Butler Twp. v. G.G. Aubrey & J.M. Aubrey v. R.C. ward ~ Appeal of: G.G. Aubrey & J.M. Aubrey ( 2023 )


Menu:
  •              IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Butler Township                     :
    :
    v.                     :
    :
    George G. Aubrey and John M. Aubrey :
    :
    v.                     :
    :
    Robert C. Ward, Deborah A. Ward,    :
    Jeffrey P. Miller and Megan M. Groh :
    Miller                              :
    :
    Appeal of: George G. Aubrey and     :        No. 405 C.D. 2022
    John M. Aubrey                      :        Submitted: March 3, 2023
    BEFORE:      HONORABLE CHRISTINE FIZZANO CANNON, Judge
    HONORABLE ELLEN CEISLER, Judge
    HONORABLE LORI A. DUMAS, Judge
    OPINION NOT REPORTED
    MEMORANDUM OPINION
    BY JUDGE FIZZANO CANNON                      FILED: June 21, 2023
    George G. Aubrey and John M. Aubrey (Aubreys) appeal from a
    judgment entered in favor of Butler Township (Township) by the Court of Common
    Pleas of Butler County (trial court) for the cost of replacing a storm water pipe and
    the Township’s attorney and engineering fees associated with the litigation. The
    trial court’s verdict also dismissed the additional defendants, Robert C. Ward and
    Deborah A. Ward (Wards) and Jeffrey P. Miller and Megan M. Groh Miller (Millers)
    from the action. Upon review, we affirm in part, reverse in part, and vacate and
    remand in part.
    I. Background
    In 1988 and 1989, the Aubreys were in the process of planning a
    residential development surrounding a golf course in the Township.                          The
    development plan contemplated the placement and maintenance of a storm water
    management system that included a retention pond and associated pipes and culverts
    on neighboring property owned by the Wards. During the development planning
    and approval process, several written agreements were drafted that are pertinent to
    the dispute in this case.
    On February 24, 1988, the Aubreys and the Wards signed a Contract of
    Agreement and Related Covenants concerning road construction and the retention
    pond (First Aubrey-Ward Agreement). Reproduced Record (RR) at 41a-47a. In
    relevant part,1 the First Aubrey-Ward Agreement required the Wards to “retain and
    maintain a ‘water retention pond’ as constructed by [the] Aubrey[s] on [the]
    Ward[s’] property pursuant to Butler Township specifications.” Id. at 43a.
    On April 1, 1988, the Aubreys and the Wards signed a second and
    supplemental Contract of Agreement (Second Aubrey-Ward Agreement). RR at
    21a-22a. The Second Aubrey-Ward Agreement referred to the First Aubrey-Ward
    Agreement and added a provision in which the Aubreys “agree[d] to repair any and
    all ‘pipes,’ except those damaged by [the] Ward[s] for[] a period of thirty (30) years . .
    . .” Id. at 21a.
    1
    In addition, the Wards agreed to dedicate a strip of land at the northern edge of their
    property for part of a planned road. RR at 41a-42a. The Wards, who were considering developing
    their own property, also agreed to pay the Aubreys $6,000 for frontage and for engineering and
    legal fees and to pay the Aubreys $38,000 toward the road construction costs in the event Wards
    developed their own property in the future. Id. at 43a.
    2
    On May 5, 1988, the Wards signed a proposed Agreement with the
    Township, which the Township never executed (Unexecuted Ward-Township
    Agreement). RR at 38a-39a. Under the Unexecuted Ward-Township Agreement,
    the Wards would have been “perpetually liable for the maintenance and upkeep of
    the storm water retention pond including any culvert, swales, drainage pipes,
    spillways, discharge channels, and/or other parts of the storm water retention pond.”
    Id. at 38a. The Unexecuted Ward-Township Agreement would also have required
    the Wards to note their perpetual maintenance obligation on the development plan
    and record the agreement at their own expense. Id. at 38a-39a. However, the
    Township and the Wards maintain that the Township never accepted the Unexecuted
    Ward-Township Agreement. Id. at 62a & 186a. That agreement was never recorded.
    Id. at 63a & 187a. The Aubreys, who were not parties to the Unexecuted Ward-
    Township Agreement, are the only parties who assert that it was ever finalized.
    On May 15, 1988, the Aubreys and the Township signed an
    Indemnification Agreement. RR at 9a-10a. In the Indemnification Agreement, the
    Aubreys, as the Developer, agreed to indemnify the Township and hold it harmless
    “against all liability, claims, judgments, actions, causes of actions, suits or demands
    for damages attributable to or arising in whole or part, from the . . . water retention
    devices . . . .” Id. at 10a.
