Hidden Creek, L.P. v. Lower Salford Twp. Authority ( 2015 )


Menu:
  •                  IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Hidden Creek, L.P.                       :
    :
    v.                 :
    :
    Lower Salford Township Authority,        :   No. 1839 C.D. 2014
    Appellant         :   Argued: May 8, 2015
    BEFORE:        HONORABLE DAN PELLEGRINI, President Judge
    HONORABLE P. KEVIN BROBSON, Judge
    HONORABLE ANNE E. COVEY, Judge
    OPINION BY
    JUDGE COVEY                                  FILED: September 14, 2015
    The Lower Salford Township Authority (Authority) presents this
    interlocutory appeal from the Montgomery County Common Pleas Court’s (trial
    court) September 15, 2014 order denying its summary judgment motion. The issues
    before the Court as directed by this Court’s October 29, 2014 Order are as follows:
    “[w]hen does the applicable two[-]year statute of limitations begin to run for Hidden
    Creek, L.P.’s [(Developer)] claim of excessive tapping fees[; and,] [i]s the Authority
    entitled to governmental immunity from [Developer’s] claim that tap[p]ing fees were
    charged in violation of the Municipal[ity] Authorities Act [(MAA).1]” 
    Id. After review,
    we affirm.
    Developer was the owner and developer of 90 single-family residential
    lots in a community known as Hidden Creek in Lower Salford Township. On
    February 17, 1998, the Authority approved Resolution 98-3-17 (1998 Resolution)
    setting a $6,875.00 tapping fee, based upon a study performed by the Authority’s
    engineer, Carroll Engineering Corporation (Engineer). On August 18, 1998, the
    1
    53 Pa.C.S. §§ 5601-5623.
    Authority and Developer entered into an “Agreement for the Construction of Sewer
    Lines” (Agreement). Pursuant to the Agreement, Developer would construct sewer
    lines as part of the Hidden Creek development.                 The Agreement also required
    Developer to purchase 90 equivalent dwelling units (EDU) of capacity in the
    Authority’s wastewater collection and treatment system, and to pay $6,875.00 per
    EDU as a tapping fee, but further provided that “[t]apping fees shall be offset by the
    cost of certain off-site sewer improvements constructed by Developer.” Reproduced
    Record (R.R.) at 170a. On December 21, 1999, the Authority approved Resolution
    99-12-21 (1999 Resolution) which increased tapping fees to $7,000.00 per EDU,
    effective January 1, 2000. Developer made its first tapping fee payment on January
    29, 1999 and its last payment on January 21, 2000.2
    On September 25, 2000, Developer filed a writ of summons to initiate
    litigation to recover its alleged tapping fees’ overpayment. Developer initially filed
    its complaint on July 31, 2002, but on November 17, 2006, filed a First Amended
    Complaint (Complaint) alleging that the Authority improperly calculated the tapping
    fees in violation of the MAA and overcharged Developer. Developer’s Complaint
    sought damages representing excess tapping fees paid to the Authority, plus interest
    and costs.
    On February 21, 2014, the Authority filed its summary judgment motion
    arguing, inter alia, that Developer’s claim was barred by the statute of limitations and
    that the Authority was protected from liability by governmental immunity. By July
    30, 2014 order, the trial court denied the Authority’s summary judgment motion. On
    August 21, 2014, the Authority filed a Motion to Amend Order Entered July 30, 2014
    to Permit Interlocutory Appeal Pursuant to 42 Pa.C.S. § 702(b) (Motion to Amend).
    2
    The Authority’s brief explains that of the 90 EDUs, Developer ultimately paid for 54
    tapping fees totaling $372,125.00, and that Developer received a credit for 36 tapping fees totaling
    $252,000.00 reflecting the Authority’s share of the cost of Developer’s off-site improvements.
    Authority’s Br. at 8.
    2
    By September 15, 2014 order, the trial court amended its July 30, 2014 order. On
    October 15, 2014, the Authority filed a Petition for Permission to Appeal with this
    Court (Petition). On October 27, 2014, Developer filed an answer to the Petition. On
    October 29, 2014, this Court granted the Petition.3
    The Authority first contends that the trial court erred when it failed to
    find that Developer’s claim was time-barred. Consistent with the case of Harleysville
    Homestead, Inc. v. Lower Salford Township Authority, 
    980 A.2d 749
    (Pa. Cmwlth.
