Green Acres One, LLC & Half Moon Acres, LLC v. Halfmoon Twp., Centre County, PA ( 2021 )


Menu:
  •            IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Green Acres One, LLC and Half Moon :
    Acres, LLC,                        :
    Appellants  :
    :
    v.                :                No. 336 C.D. 2020
    :                Argued: December 8, 2020
    Halfmoon Township, Centre County,  :
    Pennsylvania                       :
    BEFORE:       HONORABLE RENÉE COHN JUBELIRER, Judge
    HONORABLE P. KEVIN BROBSON, Judge1
    HONORABLE CHRISTINE FIZZANO CANNON, Judge
    OPINION NOT REPORTED
    MEMORANDUM OPINION BY
    JUDGE COHN JUBELIRER                               FILED: April 21, 2021
    Green Acres One, LLC and Half Moon Acres, LLC (collectively,
    Landowners) appeal from a February 25, 2020 Order of the Court of Common Pleas
    of Centre County (common pleas), which denied Landowners’ appeal from a
    decision of Halfmoon Township, Centre County, Pennsylvania (Township), denying
    Landowners’ Application for Preliminary Subdivision Plan (Application) and
    Sewage Facilities Planning Module (Sewer Planning Module). Landowners contend
    that common pleas erred by: (1) finding the Township’s denial complies with the
    applicable law governing municipal decisions; (2) not finding the Township acted
    in bad faith in summarily denying the Application and Sewer Planning Module just
    nine days after submission; (3) finding the Township could deny the Application and
    1
    This case was assigned to the opinion writer prior to January 4, 2021, when Judge Brobson
    became President Judge.
    Sewer Planning Module based upon an ordinance that merely authorized the
    Township to execute an agreement to amend its land use ordinances but did not
    actually amend said ordinances; and (4) upholding the denial because Landowners
    had a statutory right under the Pennsylvania Sewage Facilities Act2 to seek
    Department of Environmental Protection (DEP) approval to revise the applicable
    sewage facilities plan to authorize service to the proposed development with a
    community treatment plant. We reverse common pleas’ Order because, although
    the email denial satisfies the statutory requirements to constitute a municipal denial,
    the ordinance upon which the email denial was based did not substantively amend
    the Township’s land use ordinances, as the Township contends. Therefore, we
    remand this matter for further remand to the Township, which is directed to consider
    the Application and Sewer Planning Module in accordance with the Township’s
    Zoning Ordinance3 and Subdivision and Land Development Ordinance4 (SALDO)
    as they existed at the time of the Application.
    I.     BACKGROUND
    Landowners own approximately 198 acres of land north of State Route 550 in
    the Township upon which they propose to build 70 single-family detached dwellings
    that would be served by a community sewage treatment plant that Landowners also
    propose to construct.5 (Common pleas’ Opinion (Op.), Findings of Fact (FOF) ¶¶ 1,
    2
    Act of January 24, 1966, P.L. 1535, No. 537, as amended, 35 P.S. §§ 750.1-750.20a.
    3
    Zoning Ordinance of Halfmoon Township, Centre County, Pa. (Sept. 11, 1972), as
    amended.
    4
    Subdivision and Land Development Ordinance of Halfmoon Township, Centre County,
    Pa. (Oct. 14, 1985), as amended.
    5
    Landowners also own an additional 127 acres in neighboring Patton Township, which
    will be developed into Greenmoore Village. A planning module for that development was
    (Footnote continued on next page…)
    2
    12-13.) The property is located in an Agricultural Zoning District where the
    Township’s Zoning Ordinance permits community sewage treatment plants as a
    conditional use. (Zoning Ordinance, Section 255-13.C(3), Reproduced Record
    (R.R.) at 600a.) The Township’s SALDO likewise permits community septic and
    sewage systems provided the same are approved by the Board of Supervisors, DEP,
    and the sewage enforcement officer. (SALDO, Section 215-19.A(4), R.R. at 804a.)
    The Centre Region Council of Governments (CRCOG), of which the
    Township is a member,6 updated its multimunicipal comprehensive plan, the Centre
    Region Comprehensive Plan, in November 2013. (FOF ¶¶ 2-3.) Therein is a Future
    Land Use Map identifying a Regional Growth Boundary and Sewer Service Area.
    (Id. ¶ 4.) “The Regional Growth Boundary delineates a region where it was
    determined growth should occur.”          (Id. ¶ 5.)   The Sewer Service Area was
    established by the Centre Region Act 537 Sewage Facilities Plan (Act 537 Plan) and
    identifies the area serviced by public sewer. (Id. ¶¶ 4, 8.) The boundaries of the
    Sewer Service Area coincide with the Regional Growth Boundary. (Id. ¶ 8.) The
    Township, and hence Landowners’ property, is entirely located outside of this area.
