KBAJ Enterprises, LLC t/b/d/a Home Again ( 2016 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                       )
    )
    KBAJ Enterprises, LLC t/b/d/a Home Again           )    
    ASBCA No. 60222
    )
    Under Contract No. SPE5E8-14-M-4256                )
    APPEARANCE FOR THE APPELLANT:                           Mr. Joseph Dente
    General Manager, Member and
    Corporate Officer
    APPEARANCES FOR THE GOVERNMENT:                         Daniel K. Poling, Esq.
    DLA Chief Trial Attorney
    John F. Basiak, Jr., Esq.
    Steven C. Herrera, Esq.
    J. Maxwell Carrion, Esq.
    Trial Attorneys
    DLA Troop Support
    Philadelphia, PA
    OPINION BY ADMINISTRATIVE JUDGE MELNICK ON THE GOVERNMENT'S
    MOTION TO DISMISS OR TO STRIKE
    This appeal arises from the alleged deemed denial by the contracting officer
    (CO) of a claim seeking payment under a purchase order (PO). The government
    moves to dismiss the appeal for lack of jurisdiction and other grounds, or alternatively,
    to strike portions of the complaint. Since the Board determines that appellant failed to
    submit a claim to a CO, the government's motion is granted.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. On 12 September 2014, the Defense Logistics Agency Troop Support,
    Hardware (DLA or government), issued PO No. SPE5E8-14-M-4256 (PO 4256) to
    KBAJ Enterprises, LLC t/d/b/a Home Again 1 for the delivery of 5,000 hexagon nut
    1
    PO 4256 was issued to "KBAJ ENTERPRISES DBA." In related appeals pending
    before the Board in which POs were issued in the same name, the parties
    clarified that the proper name of appellant in those appeals is "KBAJ
    Enterprises, LLC t/d/b/a Home Again." See KBAJ Enterprises, LLC t/d/b/a
    Home Again, 
    ASBCA No. 59932
     et al., 16-1 BCA i! 36,493 at 177 ,835. We
    conclude that the proper name in this appeal is "KBAJ Enterprises, LLC t/d/b/a
    Home Again" and the appeal caption is modified accordingly.
    packs at a total price of $19, 750 (R4, tab 3 at 8, 11 2 ; compl. ~ 4; gov't mot. at 2, ~ I).
    Under block 6 of the PO, Ms. Sharon Sax is identified as the "Local Admin" (R4, tab 3
    at 8). Ms. Sax is not the CO who issued the PO.
    2. On or about 3 November 2014, DLA received shipment of the items
    pursuant to PO 4256 from KBAJ (compl. ~ 22; gov't mot. at 4, ~ 15). KBAJ
    subsequently received a partial payment of $5,300 from DLA, corresponding to 1,400
    out of 5,000 packs (comp I.~ 23; gov't mot. at 4, ~ 16).
    3. In an email dated 19 February 2015, CO Matheu C. Wilson (CO Wilson)
    directed KBAJ to submit traceability documentation that proved that the furnished
    items complied with PO 4256's terms (R4, tab 4 at 13-14). CO Jayne Manco
    (CO Manco) was copied on the email (id. at 13).
    4. In a letter dated 26 February 2015, sent via email on the same date to
    CO Wilson and copied to Ms. Sax and CO Manco, KBAJ responded to CO Wilson's
    19 February email (R4, tab 4 at 13 ). KBAJ, among other things, communicated that it
    would not provide any information or documentation to DLA until payment was
    issued (R4, tab 5 at 17). KBAJ concluded the letter by requesting a response from
    DLA on its payment request (id.).
    5. In a 10 March 2015 letter addressed to an individual identified by KBAJ as a
    Procurement Analyst sent via email on the same date, KBAJ sought assistance in
    obtaining acceptance and receiving payment on various items shipped under PO 4256
    and other alleged contracts between the parties (R4, tabs 6-7, 9). Concerning
    PO 4256, KBAJ stated in part:
    As you know I have copied you on other emails
    relative to this award. Therefore, you know we are owed
    $14,220.00 but have agreed to a re-labeling offset of
    $1,212.00, thereby leaving a balance due and owing our
    company in the amount of $13,008.00. This product is
    currently in possession of the Depot at Tracy, Ca. Finally,
    as you know from my prior emails the Depot did make a
    partial acceptance and we received a partial payment of
    $5,530[ 31. Be that as it may this matter has been
    2
    Citations to the Rule 4 file are to consecutively-numbered pages unless otherwise
    indicated.
    3
    This appears to be a typographical error. The parties do not dispute that KBAJ
    received a partial payment in the amount of $5,300 for deliveries made under
    PO 4256 (SOF ~ 2).
    2
    outstanding since October of 2014, with a net balance due
