D.A. Nolt, Inc. v. City of Lancaster ( 2021 )


Menu:
  •             IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    D.A. Nolt, Inc.,                        :
    Appellant    :
    :
    v.                               : No. 556 C.D. 2020
    : Argued: March 18, 2021
    City of Lancaster                       :
    BEFORE:      HONORABLE MARY HANNAH LEAVITT, Judge
    HONORABLE CHRISTINE FIZZANO CANNON, Judge
    HONORABLE J. ANDREW CROMPTON, Judge
    OPINION NOT REPORTED
    MEMORANDUM OPINION
    BY JUDGE CROMPTON                              FILED: May 12, 2021
    D.A. Nolt, Inc. (Contractor) appeals from an order of the Court of
    Common Pleas of Lancaster County (Trial Court) that ruled in its favor in part on
    its claims against the City of Lancaster (City) for breach of a publicly bid contract.
    Contractor challenges the amount of damages, asserting the Trial Court erred in not
    awarding attorney fees, costs, or penalties available under Section 3935 of the
    Commonwealth Procurement Code (Code), 62 Pa. C.S. §3935, when the Trial Court
    found the City violated the Code. Contractor argues the Trial Court abused its
    discretion and disregarded the evidence when it did not find that the City acted in
    bad faith by engaging another contractor for part of the project without public
    bidding. Contractor also seeks prejudgment interest on the damages awarded for
    breach of contract. Upon review, we reverse the Trial Court’s order in part as to the
    denial of prejudgment interest on the damage award and remand for recalculation and
    revision of the judgment to include same; we affirm in all other respects.
    I. Background
    This dispute centers on a publicly bid contract the City awarded to
    Contractor in August 2012 for green roof1 installation and “related improvements” as
    a means of stormwater management (Contract). Reproduced Record (R.R.) at 11a.
    The scope of work entailed installing green roofs on existing roofs on up to 10
    buildings and specifically included: “furnish[ing] all labor, superintendence, materials,
    necessary equipment, and other utilities and facilities for, perform[ing] all work
    necessary for or incidental to, and perform[ing] all other obligations imposed by this
    [Contract] for, the complete Work in connection with GREEN INFRASTRUCTURE
    PROGRAM 2012” (Project). R.R. at 18a. Contractor’s bid was based on a unit
    price for 10 buildings, priced at $30.00 per square foot. This litigation involves the
    work performed on two buildings, the Chlorine Building, which was part of the
    City’s water treatment facility, and the Stevens House, which was privately owned.
    To assist in the Project, the City appointed an engineering firm to
    review the structural integrity of selected roofs to sustain the additional weight of
    green roofs, and a green roof design firm to serve as the City’s agent. See Trial Ct.,
    Slip Op., 12/16/19, Finding of Fact (F.F.) Nos. 5, 6. The Project was part of the
    Stormwater Management (SWM) Department, overseen by its director (Director).
    Consequently, there were multiple contacts for communication on the Project from
    2012 to 2014, including City officials and private professionals at different times.
    The Contract required Contractor to obtain all necessary permits and to
    perform work in accordance with applicable codes and laws. F.F. No. 8. The
    Contract also required inspections to ensure the work was compliant. F.F. No. 11.
    1
    A green roof is comprised of organic materials, including soil and plantings, layered on
    a preexisting roof to aid stormwater management. See Trial Ct., Slip Op., 12/16/19, at 1 n.1.
    2
    The scope of the work changed during the Project, see F.F. No. 22, in part because
    existing roofs needed additional work as a prerequisite to green roof installation.
    Change orders2 were signed on the City’s behalf by the Mayor.
    With regard to the Chlorine Building, Contractor’s bid for installation
    was predicated on the roof being 2,500 square feet, at $30 per square foot, when
    the roof was 3,129 square feet. F.F. No. 16. Contractor advised the City of the
    discrepancy and that the work would be billed at the end of the Project based on the
    actual square footage. F.F. No. 17. Also, closer inspection of the Chlorine Building
    roof revealed that part of the roof (1,717 square feet) needed to be replaced to
    withstand installation, and the caps and stones around the roof were deteriorated.
