EDF Renewable Energy v. Foster Twp. ZHB and Foster Twp. , 150 A.3d 538 ( 2016 )


Menu:
  •          IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    EDF Renewable Energy,                :
    : No. 2601 C.D. 2015
    Appellant   : Argued: September 13, 2016
    :
    v.                 :
    :
    Foster Township Zoning               :
    Hearing Board and Foster             :
    Township                             :
    EDF Renewable Energy                 :
    : No. 2645 C.D. 2015
    v.                 : Argued: September 13, 2016
    :
    Foster Township Zoning               :
    Hearing Board                        :
    :
    v.                 :
    :
    Foster Township                      :
    :
    Appeal of: Foster Township           :
    Zoning Hearing Board                 :
    BEFORE:     HONORABLE RENÉE COHN JUBELIRER, Judge
    HONORABLE MICHAEL H. WOJCIK, Judge
    HONORABLE ROCHELLE S. FRIEDMAN, Senior Judge
    OPINION
    BY JUDGE WOJCIK                                  FILED: November 22, 2016
    EDF Renewable Energy (EDF) appeals from the November 18,
    2015 order of the Court of Common Pleas of Luzerne County (trial court), which
    affirmed the decision of the Foster Township (Township) Zoning Hearing Board
    (ZHB) to deny EDF’s application for a special exception to construct wind farms
    in three different zoning districts in the Township. The ZHB cross-appeals and
    argues that the appeal should be quashed as premature. We affirm.
    In July 2014, EDF applied for a permit to construct approximately 25
    wind turbines, approximately 525’ high, as well as roads, collection cables, and a
    substation on properties located in the Township’s C-1 (Conservation), A-1
    (Agricultural), and I-1 (General Industrial) zoning districts. The zoning officer
    denied the application because the proposed use was not a permitted use in the
    districts.1
    Township Ordinance Section 255-36 states that whenever a use is
    neither specifically permitted nor denied in a district, the zoning hearing officer
    shall refer an application for such use to the ZHB to hear and decide as a special
    exception. Pursuant to that provision, EDF submitted an application for a special
    exception to the ZHB. R.R. at 21a. The application was accompanied by a letter,
    R.R. at 22a-23a, which briefly outlined the project, the parcels likely to be included
    for the project, and the proposed uses for each parcel, as well as a map, R.R. at
    24a, which had circled areas indicating the approximate location of the wind
    turbines, and agreements with landowners, R.R. at 26a-41a.
    Under Section 255-36 of the Ordinance, the ZHB may permit a
    proposed use
    only if it is determined to be similar to and compatible
    with permitted uses in the district and in no way is in
    conflict with the general purposes and intent of this
    chapter. The burden of proof shall be upon the applicant
    to demonstrate that the proposed use would meet the
    1
    The transcript reflects that EDF had met with the township solicitor about an
    amendment to the Ordinance. Reproduced Record (R.R.) at 111a-14a. Ordinance Section
    255.132 sets forth procedures and criteria for adoption of curative amendments but is not
    referenced in this appeal.
    2
    standards and criteria for a special exception as contained
    in [Ordinance Section] 255-142B of this chapter and
    would not be detrimental to the public health, safety and
    welfare and/or environmental features and characteristics
    of the site and/or surrounding areas.
    R.R. at 483a. Section 255-51 of the Ordinance specifically authorizes the ZHB to
    approve or deny applications for uses permitted by special exception “pursuant to
    the standards and criteria set forth in §255-142B,[2] the respective zoning district in
    2
    Section 255-142B states:
    (1) The Board shall hear and decide requests for uses and/or
    development which are permitted as special exception uses.
    Special exception uses may be referred to the Planning
    Commission for its review, comments and recommendations prior
    to final action by the Board. The Board shall grant approval only
    upon determination that the proposed use and/or development
    conforms with all applicable standards and provisions within this
    chapter and the following express standards and criteria:
    (a) The proposed use shall not jeopardize community
    development objectives as [set forth in] the Foster Township
    Comprehensive Plan, including any updates, revisions and/or
    amendments thereto.
    (b) Public services and facilities such as streets . . . shall be
    adequate for the proposed use and/or development.
    (c) Existing streets and proposed access to the site shall be
    adequate . . . for emergency vehicles.
