Harber v. Pennsylvania Railroad , 56 Pa. Super. 59 ( 1914 )


Menu:
  • Opinion by

    Henderson, J.,

    It seems not to be disputed that the two pipes laid under the fill made by the defendant were insufficient to permit the passage of the water flowing in Little *63Blain Rim in the event of a heavy rain such as might ordinarily occur in that part of the country. In several instances shown by the evidence the embankment so obstructed the water of the stream that it was backed up and caused to flow over the tracks and onto the property of persons owning land on the lower side. Three such floods occurred within a month in the fall of 1911. The injury caused by them is the occasion of the pending action. That the plaintiff was subjected to a considerable loss because of the floods is conceded. The defense relied on- was that they were extraordinary and of so destructive a character that they could not reasonably have been foreseen and even if foreseen were so great that it would have been impracticable to have avoided or prevented the damage. Much of the evidence introduced in the case was directed to the inquiry whether the floods were of the magnitude alleged by the defendant. The plaintiff contended, and offered evidence to show, that the volume of water was such as might be expected after a heavy rain in that section of country and that within a few years at least seven floods of substantially the same height had occurred. The greatest injury was done on September 8, 1911, and it may be accepted as a fact that this flood was greater than those of September 15 and October 1 of the same year and probably greater than the floods of former years, but the testimony of some of the plaintiff’s witnesses who had lived in the locality for many years was that these were the ordinary conditions following very heavy rains. Some of the witnesses for the defendant regarded the flood of September 8 as extraordinary and the highest ever observed by them in that stream. This evidence raised an issue of fact which the court submitted to the jury as the first question for determination, and this submission was accompanied by the instruction that if the flood was extraordinary, one such as could not reasonably have been anticipated as likely to occur in that stream, the *64defendant could not be held for the loss sustained by the plaintiff unless that loss was in part the result of the negligence of the defendant arising out of its failure to construct and maintain an outlet for the stream under the fill adequate to allow the flow of water likely to exist during ordinary floods, regard being had to the extent of the watershed and the precipitateness of the hillsides. This was a proper subject for consideration by the jury under the evidence: Fick v. Penna. R. R. Co., 157 Pa. 622; Brown v. Ry. Co., 183 Pa. 38. The defendant in making or enlarging the fill was bound to take account of the size of the stream and the extent and character of the watershed in making provision for the flow of water. Anticipation must be had in such cases-that floods will occur with their accompanying ice and drift and provision must be made accordingly. The defendant was not required to provide against what is extraordinary. An act of Providence as related to cases of injurious negligence is one against which ordinary skill and foresight is not expected to provide. Whether a particular injury is attributable to such a cause or is the consequence of negligence is ordinarily a question of fact. The court could not have declared that the floods in question were extraordinary without usurping the function of the jury. It was said in Pitts., Ft. Wayne & Chicago Ry. Co. v. Gilleland, 56 Pa. 445: “The frequent recurrence of what was supposed to be extraordinary was some evidence that the real character of all these floods had been mistaken by those who testified as to their extraordinary character and that they were really only ordinary freshets, though measuring up to the highest altitude of that class. It was proper, therefore, to submit this question to the jury with instruction, if they so found the fact* to apply the rule as to ordinary freshets.”

    The plaintiff did not rely wholly, however, on the evidence that the floods were of an ordinary character but contended and offered evidence to show that the outlet was not only insufficient in size but was so con*65structed in the location of the two pipes that the two currents created in close proximity caused drift of various kinds to lodge in the space between the pipes and thereby greatly increased the accumulation of drift with the result that the mouths of the pipes were clogged and closed. The effect of this necessarily would be to increase the volume of water flowing over the track and onto the plaintiff’s property and this increase might be an important factor in producing the plaintiff’s damage. If the negligence of the defendant concurred with an act of Providence in producing the injury the defendant would be liable: B. & O. R. R. Co. v. School District, 96 Pa. 65; Helbling v. Cemetery Co., 201 Pa. 171. The plaintiff’s evidence showed that the pipes at times were so obstructed that their outflow was very much less than their capacity in times of flood and even in the case of an extraordinary flood the obstruction of the two pipes would probably add very materially to the destructive consequences of the flow of water over the track.' Evidence was introduced to show that when the road was originally constructed a stone culvert was made to carry off the water of the run; that this was inadequate for the purpose and that about 1891 when a double track was laid on the fill this culvert was taken out and the. two iron pipes each having a diameter of twenty-four inches were placed under the tracks. Objection was made to the testimony introduced to show the relative capacity of the old culvert and the new pipes, but we think it was competent for the purpose of showing knowledge or opportunity of knowledge by the defendant of the requirements as to the size of the culvert. If it had been demonstrated by the action of floods for a number of years that the stone culvert was not adequate, the act of the defendant’s employes in putting in a less capacious culvert would lack justification. The averment of the plaintiff’s statement that the defendant had maintained a sufficient culvert which had been removed at the time when the *66iron pipes were placed was not a necessary part of the plaintiff’s declaration nor material to the right of recovery. There was no necessity, therefore, that the plaintiff support that statement by evidence. He was not precluded thereby from showing that a larger but inadequate provision existed before the iron pipes were used. It may be remarked also that it is practically conceded that the pipes were insufficient to meet the requirements of an ordinary flood and the testimony was therefore not prejudicial to the defendant.

    The jury could not have misunderstood the answers of the learned trial judge to the plaintiff’s second and thirteenth points. They had reference to the injuries set forth in the declaration and which were the subject of consideration during the progress of the trial. The only damage which the plaintiff claimed was that resulting from the floods in September and October, 1911. Whatever the jury found to have been the plaintiff’s loss by reason of any of these floods as disclosed by the testimony would be the basis of the verdict, and we must assume that the conclusion of the jury was limited and controlled by the testimony. We are not convinced that the court erred in any material way in the trial of the case.

    The judgment is affirmed.

Document Info

Docket Number: No. 1; Appeal, No. 75

Citation Numbers: 56 Pa. Super. 59

Judges: Head, Henderson, Morrison, Orlady, Porter, Rice

Filed Date: 2/20/1914

Precedential Status: Precedential

Modified Date: 2/18/2022