    Roof replacement was within the scope of the Project, see F.F. Nos. 15, 21, whereas
    the cap/stone work was not. Contractor submitted an estimate in the form of a change
    order for the cap/stone work, to which the City did not respond. F.F. Nos. 19-20.
    For both tasks (roof replacement and cap/stone repair), the City sought
    quotes from other contractors without competitive bidding and without Contractor’s
    knowledge. Despite that replacing the roof membrane was within the Contract, F.F.
    No. 15, the City solicited quotes for partial roof replacement when it deemed
    Contractor’s pricing “very high.” F.F. No. 22. However, the City never issued a
    change order removing roof replacement from the Contract. F.F. No. 24. Instead,
    the City engaged a third party to perform that task. See R.R. at 108a. In October
    2013, Contractor installed the green roof after the other contractor completed the
    replacement work. The City paid Contractor for the installation. See F.F. No. 25.
    2
    Pursuant to the Contract, a “change order” means “a written order to the Bidder signed
    by the City ordering a change in Documents and is within the general scope and purpose of the
    work as originally shown.” Reproduced Record (R.R.) at 54a.
    3
    However, Contractor was not compensated for overhead or lost profits related to the
    roof replacement despite that it was within the scope of work.
    With regard to the Stevens House, in February 2013, Contractor noted
    there were structural issues that could necessitate roof replacement, which was not
    covered by the Contract. Contractor presented an estimate for roof replacement of
    $283,000, which the City rejected. F.F. No. 28. The City then requested change
    orders regarding the root barrier material and priming the existing roof for
    installation. Contractor prepared these change orders, which were approved by the
    Mayor and the City’s appointed engineer, for installing a root barrier in March 2013.
    F.F. No. 31. However, after delays based on the City’s negotiations with the private
    owner, this part of the Project was not commenced until spring 2014. F.F. No. 34.
    In 2014, Contractor requested a scan of the roof to ensure its integrity,
    which the City refused. Contractor sought a permit to commence work when
    requested to do so by the Code Officer, on May 6, 2014. F.F. No. 35. Contractor
    received the permit, which stated an inspection by the Code Officer was required
    prior to installation at the Stevens House. On May 12, 2014, the date the work was
    scheduled to begin at the Stevens House, the inspection was also to occur.
    However, the Code Officer called in sick the morning of the inspection; as a result,
    no inspection occurred. Nevertheless, Contractor performed work, relying on the
    signed change orders. Contractor also claimed the SWM Director agreed to pay
    for any work performed as scheduled in the event the roof was deemed unfit for
    completion per the Contract. The City did not pay for the work performed at the
    Stevens House, citing the lack of prior inspection.              Subsequently, it was
    determined the roof at the Stevens House was incapable of sustaining a green roof.
    Because it was privately owned, it was the owner’s decision not to move forward
    4
    with the green roof, and the work Contractor performed was removed and scrapped
    at no value. Ultimately, although Contractor billed the City $83,492.02 for this
    work, see F.F. No. 60, the City did not pay Contractor for its work at the Stevens
    House.
    In September 2015, Contractor filed a complaint against the City for
    breach of the Contract, (Count I), unjust enrichment (Count II), quantum meruit
    (Count III), and noncompliance with the Code (Count IV). It sought damages in
    the amount of $257,851.39, comprised of its damages for nonpayment for work at
    the Stevens House, and for overhead and lost profits at the Chlorine Building for
    reducing its scope of work, plus attorney fees, costs, and penalties under the Code.
    See F.F. No. 63. Relevant here, Contractor pled that it “invoiced the City for the
    work it completed at the Project and for its overhead and profit on the portion of
    the Contract work improperly removed from its scope of work at the Chlorine
    Building in the total amount of $506,826.36,” for which $103,796.97 remained due
    and owing. R.R. at 12a (Compl. ¶¶14-15). In its prayer for relief on its breach of
    contract claim, Contractor sought judgment in its favor for “$103,796.97, plus
    interest [and] costs of suit.” R.R. at 13a. In addition, Contractor alleged “[it] is
    entitled to recover interest at the statutory rate . . .” id. ¶34, which “will continue to
    accrue monthly during the pendency of this action.” R.R. at 14a.