    (Id. ¶ 7.) The rural areas outside of the Regional Growth Boundary are largely
    devoted to farming and forestry, and while large-lot, single-family homes are
    permitted, they cannot require the use of public sewer services. (Id. ¶ 6.) According
    to Section IX of the Centre Region Growth Boundary and Sewer Service Area
    Implementation Agreement (Implementation Agreement):
    The [Act 537 Plan] identifies on-lot sewage disposal systems as the
    only method for wastewater treatment outside of the Regional Growth
    previously submitted and approved by Patton Township. If approved by the Township, both
    developments will utilize the proposed treatment plant. (Reproduced Record (R.R.) at 99a.)
    6
    Other member municipalities include College Township, Ferguson Township, Harris
    Township, Patton Township, and State College Borough.
    3
    Boundary and Sewer Service Area. If public sewer service is requested,
    the University Area Joint Authority [(UAJA)] has been identified as the
    provider for public services in the Centre Region.
    (Implementation Agreement, Section IX, R.R. at 31a.)
    Section IX of the Implementation Agreement prohibits alternative public
    wastewater treatment systems outside of the Regional Growth Boundary and Sewer
    Service Area. (Id.) The Implementation Agreement defines “[a]lternative [p]ublic
    [w]astewater [t]reatment” as “any process designed to produce an effluent of higher
    quality than normally achieved through primary and secondary treatment processes
    and [which] does not utilize soils as the primary method for remediation.” (Id.,
    Section II, R.R. at 21a.) Section IX concludes by stating that “by enacting this
    [Implementation] Agreement, the Municipalities agree to incorporate the
    requirements described above into their municipal sewage management ordinances.”
    (Id., Section IX, R.R. at 31a.)
    On December 17, 2013, the Township enacted Ordinance 2013-20 wherein
    the Township Board of Supervisors indicated “the Township . . . wishe[d] to
    adopt . . . [the] Implementation Agreement” and “authorize[d] the Chair and the
    Secretary to execute said [Implementation] Agreement on behalf of the Board of
    Supervisors of the Township . . . .” (Ordinance 2013-20, R.R. at 19a.) Ordinance
    2013-20 included what is commonly referred to as a repealer provision, which
    provided: “All existing agreements, resolutions, and ordinances which are contrary
    to the provisions of this Ordinance are hereby repealed to the extent necessary to
    give this Ordinance full force and effect.” (Id.) The Township’s Zoning Ordinance
    and SALDO predate the Implementation Plan and Ordinance 2013-20. There is no
    evidence either was amended to reflect the Implementation Agreement and its
    requirements.
    4
    Consistent with their proposed development, Landowners submitted their
    Application on August 8, 2018, and their Sewer Planning Module on August 9,
    2018,7 requesting that the Township amend the Act 537 Plan to allow the
    development to be served by Landowners’ proposed community plant. (FOF ¶¶ 11,
    14.) Landowners did not request that the Regional Growth Boundary be expanded
    to encompass the property or request an expansion of the Act 537 Plan so the
    proposed development could be serviced by UAJA. (Id. ¶ 15.)
    On August 17, 2018, the Township Manager sent Landowners’ representative
    an email, denying the Application and Sewer Facilities Planning Module. The email
    states:
    Halfmoon Acres submitted its Application . . . for approximately 70 lots
    North of [State Route] 550. [The A]pplication notes these dwelling
    units will be served by an alternative wastewater system. To this end,
    [Landowners] submitted a Sewer Planning Module [] a few days later
    to the Township for approval. The Township hereby denies both the
    [A]pplication . . . and Sewer Planning Module []for the reasons stated
    below.
    Staff stated to both of you at the pre-application meeting a week to 10
    days ago, alternative wastewater systems are not allowed outside the
    Regional Growth Boundary.            We referred you to the . . .
    Implement[ation] Agreement and Township Ordinance 2013-20 dated
    December 17, 2013. Therefore, we stated, if an application for
    subdivision was submitted to the Township for any lots to be served by
    an alternative wastewater system as defined in both the Ordinance and
    Agreement[,] staff would, under current law, have to summarily deny
    same.
    In further support of denying the application as submitted, I spoke to
    Dan Thetford at DEP who would be reviewing and approving any
    Sewer Planning Module[s] [] for the Township. He state[d] any
    7
    Landowners originally submitted their Sewage Facilities Planning Module in September
    2010, supplemented it in November 2010, updated it in February 2011, and resubmitted it in July
    2011 before updating and resubmitting it to the Township in August 2018. (R.R. at 80a.)