    2009), the parties agree that a two-year statute of limitations applies in the instant
    matter, but disagree on when the statute began to run. The Authority argues that the
    limitations period began to run (at the latest) when the contract was executed and
    Developer was obviously aware of the amount of the tapping fee.                            In contrast,
    Developer asserts that because it is seeking an overpayments’ refund, its cause of
    action did not accrue until it paid the allegedly erroneous fees, and that it filed its
    action within two years of its first payment.
    In Harleysville, a developer sought damages representing overpayments
    to the Authority in violation of the MAA. The Authority moved to dismiss the action
    based, inter alia, on its assertion that the action was barred by the two-year statute of
    limitations set forth in Section 5524 of the Judicial Code.4 The developer countered
    that a four-year limitations period applied because it had entered into an agreement
    3
    Our scope of review of a trial court’s order granting or denying
    summary judgment is plenary, and our standard of review is clear: the
    trial court’s order will be reversed only where it is established that the
    court committed an error of law or abused its discretion. Summary
    judgment is proper only where there is no genuine issue as to any
    material fact and it is clear that the moving party is entitled to a
    judgment as a matter of law.
    Kincel v. Dep’t of Transp., 
    867 A.2d 758
    , 761 n.7 (Pa. Cmwlth. 2005) (citation omitted).
    4
    42 Pa.C.S. § 5524.
    3
    with the Authority to pay the tapping fees. Relying on the Court’s decision in
    Petticord v. Joyce, 
    578 A.2d 632
    (Pa. Cmwlth. 1990), this Court agreed that a two-
    year statute of limitations applied to the developer’s claim. The Court held that the
    developer’s refund claim sounded in tort and that the developer’s agreement to pay
    the tapping fees was merely “collateral to [the developer’s] cause of action.”
    
    Harleysville, 980 A.2d at 753
    .
    The Harleysville Court did not address the pertinent issue before us – the
    date from which the statute runs - but did note that
    [t]he trial court also relied upon two similar cases in which
    it determined, based on Petticord, that the two[-]year statute
    of limitations applied wherein the plaintiffs[] contended that
    the . . . Authority violated a statutory duty to set reasonable
    prices for the purchase of sewer capacity. Both of these
    cases were affirmed by this Court in unpublished opinions.
    See K. Hov[n]anian at Perkiomen I, Inc. v. Montgomery
    C[nty.] Sewer Auth[.], (No. 95-21147, filed January 25,
    1999) aff’d, (Pa. Cmwlth., No. 3433 C.D. 1998, filed July
    14, 1999); and LHC Realty Corp[.] v. Montgomery C[nty.]
    Sewer Auth[.], (No. 96-03457, filed June 29, 1998) aff’d,
    (Pa. Cmwlth., No. 1514 C.D. 1998, filed May 7, 1999).
    
    Harleysville, 980 A.2d at 751
    n.5. Although unreported opinions are not binding
    precedent, the cited LHC decision addresses a situation substantially similar to the
    instant case, and thus, its reasoning provides insight and is persuasive authority. See
    Commonwealth Court’s Internal Operating Procedures Section 414.
    In LHC, a developer applied to the municipal authority to reserve 341
    sewer connections for a proposed townhouse development. The municipal authority
    charged a tapping fee of $4,500.00 per unit, for a total fee of $1,534,500.00. The
    developer purchased the connections and executed a capacity rights agreement with
    the municipal authority. Thereafter, by the Act of December 19, 1990, P.L. 1227,
    No. 203 (Act 203), the General Assembly amended the then-applicable Municipal
    4
    Authorities Act of 1945 (1945 Act)5 which regulated the rates that municipal
    authorities could charge. The amendment, effective June 1991, exempted from its
    applicability all pre-existing agreements. On June 4, 1991, the municipal authority
    adopted a resolution reducing its fee for sanitary sewer capacity, but exempted pre-
    existing agreements.
    The developer defaulted on its financial obligations and, in July 1991,
    the municipal authority transferred the 341 sewer connections to the developer’s
    successor-in-interest (Successor).        In February 1994, the municipal authority
    increased the rate for sanitary sewer capacity, but exempted pre-existing agreements.
