Harvan, A. v. Krystyniak, M. v. McTavish, T. ( 2018 )


Menu:
  • J-A13040-18
    NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
    ANDREW SCOTT HARVAN A/K/A       :         IN THE SUPERIOR COURT OF
    SCOTT A. HARVAN AND MARIA A.    :               PENNSYLVANIA
    HARVAN, A/K/A MARIE A. HARVAN,  :
    HIS WIFE,                       :
    :
    Appellants      :
    :
    :
    v.                   :
    :
    :
    MARK E. KRYSTYNIAK AND KATHRYN :
    M. KRYSTYNIAK, HIS WIFE, DONALD :
    K. SEDER AND FELECIA A. SEDER,  :
    HIS WIFE, AMERISERV FINANCIAL   :
    BANK AND MORTGAGE ELECTRONIC :
    REGISTRATION SYSTEM, INC.       :
    (MERS) NOMINEE FOR AMERISERV    :
    FINANCIAL BANK, KEVIN DIX, AND  :
    VICKI L. SAMPEY-DIX, HIS WIFE,  :
    AND THE SCOTTDALE BANK & TRUST :
    CO.                             :
    v.                   :
    :
    :
    TODD A. MCTAVISH AND LORIE M.   :
    MCTAVISH, HUSBAND AND WIFE,     :
    AND WASHINGTON FINANCIAL BANK :               No. 1802 WDA 2017
    Appeal from the Judgment Entered December 29, 2017
    in the Court of Common Pleas of Westmoreland County,
    Civil Division at No(s): No. 8221 of 2005
    BEFORE: OLSON, J., DUBOW, J., and MUSMANNO, J.
    MEMORANDUM BY MUSMANNO, J.:                     FILED AUGUST 31, 2018
    Andrew Scott Harvan a/k/a Scott A. Harvan and Maria A. Harvan a/k/a
    Marie A. Harvan, his wife (collectively, “the Harvans”), appeal from the
    Judgment entered on December 29, 2017, following the denial of their Motion
    J-A13040-18
    for Post-Trial Relief,1 in a quiet title action against Mark E. Krystyniak and
    Kathryn M. Krystyniak, his wife (collectively, “the Krystyniaks”).2 We affirm.
    The trial court previously set forth the relevant history concerning the
    real property at issue in this appeal as follows:
    1. The Duncan Plan was established in 1906. The [Krystyniaks]
    and the [Harvans] own real property that is composed of lots that
    were created by the Duncan Plan. The Duncan Plan lots were
    quite small, measuring 40 feet by 120 feet, and cannot be
    occupied or developed under the Municipalities Planning Code or
    the procedures of Mt. Pleasant Township or the regulations of
    Westmoreland County.
    2. The Duncan Plan was re-subdivided twice: the Pleasant Heights
    Plan was recorded in 1966[,] and the Ivy Heights Plan was
    ____________________________________________
    1  The Harvans’ Notice of Appeal was filed from the Order denying their Motion
    for Post-Trial Relief. “It is well-settled law … that an appeal to this Court can
    only lie from judgments entered subsequent to the trial court’s disposition of
    post-verdict motions, not from the order denying post-trial motions.” U.S.
    Bank, N.A. v. Pautenis, 
    118 A.3d 386
    , 388 n.2 (Pa. Super. 2015).
    Accordingly, this Court issued a Rule to Show Cause on December 20, 2017,
    directing the Harvans to praecipe the trial court Prothonotary to enter
    judgment, and to provide a certified copy of the trial court docket reflecting
    the entry of judgment within 14 days. The Harvans timely complied by
    submitting a certified copy of the trial court docket indicating that Judgment
    had been entered on December 29, 2017. This Court thereafter entered an
    Order discharging the Rule to Show Cause. Because the trial court’s entry of
    Judgment on December 29, 2017 perfected the appeal, we conclude that the
    instant appeal is properly before us, and we have amended the caption
    accordingly. See Pa.R.A.P. 905(a)(5) (providing that “[a] notice of appeal
    filed after the announcement of a determination but before the entry of an
    appealable order shall be treated as filed after such entry and on the day
    thereof.”); see also Tincher v. Omega Flex, Inc., 
    180 A.3d 386
    , 396 n.7
    (Pa. Super. 2018) (declining to quash appeal from order denying post-trial
    motions where the appeal was perfected by the entry of judgment).