    The City counterclaimed for costs of investigating the roof condition
    of the Stevens House. It alleged improper and incomplete performance as to that
    work, arguing Contractor did not secure the proper permits/inspections and so did
    not perform its work in accordance with the law as set forth in the Contract.3
    3
    The Trial Court determined that the damages the City sought in its counterclaim related
    to the potential litigation with this third party, not as a result of Contractor’s unauthorized work.
    5
    The Trial Court conducted a two-day bench trial during which it heard
    testimony and accepted evidence. In addition to presenting testimony of several
    witnesses, both parties submitted documentation to support their respective claims,
    including emails of communications concerning the Project.
    Based on the record, the Trial Court4 ruled in Contractor’s favor as to
    the Chlorine Building, concluding the City breached the Contract and violated the
    Code. However, it awarded a fraction of the damages Contractor claimed and did
    not award fees or penalties. Id. While the Trial Court ruled in Contractor’s favor on
    the City’s counterclaim, it determined that Contractor was not entitled to payment
    for its work at the Stevens House, finding that the work was not authorized. On
    December 16, 2019, the Trial Court issued an opinion containing extensive
    findings and legal conclusions in support of its order.
    Using Contractor’s estimate for the scope of work replacing the roof,
    bid at “$75,000, of which $23,362.58 constituted expected overhead and profit,”
    F.F. No. 26, the Trial Court awarded damages to Contractor for $16,045.36 (Trial
    Ct. Op. at 20), for the City’s breach as to the Chlorine Building. See also R.R. at
    218a. The Trial Court reduced the amount based on the actual square footage of
    roof replaced (1,717), which was less than the square footage in the bid.
    The Trial Court agreed that the City violated the Code in that the roof
    replacement of the Chlorine Building was within the initial scope of work, and so
    should have been bid, and the work removed from the Contract through a change
    order. Conclusion of Law (C.L.) Nos. 10-11. However, the City did not issue such
    a change order. F.F. No. 24, R.R. at 219a. By engaging another contractor to
    replace part of the roof without bidding, the City violated the Code. C.L. No. 11.
    4
    The matter was assigned to President Judge Ashworth, as the initial trial judge recused.
    6
    Notwithstanding that it found a violation of the Code, the Trial Court
    declined to find bad faith. Rather, it reasoned the City made an error in construing
    the process, and not recognizing that once the roof replacement was part of the
    Contract, it was subject to public bid on equal terms with Contractor. See Trial Ct.
    Op. at 19. Deeming this a mistake, the Trial Court concluded the City’s improper
    removal of work from the Contract without giving Contractor an opportunity to
    match the quotes, “was not arbitrary.” Id. at 22. It also reasoned the City did not act
    vexatiously because any delays in soliciting estimates and roof replacement from
    another contractor were immaterial when Contractor did not later perform that work.
    Id. As a result, it denied Contractor’s claims for attorney fees, costs and penalties.
    As to the Stevens House, the Trial Court determined Contractor was
    not authorized to perform the work for which it sought payment. See F.F. No. 44.
    It also noted there was no evidence in the record to support Contractor’s assertion
    that the SWM Director bound the City to paying Contractor for work performed.
    Contractor filed post-trial motions, which the Trial Court denied. See
    R.R. at 397a. Contractor appealed the Trial Court’s order to the Superior Court.5
    Contractor filed a concise statement of errors complained of on appeal pursuant to
    Pa.R.A.P. 1925(b), challenging the Trial Court’s neglect to award prejudgment
    interest, and asserting attorney fees, costs, and penalties should have been awarded
    under the Code for the City’s bad faith. Per Rule 1925(a), the Trial Court advised
    it was relying on its previously issued decision that contained its findings and
    conclusions. Following entry of the judgment for the damages awarded, the appeal
    was transferred to this Court. After briefing and argument, the matter is ready for
    disposition.
    5
    The City did not file a cross-appeal of the Trial Court’s denial of its counterclaim.
    7
    II. Issues
    Contractor ascribed multiple errors to the Trial Court involving its
    disposition of the contract claims as to work that was contracted for on the
    Chlorine Building, and as to work performed, but unpaid, on the Stevens House.
