C. Carulli & B. Carulli, h/w v. N. Versailles Twp. Sanitary Auth. v. Port Vue Plumbing, Inc. ( 2019 )


Menu:
  •           IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Carmen Carulli and Barbara                :
    Carulli, husband and wife                 :
    :
    v.                           :
    :
    North Versailles Township                 :
    Sanitary Authority                        :
    :
    v.                           :
    :
    Port Vue Plumbing, Inc.,                  :   No. 751 C.D. 2017
    Appellant                :   Argued: October 17, 2018
    BEFORE:      HONORABLE MARY HANNAH LEAVITT, President Judge
    HONORABLE RENÉE COHN JUBELIRER, Judge
    HONORABLE P. KEVIN BROBSON, Judge
    HONORABLE PATRICIA A. McCULLOUGH, Judge
    HONORABLE ANNE E. COVEY, Judge
    HONORABLE CHRISTINE FIZZANO CANNON, Judge
    HONORABLE ELLEN CEISLER, Judge
    OPINION
    BY JUDGE FIZZANO CANNON                       FILED: August 13, 2019
    Port Vue Plumbing, Inc. (Port Vue) appeals a judgment of the
    Allegheny County Court of Common Pleas (trial court) entered against Port Vue and
    in favor of North Versailles Township Sanitary Authority (Authority), awarding
    damages in the amount of $39,033.69 in a breach of contract action. In doing so, the
    trial court rejected Port Vue’s claim that the four-year statute of limitations
    applicable to contract actions barred the Authority from bringing its claim. The trial
    court applied the discovery rule, reasoning that the Authority had no reason to know
    of the breach until it received a complaint from residents alleging damage to their
    residence approximately 10 years later. We vacate and remand.
    I. Background
    In December 2002, the Authority contracted with Port Vue to replace
    terra cotta sewer pipes along Bevan Road in North Versailles Township. Port Vue
    agreed to replace the pipes using the “pipe bursting” method, which bursts the
    existing pipe while simultaneously pulling through a new pipe. Notes of Testimony
    11/21/2016 (N.T.) at 75, Reproduced Record (R.R.) at 138a. The portion of sewer
    line to be replaced stretched from manhole 755 to manhole 767. Port Vue also
    contracted to excavate the new line to reconnect all residential sewer laterals to the
    new line. In July 2003, Port Vue notified the Authority that it had completed work
    on the project and requested final payment, which was approved by the Authority’s
    engineer. Trial Court Opinion at 1.1 In accordance with the contract, the Authority
    paid Port Vue for completion of the project. 
    Id. at 1-2.
                    In March 2012, the Authority was notified that the basement of a house
    along Bevan Road belonging to Carmen and Barbara Carulli (together, Carullis) had
    flooded with raw sewage. Trial Court Opinion at 2. The Authority also discovered
    that manhole 767 was surcharged2 to within several feet of its top. 
    Id. The Authority
    inspected the sewage lines with a camera and discovered that 112.71 lineal feet of
    piping between manhole 766 and manhole 767 had not been replaced in accordance
    with the contract. 
    Id. The Authority
    requested that Port Vue replace the sewer line
    1
    Pagination supplied beginning after cover page.
    2
    A “[s]ewer surcharge refers to the overloading of the sewer beyond its design capacity
    due to inflow and infiltration of water. A surcharging sewer often results in sewer overflow at
    manholes and customers’ over flow relief gully[.]” Sewer Surcharge, The Local Government
    Municipal and Knowledge Base, http://www.lgam.info/sewer-surcharge (last visited August 12,
    2019).
    2
    between manhole 766 and manhole 767. 
    Id. When Port
    Vue refused, the Authority
    retained another contractor, State Pipe Services, to replace the old sewer line. 
    Id. In September
    2012, the Carullis filed a complaint for damages against
    the Authority. In response, on or about November 20, 2012, the Authority filed a
    complaint to join Port Vue as an additional defendant arising from Port Vue’s
    alleged failure to fulfill its obligations under the contract. Trial Court Opinion at 2.
    The Carullis settled their claims, and the Authority and Port Vue proceeded to a non-
    jury trial.
    Before the trial court, Port Vue argued that the statute of limitations
    bars the Authority’s claims. Trial Court Opinion at 2. The parties did not dispute
    that Pennsylvania’s statute of limitations for a breach of contract claim of this nature
    is four years. 
    Id. (citing 42
    Pa.C.S. § 5525(1)). The parties also did not dispute that
    Port Vue was not made a party to the lawsuit until nearly 10 years after it completed
    work on the project. 
    Id. The Authority
    , however, claimed it was unaware that a
    section of the project was unfinished until those pipes caused the damage to the
    Carullis’ home, and therefore, the discovery rule tolled the running of the statute of
    limitations. See 
    id. at 2-3.
                  At trial, the Authority presented the testimony of Donald Glenn
    (Glenn), an engineer from the Authority’s engineering firm, Glenn Engineering and
    Associates Ltd. N.T. at 10-11, R.R. at 73a-74a. Glenn testified that he designed the
    project for the Authority, which consisted of replacing the sewer lines, reconnecting
    the house laterals to the new line and installing additional manholes. N.T. at 11,
    R.R. at 74a. The project was to be completed in two phases. N.T. at 12, R.R. at 75a.
    Phase 1 started at manhole 755 and ended at manhole 764. 
    Id. Phase 2
    started at
    3
    manhole 764 and ended at manhole 767. 
    Id. Port Vue
    contracted to do the work for
    both phases of the project. See N.T. at 13, R.R. at 76a.
    Glenn testified that he was not at the site every day to inspect the work
    in progress.       His colleague, Joseph Dursa (Dursa), and the Authority’s
    representative, Jack Gaffney (Gaffney), were on-site. When asked if an individual
    could visibly inspect the new sewer line between manholes 764 and 767, Glenn
    testified that “you can’t physically inspect” the pipe because there was no excavation
    of the pipe line. N.T. at 25-26, R.R. at 88a-89a. Further, the Authority did not have
    the physical equipment to do a camera inspection of the sewer line. N.T. at 59, R.R.
    at 122a. Glenn testified that Port Vue forwarded an invoice to him representing that
    the project had been completed, including bursting the entire line, and that based on
    such representation, Glenn authorized payment in full to Port Vue. N.T. at 24-25,
    R.R. at 87a-88a.
    Glenn also testified about the incident that caused the damage to the
    Carullis’ property. Glenn testified that after the incident, it was determined that the
    pipe bursting had not been done for the entire length as specified in the contract.
    N.T. at 27, R.R. at 90a. Glenn stated that this caused a backup in the sewer line and
    a surcharge at manhole 767. 
    Id. Glenn testified
    that, after the incident, the Authority
    determined the line had collapsed using two methods:            physical observation
    (climbing down a ladder in the manhole and shining a flashlight up and down the
    sewer) and inserting a camera. N.T. at 28-29, R.R. at 91a-92a. The inspection
    revealed that the old terra cotta pipe had collapsed and that a new liner had never
    been installed. N.T. at 27-29, R.R. at 90a-92a. Glenn testified that the backup in
    the sewer line and the surcharge at manhole 767, and the resulting photographs from
    the inspection, were the first indication that the sewer line had not been completed
    4
    all the way to manhole 767. See N.T. at 26-27, 31 & 81, R.R. at 89a-90a, 94a &
    144a. Despite Port Vue’s assertions to the contrary, Glenn testified that he never
    had a conversation with anyone at Port Vue, including owner Richard Perkoski
    (Perkoski), about doing other work instead of replacing the sewer line between
    manhole 764 and manhole 767. N.T. at 33, R.R. at 96a.
    Glenn testified that under the contract, Port Vue was to furnish as-built
    drawings. N.T. at 32, R.R. at 95a. He stated he did not personally request that Port
    Vue submit as-built drawings after the contract was completed but that the request
    “would have come from one of my other people at the office.” 
    Id. Glenn testified
    that, to his knowledge, Port Vue did not supply Glenn Engineering or the Authority
    with as-built drawings. N.T. at 32-33, R.R. at 95a-96a.
    Glenn also testified that after it was determined the terra cotta pipe
    collapsed, he told Port Vue it had to complete the project, but it refused, so the
    Authority contracted with, and paid, State Pipe Services to complete the work. N.T.
    at 29 & 32, R.R. at 92a & 95a.
    On cross-examination, Glenn stated that the contract defines the scope
    of the work to be performed. N.T. at 36, R.R. at 99a. Glenn also acknowledged that
    the terms of the contract provided that the engineer could inspect the contractor’s
    work at any time. N.T. at 38, R.R. at 101a. Glenn also testified that Glenn
    Engineering had assigned an inspector to the project, although not a full-time
    inspector, and that Gaffney, who worked for the Authority, was also an inspector.
    
