Gongloff Contracting v. L. Robert Kimball , 119 A.3d 1070 ( 2015 )


Menu:
  • J-A13018-15
    
    2015 PA Super 149
    GONGLOFF CONTRACTING, L.L.C.,                  IN THE SUPERIOR COURT OF
    PENNSYLVANIA
    Appellant
    v.
    L. ROBERT KIMBALL & ASSOCIATES,
    ARCHITECTS AND ENGINEERS, INC.,
    Appellee                    No. 785 WDA 2014
    Appeal from the Order Dated May 5, 2014
    In the Court of Common Pleas of Allegheny County
    Civil Division at No(s): GD-12-013865
    BEFORE: PANELLA, SHOGAN, and OTT, JJ.
    OPINION BY SHOGAN, J.:                                FILED JULY 08, 2015
    Appellant, Gongloff Contracting, L.L.C., (“Gongloff”) appeals from
    orders entered on April 18, 2013, and May 5, 2014, in the Court of Common
    Pleas of Allegheny County. The order entered on April 18, 2013, granted the
    motion for judgment on the pleadings of Appellee, L. Robert Kimball &
    Associates, Architects and Engineers, Inc.’s (“Kimball”).    That order was
    made final on May 5, 2014, by an order on a stipulation to dismiss fewer
    than all defendants pursuant to Pa.R.C.P. 229(b)(1).            After careful
    consideration, we reverse and remand for further proceedings.
    Because this Court sits in review of the trial court’s grant of Kimball’s
    motion for judgment on the pleadings, all well-pleaded statements of fact,
    admissions, and   any documents      properly attached to      the   pleadings
    presented by the party against whom the motion is filed, are considered as
    J-A13018-15
    true. Citicorp North America, Inc. v. Thornton, 
    707 A.2d 536
    , 538 (Pa.
    Super. 1998).      The facts, then, are gleaned from Gongloff’s amended
    complaint and, to a limited extent, its response to allegations raised in
    Kimball’s new matter. See Altoona Regional Health System v. Schutt,
    
    100 A.3d 260
    , 265 (Pa. Super. 2014); Swift v. Milner, 
    538 A.2d 28
    , 31
    (Pa. Super. 1988) (in determining propriety of trial court’s award of
    judgment on the pleadings, we accept as true all well-pleaded statements of
    fact of non-moving party and “against that party only those facts specifically
    admitted.”).
    In 2009, California University of Pennsylvania (the “University”)
    engaged Kimball as the architect-engineer for the construction of a
    convocation center. After Kimball completed the design, the University hired
    Whiting-Turner Contracting Company (“Whiting-Turner”) as the general
    contractor.     Whiting-Turner then entered into a contract with Kinsley
    Construction, Inc. (“Kinsley”) to do the structural steel fabrication and
    erection.      On January 18, 2010, Kinsley entered into a subcontract
    agreement with Gongloff, under which Gongloff agreed to provide all labor,
    materials, and equipment to erect the structural steel for $990,230.00.
    Am. Compl. at ¶¶ 9–12.        Kinsley also entered into a subcontract with
    Vulcraft Inc. (“Vulcraft”) to detail and fabricate the long-span steel trusses,
    which would then be delivered to the site and erected by Gongloff.          In
    addition, Kinsley hired Josh Carney of Carney Engineering (“Carney”), a
    -2-
    J-A13018-15
    registered professional engineer, to assist in the detailed design of the
    structural steel. 
    Id.
     at ¶¶ 15–16. Kimball’s design of the steel structure
    was supplied to all of the aforementioned parties. Id. at ¶ 49.
    In January and February of 2010, both Vulcraft and Carney raised
    concerns about Kimball’s roof design for the convocation center.      During
    preconstruction meetings, they repeatedly opined that the entire design of
    the roof system was faulty.    “In particular, they warned that the header
    beams that supported the roof trusses were drastically undersized.”      Am.
    Compl. ¶ at 17. Despite these concerns, on March 17, 2010, Gongloff began
    to erect the steel structure that Kimball had designed. While Gongloff had to
    address some design problems, work proceeded relatively smoothly for
    about eight weeks. Id. at ¶ 20. However, at about mid-point in this eight-
    week period, Vulcraft issued a letter maintaining that the Kimball-designed
    roof system “was not adequate to bear the construction loads.” Id. at ¶ 21.