    Specifically, Contractor presents seven issues for review, which we group as related
    to the damages calculated and awarded for work within the Contract for the Chlorine
    Building, and failure to award damages for work done at the Stevens House.6
    Regarding the Chlorine Building, Contractor argues the Trial Court
    erred in not awarding damages for the contracted amount, including lost profits and
    overhead for roof replacement. Contractor also assigns error in that the Trial Court
    did not include prejudgment interest in the award. Additionally, Contractor asserts
    the Trial Court erred in declining to award attorney fees, costs and penalties under
    Subchapter D of the Code, known as the Prompt Pay Act, 62 Pa. C.S. §§3931-3939,
    when the Trial Court found the City violated the Code by engaging a third party to
    partially replace the roof without public bidding. Essentially, Contractor maintains
    6
    Contractor presented seven issues, paraphrased as follows:
    1) The Trial Court abused its discretion in not including attorney fees, costs and penalties
    in the damage award because the City engaged in bad faith in taking roof replacement at the
    Chlorine Building from Contractor and awarding it to another contractor without public bidding;
    2) The Trial Court ignored evidence that Contractor performed some work at Chlorine
    Building when it denied claims for attorney fees/costs and penalties under the Code;
    3) Prejudgment interest should have been awarded on damages as to Chlorine Building;
    4) The Trial Court disregarded evidence that City agreed Contractor would be paid for
    work performed at Stevens House, despite noncompletion;
    5) The Trial Court disregarded evidence in finding Contractor in breach when the City
    directed it to begin work at Stevens House and was aware work was scheduled;
    6) The Trial Court disregarded evidence in finding a breach by Contractor when it began
    work on the Stevens House; and
    7) The Trial Court erred in deeming Contractor’s workmanship at the Stevens House
    defective.
    See Contractor’s Br. at 7-9.
    8
    that the Trial Court abused its discretion in not deeming the City to have acted in
    bad faith when it found the City violated the Code in contracting for roof work
    without competitive bidding.7
    Regarding the Stevens House, Contractor contends that it was entitled
    to recover payment from the City for work performed, despite its removal, because
    the SWM Director agreed that any work completed would be compensated in the
    event the roof was deemed unsound for complete green roof installation.
    Contractor maintains the City was bound by the SWM Director’s agreement.
    III. Discussion
    A. Procurement Code
    The Prompt Pay Act governs the construction contract between the
    City and Contractor. See E. Coast Paving & Sealcoating, Inc. v. N. Allegheny Sch.
    Dist., 
    111 A.3d 220
    , 232 (Pa. Cmwlth. 2015). Relevant here, the Prompt Pay Act
    requires payment for work done, 62 Pa. C.S. §3931, and sets a schedule for
    payment even where the contract does not so provide. 62 Pa. C.S. §3932(b). In
    addition, the statute allows payment to be withheld when certain notice criteria are
    satisfied. 62 Pa. C.S. §3934(b). It also allows recovery of attorney fees, costs, and
    penalties when payment is withheld in bad faith. 62 Pa. C.S. §3935.
    B. Contract Claims
    1. Stevens House
    First, we consider whether the Trial Court erred in denying
    Contractor’s claim for payment of work performed on the Stevens House. There is
    7
    As the Trial Court concluded, once the City availed itself of public bidding for the
    Project (i.e., green roof installation), the partial roof replacement on the Chlorine Building
    became subject to the same process such that the City violated the Code in not bidding the roof
    replacement. See Am. Totalisator Co., Inc. v. Seligman, 
    414 A.2d 1037
    , 1040 (Pa. 1980).
    9
    no dispute that work was performed in installing a root barrier and green roof, both
    of which were scrapped because the roof was not structurally sound.
    The dispute focuses on whether Contractor should be able to recover
    for work performed when it knowingly went ahead with the work without an
    inspection of the roof by the Code Officer. Contractor asserted that the SWM
    Director advised that the City would pay for any work already performed if a roof
    scan showed that the roof could not support green roof installation. However, the
    Trial Court found that Contractor proceeded at its own risk when it installed material
    on a roof without the Code Officer’s inspection of the existing roof. F.F. No. 39.