    Id. Glenn acknowledged
    that the contract provided that the Authority’s engineer
    was to perform a final inspection to determine whether the job was completed. 
    Id. Glenn acknowledged
    that he certified that the work had been completed even though
    neither he nor anyone from his office did any type of inspection. N.T. at 53, R.R. at
    5
    116a. Glenn also reconfirmed that the Authority had determined that a portion of
    the line was not bursted when the Authority looked into manhole 767. N.T. at 56a,
    R.R. at 119a. Glenn also conceded that the work could have been visually inspected
    at any time without the aid of any type of camera, although he stated “[i]t would take
    of lot of effort to do that,” explaining that “[y]ou would have to climb down, get a
    flashlight, [and] shine it[.]” 
    Id. Glenn stated
    he “had no idea” whether that was done
    at any time between Port Vue completing its work in 2003 and when the backup
    incident occurred in 2012, “but obviously not.” 
    Id. The Authority
    also presented Dursa’s testimony; Dursa was a project
    representative from Glenn Engineering who inspected the work performed by Port
    Vue. N.T. at 103, R.R. at 166a. He explained that, at the beginning of the
    construction period, Port Vue laid out the new sections of pipe and fused the pipes
    together so that they could be pulled through the old terra cotta pipe during the
    bursting process. N.T. at 105, R.R. at 168a. Dursa explained that during the
    installation of the pipe,
    [y]ou really can’t view [the actual bursting of the line], but
    you can just see the machines working, and it’s pulling the
    pipe through that they had on site already put together
    behind the area [that] was dug out.
    N.T. at 104, R.R. at 167a.
    Dursa stated that in January 2003, when he arrived at the site, the
    machine that was used for pipe bursting had stopped working in the vicinity of
    manhole 766. See N.T. at 105, R.R. at 168a. He understood that Port Vue was
    evaluating the problem and attempting to get the machine working again. N.T. at
    105-06, R.R. at 168a-69a. Thereafter, Dursa went on vacation, and upon his return,
    the equipment was no longer at the same location. N.T. at 107, R.R. at 170a. Dursa
    6
    testified that he never spoke to Perkoski about not completing the line replacement
    to manhole 767 and, instead, doing other work. N.T. at 108 & 110-11, R.R. at 171a
    & 173a-74a. On cross-examination, Dursa stated that he reviewed the contract
    documents before he started his inspections and that he had the contract documents
    on site, although he did not “have a copy on me[.]” N.T at 116-17, R.R. at 179a-
    80a. He acknowledged that he understood what Port Vue was supposed to do. N.T.
    at 119, R.R. at 182a.
    John McDonald (McDonald) also testified for the Authority.
    McDonald was a foreman for State Pipe Services, which replaced the broken sewer
    line in 2012. N.T. at 85, R.R. at 148a. Initially, State Pipe Services performed a
    pre-inspection of the site using a camera. N.T. at 86, R.R. at 149a. After determining
    that the old terra cotta pipe had not been completely replaced, State Pipe Services
    continued the pipe bursting process to the top of manhole 767, thereby completing
    the project. N.T. at 88, R.R. at 151a.
    Gaffney, a former foreman for the Authority at the time of the project,
    also testified for the Authority. N.T. at 191-92, R.R. at 254a-55a. Gaffney testified
    that he was instructed by the office manager and the Board of the Authority to check
    in daily if there was going to be any problems but it was not his position to inspect
    anything, and he did not, nor was he at the site daily. N.T. at 192-93, R.R. at 255a-
    56a. He confirmed that he never had a conversation with Perkoski about not
    completing the bursting of the line between manholes 766 and 767. N.T. at 193,
    R.R. at 256a. Regarding the visual inspection of a new sewer line, Gaffney
    explained:
    If it’s an open cut, in other words, if they excavate and put
    the pipe in, both the engineer and myself if I’m in the area,
    7
    make sure that it’s cemented out correctly with stone,
    make sure that there’s good flow on it.
    However, if the inspectors work by themselves, you don’t
    go down into a sewer by yourself. It’s a safety issue. By
    [Occupational Safety and Health Administration]
    standard, there should be three people on site.
    I have never been there where it’s just myself and/or Joe
    [Dursa]. So we don’t make it a habit or standard to go
    down any sewers, manholes themselves because of safety
    issues.
    N.T. at 199-200, R.R. at 262a-63a.
    In its case, Port Vue called its President, Perkoski. N.T. at 127-28, R.R.
    at 190a-91a. Perkoski testified that throughout the duration of the project, his
    communications had been with Glenn Engineering. N.T. at 129-30, R.R. at 192a-
    93a. Perkoski explained that during phase 2 of the project, from manhole 764 to
    manhole 767, his workers encountered problems connecting some of the homes to
    the new sewer line. See N.T. at 140-41, R.R. at 203a-04a. They had to enter the
    basements of these houses, cut the basement floors to find the sewer, install a new
    eight-inch pipe, and then clean up the basements. N.T. at 141, R.R. at 204a. This
    work exceeded the scope of the work set forth in Port Vue’s contract with the
    Authority. 
    Id. Perkoski testified
    that Glenn Engineering was aware of this extra
    work and agreed that it would be “traded for the other pipe bursting,” which was
    scheduled to be done for a payment of $14,000. N.T. at 143, R.R. at 206a. Perkoski
    explained:
    [t]he remaining pipe bursting that had to be done, which
    amounted to, if you looking [sic] at the schedule,
    [$]14,000, and I did eight houses or seven houses, and it
    had to cost me five to eight thousand at that time.
    8
    So I did $35,000 worth of work for $14,000, because
    [Glenn] is a friend of [mine].
    N.T. at 143-44, R.R. 206a-07a.3
    When asked if he completed the 112 feet of sewer line between
    manholes 766 and 767, Perkoski stated:
    No. I guess if that’s what we say, but that’s what we
    figured that we were going to get extras for the inside, and
    they didn’t have the money for the inside. So we said,
    okay, we’ll leave that existing sewer in and take that
    money and apply it to each house.
    N.T. at 156, R.R. at 219a. When questioned as to whether Port Vue ever supplied
    the Authority or Glenn with as-built drawings after Port Vue completed the project,
    Perkoski stated:
    A. Yeah, I drew it with Joe [Dursa] and them on the job
    the way it was. They knew the way it was. That’s how
    these come up and they’re still wrong.
    Q. Did you bring a copy of the as-builts with you?
    A. No. We draw it on paper up at the job.
    Q. You took a piece of paper at the site and said, This is
    what I did?
    A. Well, they could see what I did, but then they put it
    wrong. It ain’t even right on here.
    Q. Well, they couldn’t see that you did not complete the
    121 feet that was underground.
    A. Well, we agreed to eliminate it to save money.
    3
    On cross-examination, Perkoski explained how he arrived at the $14,000 figure. He stated
    that he decided that “wherever we were at that time, we left that pipe bursting go and said we’ll
    apply that money to bursting these people’s houses.” N.T. at 189, R.R. at 252a.
    9
    N.T. at 165, R.R. at 228a. Perkoski acknowledged that the payment application that
    his company submitted to the Authority indicated that Port Vue had completed 100%
    of the bursting of the lines from manhole 764 to manhole 767. N.T. at 171, R.R. at
    234a.
    Following the one-day trial, the trial court entered a verdict in favor of
    the Authority and awarded it $39,033.69 in damages. Trial Court Opinion at 6. The
    trial court concluded that “the discovery rule applie[d] to toll the statute of
    limitations until March of 2012 when the Authority became aware that [Port Vue]
    failed to complete the work as required by the contract.” 
    Id. at 4.
    The trial court
    also concluded that a 2008 consent order signed by the Authority in a separate case
    did not bar the instant case. 
    Id. at 4-5.
    Finally, the trial court rejected Port Vue’s
    argument that it could only be held liable for the cost of the work it did not complete
    in the original contract, which was $14,351.00. 
    Id. at 5.
    Port Vue sought post-trial
    relief, which was denied. R.R. at 61a. The present appeal followed.
    II. Arguments and Analysis
    On appeal,4 Port Vue raises three arguments. First, it contends that the
    four-year statute of limitations applicable to breach of contract claims bars the
    Authority’s claims. Second, Port Vue contends that a 2008 consent order between
    the parties released it from any future claims related to the project. Third, Port Vue
    contends that the amount of damages awarded to the Authority exceeded what it
    would have been paid under the contract and, therefore, exceeded those allowed by
    law.
    4
    “When reviewing a non-jury verdict, our standard of review is limited to determining
    whether the competent evidence supports the trial court’s findings of fact and whether the trial
    court committed an error of law.” E. Coast Paving & Sealcoating, Inc. v. N. Allegheny Sch. Dist.,
    
    111 A.3d 220
    , 225 n.8 (Pa. Cmwlth. 2015). “This Court must treat the trial court’s findings of fact
    the same as this Court would treat a jury’s findings of fact.” 
    Id. “This Court
    views the evidence
    in the light most favorable to the party that prevailed before the trial court.” 
    Id. 10 In
    response, the Authority argues that the trial court did not err or abuse
    its discretion in concluding that the Authority’s claim was not barred by the statute
    of limitations. Next, the Authority argues that this matter is not barred by the consent
    order because that order involved a separate nucleus of facts and did not release Port
    Vue from the present claim. Finally, the Authority responds that the trial court did
    not award damages in excess of those allowed by law because the Authority is
    entitled to compensation for all damages resulting from Port Vue’s failure to fulfill
    the contract.
    This case was originally argued before a panel of three judges of this
    Court.     Subsequently, the Court issued an order directing the parties to file
    supplemental briefs addressing: (1) “[w]hether a sewer authority may invoke the
    doctrine of nullum tempus occurit Regi [“time does not run against the king”] to
    defeat an otherwise applicable statute of limitations defense . . .” and whether the
    Authority “acted in its governmental capacity to enforce an obligation imposed by
    law[]”; and (2) “[w]hether the statute of limitations begins to run upon occurrence
    of a breach of contract or upon the discovery of the breach in all types of contracts.”
    Cmwlth. Ct. Order 8/7/18. The matter was then argued before the Court en banc.
    We will begin by addressing Port Vue’s argument that the consent order
    bars this action because it released Port Vue from any future claims related to the
    project.
    A. Consent Order
    By way of background, in 2005, two property owners along Bevan
    Road, William Roney and Gina Buzzard, filed suit against multiple parties including
    Port Vue and the Authority, following land subsidence events behind their homes in
    2002 and 2003 related to the sewer line replacement. See Trial Court Opinion at 4-
    11
    5; Consent Order ¶¶ 1 & 3, R.R. at 23a-24a. The lawsuit was resolved by a
    settlement agreement, wherein the Authority agreed to release Port Vue from any
    claim or cause of action related to the litigation. See R.R. at 23a-24a. Port Vue
    contends that, “[b]ut for the contract between [it] and the Authority to perform pipe
    bursting on the hillside below Bevan Road [it] would not have been involved in the
    above litigation.” Port Vue’s Brief at 13.
    “In Pennsylvania, a consent decree in an equity action is not considered
    a legal determination by the courts but is an agreement between the parties.” Penn
    Township v. Watts, 
    618 A.2d 1244
    , 1247 (Pa. Cmwlth. 1992). “‘It is in essence a
    contract binding the parties thereto.’” Cecil Township v. Klements, 
    821 A.2d 670
    ,
    674 (Pa. Cmwlth. 2003) (quoting Commonwealth v. Rozman, 
    309 A.2d 197
    (Pa.
    Cmwlth. 1973)).
    The consent order provided that the parties to the agreement, including
    Port Vue and the Authority, agreed to release and discharge one another from all
    claims or damages “arising from the slide or land subsidence occurring behind the
    Roney and Buzzard residences in 2002 and 2003 and including, but not limited to,
    any claim or cause of action arising out of, or related to, these consolidated litigation
    matters and it is so ORDERED.” Consent Order ¶ 5, R.R. at 24a-25a. Based on this
    language, the trial court concluded that the release did not apply to the instant case.
    Trial Court Opinion at 5. We agree.
    The Carullis’ claim arose because the sewer line between manholes 766
    and 767 was not replaced. The 2008 consent order was limited to actions and claims
    arising from the slide or land subsidence occurring behind the Roney and Buzzard
    residences. The Carullis were not parties in the prior litigation and did not claim any
    harm from the 2002 and 2003 land subsidence events behind the Roney and Buzzard
    12
    residences. Thus, the language of the release does not bar the Authority’s breach of
    contract claim against Port Vue arising from the sewer line not being replaced.
    Although Port Vue may not have been involved in the prior litigation but for its
    contract with the Authority, the order released all claims and actions arising from or
    related to the 2002 and 2003 slide or land subsidence behind the Roney and Buzzard
    residences. Accordingly, we agree with the trial court that the 2008 consent order
    does not bar the Authority from bringing its claims against Port Vue in this matter.
    B. Statute of Limitations
    With respect to the statute of limitations, Port Vue argues that the
    Authority’s claim is barred because the statute of limitations began to run upon the
    occurrence of the breach. In response, the Authority argues that it is not subject to
    any statute of limitations under the doctrine of nullum tempus. The Authority also
    asserts that its claim is not time-barred under the “discovery rule” and that the statute
    of limitations does not begin until the Authority, exercising reasonable diligence,
    could have discovered the injury, which it claims was when the damage to the
    Carullis’ basement occurred. Additionally, and in the alternative, the Authority
    argues that even if it is subject to a statute of limitations defense, Port Vue is
    estopped from asserting such a defense due to fraudulent concealment.
    (i)   Nullum Tempus
    We begin with the doctrine of nullum tempus. “The doctrine of nullum
    tempus permits a government agency ‘to circumvent the applicable statute of
    limitations.’” Allegheny Intermediate Unit v. E. Allegheny Sch. Dist., 
    203 A.3d 371
    ,
    378 (Pa. Cmwlth. 2019) (quoting Duquesne Light Co. v. Woodland Hills Sch. Dist.,
    
