Brandywine Village Associates and L&R Partnership v. East Brandywine Twp. Board of Supervisors and Carlino East Brandywine, L.P. ( 2018 )


Menu:
  •            IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Brandywine Village Associates and     :
    L&R Partnership,                      :
    Appellants           :
    :
    v.                        : No. 1149 C.D. 2017
    : Argued: March 8, 2018
    East Brandywine Township Board        :
    of Supervisors and Carlino            :
    East Brandywine, L.P.                 :
    BEFORE:     HONORABLE MARY HANNAH LEAVITT, President Judge
    HONORABLE MICHAEL H. WOJCIK, Judge
    HONORABLE DAN PELLEGRINI, Senior Judge
    OPINION NOT REPORTED
    MEMORANDUM OPINION BY
    SENIOR JUDGE PELLEGRINI                             FILED: April 19, 2018
    Brandywine Village Associates (BVA) and L&R Partnership (L&R)
    (collectively, Objectors) appeal the order of the Court of Common Pleas of Chester
    County (trial court) affirming a decision by the Board of Supervisors (Board) of East
    Brandywine Township (Township) granting conditional preliminary approval of a
    Preliminary and Final Land Development Plan filed by Carlino East Brandywine,
    L.P. (Developer) for the construction of a mixed-use development on a 10-acre parcel
    that it owns in the Township.
    I.
    Developer is the equitable owner of an undeveloped tract of land located
    at 1279 Horseshoe Pike in East Brandywine Township, Chester County,
    Pennsylvania, containing approximately 10.118 acres (Property). The Property was
    originally part of a 21-acre parcel. BVA owns the remaining 11 acres, which contain
    a shopping center adjacent to the east side of the Property.
    Prior to Developer’s acquisition of the Property, BVA had certain rights
    to use the 10-acre parcel under a Cross Easement Agreement entered into with
    Developer’s predecessor in title. Because the entire 21 acres did not have access to
    any public sewer, the Cross Easement Agreement provided that BVA would build, at
    its expense, a sewer plant for the use of both parties on the 10-acre parcel. The Cross
    Easement Agreement also granted BVA an easement to the 10-acre parcel for
    stormwater management as well as an access easement to use the 10-acre parcel as a
    main entrance to BVA’s shopping center.1 L&R, the general partner of BVA, is the
    owner of an undeveloped parcel of land adjacent to the north side of the Property.
    1
    Under the Cross Easement Agreement, the predecessor-in-interest granted BVA a sewer
    system easement to install an on-site septic sewer system, including a drainage area and reserve
    drainage area. It also provided an access easement to allow construction of a roadway through the
    Property to BVA property. The Cross Easement Agreement specified that the access drive could be
    modified, but that it must not “interfere with the flow of traffic . . . or with surface water drainage.”
    (Reproduced Record (R.R.) at 205a.) The Cross Easement Agreement further provided a highway
    improvement easement, dedicating land within the ultimate right-of-way along Route 322 to public
    use, and a stormwater basin and drainage easement, which included a reserve effluent disposal area.
    2
    II.
    Throughout this dispute, Developer has submitted numerous versions of
    land development plans pertaining to the Property, all of which have been opposed by
    Objectors. Although this matter was before us previously, we quashed that appeal
    because what we were being asked to provide was an advisory opinion. Further
    complicating this is that the parties do not clearly state the issues presented to this
    Court on appeal. All of this is to say, be prepared (once again) for the procedural
    slog that follows.
    A.
    Since 2010, Developer has submitted land development plans to build a
    51,525 square-foot supermarket with a 9,250 square-foot expansion area, a 4,600
    square-foot attached retail building, and a pad site for a 4,088 squar-foot bank on the
    Property. From the beginning, the Township insisted that Developer provide and pay
    for the construction of a road (Connector Road) connecting the Property with
    Horseshoe Pike (Route 322) on which it fronts and North Guthriesville Road.
    Because the Connector Road was to cross over L&R’s adjoining
    property, in 2014, the Township and Developer entered into a Memorandum of
    Understanding (MOU). Under this MOU, Developer, in lieu of paying a significant
    portion of the Township’s transportation impact fee of $1,795,000, was obligated to
    design, permit and construct at its expense the Connector Road and dedicate it to the
    Township. The MOU also provided that the Township would condemn necessary
    portions of L&R’s adjoining property as well as BVA’s easements on the Property
    granted under the Cross Easement Agreement.
    3
    B.
    Although Developer has submitted several different versions of land
    development plans pertaining to the Property, there are two particular preliminary
    plans that have been subject to much litigation. The first of those plans was filed on
    December 9, 2014 (2014 Plan).             Therein, Developer treated and identified the
    Connector Road as a “driveway,” notwithstanding that it would eventually be
    dedicated to the Township as a public road. The 2014 Plan also included the area
    under the “driveway” as part of Developer’s land area. The 2014 Plan did not
    identify the previously condemned BVA easements on the Property.