    Because Contractor knowingly proceeded with installation, without the
    prerequisite inspection, when the permit required inspection prior to covering the
    existing roof, this Court agrees that the work performed at Stevens House was not
    authorized by the Contract. Roof substrate inspection was a precondition to green
    roof installation, and the Trial Court found that Contractor should have known
    before installing the root barrier and green roof that the Stevens House roof needed
    replacing because Contractor asked about testing its soundness. As such, the Trial
    Court did not err in determining that Contractor “took upon itself the attendant risks”
    when it proceeded with the install. Trial Ct. Op. at 15.
    Further, it was Contractor’s responsibility under the Contract to secure
    all permits and to comply with local codes in the installation. See R.R. at 32a.
    When Contractor obtained the permit, it advised a roof substrate inspection by the
    Code Officer was necessary prior to installation. Of import, there is no dispute that
    Contractor did not receive the inspection prior to installing the root barrier and green
    roof overlay.   Therefore, we discern no error by the Trial Court in denying
    Contractor’s claim for payment for its work at the Stevens House.
    10
    Contractor’s argument that the SWM Director had apparent authority to
    bind the City to make payment on these new terms, despite Contractor’s
    noncompliance with prerequisites for installation, is equally unavailing. The Trial
    Court did not find that the City advised Contractor that the SWM Director had the
    authority to authorize payment on terms other than the Contract on the City’s behalf.
    Because the Contract was clear about the prerequisites for the installation work, we
    agree with the Trial Court that Contractor proceeded with work at its peril.
    2. Chlorine Building
    To recap, Contractor challenges the amount of the award for the
    City’s breach of the Contract as to the Chlorine Building because it did not include
    prejudgment interest. Contractor also argues that because the Trial Court found a
    violation of the Code, it abused its discretion and disregarded the evidence in
    denying its claims for attorney fees, costs, and penalties.
    The Trial Court awarded $16,045.36 in damages to compensate
    Contractor for its lost profits and overhead on work contemplated by the Contract,
    i.e., roof replacement, but performed by a third party. The Trial Court determined
    the City breached the Contract when it reduced the scope of work under the
    Contract, and the damage award was designed to compensate Contractor for the
    roof replacement work not performed, on which it sought anticipated profits and
    overhead. Though Contractor billed the City in October 2013 for its lost profits
    and overhead on the roof membrane (existing roof), the City did not pay that bill.
    The City paid only for the green roof installation work, which is not at issue.
    Contractor seeks prejudgment interest on the damages award, disputes
    the amount of the award, and assigns error in that the Trial Court did not award
    attorney fees and costs or penalties for clear violations of the Prompt Pay Act.
    11
    (a) Prejudgment Interest
    An appellate court’s “review of an award of pre[]judgment interest is
    for abuse of discretion.” Kaiser v. Old Republic Ins. Co., 
    741 A.2d 748
    , 755 (Pa.
    Super. 1999) (citation omitted). “A court has discretion to award or not award
    prejudgment interest on some claims, but must or must not award prejudgment
    interest on others.” Cresci Constr. Servs., Inc. v. Martin, 
    64 A.3d 254
    , 258-59 (Pa.
    Super. 2013) (citations omitted).
    As our Supreme Court explained, prejudgment “[i]nterest has been
    defined ‘to be a compensation allowed to the creditor for delay of payment by the
    debtor,’ and is said to be impliedly due ‘whenever a liquidated sum of money is
    unjustly withheld.’” TruServ Corp. v. Morgan’s Tool & Supply Co., Inc., 
    39 A.3d 253
    , 264 (Pa. 2012) (citation omitted). Longstanding Pennsylvania law adopts the
    Restatement (Second) of Contracts with regard to awarding prejudgment interest.
    See Penneys v. Pa. R.R. Co., 
    183 A.2d 544
     (Pa. 1962). The applicable section of
    the Restatement provides:
    (1) If the breach consists of a failure to pay a definite sum in money or
    to render a performance with fixed or ascertainable monetary value,
    interest is recoverable from the time for performance on the amount
    due less all deductions to which the party in breach is entitled.
    (2) In any other case, such interest may be allowed as justice requires
    on the amount that would have been just compensation had it been
    paid when performance was due.
    Restatement (Second) of Contracts §354(1)-(2) (Am. Law Inst. 1981). Consequently,
    “a party is not chargeable with interest on a sum unless its amount could [be]
    determined . . . with reasonable certainty so that he could have made a proper tender.”