    2Several additional defendants were identified in the underlying action, none
    of whom are parties to the instant appeal.
    -2-
    J-A13040-18
    record[ed] by the [Krystyniaks] in 2004. The 1966 and 2004
    plans are essentially superimposed over the Duncan Plan.
    3. Moore Avenue is a paper street that is an original part of the
    Duncan Plan, but which has never been accepted by Mt. Pleasant
    Township.
    4. The lots in the Ivy [Heights] Plan are larger than those in the
    original Duncan Plan, and Moore Avenue passes over some of
    these lots.
    5. When the plan for Ivy Heights was finalized, the Mt. Pleasant
    Township Planning Commission relocated a portion of Moore
    Avenue a very short distance from its original site and renamed it
    Rosewood Avenue. By approving the plan, the Township agreed
    to accept Rosewood Avenue as a public street. The actions of Mt.
    Pleasant Township were conducted pursuant to the Municipalities
    Planning Code.
    6. The Ivy Heights Plan relocated the segment of Moore Avenue
    that extends from Stone Street[, a street which runs perpendicular
    to Moore Avenue,] to the Rosewood Avenue cul-de-sac. …
    …
    8. Nothing in the record indicates that the [Harvans] or any other
    party appealed the decision of the Planning Commission or
    otherwise challenged the relocation and renaming of Moore
    Avenue.
    9. Rosewood Avenue runs parallel to the old Moore Avenue right-
    of-way, and it is situated only a matter of feet from Moore Avenue.
    10. The [Krystyniaks] paved Rosewood Avenue and extended
    utilities along the roadway.
    Trial Court Opinion, 3/31/09, at 4-6 (citation to record omitted).
    -3-
    J-A13040-18
    On October 25, 2005, the Harvans filed a Complaint in quiet title.3 The
    Harvans alleged that they were denied access over the Krystyniaks’ tract of
    land as a result of the subdivision of the original Duncan Plan, and the
    elimination of Moore Avenue through the recording of the Ivy Heights Plan.
    The Harvans sought a determination by the trial court that they have an
    implied easement over Moore Avenue, as shown in the Duncan Plan, to access
    their property.
    The Krystyniaks filed an Answer and New Matter on November 23, 2005,
    wherein they acknowledged that the Ivy Heights Plan eliminated Moore
    Avenue, but argued that the new plan supplies a new, paved public road, i.e.,
    Rosewood Avenue, through which the Harvans are able to access their
    property. The Krystyniaks also claimed that Moore Avenue, as provided for in
    the Duncan Plan, only allowed vehicular and pedestrian traffic, and did not
    provide an easement for utilities.
    The Harvans filed a Preliminary Objection to the Krystyniaks’ New
    Matter, and a Reply on December 13, 2005.         On January 10, 2006, the
    Harvans filed an Amended Complaint, seeking essentially the same relief
    regarding Moore Avenue.
    On September 1, 2006, with consent of the parties, the trial court
    entered an Order (“Consent Order”), which provided that (1) the Harvans were
    entitled to use, as a private right-of-way for ingress, egress and regress, the
    ____________________________________________
    3The Complaint also included a request for a declaratory judgment, and an
    action in ejectment, which are not relevant to the instant appeal.