    5
    possible DEP approval is always contingent upon any system being
    consistent with Township Ordinances or Regional policies. He also
    state[d] the Township has sole power to dictate who it wishes to own
    and operate any wastewater system within its boundaries. The
    Township wants any wastewater system within the Township to be
    owned and operated by a public entity. This means UAJA[,] and Cory
    [Miller] at UAJA state[d] any system UAJA will own and operate will
    have to be built to UAJA standards and must be approved by the region.
    [Jim] May’s letter lays out two different options for [Landowners] to
    pursue if [they] decide[] to submit a new application.
    (R.R. at 17a.)
    The letter referenced in the final paragraph of the email refers to an August
    16, 2018 letter from the Director of Centre Regional Planning Agency (CRPA), to
    the Township Manager (May’s letter). Therein, May stated he was “writing on
    behalf of the CRPA to request that [the] Township consider rejecting the
    [A]pplication” because “[t]he project proposes an alternative wastewater treatment
    system that is prohibited by the . . . Implementation Agreement.” (Id. at 399a.)
    May’s letter specifically cited Section IX.3 of the Implementation Agreement for
    this proposition. (Id.) May’s letter concludes by stating:
    [Landowners] should consider the two following options for
    resubmittal if the Township chooses to reject the [A]pplication:
    1.    Redesign the subdivision to accommodate individual on-
    lot or community on-lot septic systems and resubmit the
    preliminary subdivision plan.
    2.    Request an expansion of the Regional Growth Boundary
    [] and Sewer Service Area [] so that [] UAJA could serve the
    property. If this is the case, the Township should not review the
    subdivision unless [Landowners] first come[] to the Township to
    request an expansion of the [Regional Growth Boundary and
    Sewer Service Area], and the request is authorized by the
    Township Board of Supervisors and ultimately approved by the
    [CR]COG General Forum.
    6
    (Id. at 399a-400a.) Listed as being copied on the letter were CRCOG’s executive
    director, UAJA’s executive director, Patton Township’s manager, two of CRPA’s
    senior planners, the Township’s zoning officer, the Township’s engineer, and
    someone from DEP’s Clean Water Program. (Id. at 400a.) It is not clear whether
    May’s letter was attached to the Township Manager’s email.
    On September 17, 2018, Landowners filed their notice of appeal to common
    pleas, raising the same four issues raised before this Court.8               Without taking
    additional evidence, common pleas issued its Order on February 25, 2020, denying
    Landowners’ appeal. In an accompanying opinion, common pleas explained its
    reasoning as follows. With regard to the sufficiency of the Township’s decision,
    common pleas stated the email from the Township Manager explained the
    Application was being denied because the community treatment plant would violate
    the Implementation Agreement and Ordinance 2013-20. (Common pleas’ Op. at 7.)
    In addition, common pleas found the email incorporated by reference May’s letter
    providing two options for Landowners to resubmit the Application. (Id. at 7-8.)
    Thus, common pleas found the email denial satisfied the statutory requirements for
    a municipal decision and, therefore, no deemed approval occurred. (Id. at 8.)
    Common pleas likewise was not persuaded by Landowners’ argument that the
    Township acted in bad faith. Common pleas acknowledged that the Application was
    denied within nine days of submission but explained that the denial occurred after a
    pre-application meeting at which Township staff advised Landowners why the
    8
    Before common pleas, the Township challenged the timeliness of Landowners’ appeal on
    the basis that it was filed 31 days after the email decision instead of within 30 days. Common
    pleas deemed the appeal timely on the basis that 30 days after August 17, 2018, would have been
    Sunday, September 16, 2018, giving Landowners until Monday, September 17, 2018, to file their
    appeal, which they did. (Common pleas’ Op. at 7.) The Township does not challenge that
    determination before this Court.
    7
    Application would be denied. (Id. at 8-9.) As a result, common pleas found that the
    time between submission and denial was not indicative of bad faith. (Id. at 9.)
    Common pleas further found that the Township provided Landowners with two
    options regarding how to proceed. (Id.)
    As to Landowners’ third argument, common pleas found Ordinance 2013-20
    adopted the Implementation Agreement and repealed all ordinances that were
    contrary thereto. (Id.) Thus, “the [Implementation Agreement] and the Regional
    Growth Boundary have the legal effect of an ordinance,” to which Landowners are
    bound, and the Township’s denial of the Application on the basis the Application
    was contrary to a Township ordinance was not error. (Id. at 9-10.)