    Successor filed suit alleging that the capacity rights agreement was unlawful under
    the 1945 Act and the municipal authority’s refusal to refund overpayments violated
    the 1945 Act. The municipal authority moved for summary judgment, arguing, inter
    alia, that the action was barred by a two-year statute of limitations. The trial court
    granted summary judgment, finding that the 1945 Act, and the municipal authority’s
    rate resolutions specifically exempted pre-existing agreements. Importantly, the trial
    court also found the action was barred by the two-year statute of limitations. The trial
    court stated:
    [I]n the instant case, Plaintiff claims that it was caused to
    incur unnecessary expense because [the municipal
    authority] breached it [sic] statutory duty to set reasonable
    prices for EDU sewer capacity, and thus, as in Petticord,
    this case should be governed by a two-year statute of
    limitations period. Statutes of limitation begin to run as
    soon as the right to institute and maintain suit arises;
    lack of knowledge, mistake or misunderstanding do not
    toll the running of the limitation period. . . . Since the
    Plaintiff alleges that the unreasonable charge for EDU’s
    [sic] was incurred . . . when the Capacity Rights Agreement
    5
    Section 3 of the Act of June 19, 2001, P.L. 287, repealed the MAA of 1945, Act of May 2,
    1945, P.L. 382, as amended, formerly 53 P.S. §§ 301-322.
    5
    was executed, any claim arising therefrom should have
    been brought within two years[.]
    LHC, slip op. at 6 (quoting Common Pleas Court Opinion, June 29, 1998 at 5-6)
    (emphasis added). This Court agreed, stating: “[The developer] chose to reserve the
    EDU’s [sic] by executing the capacity rights agreement and paying $4,500[.00] per
    EDU in 1989, and the statute of limitations began to run at that time.” LHC, slip
    op. at 7 (emphasis added).
    In the instant action, Developer’s Complaint alleges, “the Authority
    required [Developer] to enter into [the Agreement]” which mandated that Developer
    pay the allegedly improper fee. R.R. at 132a (emphasis added). The Agreement
    included Developer’s obligation to:
    pay to the Authority a connection and/or tapping fee in the
    amount of Six Thousand Eight Hundred Seventy-Five
    Dollars ($6,875.00) for each of the forty-four (44) units to
    be constructed, or a total sum of Three Hundred Two
    Thousand Five Hundred Dollars ($302,500.00). Tapping
    fees shall be offset by the cost of certain off-site sewer
    improvements constructed by Developer. The remaining
    tapping fees due shall be divided by the forty-four (44) units
    and paid as a building permit for each unit at the time the
    building permit is issued.
    R.R. at 170a. Upon execution of the Agreement, Developer became legally obligated
    to pay the Authority tapping fees in the allegedly erroneous amount dictated in the
    Agreement. Although the Agreement provides that tapping fees were to be offset by
    the cost of other improvements, it is the alleged miscalculation of the tapping fees
    (and not the offsets) that is the subject of this litigation.
    A “statute of limitations begins to run as soon as the right to institute and
    maintain a suit arises.” Fine v. Checcio, 
    870 A.2d 850
    , 857 (Pa. 2005). Developer
    was harmed upon the execution of the Agreement, the moment it was legally
    obligated to pay an allegedly unlawful fee.
    6
    Developer argues that even if this Court determines that the statute of
    limitations would normally start running before the date of payment, the trial court
    properly denied the Authority’s summary judgment motion based upon the
    “discovery rule.”
    The ‘discovery rule,’ so-called, is an exception to the
    requirement that a complaining party must file suit within
    the statutory period. The discovery rule provides that where
    the existence of the injury is not known to the complaining
    party and such knowledge cannot reasonably be ascertained
    within the prescribed statutory period, the limitations period
    does not begin to run until the discovery of the injury is
    reasonably possible.
    ....
    [T]he rule is an equitable one, which excludes the period of
    time during which the injured party is reasonably unaware
    that an injury has been sustained so that people in that class
    have essentially the same rights as those who suffer an
    immediately ascertainable injury. Although the purpose of
    this rule is to mitigate, in worthy cases, the harshness of an
    absolute and rigid period of limitations, it is also true that
    the rule cannot be applied so loosely as to nullify the
    purpose for which a statute of limitations exists.
    The party seeking to invoke the discovery rule bears the
    burden of establishing the inability to know of the injury
    despite the exercise of reasonable diligence. The standard
    of reasonable diligence is objective, not subjective. It is not
    a standard of reasonable diligence unique to a particular
    plaintiff, but instead, a standard of reasonable diligence as
    applied to a reasonable person.
    Dalrymple v. Brown, 
    701 A.2d 164
    , 167 (Pa. 1997) (citations and quotation marks
    omitted).