    Finally, on April 27, 1989, the Aubreys and the Township signed an
    Agreement relating to the development plan’s storm water management system
    (Storm Water Management Agreement). RR at 12a-15a. In the Storm Water
    Management Agreement, the Aubreys, again as the Developer, agreed to be
    “perpetually responsible for the maintenance of the storm water control devices in
    accordance with the approval plan and township ordinances [and] for the
    3
    maintenance and upkeep of the storm water management plan including any
    retention devices, culverts, swales, drainage pipes, spillways, discharge channels,
    and/or other parts of the plan . . . .” Id. at 15a.
    In 2012, the Wards sold their property to the Millers. RR at 52a-55a.
    The deed recited that the conveyance was subject to the First and Second Aubrey-
    Ward Agreements. RR at 53a.
    In August 2017, within the 30-year period covered by the Second
    Aubrey-Ward Agreement, the Township obtained a written opinion from an
    engineer stating that the pipe emptying into the retention pond had deteriorated and
    needed repair. RR at 18a. The letter noted that the Storm Water Management
    Agreement made the Aubreys responsible for the repairs. Id. Later that month, the
    Township sent the Aubreys a certified letter enclosing the engineer’s written opinion
    and demanding that the Aubreys repair or replace the pipe. Id. at 17a; see also RR
    at 595a.
    The Aubreys denied responsibility for repair or replacement. They
    blamed the Township and the Wards for the pipe’s deterioration, asserting that the
    Township’s alleged dumping of “excessive chlorides/salt [(on the roads, evidently
    referring to winter road treatment)] played a major role for damage to the storm
    water management system along with the construction by Ward/Miller that exposed
    a section of pipe to air and sun.” RR at 629a. The Aubreys theorized that “[t]he
    excessive salt applied by [the Township] for decades and the exposure of the pipe to
    sun and air aged the pipe prematurely through oxidation. However, the integrity of
    the sides and top of the pipe are sound.” Id.
    Following the Aubreys’ continued refusal to repair or replace the pipe,
    the Township filed a civil complaint, including a claim seeking declaratory relief
    4
    (Count I) and a breach of contract claim to enforce the Storm Water Management
    Agreement (Count II). RR at 2a-7a. During the pendency of the action, the
    Township obtained an updated engineering opinion based on a re-examination of the
    pipe using a closed-circuit television camera (CCTV). In a March 2021 letter to the
    Township, the engineer opined:
    A review of the CCTV revealed that the pipe invert
    (bottom of pipe) has deteriorated. The invert has rusted
    away along large sections of the pipe which has in turn
    caused the pipe bedding (stone) to be washed away. This
    deterioration has reduced the structural strength of the
    pipe, which has led to the development of a sink hole on
    the property, and will likely lead to additional sink holes
    and a total collapse of the pipe.
    RR at 966a.
    The Aubreys joined the Wards and the Millers as additional defendants.
    Following discovery, the trial court issued an order granting summary judgment in
    favor of the Township except as to Count II of the complaint, the breach of contract
    claim against the Aubreys based on the Storm Water Management Agreement. See
    RR at 944a-46a. The trial court’s order also granted summary judgment in favor of
    the Wards and the Millers. Id. The Aubreys filed an improper interlocutory appeal
    from the trial court’s order but later withdrew the appeal, stipulating that the order
    was not appealable.2 See id. at 973a, 977a & 979a-81a.
    The remainder of the case proceeded to a non-jury trial in November
    2021. The trial court’s subsequent verdict provided, in pertinent part:
    2
    The Superior Court also issued an order dismissing the appeal because the Aubreys failed
    to file a brief. RR at 955a.
    5
    AND NOW, this 15th day of December, 2021, after trial
    without a jury on [Nov]ember 29th, 2021, the trial judge
    finds as follows.
    1. Verdict is for the Plaintiff BUTLER TOWNSHIP and
    against the Defendants GEORGE G. AUBREY and JOHN
    M. AUBREY in the sum of $64,350.00.
    2. Additional Defendants ROBERT C. WARD and
    DEBORAH A. WARD did not cause or in any way
    contribute to the deterioration of the Pipe, and are
    dismissed from the case.
    3. Additional Defendants JEFFREY P. MILLER, and
    MEGAN M. GROH MILLER did not cause or in any way
    contribute to the deterioration of the Pipe, and are
    dismissed from the case.