    Kimball denied that the roof design was faulty. Id. at ¶ 22.
    Shortly after Kimball’s assurances about the soundness of the design,
    Kimball rejected Gongloff’s proposed erection procedure, even though it had
    been approved by Carney, the structural engineer.      At this point, Kimball
    acknowledged that the as-designed trusses could not accommodate the
    construction loads. Am. Compl. at ¶ 23. On May 3, 2010, Carney confirmed
    that Kimball’s roof was “grossly inadequate.” Id. at ¶ 25.
    -3-
    J-A13018-15
    Gongloff continued to experience a myriad of problems, including three
    shut-downs of the steel erection project, traceable to Kimball’s “never-
    before-utilized” defective design.     Am. Compl. at ¶¶ 24–26, 30, 34.
    Attempts to redesign the structure and address its structural inadequacies
    substantially increased Gongloff’s costs.    Id. at ¶¶ 27, 32, and 39.     To
    address the required adjustments, Gongloff submitted eighty-one change
    order requests for the amount of additional work that was beyond the scope
    of its original bid. Id. at ¶¶ 39–40. While some of the change orders were
    initially approved and paid for by Kinsley, eventually Kinsley ceased making
    payments.    Id. at ¶¶ 41–42.     In mid-February, 2011, Gongloff laid off its
    crew and left the job-site. Id. at ¶ 42. Gongloff has been unable to fully
    pay its vendors and suppliers on the project, and its overall reputation has
    been significantly harmed.      Id. at ¶¶ 43–44.    Although the convocation
    center is now complete and standing, Gongloff denies that the structural
    system is the same as originally designed by Kimball.      Gongloff’s Ans. to
    Kimball’s New Matter at ¶ 68.
    On August 6, 2012, Gongloff initiated this action against Kimball and
    two of its engineers for negligent misrepresentation. Because Gongloff sued
    the wrong Kimball entity, it filed an amended complaint on December 31,
    2012, naming the correct party and dismissing the original individual
    engineers.    In response, Kimball filed an answer, new matter, and an
    amended joinder complaint to join Whiting-Turner, Kinsley, and Carney.
    -4-
    J-A13018-15
    Whiting-Turner and Kinsley filed preliminary objections to Kimball’s amended
    joinder complaint.
    After the pleadings closed, Kimball filed a motion for judgment on the
    pleadings asserting that Gongloff’s claims were barred by both the statute of
    limitations1 and application of the “economic loss doctrine.”2 Regarding the
    latter argument, Gongloff disputed that the economic loss doctrine was
    applicable, contending instead that its claim against Kimball was governed
    by an explicit exception to the doctrine, i.e., an action for negligent
    misrepresentation set forth in Section 552 of the Restatement (Second) of
    Torts and adopted by the Pennsylvania Supreme Court in Bilt-Rite
    Contractors, Inc. v. The Architectural Studio, 
    866 A.2d 270
     (Pa. 2005).
    Gongloff contended that the factual allegations of the amended complaint
    asserted that Kimball: 1) either explicitly or implicitly represented that the
    ____________________________________________
    1
    The trial court concluded that the amended complaint was not time-
    barred. Trial Court Opinion, 4/18/13, at 2. Kimball did not appeal this
    aspect of the trial court’s decision.
    2
    “Our Supreme Court has defined the economic loss doctrine as providing
    ‘no cause of action [ ] for negligence that results solely in economic
    damages unaccompanied by physical injury or property damage.’” Knight
    v. Springfield Hyundai, 
    81 A.3d 940
    , 951–952 (Pa. Super. 2013) (quoting
    Excavation Technologies, Inc. v. Columbia Gas Co. of Pennsylvania,
    
    985 A.2d 840
    , 841 (Pa. 2009)).
    -5-
    J-A13018-15
    structure could safely sustain all required construction loads and in situ3
    loads; 2) either explicitly or implicitly represented that normal construction
    methods could be employed to erect the structure; and 3) supplied false
    information, in the form of its structural design of the project. According to
    Gongloff, these assertions were sufficient to survive Kimball’s motion for
    judgment on the pleadings.
