntary and involuntary deviation, and
    noting that there is no deviation where a ship's master seeks a port of refuge for the safety and
    best interest of the crew, ship or cargo after finding that a ship is unseaworthy from the
    "unfitness of the structure.").
    48
    Westinghouse Electric Corp., 734 F.2d at 215-216.
    20
    Under COGSA,49 the shipper has the burden of declaring the value of its goods and paying
    a higher freight if it wants to have greater liability placed on the carrier.50 Where the carrier
    demonstrates that the shipper was given a fair opportunity to declare a higher value on paying a
    higher freight by being offered a choice of rates and valuations, the burden shifts to the shipper to
    demonstrate that a fair opportunity did not exist.51 The $500 per package limitation applies to
    on-deck shipments where it is plain on the face of the bill of lading that the cargo is to be carried
    on-deck and that COGSA is to be applied.52
    The district court found that Hale was not liable for the discharging and transhipment of the
    off-loaded mobile homes in Martinique because it exercised due diligence "to ensure seaworthiness
    of the vessel with respect to the stanchion system." It noted that, although the vessel's captain "had
    reason to know of a potential deficiency in the design of the stanchion system prior to the second
    voyage," he was reassured by Houston that the stanchion system was safe, and "properly deferred
    to the judgment of the engineer who designed the system and the surveyors who certified the
    suitability of the system." It noted that the captain was not present during the repairs, and the time
    charter placed full responsibility for the system in Houston's care.
    49
    
    46 U.S.C. § 1304
    (5).
    50
    Sony Magnetic Products of America v. Merivienti O/Y, 
    668 F.Supp. 1505
    , 1512
    (S.D.Ala.1987), aff'd 
    863 F.2d 1537
     (11th Cir.1989); Caterpillar Americas Company v. S.S. Sea
    Roads, 
    231 F.Supp. 647
    , 648 (S.D.Fla.1964), aff'd, 
    364 F.2d 829
     (5th Cir.1966).
    51
    Insurance Company of North America v. M/V Ocean Lynx, 
    901 F.2d 934
    , 939 (11th
    Cir.1990), cert. denied, 
    498 U.S. 1025
    , 
    111 S.Ct. 675
    , 
    112 L.Ed.2d 667
     (1991); Couthino, Caro
    and Co., Inc. v. M/V Sava, 
    849 F.2d 166
    , 170-171 (5th Cir.1988).
    52
    Brown & Root, Inc. v. M/V Peisander, 
    648 F.2d 415
    , 420-421 (5th Cir. Unit A 1981); Z.K.
    Marine, Inc. v. M/V Archigetis, 
    808 F.Supp. 1561
    , 1566-1567 (S.D.Fla.1992).
    21
    The district court's finding as to due diligence is not clearly erroneous. Under the time
    charter, Houston, as charterer, assumed full responsibility for the stanchion system. Houston hired
    a surveyor, as required by SOGUCI, to assure that the mobile homes were properly secured prior
    to the sailing of the vessels, and the surveyor inspected the system, and issued a document stating
    that all of the mobile home cargo was properly secured. SOGUCI accepted the surveyor's document
    and permitted the vessel to sail. The captain was not informed of the surveyor's apprehension of
    inadequacies of the stanchion system. The evidence showed that the captain reasonably relied on
    the surveyor, and the engineer responsible for the repairs of the stanchion system.
    The district court also found that, when the vessels sought a port of refuge at Fort de France,
    Martinique, it was necessary to remove fifteen mobile homes from the barge in order to safely
    continue the second voyage. The decision to remove the mobile homes was made by SOGUCI's
    insurance underwriters' surveyor, Christian Renaux. The vessel's captain agreed with the decision
    to remove the fifteen mobile homes and indicated that he would not continue the voyage until the
    mobile homes could safely make it to French Guyana. After removal, the fifteen mobile homes were
    transhipped on another vessel to French Guyana. The district court found that "any loosening of
    bolts on the second voyage" was attributable only to the extreme strain placed on the system by the
    improper design of the stanchion system.
    Although the offloading of the mobile homes in Fort of France may have been a change in
    the time charter, it was not a "deviation." The vessel's captain was empowered to exercise his good
    faith judgment where the safety of the cargo was involved, and in reliance on the opinion of
    SOGUCI's surveyor. The vessels were not, therefore, liable for the costs of discharging and
    transhipping the fifteen mobile homes off-loaded in Martinique.
    22
    As the vessels, in rem, were not liable and the issue was not decided by the district court, this
    court will not consider the application of the COGSA per package limitation.53
    C. Non-COGSA Liability
    1. Hale's claim for charter hire against Houston
    Houston argues that the district court erred in finding it liable to Hale for charter hire
    incurred subsequent to the cancellation of the charter party agreement because Hale unilaterally
    canceled the agreement.
    The district court noted that, following a dispute with Houston regarding payment, Hale
    withdrew the vessels from charter hire on November 22, 1989. The court commented that Houston
    owed Hale $99,606.08 in charter hire from the first voyage, and $150,000.00 advance charter hire
    for the second voyage. It noted that the time charter permitted Hale to terminate the agreement if
    Houston failed to make payment, required Houston to surrender possession of the vessels upon
    termination, and provided that Houston would remain liable for sums due under the charter hire
    despite the termination.54 The district court also found that Houston was obligated for charter hire
    until discharge of the cargo.
    As long as a vessel remains under control of the charterer, mere notice of withdrawal to the
    time charterer is not enough to effectuate a withdrawal of the charter, and the time charter remains
    in effect until the cargo is discharged.55 However, where a withdrawal is made during the term of
    53
    However, this court notes that "it is plain on the face" of the September 1989 bill of lading,
    that the "cargo is loaded on deck" and that COGSA is to be applied. See Brown & Root, Inc.,
    
