Ott v. DuPlan Silk Corp. , 271 Pa. 322 ( 1921 )


Menu:
  • Opinion by

    Mr. Justice Sadler,

    The plaintiff is a subcontractor, who performed essential service in the construction of a building for defendant. His contract for excavation work was verbal, the undertaking having been confirmed by letter of the contractor, dated May 19, 1917:.' Provision was made for payment of differing prices dependent on the character of the materials required to -be removed. All of the work was completed on August 18th following, and the compensation agreed upon not having been paid, a prop*326erly verified notice of intention to file a lien was served upon the owner, to which was attached an itemized bill. Subsequently, a motion to strike off the lien, on the ground of insufficiency of the notice, was refused, as was an application to strike therefrom certain charges. On the trial of the scire facias, these objections were renewed, and overruled in part; the court submitted to the jury three claims, which are the first appearing in the account of the subcontractor.

    The validity of the notice is the subject of complaint here, it being insisted .that the charges are not sufficiently specific. Each of the three items in question, under the heading “excavation,” sets forth the number of cubic yards removed, the price charged per unit, and the total sum due on account thereof. In the one case, the cost was sixty cents, in the second $2.10, and in the third $3.15. These were the amounts agreed to be paid respectively for the moving of material by steam shovel, of rock requiring blasting, and of like work in pier holes. No copy of the contract was attached, but that in itself would not render invalid the notice of intention, if the statutory requirements appear substantially therein: Este v. P. R. R. Co., 27 Pa. Superior Ct. 521.

    The Act of March 24, 1909, P. L. 65, amending the Act of June 4,1901, P. L. 434, section 8, provides that “any contractor, intending to file a claim, must give the owner written notice to that effect, verified by affidavit, setting forth the name of the party with whom he contracted, the amount alleged to be still due, the nature of the labor or materials furnished, and the date when the last work was done or last materials furnished.”

    It is argued that the failure to set forth in each item the particular kind of excavation for which the charge is made is a fatal defect. But the general nature of the work is designated. While a mechanic’s lien is purely a creature of statute, and compliance with the provisions of the act permitting it to be filed is necessary to give it validity, this rule applies only to essential requirements *327(American Car Co. v. Alexandria Water Co., 218 Pa. 520; Willson v. Canevin, 226 Pa. 362), and the same exactness is not insisted upon in the notice as in the lien itself: Este v. P. R. R. Co., supra.

    The purpose of the notice is to inform the owner of the claim made, so he may protect himself in the manner provided by the act in making settlement with the contractor. It must, therefore, be sufficiently definite to fairly apprise of the service which has been rendered, and the charge made therefor. The only requirement is thát “the nature of the work” be set forth. In stating the claim was for excavation for a particular building, such information was given as enabled the owner to make 'proper investigation of the correctness of the demand. What was said by this court in Willson v. Canevin, 226 Pa. 362, is applicable here, and a like conclusion should be reached. See, also, Curti v. Hartrick, 61 Pa. Superior Ct. 447; Bennett Lumber & Mfg. Co. v. Hartrick, 61 Pa. Superior Ct. 456.

    This case is to be distinguished from those in which liens have been held defective in charging a lump sum against several properties without setting forth the nature and amount of the work done on each (McFarland v. Schultz, 168 Pa. 634; Brant v. Hartrick, 60 Pa. Superior Ct. 507); or where, as in Burrows v. Carson, 244 Pa. 6, the claim was for labor, covering a considerable period, in building stairs for a house, no indication being given as to whether it was performed “in preparation of materials used in the house, at the shop of plaintiff, or in incorporating them into the building by carpenters, cabinetmakers, assistants or laborers”; or where a lump sum is charged for some general, class of materials, made up of many different items, as “lumber furnished,” not stating the kinds supplied, without which the owner would have no fair opportunity for investigation (Benton v. Berg Distilling Co., 63 Pa. Superior Ct. 412; Breitwieser v. Wyss-Thalman, 51 Pa. Superior Ct. 83). We are of the opinion these decisions are not controlling of the case at bar.