    In January 2015, the Board conditionally approved the 2014 Plan
    (Original 2015 Decision). Objectors appealed that decision on February 20, 2015
    (2015 Appeal) and Developer intervened.
    C.
    Before the trial court, Objectors alleged, inter alia, that the 2014 Plan
    contained numerous defects, including the following:
         It did not comply with the Township’s Zoning
    Ordinance (Zoning Ordinance) requirement of a minimum
    10-acre area to build a mixed-use development in a Mixed
    Use (MU) zoning district.2
        It did not comply with Section 399-46.C of the
    Zoning Ordinance, requiring that “[n]o building shall be
    2
    Section 399-46.A of the Zoning Ordinance provides that “[a] minimum gross tract area of
    10 acres shall be required for any use or combination of uses permitted in the MU District.” (R.R.
    at 136a.)
    4
    situated less than 85 feet from the front lot line” because the
    bank building, as designed on the 2014 Plan, is set back 50
    feet from the Connector Road. (R.R. at 136a.) Developer
    argued that the Connector Road was merely a private
    driveway until such time as it is dedicated to the Township,
    and therefore, the 85-foot setback requirement is
    inapplicable.
           Even though the Property was going to be connected
    to the public sewer system, the 2014 Plan violated Section
    399-47.K3 of the Zoning Ordinance, providing that sewage
    facilities must be in compliance with the Township’s
    Subdivision and Land Development Ordinance (SALDO),
    Sections 350-47.B(2)4 & 350-48.5 BVA argued that this
    3
    Section 399-47.K of the Zoning Ordinance provides:
    Sewage facilities and water supply. The applicant’s proposals for
    sewage facilities and for water supply (both quality and quantity) in
    relation to the proposed uses shall be in compliance with the
    requirements of §§ 350-47 and 350-48, respectively, of Chapter 350,
    Subdivision and Land Development. Any approval of an application
    for development within the MU District shall be contingent upon the
    requisite approvals and certifications from the Chester County Health
    Department and/or the Pennsylvania Department of Environmental
    Protection.
    (R.R. at 137a.)
    4
    Section 350-47.B(2) of the SALDO provides in pertinent part:
    All subdivisions and land developments shall be self-sustaining
    relative to the storage and disposal of treated sewage effluent. The
    applicant shall provide sufficient storage and land area on or off the
    subdivision or land development site to store and dispose of all treated
    sewage effluent which is generated by the uses on the site by means
    of conventional underground seepage beds or drip irrigation.
    (R.R. at 616a.)
    5
    Section 350-48 of the SALDO pertains to water supply. (R.R. at 160a.)
    5
    provision was incorporated into the Zoning Ordinance and
    could not be waived.
         It did not comply with Section 399-81.E6 of the
    Zoning Ordinance because Developer failed to provide safe
    and efficient ingress and egress from Route 322 over the
    combined Connector Road to BVA’s shopping center.
        It did not comply with Section 399-47.N7 of the
    Zoning Ordinance, regarding stormwater management.
    6
    Section 399-81.E of the Zoning Ordinance provides that to minimize traffic congestion and
    encourage “orderly development of street highway frontage,” an applicant is responsible for
    providing:
    [S]afe and efficient ingress and egress to and from public streets,
    without undue congestion or interference with normal traffic flow
    within the Township. The developer shall be responsible for the
    design, construction, and costs of any necessary traffic control devices
    and/or highway modifications required by the Township and/or the
    Pennsylvania Department of Transportation.
    (R.R. at 141a-42a.)
    7
    Section 399-47.N of the Zoning Ordinance provides:
    The tract of land to be developed shall be in one ownership, or shall
    be the subject of an application filed jointly by the owners of the
    entire tract, and shall be under unified control. If ownership of the
    entire tract is held by more than one person or entity, the application
    shall identify and be filed on behalf of the said owners. Approval of
    the plan shall be conditioned upon agreement by the applicant or
    applicants that the tract shall be developed under single direction in
    accordance with the approved plan. If ownership of the tract changes
    subsequent to approval of the plan, no site preparation or construction
    by such new owner or owners shall be permitted unless and until such
    owner or owners shall review the terms and obligations of the
    approved plan and agree in writing to be bound thereby with respect
    to development of the tract.
    (R.R. at 137a-38a.)
    6
    Objectors then filed a motion for an additional evidentiary hearing,
    which the trial court granted, remanding the matter to the Board to take additional
    evidence. The Board conducted five hearings during which Objectors presented
    additional evidence in opposition to the 2014 Plan. In September 2015, because the
    parties disagreed as to the parameters of the Board’s obligation following the
    conclusion of the hearings, the trial court issued an order requiring the Board to
    consider all evidence presented on remand and to make a decision based upon the
    entire record.