    RR at 1098a-99a. On December 20, 2021, the trial court issued findings and
    conclusions in support of its verdict. Id. at 1093a-97a. The trial court determined
    that the Township satisfied its burden of proof, that the pipe required replacement,
    and that the Township was entitled to recover the replacement cost of $64,350.00
    from the Aubreys. Id. at 1097a. The trial court also reiterated that neither the Wards
    nor the Millers “caused or in any way contributed to the deterioration of the Pipe.”
    Id.
    In addition, the trial court accepted post-trial briefs from the Township
    and the Aubreys regarding the Township’s request for an award of attorney fees.
    See RR at 1075a-91a. In a separate memorandum opinion, the trial court ordered
    the Aubreys to pay attorney fees of $31,492.50 to the Township. RR at 1102a-
    1112a. The trial court held that the Storm Water Management Agreement required
    the Aubreys to pay the Township’s attorney and engineering fees. Id. at 1102a. In
    the trial court’s opinion, “the contractual obligation was clear as it relates to the
    Aubreys and Butler Township, and litigation was only made necessary by the
    6
    Aubreys refusal to perform under that obligation.” Id. at 1109a. The trial court also
    found the fee amount was “fair and reasonable.” Id. at 1102a & 1109a.
    However, the trial court did not base its fee award solely on its finding
    of a contractual obligation. The trial court also concluded that “the conduct of the
    Aubreys has been exceedingly dilatory, obdurate, and vexatious.” RR at 1111a. In
    a detailed analysis, the trial court explained that
    the Aubreys could have prevented many of these fees by
    not filing numerous motions, which in[] turn required
    preparation by opposing counsel, only to later withdraw
    them shortly before trial, or if they were not withdrawn,
    many allegation[s] within were entirely devoid of factual
    support at the hearing. First, while acting pro[] se, the
    Aubreys filed a Motion to Dismiss for Spoliation of
    Evidence without any factual support, then withdrew the
    Motion at the time scheduled for argument on the Motion.
    Next, the Aubreys filed an Appeal only to later stipulate
    that it was improperly filed and withdr[a]w it, which
    delayed the case seven (7) months. Finally, the Aubreys
    filed a Motion to Vacate Summary Judgment, in which
    they allege[d] fraud, then withdrew the allegation a week
    before the hearing. In the same Motion, the Aubreys
    alleged that [the Wards’] actions damaged the Pipe[;]
    however, they failed to provide a quantum of support at
    trial for this allegation. In fact, experts for both [the
    Township] and [the Aubreys] testified that [the Wards] did
    not cause or in any way contribute to the deterioration of
    the Pipe. Therefore, the Court finds the full [attorney fee]
    amount requested by the [Township] fair and reasonable.
    Id. at 1109a-10a. The trial court found further that the Aubreys’ “repeated pattern
    of filing motions in which they allege arguments, only to later withdraw or have no
    factual support for them, was intended to frustrate the legal process and intended to
    annoy the Township.” Id. at 1111a.
    Thus, the trial court based its decision to award attorney fees on both
    the Aubreys’ contractual obligation and their dilatory, obdurate, and vexatious
    7
    conduct during the litigation. However, because the trial court concluded the
    Aubreys were contractually obligated to pay the Township’s attorney fees in any
    event, it posited that it did not need to determine specifically what portion of those
    attorney fees were attributable to the Aubreys’ dilatory, obdurate, and vexatious
    conduct. RR at 1111a.
    Finally, regarding the Township’s engineering fees, the trial court
    observed that the Storm Water Management Agreement obligated the Aubreys to
    “pay all costs reasonably incurred by [the T]ownship for engineering and legal fees
    for the review of the plan, inspection of the plan, approval of the plan and
    improvements . . . .” RR at 15a. The trial court concluded that this provision
    required the Aubreys to pay the Township’s engineering fees of $4,500.00 relating
    to the engineer’s investigation and opinion concerning the deterioration of the pipe
    more than two decades after the development plan’s approval. Id. at 1110a.
    The Aubreys filed a motion for post-trial relief, which the trial court
    denied in a memorandum opinion and order dated March 24, 2022. RR at 1117a-
    98a. This appeal by the Aubreys followed.3
    3
    Our review of a trial court’s order granting summary judgment is de novo, and our scope
    of review is plenary; this Court applies the same standard for summary judgment as the trial court.
    Lancaster Cnty. Agric. Pres. Bd. v. Fryberger, 
    257 A.3d 192
    , 199 n.13 (Pa. Cmwlth. 2021).
    Summary judgment is appropriate only where there are no genuine issues of material fact and the
    moving party is entitled to judgment as a matter of law. 
    Id.
