Torma, J. v. Parrot Construction Corp. ( 2018 )


Menu:
  • J-A02040-18
    NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
    JUDY TORMA,                                  IN THE SUPERIOR COURT
    OF
    PENNSYLVANIA
    Appellant
    v.
    PARROT CONSTRUCTION CORP.,
    PAUL CHAMBERS,
    Appellees              No. 1105 WDA 2017
    Appeal from the Order entered June 29, 2017,
    in the Court of Common Pleas of Allegheny County,
    Civil Division, at No(s): GD-15-017669.
    BEFORE: BOWES, J., OLSON, J., and KUNSELMAN, J.
    MEMORANDUM BY KUNSELMAN, J.:                       FILED MARCH 27, 2018
    Judy Torma appeals from the Order denying her Petition to Vacate or
    Modify Arbitration Award and claims that a dispute over an agreement to
    provide additional moving services was not covered by the arbitration clause
    of the parties’ original construction contract. For the following reasons, we
    affirm.
    On May 15, 2014, Torma, on behalf of her parents, and Parrot
    Construction Corporation,1 entered into a construction contract (“Construction
    Contract”), in which Parrot agreed to renovate certain portions of a building
    ____________________________________________
    1Appellee, Paul Chambers, is the President of Parrot Construction
    Corporation.
    J-A02040-18
    owned by Torma’s parents. The parties used a form contract produced by the
    Associated General Contractors of America, which included the following
    arbitration clause:
    16.1 All claims, disputes and other matters in questions arising
    out of, or relating to, this Agreement or the breach thereof, Except
    with respect to the Architect/Engineer’s decision on matters
    relating to artistic effect, and except for claims which have been
    waived by the making or acceptance of Final Payment shall be
    decided by arbitration in accordance with the Construction
    Industry Arbitration Rules of the American Arbitration Association
    then obtaining unless the parties mutually agree otherwise. This
    Agreement to arbitrate shall be specifically enforceable under the
    prevailing arbitration law.
    A few weeks later, on June 6, 2014, the parties executed another
    Agreement of Understanding (“Moving Contract”). Under this Agreement,
    Parrot agreed to photograph, inventory, transport, store, and sell a number
    of arcade and coin-operated machines owned by Torma’s parents, stored in
    areas where Parrot needed access to perform the renovation/construction
    work. Torma agreed to pay Parrot for transportation costs and other fees, as
    well as a fee for selling any of the machines.
    On March 27, 2015, Parrot filed an arbitration claim with the American
    Arbitration Association (“AAA”), demanding payment for its work under both
    the Construction and Moving Contracts.           Parrot alleged that the Moving
    Contract was a change order and, thus, an integrated part of the Construction
    Contract. Torma filed an answer and counterclaim arguing, in pertinent part,
    that the Moving Contract was separate and distinct from the Construction
    Contract, and not covered by the arbitration clause of the original agreement.
    -2-
    J-A02040-18
    At the arbitration hearing on August 22, 2015, Torma objected to the
    arbitrator considering the Moving Contract, arguing that the AAA lacked
    jurisdiction over this claim. However, the arbitrator chose to hear all evidence
    related to the Construction Contract and Moving Contract before issuing a
    decision on whether he had jurisdiction.
    On August 26, 2015, the arbitrator issued a written order stating that
    the AAA had jurisdiction to hear the Moving Contract claim, characterizing the
    Moving Contract as a Change Order under the Construction Contract.           On
    September 3, 2015, the arbitrator entered an award in favor of Parrot which
    included, inter alia, $7,500 representing the balance due pursuant to the
    Moving Contract.
    On October 5, 2015, Torma filed a Petition to Vacate or Modify
    Arbitration Award in the Court of Common Pleas. Therein, Torma claimed,
    inter alia, that the arbitrator exceeded the scope of the arbitration agreement
    by ruling on the Moving Contract. Consequently, Torma sought to have the
    Arbitration award modified to exclude the amount attributable to the Moving
    Contract.