    648 F.2d at 420-421
    .
    54
    Although the district court refers to Paragraph 7, the default clause is found at Paragraph 4.
    55
    Schirmer Stevedoring Co., Ltd. v. Seaboard Stevedoring Corp., 
    306 F.2d 188
    , 193 (9th
    Cir.1962).
    23
    the charter, and the owners immediately make a new charter with a new voyage charterer, the
    withdrawal may be effective although the vessel has not been unloaded.56 Generally, the obligation
    to carry and care for the goods remains on the carrier until the goods are actually delivered by being
    discharged at the port of discharge at the shore or alongside of a vessel.57 The measure for lost
    income of a vessel by its owner for a vessel under charter hire is the contract rate for the vessel
    under the time charter.58
    Houston was liable for charter hire incurred subsequent to the cancellation of the charter
    party agreement because, under the terms of the time charter, Houston remained liable, after
    termination, for any sums due at the time of the termination, and for charter hire until discharge of
    the cargo. Further, under the charter agreement, Houston was responsible for all consequences
    arising from the stanchion system. The district court did not err in finding Houston liable, or in
    calculating the loss of the use of the vessel.
    2. NCB's liability to SOGUCI
    SOGUCI maintains that the district court erred in not finding NCB's negligence in examining
    the bolting of the stanchion system causation for damages to the mobile homes. It contends that the
    56
    