    Our review of a non-jury trial verdict is limited to determining whether the findings of the
    trial court are supported by substantial evidence and whether the trial court committed an error in
    applying the law. Pottstown Sch. Dist. v. Montgomery Cnty. Bd., 
    289 A.3d 1142
    , 1145 n.3 (Pa.
    Cmwlth. 2023). The trial judge’s findings of fact have the same weight and effect on appeal as
    the verdict of a jury: we consider the evidence in the light most favorable to the verdict winner
    and reverse the trial court only if its findings of fact are not supported by substantial evidence in
    the record or are premised on an error of law. 
    Id.
     Thus, our scope of review of a question of law
    is plenary. 
    Id.
    8
    II. Issues on Appeal
    The Aubreys raise a number of issues on appeal, which we combine
    and reorder for convenience and clarity as follows.4
    First, the Aubreys assert various errors in the trial court’s decision to
    grant partial summary judgment against them.                  They insist the Storm Water
    Management Agreement was actually entered in April 1988, not April 1989, and that
    the date on the agreement was improperly changed later. According to the Aubreys,
    this perceived date discrepancy is significant because it means that the Unexecuted
    Ward-Township Agreement was entered later and, therefore, supplanted their repair
    obligations under the Storm Water Maintenance Agreement. Thus, the Aubreys
    maintain that the trial court erred by concluding that their pipe repair obligations
    under the Storm Water Management Agreement were not abrogated by the Second
    Aubrey-Ward Agreement or the Unexecuted Ward-Township Agreement. In a
    related argument, the Aubreys claim that the trial court erred in determining that the
    First and Second Aubrey-Ward Agreements limited the Wards’ maintenance and
    repair obligations to the retention pond and did not include the pipe at issue. The
    Aubreys also insist that the trial court erred in determining that the Unexecuted
    Ward-Township Agreement was unenforceable.                        The Aubreys assert that
    contemporaneous Township meeting minutes from May 1988 establish the
    Township’s acceptance of the agreement even though it was never signed or
    recorded. Finally, regarding the cause of the pipe’s deterioration, the Aubreys
    contend the trial court should not have determined in its summary judgment decision
    4
    We note that our reorganization of the issues was necessitated in part by the fact that the
    Aubreys’ arguments are not organized in correlation with the statement of questions presented.
    See Pa.R.A.P. 2119(a) (directing that “[t]he argument shall be divided into as many parts as there
    are questions to be argued . . .”).
    9
    that the Wards could not have damaged the pipe and that expert testimony was
    required to prove any such alleged damage by them. Similarly, the Aubreys posit
    that the trial court erred again after the trial, when it found as a fact that neither the
    Wards nor the Millers caused or contributed to the deterioration of the pipe.
    The Aubreys also argue that they did not have prior notice that the trial
    would encompass the question of causation of the pipe’s deterioration. They
    likewise contend they had no advance notice that the trial evidence would encompass
    the cost of replacing the pipe. In a related argument, they assert that the trial court
    erred by allowing the Township’s expert witness to testify about replacement cost.
    Finally, the Aubreys allege error in the trial court’s award of
    engineering and attorney fees against them. The Aubreys maintain that the Storm
    Water Management Plan, on which the trial court relied, does not authorize the
    imposition of such fees. Further, the Aubreys assert that the trial court did not have
    sufficient evidence before it to support its finding that the fees were reasonable.
    III. Discussion
    A. Summary Judgment
    The Aubreys’ primary argument is that the trial court should not have
    entered summary judgment for various reasons. We address each in turn.
    1. The Date of the Storm Water Management Agreement
    The Aubreys allege that the Storm Water Management Agreement was
    entered on April 27, 1988, not April 27, 1989. They point out that the “9” in “1989”
    in the first paragraph of the agreement is in different type from the rest of the date,
    and they suggest it was fraudulently altered. In a motion to vacate the trial court’s
    10
    summary judgment order, the Aubreys conceded that they did not timely or properly
    assert fraud as an affirmative defense in their pleadings, but they blamed their failure
    to plead the defense on their attorney’s health issues. RR at 974a. However, they
    later withdrew that motion. Accordingly, the assertion of fraud was waived.
    Moreover, review of the Storm Water Management Agreement shows
    that it was a form agreement with blanks for the day and month, and with the year
    stated as “198 ” leaving the specific year blank. See RR at 12a. All of the parts of
    the date – the day, the month, and the final digit of the year – were added in italic
    type slightly smaller than the type font of the form, as were the Aubreys’ names as
    “Developers.” 
    Id.
     There is nothing in that fact which suggests the year was altered.
    In addition, the notarization at the end of the agreement also bore the date of April
    27, 1989 as the date of the Aubreys’ signatures, again with their names and the date
    typed in slightly smaller italic font on a preprinted form. 