    -4-
    J-A13040-18
    streets and alleys identified in the Duncan Plan; (2) the Harvans could use the
    Duncan Plan’s streets and alleys to install utilities and to implement storm
    water management; and (3) the Krystyniaks, their grantees, heirs and assigns
    (including individuals who had purchased or would purchase lots within the
    Ivy Heights Plan) were enjoined from inhibiting or restricting in any way the
    Harvans’ right to access their property. The trial court also ordered that the
    action be discontinued, but the court retained jurisdiction to compel
    compliance with the terms of the Consent Order.
    On July 28, 2008, the Krystyniaks filed a Petition to Modify the Consent
    Order, asserting that the Harvans had been intentionally abusing the scope of
    the Consent Order. The Krystyniaks argued that Rosewood Avenue provides
    a substantially similar means of vehicular access to the Harvans’ property,
    and that the Harvans do, in fact, use Rosewood Avenue to access their
    property.   The Krystyniaks claimed that the Harvans had nevertheless
    continued to use Moore Avenue, which is a dirt path, for the sole purpose of
    harassment and disruption, and that the Harvans’ actions caused damage to
    the Krystyniaks’ properties.
    The Harvans filed an Answer, alleging that they had used Rosewood
    Avenue to access their property only when the Krystyniaks failed to abide by
    the terms of the Consent Order, i.e., when Moore Avenue was blocked due to
    construction, or by the placement of dirt, trees and vehicles within Moore
    Avenue.
    -5-
    J-A13040-18
    Following three days of evidentiary hearings, the Honorable William J.
    Ober (“Judge Ober”) determined, inter alia, that (1) Rosewood Avenue is “in
    every respect superior to Moore Avenue” and provides greater utility to the
    Harvans than Moore Avenue; (2) because the Moore Avenue right-of-way
    passes over the front yards of residential lots in the Ivy Heights Plan, vehicular
    traffic over Moore Avenue poses a hazard to the health, safety and property
    of the Ivy Heights Plan’s residents; and (3) the Krystyniaks had agreed to
    allow the Harvans to extend utility lines from the Rosewood Avenue cul-de-
    sac to the Harvans’ property. See Trial Court Opinion, 3/31/09, at 6. The
    trial court additionally determined that “the process of repeatedly re-
    subdividing the 1906 Duncan Plan ha[d] either de jure or de facto relocated a
    portion of Moore Avenue to be the present Rosewood Avenue.” 
    Id. at 4.
    The
    trial court, exercising its equitable powers, entered an Order on March 31,
    2009 (the “Modification Order”), vacating the Moore Avenue right-of-way and
    relocating it to Rosewood Avenue, allowing the Harvans to extend utility lines
    from the Rosewood Avenue cul-de-sac to their property, and providing for
    reimbursement for the proportionate costs of such extension of utilities. 
    Id. at 9.
    The Harvans subsequently filed a Motion for Post-Trial Relief, requesting
    that the trial court reinstate the Consent Order, and asking for clarification
    regarding the provision providing for reimbursement of the extension of
    utilities.   On April 21, 2009, the trial court entered an Order denying the
    Harvans’ Motion to reinstate the Consent Order, and granting their Motion for
    -6-
    J-A13040-18
    clarification. The trial court amended the portion of the Modification Order
    providing for reimbursement as follows:
    The court finds, and therefore orders, that the implementation of
    [the] Krystyniaks’ consent to permit the extension of utilities from
    their present Northerly terminus in Rosewood Avenue to the
    Sourtherly property line of [the] Harvans’ (approximately 420
    feet) be accomplished by [the] Krystyniaks conveying an
    appropriate utilities easement. It is further ordered that [the]
    Krystyniaks pay or reimburse to the Harvans the proportionate
    amount of costs per foot of such extension over the Krystyniaks’
    property at such time as the Harvans elect to and otherwise gain
    necessary approvals to extend such utilities to and for use upon
    their property.
    Order, 4/21/09, at 1-2 (unnumbered). This Court subsequently affirmed the
    Modification Order, and the Pennsylvania Supreme Court denied allowance of
    appeal.   See Harvan v. Krystyniak, 
    4 A.3d 668
    (Pa. Super. 2010)
    (unpublished memorandum), appeal denied, 
    608 Pa. 668
    (Pa. 2011).