    Id.
    57
    Surrendra (Overseas) Private, Ltd. v. S.S. Hellenic Hero, 
    213 F.Supp. 97
    , 101 (S.D.N.Y.),
    aff'd, 
    324 F.2d 955
     (2nd Cir.1963); Cardinal Shipping Corporation v. M/S Seisho Maru, 
    744 F.2d 461
    , 468 (5th Cir.1984), quoting Luckenbach v. Pierson, 
    229 F. 130
    , 132 (2nd Cir.1915),
    and citing Diana Compania Maritime, S.A. v. Subfreights of the S.S. Admiralty Flyer, 
    280 F.Supp. 607
    , 612 (S.D.N.Y.1968), 2B Benedict on Admiralty § 6, at 53 (7th ed.1983); and W.
    Poor, American Law of on Charter Parties and Ocean Bills of Lading § 8, at 38 (1968);
    Rainbow Navigation, Inc. v. United States, 
    742 F.Supp. 171
    , 183 (D.N.J.1990), aff'd, 
    937 F.2d 105
     (3rd Cir.1991); Finora Co., Inc. v. Amitie Shipping, Ltd., 
    852 F.Supp. 1298
    , 1307
    (D.S.C.1994), aff'd, 
    54 F.3d 209
     (1995).
    58
    Delta S.S. Lines, Inc. v. Avondale Shipyards, Inc., 
    747 F.2d 995
    , 1009 (5th Cir.1984).
    24
    district court's reasoning was speculative, and contrary to the evidence. It also contends that the
    district court erred in not finding that NCB negligently misrepresented the seaworthiness of the
    barge, and failed to disclose the barge's unseaworthiness.59 It argues that NCB was aware that
    SOGUCI was relying on NCB to ensure the seaworthiness of the tug and barge, and misled SOGUCI
    by issuing a letter making no mention of its observation that the stanchion system was in danger of
    failing.
    The district court's determination of negligence is a finding of fact that will not be disturbed
    unless clearly erroneous.60 In performing a survey of a vessel, a marine surveyor must use due care
    in making its recommendations and detecting all perceptible defects and must notify the owner of
    any defects.61
    In order to state a claim for negligent misrepresentation, a plaintiff must allege that: (1) the
    defendant, in the course of its profession, supplied false information to the plaintiff for a business
    transaction; (2) the defendant failed to exercise reasonable care in gathering the information; (3)
    the plaintiff relied on the information for the transaction that was intended by the defendant; and
    59
    Despite NCB's argument to the contrary, this issue was raised in and addressed by the
    district court.
    60
    Verrett v. McDonough Marine Service, 
    705 F.2d 1437
    , 1441 (5th Cir.1983).
    61
    Dillingham Tug & Barge Corporation v. Collier Carbon & Chemical Corporation, 
    548 F.Supp. 691
    , 698 (N.D.Ca.1981), aff'd in part and rev'd on other grounds, 
    707 F.2d 1086
     (9th
    Cir.1983), cert. denied, 
    465 U.S. 1025
    , 
    104 S.Ct. 1280
    , 
    79 L.Ed.2d 684
     (1984).
    25
    (4) the plaintiff suffered a resulting pecuniary loss.62 A party's access to information and the failure
    to inquire precludes, as a matter of law, claims of reliance on misrepresentations.63
    As to the causation issue, the court found that:
    On the second voyage, the stanchions bent again due to the improper placement of
    a fourth tier on the system.... SOGUCI assert(s) that failed bolt connections in the system
    also caused its collapse. Various witnesses testified that just prior to the second voyage,
    stevedores climbed to all tiers of the system to ensure all bolts were tightened. Don Jones
    testified that pursuant to his request, Project Logistics had their stevedores undertake this
    activity. NCB confirmed in its physical and visual inspection that the stevedores adequately
    secured the bolts in the system. The Court finds that any loosening of bolts on the second
    voyage can be attributed only to the extreme strain placed on the system by the improper
    design of the fourth tier in conjunction with the pitching at sea.64
    * * * * * *
    Although NCB fully inspected the bolting on the first tier of the system, it failed to properly
    examine the bolting on upper tiers of the system. NCB could not have fully assessed the
    proper tightening of bolts on the upper tiers by visual inspection, as it was difficult to view
    the bolts from the ground. Additionally, it appears that NCB's surveyors made very little
    effort to obtain a ladder or to utilize other means to physically examine the bolting on the
    upper tiers. Nevertheless, NCB's negligence in examining these bolts on the upper tiers had
    no causal relationship to the cargo damage. The Court has concluded that the bolts on all
    tiers were adequately tightened prior to departure of the second voyage and that the failure
    of the stanchion system and damage to the cargo did not result from loose bolting of the
    system prior to the second voyage. NCB's failure to examine the bolts did not, therefore,
    contribute to the failure of the stanchion system.65
    62
    Coastal (Bermuda) Ltd. v. E.W. Saybolt & Co., Inc., 
    826 F.2d 424
    , 428-429 (5th Cir.1987),
    reh'g denied, citing Grass v. Credito Mexicano, S.A., 
    797 F.2d 220
     (5th Cir.1986), cert. denied,
    