    Id.
     at 16a. Thus, the
    Aubreys adduced no evidence whatsoever of any alteration of the date on the
    agreement. Their bare averment was insufficient to raise a genuine issue of material
    fact.
    The Aubreys contend that the date of the Storm Water Management
    Agreement is “critical to the determination of liability for the maintenance of the
    pipe,” because if the Unexecuted Ward-Township Agreement was executed later, it
    would have “superseded, or at a minimum, modified” the Aubreys’ obligations
    under the Storm Water Management Agreement. Aubreys’ Br. at 15. We disagree
    and conclude that the date of the Storm Water Management Agreement is ultimately
    unimportant for two reasons. First, as discussed further below, the Unexecuted
    Ward-Township Agreement was never finalized. Second, the enforceability of the
    Storm Water Management Agreement does not depend on the date on which it was
    11
    executed. We agree with the trial court that the existence or nonexistence of an
    enforceable agreement between the Township and the Wards has no bearing on the
    Aubreys’ obligations under the Storm Water Management Agreement. There was
    nothing in the terms of the Unexecuted Ward-Township Agreement that stated any
    intent to abrogate the Aubreys’ responsibilities as Developer under the Storm Water
    Management Agreement. Thus, the trial court correctly concluded that the Aubreys’
    obligations to the Township under the Storm Water Management Agreement were
    not affected by any alleged separate agreement between the Wards and the Township
    to which the Aubreys were not parties. Therefore, whether the date of the Storm
    Water Management Agreement was 1988 or 1989 was immaterial.
    For these reasons, we reject the Aubreys’ challenge to the date of the
    Storm Water Management Agreement.
    2. Enforceability of the Unexecuted Ward-Township Agreement
    The Aubreys claim there was evidence of the Township’s acceptance
    of the Unexecuted Ward-Township Agreement in contemporary meeting minutes.
    However, our review of the record indicates that such acceptance by the Township
    is not a fair or reasonable inference from the cited minutes.
    The Township Planning Commission’s meeting minutes of March 1,
    1988 indicated that an unspecified Ward dedication document was reviewed. RR at
    813a. The minutes did not make clear what document was referenced. More
    importantly, there was no indication in the minutes that the Township was agreeing
    to the document; to the contrary, the minutes stated that the Township’s solicitor
    needed to check some of the document’s language. 
    Id.
    12
    The Planning Commission’s meeting minutes of April 5, 1988 stated,
    in pertinent part: “Require copy of standard Improvements-Maintenance-Amenities
    Agreement to Wards for signature. They will be bound by that agreement to
    maintain the pond.” RR at 820a. It was not clear from the minutes whether the
    referenced agreement was to be between the Wards and the Township or between
    the Wards and the Aubreys. However, the minutes stated that the Aubreys, as
    Developer, were also required to sign the agreement. Notably, there was no
    signature space for the Aubreys on the Unexecuted Ward-Township Agreement,
    which indicated it was not the anticipated agreement mentioned in the meeting
    minutes. See 
    id.
     at 809a.
    The Township Commissioners’ meeting minutes of May 16, 1988
    contained a notation that “[a] major detention pond is to be located on the Ward
    property. Easements, rights-of-way and agreements with [the] Ward[s] have been
    executed.” RR at 816a. Again, nothing in the minutes indicated that any of the
    described agreements were between the Township and the Wards. In fact, the
    minutes did not even suggest that the unspecified “agreements” related to
    maintenance or repairs of any pipes leading to the retention pond.
    Moreover, the Township, which was the party that would have
    benefitted from the Unexecuted Ward-Township Agreement, specifically averred
    that it had never entered into that agreement. RR at 62a-63a. The Wards concurred.
    
    Id.
     at 186a. As both parties named in the purported contract agreed it was never
    finalized, and in light of the vague nature of the meeting minutes produced as the
    Aubreys’ only evidence of the Township’s supposed acceptance of the agreement,
    we cannot say that the trial court erred in determining that the Aubreys failed to
    13
    adduce sufficient evidence to raise a genuine issue of material fact concerning the
    enforceability of the Unexecuted Ward-Township Agreement.
    In any event, as discussed in subsection 1 above, we agree with the trial
    court that the existence or nonexistence of an enforceable agreement between the
    Township and the Wards has no bearing on the Aubreys’ obligations under the Storm
    Water Management Agreement. For all of these reasons, the trial court did not err
    in determining that the Unexecuted Ward-Township Agreement did not affect the
    Aubreys’ liability under the Storm Water Management Agreement.
