Ephrata Water Co. v. Borough , 20 Pa. Super. 149 ( 1902 )


Menu:
  • Opinion by

    Rice, P. J.,

    The defendant’s second point suggests the questions to be considered on the appeal. It does not suggest that the contract of February 6,1893, was invalid ; nor is the argument of the defendant’s counsel in support of the affirmance of the point, arid the consequent binding instructions that the plaintiff could not recover, based on that ground. The two grounds of defense we are called upon to consider are: first, failure of performance on the part of the plaintiff; second, rescission or abandonment of the contract.

    The provisions of the contract pertinent to the first question are as follows:

    “ That the party of the first part, viz: the Ephrata Water Company, shall and will commence the necessary arrangements for supplying the party of the second part, viz: the borough of Ephrata, with water immediately on the signing of this agreement, and that, at the expiration of one year from the date, of this agreement, all main water pipes in the limits of said borough, which are to supply the fire plugs or hydrants hereinafter referred to, shall be properly laid in place, and the said fire plugs shall be supplied with water at the same time.”

    “ Fourth. The party of the first part will furnish to the party of the second part thirty first-class, double discharge, frost-proof fire plugs or hydrants to be located at such places as the proper authority of said borough may direct, which places shall be designated by the party of the second part within three months after the date of this agreement.”

    *154The first branch of the plaintiff’s undertaking was to commence the necessary arrangements for supplying the borough with water, immediately on the signing of the agreement. “ The word immediately,’ although in strictness it excludes all mean times, yet to make good the deeds and intents of parties, it shall be construed such convenient time as is reasonably requisite to do the thing : ” Pybus v. Mitford, 2 Lev. 77. It has been construed to be a stronger term than the expression “ within a reasonable time,” and to imply “ prompt, vigorous action without delay,” but in the same case in which the latter opinion was expressed, it was also held that whether there has been such action is a question of fact, having regard to the circumstances of the particular case: Queen v. Justices of Berkshire, L. R. 4 Q. B. Div. 469; 1 Bouv. Law Dict. (Rawle’s ed.) 983. We suppose there may be cases, where, the facts being undisputed and the inferences from them free from doubt, it would be the duty of the court to determine the question. But whether it be a question of law for the court or a question of fact for the jury, all the authorities agree, that it is impossible to lay down any hard and fast rule as to what is the meaning of the word in all cases. As has been said of the word “ forthwith,” with which it is synonymous, it has a relative meaning, and will imply a longer or shorter period according to the nature of the thing to be done. The plaintiff’s witnesses testified: that at the date of the contract, the company had a reservoir having a capacity of 70,000 gallons; that in the spring of the same year, it drove two or three tunnels into the mountain and thereby obtained a considerable supply of water; that in the same year it purchased all the pipes that would be required and had them in readiness to be laid; and that in the fall of that year it commenced the construction of a reservoir, which was completed in October, 1894, having a capacity of 700,000 gallons. The court would have been warranted in charging the jury, that if the foregoing facts were established to their satisfaction, the plaintiff had not forfeited its rights under the contract by failure to commence the work within the time contemplated by the parties.

    The second branch of the plaintiff’s undertaking was, that, at the expiration of one year from the date of the agreement, all main water pipes which were to supply the fire plugs or *155hydrants “ hereinafter referred to ” should be properly laid in place and the fire plugs supplied with water. It is an admitted fact that the pipes were not laid within a year from the date of the contract; but it is to be borne in mind that the pipes were to be laid to supply fire plugs, which were to be of such pattern, and were to be located at such places, as the proper authorities of the borough should designate, and that, although by the terms of the contract such designation was to be made within three months from its daté, it was not made until J uly or August, 1894. Promptly thereafter, according to the testimony, the plaintiff laid the seven or eight miles of pipe it had previously purchased, connected them with the fire plugs, and, having completed the reservoir, turned on the water early in October, 1894.