    700 A.2d 1038
    , 1051 (Pa. Cmwlth. 1997)), petition for allowance of appeal denied,
    (Pa., No. 52 WAL 2019, July 24, 2019). “Under the nullum tempus doctrine, statutes
    13
    of limitations do not apply to actions brought by the state and its agencies, unless the
    statute of limitation expressly provides that it limits the government’s right to sue.”
    Township of Salem v. Miller Penn Dev., LLC, 
    142 A.3d 912
    , 918 (Pa. Cmwlth.
    2016). The four-year statute of limitations for contract actions does not expressly
    provide that it applies to actions brought by government entities. See 42 Pa.C.S. §
    5525. Therefore, the statute of limitations cannot bar this action if nullum tempus
    applies. See Township of 
    Salem, 142 A.3d at 918
    .
    “The nullum tempus doctrine does not apply to all suits by local
    governments, but does extend to local governments where they are enforcing strictly
    public rights.” Township of 
    Salem, 142 A.3d at 918
    . “For the nullum tempus
    doctrine to exempt a municipality from the statute of limitations, the municipality’s
    claims must both 1) accrue to the municipality in its governmental capacity and 2)
    seek to enforce an obligation imposed by law, as distinguished from one arising out
    of a voluntary agreement.”5 
    Id. “An action
    involving a local government contract
    or agreement is brought in the local government’s governmental capacity and seeks
    5
    We note that Port Vue first asserts that the doctrine of nullum tempus does not apply
    because the Authority is not a Commonwealth party. Port Vue’s Supplemental Brief at 1-2. We
    note that the Authority does not argue that it is a Commonwealth party and does not dispute that
    this two-prong test is the appropriate test to apply to determine whether nullum tempus applies.
    See Authority’s Supplemental Brief at 1-2. For purposes of nullum tempus, we conclude that the
    Authority cannot be construed as being a Commonwealth party. See Se. Pa. Transp. Auth. v. Union
    Switch & Signal, Inc., 
    637 A.2d 662
    , 666 (Pa. Cmwlth. 1994) (stating, “[w]hile authorities may be
    considered an ‘instrumentality of the Commonwealth’, that does not mean that they are
    automatically considered to be ‘the Commonwealth’ for all purposes”). In Northampton County
    Area Community College v. Dow Chemical, U.S.A., 
    566 A.2d 591
    , 596 (Pa. Super. 1989), aff’d,
    
    598 A.2d 1288
    (Pa. 1991), the Superior Court held that community colleges cannot be construed
    as Commonwealth parties “because the legislature did not create them but merely authorized their
    creation by means of an enabling statute[.]” Likewise here, the legislature, via the Municipality
    Authorities Act (Act), 53 Pa.C.S. §§ 5601-5623, authorized the creation of municipal authorities,
    but it is the municipality that creates authorities. See 53 Pa.C.S. § 5603 (concerning method of
    incorporation); Se. Pa. Transp. 
    Auth., 637 A.2d at 664
    (stating, “authorities owe their existence to
    the various units of government and their governing boards are appointed by those entities”).
    14
    to enforce obligations imposed by law where the contract is one that the local
    government entity was required to enter into as part of its public duties.” 
    Id. “The requirement
    that the action be brought in the local government’s governmental
    capacity and seek to enforce obligations imposed by law is likewise satisfied and
    nullum tempus applies where the parties’ rights are governed by statute, even though
    the local government was not required to enter into the contract.” 
    Id. Thus, for
    nullum tempus to apply, “the right sought to be enforced must be strictly public, as
    well as imposed by law.” Duquesne Light 
    Co., 700 A.2d at 1051
    .
    In Township of Salem, this Court applied the doctrine of nullum tempus.
    In that case, the township brought suit against the subdivision developer for
    breaching the parties’ agreement for site improvements and to recover damages for
    the cost of making the street repairs. Township of 
    Salem, 142 A.3d at 916
    . In
    concluding that the township’s action was not barred by the statute of limitations
    because of nullum tempus, this Court stated:
    the [d]eveloper’s [a]greement] and fixing [the street]
    involve the [t]ownship’s duties to its residents. Ensuring
    the adequate construction of streets is a purely public
    purpose within a municipality’s obligations to its citizens,
    not a mere voluntary contractual undertaking. Pocono
    Township [v. Hall], 561 A.2d [53,] 56 [(Pa. Cmwlth.
    1989)]. Indeed, Section 509 of the [Pennsylvania
    Municipalities Planning Code6 (MPC)] imposes a duty on
    municipalities to require that developers complete public
    improvements in accordance with [subdivision and land
    development ordinance] requirements. 53 P.S. §10509;
    Stivala Investments, Inc. v. South Abington Township
    Board of Supervisors, 
    815 A.2d 1
    , 5 (Pa. Cmwlth. 2003).
    6
    Act of July 31, 1968, P.L. 805, as amended, 53 P.S. §§ 10101–11202.
    15
    Moreover, the parties’ rights in this action are governed by
    statute. Section 511 of the MPC imposes on developers the
    cost of correcting improperly installed improvements. 53
    P.S. §10511; Stivala 
    Investments, 815 A.2d at 4
    ; Safford
    v. Board of Commissioners, Annville Township, 35 Pa.
    Cmwlth. 631, 
    387 A.2d 177
    , 182 (1978).
    Township of 
    Salem, 142 A.3d at 918
    -19.
    Similarly, this Court held that the doctrine of nullum tempus applied in
    Delaware County v. First Union Corporation, 
    929 A.2d 1258
    (Pa. Cmwlth. 2007),
    wherein the county brought suit against banks that were the depositories for bonds
    issued by the county. The banks did not return unclaimed funds within two years to
    the county as required by the Local Government Unit Debt Act (Debt Act),7 but
    rather, after another five years, escheated the unclaimed funds to the Commonwealth
    pursuant to section 1301.3 of the act commonly known as the Unclaimed Property
    Act.8 
    Id. at 1260.
    This Court held that nullum tempus applied, because while the
    county had the discretion to decide whether to issue the bonds, once the bonds were
    issued, the parties’ rights were controlled by statute, i.e., the Debt Act. 
    Id. at 1262.
                    In contrast, in Altoona Area School District v. Campbell, 
    618 A.2d 1129
    (Pa. Cmwlth. 1992), this Court held that a school district could not invoke the
    doctrine of nullum tempus to defeat the statute of limitations in an action for breach
    of contract and on the related performance bond concerning the construction of a
    public library. 
    Id. at 1134.
    We noted that although the school district was authorized
    7
    53 Pa.C.S. §§ 8001-8049.
    8
    Act of April 9, 1929, P.L. 343, as amended, added by Section 5 of the Act of December
    9, 1982, P.L. 1057, 72 P.S. § 1301.3.
    16
    to build libraries under section 418 of The Library Code,9 it was not mandated to do
    so. 
    Id. at 1132.
    Therefore, we reasoned that the school district was not obligated by
    law to enter into a contract to construct the library, but rather, entered into the
    contract voluntarily as it was authorized to do under The Library Code. 
    Id. at 1132-
    33. Accordingly, we concluded that the school district was not seeking to enforce
    strictly public rights, and therefore, nullum tempus did not apply. 
    Id. at 1134.
                  Here, Port Vue argues that nullum tempus does not apply because there
    is no statutory duty or obligation to provide sewer service. The Authority, on the
    other hand, argues that it was created pursuant to the Municipality Authorities Act
    (Act) for the sole purpose of extending the public right of sewer services to
    Township residents, and the Authority is the governmental arm through which the
    Township acts in its governmental capacity. Authority’s Supplemental Brief at 2.
    Further, the Authority argues that once a sewer service exists, the Authority has a
    duty, or legal obligation, to continue to provide those services and keep them in good
    repair. 
    Id. at 3.
                  The Act defines an authority as “[a] body politic and corporate created
    under this chapter[.]” 53 Pa.C.S. § 5602. The Act authorizes the creation of an
    authority for:
    (a) Scope of projects permitted.—Every authority
    incorporated under this chapter shall be a body corporate
    and politic and shall be for the purposes of financing
    working capital; acquiring, holding, constructing,
    financing, improving, maintaining and operating, owning
    or leasing, either in the capacity of lessor or lessee,
    9
    Act of June 14, 1961, P.L. 324, as amended, formerly 24 P.S. § 4418, repealed by Act of
    November 1, 2012, P.L. 1683.
    17
    projects of the following kind and character and providing
    financing for insurance reserves:
    ...
    (5) Sewers, sewer systems or parts thereof.
    53 Pa.C.S. § 5607(a)(5). Further, the Act states that an authority “may exercise all
    powers necessary or convenient for the carrying out of the[se] purposes . . . .” 53
    Pa.C.S. § 5607(d) (emphasis added).
    Thus, the Act only authorizes the creation of the Authority for the
    purpose of, inter alia, improving and maintaining sewers or sewer system projects;
    the Act does not mandate such. The Authority argues, however, that this is of no
    consequence; rather, the Authority contends that it is mandated to continue the
    provision of such services and that this mandate is important and what distinguishes
    this case from Altoona. Authority’s Supplemental Brief at 2-3. The Authority
    argues that once it undertakes a sewer system, it has a duty to maintain it. While we
    agree with the Authority that once it undertakes a sewer system, it has a duty to
    maintain it, there is no statutory duty. The Act does not control the terms of any
    contract between a contractor and an authority relating to the sewer or sewer system
    or the maintenance thereof. Rather, the duty the Authority forwards is no different
    than the common law duty of care. This duty is unlike the statutory duty in Township
    of Salem, where the parties’ contractual terms were governed by the township’s
    subdivision and land development ordinance, and unlike Delaware County, where
    the Debt Act governed the parties’ rights. Thus, the Authority’s claims do not accrue
    to it in its governmental capacity and do not seek to enforce an obligation imposed
    by law. In sum, unlike the case of Township of Salem and similar to the case of
    Altoona, here, the parties’ obligations are not imposed by statutory law but are
    dictated solely by the actual terms of the contract. Accordingly, the doctrine of
    18
    nullum tempus does not apply, and therefore, the statute of limitations applies to this
    action.
    (ii)   Whether the statute of limitations begins
    to run upon the occurrence of the breach
    or upon the discovery of the injury
    Port Vue argues that the statute of limitations begins to run upon the
    occurrence of the breach. The Authority, on the other hand, argues the discovery
    rule applies, pursuant to which the statute of limitations does not begin to run until
    a party, using reasonable diligence, discovers the breach. Authority’s Supplemental
    Brief at 4-5. The trial court applied the discovery rule.
    The Supreme Court of the United States observed:
    Statutes of limitation are vital to the welfare of society and
    are favored in the law. They are found and approved in all
    systems of enlightened jurisprudence. They promote
    repose by giving security and stability to human affairs.
    An important public policy lies at their foundation. They
    stimulate to activity and punish negligence. While time is
    constantly destroying the evidence of rights, they supply
    its place by a presumption which renders proof
    unnecessary. Mere delay, extending to the limit
    prescribed, is itself a conclusive bar.
    Wood v. Carpenter, 
    101 U.S. 135
    , 139 (1879).
    In Pennsylvania, our courts have noted that, generally, “[s]tatutes of
    limitations ‘are designed to effectuate three purposes: (1) preservation of evidence;
    (2) the right of potential defendants to repose; and (3) administrative efficiency and
    convenience.’” Lesoon v. Metro. Life Ins. Co., 
    898 A.2d 620
    , 626-27 (Pa. Super.
    2006) (quoting Kingston Coal Co. v. Felton Mining Co., 
    690 A.2d 284
    , 288 (Pa.
    Super. 1987)). “Whether a complaint is timely filed within the limitations period is
    19
    a matter of law for the court to determine.” Crouse v. Cyclops Indus., 
    745 A.2d 606
    ,
    611 (Pa. 2000).
    Section 5502 of the Judicial Code sets forth the method of computing
    periods of limitation and provides:
    The time within which a matter must be commenced under
    this chapter shall be computed, except as otherwise
    provided by subsection (b) or by any other provision of
    this chapter, from the time the cause of action accrued, the
    criminal offense was committed or the right of appeal
    arose.
    42 Pa.C.S. § 5502(a) (emphasis added). Our Supreme Court has stated, “[i]n
    construing this language for general contract purposes, we have adopted the view of
    a majority of jurisdictions that it is the accrual of the right of action that starts a
    limitations period to run.” Erie Ins. Exch. v. Bristol, 
    174 A.3d 578
    , 585 (Pa. 2017).
    Our Supreme Court noted that this view is “in accord with the law across the
    country[,]” which provides:
    Unless a statute provides otherwise, the statute of
    limitations begins to run at the time when a complete
    cause or right of action accrues or arises, which occurs as
    soon as the right to institute and maintain a suit arises.
    The general rule, as embodied in most statutes, is that,
    unless a statute specifically provides otherwise, as, for
    example, a statute specifically providing that the statute of
    limitations shall run from a particular event which may
    precede the time where the liability actually arises, the
    statute of limitations begins to run at the time when a
    complete cause or right of action accrues or arises, and
    only at such time, that is, as soon as the right to institute
    and maintain a suit arises, or when there is a demand
    capable of present enforcement. An action may accrue at
    20
    the time of a wrongful act, although the limitations period
    does not always begin on the date the wrong is committed.
    54 C.J.S. Limitations of Actions, § 81 (footnotes and case
    citations omitted.)
    Erie Ins. 
    Exch., 174 A.3d at 585-86
    (citing Ctr. Concrete Co. v. AGI, Inc., 
    559 A.2d 516
    , 518-19 (Pa. 1989)) (emphasis in original).10 “In general, for a claim based upon
    contract, the cause of action accrues and the statute of limitations begins to run on
    the date that the contract is breached.” GAI Consultants, Inc. v. Homestead Borough,
    