    3. Cause of the Pipe’s Deterioration
    a. The Summary Judgment Ruling
    The Aubreys contend that the trial court improperly entered summary
    judgment on the issue of causation, finding that there was no evidence that the Wards
    or the Millers contributed to the pipe’s deterioration. We disagree.
    The argument section of the Aubreys’ brief includes a single paragraph
    on this issue. That paragraph consists of a bare averment that the Wards caused
    damage to the pipe and a bare averment that the trial court erred by granting
    summary judgment on that issue. See Aubreys’ Br. at 27. This is insufficient to
    allow this Court to conduct a meaningful review of the issue on appeal. See
    Pa.R.A.P. 2119(a) (requiring that the argument on each issue include “such
    discussion and citation of authorities as are deemed pertinent”); Pa.R.A.P. 2119(d)
    (requiring that “[w]hen the finding of, or the refusal to find, a fact is argued, the
    argument must contain a synopsis of all the evidence on the point, with a reference
    to the place in the record where the evidence may be found”). Accordingly, the
    argument is waived. See Commonwealth v. Bishop, 
    217 A.3d 833
    , 841 (Pa. 2019)
    14
    (quoting Wirth v. Commonwealth, 
    95 A.3d 822
    , 837 (Pa. 2014) (holding that “where
    an appellate brief fails to provide any discussion of a claim with citation to relevant
    authority or fails to develop the issue in any other meaningful fashion capable of
    review, that claim is waived”) (additional citation omitted)).
    Even had the Aubreys not waived the argument, we would discern no
    error in the trial court’s entry of summary judgment in favor of the Wards and the
    Millers. In opposing a summary judgment motion, the nonmoving party may not
    rest solely on the pleadings, but rather, must identify “one or more issues of fact
    arising from evidence in the record controverting the evidence cited in support of
    the motion or from a challenge to the credibility of one or more witnesses testifying
    in support of the motion . . . .” Pa.R.Civ.P. 1035.3(a)(1). Here, the trial court
    explained its reasoning in granting summary judgment as follows:
    George Aubrey testified [in his deposition] that the re-
    excavation occurred only at the retention pond and not
    near the roadway. [RR at 844a]. Based on the evidence
    of record, the [trial c]ourt concluded it was not possible for
    the damage to have been caused by [the] Ward[s’] heavy
    equipment because the pipe at issue was not in the area
    where the excavation was performed. See [RR at 680a
    (site plan drawing of development and retention pond)].
    Further, the Aubrey[s’] allegation that the Ward[s’]
    excavation work could have affected pipe in another area
    is unsupported. There was no evidence or expert
    testimony produced to indicate that the culvert pipe’s
    deterioration is related in any manner to the re-excavation
    work of the storm water pond. For these reasons, the Court
    determined there was no genuine issue of fact in regard to
    this issue.
    RR at 945a-46a. Our review of the record reveals no error in the trial court’s
    reasoning.
    15
    As between the Township and the Aubreys, the Storm Water
    Management Agreement clearly imposed responsibility on the Aubreys to maintain
    the pipe. As between the Aubreys and the Wards and Millers, the Second Aubrey-
    Ward Agreement provided that the Aubreys must maintain the pipes, except for
    damage caused by the Wards or their successors in title, for a period of 30 years from
    April 1, 1988. The Township notified the Aubreys of the pipe’s deterioration and
    demanded repair or replacement in August 2017, within the 30-year period covered
    by the Second Aubrey-Ward Agreement. RR at 17a-18a; see also 
    id.
     at 595a. As
    there was no genuine issue of material fact concerning the lack of fault on the parts
    of the Wards and the Millers regarding the deterioration of the pipe or the date the
    Aubreys were notified of the pipe’s deterioration, it necessarily follows that the
    Aubreys are liable for the cost of replacing the pipe.
    b. Post-Trial Finding of Fact
    The Aubreys further assert that the trial court erred by ruling on the
    causation issue after trial because it had already decided that issue in granting
    summary judgment. This issue likewise is not supported by sufficient analysis to
    allow meaningful review on appeal, and it is therefore waived. See Bishop, 217 A.3d
    at 841 (quoting Wirth, 95 A.3d at 837). Moreover, because we have already
    determined that the trial court did not err by granting summary judgment on this
    issue, any alleged error by the trial court in allowing the issue to be addressed again
    at trial was harmless.
    16
    B. Notice of Replacement Cost as a Trial Issue
    The Aubreys assert that the trial court erred by allowing the Township’s
    expert witness to testify concerning the cost of replacing the pipe. The Aubreys
    insist they had no notice that replacement cost would be an issue at trial because the
    trial court’s scheduling order stated only that a non-jury trial would “determine
    whether the condition of the pipe at issue necessitates repair or replacement.” RR at
    956a. This argument lacks merit.