    Then, in a decision dated October 1, 2015 (Revised 2015 Decision), the
    Board reversed the Original 2015 Decision granting conditional approval of the 2014
    Plan. It did so because it found that the 2014 Plan was deficient in that it violated
    certain ordinance provisions dealing with street design, stormwater management and
    treatment of sewage effluent. The Board did not revisit other issues that Objectors
    raised regarding the defects in the plan.
    D.
    Developer appealed the Revised 2015 Decision to the trial court.
    However, pursuant to a stipulation of the parties approved by the trial court,
    Developer withdrew that appeal and the parties agreed that they could raise all issues
    related thereto in the still-pending appeal of the Original 2015 Decision.
    On October 22, 2015, Developer filed a new Preliminary/Final Land
    Development Plan (2015 Plan), which was substantially similar to its previous plans
    and, once again, included a Connector Road through Developer’s property and
    7
    addressed the issues raised in the Revised 2015 Decision. The 2015 Plan was last
    revised on December 9, 2015.
    The Board conditionally approved the 2015 Plan on April 20, 2016
    (2016 Approval), subject to Developer providing an updated Traffic Impact Study for
    the proposed development and complying with any recommendations of the
    Township traffic engineer. As pertinent, the Board also granted a requested waiver of
    § 350-47.B.2 of SALDO (sewage effluent requirements) and Section 350-40.N.2 of
    SALDO (radius requirements for non-residential driveways).            The Board also
    determined that Developer “shall comply with the provision of § 350-36 [of SALDO]
    (Acceleration, deceleration and turning lanes) or request a waiver of the same from
    the Board.” (R.R. at 17a.)
    Objectors appealed, raising almost identical issues to those raised against
    the 2014 Plan. And, once again, the trial court sent the matter back to the Board,
    which then conducted three evidentiary hearings where Objectors presented
    substantially similar testimony.
    The 2015 Plan that was conditionally approved by the Board in the 2016
    Approval is, ultimately, the subject of the instant appeal.
    III.
    While resolution of Objectors’ appeal of the 2016 Approval was still
    pending, on January 6, 2017, the trial court issued an Opinion and Order granting, in
    part, Objectors’ appeal of the Original 2015 Decision. Notwithstanding, the trial
    8
    court rejected numerous arguments offered by Objectors and made the following
    pertinent findings:
          Setback requirement: As to Objectors’ contention
    that Developer’s proposed bank building must be set back
    85 feet from both Route 322 and the proposed Connector
    Road,8 the trial court found that the development tract is a
    single lot within the meaning of the Zoning Ordinance
    fronting on Route 322. It found that meant the proposed
    bank building is not required to be set back 85 feet from the
    Connector Road, only Route 322.
          Minimum Lot Area: Objectors contended that the
    2014 Plan violated Section 399-46.A of the Zoning
    Ordinance, requiring that a development in a MU zoning
    district must have a minimum lot area of 10 acres because
    the area of the easements previously granted to BVA under
    the terms of the Cross Easement Agreement must be netted
    out from the gross tract area of 10.189 acres, leaving only a
    net lot area of 9.189 acres. The trial court rejected that
    argument because the Township’s taking of BVA’s
    easements on the Property did not take Developer’s
    8
    Section 300-17 of the Township’s Land Use Ordinance, provides: “Building Setback Line.
    An established line within a property defining the minimum required distance between any principal
    building and the adjacent right-of-way line of the street on which it fronts, to provide the front yard
    specified by Chapter 399.” Available at: https://ecode360.com/31873664 (last visited March 16,
    2018). Section 399-46.C of the Zoning Ordinance provides: “Minimum front yard. No building
    shall be situated less than 85 feet from the front lot line.” (R.R. at 136a.) Pertinent terms are
    defined in Section 399-9 of the Zoning Ordinance. The term “lot” is pertinently defined as a
    “parcel of land, undivided by any street or dedicated future street right-of-way.” (R.R. at 119a.)
    The front yard is defined as “[a] yard extending the full width of the lot, along the front lot line and
    extending in depth from the front lot line to the nearest point of a structure on the lot. . . .” (R.R. at
    134a.) The Zoning Ordinance defines the term, “lot line” as “[a] property boundary line of any lot
    held in single and separate ownership. . . .” (R.R. at 120a.) A front lot line is defined as “[a] lot
    line abutting any street and coinciding with any street line.” (R.R. at 120a.) The term “street line”
    is defined by the Zoning Ordinance, in pertinent part, as “[t]he dividing line between a lot and the
    outside boundary or right-of-way of a public street, road, or highway legally open or officially
    platted. . . .” (R.R. at 129a.)
    9
    underlying fee simple so that the land could be counted as
    complying with the land area requirement.