    us in the amount of $13,008.00.
    (R4, tab 7 at 20)
    6. In a letter dated 21 April 2015 addressed to Ms. Sax, KBAJ stated in part:
    RE: CONTRACT NO. SPE5E8- l 4-M-4256
    Dear Sharon:
    You are listed as the local administrator of the
    above referenced contract. As you know from our past
    requests we have been attempting to resolve the alleged
    issues associated with this award. To date we have been
    ignored, stonewalled and simply not responded to with
    regard to our attempts to resolve the alleged problems.
    Therefore, pursuant to the terms and conditions of said
    contract we are hereby asking if you would agree to submit
    this matter to [Alternative Dispute Resolution] for
    resolution. Please let us know your position on or before
    COB, Friday April 24, 2015. Ifwe do not hear from you
    by that date we will take you[r] lack of response as a
    refusal to submit the matter to [ADR].
    Finally, if you are not going to agree to [ADR], then
    please provide us with your written decision as to why you
    are refusing to pay the balance due and owning [sic] under
    this award. We require your decision so that the same can
    be submitted with our claim we intend on filing with the
    Armed Services Board Of Contract Appeals. If we do not
    receive your decision by COB, Friday April 24, 2015, we
    will notify the Board that no decision was received from
    despite our requests for the same.
    (R4, tab 9) COs Wilson and Manco were not copied on the letter.
    7. In a letter dated 22 April 2015, CO Manco responded to KBAJ's
    26 February and 10 March 2015 letters. Concerning the 26 February letter, CO Manco
    reiterated that KBAJ was requested to provide adequate traceability documentation,
    and failure to comply with the request would be deemed as non-compliance with
    PO 4256's terms (R4, tab I 0 at 25). Concerning the I 0 March letter, CO Manco
    communicated that acceptance and payment under PO 4256 and other POs issued to
    3
    KBAJ were under the purview of the contracting office and that failure to provide
    adequate traceability could lead to possible termination of the POs (id.).
    8. In a letter dated 24 April 2015, CO Manco denied KBAJ' s request to
    proceed under ADR in PO 4256 and other POs. The letter does not mention or
    reference KBAJ's 21April2015 letter. (R4, tab 11)
    9. On 24 September 2015, KBAJ filed its notice of appeal to this Board,
    appealing "the Deemed Denial of the Contracting Officer, SHARON SAX of [DLA]"
    of its "repeated requests for a written decision as why final payment. .. was not
    tendered."
    DECISION
    DLA's motion raises several grounds for dismissing the appeal and we begin
    with its contention that no proper claim was submitted to the CO for a final decision
    because the submission of a claim is a jurisdictional prerequisite for the Board under
    the Contract Disputes Act of 1978 (CDA), 
    41 U.S.C. §§ 7101-7109
    . CCIE & Co.,
    ASBCA Nos. 58355, 59008, 14-1 BCA ii 35,700 at 174,816. DLA argues that
    KBAJ' s 21 April 2015 letter is insufficient as a claim because it lacks enough detail to
    inform the CO of an assertion of a demand for payment and the underlying basis.
    DLA also argues that the letter's request for ADR is a contract administration matter.
    DLA alleges that the CO's 24 April 2015 letter, in response to the 21 April letter,
    rejected KBAJ's ADR request but did not invoke the CDA disputes process because it
    was not a final decision and did not foreclose KBAJ an opportunity to receive
    payment. (Gov't mot. at 15-16) KBAJ did not submit a response.
    The CDA does not define the term "claim"; however, FAR 2.101 defines a
    claim, in relevant part, as "a written demand or written assertion by one of the
    contracting parties seeking, as a matter of right, the payment of money in a sum
    certain." A claim is not required to be submitted in any particular form or use any
    particular wording, but must provide to the CO adequate notice of the basis and
    amount of the claim and request a final decision. M Maropakis Carpentry, Inc. v.
    United States, 
    609 F.3d 1323
    , 1328 (Fed. Cir. 2010). The claim must also be
    submitted to a CO for a decision. To satisfy the submission requirement, a contractor
    can either submit its claim directly to a CO or "to its primary contact [with the
    government] with a request for a final decision of the contracting officer and a