    The trial court explained in its post-trial findings that it added that
    language to its scheduling order in response to an objection by the Aubreys that the
    trial should not be limited solely to the amount of damages, but should also include
    the question of whether the Wards or the Millers had damaged the pipe. RR at
    1093a. The clear implication of the trial court’s observation is that the Aubreys must
    therefore have known that damages would be an issue at trial.
    Moreover, in its opinion denying the Aubreys’ post-trial motion, the
    trial court explained that the Township’s damage demand related to its breach of
    contract claim, the only claim remaining for trial after the trial court granted partial
    summary judgment. RR at 1185a. “Additionally, the price quotes for replacing the
    pipe were included in the expert reports accompanying the Pre-Trial Statements, and
    [the Aubreys] failed to file a motion in limine challenging the price quotes prior to
    trial.” Id. (italics added). Further, the trial court observed that it had denied the
    Township’s motion in limine to preclude the testimony of the Aubreys’ expert
    witness, whose identity and proposed testimony they disclosed “only days before
    trial[,5 such that the Aubreys] had the opportunity to question the [Township’s]
    5
    In its motion in limine, the Township averred that, although discovery had been closed
    for more than a year, the Aubreys did not provide notice of their intent to call an expert witness
    17
    expert and their own regarding the price quotes for the replacement of the pipe.” Id.
    (emphasis added).
    Accordingly, we conclude that the trial court did not err by allowing
    evidence of damages at trial.
    C. The Awards of Attorney and Engineering Fees
    As explained above, the Storm Water Management Agreement required
    the Aubreys to “pay all costs reasonably incurred by [the T]ownship for engineering
    and legal fees for the review of the plan, inspection of the plan, approval of the plan
    and improvements . . . .” RR at 15a & 1110a. The trial court relied solely on this
    provision in awarding engineering fees and relied on it in part in awarding attorney
    fees.
    The Aubreys contend that this provision does not apply to the
    Township’s attorney fee claim. We agree. The plain language of the Storm Water
    Management Agreement made its reimbursement requirement applicable to legal
    and engineering expenses only insofar as the Township incurred those expenses
    regarding the plan approval process.6 That process ended more than 30 years ago.
    Therefore, we conclude that the trial court erred by awarding engineering fees, and
    we reverse the trial court’s award of engineering fees to the Township.
    until just before the close of business on the Wednesday before Thanksgiving, with the trial due to
    start the following Monday. RR at 1066a-67a.
    6
    We note that the Indemnification Agreement separately requires the Aubreys to “save,
    indemnify, defend and hold harmless the Township against all liability, claims, judgments, actions,
    causes of actions, suits or demands for damages attributable to or arising in whole or part” from
    the storm water management system’s water retention devices. RR at 10a. Neither the Township
    nor the trial court addressed the attorney and engineering fee claims in relation to this provision,
    and we do not consider it here.
    18
    The trial court similarly erred to the extent that it based its award of
    attorney fees on obligations arising from the Storm Water Management Agreement.
    However, that conclusion does not end our analysis regarding the trial court’s award
    of attorney fees. The trial court also found that the Aubreys’ conduct throughout the
    litigation process was “exceedingly dilatory, obdurate, and vexatious” based on their
    “repeated pattern of filing motions in which they allege[d] arguments, only to later
    withdraw or have no factual support for them, [which] was intended to frustrate the
    legal process and intended to annoy the Township.” RR at 1111a.
    Section 2503(7) of the Judicial Code7 provides that “[t]he following
    participants shall be entitled to a reasonable counsel fee as part of the taxable costs
    of the matter: . . . [a]ny participant who is awarded counsel fees as a sanction against
    another participant for dilatory, obdurate or vexatious conduct during the pendency
    of a matter.” 42 Pa.C.S. § 2503 (7). In addition, Rule 2744 of the Rules of Appellate
    Procedure provides, in relevant part:
    In addition to other costs allowable by general rule or Act
    of Assembly, an appellate court may award as further costs
    damages as may be just, including [] a reasonable counsel
    fee . . . if it determines that an appeal is frivolous or taken
    solely for delay or that the conduct of the participant
    against whom costs are to be imposed is dilatory, obdurate,
    or vexatious.