    Developer contends “that it was not aware until after it had made the
    payments, and . . . did not have any reason to know at the time it made such
    7
    payments, that [the Authority] had improperly calculated the base amount of the
    tapping fee[.]” Developer Br. at 8.
    Importantly, Section 5607(d)(24)(i)(C) of the MAA, entitled “Tapping
    fee[,]” provides:
    A tapping fee shall not exceed an amount based upon some
    or all of the following parts [capacity part; distribution or
    collection part; special purpose part; reimbursement part]
    which shall be separately set forth in the resolution
    adopted by the authority to establish these fees. In lieu
    of payment of this fee, an authority may require the
    construction and dedication of only such capacity,
    distribution-collection or special purpose facilities
    necessary to supply service to the property owner or
    owners.
    53 Pa.C.S. § 5607(d)(24)(i)(C) (emphasis added). Further, Section 5607(d)(24)(ii) of
    the MAA states in relevant part:
    Every authority charging a tapping, customer facilities or
    connection fee shall do so only pursuant to a resolution
    adopted at a public meeting of the authority. The authority
    shall have available for public inspection a detailed
    itemization of all calculations, clearly showing the
    maximum fees allowable for each part of the tapping fee
    and the manner in which the fees were determined,
    which shall be made a part of any resolution imposing
    such fees.
    53 Pa.C.S. § 5607(d)(24)(ii) (bold and italic emphasis added).         Finally, Section
    5607(d)(24)(iii) provides: “No authority shall have the power to impose a connection
    fee, customer facilities fee, tapping fee or similar fee except as provided specifically
    under this section.” 53 Pa.C.S. § 5607(d)(24)(iii).
    The Authority’s resolutions establishing the applicable tapping fees
    state, in relevant part:
    8
    RESOLUTION   ESTABLISHING               TAPPING       FEE
    PURSUANT TO ACT 203
    WHEREAS, [Engineer] has performed a study to
    determine the appropriate amount that the [Authority] may
    charge as a tapping fee; and
    WHEREAS, the results of the Engineer’s study
    indicated that the Authority could charge a tapping fee in
    excess of Seven Thousand Dollars ($7,000.00); and
    WHEREAS, the Authority is desirous of increasing
    its tapping fee but does not desire to charge the maximum
    fee permissible; and
    WHEREAS, the Authority, upon the proper motion
    and second, adopted an increase in tapping fees at its
    December 11, 1997 meeting.
    NOW, THEREFORE, be it resolved and it is hereby
    resolved as follows:
    1. Authority hereby adopts Engineer’s Act 203 study dated
    November, 1997 as a basis for calculating its tapping fees.
    2. Authority hereby establishes its tapping fee at Six
    Thousand Eight Hundred and Seventy-five Dollars
    ($6,875,00), effective December 11, 1997.
    3. All other resolutions inconsistent herewith are deemed
    rescinded.
    1998 Resolution, R.R. at 152a-153a.
    RESOLUTION   ESTABLISHING               TAPPING       FEE
    PURSUANT TO ACT 203
    WHEREAS, [Engineer] has performed a study to determine
    the appropriate amount that the [Authority] may charge as a
    tapping fee; and
    WHEREAS, the results of the Engineer’s study indicated
    that the Authority could charge a tapping fee in excess of
    Seven Thousand Dollars ($7,000.00); and
    9
    WHEREAS, the Authority is desirous of increasing its
    tapping fee but does not desire to charge the maximum fee
    permissible; and
    WHEREAS, the Authority, upon the proper motion and
    second, adopted an increase in tapping fees at its December
    21, 1999 meeting.
    NOW, THEREFORE, be it resolved and it is hereby
    resolves as follows:
    1. Authority hereby adopts Engineer’s Act 203 study dated
    December, 1999 as a basis for calculating its tapping fees.
    2. Authority hereby establishes its tapping fee at Seven
    Thousand Dollars ($7,000.00), effective January 1, 2000.
    3. All other resolutions inconsistent herewith are deemed
    rescinded.