    In May 2012, the Harvans filed a Motion for Rule to Show Cause why
    the Modification Order and the April 21, 2009 Order should not be enforced,
    alleging that they had initiated a plan to install utilities in September 2011,
    but that the Krysyniaks had failed to cooperate, and had refused to execute
    rights-of-way agreements with utility companies. The Harvans additionally
    requested counsel fees.    The trial court thereafter issued a Rule to Show
    Cause, and directed the Krystyniaks to file a response within 30 days. The
    Krystyniaks filed a Response, offering to extend utilities only for a single-
    family residence.    The Honorable Anthony G. Marsili (“Judge Marsili”)
    conducted several evidentiary hearings on the matter.         By Order dated
    -7-
    J-A13040-18
    January 22, 2014, the trial court directed that the Harvans be permitted to
    connect a sewer pipeline at the Rosewood Avenue cul-de-sac to service up to
    eight residences, and that each party would be responsible for their own
    counsel fees and costs. The trial court additionally stated that it would require
    additional expert testimony concerning the cost of extending the utilities.
    On November 18, 2016, the Harvans filed an Omnibus Motion to
    Conclude Action, requesting (1) a hearing for the consideration of expert
    testimony regarding the costs of the extension of utilities; and (2) a hearing
    to reconsider the court’s denial of counsel fees and costs. By Order dated
    December 30, 2016, the trial court denied the Harvans’ request for a hearing
    to reconsider the imposition of counsel fees, and scheduled a hearing for the
    presentation of expert testimony regarding the costs of extension of utilities.
    The trial court conducted a hearing on May 18, 2017, during which the
    Harvans and the Krystyniaks each presented expert testimony as to the costs
    of the utilities extension.   The Harvans’ expert witness, Garrett Salandro
    (“Salandro”) of G. Salandro Landscaping, LLC, testified that his company could
    complete the project for $37,120, and that the Municipal Authority of
    Westmoreland County (“Municipal Authority”) would supply the necessary
    pipes for $13,750.      The Krystyniaks’ expert witness, Michael Koehler
    (“Koehler”), testified that his bid of $22,000 would include placing the electric
    and water lines. Koehler also testified that laying the sewer line would cost
    an additional $5,000, and landscaping would cost an additional $3,000.
    -8-
    J-A13040-18
    Koehler testified that he was not aware that he would have to install a sewer
    line, so the cost of the pipe was not included in his estimate.
    Following the hearing, the trial court directed both parties to submit
    proposed findings of fact and conclusions of law.        The Harvans and the
    Krystyniaks timely complied. The trial court issued an Opinion and Order on
    July 26, 2017, wherein the trial court determined that Salandro’s bid did not
    include the $13,750 necessary to purchase pipe from the Municipal Authority,
    and therefore, Salandro’s total estimate is $50,870 for the completion of all
    required utility work and restoration of the roadway.       The trial court also
    determined that Koehler’s total estimate would increase to $43,750, after
    adding the estimated costs of purchasing pipe from the Municipal Authority,
    laying the sewage line, and landscaping (excluding restoration of the
    roadway).     Based upon its determinations, the trial court ordered the
    Krystyniaks to pay $43,750 into a mutually selected escrow/trust account so
    the Harvans could choose any contractor to complete the project. The trial
    court additionally stated that the Harvans would be responsible for any
    additional costs necessary to complete the work.