    480 U.S. 934
    , 
    107 S.Ct. 1575
    , 
    94 L.Ed.2d 766
     (1987) for the requirements to state a cause of
    action for negligent misrepresentation under Restatement (Second) of Torts § 552 (1977).
    63
    Grumman Allied Industries, Inc. v. Rohr Industries, Inc., 
    748 F.2d 729
    , 737-738 (2nd
    Cir.1984).
    64
    R2-257 at 18.
    65
    R6-257 at 33.
    26
    The district court's conclusion that any failure to inspect was not casually related to the
    damage to the mobile homes does not appear clearly erroneous. There was testimony that the bolts
    were tightened prior to the voyage after NCB inspection revealed that some of the nuts and bolts on
    the first tier were extremely loose, and that any loosening of the bolts during the voyage was due
    to the improper design of the system, and the pitching of the sea. Renaux explained that the damage
    resulted from "the lack of rigidity from the whole structure,"66 and, due to the damage incurred on
    the first voyage, he had advised replacing "all the deformed stanchions to consolidate the lashing
    and to carry, to transport the mobile homes on three levels only."67 Although Renaux answered "I
    suppose so" when asked whether the bolts were loose because they weren't properly tightened when
    the barge was in Tampa,68 and "I think so, yes," when asked whether "had the bolts been properly
    tightened in Tampa they would not have come loose,"69 and testified that the mobile homes
    "sustained damage ... because the structures were loose, got loose,"70 his answers were in response
    to questions about his thoughts during his inspection of the cargo in Martinique.
    As to negligent misrepresentation, the district court found that NCB could not "be held liable
    for a failure to conduct a full trip and tow survey," because NCB had no duty to Houston, SOGUCI,
    or any other party to perform a trip and tow survey or to detect and report defects which such a
    survey would have encompassed. It reasoned that NCB entered into the agreement to perform the
    66
    R10 at 42, 67-69, 74, 87-89, 91; Renaux deposition at 106-107.
    67
    