    The trial court denied Torma’s Petition on all issues, including Torma’s
    claim that the arbitrator did not have jurisdiction. Torma filed a Notice of
    Appeal. By Memorandum dated January 11, 2017, this Court remanded the
    case on the jurisdictional issue for hearing to determine whether the arbitrator
    had jurisdiction over the Moving Contract. There, in pertinent part, we stated:
    -3-
    J-A02040-18
    Upon review of the Construction Contract and the Moving
    Contract, we conclude that, contrary to the apparent view of both
    the arbitrator and the trial court, the terms of the two contracts
    do not clearly resolve the question whether disputes under the
    Moving Contract are subject to the arbitration clause in the
    Construction Contract. . . . Torma argues that the arbitration
    clause of the Construction Contract does not apply to the Moving
    Contract. According to Torma, ‘[t]he plain meaning of the
    language of the Moving Contract makes it clear that its scope
    applied to the moving storing and selling of personal property. . .
    [, which] has nothing to do with the design and construction of
    renovations to the. . . [b]uilding.’ Parrot argues in response that
    the Moving Contract ‘was a change order to the [Construction
    C]ontract as the removal of items and other preparations were
    necessary as part of the renovations.’ According to Parrot, “the
    parties contemplated and executed that agreement as part of the
    [C]onstruction [C]ontract and incorporated it and other change
    orders. Because we find that both of these interpretations are
    reasonably plausible, we remand the matter to the trial court so
    that the parties may present evidence to assist the trial court in
    determining whether the arbitrator had jurisdiction over the
    Moving Contract.
    Torma v. Parrot Constr. Corp., et al., 363 WDA 2016, unpublished
    memorandum at 15-18 (January 11, 2017).
    On June 5, 2017, the trial court held an evidentiary hearing which
    focused on whether the language of the agreement, and the facts related
    thereto, justified the arbitrator’s exercise of jurisdiction over the dispute
    concerning Parrot’s moving, storage and sale of certain machines and
    equipment which were stored in the building. From this hearing, the trial court
    elicited the following facts surrounding the execution of the two documents in
    issue.
    Torma hired Parrot to correct serious structural and other deficiencies in
    a commercial building owned by her parents. A lot of old tools and other items
    -4-
    J-A02040-18
    were stored in the building which had to be moved and scrapped. There were
    also old vending machines stored in the building. All these items had to be
    removed so that Parrot could perform the construction/renovation work.
    Torma was well aware that these things had to be moved so that construction
    could start. Torma believed that the vending machines were valuable, and
    tried to remove the machines on her own, but was unable to find someone to
    do it. As a result, she asked Parrot to remove these things from the building
    until the work was finished and scrap the junk. This resulted in the execution
    of the Moving Contract on June 6, 2014, between Torma and Parrot. This was
    one of several change orders executed under the Construction Contract.
    Thereafter, the trial court entered a decision on June 28, 2017,
    concluding the arbitrator properly had jurisdiction over the Moving Contract,
    because it was a change order to the original Construction Contract which
    contained an arbitration clause requiring all claims to be arbitrated. Torma
    appealed again; the matter is now before us.
    In this appeal, Torma raises the following issue:
    Whether the trial court erred as a matter of law or abused its
    discretion when it concluded that the Moving Contract was a
    change order to the Agreement, and therefore the arbitrator had
    jurisdiction over the Moving Contract.
    Torma Brief at 5.
    The arbitration agreement in the instant case is governed by 42 Pa.C.S.
    section 7341 et seq. which pertains to common law arbitration. 42 Pa.C.S. §
    7341 et seq. Our standard of review of common law arbitration is very limited.
    -5-
    J-A02040-18
    In reviewing a trial court’s order on a petition to vacate or modify a common
    law arbitration award, our review is limited as follows:
    The award of an arbitrator in a nonjudicial arbitration which
    is not subject to statutory arbitration or to a similar statute
    regulating nonjudicial arbitration proceedings is binding and may
    not be vacated or modified unless it is clearly shown that a party
    was denied a hearing or that fraud, misconduct, corruption or
    other irregularity caused the rendition of an unjust, inequitable or
    unconscionable award. The arbitrators are the final judges of both
    law and fact, and an arbitration award is not subject to reversal
    for a mistake of either. A trial court order confirming a common
    law arbitration award will be reversed only for an abuse of
    discretion or an error of law. The appellant bears the burden to
    establish both the underlying irregularity and the resulting
    inequity by clear, precise, and indubitable evidence.
    Andrew v. CUNA Brokerage Services, Inc., 
    976 A.2d 496
    , 500 (Pa. Super.