    On August 7, 2017, the Harvans filed a Motion for Post-Trial Relief,
    alleging that the trial court erred in concluding that $43,750 would satisfy the
    April 21, 2009 Order, and asserting that Koehler’s bid was incomplete because
    it did not include restoration of the roadway. The Harvans also claimed that
    the trial court erred in failing to provide for contingencies or extra costs, and
    pointed out that the April 21, 2009 Order requires the Krystyniaks to
    -9-
    J-A13040-18
    reimburse the Harvans for the installation costs. Additionally, the Harvans
    argued that the trial court erred in failing to consider their request for counsel
    fees. The trial court denied the Harvans’ Motion by Order dated November 1,
    2017.4 The instant appeal followed.
    On appeal, the Harvans raise the following questions for our review:
    1. Did the [trial c]ourt err in failing to apply the coordinate
    jurisdiction rule by failing to comply with Judge Ober’s Order of
    April 21, 2009, by requiring the Krystyniaks to pay into escrow
    the sum of $43,750.00, rather than the $50,870.00 testified to by
    [the Harvans’] expert witness?
    2. Did the [trial] court err in failing to conduct a hearing regarding
    whether or not to award counsel fees pursuant to 42 Pa.C.S.[A.
    §] 2503(7) in light of [the] Krystyniak[s’] dilatory, obdurate, or
    vexatious conduct which required [the Harvans’] incurred legal
    fees to implement Judge Ober’s Order of April 21, 2009?
    Brief for Appellants at 4.
    In the Modification Order, the trial court exercised its equitable powers
    to relocate the Moore Avenue right-of-way. Because we are now asked to
    consider the trial court’s decision regarding the manner in which the
    Modification Order, and its amendment in the April 21, 2009 Order, should be
    implemented, we will apply the equity standard of review. See Armstrong
    Sch. Dist. v. Armstrong Educ. Ass’n, 
    595 A.2d 1139
    , 1143 (Pa. 1991)
    (stating that “[w]here equity assumes jurisdiction for one or more purposes,
    it will retain jurisdiction for all purposes to give complete relief and to do
    complete justice between the parties. This may include an award of equitable
    ____________________________________________
    4   The Order was docketed on November 2, 2017.
    - 10 -
    J-A13040-18
    relief not covered by the original prayer.” (citation omitted; emphasis in
    original)).
    “In an appeal from a trial court sitting in equity, the standard of review
    is rigorous.” Lilly v. Markvan, 
    763 A.2d 370
    , 372 (Pa. 2000). Our review
    “is limited to determining whether the trial court committed an error of law or
    an abuse of discretion.       The scope of review of a final decree in equity is
    limited[,] and will not be disturbed unless it is unsupported by the evidence
    or demonstrably capricious.” Coldren v. Peterman, 
    763 A.2d 905
    , 907-08
    (Pa. Super. 2000).5
    In their first claim, the Harvans argue that the trial court erred in failing
    to apply the coordinate jurisdiction rule, and awarding the Harvans only 86%
    of the total cost of extending utilities to their property. Brief for Appellants at
    15. The Harvans assert that Judge Ober’s April 21, 2009 Order required the
    Krystyniaks to reimburse the Harvans for the total cost of the extension of
    utilities, and therefore, the Harvans were entitled to have $50,870 placed into
    escrow.       
    Id. at 18-19.
        The Harvans claim that the trial court properly
    determined that Salandro’s bid was complete, but nevertheless improperly
    ordered the Krystyniaks to pay $43,750 into escrow to satisfy Koehler’s bid,
    ____________________________________________
    5We note that the underlying action in this case is an action in quiet title, and
    our standard of review in such cases similarly limits us to considering whether
    a trial court’s factual findings are supported by competent evidence, and
    whether the trial court committed an error of law. See Birdsboro Mun.
    Auth. v. Reading Co. and Wilmington & N. R.R., 
    758 A.2d 222
    , 225 (Pa.
    Super. 2000).
    - 11 -
    J-A13040-18
    which was approximately $7,000 lower and did not provide for the restoration
    of the roadway. 
    Id. at 16-17.
    Our Supreme Court has set forth the following explanation of the
    coordinate jurisdiction rule:
    One of the distinct rules that are encompassed within the “law of
    the case” doctrine is the coordinate jurisdiction rule. Generally,
    the coordinate jurisdiction rule commands that upon transfer of a
    matter between trial judges of coordinate jurisdiction, a transferee
    trial judge may not alter resolution of a legal question previously
    decided by a transferor trial judge. More simply stated, judges of
    coordinate jurisdiction should not overrule each other’s decisions.