    120 A.3d 417
    , 423-24 (Pa. Cmwlth. 2015) (citing McGaffic v. City of New Castle,
    
    973 A.2d 1047
    , 1052 (Pa. Cmwlth. 2009)). Therefore, applying contract principles
    to the Authority’s breach of contract claim at issue here, the statute of limitations
    would begin to run when the Authority’s cause of action accrued, i.e., when Port
    Vue breached its duty under the agreement. The trial court, however, applied the
    discovery rule. We therefore consider whether grounds exist to deviate from the
    general rule concerning the statute of limitations in a breach of contract action and
    whether the application of the discovery rule to such breach of contract claim is
    appropriate.
    With respect to the statute of limitations and the discovery rule, our
    Supreme Court has stated:
    10
    In Erie Insurance Exchange, our Supreme Court considered when the statute of
    limitations begins to run when an insurer is alleged to have breached its duty under an insurance
    contract involving a claim for uninsured motorist coverage. Erie Ins. 
    Exch., 174 A.3d at 579
    . The
    case did not involve the discovery rule. Nonetheless, the relevance of this decision to the case
    before us is that our Supreme Court emphasized that the controlling law for determining when the
    limitations period begins to run for a breach of contract action is when the cause of action accrued.
    
    Id. at 585-86.
    Further, the Court concluded that because there was no compelling public policy
    ground or legislative intent in the related motor vehicle statute, there was no reason to create a
    special rule for when the statute of limitations begins to run in an uninsured motorist case. 
    Id. at 589.
                                                    21
    As a matter of general rule, a party asserting a cause
    of action is under a duty to use all reasonable diligence to
    be properly informed of the facts and circumstances upon
    which a potential right of recovery is based and to institute
    suit within the prescribed statutory period. . . . Thus, the
    statute of limitations begins to run as soon as the right to
    institute and maintain a suit arises; lack of knowledge,
    mistake or misunderstanding do not toll the running of the
    statute of limitations . . . ; even though a person may not
    discover his injury until it is too late to take advantage of
    the appropriate remedy, this is incident to a law arbitrarily
    making legal remedies contingent on mere lapse of time.
    Once the prescribed statutory period has expired, the party
    is barred from bringing suit unless it is established that an
    exception to the general rule applies which acts to toll the
    running of the statute.
    The “discovery rule” is such an exception, and arises from
    the inability of the injured, despite the exercise of due
    diligence, to know of the injury or its cause. . . . The salient
    point giving rise to the equitable application of the
    exception of the discovery rule is the inability, despite the
    exercise of diligence by the plaintiff, to know of the injury.
    Pocono Int’l Raceway, Inc. v. Pocono Produce, Inc., 
    468 A.2d 468
    , 471 (Pa. 1983)
    (emphasis in original) (citations omitted). The discovery rule is a “judicially created
    device[.]” Gustine Uniontown Assocs., Ltd. v. Anthony Crane Rental, Inc., 
    842 A.2d 334
    , 334 n.8 (Pa. 2004) (Gustine I).
    “The discovery rule . . . was first used in the limited area of medical
    malpractice and soon spread to other tort fields.” 
    33 A.L.R. 5th 1
    (originally
    published in 1995); see, e.g., Gleason v. Borough of Moosic, 
    15 A.3d 479
    (Pa. 2011)
    (applying discovery rule in action alleging negligent road construction); Hidden
    Creek, L.P. v. Lower Salford Twp. Auth., 
    129 A.3d 602
    (Pa. Cmwlth. 2015)
    (applying discovery rule in action that alleged authority’s charges for sewer tapping
    22
    fees violated Act and noting similarity of claim to that in Harleysville Homestead,
    Inc. v. Lower Salford Township Authority, 
    980 A.2d 749
    (Pa. Cmwlth. 2009), a claim
    that was held to sound in tort); Garvey v. Rosanelli, 
    601 A.2d 1334
    (Pa. Cmwlth.
    1992) (applying discovery rule in negligence action alleging latent defects in
    residential construction).
    Pennsylvania courts have also considered the application of the
    discovery rule to non-tort actions. See, e.g., 
    Altoona, 618 A.2d at 1135
    (Pa. Cmwlth.
    1992) (stating that Section 5523 of Judicial Code, 42 Pa.C.S. § 5523, is a statute of
    limitations and, therefore, cause of action on performance bond brought pursuant to
    that section is subject to discovery rule)11; Amodeo v. Ryan Homes, Inc., 
    595 A.2d 1232
    (Pa. Super. 1991) (holding that discovery rule applied to breach of implied
    11
    In Altoona, this Court held that a school district’s claims against the contractor and surety
    based on the performance bond raised genuine issues of fact as to when the statute of limitations
    began to run, and that because Section 5523 of the Judicial Code— which states that an action
    upon any payment or performance bond must be commenced within one year— is a statute of
    limitations, rather than a statute of repose, the claim was subject to the discovery rule. Altoona
    Area Sch. 
    Dist., 618 A.2d at 1135
    . That case does not mandate applying the discovery rule here,
    as it is distinguishable given the role of the entity seeking to enforce the performance bond. An
    action asserting a claim based on a performance bond is not a breach of contract action per se and
    is sui generis. A performance bond is “[a] bond given by a surety to ensure the timely performance
    of [the terms of] a contract.” Performance Bond, Black’s Law Dictionary 1319 (10th ed. 2014).
    Under a performance bond, a third party, usually known as a surety, agrees to guarantee the
    completion of a construction contract. See 
    id. The contractor
    purchases the performance bond
    from the surety to ensure the contractor’s performance of the construction contract for the benefit
    of the named obligee (e.g., the property owner who is a party to the underlying construction
    contract), which in Altoona was the school district. See Philip L. Bruner & Patrick J. O’Connor,
    Jr., 4A Bruner & O’Connor on Construction Law § 12:32 (June 2018) (stating that purpose of
    performance bond is to protect named obligee against contractor’s default in completion of
    underlying contract). Notably, the obligee, the entity seeking to enforce the performance bond, is
    not involved in the creation/procurement of the performance bond and does not provide
    consideration (or payment) for the performance bond. In other words, that entity is essentially a
    third-party beneficiary and is not a negotiating party at arms’ length. When determining liability
    of the surety under the performance bond, the terms of the bond instrument control, not the
    underlying contractor agreement. 20 Standard Pa. Practice 2d § 108:18 (June 2019).
    23
    warranty of habitability claims involving defective construction). The Pennsylvania
    Superior Court has stated, “[t]he discovery rule in Pennsylvania applies to all causes
    of action, including breach of contract.” Morgan v. Petroleum Prods. Equip. Co.,
    