          Traffic: Objectors also contended that the proposed
    Connector Road is of inadequate width to provide for safe
    and efficient ingress and egress for delivery trucks to enter
    and exit both the development and BVA’s center, arguing
    that tractor trailers attempting to make required turning
    movements from Route 322 onto the Connector Road will
    be required to encroach on opposing travel lanes and raised
    concrete medians. Adopting the opinion of the Township
    engineer, the trial court found that Objectors did not prove
    the proposed access is either unsafe or inefficient and that
    the Board did not commit error in declining to deny the plan
    based upon that alleged violation.
    However, the trial court agreed with the Township that the
    plan was deficient in that it constricted the turning
    movements for tractor-trailers accessing the supermarket
    loading dock located at the rear of the Property. Ultimately,
    it went on to find that this issue could be rectified by
    adjusting the guardrails or an increase in the loading zone
    area.
           Stormwater Management: The trial court affirmed
    the Board’s finding that the 2014 Plan violated Section 399-
    47.N of the Zoning Ordinance, requiring that stormwater
    facilities must be located on a tract of land under one
    ownership, because permanent stormwater facilities are
    shown as being outside the development tract owned by
    either Developer or the Township. The 2015 Plan depicted
    those facilities as located on L&R’s land. It noted though
    that the 2015 Plan has been subsequently revised to locate
    those facilities within the area condemned by the Township
    for the Connector Road.
         Sewage Effluent: The trial court agreed with the
    Board that the 2015 Plan was deficient because it failed to
    provide the required effluent disposal area either on the
    development tract or elsewhere. However, it found that this
    was easily correctable because the new center will be
    connected to the public sewer system because the Board is
    empowered to grant a waiver from this SALDO regulation
    10
    pursuant to Section 503(8) of the Pennsylvania
    Municipalities Planning Code (MPC)9 upon meeting the
    standard for waiver.
    However, the trial court disagreed with Objectors’ argument
    that because Section 399-47.K of the Zoning Ordinance
    incorporates the SALDO provision, the MPC’s traditional
    zoning variance hardship standards apply rather than the
    waiver requirement within the MPC. The trial court found
    that argument meritless because the Zoning Ordinance
    merely references the necessity of a developer’s compliance
    with the SALDO provision, but does not incorporate it into
    the Zoning Ordinance.
    Objectors appealed to this Court, arguing that the trial court erred in
    finding that: (1) Developer did not violate the front-yard setback requirement in the
    Zoning Ordinance; (2) SALDO’s requirement to set aside land for sewage effluent is
    not a zoning regulation by incorporation; and (3) Developer met its burden to
    establish that its 2014 Plan provided safe and efficient ingress and egress.
    However, because Objectors were the prevailing party below, the
    Township requested for the appeal to be quashed because Objectors lacked standing
    to bring the appeal. In response, Objectors argued that they were aggrieved by the
    9
    Section 503(8) of the Pennsylvania Municipalities Planning Code, Act of July 31, 1968,
    P.L. 805, as amended, 53 P.S. § 10503(8), provides:
    Provisions for administering waivers or modifications to the
    minimum standards of the ordinance in accordance with section §
    512.1 when the literal compliance with mandatory provisions is
    shown to the satisfaction of the governing body or planning agency,
    where applicable, to be unreasonable, to cause undue hardship, or
    when an alternative standard can be demonstrated to provide equal or
    better results.
    11
    trial court’s determinations because in any future appeals, Objectors will be estopped
    from raising issues the trial court decided against them.
    Ultimately, we agreed with the Township and quashed Objectors’ appeal
    for lack of standing. Rejecting Objectors’ concern, we further explained, “collateral
    estoppel will not apply to those determinations because those purportedly adverse
    determinations against Objectors, as the prevailing party, were not ‘essential’ to the
    judgment below.” Brandywine Village Associates v. East Brandywine Township
    Board of Supervisors (Pa. Cmwlth., No. 164 C.D. 2017, filed January 5, 2018) (citing
    Callowhill Center Associates, LLC v. Zoning Board of Adjustment, 
    2 A.3d 802
    , 809
    (Pa. Cmwlth. 2010)) (emphasis added) (“Brandywine I”).
    IV.
    Prior to our disposition of Brandywine I, the trial court issued an order
    dated July 18, 2017 (2017 Decision) denying Objectors’ appeal of the 2016 Approval.
    And, of course, that decision, which is the subject of this appeal, construed the
    Original 2015 Decision as denying Objectors’ appeal of the 2015 Approval, finding
    that any issue also raised by Objectors in the Original 2015 Decision were barred by
    the doctrine of collateral estoppel.
    Notwithstanding, the trial court went on to resolve various issues on
    appeal. For instance, for the first time, Objectors challenged the Board’s granting a
    waiver of: (1) Section 350-40.N.2 of SALDO, which requires that non-residential
    driveways have a minimum radius of 30 feet; and (2) Section 350-36, which pertains
    to deceleration lanes. Objectors also reasserted their challenge to the waiver of a
    12
    sewage effluent provision, contending that because Section 399-47.K of the Zoning
    Ordinance incorporates SALDO provision, the MPC’s traditional zoning variance
    hardship standards apply rather than the waiver requirement within the MPC.