    Where a contract imposes reciprocal duties on the parties and the ability of one to perform depends on performance by the other, it would seem plain that the latter’s failure to perform within the time fixed for performance by the former would be a waiver of the time limitation. A party who is himself in default has no right to insist on rescission while in default, and where there has been indulgence on both sides, one party cannot suddenly rescind without notice to the other: Hatton v. Johnson, 83 Pa. 219; Irvin v. Bleakley, 67 Pa. 24; Forsyth v. North American Oil Co., 53 Pa. 168; Eberz v. Heisler, 12 Pa. Superior Ct. 388. After waiver, or where the agreement was originally indefinite, time does not become of the essence until notice be given by one of the parties, insisting on compliance within a reasonable time. Applying these principles to the case in hand we conclude, that, if without fault on the part of the plaintiff, there was not complete performance within the year, but there was part performance involving the expenditure of money, the defendant could not take advantage of its own default and arbitrarily rescind the contract at the end of the year.

    But it is argued that the plaintiff afterwards treated the contract as at an end, and, therefore, its binding force could not be restored except in the mode and with the formalities prescribed by law for the enactment of an ordinance. We cannot better state the proposition than by quoting from the charge of the court. The court said: “ But, when the year terminated, it *156seems to have been considered on all hands that the provisions and stipulations of the agreement liad not been carried into effect. The water company, recognizing this situation, on March 5, 1894 (a proposition from another company having been before councils offering better terms), submitted another proposition signed by its president and secretary to the borough council, whereby it agreed that it would lay the main water pipes in the limits of the borough and supply the fire plugs or hydrants with water within one year, and execute a bond in the sum of |5,000 for the compliance of that agreement, the terms being substantially, except as to price, the same as the first agreement. . . . This proposition was embodied into an ordinance and was passed by the borough council. It failed, however, to be carried out, by reason of the veto of the burgess and the inability of councils to pass the same over that veto. It was then that the water company fell back on the old agreement, and is now here attempting to recover the original price. . ... We think that, they having treated that agreement as dead, they cannot in this way, instill it with life.” Where a party.to a contract or transaction induces another to act upon the reasonable belief that he will waive certain rights or terms, he will be estopped to insist upon such rights or terms to the injury of the one misled by his conduct. But it does not appear in this case that the defendant was misled into anjr action in consequence of the proposition submitted by the plaintiff. There is only the bare fact of an offer to enter into a new contract upon the same terms as the old, except as to the price, which was not accepted. The motive of the plaintiff may have been to avoid the litigation that would probably ensue if the offer of the rival company was accepted. This supposition is quite as probable as any that can be made. At any rate its offer did not create an estoppel nor operate as a rescission of the original contract or as an abandonment of all claims thereunder. The utmost that can be claimed for it is that it was in effect an offer to rescind the old contract and relinquish all rights under it, if the borough would enter into the proposed new contract. Possibly it would have been evidence upon the question whether there was a mutual rescission, but standing alone it would not establish that fact. We conclude, therefore, that there was error in the instructions above quoted, in the *157answers to the plaintiff’s fourth point and in the affirmance of the defendant’s points.

    The plaintiff’s first, second, fourth and fifth points practically asked for binding instructions. As its case depended to some extent upon the testimony of witnesses and conclusions of fact to be drawn therefrom, these points could not have been unqualifiedly affirmed; therefore, the first, second and fourth assignments are overruled.

    We cannot say that there was error in any of the rulings upon evidence, excepting, possibly, that which is the subject of the seventh assignment. As bearing upon the question whether the plaintiff furnished a supply of water for the purposes contemplated by the contract, the evidence embraced in the offer was admissible. But the court committed no error in holding, as we construe its ruling to be, that it was not admissible for the other purposes stated in the offer.

    Judgment reversed and venire facias de novo awarded.

Document Info

Docket Number: Appeal, No. 231

Citation Numbers: 20 Pa. Super. 149

Judges: Beaver, Oread, Porter, Rice

Filed Date: 4/21/1902

Precedential Status: Precedential

Modified Date: 2/18/2022