    Finally, common pleas found the Township did not deny Landowners the right
    to submit a private request to DEP to revise the Act 537 Plan as provided in the
    Pennsylvania Sewage Facilities Act. Common pleas stated Landowners “have not
    provided [common pleas] with evidence of a prior written demand to the Township,
    and the Township’s subsequent written refusal to implement or revise the [Act] 537
    Plan,” both of which are required under DEP’s regulations. (Id. at 10.) In addition,
    common pleas found Landowners were provided two options for proceeding, to
    which they did not avail themselves. (Id.)
    Following Landowners’ appeal of common pleas’ Order to this Court,
    common pleas issued an opinion pursuant to Rule 1925(a) of the Pennsylvania Rules
    of Appellate Procedure, Pa.R.A.P. 1925(a) (1925(a) Op.), wherein it further
    explained its reasoning related to the fourth issue. Common pleas explained that
    even if it accepted Landowners’ argument that the Application and email denial
    constituted a request and denial to amend the Act 537 Plan, Landowners’ fourth
    “argument lacks merit.”     (1925(a) Op. at 2.)     According to common pleas,
    8
    Landowners’ “right to seek DEP approval did not mean the Township was required
    to approve” Landowners’ Application. (Id. at 2-3.) Common pleas stated that DEP
    approval would permit Landowners to proceed with their plan “notwithstanding the
    lack of approval from the Township and notwithstanding any agreements of the
    Centre Region [m]unicipalities.” (Id. at 3.) Common pleas explained that nothing
    in DEP’s regulations “precluded [Landowners’] right to seek DEP approval” when
    the request is denied by the Township. (Id.) Instead, common pleas found that the
    regulations “actually require[] a denial by the Township before [Landowners] can
    make the request.” (Id.) Common pleas further found that “[t]he Township did not
    ignore [Landowners’] right to seek DEP approval, and actually consulted with DEP,
    which informed the Township it would deny [Landowners’] Plan as well.” (Id.)
    Lastly, common pleas reiterated that the Township provided Landowners with two
    options, neither of which Landowners pursued. (Id. at 3-4.)
    II.    PARTIES’ ARGUMENTS
    On appeal,9 Landowners argue that common pleas’ Order should be reversed
    for four reasons. First, Landowners claim the email from the Township Manager
    does not comply with the statutory requirements for a municipal decision and, as a
    result, Landowners are entitled to a deemed approval of their Application and Sewer
    Planning Module. Landowners assert that both Section 508(2) of the Pennsylvania
    Municipalities Planning Code (MPC)10 and Section 215-7.F(3) of the Township’s
    SALDO require a decision to describe the defects with an application, explain which
    9
    “In a land use appeal, where [common pleas] has not taken any additional evidence, this
    Court’s scope of review is limited to a determination of whether the governing body has committed
    an error of law or abused its discretion.” Koller v. Weisenberg Township, 
    871 A.2d 286
    , 289 n.2
    (Pa. Cmwlth. 2005).
    10
    Act of July 31, 1968, P.L. 805, as amended, 53 P.S. § 10508(2).
    9
    requirements are not met, and cite specific provisions of an ordinance that are at
    issue. Landowners argue the only ordinance referenced in the Township Manager’s
    email is Ordinance 2013-20, which merely authorized the Township to adopt the
    Implementation Agreement. Landowners dispute that May’s letter was incorporated
    by reference into the email, as common pleas found. Landowners further argue May
    is not a Township official. Assuming May’s letter was incorporated into the
    Township Manager’s email, Landowners argue it only contains a recommendation
    and does not provide a basis for the denial.
    Second, Landowners argue the Township had a duty to act in good faith in
    reviewing Landowners’ plans, which the Township did not do. As evidence,
    Landowners argue the Application and Sewer Planning Module were denied just
    nine days after submission and the email denial did not provide Landowners with an
    opportunity to respond to modify the plan. To the extent common pleas found there
    was no bad faith because May’s letter provided two options for resubmitting the
    Application, Landowners argue neither of those options are feasible as on-lot
    systems would be too expensive and approval by the Township and/or CRCOG to
    amend the Act 537 Plan was unlikely.
    Third, Landowners argue the Township never amended its ordinances in
    accordance with the Implementation Agreement, and, therefore, the ordinances that
    were still on the books allowed off-lot systems and alternative wastewater treatment
    systems, such as community sewer treatment plants. Contrary to the Township’s
    assertion, Landowners argue that Ordinance 2013-20 does not actually impose any
    land use requirements; it merely authorizes Township officials to sign the
    Implementation Agreement. For similar reasons, Landowners assert the repealer
    provision in Ordinance 2013-20 does not save the Township.            According to
    10
    Landowners, at best, the repealer provision only repeals any ordinances that would
    prevent the Township from signing the Implementation Agreement, not any
    substantive land use ordinances themselves.