    On April 18, 2013, the trial court decided that Gongloff could not
    pursue its negligent misrepresentation claim and granted Kimball’s motion
    for judgment on the pleadings.            The trial court explained its ruling, as
    follows:
    [Kimball’s] second argument deals with the economic loss
    doctrine as it applies to the facts of the case. The economic loss
    rule is that tort law is not intended to compensate parties for
    losses suffered as a result of a breach of duties assumed only by
    agreement. To recover in negligence there must be a showing of
    harm above and beyond disappointed expectations evolving
    solely from a prior agreement. Bilt-Rite v. The Architectural
    Studio, 
    866 A.2d 270
    , 283 (Pa. 2005). The Bilt-Rite [] decision
    adopted Section 552 of the Restatement ([S]econd) of Torts
    entitled Information Supplied for the Guidance of Others. The
    Supreme Court went on to recognize that a design professional’s
    liability for economic damages to third parties cannot be without
    limits. 
    Id. 286
    .
    The language of Section 552 requires that the design
    professional make a negligent representation that is relied upon
    ____________________________________________
    3
    Earlier in the litigation, the parties offered different definitions of “in situ”
    loads, but now apparently agree that the term refers to loads to which a
    structure is subjected to when it is completed, e.g., accumulated snow on a
    roof.
    -6-
    J-A13018-15
    by the third party and causes the third party economic harm.
    [Gongloff] alleges that Kimball either “expressly or impliedly”
    represented that the structure could safely sustain all required
    construction loads and in situ loads. No representation to that
    effect is shown. [Gongloff] may have suffered economic loss but
    cannot point to the negligent misrepresentation by Kimball that
    led to the loss. The fact that the design was complex and
    required further engineering and design by the contractor cannot
    be attributed to any representation by Kimball.
    Finally, [Gongloff] contends that Kimball explicitly or
    impliedly represented that normal construction methods could be
    employed to erect the structural steel. There is no express
    representation concerning means and methods of construction.
    In fact, Kimball required that the structural steel erector have
    special credentials issued by the American Institute of Steel
    Construction.
    [Gongloff] did not have said credentials, although sub-
    contractor Kinsley did. The requirement of special qualifications
    for the steel erectors undermines [Gongloff’s] position that
    Kimball implied that normal construction methods could be used
    to erect the structural steel.
    Trial Court Opinion, 4/18/13, at 2–3.       The trial court did not address the
    preliminary objections of the additional defendants.
    On April 22, 2013, Gongloff appealed the April 18, 2013 order.           On
    March 6, 2014, a panel of this Court quashed the appeal, holding that the
    trial court’s order granting Kimball’s motion for judgment on the pleadings
    was not a final appealable order because the preliminary objections of the
    additional defendants remained unresolved.       Gongloff v. Kimball, et al.,
    680 WDA 2013, 
    100 A.3d 297
     (Pa. Super. March 6, 2014) (unpublished
    memorandum at 8).
    On March 17, 2014, Gongloff filed a motion for final order to dispose of
    all claims of all parties in the trial court. Thereafter, the parties entered into
    -7-
    J-A13018-15
    a stipulation to dismiss as to fewer than all defendants/additional defendants
    pursuant to Pa.R.C.P. 229(b)(1).           An order approving the stipulation was
    signed on May 5, 2014.           As the April 18, 2013 order granting Kimball’s
    judgment on the pleadings motion was now final, Gongloff appealed to this
    Court. Gongloff filed its Pa.R.A.P. 1925(b) statement of errors complained of
    on appeal on May 22, 2014. On December 2, 2014, the trial court issued an
    order adopting the reasons set forth in its April 18, 2013 Memorandum in
    Lieu of Opinion pursuant to Pa.R.A.P. 1925(a).
    Gongloff raises two issues on appeal:
    1. Does Section 552 of the Restatement (Second) of Torts
    require that a design professional make an explicit negligent
    misrepresentation of a specific fact for a third party to
    recover economic damages?
    2. Did Gongloff properly allege that Kimball either “expressly”
    or “impliedly” represented that the structure could safely
    sustain all required in situ loads?
    Gongloff’s Brief at 6 (emphasis in original). 4
    ____________________________________________
    4
    In its Pa.R.A.P. 1925(b) statement, Gongloff also referenced Kimball’s
    alleged misrepresentation that the as-designed structure could safely sustain
    all required construction loads. Gongloff’s Pa.R.A.P. 1925(b) statement, at
    ¶ 4. Before this Court, Gongloff’s “Statement of Questions Involved” limited
    this issue to Kimball’s representation about the structure’s ability to handle
    in situ loads. Gongloff’s Brief at 6. In the argument portion of its brief,
    however, Gongloff reverts to its original challenge to the trial court’s holding
    regarding both construction and in situ loads. Because Gongloff’s Statement
    of Questions Presented as to this issue fairly suggests that it is contesting
    the trial court’s conclusion concerning both construction and in situ loads, we
    will not find the construction load component of the argument to be waived.