    (d) Existing streets and proposed access to the site shall be
    adequate to accommodate anticipated traffic volumes . . . .
    (e) The proposed use shall be compatible with adjoining
    development and the character of the zoning district and
    neighborhood in which it is proposed to be located. The nature
    and intensity of the operation of the proposed use shall be
    considered regarding its compatibility or lack thereof.
    (Footnote continued on next page…)
    3
    which the use is located, [and] all other applicable regulations of this chapter . . . .”
    R.R. at 503a.
    Additionally, Ordinance Section 255-52 states that an applicant for a
    special exception must file a site plan:
    A. Uses classified as a special exception shall file, in
    addition to a zoning permit, a site plan at a scale of: (1)
    One inch equals 50 feet for uses/developments located
    upon properties in excess of two acres; or (2) One inch
    equals 20 feet for uses/developments located upon
    properties two acres or less.
    B. Such plan shall provide all applicable information
    required for the Zoning Hearing Board to render a
    decision, including, but not limited to the following:
    (1) The applicant shall submit a narrative outline that
    fully describes all proposed uses or development of the
    site, and all pertinent operational aspects, features, and/or
    (continued…)
    (f) The proposed use shall not substantially impair the value of
    other property in the neighborhood where it is proposed to be
    located.
    (g) The proposed use and/or development shall not be more
    objectionable in its operations in terms of noise, fumes, odors,
    vibration, or lights than would be the operations of any permitted
    use in the subject zoning district.
    (h) The submission of any reports and/or studies, required by the
    Board, within the context of the definition “impact analysis,” . . . .
    (i) The proposed use and/or development shall not be injurious to
    the public interest.
    R.R. at 581a-82a.
    4
    activities related to the proposed uses or development of
    the site.
    (2) The applicant shall provide upon the site plan the
    location and size of all buildings and structures, existing
    and proposed, including both principal and accessory
    buildings and structures.
    (3) The applicant shall provide upon the site plan the
    location of all off-street parking areas and/or loading
    areas.
    (4) The applicant shall provide upon the site plan the
    location of all open space areas, including buffer areas
    and fencing, if applicable.
    (5) The applicant shall provide upon the site plan the
    means of traffic access to the site and internal traffic
    circulation within the site including the width and
    pavement of traffic lanes, and aisle widths.
    (6) The applicant shall provide upon the site plan all
    streets, both public and private, within 200 feet of the
    site, including the right-of-way and cartway widths.
    (7) The applicant shall provide upon the site plan the
    contours of the site for each five feet of change in
    elevation, based upon a field survey of the site, with the
    name of the person or firm who conducted the survey and
    the date of the survey when the proposed use includes
    new construction and/or grading of the site.             If
    applicable, the applicant shall be required to submit a
    Soil Erosion and Sedimentation Plan for review and
    approval by the Luzerne County Conservation District.
    (8) The applicant shall provide upon the site plan the
    location, nature and terms of any existing or proposed
    easements on the site and any easements both on-site and
    off-site which are used or intended to be used for access
    to the site, including the name and address of the owner
    or owners granting such easements.
    5
    (9) The applicant shall provide upon the site plan the
    location of all streams, ponds, watercourses, wetlands or
    any other bodies of water, including natural or man-made
    drainage swales, located on the site or within 200 feet of
    the site.
    (10) The applicant shall provide upon the site plan the
    location of any residential structure within 200 feet of
    any property boundary line of the subject site, when the
    proposed use is nonresidential.
    (11) The applicant shall supply upon the site plan the
    County Map, block and lot number of the subject parcel
    as contained in the records in the office of the Luzerne
    County Recorder of Deeds and a copy of the deed to the
    subject property.
    (12) The applicant shall provide upon the site plan a
    location map at a scale of not greater than one inch
    equals 2,000 feet, indicating the relationship of the site to
    its geographic proximity within the Township.
    (13) The applicant shall supply any other information
    required by the Foster Township Zoning Hearing Board
    for determining the conformance of the special exception
    use with the applicable regulations for that particular use.
    R.R. at 503a-504a (emphasis added).
    The ZHB held a hearing on EDF’s application on September 24,
    2014, which was continued to November 6, 2014, and concluded on December 3,
    2014. EDF presented testimony and other evidence and provided a 36” x 24” copy
    of the map submitted with its application for reference.