    Fourth and finally, Landowners argue it was error to deny the Application and
    Sewer Planning Module because, under the Pennsylvania Sewage Facilities Act,
    Landowners had the right to privately request that DEP revise the Act 537 Plan.
    While common pleas found Landowners did not complete the prerequisites for such
    relief, Landowners contend that they did comply with DEP’s regulations requiring a
    request to a municipality, here, Landowners’ Application, and a denial by the
    Township, here, the Township Manager’s email. Although common pleas, in its
    Rule 1925(a) Opinion, found nothing prevented Landowners from still submitting
    their request to DEP, Landowners argue DEP cannot require the Township to reverse
    the denial. According to Landowners, the Township should have approved the
    Application contingent upon Landowners receiving DEP approval. To the extent
    common pleas found, based on a statement in the email denial, that the request to
    DEP would have been futile, Landowners respond that this misses the point that
    Landowners’ right to make the request cannot be circumvented.
    The Township argues in response as follows. The email from the Township
    Manager sufficiently sets forth the reasons for denial, cites Ordinance 2013-20 as a
    basis, incorporates by reference May’s letter, which cites the Implementation
    Agreement, and provides Landowners with two options. Therefore, there was no
    deemed approval, and the Township acted in good faith. The Township argues
    Landowners cite no authority for the proposition that the Township cannot
    incorporate by reference a letter from a third party. The Township also argues that
    it acted in good faith in reviewing the Application. The Township also points out
    11
    that Landowners were advised at a pre-application meeting of the deficiencies in
    their plan. The Township further contends that Ordinance 2013-20 adopted the
    Implementation Agreement, which requires individual or community on-lot sewer
    systems, and there is no requirement that an ordinance must be part of a SALDO or
    zoning ordinance if it relates to land use. For support, it provides as examples
    ordinances related to driveways and stormwater management. The Township also
    argues Ordinance 2013-20 contained a repealer provision, which would have
    repealed any provisions from other ordinances that conflicted with Ordinance 2013-
    20 and the Implementation Agreement it adopted. Finally, the Township argues
    Landowners can still submit a private request to DEP for amendment of the Act 537
    Plan. In fact, the Township points out, this was one of the two options provided for
    in May’s letter. The Township asserts its denial actually opened the avenue for
    Landowners to pursue that DEP approval because one of the prerequisites for such
    relief is a denial by the municipality.
    In their reply brief, Landowners disagree the email constituted a valid denial.
    According to Landowners, the governing body of the Township, its Board of
    Supervisors, did not even act on the Application; rather, its Township Manager
    summarily denied it. Landowners also reiterate that the email did not incorporate
    May’s letter and the options provided therein were not really options. The first
    alternative essentially amounted to compliance, Landowners argue. The second
    option was to request expansion of the Regional Growth Boundary, which would
    have required the Township, which denied the Application, to authorize the request
    to CRCOG’s General Forum.           Landowners also reassert their argument that
    Ordinance    2013-20 merely        authorized Township     officials   to   sign   the
    Implementation Agreement and nothing more and that the repealer provision did not
    12
    affect the ordinances which allow the alternative sewer system that Landowners
    propose.    Landowners argue that the Implementation Agreement requires the
    member municipalities to amend their own ordinances, which the Township did not
    do. Landowners also argue that they should not be left to guess what, if anything,
    has been repealed.      Finally, Landowners argue that the Township misses
    Landowners’ point about the Act 537 Plan. Landowners contend they should have
    been given the opportunity to make the request to DEP and the Township should
    have approved the Application with the condition that Landowners receive such
    approval.
    III.   DISCUSSION
    Landowners first argue that the email denying the Application and Sewer
    Planning Module did not comply with the statutory requirements for a municipal
    decision. Section 508(2) of the MPC provides that a denial of an application “shall
    specify the defects found in the application and describe the requirements which
    have not been met and shall, in each case, cite to the provisions of the statute or
    ordinance relied upon.” 53 P.S. § 10508(2). “It is well-settled that this provision is
    mandatory.” Warwick Land Dev., Inc. v. Bd. of Supervisors of Warwick Twp.,
    Chester Cnty., 
    695 A.2d 914
    , 918 (Pa. Cmwlth. 1997). Section 215-7.F(3) of the
    Township’s SALDO also specifies the content of a decision by the Township: “If
    the plan is not approved, the decision shall specify the defects found in the plan and
    describe the requirements which have not been met and shall, in each case, cite the
    provisions of this chapter from which such defects or requirements originate.”
    (SALDO, § 215-7.F(3), R.R. at 776a.)           The failure to comply with these
    requirements results in a deemed approval of the application. 53 P.S. § 10508(3).