    The trial court rejected each of Objectors’ challenges. As pertinent, it
    found that waiver of Section 350-40.N.2 (radius requirements for non-residential
    driveways) was proper because the credible testimony offered by both traffic experts
    established that “literal enforcement of the radius requirement . . . would require
    shifting the Connector Road to the West, thereby reducing the separation of traffic
    signals on Route 322 . . . . [and] would not improve Brandywine Center’s access,
    which is fixed by the existing travel isles within that development.” (Trial Court
    Opinion dated July 18, 2015 at 25-26.) The trial court rejected Objectors’ contention
    that waiver of Section 350-47.B.2 of SALDO (pertaining to sewage effluent) was not
    permitted because it was incorporated under the Zoning Ordinance. The trial court
    also found their challenge to the purported waiver of Section 350-36.B.3 (pertaining
    to deceleration lanes) meritless because the Connector Road was not, in fact, a
    deceleration lane. This appeal followed.10
    V.
    Although neither party acknowledges our disposition of Brandywine I,
    upon review, it is obvious that the trial court erred when concluding that the Original
    10
    In a land use appeal where a full and complete record was made and the trial court took no
    additional evidence, our scope of review is limited to determining whether the board committed an
    error of law or an abuse of discretion. In re Brandywine Realty Trust, 
    857 A.2d 714
     (Pa. Cmwlth.
    2004).
    13
    2015 Decision denied Objectors’ appeal and that all issues identical to those raised in
    the previous decision were barred under the doctrine of collateral estoppel.
    Notwithstanding, because the Board serves as factfinder and the trial court took no
    additional evidence below, we still reach each of Objectors’ challenges against
    conditional preliminary approval of the 2015 Plan.
    A.
    It is beyond well settled that a preliminary plan must be approved if it
    meets all specific, objective requirements under a subdivision and land development
    ordinance. Herr v. Lancaster County Planning Commission, 
    625 A.2d 164
     (Pa.
    Cmwlth. 1993). The preliminary plan is essentially conditional in nature in that after
    its approval, the developer must still fulfill all the requirements to obtain final
    approval. Graham v. Zoning Hearing Board of Upper Allen Township, 
    514 A.2d 236
    (Pa. Cmwlth. 1986). Consequently, even where the preliminary plan fails to comply
    with the objective, substantive requirements, the governing body may in its discretion
    either reject the plan outright or grant conditional approval. Schultheis v. Board of
    Supervisors of Upper Bern Township, 
    727 A.2d 145
     (Pa. Cmwlth. 1999). Further, the
    preliminary plan containing minor defects correctable by amendment must be
    approved subject to a condition that necessary corrections be made. Shelbourne
    Square Association v. Board of Supervisors of Township of Exeter, 
    794 A.2d 946
     (Pa.
    Cmwlth. 2002). Once a preliminary application has been approved, the applicant is
    entitled to final approval in accordance with the approved preliminary plan.
    14
    Section 503(8) of the MPC, 53 P.S. § 10503(8), expressly authorizes a
    municipality to enact provisions for administering waivers or modifications of literal
    compliance with the provisions of its SALDO. It provides:
    The subdivision and land development ordinance may
    include, but need not be limited to: . . . (8) Provisions for
    administering waivers or modifications to the minimum
    standards of the ordinance in accordance with section 512.1,
    when the literal compliance with mandatory provisions is
    shown to the satisfaction of the governing body or planning
    agency, where applicable, to be unreasonable, to cause
    undue hardship, or when an alternative standard can be
    demonstrated to provide equal or better results.
    Id. Moreover, Section 512.1 of the MPC11 vests discretion with the Township to
    grant or deny waivers.
    (a) The governing body or the planning agency, if
    authorized to approve applications within the subdivision
    and land development ordinance, may grant a modification
    of the requirements of one or more provisions if the literal
    enforcement will exact undue hardship because of peculiar
    conditions pertaining to the land in question, provided that
    such modification will not be contrary to the public interest
    and that the purpose and intent of the ordinance is observed.
    (b) All requests for a modification shall be in writing and
    shall accompany and be a part of the application for
    development. The request shall state in full the grounds and
    facts of unreasonableness or hardship on which the request
    is based, the provision or provisions of the ordinance
    involved and the minimum modification necessary.
    11
    Act of July 31, 1968, P.L. 805, as amended, added by Section 40 of the Act of December
    21, 1988, P.L. 1329, 53 P.S. § 10512.1.
    15
    Section 350-62 of SALDO, entitled “Relief from unnecessary hardship,”
    sets the Board’s authority to grant a waiver.