    2009) (internal citations and quotation marks omitted).       In particular, an
    award may also be corrected if the arbitrator exceeds the scope of his
    authority.   Gargano v. Terminix Int’l Co., L.P., 
    784 A.2d 188
    , 193 (Pa.
    Super. 2001). “’The power and authority of arbitrators are wholly dependent
    upon the terms of the agreement of submission, and they cannot exercise
    authority as to matters not included therein, or validly determine the dispute
    if they violate or act inconsistently with the terms of the submissions.’”
    Boulevard Associates v. Seltzer P’ship, 
    664 A.2d 983
    , 987 (Pa. Super.
    1995) (quoting Sley Sys. Garages v. Transportation Workers Union of
    Am., 
    178 A.2d 560
    , 561 (Pa. 1962)).
    Torma argues that the trial court erred in concluding that the Moving
    Contract was a change order, rather than an entirely separate contract
    -6-
    J-A02040-18
    between the parties.      According to Torma, “the Trial Court abused its
    discretion because it relie[d] entirely upon the credibility of witness testimony
    presented to support its conclusion; and that the Trial Court committed an
    error of law by simultaneously ignoring the provisions of the documentary
    evidence that unambiguously show the Moving Contract does not fall under
    the Agreement’s definition of change order as a matter of law.” Torma Brief,
    at 16. Torma emphasizes that “[w]hen interpreting agreements containing
    clear and unambiguous terms, we need only examine the writing itself to give
    effect to the parties.” Melton v. Melton, 831 A2d 646, 653-54 (Pa. Super.
    2003). Where the rights are based on an unambiguous writing, the parties’
    intent must be determined from the writing itself, not from testimony as to
    the parties understanding or intent.    Personal belief is irrelevant. Grey Fox
    Plaza v. Herbert, Rowland and Grubic, Inc., 
    2017 WL 519827
     at 8 (Pa.
    Comwlth. 2017). Consequently, Torma’s entire argument is premised solely
    upon the documents themselves.
    Conversely, Parrot argues that the trial court did not err in concluding
    the Moving Contract was a Change Order and thus, was subject to the
    arbitration clause. The documents and testimony support this conclusion.
    Before addressing the core of the matter before us, we review the basic
    principles of contract interpretation applicable to this claim.
    Generally, the intent of the parties, which governs the interpretation of
    the contract, is to be ascertained from the writing itself. In most cases, the
    -7-
    J-A02040-18
    trial court is limited to examining only the contents of the actual agreements
    between the parties. However, as a panel of this Court previously concluded,
    contrary to Torma’s contention, the terms of the contracts in this matter were
    not clear and unambiguous. The intent of the parties, regarding whether the
    Moving Contract was subject to arbitration, was not evident from the face of
    the documents. Under these circumstances, “parol evidence is admissible to
    explain or clarify or resolve the ambiguity . . . .” Miller v. Poole, 
    45 A.3d 1143
    , 1146 (Pa.Super. 2012).
    “Where the words used in a contract are ambiguous, the surrounding
    circumstances may be examined to ascertain the intent of the parties.”
    Walton v. Philadelphia Nat'l Bank, 
    545 A.2d 1383
    , 1389 (Pa. Super. 1988).
    While “[t]his Court may determine the existence of an ambiguity as a matter
    of law, [ ] the resolution of conflicting parol evidence relevant to what the
    parties intended by the ambiguous provision is for the trier of fact.” Windows
    v. Erie Ins. Exch., 
    161 A.3d 953
    , 958 (Pa. Super. Ct. 2017) (quoting Walton,
    supra). Concluding that the contracts were ambiguous, we remanded the
    case to the trial court for testimony to ascertain the parties’ intent.
    The provisions in the contracts at issue in this case are no different now
    than they were when the trial court entered its Decision of June 28, 2017, and
    when this Court issued its Memorandum of January 11, 2017. Consequently,
    for us to rely solely on the documents in this situation, as advocated by Torma,
    would completely contradict our prior decision. The trial court did not err by
    -8-
    J-A02040-18
    conducting an evidentiary hearing and considering evidence outside the
    documents themselves. To the contrary, the trial court did exactly as this
    Court instructed.   Thus, in deciding this appeal, we look beyond the four
    corners of the documents and consider all the evidence presented to the trial
    court in this matter, both testimony and documentary.
    In claiming that the Moving Contract was a separate contract or
    transaction, and not subject to the arbitration clause, Torma first argues that
    the Construction Contract spelled out a very narrow and limited scope of work.