    13
    The Pennsylvania Supreme Court has explained that “the measure of the
    adequacy of a decision depends on whether it is sufficient to permit the applicant to
    understand the specific nature of the deficiency identified, so as to permit the
    applicant to take whatever further action it deems necessary or appropriate.”
    Kassouf v. Township of Scott, 
    883 A.2d 463
    , 474 (Pa. 2005). Importantly, the courts
    have held that an applicant’s actual knowledge of the deficiencies of the plan does
    not excuse noncompliance with Section 508(2). Lease v. Hamilton Township, 
    885 A.2d 684
    , 688 (Pa. Cmwlth. 2005); Dobrinoff v. Bd. of Supervisors of Franklin Twp.,
    
    582 A.2d 1156
    , 1160 (Pa. Cmwlth. 1990); Bensalem Township v. Blank, 
    539 A.2d 918
    , 951 (Pa. Cmwlth. 1988). Rather, the test is “whether this information is
    contained within the four corners of the written decision itself.”           Bensalem
    Township, 539 A.2d at 951.
    That is not to say that a municipality cannot incorporate by reference another
    document into its decision. In Kassouf, our Supreme Court addressed this exact
    issue. The Supreme Court reasoned that
    [i]f the reasons for a denial consist of defects which have already been
    adequately set forth in an engineer’s report, or other documentation
    provided to the developer and available to the municipal authority in its
    decision-making process, it would be a pointless evaluation of form
    over substance to require the authority to essentially cut-and-paste
    those conclusions into its own decision letter.
    Kassouf, 883 A.2d at 472.
    The Supreme Court, however, cautioned that while “there is no absolute
    impediment to incorporation by reference, [that] does not mean that any and all
    references to supporting documentation will provide, as a substantive matter, an
    adequate articulation of the reasons for a denial for purposes of Section 508(2).” Id.
    There, the Supreme Court stated the municipality’s “letter d[id] not refer to a specific
    14
    report, identifiable by title or date or subject matter,” did not include the words
    “incorporate by reference,” and did not attach the subject document to its letter. Id.
    “Instead, the decision letter merely and variously refers to the township engineer’s
    ‘comments,’ ‘requests’ or ‘requirements,’ which [the landowner] failed to satisfy,
    usually without any reference to the source or date of the comments.” Id. The
    Supreme Court further reasoned
    the subdivision applicant should not be left to guess at whether the
    township was truly relying upon an external document in lieu of its own
    Section 508 statement. Nor should the applicant be left to guess as to
    which of multiple documents is the one that would serve as the
    “incorporated” basis for the decision. If a municipal authority indeed
    intends for an external document to serve as the substantive explanation
    of the basis for its decision, it should make that point explicitly in the
    decision letter, and not ask the applicant, and the court system, to infer
    the point. Such a plain statement is a very simple task; and because the
    township commissioners did not make clear that such was their
    intention here, we must reject appellee’s incorporation by reference
    argument.
    Id. at 472-73. This Court has echoed that sentiment, holding “from a practical
    standpoint, incorporation by reference and attachment of such documentation is not
    in any way burdensome to the governing body and serves to protect it from claims
    that the developer did not receive a list of a plan’s deficiencies.” Lease, 
    885 A.2d at 690
    .
    Our Court has, on a number of occasions, reviewed the sufficiency of an
    alleged decision letter. For instance, in Advantage Development, Inc. v. Board of
    Supervisors of Jackson Township, 
    743 A.2d 1008
     (Pa. Cmwlth. 2000), we held that
    a decision that incorporated by reference a 16-page engineer’s report satisfied the
    requirements of Section 508(2). However, we found a township’s decision did not
    comport with Section 508(2) in Warwick Land Development where “we note[d] that
    15
    the [d]enial [l]etter itself d[id] not specifically cite any statute or ordinance provision
    which [the p]roperty [o]wner’s subdivision plan [wa]s said to have violated.” 
    695 A.2d at 918
    . The only citations therein were to two sections of the zoning ordinance,
    which did not “set forth any reason sufficient” to justify denial of the application.
    
    Id.
     Moreover, we found the township’s attempt to incorporate other documents into
    its decision was unsuccessful. We stated:
    [T]he [d]enial [l]etter refers to four different documents which, in turn,
    list numerous objections to [the p]roperty [o]wner’s subdivision plan.