    92 A.3d 823
    , 828 (Pa. Super. 2014) (citing Sadtler v. Jackson-Cross Co., 
    587 A.2d 727
    , 731 (Pa. Super. 1991)) and applying discovery rule to breach of contract claim);
    Sadtler (applying discovery rule to breach of contract case in which purchasers of
    real estate brought suit against their appraiser).12 Compare Gustine Uniontown
    Assocs., Ltd., ex rel. Gustine Uniontown, Inc. v. Anthony Crane Rental, Inc., 
    892 A.2d 830
    , 836 (Pa. Super. 2006) (Gustine II) (holding that contract language, which
    stated that “applicable statute of limitations shall commence to run” not later than
    the date of substantial completion, precluded application of discovery rule).
    Our Supreme Court, however, has not pronounced the applicability of
    the discovery rule to a breach of contract action based on an express written contract
    negotiated at arms’ length. In Crouse, our Supreme Court affirmed the Superior
    Court’s application of the discovery rule to a claim based on promissory estoppel, a
    doctrine which, while sounding in contract law, “makes otherwise unenforceable
    agreements binding,” 
    id. at 610,
    and, thus, is not based on an express written
    negotiated term.13 Notably, in his concurring and dissenting opinion, Justice Saylor
    stated:
    12
    Although the plaintiffs in Sadtler alleged negligent performance of an agreement to
    appraise real estate, the Superior Court held that the action was a breach of contract action because
    the appraiser owed no duties to the plaintiffs except those imposed by the appraisal agreement.
    
    Sadtler, 587 A.2d at 731
    .
    13
    “For example, the doctrine allows a party to enforce a promise that is not supported by
    consideration.” Peluso v. Kistner, 
    970 A.2d 530
    , 532 (Pa. Cmwlth. 2009) (citing 
    Crouse, 745 A.2d at 610
    ). Promissory estoppel is also referred to as detrimental reliance. 
    Id. 24 I
    also question whether the discovery rule should apply to
    a claim based upon promissory estoppel. Although the
    discovery rule, which evolved in the tort context, has been
    applied by Pennsylvania courts in some discrete categories
    of cases involving contractual or quasi-contractual claims,
    see, e.g., Amodeo v. Ryan Homes, Inc., 
    407 Pa. Super. 448
    ,
    453-54, 
    595 A.2d 1232
    , 1235 [1991] (stating that “the
    discovery rule does apply to cases involving defective
    construction”), its use has not been adopted on a
    wholesale basis in this area, and, notably, other
    jurisdictions are divided as to its applicability. Compare
    Morris v. Fauver, 
    153 N.J. 80
    , 
    707 A.2d 958
    , 972
    (1998)(“the rationale for employing the discovery rule in
    tort- or fraud-type actions . . . does not carry over to most
    contract actions, and therefore, the discovery rule has not
    been applied in such suits”); CLL Assoc[s.] Ltd. v.
    Arrowhead Pacific Corp., 
    174 Wis. 2d 604
    , 
    497 N.W.2d 115
    , 117 (1993)(“[i]n the context of general contract law,
    public policy favors the current rule that the contract
    statute of limitations begins to run at the time of breach”),
    with Heron Financial Corp. v. United States Testing Co.,
    
    926 S.W.2d 329
    , 332 (Tex. App. 1996)(“a discovery rule
    analysis applies to both tort and contract actions alike”).
    