    Id. at 29, 138
    .
    68
    Renaux deposition at 111.
    69
    
    Id.
    70
    
    Id. at 107
    .
    27
    survey with Houston, and conducted the survey according to Houston's instructions. It noted that,
    although Houston had initially requested a trip and tow survey, Houston acquiesced to a different
    type of survey when NCB informed Houston that it would be unable to perform a full trip and tow
    survey.
    The district court's conclusion is not clearly erroneous. NCB was hired by Houston, albeit
    at SOGUCI's insurers' insistence that a survey would be required before departure of the second
    voyage, to "assure that the mobile homes were properly secured."71 Although NCB was initially
    asked by Houston to perform a trip and tow survey, addressing the seaworthiness of the tug and its
    ability to safely carry the cargo to its destination, NCB declined to perform a trip and tow survey.
    Further, Houston advised NCB's surveyor that the stanchion system was none of his concern, and
    not to worry about it. NCB was not notified that the sailing of the barge was conditioned on the
    issuance of a trip and tow survey.
    The November 13, 1989 letter issued by NCB states:
    This will confirm that the National Cargo Bureau, Inc., performed a final inspection of the
    cargo loaded on the Barge Liberty Trader on November 13, 1989. We sighted the stowage
    and securing of cargo, specifically noting that the frames of houses/mobile homes were
    properly secured to the network of framed bays ... The frames comprising the bays were also
    noted to be secured to one another. The cargo of mobile homes was stowed three high
    throughout except the aftermost thwartship row was stowed four high. In our opinion, all
    cargo, including the row stowed four high, was adequately secured with respect to frames
    of mobile homes being secured to frames in bays.72
    The letter made no reference to the seaworthiness of the barge or the stanchion system, and
    clearly indicated that some of the mobile homes were being transported on a fourth level. After the
    71
    R8 at 71.
    72
    Hale trial exh. 2 at 8.
    28
    first voyage, SOGUCI had been advised by its own surveyor that the mobile homes should be
    transported on only three levels, and a representative of SOGUCI was present for both the loading
    of the barge and the issuance of NCB's letter. SOGUCI, therefore, had access to information of the
    defect in the stanchion system design, and could not rely on NCB's failure to address such in its
    letter.
    D. Calculations of Loss of Rental Income
    SOGUCI claims that the district court erred in finding that SOGUCI had failed to mitigate
    damages by repairing the mobile homes, and committed a clerical error in the calculation of its loss
    of rental income.73 It maintains it made the repairs as quickly as possible, and that the six-month
    delay was due to the unavailability of replacement parts, materials, and repair facilities in French
    Guyana. It states that the district court erroneously calculated the lost rental income using 375
    francs per month as the loss of rental income for each mobile home, although the undisputed
    testimony was that the rent for each mobile home was 6,375 francs. It suggests that this
    miscalculation was a clerical error in the calculation of the judgment, or was unsupported by the
    record. As to the miscalculation, Hale responds that the matter should be remanded as the district
    court's intention is not clear.
    73
    Although SOGUCI states that it filed a Fed.R.Civ.P. 60(a) motion for correction of the
    clerical error with this court, the clerk of this court returned that motion to SOGUCI in March
    1996, with instructions that the motion be filed in the district court pursuant to Lairsey v.
    Advance Abrasives Company, 
    542 F.2d 928
     (5th Cir.1976) (if the district court is inclined to
    grant the motion, it should certify such to this court so that the movant can request remand from
    this court). By telephone, SOGUCI's counsel advises that the motion was filed with the district
    court on January 8, 1998. On March 2, 1998, the district court denied the motion without
    prejudice. It noted that it was without authority to correct the alleged clerical error absent leave
    of this court.
    29
    This court reviews a district court's finding of fact for clear error, and will not reverse
    unless, after "making all credibility choices in the fact-finder's choice" and reviewing the record as
    a whole, it is clear that a mistake has been made.74 If the district court's finding is plausible in light
    of the entire record, this court will not reverse "even though convinced that had it been sitting as the
    trier of fact, it would have weighed the evidence differently."75 Under general maritime law,
    damages for lost profits against a tortfeasor are allowed only when the amount of such profits is
    proven with reasonable certainty.76 In order to apportion damages based on a theory of failure to
    mitigate, the movant must establish that the failure to mitigate was unreasonable under the
    circumstances and aggravated the harm.77          In determining whether a victim's conduct was
    reasonable, a court must consider that "the necessity for decision-making was thrust upon him by
    the defendant, and judgments made at times of crisis are subject to human error," and should "allow
    the injured party a wide latitude in determining how best to deal with the situation."78
    74
    Hiram Walker & Sons, Inc. v. Kirk Line, 
    30 F.3d 1370
    , 1374 (11th Cir.1994), cert. denied,
    
    514 U.S. 1018
    , 
    115 S.Ct. 1362
    , 
    131 L.Ed.2d 219
    , quoting Meek v. Metropolitan Dade County,
    
    985 F.2d 1471
    , 1481 (11th Cir.1993); Verrett v. McDonough Marine Service, 
    705 F.2d 1437
    ,
    1441 (5th Cir.1983).
    75
    Hiram Walker & Sons, Inc., 
    30 F.3d at 1374
    , quoting Anderson v. City of Bessemer City,
    