    Doug Copeland, EDF’s regional development manager, testified that
    EDF had obtained several leases and had secured rights with other property
    owners. He stated that the noise generated by the proposed use would be only
    about 55 decibels, the equivalent of a running refrigerator, at the property line of
    6
    adjacent land. Copeland provided additional testimony about each of the three
    areas in which wind turbines would be situated.
    As to the C-1 district, he stated that roads would be constructed using
    existing haul roads to minimize land clearing. He estimated that there would be 8
    or 9 wind turbines in this area, with the closest turbine situated 1700 feet from the
    nearest home. Coleman explained that the final location of the wind turbines
    would be determined based upon soil conditions and added that trees would block
    the view from most homes. R.R. at 101a-40a.
    Copeland testified that the area zoned A-1 was situated between 2
    coal seams and said that there were no homes within a mile of that location.
    Coleman estimated that there would be 4 or 5 wind turbines on the A-1 site. He
    said that EDF would use existing roads in this area to the extent possible. R.R. at
    147a-50a.
    Copeland stated that the I-1 property was scrub land, a high point
    between two active mining operations, with mining on one side and a quarry to the
    north. He stated that EDF would build a new road, approximately 3 miles long and
    15 feet wide, with a clearance of 50 feet. He estimated that EDF would construct
    12 to 14 wind turbines at that location. R.R. at 154a-57a.
    Copeland testified that a substation also would be located on the I-1
    property, explaining that a substation acts like a breaker box. Coleman could not
    say how the wind turbines in each area would be connected to the substation. He
    testified that EDF’s preference would be underground connections, but he noted
    that overhead connections would be simpler, and he stated that EDF was “in the
    process of figuring that out.” R.R. at 158a-61a.
    7
    Copeland estimated that the wind turbines would be situated about
    1000 feet apart, with each encompassing about 1 acre of land. R.R. at 307a, 373a.
    He added that the wind farm would have FAA-required lighting, which would have
    minimal or no impact on nearby residents. Copeland also testified regarding
    preliminary studies EDF conducted concerning sound and wildlife impact, noting
    that EDF signed an agreement for cooperation with the Pennsylvania Game
    Commission. Copeland emphasized the economic benefit the project would bring
    to the area, stating that it would likely generate half a million dollars in zoning
    permit fees alone. R.R. at 185a-86a.
    Bob Hazenstab, EDF operations manager for Chestnut Flats
    Windfarm in Altoona, testified about the revenue generated by the Altoona project.
    He described noise studies conducted there, and he noted the absence of water
    runoff issues. Hazenstab also addressed potential safety concerns and explained
    that the wind turbines are designed to fall in half, not their full length of 525 feet.
    R.R. at 191a-208a.
    Alan Rosen, a licensed real estate appraiser, testified that he is
    familiar with the area and that the wind farm would have no adverse effect on
    property values in the area. R.R. at 72a-99a.
    Several residents testified in opposition to the proposal, including the
    president of the Greater Hazleton Area Astronomical Society, who complained that
    the wind turbines would block the night sky and would cause light pollution. R.R.
    at 310a-15a.     The general manager of the nearby Beech Mountain Lakes
    development testified that the wind farm would have a detrimental impact on
    property values, up to 11% according to a British study. R.R. at 319a. Other
    8
    residents objected based on concerns of noise and the project’s potential impact on
    wildlife.
    During the course of the hearing, the ZHB referred the matter to the
    township planning commission, which held two hearings and twice recommended
    that the proposed use be denied as not similar to or compatible with permitted uses
    in the districts. On December 3, 2014, the ZHB voted to deny EDF’s application,
    and the ZHB confirmed its oral decision in a January 2, 2015 letter to EDF,
    detailing its findings and conclusions. R.R. at 607a-12a.
    In its written decision, the ZHB found that EDF wanted to construct
    approximately 25 wind turbines, each approximately 525-feet high, and would
    construct approximately 4 miles of roadways, utilizing approximately 2 miles of
    existing roads. The ZHB noted that EDF produced a generalized map of the entire
    area, including other municipalities, with ovals indicating the approximate location
    of the wind turbines. However, the ZHB observed that the map does not show the
    roadways or the location of the 25 wind turbines, proposed collection cables and
    substation.3 (FF Nos. 10-13).