    Pa.R.A.P. 2744; see also Pa. Tpk. Comm’n v. Elec. Transaction Consultants Corp.,
    
    230 A.3d 548
    , 562 (Pa. Cmwlth. 2020) (quoting Pa.R.A.P. 2744). Conduct is
    “dilatory” if it is “[d]esigned or tending to cause delay.” Dilatory, Black’s Law
    Dictionary (11th ed. 2019). Conduct is “obdurate” if it is “stubbornly resistant in
    wrongdoing.” Obdurate, Webster’s Third New Int’l Dictionary 1555 (Gove, ed.
    7
    42 Pa.C.S. §§ 101-9913.
    19
    1986). Conduct is “vexatious” if it is “without reasonable or probable cause or
    excuse[,] harassing[, or] annoying.” Vexatious, Black’s Law Dictionary (11th ed.
    2019). See Transaction Consultants, 230 A.3d at 562 nn.11-13 (quoting dictionary
    definitions of “dilatory,” “obdurate,” and “vexatious”).
    An award of attorney fees will not be disturbed on appeal unless the
    trial court “palpably abused its discretion” by awarding fees. Thurnberg v. Strause,
    
    682 A.2d 295
    , 299 (Pa. 1996). Here, the trial court specifically found that the
    Aubreys’ conduct was intended “to frustrate the legal process and . . . annoy the
    Township.” RR at 1111a. Moreover, we conclude that the Aubreys’ pattern of filing
    and then withdrawing meritless motions, along with the lack of any factual or legal
    support for several other positions they asserted, further supported the trial court’s
    decision to award attorney fees to the Township. Thus, we cannot say that the trial
    court palpably abused its discretion in concluding that the Aubreys’ conduct justified
    an award of attorney fees against them.
    Nonetheless, the trial court erred in its determination of the amount of
    its attorney fee award. Because it based the amount of its attorney fee award on the
    terms of the Storm Water Management Agreement, the trial court did not reach the
    question of how much the Township’s attorney fees were increased as a result of the
    Aubreys’ dilatory, obdurate, and vexatious conduct in the course of the litigation.
    Because that conduct, not a contractual obligation, provided the only support for an
    attorney fee award, the trial court erred by failing to calculate the fee award on that
    basis. Accordingly, we will vacate the trial court’s attorney fee award and remand
    this matter to the trial court for a new determination of the amount of that award in
    accordance with this opinion.
    20
    IV. Conclusion
    For the foregoing reasons, we conclude that the trial court did not err in
    its grant of partial summary judgment, its subsequent verdict in favor of the
    Township and against the Aubreys regarding their responsibility to replace the pipe
    at issue, its dismissal of the Wards and the Millers from the action, or its finding that
    the Aubreys’ conduct during the litigation was dilatory, obdurate, and vexatious.
    However, we conclude that the trial court erred as a matter of law in awarding
    engineering fees to the Township, as well as in awarding the attorney fee amount
    requested by the Township without determining what portion of the requested fee
    was attributable to the Aubreys’ dilatory, obdurate, and vexatious conduct and
    whether that fee amount was reasonable. Accordingly, we reverse the trial court’s
    award of engineering fees. We vacate the attorney fee award and remand to the trial
    court for a new determination of the appropriate fee amount. We affirm the trial
    court’s orders in all other respects.
    __________________________________
    CHRISTINE FIZZANO CANNON, Judge
    21
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Butler Township                     :
    :
    v.                     :
    :
    George G. Aubrey and John M. Aubrey :
    :
    v.                     :
    :
    Robert C. Ward, Deborah A. Ward,    :
    Jeffrey P. Miller and Megan M. Groh :
    Miller                              :
    :
    Appeal of: George G. Aubrey and     :         No. 405 C.D. 2022
    John M. Aubrey                      :
    ORDER
    AND NOW, this 21st day of June, 2023, the judgment of the Court of
    Common Pleas of Butler County (trial court) is REVERSED as to the award of
    engineering fees of $4,500.00 to Butler Township (Township). The trial court’s
    judgment is VACATED as to the award of attorney fees of $31,492.50 to Butler
    Township, and this matter is REMANDED to the trial court for a determination of
    the attorney fee award amount that is fair and reasonable to compensate the
    Township for its attorney fees arising from delays and unnecessary legal work
    caused by the conduct of George G. Aubrey and John M. Aubrey that the trial court
    found was dilatory, obdurate, and vexatious.       The trial court’s judgment is
    AFFIRMED in all other respects.
    Jurisdiction relinquished.
    __________________________________
    CHRISTINE FIZZANO CANNON, Judge
    

Document Info

Docket Number: 405 C.D. 2022

Judges: Fizzano Cannon, J.

Filed Date: 6/21/2023

Precedential Status: Precedential

Modified Date: 6/21/2023