    1999 Resolution, R.R. at 196a-197a.
    Although both Resolutions adopted the Engineer’s studies, the
    components providing the basis for the tapping fees were not separately set forth in
    the Resolutions as the MAA required. Nor do the Resolutions indicate that the
    Engineer’s studies are attached thereto. Thus, the Resolutions do not provide any
    basis to evaluate the accuracy of the tapping fees. The absence of these required
    components in the Resolutions further supports Developer’s contention that it did not
    have reason to know of the alleged calculation errors in the tapping fee at the time it
    agreed to pay the fee or thereafter.6
    6
    Because the issue is not before us, we do not consider the impact of the apparent defects in
    the Resolutions on the Authority’s ability to impose the tapping fees based thereon. See Norristown
    Mun. Waste Auth. v. 200 E. Airy, LLC (Pa. Cmwlth. No. 1977 C.D. 2010, filed November 30,
    2011). In Norristown, an unreported opinion, this Court held that a trial court properly struck off a
    lien imposed by a municipal authority for failure to pay a tapping fee. Although the trial court
    struck the lien because the resolution imposing the fee was adopted after the municipality sought
    payment from the landowner, this Court also noted that the result would be the same had the
    municipal authority relied upon an earlier resolution because:
    10
    Our Supreme Court has held:
    The point at which the complaining party should be
    reasonably aware that he or she has suffered an injury
    and its cause is ordinarily an issue of fact to be
    determined by the jury due to the fact[-]intensive nature
    of the inquiry. Only where the facts are so clear that
    reasonable minds could not differ may a court determine as
    a matter of law at the summary judgment stage, the point at
    which a party should have been reasonably aware of his or
    her injury and its cause and thereby fix the commencement
    date of the limitations period.
    Gleason v. Borough of Moosic, 
    15 A.3d 479
    , 485 (Pa. 2011) (citations omitted;
    emphasis added).
    Here, legitimate factual questions remain as to whether Developer was
    reasonably unaware that the tapping fee was allegedly erroneous, and the Authority’s
    apparent failure to comply with the MAA in adopting its tapping Resolutions may
    have deprived Developer of information necessary to evaluate the accuracy of the
    tapping fee. Because “the facts are [not] so clear that reasonable minds could not
    differ” as to when Developer should have been reasonably aware of the alleged error
    The . . . [r]esolution purports to set tapping fees ‘as such term is
    defined in the Sewer System Tapping Fee Report, and prepared by
    Keystone Alliance Consulting and dated February 2008.’ R.R. 64a.
    The . . . [r]esolution further provides that ‘[t]he tapping fee amount is
    based on the calculations, prepared by Keystone Alliance Consulting
    and presented in the aforementioned Report, and is allocated between
    the collection and capacity components.’ 
    Id. However, the
                   [r]esolution does not attach the report or have a separate resolution
    setting forth the fees as required by the [sic] 53 Pa.C.S.
    §5607(d)(24)(i). 
    Id. Norristown, slip
    op. at 9 n.9.
    11
    in tapping fees, we conclude that the trial court properly denied the Authority’s
    summary judgment motion on the timeliness issue. 
    Id. at 485.
                  The Authority next asserts that Developer’s action is barred by the act
    commonly known as the Political Subdivision Tort Claims Act (Tort Claims Act), 42
    Pa.C.S. §§ 8541-8542. Section 8541 of the Tort Claims Act provides that “[e]xcept
    as otherwise provided in this subchapter, no local agency shall be liable for any
    damages on account of any injury to a person or property caused by any act of the
    local agency or an employee thereof or any other person.” 42 Pa.C.S. § 8541.
    Section 8542 of the Tort Claims Act, 42 Pa.C.S. § 8542, provides exceptions to the
    aforementioned immunity, none of which are applicable to the instant matter.
    In Meyer v. Community College of Beaver County, 
    2 A.3d 499
    (Pa.
    2010) (Meyer I), our Supreme Court considered whether a community college was
    immune from liability to its former students when it lost its certification. The Court
    vacated the decision of the Commonwealth Court which had reversed the trial court’s
    denial of the college’s partial summary judgment motion, and held that
    “governmental immunity does not extend to all statutory causes of action, regardless
    of whether they sound in tort or contract.” 
    Id. at 503.7
                  Thereafter, in Dorsey v. Redman, 
    96 A.3d 332
    (Pa. 2014), the Supreme
    Court considered whether a register of wills was immune under the Tort Claims Act
    from statutory liability permitted by Section 3172 of the Probate, Estates and
    Fiduciaries Code (PEF Code).8 The Court first noted:
    7
    On remand, this Court, in an en banc decision, concluded that the college, a political
    subdivision agency, was a person subject to suit under the Unfair Trade Practices and Consumer
    Protection Law (CPL), Act of December 16, 1968, P.L. 1224, as amended, 73 P.S. §§ 201.1—201-
    9.3. The Court further found that the students’ claims sounded in contract and thus the Tort Claims
    Act did not bar the action. On appeal, the Supreme Court reversed, finding that the General
    Assembly did not intend that the definition of ‘person’ include political subdivision agencies.