    A. In any case in which an applicant demonstrates to the
    satisfaction of the Board that strict application of any
    provisions of this chapter would be unreasonable and would
    cause unnecessary hardship as applied to the proposed
    subdivision or land development, the Board may grant a
    modification of such provision so as to grant relief from the
    unnecessary hardship. Any such modification granted shall
    be the least modification necessary to grant relief from the
    unnecessary hardship and shall be applied so that
    substantial justice may be done and the public interest
    secured; provided, however, that such modification shall
    not be granted if it would have the effect of nullifying the
    intent and purpose of this chapter.
    B. In granting modifications, the Board may impose such
    conditions as will, in its judgment, secure substantially the
    objectives of the standards and requirements so modified.[12]
    B.
    Objectors contend that the trial court erred in finding that the proposed
    bank building is not required to have an 85-foot setback from the Connector Road.
    Section 399-46.C of the Zoning Ordinance provides a setback of 85 feet for all
    buildings from the front lot line. Section 399-9 of the Zoning Ordinance defines a
    “front lot line” as:
    The lot line abutting any street and coinciding with any
    street line. In the case of a corner lot, each of the two (or
    12
    Although not provided in the Reproduced Record, SALDO Section 350-62 is available at:
    https://ecode360.com/11881470 (last visited March 16, 2018).
    16
    more) street-abutting lot lines shall be considered a front lot
    line. In the case of an interior lot, the front lot line shall be
    the line most parallel and closest to the street line at the end
    of the access strip; all other lines shall be side or rear lot
    lines.
    (R.R. at 120a) (emphasis added).            Furthermore, “street” is defined in Zoning
    Ordinance § 399-9 as:
    A right-of-way intended for general public use to provide
    means of approach for vehicles and pedestrians. The word
    “street” includes the words “road,” “highway,”
    “thoroughfare,” and “way.”
    (R.R. at 129a.) “Street line” is defined in Zoning Ordinance § 399-9 as:
    The dividing line between a lot and the outside boundary or
    right-of-way line of a public street, road, or highway legally
    open or officially platted, or between a lot and a privately
    owned street, road, or way over which the owners or tenants
    of two or more lots, each held in single and separate
    ownership, have the right of way. (Id.)
    Central to this dispute is Developer’s insistence that the Connector Road
    is actually a “driveway.”13 If it is found that the Connector Road is a “street,” then
    the setback requirement stated above will become applicable.
    13
    Section 300-17 of the Township’s Land Use Ordinance defines a “Driveway” as “A
    private means of vehicular access from a public or private street to a single lot.” Available at:
    https://ecode360.com/31873664 (last visited March 16, 2018).
    17
    We disagree with Developer that the Connector Road is a “driveway”
    because that position is inconsistent with the purpose of the underlying taking, the
    2015 Plan, and the MOU between the Township and Developer. The 2015 Plan
    specifically provides in a note that the purported driveway “will be ultimately used as
    a public road.” (R.R. at 181a.) This note is consistent with the MOU that Developer
    entered into with the Township, which provides:
    In order to support existing volumes of traffic and traffic
    projected to be generated by new growth and development
    in the Township, the Township has an interest in creating a
    new public road connecting Horseshoe Pike to North
    Guthriesville Road (“Connector Road”).
    The Connector Road would traverse the eastern side of the
    Carlino Property and extend northward through [L&R’s
    property].
    ***
    The Connector Road is intended as a public road for use
    by the general public and is not necessary for the
    development of [Developer’s] Property. The Township
    has made an independent judgment that the Connector Road
    is in the public interest and for a public purpose.
    The Township has informed Developer that the Township
    would like the Connector Road constructed by Developer in
    connection with development of the Project.
    ***
    In the event the Project receives final land development
    approval and all necessary permits, Developer will, at its
    sole expense, design, permit and construct the Connector
    Road in conjunction with the Project, in accordance with
    Township and Pennsylvania Department of Transportation
    requirements, and when completed, dedicate the Connector
    Road, the associated right-of-way and all related facilities
    18
    and improvements to the Township, at no cost to the
    Township and prior to the issuance of the first certificate of
    occupancy for a building on the [Developer’s] Property.
    (R.R. at 83a-85a) (emphasis added).
    In a separate action, Objectors raised preliminary objections before the
    trial court challenging, inter alia, the Township’s taking for the construction of the
    Connector Road. The trial court denied those preliminary objections, concluding, in
    pertinent part, that the taking was for a public purpose and that the condemnation is
    intended to be used to construct a public road or street. (See Carlino’s Brief at
    Appendix “A,” Trial Court Decision filed September 8, 2017 at 28) (citing Section
    204(b)(9) of the Eminent Domain Code, 26 Pa.C.S. § 204(b)(9)).