    Id. cmt. c. Thus, before awarding prejudgment interest, the court must identify
    whether the damages were ascertainable based on the nature of the breach. See id.
    12
    An award of prejudgment interest is mandatory when the amount is
    mathematically calculable or ascertainable from the contract. TruServ Corp., 39
    A.3d at 264; see A. Scott Enters., Inc. v. City of Allentown, 
    102 A.3d 1060
    , 1072-
    73 (Pa. Cmwlth. 2014), rev’d on other grounds, 
    142 A.3d 779
     (Pa. 2016). The
    recovery of prejudgment interest under this standard is a matter of law, not of
    discretion. TruServ Corp.; see also Cresci Constr. Servs., 
    64 A.3d at 258-59
    .
    Such interest is due even when a party contested the claims in good faith. See Ely
    v. Susquehanna Aquacultures, Inc., 
    130 A.3d 6
    , 16 (Pa. Super. 2015).
    Additionally, a reduction in the amount of damages does not render
    the amount non-discernible such that it does not qualify for prejudgment interest.
    See id.; Widmer Eng’g, Inc. v. Dufalla, 
    837 A.2d 459
     (Pa. Super. 2003). Indeed,
    “simply because a [factfinder] returns a verdict in an amount less than that prayed
    for does not convert an otherwise liquidated amount into an unliquidated amount
    upon which interest does not accrue.” Ely, 130 A.3d at 16.
    When damages are mathematically calculable, prejudgment interest is
    due at the statutory rate of six per cent per year. See Section 202 of the Act of
    January 30, 1974, P.L. 13, 41 P.S. §202. Prejudgment interest is due from the time
    payment was due or claimed until the entry of judgment. See, e.g., Commonwealth
    State Pub. Sch. Bldg. Auth. v. Noble C. Quandel Co., 
    585 A.2d 1136
     (Pa. Cmwlth.
    1991) (explaining timing for prejudgment interest award as based on when payment
    was due; remanding for recalculation of prejudgment interest on part of claim).
    Upon careful review of this case and the Trial Court’s findings, the
    damage award for lost profits and overhead was reasonably ascertainable such that
    prejudgment interest should have been awarded. Contractor consistently claimed a
    specific amount ($23,362.58) for overhead and lost profits related to the
    13
    replacement of the roof membrane of the Chlorine Building. The figure was
    derived from its bid documents that were incorporated in the Contract. However,
    the Trial Court reduced the amount claimed to account for the difference in square
    footage between the anticipated roof membrane replacement in the bid and the
    partial roof replacement. Using Contractor’s bid, which was based on 2,500 square
    feet, the Trial Court reduced the amount of damages claimed for lost profits and
    overhead related to roof replacement to reflect the square footage actually replaced,
    1,717 (F.F. No. 18), to derive its award of $16,045.36. All of these figures were
    available and ascertainable at the time Contractor submitted an invoice to the City
    for payment of lost profits and overhead related to the Chlorine Building on October
    23, 2014. See R.R. at 267a (Notes of Testimony, 2/4/19, at 135, explaining amounts
    were due and owing since 2014). Accordingly, prejudgment interest is calculable
    from the date of the invoice that presented the claim for lost profits and overhead,
    which was reduced from $23,362.58 to $16,045.36. See Noble C. Quandel Co.
    Notably, the Trial Court’s decision denying prejudgment interest is
    inconsistent with its methodology of determining the award based on the evidence
    Contractor submitted as to its overhead and lost profits. F.F. No. 26; C.L. No. 12.
    The Trial Court calculated damages related to the City’s reduction of work under
    the Contract using a mathematical formula derived from the per unit/square foot
    price contained in the Contract documents and the actual square footage replaced.
    Since the amount was ascertainable from the Contract, F.F. Nos. 15-
    18, the Trial Court erred in denying prejudgment interest. Accordingly, that part of
    the Trial Court’s order dated December 16, 2019, is reversed, and the matter is
    remanded for the Trial Court to recalculate the judgment to include prejudgment
    interest at the statutory rate of 6% from the date when payment was due upon
    14
    Contractor’s claim for overhead and lost profits on the replacement aspect of the
    Chlorine Building until the judgment.