    The Construction Contract describes the Project as: “Renovations to the front
    wall and middle of the roof of existing space known located at 1007 Constance
    Street, Pittsburgh, PA 15212”.     The Construction Contract further defines
    Project in Article 1.3 as the “total construction to be designed and constructed
    of which the Work is a part. The Work comprises the complete construction
    required by the drawings and specifications.” Based upon these provisions,
    Torma argues that the scope of the Construction Contract was solely for
    renovation and construction to the front wall and middle of the roof of the
    building based upon the Architect’s plans. Torma further suggests that this
    scope could not be modified.
    Torma additionally argues that the term “Change Order” was defined in
    the Construction Contract. According to Torma, based upon the definition of
    “Change Order” in the Construction Contract, “Change Orders” can only be
    issued in the following situations: 1) unknown or concealed condition; 2)
    -9-
    J-A02040-18
    change in price; 3) extension of time; and 4) an emergency. The Moving
    Contract, additional services to be provided by Parrot, did not fall within any
    of these categories, and thus cannot be considered a “Change Order”.
    Parrot argues that, although the Moving Contract is not termed a
    “Change Order”, it nonetheless is a “Change Order” to the scope of the Project
    as provided for under Article 9 of the Construction Contract. We agree.
    Obviously, the moving work performed by Parrot was not included in the
    original scope of work. Contrary to Torma’s argument, however, the terms of
    the Construction Contract did not preclude those services from being added.
    Ariticle 9.1 permits the Owner to “order changes in the Project within the
    general scope of this Agreement consisting of additions, deletions or other
    revisions . . . .” Article 9.1.1 of the Construction Contract clearly states that
    “[a] Change Order is a written order to the Contractor signed by the Owner or
    his authorized agent and issued after the execution of the Agreement,
    authorizing a Change in the Project . . . .” (emphasis added). Thus, the
    Project could be redefined or expanded, and was not limited to renovations or
    construction as argued by Torma. Moreover, the Moving Contract met the
    technical requirements of a Change Order. It was executed by Torma a little
    less than a month after the execution of the Construction Contract.            It
    expanded the scope of the Project to include removal of the things stored in
    the building.   Consequently, contrary to Torma’s argument, the Moving
    Contract could be considered as a Change Order to the Project. The testimony
    - 10 -
    J-A02040-18
    adduced at the hearing before the trial court supports the trial court’s finding
    that the Moving Contract was a change order rather than a separate
    agreement.
    Before the renovation work could commence, the building had to be
    cleared out; the building was full of items including, vending machines,
    material, metal, old tools, and debris. Removal of these items is typically the
    responsibility of the owner. Torma, however, was unable to arrange to have
    the building cleared out on her own, and was being pressured by the city to
    make the required repairs. Parrot told Torma that construction could not start
    until the most of the items were cleared out of the building. Torma asked for
    a proposal from Parrot to perform this work.         Consequently, the parties
    entered into the Moving Contract. Parrot reasonably considered this to be a
    Change Order as defined under the Construction Contract.
    The    presentation   of   testimony   to   explain   the   circumstances
    surrounding the formation of the Moving Contract helped the trial court to
    resolve the ambiguity between the Construction Contract and Moving
    Contract. Because the removal of the items was necessary to carry out the
    Construction Contract, we think the trial court properly found that the moving
    services expanded the scope of the original services under the Construction
    Contract and constituted a Change Order. In making this decision, as the trier
    of fact, the trial court properly considered the credibility of Torma and
    - 11 -
    J-A02040-18
    Chambers as witnesses when they described the circumstances surrounding
    the execution of the two contracts.
    Finally, the trial court’s interpretation is consistent with the long-
    standing principle of contract law that “[w]here several instruments are made
    as part of one transaction they will be read together, and each will be
    construed with reference to the other; and this is so although the instruments
    may have been executed at different times and do not in terms refer to each
    other.” Neville v. Scott, 
    127 A.2d 755
    , 757 (Pa. Super. 1957).              We,
    therefore, conclude that the trial court did not abuse its discretion in finding
    that the Moving Contract was a Change Order to the Construction Contract
    rather than a separate, unrelated agreement between the same parties.