    Crouse, 745 A.2d at 613
    n.1 (Saylor, J., concurring and dissenting) (emphasis
    added).
    Subsequent to Justice Saylor’s statement above, this Court issued an
    unreported decision in Ruddy v. Mt. Penn Borough Municipal Authority (Pa.
    Cmwlth., Nos. 1120 C.D. 2013 & 1200 C.D. 2013, filed May 6, 2014), in which we
    applied the discovery rule to a claim for unjust enrichment. In doing so, however,
    the Court noted, among other things, that the situation was not one “where the
    damages were based on an actual contract, but instead, on the quasi-contractual and
    equitable doctrine of unjust enrichment.” 
    Id., slip op.
    at 6.
    25
    As pointed out by Justice Saylor in Crouse, states are split as to the
    applicability of the discovery rule in breach of contract actions. For example, in
    Wisconsin, the discovery rule does not apply to actions for breach of contract. CLL
    Assocs. Ltd. The Wisconsin Supreme Court stated that although it applies the
    discovery rule to tort cases, it would not extend the doctrine to breach of contract
    actions because, “unlike in tort law, the need to protect defendants from stale or
    fraudulent claims outweighs any injustice caused by barring rights of action prior to
    discovery.” 
    Id. at 118.
    In so holding, the court relied on two critical differences
    between tort and contract claims. 
    Id. The first
    stemmed from the availability of
    liability insurance in tort law, whereas, “[i]n contrast, contract law, which deals
    primarily with the enforcement of private promises, has nothing comparable to
    liability insurance.” 
    Id. The second
    difference was that, unlike a potential tort
    claimant, “a contract claimant often has a significant amount of control over its risk
    of loss.” 
    Id. The court
    noted, for example that the parties had choices regarding
    what materials to use, inspections, warranties, price adjustments, etc., and that such
    “increased ability of potential contract claimants to protect themselves in the first
    instance lessens the need to provide them an opportunity for legal redress.”14 
    Id. Likewise, in
    New York, the discovery rule does not apply to breach of
    contract actions because
    [the state’s] statutes of limitation serve the same objectives
    of finality, certainty and predictability that New York’s
    contract law endorses. Statutes of limitation not only save
    14
    The Wisconsin Supreme Court noted that, to the extent its holding “creates unjust results
    in specific situations not now before this court, i.e.[,] in the consumer context where contracting
    consumers have limited bargaining power, the legislature, with its greater resources for weighing
    policy, is best equipped to enact specific ameliorative laws.” CLL Assocs. 
    Ltd., 497 N.W.2d at 119
    .
    26
    litigants from defending stale claims, but also “express[ ]
    a societal interest or public policy of giving repose to
    human affairs” . . . . And we have repeatedly “rejected
    accrual dates which cannot be ascertained with any degree
    of certainty, in favor of a bright line approach” . . . .
    Accordingly, New York does not apply the “discovery”
    rule to statutes of limitations in contract actions . . . .
    Rather, the “statutory period of limitations begins to run
    from the time when liability for wrong has arisen even
    though the injured party may be ignorant of the existence
    of the wrong or injury” . . . . This is so even though the
    result may at times be “harsh and manifestly unfair, and
    creates an obvious injustice” because a contrary rule
    “would be entirely dependent on the subjective equitable
    variations of different [j]udges and courts instead of the
    objective, reliable, predictable and relatively definitive
    rules that have long governed this aspect of commercial
    repose” . . . . Indeed, “[t]o extend the highly exceptional
    discovery notion to general breach of contract actions
    would effectively eviscerate the [s]tatute of [l]imitations
    in this commercial dispute arena” . . . .
    ACE Sec. Corp. v. DB Structured Prods., Inc., 
    36 N.E.3d 623
    , 627-28 (N.Y. 2015)
    (internal citations omitted).
    Similarly, in holding that the discovery rule did not apply to a breach
    of contract action for failure to follow payment provisions of a contract, the New
    Jersey Supreme Court explained:
    [a]lthough it seems “inequitable that an injured person,
    unaware that he has a cause of action, should be denied his
    day in court solely because of his ignorance, if he is
    otherwise blameless,” it may also be “unjust, however, to
    compel a person to defend a law suit long after the alleged
    injury has occurred, when memories have faded, witnesses
    have died and evidence has been lost.” . . .
    27
    Although some negligence or malpractice actions involve
    inherently undiscoverable types of injuries, most contract
    actions presume that the parties to a contract know the
    terms of their agreement and a breach is generally obvious
    and detectable with any reasonable diligence. Because
    the discovery rule imposes on plaintiffs an affirmative
    duty to use reasonable diligence to investigate a potential
    cause of action, and thus bars from recovery plaintiffs who
    had “reason to know” of their injuries, the discovery rule
    generally does not apply to contract actions.
    County of Morris v. Fauver, 
    707 A.2d 958
    , 972-73 (N.J. 1998) (emphasis added)
    (citations omitted).
    Where the discovery rule has been applied in other jurisdictions, courts
    have done so because it would be unjust to deprive plaintiffs of a cause of action
    before they are aware of an injury. For example, in California:
    the discovery rule applies to unique breach of contract
    cases when: 1) “[t]he injury or the act causing the injury,
    or both, have been difficult for the plaintiff to detect”; 2)
    “the defendant has been in a far superior position to
    comprehend the act and the injury”; or 3) “the defendant
    had reason to believe the plaintiff remained ignorant [that]
    he had been wronged.” [April Enters., Inc. v. KTTV and
    Metromedia, Inc., 
    195 Cal. Rptr. 421
    , 436 (Cal. Ct. App.
    1983)]. The rationale underlying application of the
    discovery rule is that “plaintiffs should not suffer where
    circumstances prevent them from knowing they have been
    harmed . . . [and] defendants should not be allowed to
    knowingly profit from their injuree’s ignorance.” 
    Id. El Pollo
    Loco, Inc. v. Hashim, 
    316 F.3d 1032
    , 1039 (9th Cir. 2003).
    In Arizona, the Supreme Court held that the discovery rule can apply to
    breach of contract actions because “the important inquiry in applying the discovery
    28
    rule is whether the plaintiff’s injury or the conduct causing the injury is difficult for
    plaintiff to detect, not whether the action sounds in contract or in tort.” Gust,
    Rosenfeld & Henderson v. Prudential Ins. Co. of Am., 
    898 P.2d 964
    , 968 (Ariz.
    1995).
    One commentator in discussing the discovery rule and computing a
    limitations period from “when a cause of action accrues” noted the division, i.e., the
    statutory period may begin either when the defendant commits the wrong or when
    the plaintiff is injured. Marc M. Schneier, Esq., 28 No. 2 Constr. Litig. Rep. 10 (Feb.
    2007). He explained:
    This division is fundamental to the distinction between
    contract and tort: a contract action may be brought
    immediately upon breach, whereas a tort action cannot be
    brought until the plaintiff suffers appreciable injury. The
    reason for this distinction is that, immediately upon
    material breach, a contract plaintiff is entitled to at least
    nominal damages; however, a negligent defendant is liable
    to no one until he or she causes injury. See 18 Samuel
    Williston, Williston on Contracts § 2021A at 698 (3d ed.
    1978); 51 Am.Jur.2d Limitations of Actions §§ 160 & 167
    (2000) (contract and tort, respectively); and 54 C.J.S.
    Limitations of Actions §§ 163 & 193 (2005) (contract and
    tort, respectively); accord, Travis Pruitt & Assocs., P. C.
    v. Bowling, 238 Ga.App. 225, 
    518 S.E.2d 453
    (1999), 
    20 Conn. L. Rptr. 340
    (1999).
    Schneier, 28 No. 2 Constr. Litig. Rep. 10.
    This distinction is significant. In a breach of contract action such as
    here, the injury is the failure to perform or, in other words, the breach. See Freedom
    Oil Works Co. v. Williams, 
    152 A. 741
    , 743 (Pa. 1930) (holding that where defendant
    admitted there was a breach of contract, plaintiffs were entitled at least to nominal
    29
    damages); Wolfe v. Allstate Prop. & Cas. Ins. Co., 
    790 F.3d 487
    , 497 (3d Cir. 2015)
    (stating, “[u]nder Pennsylvania law, if a plaintiff is able to prove a breach of contract
    but can show no damages flowing from the breach, the plaintiff is nonetheless
    entitled to recover nominal damages”).
    In sum, we are faced with the binding precedent of this Commonwealth
    wherein the discovery rule has been extended from the tort context to breach of
    implied warranty actions and quasi-contractual matters of promissory estoppel and
    unjust enrichment. See supra pp. 22-25. However, our Supreme Court has neither
    expressed a blanket prohibition nor has it applied the discovery rule— a judicially
    created doctrine— to a breach of contract action where a party is seeking to enforce
    an express written contract that the party negotiated. Further, although the Superior
    Court has applied the discovery rule to a breach of contract action, its decisions are
    not controlling authority for this Court. Additionally, as noted by Justice Saylor,
    other jurisdictions are split on the application of the discovery rule in a breach of
    contract action.
    We are mindful that the controlling law for determining when the
    limitations period begins to run for a breach of contract action is when the cause of
    action accrued, i.e., upon the occurrence of the breach. See 42 Pa.C.S. § 5502(a);
    Erie Ins. 
    Exch., 174 A.3d at 585-86
    ; GAI 
    Consultants, 120 A.3d at 423-24
    . Further,
    we are mindful that the discovery rule is a judicially created doctrine with equitable
    application. The Authority has not forwarded any compelling inequities as a reason
    to create a special rule as to when the statute of limitations begins to run in a breach
    of contract action based on an express written negotiated contract. The mere fact
    that a municipality is involved is not a sufficiently compelling ground. Because our
    Supreme Court has not extended the discovery rule, a judicially created equitable
    30
    doctrine, to the arena of breach of contract actions involving express written
    negotiated contracts,15 we decline to do so.
    In declining to extend the discovery rule to breach of contract actions
    based on an express written negotiated contract in the absence of precedent from our
    Supreme Court, we note that the parties to a contract are not without recourse and,
    thus, equity does not demand a contrary result. As the Wisconsin Supreme Court
    reasoned when it refused to apply the discovery rule to a breach of contract action,
    “a contract claimant often has a significant amount of control over its risk of loss.”
    CLL Assocs. 
    Ltd., 497 N.W.2d at 118
    .
    The parties here had choices over the material to use and the inspection
    procedures, and they specified those in the agreement.16                         See Bid, Div. IX,
    15
    We note the case of Gustine I in which the owners of a shopping mall sued the
    architectural contractor, as well as others, for, inter alia, breach of contract, asserting claims arising
    out of a written construction contract. Gustine 
    I, 842 A.2d at 338-39
    . Notably, the only issue
    before our Supreme Court was whether the breach of contract claim was subject to the Judicial
    Code’s four-year or six-year statute of limitations period. 
    Id. at 338.
    Although the appellants, in
    arguing for a longer limitations period, stated that Pennsylvania recognizes the discovery rule in
    breach of contract actions, 
    id. at 344,
    the Court did not mention whether the appellants cited any
    authority in support of such claim, and the Court’s note appended to that statement only cites
    Crouse relative to the discovery rule. See 
    id. at 344
    n.8. As 
    discussed, supra
    , Crouse asserted a
    claim based on the quasi-contractual theory of promissory estoppel, not a breach of contract claim
    based on a written contract.
    In Gustine I, on remand to the Superior Court, the court held that the contract language
    (stating that the “applicable statute of limitations shall commence to run” not later than the date of
    substantial completion) precluded application of the discovery rule. Gustine 
    II, 892 A.2d at 836
    .
    16
    The agreement states that the “Contract Documents form the Contract for construction.”
    Div. II, Information to Bidders, art. I- Definitions (.14), R.R. at 303a. The “Contract Documents”
    consist of the following:
    the Owner-Contractor Articles of Agreement, The Contract
    Provisions, Information to Bidders, Legal Section, Proposal and
    Bidding Sheets, Scope of Work, Statement of Bidders
    Qualifications, Engineering Specifications (General and Detail),
    Plans as defined in the Scope of Work, Schedule of Drawings, and
    31
    Engineering Specifications, R.R. at 408a-85a. For example, the contract provided
    that the engineer would be the Authority’s representative during construction until
    final payment is due. Bid, Div. VI, Contract Provisions, art. 1, § 1.01(.2); R.R. at
    353a. The contract further provided that the engineer would visit the site at
    appropriate intervals to become familiar with the progress and quality of work. 
    Id. at §
    1.01(.4); R.R. at 353a. The contract further required Port Vue to have copies of
    the contract documents and an additional set of plans at the work site for use by the
    engineer and the Authority, and provided for observation of the work at all times by
    the engineer and the Authority. 
    Id. at §
    1.01(.4-.5); R.R. at 353a; see also Bid, Div.
    VI, Contract Provisions, art. 3, § 3.11(.1); R.R. at 366a.
    We recognize that despite Glenn’s acknowledgement that the work
    could have been visually inspected at any time by climbing down the manhole with
    a flashlight, N.T. at 56, R.R. at 119a, the trial court found that “technology for video
    inspection of the work was not readily available at the time and physical inspection
    of the work after it was completed was not possible due to the subsurface nature of
    the project.” Trial Court Opinion at 4. However, parties to a contract have choices
    over inspection procedures and can negotiate those in advance. That was done here
    using various procedures that were available to the parties at the time. Indeed, the
    bid specifications for the project set forth documents that Port Vue would be
    responsible for providing upon completion of the project and expressly required,
    among other things:
    shall include the Public Advertisement, Addenda (if any), Change
    Orders, as issued, Notice of Award, Notice to Proceed, all Bonds
    and Insurance as defined elsewhere, and the Federal Guideline
    Requirements, if applicable.
    Div. II, Information to Bidders, art. 1, Definitions (.15), R.R. at 304a.
    32
    “Record” or “As-Built” Drawings
    01.    The Contractor shall be responsible for supplying a
    clean and legible set of final drawings clearly showing the
    final position of all equipment or materials used in
    construction of the project. This set of drawings must be
    turned over to the Engineer and approved by the Owner
    before the final payment is released on the project. This
    drawing must be on the same data set as the existing
    drawing and a CAD.dwg file of the manholes supplied.
    Bid, Div. V, Scope of Work, Part 4.00, § 4.04(.01); R.R. at 345a. The contract also
    provided for the engineer to conduct reviews to determine final completion. Bid,
    Div. VI, Contract Provisions, art. 1, § 1.06(.2); R.R. at 356a. Port Vue also agreed
    under the contract to make repairs for a period of 18 months after the date of
    completion and to deliver a bond to the Authority to ensure completion. Bid, Div.
    VI, Contract Provisions, art. 3, § 3.06(.14); R.R. at 364a; see 
    id. at §
    3.18(.2); R.R.
    at 370a. The Authority does not argue, nor does it point to any contract provision,
    that purportedly provides for a statute of limitations period longer than the four years
    allowed by law upon the occurrence of a breach. This “increased ability of potential
    contract claimants to protect themselves in the first instance lessens the need to
    provide them an opportunity for legal redress.” CLL Assocs. 
    Ltd., 497 N.W.2d at 118
    . Further, from a practical equitable perspective, to apply the discovery rule to
    the situation here would leave contractors with prolonged and open-ended liability
    and an unwillingness to contract with municipalities given an open-ended exposure
    period.
    Because we decline to extend the discovery rule to this breach of
    contract action based on an express written negotiated contract in the absence of
    Pennsylvania Supreme Court precedent doing so, we conclude that the trial court
    erred as a matter of law in applying the discovery rule to the Authority’s breach of
    33
    contract claim and, therefore, in concluding that the complaint was timely. See
    