    Meyer v. Cmty. College of Beaver County, 
    93 A.3d 806
    (Pa. 2014).
    8
    20 Pa.C.S. §§ 3171-3172. Section 3172 of the PEF Code states:
    12
    As questions of governmental immunity are legislative in
    nature, we begin by considering the dictates found in the
    Statutory Construction Act (‘SCA’). 1 Pa.C.S.[] §§ 1501 et
    seq. The objective of all interpretation and construction of
    statutes is to ascertain and effectuate the intention of the
    General Assembly. 1 Pa.C.S.[] § 1921(a). The best
    indication of the legislature’s intent is the plain language of
    the statute. When the words of a statute are clear and
    unambiguous, we may not go beyond the plain meaning of
    the language of the statute ‘under the pretext of pursuing its
    spirit.’ 
    Id. § 1921(b).
    Therefore, only when the words of a
    statute are ambiguous, should a reviewing court seek to
    ascertain the intent of the General Assembly through
    considerations of the various factors found in Section
    1921(c) [of the SCA]. 
    Id. § 1921(c);
    see generally Bayada
    Nurses Inc. v. . . . Dep[’]t [of] Labor [&] Indus., . . . 
    8 A.3d 866
    , 880-81 ([Pa.] 2010). Additionally, we are mindful
    that, in interpreting the Tort Claims Act, exceptions to the
    absolute rule of immunity expressed in the statute ‘must be
    narrowly interpreted given the expressed legislative intent
    to insulate political subdivisions from tort liability.’
    Mascaro v. Youth Study Ctr., . . . 
    523 A.2d 1118
    , 1123
    ([Pa.] 1987).
    
    Dorsey, 96 A.3d at 340-41
    . The Dorsey Court further explained that in Meyer I, it
    had
    eschewed a rote approach to determining immunity. While,
    generally, the appropriate analysis to determine whether the
    protections of the Tort Claims Act may cloak an employee
    of a local government entity with immunity first looks to
    whether the cause of action sounds in tort, or some other
    cause of action, such as in contract, we do not find this
    tort/contract construct to be necessarily appropriate in all
    questions of immunity.
    If any register shall grant letters without having taken such bond as is
    required by law, he and his surety shall be liable to pay all damages
    which shall accrue to any person by reason thereof. Nothing herein
    stated shall be deemed to relieve the personal representative from
    liability which would otherwise be imposed upon him by law.
    20 Pa.C.S. § 3172.
    13
    
    Dorsey, 96 A.3d at 341
    .
    Ultimately, the Dorsey Court held that governmental immunity did not
    apply, finding that Section 3172 of the PEF Code “creates a targeted form of
    accountability resting outside of the scope of governmental . . . immunity.” 
    Dorsey, 96 A.3d at 341
    . Applying the canons of statutory construction, the Court found “that
    the General Assembly . . . intended to maintain a protective scheme for preservation
    of estate assets through the PEF Code, and that this scheme persists outside of the
    scope of governmental . . . immunity under the Tort Claims Act.” 
    Id. at 342.
                 Relying on Dorsey and Meyer I, and citing to various sections of the
    MAA, Developer contends that its claim is not barred because the MAA expressly
    permits it. Specifically, Developer points to Section 5607(d)(2) of the MAA which
    allows municipal authorities to “sue and be sued.”           53 Pa.C.S. § 5607(d)(2).
    Developer also references Section 5607(d)(9) of the MAA which authorizes “[a]ny
    person questioning the reasonableness or uniformity of a rate fixed by an authority or
    the adequacy, safety and reasonableness of the authority’s services, including
    extensions thereof, [to] bring suit against the authority in the court of common pleas
    of the county where the project is located . . . .” 53 Pa.C.S. § 5607(d)(9). Developer
    further relies upon Section 5607(d)(24)(iii) of the MAA which prohibits an authority
    from imposing a tapping fee in contravention of the MAA. Developer maintains that
    it is not seeking an award of consequential damages or general damages, but rather
    the return of its own funds that the Authority allegedly improperly charged and
    collected, plus interest for the time it was deprived of those funds.