    reasonable expectation that such a request will be honored, and the primary contact in
    fact timely delivers the claim to the contracting officer." Neal & Co., Inc. v. United
    States, 
    945 F.2d 385
    , 388 (Fed. Cir. 1991); see also Gardner Zemke Co., 
    ASBCA No. 51499
    , 98-2 BCA ii 29,997.
    4
    As the proponent of our jurisdiction, KBAJ bears the burden to establish
    jurisdiction by a preponderance of the evidence. CCIE & Co., 14-1BCAii35,700
    at 174,816. "The facts supporting jurisdiction are subject to our fact-finding upon a
    review of the record." 
    Id.
     KBAJ's notice of appeal did not attach or indicate a
    specific document that serves as its claim in this appeal. However, KBAJ's complaint
    alleges that it "sent out a final demand letter dated April 21, 2015, requesting full
    payment or submission of the matter to [ADR]" (compl. ii 49). We presume that
    KBAJ attempts to appeal from an alleged CO's deemed denial of this letter.
    On its face, the 21 April letter is specifically addressed to Ms. Sax, who is
    identified by KBAJ as a local administrator and is also identified as a "Local Admin''
    under PO 4256 (SOF iiii I, 6). KBAJ's notice of appeal to the Board alleges that
    Ms. Sax is a CO, but a review of the record does not substantiate that allegation.
    Therefore, KBAJ has not established that its 21 April letter was submitted directly to a
    co.
    We next determine whether KBAJ meets the CDA's submission requirement by
    sending a proper claim to a primary contact. Pursuant to Neal, the requirement may be
    met by submitting a claim to the primary contact "with a request for a final decision of
    the contracting officer and a reasonable expectation that such a request will be
    honored." 
    945 F.2d at 388
    . While the 21 April letter does expressly request a decision
    from Ms. Sax, even if we were to assume she is a primary contact and the letter
    otherwise meets the requirements of the FAR definition of a claim, it is apparent that
    KBAJ intended to resolve its dispute with her. Prior to its 21 April submission, KBAJ
    received a 19 February 2015 email from CO Wilson that requested traceability
    documentation in connection with PO 4256 (SOF ii 3). KBAJ subsequently responded
    to CO Wilson's email and copied CO Manco, demanding payment before submitting
    any documentation (SOF ii 4). Therefore, KBAJ was aware of the identities of the
    pertinent COs yet elected to submit its 21 April letter to Ms. Sax and request a
    decision from her. See D.L. Braughler Co. v. West, 
    127 F.3d 1476
    , 1481-82 (Fed. Cir.
    1997) (letter styled as a claim with a certification and submitted to the resident
    engineer, who was an authorized representative of the CO, did not meet submission
    requirement because letter sought to resolve matter directly with resident engineer);
    Bruce E. Zoeller, 
    ASBCA No. 55654
    , 07-1BCAii33,581at166,347 (appellant was
    aware of the CO's identity under the lease, and submitted a claim seeking "a Chief
    Accountable Officer's decision" that failed to establish a submission of a claim to a
    CO under the CDA). Under these circumstances, we conclude that KBAJ neither
    pursued nor reasonably expected a decision from a CO through its 21 April
    submission. Based on the foregoing, KBAJ has not satisfied the CDA's submission
    requirement, depriving the Board of jurisdiction over its appeal. 4
    4
    We need not address alternative grounds for dismissal and to strike portions of the
    complaint raised in DLA's motion.
    5
    CONCLUSION
    We dismiss the appeal for lack of jurisdiction. The government's motion is
    granted.
    Dated: 22 November 2016
    ~~MARK A. MELNICK
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                       I concur
    ~4d-
    'MARK N. STEMPLER
    Administrative Judge
    RICHARD SHACKLEFORD
    Administrative Judge
    Acting Chairman                               Vice Chairman
    Armed Services Board                          Armed Services Board
    of Contract Appeals                           of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 60222
    , Appeal ofKBAJ
    Enterprises, LLC t/d/b/a Home Again, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    6
    

Document Info

Docket Number: ASBCA No. 60222

Judges: Melnick

Filed Date: 11/22/2016

Precedential Status: Precedential

Modified Date: 12/5/2016