    (b) Attorney Fees, Costs, & Penalties (Bad Faith)
    Lastly, we address Contractor’s contention that it is entitled to
    attorney fees, costs, and penalties based on the City’s bad faith in negotiating for
    and securing another contractor to replace part of the roof on the Chlorine Building,
    without utilizing the public contract process. Contractor’s claims are based on the
    Trial Court’s determination that the City violated the Code. Contractor maintains
    that because the Trial Court found the City committed a violation of the Code, it
    was a clear abuse of discretion for the Trial Court to not also find bad faith.
    The Prompt Pay Act, relating to attorney fees/litigation costs and
    penalties, states as follows:
    (a) Penalty. -- If arbitration or a claim with the Board of Claims or a
    court of competent jurisdiction is commenced to recover payment due
    under this subchapter and it is determined that the government
    agency, contractor or subcontractor has failed to comply with the
    payment terms of this subchapter, the arbitrator, the Board of Claims
    or the court may award, in addition to all other damages due, a
    penalty equal to 1% per month of the amount that was withheld in bad
    faith. An amount shall be deemed to have been withheld in bad faith
    to the extent that the withholding was arbitrary or vexatious. An
    amount shall not be deemed to have been withheld in bad faith to the
    extent it was withheld pursuant to section 3934 (relating to
    withholding of payment for good faith claims).
    (b) Attorney fees. -- Notwithstanding any agreement to the contrary,
    the prevailing party in any proceeding to recover any payment under
    this subchapter may be awarded a reasonable attorney fee in an
    amount to be determined by the Board of Claims, court or arbitrator,
    together with expenses, if it is determined that the government
    agency, contractor or subcontractor acted in bad faith. An amount
    shall be deemed to have been withheld in bad faith to the extent that
    the withholding was arbitrary or vexatious.
    15
    62 Pa. C.S. §3935 (emphasis added). The statutory language uses the permissive
    form of may, leaving the determination of whether to award penalties or attorney
    fees and costs as a matter of discretion.
    Also by its terms, under the Prompt Pay Act, actions are in “bad faith”
    when they are arbitrary or vexatious. Cummins v. Atlas R.R. Constr. Co., 
    814 A.2d 742
    , 747 (Pa. Super. 2002).       Although the statute does not define the terms
    “arbitrary” and “vexatious,” decisions construing these terms in the procurement
    context instruct that we define the terms based on their “popular and plain
    everyday sense, and popular meanings of such words must prevail.” 
    Id.
     (citation
    omitted). See also 1 Pa. C.S. §1903(a) (“Words and phrases shall be construed
    according to . . . their common and approved usage . . . .”). Webster’s Dictionary
    defines “arbitrary” as “determined by impulse or whim” and “vexatious” as
    “causing or creating vexation” which is then defined as “a source of annoyance or
    irritation.” Id. (citing Webster’s II New Collegiate Dictionary 57, 1229 (2001)).
    Our Supreme Court clarified in its opinion reversing our decision in A.
    Scott Enterprises v. City of Allentown, 
    142 A.3d 779
     (Pa. 2016), that the imposition
    of penalties and attorney fees is not mandatory under the Prompt Pay Act, even
    where there is a finding that a government agency has “acted in bad faith.” A. Scott
    Enters., 142 A.3d at 783 (reversing this Court’s holding that “Section 3935 of the
    Procurement Code requires the imposition of attorne[y] fees and the statutory
    penalty upon a [factfinder’s] finding of bad faith”).
    In an unreported decision also involving a bad faith claim under the
    Prompt Payment Act, this Court recognized that a difficulty in agreeing on change
    orders or how to address problems as they arise over the course of a project, while
    laden with misunderstanding, does not implicate bad faith.             See Trinity
    16
    Contracting, Inc. v. Mun. Sewage Auth. (Pa. Cmwlth., Nos. 523 & 524 C.D. 2015,
    filed Dec. 15, 2015), 
    2015 WL 8776568
     (unreported).8 Moreover, this Court may
    not reject a factfinder’s bad faith determination absent a clear abuse of discretion.