    In affirming the trial court’s conclusion that the Moving Contract was a
    Change Order to the Construction Contract, we believe we have resolved the
    parties’ issue of whether the arbitration clause could cover the Moving
    Contract dispute since it was part of the Construction Contract. Next, we will
    briefly address whether the dispute did fall within the specific language of the
    arbitration clause. In reviewing the arbitration clause, we keep in mind the
    following legal principles.
    “Arbitration agreements are contracts and should be interpreted using
    contract principles.” Bucks Orthopedic Surgery Associates, P.C. v. Ruth,
    
    925 A.2d 868
    , 872 (Pa. Super. 2007). “The fundamental rule in construing a
    contract is to ascertain and give effect to the intention of the parties.” Lower
    - 12 -
    J-A02040-18
    Frederick Twp. v. Clemmer, 
    543 A.2d 502
    , 510 (1988).              “The scope of
    arbitration is determined by the intention of the parties as ascertained in
    accordance with the rules governing contracts generally” as discussed in full
    above. D & H Distrib. Co. v. Nationall Union Fire Ins. Co., 
    817 A.2d 1164
    ,
    1166 (Pa. Super. 2003). “Even though it is now the policy of the law to favor
    settlement of disputes by arbitration and to promote the swift and orderly
    disposition of claims, arbitration agreements are to be strictly construed
    and such agreements should not be extended by implication.” Setlock
    v. Pinebrook Pers. Care & Ret. Ctr., 
    56 A.3d 904
    , 907–08 (2012) (quoting
    Elwyn v. DeLuca, 
    48 A.3d 457
    , 461 (Pa.Super.2012)) (citations and
    quotation marks omitted; emphasis added).
    In this case, the arbitration clause of the Construction Contract
    provided in pertinent part:
    All claims, disputes and other matters in questions arising
    out of, or relating to, this Agreement or the breach thereof,
    Except with respect to the Architect/Engineer’s decision on
    matters relating to artistic effect, and except for claims which have
    been waived by the making or acceptance of Final Payment shall
    be decided by arbitration. . . .
    It is clear that the issue of payment for Parrot’s moving services, a matter of
    contract, plainly arose out of the Construction Contract as modified by the
    terms of the Moving Contract. Furthermore, the arbitration clause in this case
    is very broad.   In Dodds v. Pulte Home Corp., 
    909 A.2d 348
     (Pa. Super.
    2006), this Court found that contractual language such as the language at
    issue herein to be an “unlimited arbitration clause”. Dodds, 
    909 A.2d at 350
    .
    - 13 -
    J-A02040-18
    “Where an arbitration clause is unrestricted, the parties to the contract could
    be compelled to arbitrate any claim that implicates a contractual
    obligation.” Smay v. E.R. Stuebner, Inc. 
    864 A.2d 1266
    , 1274 (Pa.Super.
    2004) (emphasis added).         Here, it is apparent that without the moving
    services of Parrot, the original scope of the Construction Contract, i.e.,
    construction of and renovation to the building, could not have been performed.
    Thus, the moving services were fundamentally related to Parrot’s performance
    of its obligations under the Construction Contract. Consequently, consistent
    with the rationale of Smay, any issues with the moving services would
    properly   be   subject   to   arbitration   under   the   Construction   Contract.
    Additionally, but for the construction/renovation project, there would be no
    Moving Contract. Clearly, the moving services arose out of, or are related to,
    the Construction Contract and the work to be done thereunder.              Per the
    language of the arbitration clause in this case, anything arising out of the
    Construction Contract, such as the moving services, was subject to the
    arbitration clause and properly within the arbitrator’s jurisdiction.          We,
    therefore, conclude that the trial court did not commit an error of law in finding
    that Torma and Parrot’s dispute over the moving services arose out of or was
    related to the Construction Contract and thus subject to arbitration.
    CONCLUSION
    After careful review of the contract provisions and the parties' intentions
    as reflected in the contract documents as well as the testimony presented
    - 14 -
    J-A02040-18
    before the trial court, we conclude that the trial court did not abuse its
    discretion or commit an error of law when it confirmed2 the arbitration award
    with respect to the Moving Contract.
    Order affirmed.
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 3/27/2018
    ____________________________________________
    2We view the trial court’s decision as a confirmation of the arbitrator’s award
    even though the trial court did not specifically enter an order stating that it
    was confirmed. Another panel of this Court previously addressed this issue.
    See Torma, 363 WDA 2016, unpublished memorandum at 15-18 n. 3.
    - 15 -