    The ZHB also found that the matter was referred to the township’s
    planning commission, which issued a written decision finding that the proposed
    use of wind turbines as part of a wind farm is not similar to or compatible with
    permitted uses in the district and does not fall within the Comprehensive Plan for
    Foster Township, and the ZHB stated that it adopted the planning commission’s
    recommendation and decision. (FF Nos. 14-20).
    3
    The ZHB erroneously stated that no leases were entered into the record. FF No. 2. We
    conclude that this error is harmless.
    9
    The ZHB recognized that Ordinance Section 255-52 expressly
    requires an applicant for a special exception to submit a site plan, at a scale of 1
    inch equals 50 feet for developments in excess of 2 acres, along with 13 specific
    requirements, such as the location and size of all proposed structures. (FF Nos. 21-
    29). The ZHB found that the scale of the map submitted by EDF is 1 inch equals
    1.4 miles and that the map is devoid of essential information, including the number
    of wind turbines proposed for each of the three areas, the proposed location of the
    turbines at each site, and their proposed size and height. (FF No. 30). The ZHB
    determined that as a result of its non-compliance with Section 255-52, EDF did not
    supply the information necessary to demonstrate compliance with the standards
    and criteria set forth in Ordinance Section 255-142(B). (FF Nos. 31-32).
    The ZHB further found that EDF failed to produce sufficient evidence
    to establish that the proposed use would not adversely affect the community or
    impact property values. (FF No. 39) Additionally, the ZHB found that EDF failed
    to meet its burden of production and burden of proof on the standards necessary for
    a special exception under Section 255-36, in that EDF did not demonstrate that the
    proposed use as a wind farm is similar to or compatible with permitted uses in the
    district and falls within the Comprehensive Plan for Foster Township, and EDF’s
    documents did not provide the information required under Section 255-52 of the
    Ordinance. (FF Nos. 33-37).
    The ZHB’s written decision is dated January 2, 2015. R.R. at 629a-
    34a. On that same date, EDF filed a Notice of Land Use Appeal, stating that it was
    appealing the ZHB’s December 3, 2014 decision.          According to affidavits of
    counsel for the ZHB and the Township, the ZHB’s written decision was not mailed
    until January 5, 2015.    The ZHB filed a motion to quash EDF’s appeal as
    10
    prematurely filed, which the trial court denied by order dated June 4, 2015. EDF
    filed a Supplemental Notice of Appeal on January 30, 2015.
    The trial court denied EDF’s appeal on the grounds that EDF failed to
    comply with the objective criteria of the Ordinance, i.e., Section 255-52 (site plan),
    and failed to carry its burden of persuasion to demonstrate that the proposed use of
    wind turbines was similar to or compatible with the comprehensive plan for the
    Township. EDF now appeals to this Court,4 arguing that the ZHB capriciously
    disregarded evidence and thus erred in denying the special exception application.
    The ZHB cross-appeals, arguing that the trial court erred in failing to grant the
    ZHB’s motion to quash EDF’s appeal as premature.
    We first address the ZHB’s contention that EDF’s appeal should be
    quashed as premature.           Citing Magyar v. Zoning Hearing Board of Lewis
    Township, 
    885 A.2d 123
    , 128 (Pa. Cmwlth. 2005), Snyder v. Zoning Hearing
    Board of Warminster Township, 
    782 A.2d 1088
    , 1090 (Pa. Cmwlth. 2001),
    Sections 914.1(b), 1001-A, and 1002-A of the Municipalities Planning Code
    (MPC),5 and Section 5572 of the Judicial Code, 42 Pa.C.S. §5572,6 the ZHB
    4
    When the trial court takes no additional evidence in a land use appeal, our scope of
    review is limited to determining whether the zoning hearing board committed an error of law or
    abused its discretion. Slusser v. Black Creek Township Zoning Hearing Board, 
    124 A.3d 771
    ,
    773 n.2 (Pa. Cmwlth. 2015). A zoning hearing board abuses its discretion when its findings are
    not supported by substantial evidence. Id. Substantial evidence means relevant evidence that a
    reasonable mind might accept as adequate to support a conclusion. Id.