    Developer contends that the adoption of the Authority’s position would
    frustrate Section 5607 of the MAA’s purpose. Developer reasons:
    To uphold [the Authority’s] position would mean that a
    municipal authority can adopt a fee that is in violation of
    the statute and can then use its power to withhold needed
    permits, thereby placing a developer in a squeeze where the
    14
    developer has to choose between: [a] economic loss by
    refusing to pay the excessive fees and not getting the
    needed permit and, instead, spending years in litigation with
    the municipal authority trying to get the permits without
    paying the excessive fee, or [b] paying the fee and never be
    able to secure a refund of its own funds that the legislature
    decided could not be charged. It defies logic (and any sense
    of justice) to hold that the legislature when it adopted the
    limitation on tapping fees in the [MAA] and when it
    allowed a municipal authority to be sued, including sued as
    to its fees, made such prohibition to be so toothless and
    ineffective that a party faced with a demand for an improper
    fee was limited to the Hobson’s choice set forth above
    between suffering damages of one type or the other. It
    similarly would be improper and illogical to hold that the
    legislature when it allowed municipal authorities to be sued
    and for lawsuits to be filed over an authority’s fees did not
    intend that the permitted lawsuits and challenges to fees
    would include suits for a return of fees that the legislature
    had declared that the authority could not charge but that
    immunity would apply to bar the return of improperly
    charged fees.
    Developer’s Br. at 30-31. We agree.
    The General Assembly, through its careful crafting of the MAA’s
    extraordinarily detailed provisions for determining the component parts, limited the
    amounts that municipal authorities could charge for tapping fees. See 53 Pa.C.S. §
    5607(d)(24)(i)(C).   The General Assembly also specifically permitted municipal
    authorities to be sued, and for the reasonableness of their rates to be challenged.
    Rates charged in excess of those permitted by statute are not reasonable rates.
    Although Developer’s action is indeed a challenge to the Authority’s
    fees, it is also an action to recover damages. However, those damages are simply the
    funds the Authority collected, if any, exceeding the lawfully permitted rate. There is
    no claim for consequential damages. Developer’s cause of action, if successful,
    merely makes the Authority adhere to the MAA by returning monies it obtained in
    violation thereof, along with accrued interest. It is illogical to presume that where the
    15
    General Assembly set forth stringent restrictions on tapping fees, providing extensive
    guidance for the determination of those fees and permitting legal challenges thereto,
    it intended that a municipal authority which violates the restrictions and collects
    excessive fees, should be immune from an action to recover those unlawfully
    assessed fees. “We cannot presume that the legislature intended such an absurd
    result. 1 Pa.C.S. § 1922(1).” Todd v. Workmen’s Comp. Appeal Bd. (NCR Corp.),
    
    692 A.2d 1086
    , 1087 (Pa. 1997). Accordingly, in the instant circumstances, we
    conclude that Section 5607(d) of the MAA “creates a targeted form of accountability
    resting outside of the scope of governmental . . . immunity.” 
    Dorsey, 96 A.3d at 341
    .
    For all of the above reasons, the trial court’s order is affirmed.
    ___________________________
    ANNE E. COVEY, Judge
    16
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Hidden Creek, L.P.                    :
    :
    v.                  :
    :
    Lower Salford Township Authority,     :   No. 1839 C.D. 2014
    Appellant      :
    ORDER
    AND NOW, this 14th day of September, 2015, the Montgomery County
    Common Pleas Court’s September 15, 2014 order is affirmed.
    ___________________________
    ANNE E. COVEY, Judge
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Hidden Creek, L.P.                :
    :
    v.                    : No. 1839 C.D. 2014
    : Argued: May 8, 2015
    Lower Salford Township Authority, :
    Appellant        :
    BEFORE:      HONORABLE DAN PELLEGRINI, President Judge
    HONORABLE P. KEVIN BROBSON, Judge
    HONORABLE ANNE E. COVEY, Judge
    CONCURRING OPINION BY
    PRESIDENT JUDGE PELLEGRINI                            FILED: September 14, 2015
    I concur with the result reached by the majority because of the issues
    that have been raised and the interlocutory nature of the appeal. I write separately
    because I do not believe that the challenge regarding whether the tap-in fees are
    excessive is maintainable under the facts of this case.
    In February 1998, the Lower Salford Township Authority (Authority)
    approved a resolution setting a $6,875.00 tapping fee. After the enactment of the
    resolution, in August 1998, the Authority and Hidden Creek, L.P. (Developer)
    entered into an “Agreement for the Construction of Sewer Lines” (Agreement) under
    which the Developer would construct sewer lines and pay the Authority for the costs
    incurred by inspecting and administering the project. The Agreement also provided
    that the Developer was to pay $6,875.00 per each equivalent dwelling unit (EDU) as
    a tapping fee,1 but that those tapping fees would be offset by the cost of certain off-
    site sewer improvements made by the Developer.2 The Developer made its first
    tapping fee payment on January 29, 1999, and its last payment on January 21, 2000.