    The [b]oard of [s]upervisors, however, makes no attempt to identify
    with any particularity which of the many concerns set forth in these
    documents form the basis for the [a]pplication denial and why. Instead,
    the [b]oard of [s]upervisors sweeps together the entire list of objections,
    indiscriminately labelling them all as reasons to deny the subdivision
    request without ever citing a single one of these reasons in the [d]enial
    [l]etter itself. Although it may well have valid grounds to deny [the
    p]roperty [o]wner’s subdivision plan, the [b]oard of [s]upervisors’
    resort to this type of indeterminate approach does not in our view satisfy
    the specificity requirements of [S]ection 508(2) of the MPC,
    particularly where so many of the objections seem wanting or otherwise
    fail to justify denial at this preliminary stage.
    
    Id. at 920
    . Accordingly, we concluded the denial letter did not provide the property
    owner with “the meaningful notice that [S]ection 508(2) was designed to provide.”
    
    Id. at 920-21
    .
    Here, the email appears to “specify the defects found in the [A]pplication and
    describe the requirements which have not been met,” leaving only the question of
    whether the email denial “cite[s] to the provisions of the statute or ordinance relied
    upon.” 53 P.S. § 10508(2). Landowners argue the email denial does not, as it only
    generally references Ordinance 2013-20 and the Implementation Agreement. The
    Township contends that Landowners knew of the deficiencies with the Application
    based upon a pre-application meeting with Landowners and that the email denial
    16
    incorporates May’s letter, which specifically identifies the relevant sections of
    Ordinance 2013-20 and the Implementation Agreement.
    As for the Township’s first argument, it is well-settled that an applicant’s
    actual knowledge of a plan’s deficiencies does not excuse a municipality from
    complying with Section 508(2) of the MPC and, here, the SALDO, which mirrors
    the MPC’s language. Lease, 
    885 A.2d at 688
    ; Dobrinoff, 
    582 A.2d at 1160
    ;
    Bensalem Township, 539 A.2d at 951.             We evaluate the sufficiency of a
    municipality’s decision based upon what “information is contained within the four
    corners of the written decision itself,” Bensalem Township, 539 A.2d at 951, unless
    the purported decision incorporates other documents by reference, in which case, we
    may consider those other documents, Kassouf, 883 A.2d at 472.
    That brings us to the Township’s second argument related to May’s letter.
    The email denial concludes by stating that “May’s letter lays out two different
    options for [Landowners] to pursue if [they] decide[] to submit a new application.”
    (R.R. at 17a.) The Township argues, and common pleas found, this was sufficient
    to incorporate May’s letter into the email denial. However, our Supreme Court has
    held that “[i]f a municipal authority indeed intends for an external document to serve
    as the substantive explanation of the basis for its decision, it should make that point
    explicitly in the decision letter, and not ask the applicant, and the court system, to
    infer the point.” Kassouf, 883 A.2d at 472 (emphasis added). “[A]ny and all
    references to supporting documentation” does not mean the documentation has been
    properly incorporated by reference, such that it can provide a basis for concluding
    the requirements of Section 508(2) are satisfied. Id. Here, the passing reference to
    May’s letter does not suffice. It is not clear whether May’s letter was attached to the
    email denial or that Landowners had been provided a copy of same, as May’s letter
    17
    was not addressed to Landowners and Landowners were not listed as being copied
    on same. Incorporating a document by reference “is a very simple task,” id. at 473,
    which we cannot conclude was done here.11
    Thus, we limit our review to “the four corners of the written decision itself.”
    Bensalem Township, 539 A.2d at 951. As stated, the email denial references
    Ordinance 2013-20 and the Implementation Agreement. Ordinance 2013-20 is a
    simple one-page ordinance to which there was no specific provision that needed to
    be cited. Although the Implementation Agreement is longer and contains multiple
    sections, it is apparent from a review of the Implementation Agreement and the email
    that Section IX requiring on-lot systems and prohibiting alternative public
    wastewater treatment systems is the basis for the Township’s decision. Therefore,
    the purpose behind Section 508(2) of the MPC appears to be satisfied and no deemed
    approval occurred.
    That brings us to the effect of Ordinance 2013-20. When interpreting an
    ordinance, courts are guided by principles of statutory construction. THW Grp., LLC
    v. Zoning Bd. of Adjustment, 
    86 A.3d 330
    , 336 (Pa. Cmwlth. 2014).
    Like statutes, the primary objective of interpreting ordinances is to
    determine the intent of the legislative body that enacted the
    ordinance. . . . In pursuing that end, we are mindful that an ordinance’s
    plain language generally provides the best indication of legislative
    intent. . . . Thus, statutory construction begins with examination of the
    text itself.
    
    Id.
     (internal citations omitted).
    11
    Even if the email denial did successfully incorporate by reference May’s letter, at best,
    it incorporated the two options May provided for resubmission. (See R.R. at 17a (“May’s letter
    lays out two different options for [Landowners] to pursue if [they] decide[] to submit a new
    application.”).) It makes no reference to the remainder of May’s letter such that one could
    conclude that the Township intended to incorporate by reference the entirety of May’s letter.