    James Corp. v. N. Allegheny Sch. Dist., 
    938 A.2d 474
    , 489 (Pa. Cmwlth. 2007).
    Critically, the necessary predicate finding of bad faith is absent from
    the Trial Court’s extensive and thorough findings. See generally Trial Ct. Op., F.F.
    Nos. 1-64.     Here, the Trial Court did not deem the City’s actions in asking
    Contractor to prepare change orders for work it was simultaneously engaging
    another contractor to perform as vexatious or arbitrary. To the contrary, the Trial
    Court characterized the City’s actions as erroneous and mistaken, not bad faith.
    See Trial Ct. Op. at 21 (“mere failure to adhere to the required contracting process,
    however, does not appear to constitute bad faith”). The Trial Court found that the
    City’s violation of the Code in not bidding the roof replacement for the Chlorine
    Building was not intentional; rather, it was an “incorrect interpretation of the law
    and the facts of this case” when the City did not recognize that the partial roof
    replacement, which was within the scope of work for the Project, F.F. No. 15, had to
    be publicly bid. 
    Id.
    This Project was fraught with confusion in that it seems more than one
    officer or engineer was utilized in the Project, and there was some question as to
    who had the ultimate authority to permit the continuation of the Project, set terms,
    and make other decisions on the City’s behalf. Nonetheless, applying an abuse of
    8
    We cite this unreported decision for its persuasive value in accordance with Section
    414(a) of this Court’s Internal Operating Procedures, 
    210 Pa. Code §69.414
    (a).
    17
    discretion standard,9 A. Scott Enters., 142 A.3d at 790, this Court discerns sufficient
    grounds to uphold the Trial Court’s conclusion that the City’s conduct did not
    amount to bad faith under the Prompt Pay Act.
    Additionally, we recognize that whether to award attorney fees and
    costs is a matter entirely within a trial court’s discretion. Cummins. Further, “[t]he
    trial court has great latitude and discretion with respect to the amount of an attorney
    fee award under the Prompt Pay Act.” Klipper Constr. Assocs., Inc. v. Warwick
    Twp. Water & Sewer Auth. (Pa. Cmwlth., Nos. 471 & 792 C.D. 2014, filed Dec. 16,
    2014), slip op. at 27, 
    2014 WL 10316918
    , at *12 (unreported). We discern no abuse
    of discretion that warrants a remand for inclusion of attorney fees and costs here.
    IV. Conclusion
    For the foregoing reasons, we reverse the Trial Court’s order
    containing the damage award in Contractor’s favor to the extent it excluded
    prejudgment interest. We remand the matter to the Trial Court, as to the damages
    calculation only, to recalculate the award to include prejudgment interest from the
    date payment was due on the invoice corresponding to overhead and lost profits for
    the replacement of the roof membrane on the Chlorine Building until the entry of
    judgment. We affirm the Trial Court’s order in all other respects.
    ______________________________
    J. ANDREW CROMPTON, Judge
    9
    “Abuse of discretion is shown where the trial court misapplies the law or its decision is
    manifestly unreasonable, arbitrary or capricious, or was motivated by partiality.” James Corp. v.
    N. Allegheny Sch. Dist., 
    938 A.2d 474
    , 483 n.7 (Pa. Cmwlth. 2007).
    18
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    D.A. Nolt, Inc.,                          :
    Appellant       :
    :
    v.                                 : No. 556 C.D. 2020
    :
    City of Lancaster                         :
    ORDER
    AND NOW, this 12th day of May 2021, the order of the Court of
    Common Pleas of Lancaster County that denied D.A. Nolt, Inc.’s post-trial
    motions, which challenged the calculation of damages underlying the verdict in its
    favor, and awarded damages in part on Contractor’s breach of contract claim is
    REVERSED IN PART, as to the denial of prejudgment interest on the damages
    awarded for work performed on the Chlorine Building, and is AFFIRMED IN
    PART in all other respects.
    IT IS FURTHER ORDERED that the matter is REMANDED to the
    Trial Court to recalculate the damage award to include prejudgment interest at the
    statutory rate of 6% and to modify the order and related judgment to include the
    recalculated total amount.
    Jurisdiction relinquished.
    ______________________________
    J. ANDREW CROMPTON, Judge