    On September 25, 2000, the Developer filed a writ of summons to
    initiate litigation to recover its alleged overpayment of tapping fees that ultimately led
    to the First Amended Complaint (Complaint) filed in November 2006, which alleged
    that the Authority overcharged the Developer by improperly calculating the tapping
    fees in violation of the Municipal Authorities Act (MAA)3 and sought damages
    representing the excess tapping fees paid to the Authority, plus interest and costs.
    The Authority claimed that the claim, among other things, was time barred.
    The parties agree that a two-year statute of limitations applies, but
    disagree on when the statute of limitations began to run. The Authority argues that
    the limitations period began to run (at the latest) when the contract was executed and
    that the Developer was obviously aware of the amount of the tapping fee. The
    Developer asserts that because it is seeking a refund of overpayments, its cause of
    action did not accrue until it paid the allegedly erroneous fees, and that it filed its
    action within two years of its first payment.
    1
    The Developer ultimately paid for 54 tapping fees totaling $372,125.00, and received a
    credit for 36 tapping fees totaling $252,000.00, reflecting the Authority’s share of the cost of the
    Developer’s off-site improvements.
    2
    Later, on December 21, 1999, the Authority approved Resolution 99-12-21 (1999
    Resolution) which increased the tapping fees to $7,000.00 per EDU, effective January 1, 2000.
    3
    53 Pa. C.S. §§5601-5623.
    DRP - 2
    While the majority finds that the Developer was harmed upon the
    execution of the Agreement, the moment that it was legally obligated to pay an
    allegedly unlawful fee, it remands to determine whether the Developer was aware
    under the discovery rule that the tapping fee was excessive due to the Authority’s
    apparent failure to comply with the MAA in adopting its tapping resolution which
    may have deprived the Developer of information necessary to evaluate the accuracy
    of the tapping fee.
    In this case, the Agreement provided that the Developer would perform
    some off-site sewer work and would pay the Authority for its costs and expenses in
    inspecting the Developer’s work, as well as other administrative costs that it incurred.
    If there is a dispute regarding those administrative costs, the property owner is
    required to challenge them within 60 days of billing of those costs and the matter is
    then submitted to arbitration on a strict schedule. Section 5607(30) of the MAA, 53
    Pa. C.S. §5607(30).
    Under this Agreement, there was also an additional provision that the
    Developer was to pay the Authority an agreed-upon price of $6,875.00 per EDU, and
    that there was no reservation of the right to challenge the tapping fee in the
    Agreement. Notwithstanding that it agreed to pay a certain amount, the Developer is
    attempting to challenge the underlying calculation of the tapping fees as if they were
    not fixed by the Agreement. The question then is can property owners challenge the
    amount of the tapping fee and when can they challenge it.
    Without definitively deciding the issue, there seems to me to be only two
    possible ways to challenge the fee. When a property owner desires to connect to a
    DRP - 3
    sewer system, there is no written agreement between the property owner and the local
    authority or municipality. Normally, as a prerequisite to obtaining a building permit
    from the local municipality, the property owner has to show proof that it can dispose
    of solid waste whether by an approved septic system or a tap-in to an approved
    sewage system. When the owner obtains the permission to tap-in, he or she pays the
    required fee.        If, at that time, the property owner believes that the amount is
    excessive, he or she can pay the fee under protest and bring a challenge, like all
    administrative determinations, under the Local Agency Law4 that the fee is not
    properly calculated, with subsequent appeals to the common pleas court. In some
    circumstances, though, before the permit process has even begun, a property owner
    may be able to challenge the fee through an action under the Declaratory Judgments
    Act.5
    While I believe that a property owner can normally challenge the fee as
    outlined above, I disagree that, in this case, the Developer can challenge the amount
    here because it agreed to pay $6,875.00 per EDU under the Agreement and can pay
    no more or no less. However, because this issue is not before us, I concur with the
    majority’s result.
    ___________________________________
    DAN PELLEGRINI, President Judge
    4
    2 Pa. C.S. §§551-555, 751-754.
    5
    42 Pa. C.S. §§7531-7541.
    DRP - 4