    470 U.S. 564
    , 574, 
    105 S.Ct. 1504
    , 1511, 
    84 L.Ed.2d 518
     (1985); Pacific Employers Insurance
    Company v. M/V Gloria, 
    767 F.2d 229
    , 235 (5th Cir.1985).
    76
    Domar Ocean Transportation, Ltd. v. Independent Refining Company, 
    783 F.2d 1185
    , 1191-
    1192 (5th Cir.1986), citing Bolivar County Gravel Company v. Thomas Marine Co., 
    585 F.2d 1306
    , 1308 n. 2 (5th Cir.1978).
    77
    Bosnor, S.A. de C.V. v. Tug L.A. BARRIOS, 
    796 F.2d 776
    , 783 (5th Cir.), reh'g denied, 
    803 F.2d 717
     (1986), citing Tennessee Valley Sand & Gravel Co. v. M/V Delta, 
    598 F.2d 930
    , 933
    (5th Cir.1979).
    78
    Tennessee Valley Sand & Gravel Co., 598 F.2d at 933.
    30
    A district court may correct clerical mistakes in judgments based on oversight or omission
    at any time on its own initiative or on motion of any party,79 in order to correct mistakes that were
    not intended.80 A damages award that is incorrect because it is based on an erroneous mathematical
    computation that does not involve the substantive rights of the parties may be corrected under Rule
    60(a).81
    The district court noted that SOGUCI had asserted that it had contracted to rent the mobile
    homes commencing January 1, 1990, at the rate of 375 francs per month.82 It found that SOGUCI's
    loss of rental income for the mobile homes while the mobile homes were being repaired was "a
    foreseeable damage resulting from Houston's negligence."83 It found that SOGUCI "acted promptly
    in making repairs to the homes during January and February of 1990," but did not have the
    remaining repairs made until August 1990.84 The district court concluded that SOGUCI had failed
    to mitigate damages by making repairs and facilitating the rental of these mobile homes at an earlier
    date, and allowed lost rental income for January and February, but denied lost rental income from
    March to September.85
    79
    Fed.R.Civ.P. 60(a).
    80
    Allied Materials Corporation v. Superior Products Company, Inc., 
    620 F.2d 224
    , 225-226
    (10th Cir.1980).
    81
    Matter of West Texas Marketing Corp., 
    12 F.3d 497
    , 502-505 (5th Cir.1994).
    82
    R2-257 at 37. The judgment was subsequently calculated in U.S. dollars based on the 375
    franc rent. R2-262 at 2.
    83
    Id.. R2-257 at 37.
    84
    Id. at 37-38.
    85
    Id. at 38.
    31
    Both testimony and documentary evidence showed that each of the mobile homes were to
    be rented for 6,375 francs per month. The district court made no factual findings reducing the rent.
    Therefore, this matter is remanded to the district court for correction pursuant to Rule 60(a).
    Mark Richard Bushey, a mobile home repairman from Florida, was employed by the
    manufacturer of the mobile homes to make the repairs on the damaged mobile homes in French
    Guyana. Bushey was contacted in December 1989, and went to French Guyana in February 1990.
    Although the materials that the mobile home manufacturer's representative had indicated would be
    needed for the repairs were shipped to French Guyana, once Bushey arrived in French Guyana, he
    realized that more materials were needed, specifically sheet metal corners and toilet parts, and
    ordered the additional parts. He repaired most of the first 105 damaged mobile homes by using all
    of the available materials, and left about ten to fifteen mobile homes needing repairs. Bushey said
    that he was available to return to French Guyana at any time, but was not called to return until
    August or September. When he returned, there were about 50 mobile homes in need of repair.
    Mobile home representative Charles Aylor testified that it took about five months to get the
    necessary repair materials for the second trip to French Guyana, because the materials were shipped
    from Florida in April or May, and did not arrive in French Guyana until July or August.86 He
    explained that the shipping delay was due to a strike, problems with the shipping company, and the
    need for a boat to take the materials from Surinam to French Guyana. He said that, although a
    couple of packages were sent by air, the bulk of the other materials made it very expensive to send
    86
    Aylor did not explain why the materials which were ordered in February were not shipped
    until April or May.
    32
    them by air. When asked whether the repairs were done "as quickly and as efficiently as possible"
    based on the need to get the materials to French Guyana, and the shipping problems, Aylor replied:
    Using the transportation methods that were there, they were done as quickly as
    possible. We could have gotten Air France to fly in a plane or something like that done
    quicker, obviously. But there wasn't any delay because of money or anything of that nature
    that kept us from meeting the time schedules.87
    Houston had the burden of showing that SOGUCI acted unreasonably in mitigating its
    damages. Although the district court noted that SOGUCI did not have the repairman return to make
    the repairs until August 1990, it is not clear that the district court considered the evidence explaining
    that this delay was due to problems in shipping the needed materials to French Guyana. The district
    court's denial of lost rental income from March to September 1990, is vacated, and the matter is
    remanded for consideration of the reasonableness of SOGUCI's conduct.
    III. CONCLUSION
    The district court's findings of fact and conclusions of law are AFFIRMED on all issues,
    other than SOGUCI's loss of rental income and the calculation of that rental income. As to those
    issues, the district court's findings are VACATED and the matter is REMANDED for further
    consideration consistent with this opinion.
    AFFIRMED IN PART and VACATED AND REMANDED IN PART.
    87
    Aylor deposition at 145.
    33
    