    The reason for this respect for an equal tribunal’s decision … is
    that the coordinate jurisdiction rule is based on a policy of
    fostering the finality of pre-trial applications in an effort to
    maintain judicial economy and efficiency. Furthermore, consistent
    with the law of the case doctrine, the coordinate jurisdiction rule
    serves to protect the expectations of the parties, to insure
    uniformity of decisions, to maintain consistency in proceedings, to
    effectuate the administration of justice, and to bring finality to the
    litigation.
    Zane v. Friends Hosp., 
    836 A.2d 25
    , 29 (Pa. 2003) (internal citations,
    footnote and paragraph break omitted).
    Here, Judge Ober’s April 21, 2009 Order (which, in relevant part,
    amended the prior Modification Order) required that the “Krystyniaks pay or
    reimburse to the Harvans the proportionate amount of costs per foot of
    such extension [of utilities] over the Krystyniaks’ property….” Order, 4/21/09,
    at 2 (unnumbered; emphasis added).             However, the Order does not
    specifically designate, to either party, the costs of restoring the affected
    property to its original condition. Following an evidentiary hearing limited to
    the cost of the extension of utilities, Judge Marsili considered the evidence of
    - 12 -
    J-A13040-18
    each party’s expert witness, acknowledged the approximately $7,120
    difference between the two bids, and concluded that the Krystyniaks were
    responsible for the payment of $43,750 to complete the project. Further, the
    trial court noted the following considerations for its decision:
    1. [The Harvans’] expert did not itemize the cost of the individual
    phases of his work estimate, including the specific itemization of
    restoring the roadway;
    2. Both [the Harvans’] estimate and the [Krystyniaks’] estimate
    contained a “rock clause”,[6] but neither provided any potential
    estimate and further, the [Harvans’] expert implied … that such a
    contingency should not be necessary;
    3. The Order of April 21, 2009 … does not specifically address the
    issue of any costs above and beyond that the [Krystyniaks] pay
    or reimburse the [Harvans] the proportional amount of costs per
    foot of such extension over the [Krystyniaks’] property.
    Opinion and Order, 7/26/17, at 4 (footnote added). The trial court additionally
    acknowledged that “this case has been extremely argumentative and
    contentious during the course of litigation and [] the litigation itself has
    extended over a twelve[-]year period.” 
    Id. Significantly, the
    trial court did not overrule Judge Ober’s April 21, 2009
    Order. Instead, Judge Marsili interpreted the manner in which the dictates of
    the Modification Order and the April 21, 2009 Order should be implemented.
    See Decision and Order, 1/22/14, at 3 (stating that the trial court, i.e., Judge
    ____________________________________________
    6 A “rock clause” provides for additional charges if a contractor encounters
    rock during excavation. See N.T., 5/18/17, at 36 (wherein Salandro testified
    that an additional machine would be necessary to dig through solid rock); see
    also 
    id. at 25,
    Plaintiff’s Exhibit 5 (Salandro’s Bid Proposal); 53, Defendant’s
    Exhibit A (Koehler’s Bid).
    - 13 -
    J-A13040-18
    Marsili, “is faced with determining the practical implications of interpreting the
    legal terms and conditions of said March 3[1], 2009 and April 21, 2009
    Orders….”).     Because the trial court’s determination is supported by the
    evidence of record, and we discern no abuse of discretion or error of law, the
    Harvans are not entitled to relief on their first claim.
    In their second claim, the Harvans contend that the trial court erred by
    refusing to conduct a hearing regarding the imposition of counsel fees
    pursuant to 42 Pa.C.S.A. § 2503(7).7 Brief for Appellants at 19. Essentially,
    the Harvans argue that the Krystyniaks are responsible for prolonging the
    period of litigation in this case. See 
    id. at 20-26.