    5
    Act of July 31, 1968, P.L. 805, as amended, added by the Act of December 21, 1988,
    P.L. 1329, 53 P.S. §§10914.1(b), 11001-A, and 11002-A. Section 11001-A of the MPC states
    that “[t]he procedures set forth in this article shall constitute the exclusive mode for securing
    review of any decision rendered pursuant to Article IX or deemed to have been made under this
    act.” Section 10914.1(b) of the MPC provides that “[a]ll appeals from determinations adverse to
    the landowners shall be filed by the landowner within 30 days after notice of the determination is
    issued.” 53 P.S. §10914.1(b). Section 11002-A of the MPC states that appeals from land use
    (Footnote continued on next page…)
    11
    asserts that for purposes of appeal, the date of entry of the ZHB’s order is the mail
    date. Noting that counsel for both the ZHB and the Township attested that the
    ZHB’s written decision was not mailed until January 5, 2015, the ZHB argues that
    EDF’s January 2, 2015 appeal, which references the ZHB’s December 3, 2014
    decision, was taken from the ZHB’s oral decision and should be quashed as
    premature.
    However, both Magyar and Snyder are distinguishable from the
    circumstances presented here. Magyar was a “procedurally unusual case,” 885
    A.2d at 124, involving an appeal from a deemed denial governed by Section 908(a)
    of the MPC, 53 P.S. §10908(a) (requiring public notice of a deemed denial to
    trigger the 30-day appeal period). In Snyder, the appeal was filed 15 days before
    the date of the zoning board’s order, and this court pointedly noted “[a]dditionally,
    Appellants never filed a subsequent appeal within thirty days after the entry of the
    decision, as required by the MPC.” 782 A.2d at 1090 (emphasis added).
    EDF responds that the ZHB’s decision is in fact dated January 2,
    2015, and it expressly states that an appeal must be filed “within thirty (30) days of
    the date of this letter.” R.R. 634a (emphasis added). EDF further notes that it
    reserved the right to supplement its January 2, 2015 Notice of Land Use Appeal
    because it had not received the ZHB’s findings and conclusions.
    (continued…)
    decisions “shall be filed within 30 days after entry of the decision as provided in 42 Pa.C.S.
    §5572 (relating to time of entry of order). . . .”
    6
    Section 5572 states that the date of service of an order of a government unit, “which
    shall be the date of mailing if service is by mail, shall be deemed to be the date of entry of the
    order for the purposes of this subchapter . . . .” 42 Pa.C.S. §5572.
    12
    Based on the date and language of the ZHB’s decision, we conclude
    that the trial court did not err in denying the motion to quash the appeal as
    premature. While EDF’s second filing is entitled “Supplemental Notice of Land
    Use Appeal,” it was filed after January 5, 2015, and within the 30-day appeal
    period.    Although the ZHB argues that a premature appeal cannot be
    “supplemented,” we conclude that the second notice of appeal cured any
    jurisdictional defect. Snyder.
    Turning to the merits, we note that a special exception in a zoning
    ordinance is not an exception to a zoning restriction, but rather, a use that is
    expressly permitted. Broussard v. Zoning Board of Adjustment of Pittsburgh, 
    831 A.2d 764
    , 769 (Pa. Cmwlth. 2003).
    An ‘exception’ in a zoning ordinance is one allowable
    where facts and conditions detailed in the ordinance, as
    those upon which an exception may be permitted, are
    found to exist. Thus, an exception has its origin in the
    zoning ordinance itself. It relates only to such situations
    as are expressly provided for and enunciated by the terms
    of the ordinance. The rules that determine the grant or
    refusal of the exception are enumerated in the ordinance
    itself. The function of the board when an application for
    an exception is made is to determine that such specific
    facts, circumstances and conditions exist which comply
    with the standards of the ordinance and merit the granting
    of the exception.
    Id. (quotations and citations omitted) (emphasis in original).
    EDF argues that it presented sufficient evidence, in its application and
    through witness testimony, to satisfy all applicable ordinance criteria for the grant
    of a special exception. More specifically, EDF contends that it presented expert
    testimony regarding many details of the proposal, including concerns raised by
    objectors. EDF asserts that its witnesses also addressed the most contentious
    13
    issues, which were the effect of the wind farm on neighboring property values and
    its compatibility with adjoining development and the character of the zoning
    districts. EDF emphasizes that it submitted a 36” x 24” map with its application
    and that the map was used by witnesses to identify specific locations and
    geographical issues.    EDF maintains that its evidence was not rebutted, and,
    therefore, the ZHB abused its discretion in denying the requested special
    exception.