Document Info

Docket Number: 95-3201, 95-3296

Citation Numbers: 137 F.3d 1455

Judges: Birch, Clark, Hatchett

Filed Date: 4/3/1998

Precedential Status: Precedential

Modified Date: 8/2/2023

Authorities (13)

Unimac Company, Inc. v. C.F. Ocean Service, Inc. , 43 F.3d 1434 ( 1995 )

carrie-meek-xavier-suarez-james-c-burke-maurice-a-ferre-pedro-jose , 985 F.2d 1471 ( 1993 )

Finora Company, Incorporated v. Amitie Shipping, Limited , 54 F.3d 209 ( 1995 )

Brown & Root, Inc. v. M/v Peisander, Etc. , 648 F.2d 415 ( 1981 )

United States v. Kellogg (In Re West Texas Marketing Corp.) , 12 F.3d 497 ( 1994 )

hiram-walker-sons-inc-v-kirk-line-rb-kirkconnell-bro-ltd , 30 F.3d 1370 ( 1994 )

Otto Wolff Handelsgesellschaft v. Sheridan Transp. , 800 F. Supp. 1359 ( 1992 )

The Malcolm Baxter, Jr. , 48 S. Ct. 516 ( 1928 )

Anderson v. City of Bessemer City , 105 S. Ct. 1504 ( 1985 )

J. Gerber & Co., Inc. v. M/V INAGUA TANIA , 828 F. Supp. 458 ( 1992 )

ZK Marine, Inc. v. M/V Archigetis , 808 F. Supp. 1561 ( 1992 )

Rainbow Navigation, Inc. v. United States , 742 F. Supp. 171 ( 1990 )

Finora Co., Inc. v. Amitie Shipping, Ltd. , 852 F. Supp. 1298 ( 1994 )

View All Authorities »

Cited By (12)

Polo Ralph Lauren, L.P. v. Tropical Shipping & Construction ... , 215 F.3d 1217 ( 2000 )

Drew v. Department of Corrections , 297 F.3d 1278 ( 2002 )

Polo Ralph Lauren v. Tropical , 215 F.3d 1217 ( 2000 )

James N. Kirby, Pty Ltd. v. Norfolk Southern Railway Co. , 300 F.3d 1300 ( 2002 )

Commodity Futures Trading Commission v. Gibraltar Monetary ... , 575 F.3d 1180 ( 2009 )

cheryl-maloof-johansen-mildred-d-goldman-aubrey-g-mcgill-william-e , 170 F.3d 1320 ( 1999 )

The RICE COMPANY (SUISSE) v. Precious Flowers Ltd. , 523 F.3d 528 ( 2008 )

Whitaker v. J R Produce Corp. (In Re Gulf Northern ... , 340 B.R. 111 ( 2006 )

Linea Navira De Cabotaje v. Mar Caribe , 169 F. Supp. 2d 1341 ( 2001 )

El Jordan v. Solymar, S. De R.L. , 315 F. Supp. 2d 1355 ( 2004 )

Pacific Tall Ships Co. v. Kuehne & Nagel, Inc. , 76 F. Supp. 2d 886 ( 1999 )

Realini v. Contship Containerlines, Ltd. , 143 F. Supp. 2d 1337 ( 1999 )

View All Citing Opinions »