    (Footnote Continued Next Page)
    -8-
    J-A13018-15
    Our standard of review of judgment on the pleadings is well-settled.
    A motion for judgment on the pleadings is similar to that of a demurrer in
    that it may be entered only when there are no disputed issues of fact, and
    the moving party is entitled to judgment as a matter of law.          Rourke v.
    Pennsylvania National Mutual Casualty Insurance Co., ___ A.3d ___,
    
    2015 WL 1912914
    , at *2 (Pa. Super., filed April 28, 2015). Appellate review
    of an order granting a motion for judgment on the pleadings is plenary, and
    we apply the same standard employed by the trial court. 
    Id.
     We will affirm
    the grant of the motion “only when the moving party’s right to succeed is
    certain and the case is so free from doubt that the trial would clearly be a
    fruitless exercise.” 
    Id.
     at *3 (citing Southwest Energy Production Co. v.
    Forest Resources, LLC, 
    83 A.3d 177
    , 185 (Pa. Super. 2013) (citation
    omitted)).
    Gongloff first argues that the trial court committed legal error when it
    construed Section 552 of the Restatement to require a design professional to
    make an explicit negligent misrepresentation before a party can recover
    economic damages.           It offers instead that liability is premised upon the
    _______________________
    (Footnote Continued)
    See Pa.R.A.P. 2116(a) (“the statement [of question involved] will be
    deemed to include every subsidiary question involved or fairly suggested
    thereby.”); See also Phillips v. Selig, 
    959 A.2d 420
    , 428 (Pa. Super.
    2008) (overlooking appellant’s incomplete statement of question presented
    when appellant developed the issue in argument section of his brief, and
    omission did not impede ability to address merits of issue).
    -9-
    J-A13018-15
    posture and relationship of the parties to the construction project.     Our
    standard of review of this legal question is de novo and our scope of review
    is plenary.   Egan v. USI Mid-Atlantic, Inc. 
    92 A.3d 1
    , 10 (Pa. Super.
    2014) (citations omitted).
    We begin with an overview of the tort of negligent misrepresentation.
    The elements of a common law claim for negligent misrepresentation are:
    “(1) a misrepresentation of a material fact; (2) made under circumstances in
    which the misrepresenter ought to have known its falsity; (3) with an intent
    to induce another to act on it; and (4) which results in injury to a party
    acting in justifiable reliance on the misrepresentation.” Bilt-Rite, 866 A.2d
    at 277 (quoting Bortz v. Noon, 
    729 A.2d 555
    , 561 (Pa. 1999)). Negligent
    misrepresentation differs from intentional misrepresentation “in that the
    misrepresentation must concern a material fact and the speaker need not
    know his or her words are untrue, but must have failed to make a
    reasonable investigation of the truth of these words.”   Bortz, 729 A.2d at
    561.
    Pennsylvania law generally bars claims brought in negligence that
    result solely in economic loss. David Pflumm Paving & Excavating, Inc.
    v. Foundation Services Company, 
    816 A.2d 1164
    , 1168 (Pa. Super.
    2003) (“This Court has consistently denied negligence claims that cause only
    economic loss”). However, a narrow exception is found in Section 552 of the
    - 10 -
    J-A13018-15
    Restatement (Second) of Torts entitled, “Information Negligently Supplied
    for the Guidance of Others,” and provides:
    (1) One who, in the course of his business, profession or
    employment, or in any other transaction in which he has a
    pecuniary interest, supplies false information for the guidance of
    others in their business transactions, is subject to liability for
    pecuniary loss caused to them by their justifiable reliance upon
    the information, if he fails to exercise reasonable care or
    competence in obtaining or communicating the information.
    Restatement (Second) of Torts § 552(1).
    In Bilt-Rite, the Pennsylvania Supreme Court adopted Section 552
    and held that it applied in:
    cases where information is negligently supplied by one in the
    business of supplying information, such as an architect or design
    professional, and where it is foreseeable that the information will
    be used and relied upon by third persons, even if the third
    parties have no direct contractual relationship with the supplier
    of information.
