Simon, B. v. Sunoco Pipeline, L.P. ( 2019 )


Menu:
  • J-A13006-18
    NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
    BRADLEY A. SIMON AND AMY J.    :            IN THE SUPERIOR COURT OF
    SIMON, HUSBAND AND WIFE        :                 PENNSYLVANIA
    :
    Appellants      :
    :
    :
    v.                   :
    :
    :            No. 771 WDA 2017
    SUNOCO PIPELINE, L.P.; SUNOCO  :
    LOGISTICS PARTNERS, L.P.;      :
    PERCHERON FIELD SERVICES, LLC; :
    EVAN DESVERNINE, LORI ANDREWS; :
    TOM KENNEY; MICHAEL JONES      :
    Appeal from the Order May 4, 2017
    In the Court of Common Pleas of Washington County Civil Division at
    No(s): 2015-3302
    BEFORE: OLSON, J., DUBOW, J., and MUSMANNO, J.
    MEMORANDUM BY OLSON, J.:                         FILED JANUARY 07, 2019
    Appellants, Bradley A. Simon and Amy J. Simon (husband and wife),
    appeal from an order entered on May 4, 2017 in the Civil Division of the Court
    of Common Pleas of Washington County that denied their petition for a
    preliminary injunction. We affirm.
    The relevant facts and procedural history are as follows. On September
    13, 2013, Appellants executed a right-of-way (ROW) agreement with Sunoco
    Pipeline, L.P. (Sunoco).   The parties’ ROW agreement granted Sunoco a
    permanent, non-exclusive 50-foot ROW across Appellants’ property to
    construct the Mariner East 1 Pipeline for use in the transportation of natural
    gas liquids and other petroleum products. The ROW agreement also conveyed
    J-A13006-18
    to Sunoco a 25-foot wide temporary workspace, together with and an
    additional 30-foot wide temporary workspace, next to the permanent ROW
    across Appellants’ property.        Pursuant to the parties’ agreement, Sunoco’s
    right to use the temporary construction workspaces started on the date
    construction commenced on the Mariner East 1 Pipeline, which occurred in
    2014.     The ROW further provided, however, that if Sunoco’s use of the
    temporary workspaces ended before the passage of 12 months, then the
    temporary workspaces would immediately terminate. The ROW agreement
    also granted Sunoco the right to construct additional pipelines through
    Appellants’ property in the future.            These additional pipelines were to be
    located parallel to the initial Mariner East 1 Pipeline and within the 50-foot
    permanent easement. Sunoco completed construction of the Mariner East 1
    Pipeline in 2014 and its use of the temporary workspaces ended in 2015.
    On April 12, 2016, Sunoco notified Appellants of its intent to install a
    second pipeline, known as the Mariner East 2 Pipeline, through their property.
    In response, Appellants, on April 28, 2017, filed a petition for preliminary
    injunctive relief, seeking to prevent Sunoco from using the temporary
    workspace easements to construct the Mariner East 2 Pipeline. 1 Appellants
    ____________________________________________
    1 On June 8, 2015, prior to filing their petition for preliminary injunctive relief,
    Appellants filed a first amended complaint against Sunoco alleging fraud,
    negligence, and negligent misrepresentation because Sunoco allegedly
    claimed it had eminent domain powers at the time the parties executed the
    ROW agreement. The amended complaint requested rescission of the ROW
    agreement and damages. Appellants’ petition for preliminary injunctive relief
    was filed at the same docket number as their amended complaint for
    damages.
    -2-
    J-A13006-18
    asserted that the ROW agreement granted Sunoco the right to install
    additional pipelines within the 50-foot permanent easement but not the right
    to use the temporary workspace easements to facilitate construction of those
    additional pipelines.   As such, Appellants asked the trial court to enjoin
    Sunoco’s construction work in connection with the Mariner East 2 Pipeline
    along the temporary easements on their property.
    The trial court heard oral argument on May 3, 2017 and denied
    Appellants’ petition on May 4, 2017.      The court concluded, inter alia, that
    Appellants failed to demonstrate irreparable harm.
    Appellants filed a timely notice of appeal on May 25, 2017. Pursuant to
    court order, Appellants filed a concise statement of errors complained of on
    appeal on August 16, 2017. See Pa.R.A.P. 1925(b). The trial court issued its
    Rule 1925(a) opinion on September 29, 2017.
    Appellants raise the following claims for our review:
    Whether the [trial court] erred as a matter of law when it denied
    [Appellants’] petition for preliminary injunction, which requested
    that [Sunoco’s] easement for the Mariner East 2 Pipeline across
    [Appellants’] land be limited to the fifty (50’) permanent
    right-of-way granted by [Appellants] to Sunoco for the Mariner
    East 2 Pipeline?
    Whether [Appellants] met the criteria for granting a preliminary
    injunction?