    Because the Connector Road is obviously a “right-of-way intended for
    general public use,” Zoning Ordinance § 399-9, the Board erred when determining
    that it is a “driveway” that does not require an 85-foot setback.14
    14
    As previously mentioned, in Brandywine I, a different trial judge determined that the
    proposed bank building is not required to be set back 85 feet from the Connector Road, only Route
    322. As that trial judge reasoned, the bank building’s development tract was a single lot and not a
    “corner lot” because “the proposed driveway does not create a subdivision of the Carlino
    development tract.” (Trial Court Opinion dated January 6, 2017 at 10-11.) In the decision now
    before us on appeal, the trial court did not revisit this issue, summarily deeming any further
    discussion collaterally estopped. Developer also does not raise the issue on appeal.
    In any event, in light of our determination that the Connector Road is a “street,” it is clear
    that the bank building’s 85-foot setback must be measured from the Connector Road. Section 399-
    46.C of the Zoning Ordinance provides: “Minimum front yard. No building shall be situated less
    than 85 feet from the front lot line.” (R.R. at 136a) (emphasis added). A front lot line is defined as
    “[a] lot line abutting any street and coinciding with any street line.” (Section 399-9 of the
    Zoning Ordinance, R.R. at 105a-135a.) A “street line” is defined as “[t]he dividing line between a
    (Footnote continued on next page…)
    19
    C.
    Objectors next contend that the 2015 Plan contains multiple violations of
    Zoning Ordinance Section 399-81.E, which provides that to minimize traffic
    congestion and encourage “orderly development of street highway frontage,” an
    applicant is responsible for providing:
    [S]afe and efficient ingress and egress to and from public
    streets, without undue congestion or interference with
    normal traffic flow within the Township. The developer
    shall be responsible for the design, construction, and costs
    of any necessary traffic control devices and/or highway
    modifications required by the Township and/or the
    Pennsylvania Department of Transportation.
    (R.R. at 141a-42a.) Objectors argue that they produced two professional engineers
    who testified that the narrow layout and location of the Connector Road created
    turning radii that prevent standard-size delivery trucks from making any normal
    turning movements into BVA’s property without either: (1) crossing into left-turn
    lanes to make right-hand turns or (2) encroaching into and blocking opposing traffic
    lanes on the Connector Road.
    (continued…)
    lot and the outside boundary or right-of-way of a public street, road, or highway legally open or
    officially platted. . . .” (Id.) (emphasis added). Significantly, a corner lot is “[a] lot at the junction
    of and abutting two or more intersecting streets . . . Each yard abutting a street shall be
    considered a front yard.” (Id.) (emphasis added).
    Having determined that both Route 322 and the Connector Road are public “streets” that
    intersect with the bank building, that development tract is obviously a corner lot and must have an
    85-foot setback from the front lot line abutting the Connector Road.
    20
    However, both the Township engineer and the Township traffic engineer
    determined that the street design in the 2015 Plan provided safe and efficient ingress
    and egress. Moreover, contrary to Objectors’ assertions, the trial court “found no
    instance in which [the Township traffic engineer] concluded the road intersections
    were deficient or unsafe. In fact he specifically testified that the Connector Road
    intersections were not unsafe, and that there were no safety issues.” (Trial Court
    Opinion dated July 18, 2017 at 29-30.) He also disagreed with each of BVA’s
    expert’s opinions and testified to the contrary. (Id. at 31.)
    What we have is a difference of opinion between competing testimonies
    of experts and the factfinder found the Township experts to be more credible.
    Obviously, the weight of such testimony and evidence and the acceptance of
    conflicting testimony is within the Board’s sole authority. Regardless, as the trial
    court correctly noted, “the Board took the path of caution, ordering [Developer] ‘to
    provide an updated Traffic Impact Study for the proposed development’, thus
    mooting this issue.” (Id. at 32.)
    D.
    Acknowledging that the trial court agreed with the Board that
    Developer’s plan was deficient because it failed to provide the required effluent
    disposal area either on the development tract or elsewhere, Objectors also challenge
    the trial court’s finding that while Developer has not satisfied the sewage effluent
    provision in SALDO, it can be waived under Section 503(8) of the MPC, 53 P.S.
    §10503(8), upon meeting the standard for waiver created by Section 512.1 of the
    21
    MPC, 53 P.S. §10512.1. However, as the trial court cogently explained, this assertion
    is meritless.
    [Developer] proposes to provide public sanitary sewage
    service to its proposed development, and has obtained
    approval from both the Township and its Sewage Authority
    to do so, thereby leading the Board to conclude that an
    effluent storage area is not required in this instance.