    *328The defendant also insists that the statement as to the time when the last work was done is not properly set forth. This objection is untenable, in view of the express declaration that the contract of May 19,1917, was fully performed on August 18, 1917. The same exceptions are urged against the lien filed, — which does contain the contract and describe in detail the various classes of excavation work, — as to the notice of intention, but they cannot be sustained. Nor was there error in the refusal of the court below to strike off preliminarily the entire lien, since some items appearing therein were valid: McCristal v. Cochran, 147 Pa. 225; Dyer v. Wallace, 264 Pa. 169.

    The fourteenth error assigned is directed to the swearing of the jury as to both owner and contractor, the latter not being properly in court by service or appearance. He was necessarily, under the act of assembly, named in the proceeding as a party defendant. Though the action complained of may be deemed irregular (Sullivan v. Johns, 5 Whart. 366), we cannot see how the present appellant was injured; if any one can complain of such action, it is the contractor, and he is not objecting here: Hills v. Elliott, 16 S. & R. 56.

    The defendant also complains of the admission in evidence of the mechanic’s lien. The document could not be received as proof of the contents (Hills v. Elliott, supra), for the paper is merely a statement of the claim made: Bernheisel v. Smothers, 5 Pa. Superior Ct. 113. An examination of the record, however, indicates that the offer was merely as a part of the history of the case, and was followed by reading the portions thereof which the affidavit of defense conceded to be true. As to the other statements, evidence was offered to show their correctness. Further, it is to be observed that, though a general objection to the admission of the evidence in question was made, this was coupled with a specification of the reasons for not receiving it, based on the claim of the insufficiency of the lien, and of the intention to file the *329same, heretofore considered. To the special complaint made at the trial, the defendant should now be confined (Danley v. Danley, 179 Pa. 170), in view of the fact that it clearly appears the lien’s use as evidence was limited to the parts admitted by defendant’s pleadings.

    One other matter requires consideration. After the filing of the mechanic’s lien in the Luzerne courts against the owner and contractor, the latter brought suit in Philadelphia County against the' subcontractor, claiming an over-payment to him. Ott defended on the ground that the contrary was true, and to establish his defense necessarily showed the amount of work done by him, and that a balance was due on account thereof. He set up no counterclaim, and asked no certificate in his favor. The verdict was generally for defendant. It is insisted Ott’s duty was to assert his claim at that time, and, not having done so, he is now debarred -from proceeding with the enforcement of his mechanic’s lien, since the owner of the land is entitled to the benefit of any defense which the contractor might have; and, as to him, it is argued, the plaintiff’s claim is res adjudicata.

    It is undoubtedly true that what has once been judicially determined shall hot again be the subject of litigation, and that this principle extends to every question in the proceeding which was legally cognizable (McGunnegle v. R. R., 269 Pa. 404); but the plaintiff’s claim did not come within this rule. He proved that nothing was owing by him at the trial, but did not set up his counterclaim. He was not bound to do so: Gilmore v. Reed, 76 Pa. 462. “The mere pendency of a suit upon a claim, will not prevent the same claim from being used as a set-off in another action; or vice versa, the introduction of a claim as a set-off in one action, will not create a bar to a suit in another court, in a direct action upon the same claim”: National Metal Edge Box Co. v. American Metal Edge Box Co., 246 Pa. 78, 83.

    Further, it is to be noticed that the action in Philadelphia was a personal one in which the contractor was *330the opposing party, while that in Luzerne was against the owner, having for its purpose the liening of the land, —a proceeding in rem. There was no such identity of action as would make the suit first tried a bar to proceeding upon the one first brought, but heard subsequently: Powell’s Assignee v. Wyoming Valley Mfg. Co., 8 W. N. C. 293. For the reasons stated, the error alleged cannot be sustained.

    Other assignments of error have been filed, but a discussion of them is unnecessary; all are overruled. A like disposition is made of the motion to quash filed by appellee, in which we see no merit.

    The judgment is affirmed.

Document Info

Docket Number: Appeal, No. 445

Citation Numbers: 271 Pa. 322

Judges: Carman, Frazer, Izisker, Mosci, Sadler, Schaffer, Simpson, Walling

Filed Date: 7/1/1921

Precedential Status: Precedential

Modified Date: 2/17/2022