    866 A.2d at 287. The adoption of Section 552 was not meant to “supplant[]
    the common law tort of negligent misrepresentation, but rather, [to] clarify[]
    the contours of the tort as it applies to those in the business of providing
    information to others.” Id.
    Subsequently, in Excavation Technologies, Inc. v. Columbia Gas
    Company of Pennsylvania, 
    936 A.2d 111
     (Pa. Super. 2007) (en banc),
    aff’d, 
    985 A.2d 840
     (Pa. 2009), this Court explained the Supreme Court’s
    justification for sanctioning potential Section 552 liability in disputes against
    architects and other design professionals:
    - 11 -
    J-A13018-15
    [O]ur Supreme Court found persuasive the rationale expressed
    by the Court of Appeals of North Carolina in Davidson and Jones,
    Inc. v. County of New Hanover, 
    41 N.C.App. 661
    , 
    255 S.E.2d 580
    (1979), cert. denied, 
    298 N.C. 295
    , 
    259 S.E.2d 911
     (1979),
    wherein the Davidson court stated:
    An architect, in the performance of his contract with
    his employer, is required to exercise the ability, skill,
    and care customarily used by architects upon such
    projects . . . . Where breach of such contract results
    in foreseeable injury, economic or otherwise, to
    persons so situated by their economic relations, and
    community of interests as to impose a duty of due
    care, we know of no reason why an architect cannot
    be held liable for such injury. Liability arises from the
    negligent breach of a common law duty of care
    flowing from the parties’ working relationship.
    Accordingly, we hold that an architect in the absence
    of privity of contract may be sued by a general
    contractor or the subcontractors working on a
    construction project for economic loss foreseeably
    resulting from breach of an architect’s common
    law duty of due care in the performance of his
    contract with the owner.
    Bilt-Rite, at 480-481, 866 A.2d at 286 (quoting Davidson, 
    255 S.E.2d at 584
    ) (emphasis added). A design professional is
    typically responsible for the preparation of plans and
    specifications (information) that are supplied to and used by
    potential bidders in formulating a bid for a project. Additionally,
    a design professional may make representations to the
    contractor while performing administrative responsibilities, which
    are either assumed or specifically made a part of his or her
    contract with the owner. The design professional is paid a fee
    for using his or her skills and training to provide information that
    is relied on by others prior to and during construction. If the
    plans and specifications prove to be erroneous, the contractor is
    at grave risk of suffering economic loss.              Under these
    circumstances, it is quite clear that the design professional is
    supplying information in his or her professional capacity, as part
    of his or her business, for the guidance of others in a business
    transaction.    Furthermore, a design professional’s negligent
    misrepresentation could injure a third party in a variety of ways.
    Accordingly, the Supreme Court had little trouble reaching the
    - 12 -
    J-A13018-15
    conclusion that the requirements of section 552(1) are met
    under these circumstances.        This was a logical conclusion
    because there are numerous tasks performed by the design
    professional on a typical project that support the conclusion that
    he or she is in the business of supplying information.
    Id. at 115.    This Court then detailed the elements required to establish
    liability under Section 552(1) of the Restatement:
    the defendant is in the business of supplying information for the
    guidance of others and the information provider must have a
    pecuniary interest in the transaction; the information provided is
    false; the information was justifiably relied upon; and the
    defendant failed to exercise reasonable care in obtaining or
    communicating the information.
    Id. at 115–116. The Court, however, noted that the scope of liability under
    Section 522(1) was limited to those known by the information provider who
    are intending to engage in a commercial transaction and whom the provider
    means to influence in that transaction with its information. Id. at 116.
    We are persuaded that Excavation Technologies, interpreting the
    reach of Bilt-Rite, could reasonably be understood to subject architects to
    liability for Section 522 negligent misrepresentation claims when it is alleged
    that those professionals negligently included faulty information in their
    design documents. The design itself can be construed as a representation
    by the architect that the plans and specifications, if followed, will result in a
    successful project. If, however, construction in accordance with the design
    is either impossible or increases the contractor’s costs beyond those
    anticipated because of defects or false information included in the design,
    the specter of liability is raised against the design professional.