    Whether the [trial court] erred in allowing Sunoco to occupy a
    larger easement for [the Mariner East 2 Pipeline] without an
    evidentiary hearing allowing Sunoco to evade the requirements of
    the Eminent Domain Act?
    Appellants’ Brief at 4 (certain capitalization omitted).
    -3-
    J-A13006-18
    Appellants’ claims assert that the trial court erred in denying their
    petition for a preliminary injunction.    We apply a well settled standard of
    review to such claims:
    [Our] review of a trial court's order granting or denying
    preliminary injunctive relief is highly deferential. Summit Towne
    Centre, Inc. v. Shoe Show of Rocky Mount Inc., 
    828 A.2d 995
    , 1000 (Pa. 2003). This highly deferential standard of review
    states that in reviewing the grant or denial of a preliminary
    injunction, an appellate court is directed to examine the record to
    determine if there were any apparently reasonable grounds for
    the action of the court below. 
    Id.
     [Based upon the analysis in
    Summit Town Centre, which implies that an appellate court
    must conduct a searching inquiry of the record, a plenary scope
    of review is applied. An appellate court should] find that a trial
    court had apparently reasonable grounds for its denial of
    injunctive relief where the trial court has properly found that any
    one of the following essential prerequisites for a preliminary
    injunction is not satisfied. 
    Id. at 1002
    .
    There are six essential prerequisites that a party must establish
    prior to obtaining preliminary injunctive relief. The party must
    show: 1) that the injunction is necessary to prevent immediate
    and irreparable harm that cannot be adequately compensated by
    damages; 2) that greater injury would result from refusing an
    injunction than from granting it, and, concomitantly, that issuance
    of an injunction will not substantially harm other interested parties
    in the proceedings; 3) that a preliminary injunction will properly
    restore the parties to their status as it existed immediately prior
    to the alleged wrongful conduct; 4) that the activity it seeks to
    restrain is actionable, that its right to relief is clear, and that the
    wrong is manifest, or, in other words, must show that it is likely
    to prevail on the merits; 5) that the injunction it seeks is
    reasonably suited to abate the offending activity; and, 6) that a
    preliminary injunction will not adversely affect the public interest.
    
    Id. at 1002
    .      The burden is on the party who requested
    preliminary injunctive relief[.]
    Warehime v. Warehime, 
    860 A.2d 41
    , 46-47 (Pa. 2004) (footnote omitted;
    internal quotation marks omitted).
    -4-
    J-A13006-18
    In applying the above principles in this case, we are convinced that the
    trial court had reasonable grounds to deny relief. In its Rule 1925(a) opinion,
    the trial court found that Appellants did not meet their burden of
    demonstrating irreparable harm.      Trial Court Opinion, 9/29/17, at 2.      In
    particular, the trial court reasoned that the temporary workspaces at issue in
    this case would be returned to Appellants in a restored condition. See 
    id.
    Significantly, Appellants do not dispute this finding before this Court.
    Instead, Appellants argue that recurrent future use of the temporary
    workspaces by Sunoco qualifies as irreparable harm. See Appellants’ Brief at
    16-23. Appellants’ buttress this claim by declaring that Sunoco’s use of the
    temporary workspaces has extended beyond the timelines and/or parameters
    contemplated by the parties’ ROW agreement. See id. at 23.
    Notwithstanding these contentions, we fail to see how Appellants have
    proven irreparable harm. “An injury is regarded as ‘irreparable’ if it will cause
    damage which can be estimated only by conjecture and not by an accurate
    pecuniary standard.” Anchel v. Shea, 
    762 A.2d 346
    , 351 (Pa. Super. 2000),
    appeal denied, 
    782 A.2d 541
     (Pa. 2001).         Here, Appellants conveyed to
    Sunoco the right to use the temporary workspaces for construction of the
    Mariner East 1 Pipeline. Even if Appellants are correct that Sunoco has used
    the temporary workspaces outside the original contemplation of the parties as
    expressed in the ROW agreement, they have offered nothing to show that
    -5-
    J-A13006-18
    Sunoco’s use of the land is incapable of reclamation or not amenable to
    compensation pursuant to an accurate pecuniary standard.
    In view of the record before us, we cannot conclude that the trial court
    lacked any reasonable grounds for its order denying relief.2 Consequently,
    pursuant to our highly deferential standard of review, the order denying
    Appellants’ preliminary injunction must be upheld.
    Order affirmed.
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 1/7/2019
    ____________________________________________
    2 Some of the arguments raised by Appellants, e.g. the issues raised in parts
    III and IV of Appellants’ brief, invite us to address the ultimate merits of some
    of the claims present in this case. We decline this invitation. The scope of
    this appeal extended to whether or not the trial court had any apparently
    reasonable grounds to deny Appellants’ request for a preliminary injunction.
    As such, it would be improper for this Court to address any issues beyond
    whether Appellants proved the essential prerequisites for preliminary
    injunctive relief. We have confined our discussion accordingly.
    -6-
    J-A13006-18
    -7-
    