    The Harvans claim that the
    Krystyniaks’ conduct required the litigation of several issues (and therefore,
    the payment of additional counsel fees), which could have been avoided if the
    Krystyniaks had allowed them to access their property over Moore Avenue.
    
    Id. at 20,
    25. The Harvans also assert that “[t]he equity of Judge Ober’s
    Orders has been lost by the contemptuous and obdurate conduct of the
    Krystyniaks.” 
    Id. at 26.
    Here, the Harvans failed to cite to any relevant case law in support of
    ____________________________________________
    7Section 2503(7) provides for the imposition of counsel fees as a sanction
    against “dilatory, obdurate or vexatious conduct during the pendency of a
    matter.” 42 Pa.C.S.A. § 2503(7).
    - 14 -
    J-A13040-18
    their second claim.8 See Pa.R.A.P. 2119(a) (stating that the argument shall
    include “such discussion and citation of authorities as are deemed pertinent.”).
    Accordingly, the Harvans’ second issue is waived. See Lackner v. Glosser,
    
    892 A.2d 21
    , 29 (Pa. Super. 2006) (stating that “arguments which are not
    appropriately developed are waived. Arguments not appropriately developed
    include those where the party has failed to cite any authority in support of a
    contention.” (internal citation omitted)); see also In re Estate of Whitley,
    
    50 A.3d 203
    , 209 (Pa. Super. 2012) (stating that “[t]his Court will not consider
    the merits of an argument which fails to cite relevant case or statutory
    authority. Failure to cite relevant legal authority constitutes waiver of the
    ____________________________________________
    8  The Harvans only included citations to case law relating to their assertions
    that the trial court’s actions in vacating the Consent Order, and relocating the
    defined right of way, were “contrary to well-established legal principles[.]”
    Brief for Appellants at 22. No such argument is identified in the Harvans’
    Statement of Questions Involved. See Pa.R.A.P. 2116(a) (providing that
    “[n]o question will be considered unless it is stated in the statement of
    questions involved or is fairly suggested thereby.”). Moreover, this Court
    previously considered the propriety of the Modification Order in the Harvans’
    first appeal. See Harvan v. Krystyniak, 
    4 A.3d 668
    (Pa. Super. 2010)
    (unpublished memorandum).
    - 15 -
    J-A13040-18
    claim on appeal.” (internal citation omitted)).9
    Based upon the foregoing, we affirm the Judgment of the trial court.
    Judgment affirmed.
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 8/31/2018
    ____________________________________________
    9  Even if the Harvans had properly developed this argument, we would
    conclude that it is without merit. “The denial of a request for attorney’s fees
    is a matter within the sound discretion of the trial court[.]” Hart v. O’Malley,
    
    781 A.2d 1211
    , 1216 (Pa. Super. 2001). Additionally, this Court has upheld
    a trial court’s denial of counsel fees without an evidentiary hearing. See, e.g.,
    ACE Am. Ins. Co. v. Underwriters at Lloyds and Cos., 
    939 A.2d 935
    , 946
    (Pa. Super. 2007) (stating that “the trial court was well within its discretionary
    authority to deny [the participant’s] motion for sanctions and in doing so
    without convening an evidentiary hearing.”). In denying the Harvans’ request
    for counsel fees, the trial court stated that the practical implications of the
    Modification Order and the April 21, 2009 Order were not clear and
    straightforward, and that the Krystyniaks had attempted to provide
    counterproposals to the Harvans’ requests. The trial court also noted that
    “through these many years of litigation, each party has become fixed upon,
    and convinced that his own position is correct.” Decision and Order, 1/22/14,
    at 6. In light of the fact that both parties have been “extremely argumentative
    and contentious during the course of the litigation,” Order, 11/1/17, at 2, we
    would not disturb the trial court’s denial of the Harvans’ request for counsel
    fees.
    - 16 -