    Crouse, 745 A.2d at 611
    (stating whether a complaint is timely filed is a matter of
    law). Nonetheless, we must address the Authority’s alternative argument that Port
    Vue is estopped from asserting the statute of limitations as a defense under the
    doctrine of fraudulent concealment.
    (iii)     Fraudulent concealment
    The discovery rule is distinct from the issue of whether a
    party is equitably estopped from invoking the statute of
    limitations. Fine v. Checcio, 
    582 Pa. 253
    , 
    870 A.2d 850
                (2005). The discovery rule operates to toll the statute of
    limitations during the period the plaintiff’s injury or its
    cause was neither known nor reasonably knowable to the
    plaintiff. 
    Id. The separate
    doctrine of fraudulent
    concealment tolls the statute based on an estoppel theory
    and provides that a defendant may not invoke the statute
    of limitations if through either intentional or unintentional
    fraud or concealment, the defendant causes the plaintiff to
    relax his vigilance or deviate from his duty of inquiry into
    the facts. 
    Id. Thus, the
    former doctrine involves a
    plaintiff’s lack of knowledge and the latter doctrine
    pertains to a defendant’s conduct after the cause of action
    arose.
    Gustine 
    II, 892 A.2d at 835
    n.2.
    The doctrine of fraudulent concealment is rooted in equity. 4 West’s
    Pa. Prac., Torts: Law and Advocacy § 17.6 (November 2018) (citing Nesbitt v. Erie
    Coach Co., 
    204 A.2d 473
    , 476 (Pa. 1964)). Our Supreme Court has explained that
    “[t]he doctrine does not require fraud in the strictest sense encompassing an intent
    to deceive, but rather, fraud in the broadest sense, which includes an unintentional
    deception.” 
    Fine, 870 A.2d at 860
    (citing Deemer v. Weaver, 
    187 A. 215
    (Pa. 1936)).
    “The plaintiff has the burden of proving fraudulent concealment by clear, precise,
    34
    and convincing evidence.” 
    Id. “Mistake, misunderstanding
    or lack of knowledge in
    themselves do not toll the running of the statute of limitations.” 
    Id. at 857.
    “While
    it is for the court to determine whether an estoppel results from established facts, it
    is for the jury [or judge sitting as the factfinder] to say whether the remarks that are
    alleged to constitute the fraud or concealment were made.” 
    Id. at 860
    (citing 
    Nesbitt, 204 A.2d at 476
    ).
    The trial court never addressed the Authority’s argument regarding
    fraudulent concealment, presumably because it was not necessary to do so given the
    trial court’s determination that the discovery rule applied to toll the statute of
    limitations.17 Our ruling, however, makes it necessary to reach this issue. Because
    factual determinations are necessary, we must remand this matter to the trial court
    to address this issue.
    Accordingly, we vacate the trial court’s order and remand the matter to
    the trial court to issue a new decision determining whether Port Vue is estopped from
    asserting the statute of limitations as a defense to the Authority’s claim under the
    doctrine of fraudulent concealment.18
    __________________________________
    CHRISTINE FIZZANO CANNON, Judge
    17
    We note the Authority raised the issue of fraudulent concealment before the trial court.
    See Authority’s Complaint ¶ 18, 20; Authority’s Brief in Opposition of Port Vue’s Motion for
    Post-Trial Relief, R.R. at 53a-54a.
    18
    Because of our disposition, we do not reach the issue of whether the damages awarded
    to the Authority exceeded those allowed by law.
    35
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Carmen Carulli and Barbara                 :
    Carulli, husband and wife                  :
    :
    v.                             :
    :
    North Versailles Township                  :
    Sanitary Authority                         :
    :
    v.                             :
    :
    Port Vue Plumbing, Inc.,                   :   No. 751 C.D. 2017
    Appellant                 :
    ORDER
    AND NOW, this 13th day of August, 2019, the order of the Allegheny
    County Court of Common Pleas (trial court) is VACATED and the matter is
    REMANDED to the trial court to issue a new decision in accordance with the
    foregoing opinion.
    Jurisdiction relinquished.
    __________________________________
    CHRISTINE FIZZANO CANNON, Judge
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Carmen Carulli and Barbara Carulli,     :
    husband and wife                        :
    :
    v.                          :
    :
    North Versailles Township Sanitary      :
    Authority                               :
    :   No. 751 C.D. 2017
    v.                          :
    :   Argued: October 17, 2018
    Port Vue Plumbing, Inc.,                :
    Appellant              :
    BEFORE:     HONORABLE MARY HANNAH LEAVITT, President Judge
    HONORABLE RENÉE COHN JUBELIRER, Judge
    HONORABLE P. KEVIN BROBSON, Judge
    HONORABLE PATRICIA A. McCULLOUGH, Judge
    HONORABLE ANNE E. COVEY, Judge
    HONORABLE CHRISTINE FIZZANO CANNON, Judge
    HONORABLE ELLEN CEISLER, Judge
    DISSENTING OPINION
    BY JUDGE McCULLOUGH                                      FILED: August 13, 2019
    I dissent respectfully, yet earnestly, from the Majority’s conclusions
    that the Allegheny County Court of Common Pleas (trial court) erred in applying
    the discovery rule—or, more precisely, that the discovery rule does not apply in
    this case—and that a remand is required in order for the trial court to address the
    issue of whether the statute of limitations (SOL) was tolled under the doctrine of
    fraudulent concealment. To me, both of these conclusions are unnecessary and
    unwarranted.
    First, in my view, a remand to the trial court would be entirely
    redundant because the trial court already issued the factual findings necessary for
    this Court to readily conclude that Port Vue Plumbing, Inc. (PVP) engaged in
    conduct that amounted to fraudulent concealment. Specifically, as found by the
    trial court, PVP made an affirmative misrepresentation to North Versailles
    Township Sanitary Authority (Authority) that it performed the contract and
    replaced the sewer lines, and the Authority relied on that misrepresentation and
    was unable to discover the non-performance through the exercise of reasonable
    diligence.1 Under long-standing precedent, these facts are sufficient to establish
    1
    In its opinion, the trial court found and determined that the SOL was tolled until the
    point in time in which,
    The Authority became aware that PVP failed to complete the work
    as required by the contract. PVP contracted with the Authority to
    complete the entire project. On all occasions PVP represented to
    the Authority that all work required under the contract was
    completed. The Authority relied on PVP’s representation that all
    work had been completed because technology for video inspection
    of the work was not readily available at the time and physical
    inspection of the work after it was completed was not possible due
    to the subsurface nature of the project. Testimony was provided at
    trial that conducting a video inspection of a newly installed sewer
    line was not a standard practice at the time. Without such special
    equipment, inspection of the site was limited to surface conditions
    and there was no indication that PVP had not completed the work
    or that there was a problem with the work. PVP was fully
    qualified to complete the work, had performed work for the
    Authority on prior occasions, and continually informed
    representatives of the Authority that the work was being
    completed. In light of the circumstances, it was reasonable for the
    Authority to rely on the representations of PVP that all work had
    been completed.
    There was nothing to put the Authority on notice that the work
    may not have been completed until [the date on which] the
    (Footnote continued on next page…)
    PAM – 2
    fraudulent concealment and toll the applicable SOL as a matter of law. See, e.g.,
    Nesbitt v. Erie Coach Co., 
    204 A.2d 473
    , 477 (Pa. 1964) (concluding that the SOL
    was tolled via fraudulent concealment where “the agents of the defendant misled
    the plaintiff into believing” that a set a circumstances existed and “lulled her into a
    sense of false security”); cf. Toy v. Metropolitan Life Ins. Co., 
    928 A.2d 186
    , 207
    (Pa. 2007) (stating that “the recipient of an allegedly fraudulent misrepresentation
    is under no duty to investigate its falsity in order to justifiably rely”).2
    Second, while fraudulent concealment requires a showing of at least
    unintentional deception, 
    Nesbitt, 204 A.2d at 477
    , be it a misrepresentation or
    concealment, on the part of a defendant, the discovery rule does not. Instead, as
    the Majority acknowledges, the discovery rule is a distinct legal principle that
    focuses upon a plaintiff’s lack of knowledge with respect to his/her injury or its
    cause. See Fine v. Checcio, 
    870 A.2d 850
    , 857-61 (Pa. 2005); Nesbitt, 204 A.2d
    (continued…)
    Authority was notified that the basement of a house along Bevan
    Road was flooded with raw sewage. Upon such occurrence, the
    Authority acted with reasonable diligence to inspect the line and it
    was then that the Authority discovered the failure of PVP to
    complete the work.        For the aforementioned reasons, the
    Authority's claims are not time barred.
    Trial court op. at 4. Notably, although the trial court did not use the words “fraudulent
    concealment” in its opinion, the trial court clearly applied the doctrine in theory.
    2
    See also Amodeo v. Ryan Homes, Inc., 
    595 A.2d 1232
    , 1236-37 (Pa. Super. 1991)
    (concluding that principles of estoppel prevent a party from raising a SOL defense where the
    party agrees to perform a repair, represents to the other party that the repair was performed, and
    the other party relied upon the representation); Via Net v. TIG Insurance Co., 
    211 S.W.3d 310
    ,
    313 (Tex. 2006) (“Due diligence may include asking a contract partner for information needed to
    verify contractual performance. If a contracting party responds to such a request with false
    information, accrual may be delayed for fraudulent concealment.”).
    PAM – 3
    at 476-77; Gustine Uniontown Associates, Ltd. v. Anthony Crane Rental, Inc., 
    892 A.2d 830
    , 835 n.2 (Pa. Super. 2006). Since this matter can be disposed based
    solely upon the doctrine of fraudulent concealment, I believe that the Majority
    should refrain from addressing and deciding the broader issue of whether the
    discovery rule should apply to breach of contract claims in the context of this
    particular case where a misrepresentation is present. I find that such judicial
    restraint is absolutely imperative considering the body of case law from our
    Supreme Court, which, at the very least, strongly suggests that, as a matter of
    statutory construction, the discovery rule is implied or read into the term “accrued”
    in section 5502(a) of the Judicial Code, 42 Pa.C.S. §5502(a), and applies to each
    and every SOL listed in subchapter B of Chapter 55 of the Judicial Code, 42
    Pa.C.S. §§5521-38, necessarily including the SOL in section 5525(8) for contract
    actions based on an express written agreement, 42 Pa.C.S. §5525(8).3                       See
    Pastierik v. Duquesne Light Co., 
    526 A.2d 323
    , 325 (Pa. 1987) (holding that
    “application of the discovery rule” occurs when there are “[s]tatutory references to
    . . . the accrual of a ‘cause of action’” because these claims “are subject to judicial
    interpretation as to the degree of knowledge a plaintiff must possess before the
    statute will start to run”); see also Wilson v. El Daief, 
    964 A.2d 354
    , 363 (Pa.
    2009) (“[T]he discovery rule . . . is now appropriately regarded as an application of
    statutory construction arising out of the interpretation of the concept of the
    ‘accrual’ of causes of action. See 42 Pa.C.S. §5502(a).”); 
    Fine, 870 A.2d at 857-58
    3
    Section 5502 contains the heading, “Method of computing periods of limitation
    generally,” and states in relevant part: “The time within which a matter must be commenced
    under this chapter shall be computed . . . from the time the cause of action accrued . . . .” 42
    Pa.C.S. §5502(a) (emphasis added). Undoubtedly, the four-year limitation period in section
    5525 of the Judicial Code for actions sounding in contract is part of Chapter 55.
    PAM – 4
    (reiterating that section 5502(a) provides “that limitations periods are computed
    from the time the cause of action accrued” and emphasizing that even if a cause of
    action “has accrued and the prescribed statutory period has run,” the discovery rule
    is an “exception[] that act[s] to toll the running of a statute of limitations,” and that
    “the salient point giving rise to its application is the inability of the injured, despite
    the exercise of reasonable diligence, to know that he is injured and by what
    cause”); Crouse v. Cyclops Industries, 
    745 A.2d 606
    (Pa. 2000) (concluding that a
    count for promissory estoppel, although technically a “quasi-contract” claim, was
    governed by the four-year SOL in section 5525(4) for breach of contract claims
    and, more importantly, was subjected to the discovery rule).
    Moreover, following the above precedent from our Supreme Court,
    the Superior Court has concluded definitively that “[t]he discovery rule in
    Pennsylvania applies to all causes of action, including breach of contract.”
    Morgan v. Petroleum Products Equipment Co., 
    92 A.3d 823
    , 828 (Pa. Super.
    2014); see, e.g., Levenson v. Souser, 
    557 A.2d 1081
    , 1086-87 (Pa. Super. 1989) (en
    banc) (concluding that where the cause of action “does not fix a definite event as
    the beginning of the limitations period” and is instead subjected to section 5502(a)
    and the concept of “accrual” enunciated therein, the discovery rule applies
    “because the accrual of the cause of action is not fixed as one definitively
    established event and the existence of the cause of action may not be reasonably
    ascertainable within the limitations period”).        Likewise, in cases concerning
    alleged breaches of express oral and written contracts, federal district courts have
    held that “Pennsylvania recognizes a discovery rule in breach of contract cases.”
    Creghan v. Procura Management, Inc., 
    91 F. Supp. 3d 631
    , 649 (E.D. Pa. 2015);
    accord Slamon v. Carrizo (Marcellus) LLC (M.D. Pa., No. 3:16-CV-2187, filed
    PAM – 5
    September 5, 2017) (unreported), 
    2017 U.S. Dist. LEXIS 143242
    , at *31.
    Ultimately, this case law, although not binding, should provide this Court with
    additional cause for concern, prompting hesitation and reluctance to decide an
    issue that need not be decided and “to tread lightly in our examination.” In re
    Tribune Media Co., 
    799 F.3d 272
    , 276 (3d Cir. 2015).
    The Majority says that “[o]ur Supreme Court, however, has not
    pronounced the applicability of the discovery rule to a breach of contract action
    based on an express written contract negotiated at arms’ length.” Slip op. at 24.
    However, the Majority has not cited one case where a court has concluded that the
    discovery rule does not apply to any of the causes of action in subchapter B of
    Chapter 55 of the Judicial Code.          Absent such authority, and in light of the
    Pennsylvania case law discussed above, I cannot find persuasive value in the
    foreign jurisdictions that the Majority relies upon to reach its conclusion and must
    consider these cases to be of little to no value because they appear to be
    inconsistent with the law of our state.
    Rather, on balance, I find that the foreign jurisdictions that have
    concluded that the discovery rule applies in breach of contract actions represents a
    more considered and reasoned judgment on the issue—one that is in harmony with
    Pennsylvania Supreme Court precedent and the spirit of Pennsylvania law. Under
    this approach, the discovery rule would apply to an alleged breach of a written
    contract “in situations where the breach is ‘inherently undiscoverable,’ ‘inherently
    unknowable,’ or ‘difficult to detect,’” Individual Healthcare Specialists, Inc. v.
    BlueCross BlueShield of Tennessee, Inc., 
    566 S.W.3d 671
    , 711-12 & n.43 (Tenn.
    2019), but would not apply in cases where the plaintiff fails to exercise due
    diligence, specifically “cases where the plaintiff’s injury is open and obvious.”
    PAM – 6
    Gust, Rosenfeld & Henderson v. Prudential Insurance Co. of America, 
    898 P.2d 964
    , 967 (Ariz. 1995). Indeed, our Supreme Court has stressed that “[t]he salient
    point giving rise to the equitable application of the exception of the discovery rule
    is the inability, despite the exercise of diligence by the plaintiff, to know of the
    injury,” Pocono International Raceway, Inc., v. Pocono Produce Inc., 
    468 A.2d 468
    , 471 (Pa. 1983), and “[t]he rationale behind the discovery rule is that it is
    unjust to deprive a plaintiff of a cause of action before the plaintiff has a
    reasonable basis for believing that a claim exists.” 
    Gust, 898 P.2d at 967
    . In my
    view, the underlying reasons supporting the discovery rule are not diminished in
    any way based upon the status of a suit being labeled a contract claim, for the
    discovery rule “relates more to the circumstances under which a legal duty is
    breached and less to the nature of the cause of action.” 
    Id. As the
    Arizona
    Supreme Court explained:
    In fact, we find little to distinguish tort and contract such
    that the discovery rule should properly apply to one but
    not to the other. The difference between tort and contract
    liability has become an increasingly difficult distinction
    to make.        But insofar as tort and contract are
    distinguishable, [the defendant’s] arguments do not
    persuade us. We have said that the statute of limitations
    serves to protect defendants and courts from stale claims
    where plaintiffs have slept on their rights. However
    whether a tort victim or contract claimant, a blamelessly
    uninformed plaintiff cannot be said to have slept on his
    rights. Furthermore, the problems associated with stale
    litigation (e.g., failing memory, unavailable witnesses)
    are no more acute in contract claims than they are in tort.
    And in either case, the requirement that parties exercise
    reasonable diligence safeguards against cases where a
    plaintiff has truly allowed his claim to become stale. We
    also reject the suggestion that application of the
    discovery rule to contract cases would eviscerate the
    statute of limitations in commercial disputes. The
    PAM – 7
    discovery rule has applied uniformly in tort cases for
    some time, and we do not believe that the statute of
    limitations has ceased to serve its purpose in tort cases.
    