    In response, the ZHB and Township argue that, as the applicant for a
    special exception, EDF had the burden of proving that the proposed use meets the
    objective standards set forth in the zoning ordinance. Bray v. Zoning Board of
    Adjustment, 
    410 A.2d 909
    , 910 (Pa. Cmwlth. 1980). The Township argues that
    EDF did not meet this burden because it did not file a detailed site plan, as required
    by Section 255-52 of the Ordinance, and failed to show that the proposed use is
    similar to and compatible with permitted uses in the district, as required by
    Ordinance Sections 255-36 and 255-142.
    Our review of the record confirms the ZHB’s conclusion that EDF did
    not satisfy the objective requirements of the Ordinance. In particular, EDF’s
    failure to submit a site plan as required by Ordinance Section 255-52(B), (or
    request a waiver of that requirement, or an extension of time to do so), is sufficient
    grounds on its own to deny the special exception application.
    Contrary to EDF’s assertions, the evidence offered at the hearing did
    not provide all of the information required by Section 255-52(B).             Indeed,
    Copeland testified that the number of wind turbines and the precise location of the
    turbines and other details could not be determined until the soil was tested.
    Copeland could not say whether the wind turbines’ connection to the substation
    14
    would be underground or above ground. He stated that EDF would use existing
    roads “to the extent possible.” While EDF referred to a map during the hearing,
    neither the map nor the testimony of EDF’s witnesses satisfies the Ordinance’s
    requirement for a site plan that reflects the location of all structures, existing and
    proposed; all open space areas; means of traffic access and all streets; contours of
    the site for each five feet of change of elevation; and the location of any residential
    structure within 200 feet of any property boundary line of the subject site.
    EDF argues that the zoning officer’s assurance to the ZHB that EDF’s
    application was completed properly, R.R. at 52a, and his submission of the
    application to the ZHB is evidence that the application complied with the
    Ordinance.7 However, EDF does not elaborate or provide any authority for this
    assertion, and a party’s failure to include analysis and relevant authority hampers
    the court’s ability to conduct meaningful appellate review. Korunsky v. Housing
    Code Board of Appeals, 
    660 A.2d 180
    , 183-84 (Pa. Cmwlth. 1995); see also 2 G.
    Ronald Darlington et al., Pennsylvania Appellate Practice, §2119.4 (2015-2016).
    Nevertheless, we observe that the Ordinance confers authority on the ZHB, not the
    zoning officer, to hear and decide requests for special exceptions. See Ordinance
    Section 255-51 (“The authority for approving or denying applications for uses
    permitted by special exception shall be vested in the Zoning Hearing Board”).
    Further, we note that the statement on which EDF relies was made during the
    7
    In relevant part, Section 255-142 A of the Ordinance states that an application for a
    special exception use shall not be submitted to or considered by the Zoning Hearing Board until
    the applicant submits an application for a zoning permit to the zoning officer and a site plan in
    accordance with §255-52 of this chapter. The zoning officer “shall initially review the site plan
    to determine its compliance with §255-52 of this chapter.” R.R. at 581(a).
    15
    hearing, and EDF does not assert that it detrimentally relied on the zoning officer’s
    acceptance of the application.
    Accordingly, we affirm.
    MICHAEL H. WOJCIK, Judge
    16
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    EDF Renewable Energy,                 :
    : No. 2601 C.D. 2015
    Appellant    :
    :
    v.                  :
    :
    Foster Township Zoning                :
    Hearing Board and Foster              :
    Township                              :
    EDF Renewable Energy                  :
    : No. 2645 C.D. 2015
    v.                  :
    :
    Foster Township Zoning                :
    Hearing Board                         :
    :
    v.                  :
    :
    Foster Township                       :
    :
    Appeal of: Foster Township            :
    Zoning Hearing Board                  :
    ORDER
    AND NOW, this 22nd day of November, 2016, the order of the Court
    of Common Pleas of Luzerne County, dated November 18, 2015, is affirmed.
    __________________________________
    MICHAEL H. WOJCIK, Judge
    