    18
    Ordinance 2013-20 plainly states that it “authorize[d] the Chair and the
    Secretary to execute [the Implementation] Agreement on behalf of the Board of
    Supervisors of the Township. . . .” (Ordinance 2013-20, R.R. at 19a.) Pursuant to
    Ordinance 2013-20, the Township did adopt the Implementation Agreement;
    however, there is no evidence the Township incorporated the requirements of the
    Implementation Agreement into its ordinances as required by Section IX of the
    Implementation Agreement. Section IX of the Implementation Agreement provides
    that “by enacting th[e Implementation Agreement], the [member m]unicipalities
    agree to incorporate the requirements described [therein] into their municipal sewage
    management ordinances.” (R.R. at 31a.)
    The Township appears to argue that Ordinance 2013-20 was sufficient to
    accomplish this because it contained a general repealer provision. However, the
    repealer provision does not provide that it is incorporating the requirements of the
    Implementation Agreement into the Township’s ordinances, as Section IX required;
    it only discusses repealing “[a]ll existing agreements, resolutions, and ordinances
    which are contrary to the provisions of this Ordinance.”12 (emphasis added). As
    12
    Had the repealer provision stated it was repealing “all existing agreements, resolutions,
    and ordinances which are contrary to the provisions of the Implementation Agreement,” instead
    of “contrary to the provisions of this Ordinance,” (R.R. at 19a (emphasis added)), we would agree
    with the Township that it would have repealed the ordinances on its books, which were contrary
    to the Implementation Agreement. While the Township may have intended for Ordinance 2013-
    20 to accomplish this, its language did not do so. THW Grp., LLC, 
    86 A.3d at 336
    . A review of
    the existing ordinances in the record provides further support for this conclusion. The Zoning
    Ordinance and SALDO contain references to additions and amendments throughout, including
    some that occurred after Ordinance 2013-20 was enacted. (See, e.g., R.R. at 827a-28a (reflecting
    amendments made in 2017).) The Zoning Ordinance and SALDO also contain “Editor’s Note[s],”
    which show that some provisions were repealed and/or deleted by subsequent ordinances. (See,
    e.g., R.R. at 574a, 580a, 582a, 598a, 608a, 610a, 617a-19a, 622a, 626a, 653a, 683a, 693a-94a,
    701a, 706a, 772a, 792a-93a, 797a, 804a, 819a, 833a-36a, 838a, 840a, 843a.) Notably, neither
    Section 255-13.C(3) of the Zoning Ordinance nor Section 215-19 of the SALDO, both of which
    (Footnote continued on next page…)
    19
    with statutes, the plain language of an ordinance is the best indicator of a
    municipality’s intent. THW Grp., LLC, 
    86 A.3d at 336
    . We cannot conclude that a
    repealer provision successfully incorporates new requirements into existing
    ordinances when its plain language makes no mention of incorporation. Therefore,
    the Application and Sewer Planning Module could not have been denied on that
    basis.
    IV.      CONCLUSION
    Although the email denial from the Township Manager was sufficient to
    comply with Section 508(2) of the MPC and Section 215-7.F(3) of the Township’s
    SALDO, the denial was based upon Article IX of the Implementation Agreement,
    which could not serve as the basis for the Township’s denial because the
    requirements set forth in the Implementation Agreement were never incorporated
    into the Township’s existing ordinances, as the Implementation Agreement, by its
    own terms, required. Accordingly, we reverse common pleas’ Order dismissing
    Landowners’ appeal and remand this matter for further remand to the Township to
    consider the Application and Sewer Planning Module under the Zoning Ordinance
    and SALDO as it existed at the time Landowners submitted the Application.13
    _____________________________________
    RENÉE COHN JUBELIRER, Judge
    permit community sewage plants, includes such references or “Editor’s Note[s].” (R.R. at 600a,
    803a-04a.)
    13
    Given our decision, it is unnecessary to address Landowners’ remaining arguments.
    20
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Green Acres One, LLC and Half Moon :
    Acres, LLC,                        :
    Appellants  :
    :
    v.                :         No. 336 C.D. 2020
    :
    Halfmoon Township, Centre County,  :
    Pennsylvania                       :
    ORDER
    NOW, April 21, 2021, the Order of the Court of Common Pleas of Centre
    County, dated February 25, 2020, is hereby REVERSED. This matter is remanded
    for further proceedings consistent with the foregoing opinion.
    Jurisdiction relinquished.
    _____________________________________
    RENÉE COHN JUBELIRER, Judge