    Sewage effluent is the end by-product of the treatment of
    raw sewage. We addressed the need for a waiver from this
    Section in our January 6, 2017 Opinion. [Objectors] had
    also previously argued that [Developer] needed a variance
    from Section 399-47.K of the Zoning Ordinance because
    the latter Section incorporates the Section 350-47.B(2)
    SALDO provisions, thereby rendering them subject to
    traditional zoning variance hardship standards. It pressed
    the argument that in its future plans [Developer] would be
    precluded from seeking a waiver of 350-47.B(2). We found
    [Objectors’] argument to be meritless. Section 350-47.K
    merely references the necessity of the developer’s
    compliance with the cited sections of the SALDO, but
    does not by incorporation make them zoning
    regulations.     We have previously found that [the
    Pennsylvania Department of Environmental Protection]
    approved the Township’s expansion of its public sewage
    system to include both the Watters’ Parcel and [BVA’s]
    Property, including the facilities needed to convey and treat
    raw sewage from those development parcels and dispose of
    the treated effluent on other land. Accordingly, we now
    conclude that the Board is empowered to grant a waiver
    from this SALDO regulation pursuant to [MPC] Section
    503(8), 53 P.S. § 10503(8) upon its determination that
    [Developer] complies with the standard for waiver created
    by [MPC] Sections 512.1, 53 P.S. § 10512.1.
    (Trial Court’s Opinion dated July 18, 2015 at 26-28) (emphasis added).
    22
    Simply, Section 399-47.K of the Zoning Ordinance merely references
    that “the applicant’s proposals for sewage facilities and for water supply (both quality
    and quantity) in relation to the proposed uses shall be in compliance with the
    requirements of §§ 350-47 and 350-48 [of SALDO]” but does not mention or
    otherwise state that a party is precluded from seeking waiver of those SALDO
    provisions. (R.R. at 137a.) Accordingly, we agree with the trial court and reject
    Objectors’ second contention.
    E.
    Objectors also contend that the trial court erred when approving “a
    waiver to reduce turn radii on the Connector [R]oad which directly increase the
    already unsafe turn issues detailed by the testimony.” (Objectors’ Brief at 54.) Here,
    the 2015 Plan proposes to install a Connector Road, which Objectors will be required
    to use in order to have access to State Route 322 because BVA’s access easements
    were condemned by the Township. The 2015 Plan shows that the Connector Road
    has a 25-foot radius at the signalized intersection with Route 322.
    Significantly, Section 350-40 of SALDO pertains to “Driveways,” and
    Section 350-40.N.2 provides, in relevant part, that “In order to provide for safe and
    convenient ingress and egress, private driveway entrances shall be rounded as
    follows: . . . (2) For non-residential driveways, a minimum radius of 30 feet shall
    be provided. Greater radii may be required where truck traffic is to occur.”15
    15
    Available at: https://ecode360.com/11881082 (last visited March 16, 2018).
    23
    Obviously, having already decided that the Connector Road is not a
    driveway but instead a public road, this issue is moot. The radii requirement set forth
    in Section 350-40.N.2 does not apply because the Connector Road is a “street” and
    not a driveway.
    F.
    Finally, Objectors contend, without citing any authority, that it was an
    abuse of discretion for the Board to grant conditional preliminary approval
    notwithstanding its determination that Developer “shall comply with the provision of
    §350-36 (Acceleration, deceleration and turning lanes) or request a waiver of the
    same from the Board.” (R.R. at 39a.) They do not, however, dispute the trial court’s
    finding that Section 350-36.B.3 was actually inapplicable because the Connector
    Road was not a deceleration lane. This contention is wholly meritless. It is beyond
    settled that a preliminary plan containing minor defects can be approved subject to
    the condition that those defects are corrected. The Board, in granting the 2015 Plan,
    simply was doing so under the condition that Developer comply with Section 350-36
    or otherwise obtain a waiver of that requirement.                In doing so, the Board was
    obviously not asserting an argument on Developer’s behalf or abusing its discretion,
    but instead alerting Developer on how to resolve certain deficiencies.16
    Accordingly, while we agree with the Board’s disposition of all other
    issues on appeal, we reverse the trial court’s order affirming the Board’s decision
    16
    In any event, Objectors’ contention is moot. Because the trial court’s unchallenged
    determination is that the requirements set forth in Section 350-36.B.3 are inapplicable, even if the
    Board did improperly grant a waiver, that waiver could not even apply to the Connector Road
    because it was found not to be a deceleration lane.
    24
    granting conditional preliminary approval of the 2015 Plan because the Connector
    Road is a public road and the 2015 Plan does not provide the required 85-foot setback
    from its front lot line to the building it proposes to construct.
    _______________________________
    DAN PELLEGRINI, Senior Judge
    25
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Brandywine Village Associates and     :
    L&R Partnership,                      :
    Appellants           :
    :
    v.                     : No. 1149 C.D. 2017
    :
    East Brandywine Township Board        :
    of Supervisors and Carlino            :
    East Brandywine, L.P.                 :
    ORDER
    AND NOW, this 19th day of April, 2018, it is hereby ordered that the
    order of the Court of Common Pleas of Chester County in the above-captioned matter
    is reversed.
    _______________________________
    DAN PELLEGRINI, Senior Judge