    Id. at 968-69
    (internal citations and quotation marks omitted).
    Therefore, I believe that the Majority lacks sufficient justification to
    create a special exception for written contracts—an exception that, apparently for
    the first time in the history of Pennsylvania law, exempts application of the
    discovery rule from a cause of action listed in subchapter B of Chapter 55 of the
    Judicial Code. In the end, though, I would decline to reach the issue of whether the
    discovery rule applies to actions founded upon an express written contract and
    would conclude that, under the doctrine of fraudulent concealment, the Authority’s
    claim is not barred by the SOL.
    Hence, I respectfully dissent.
    ________________________________
    PATRICIA A. McCULLOUGH, Judge
    PAM – 8
    

Document Info

Docket Number: 751 C.D. 2017

Judges: Fizzano Cannon, J. ~ Dissenting Opinion by McCullough, J.

Filed Date: 8/13/2019

Precedential Status: Precedential

Modified Date: 8/13/2019

Authorities (34)

Gust, Rosenfeld & Henderson v. Prudential Insurance Co. of ... , 182 Ariz. 586 ( 1995 )

El Pollo Loco, Inc. v. Hashim , 316 F.3d 1032 ( 2003 )

Travis Pruitt & Associates, P. C. v. Bowling , 238 Ga. App. 225 ( 1999 )

Gleason v. Borough of Moosic , 609 Pa. 353 ( 2011 )

April Enterprises, Inc. v. KTTV , 195 Cal. Rptr. 421 ( 1983 )

Fine v. Checcio , 582 Pa. 253 ( 2005 )

Wilson v. El-Daief , 600 Pa. 161 ( 2009 )

Pocono International Raceway, Inc. v. Pocono Produce, Inc. , 503 Pa. 80 ( 1983 )

Toy v. Metropolitan Life Insurance , 593 Pa. 20 ( 2007 )

Centre Concrete Co. v. AGI, INC. , 522 Pa. 27 ( 1989 )

Crouse v. Cyclops Industries , 560 Pa. 394 ( 2000 )

Freedom Oil W. Co. v. Williams , 302 Pa. 51 ( 1930 )

Deemer v. Weaver, Exrx. , 324 Pa. 85 ( 1936 )

Northampton County Area Community College v. Dow Chemical, ... , 528 Pa. 502 ( 1991 )

Peluso v. Kistner , 970 A.2d 530 ( 2009 )

Harleysville Homestead, Inc. v. Lower Salford Township ... , 980 A.2d 749 ( 2009 )

McGAFFIC v. City of New Castle , 973 A.2d 1047 ( 2009 )

Southeastern Pennsylvania Transportation Authority v. Union ... , 161 Pa. Commw. 400 ( 1994 )

Pastierik v. Duquesne Light Co. , 514 Pa. 517 ( 1987 )

Gustine Uniontown Associates, Ltd. v. Anthony Crane Rental, ... , 577 Pa. 14 ( 2004 )

View All Authorities »