    - 13 -
    J-A13018-15
    Kimball, to the contrary, avers that courts applying Section 522
    subsequent to Bilt-Rite have held that an “actual misrepresentation” is
    required, citing State College Area School District v. Royal Bank of
    Canada, 
    825 F. Supp. 2d 573
    , 584 (M.D. Pa. 2011), and that Bilt-Rite itself
    refers to an “express representation” made by the architect.      866 A.2d at
    272. Kimball asserts that the language in these cases requires Gongloff to
    identify some particular communication or document provided by Kimball
    that was false.
    We do not agree that State College and Bilt-Rite compel such a
    conclusion.    In State College, a federal court, applying Pennsylvania law,
    declared that “[a] negligent misrepresentation claim requires an actual
    misrepresentation as opposed to assumptions on the part of the recipient.”
    
    825 F.Supp.2d at 584
     (citation omitted).           The word “actual,” however,
    differs in meaning from the word “express,” which was employed by the trial
    court to describe Gongloff’s pleading requirements in this matter.5 Merriam–
    Webster defines “actual” as “existing in fact.”            MERRIAM–WEBSTER,
    http://www.Merriam-Webster.com/dictionary/actual (last visited June 17,
    2015).     Indeed, the court in State College embraced this definition of
    ____________________________________________
    5
    We note that the trial court used the word “express” in rejecting
    Gongloff’s assertion that Kimball represented that normal construction
    methods could be utilized to erect the structural steel. Although Gongloff did
    not appeal this specific trial court finding, we view the challenged language
    as indicative of the trial court’s misunderstanding of the proper standard for
    evaluating motions for judgment on the pleadings.
    - 14 -
    J-A13018-15
    “actual” when it described its opposite meaning as “assum[ed].”              
    825 F.Supp. 2d at 584
    . The actual misrepresentation alleged by Gongloff here
    was Kimball’s roof design, composed of tangible documents which exist in
    fact.
    “Express,” on the other hand, is defined as “directly, firmly, and
    explicitly     stated.”            MERRIAM–WEBSTER,       http://www.Merriam-
    Webster.com/dictionary/ express (last visited June 17, 2015).         The word
    “express” contemplates a higher degree of exactitude than the word
    “actual.” Accordingly, requiring Gongloff to explicitly pinpoint the specifics of
    the faulty design, i.e., to refer to an express representation by Kimball, is
    not endorsed by the language in State College, and, more significantly, is
    inappropriate at the judgment on the pleadings stage.6
    Nor does Bilt-Rite necessitate Gongloff’s precise identification of a
    misrepresentation in the design documents. While Kimball is correct that in
    its factual recital of the case, the Supreme Court detailed that the design
    professional therein “expressly represented” that its aluminum curtain wall
    “could be installed and constructed through the use of normal and
    ____________________________________________
    6
    Regardless, “pronouncements of the lower federal courts have only
    persuasive, not binding, effect on the courts of this Commonwealth—
    although we certainly are bound by the decisions of the U.S. Supreme Court
    on questions of federal law.” In re Stevenson, 
    40 A.3d 1212
    , 1221 (Pa.
    2012) (citation omitted).
    - 15 -
    J-A13018-15
    reasonable means and methods, using standard construction design tables,”
    see Bilt Rite, 866 A.2d at 272, the Court did not include an “express
    representation” as an element of a Section 552 negligent misrepresentation
    claim.   Instead, Bilt-Rite explained that recovery under Section 552 is
    permissible in cases where one in the business of supplying information,
    such as an architect, negligently supplies such information when he knows
    that third parties will likely use or rely on the information.      Herndon
    Borough Jackson Township Joint Municipality Authority v. Pentair
    Pump Group, Inc., No. 4: 12-cv-01116, 
    2015 WL 2166097
    , at *7 (M.D.Pa.
    May 5, 2015) (quoting Bilt-Rite, 866 A.2d at 287). Bilt-Rite requires only
    that information, a rather general term, be negligently supplied by the
    design professional. Accordingly, the trial court’s decision that Gongloff was
    required to identify an express representation by Kimball to succeed on its
    Section 522 claim was legally erroneous.
    Our contrary legal conclusion, however, does not, in and of itself,
    mandate reversal of the trial court’s decision. Gongloff cannot defeat entry
    of judgment on the pleadings against it merely by contending in its amended
    complaint that Kimball supplied design documents to the participants
    involved in the convocation center construction.     It also was required to
    plead with some specificity that the documents included false information.
    The parameters of Gongloff’s pleading obligation form the basis of
    Gongloff’s second argument—that the trial court prematurely held that
    - 16 -
    J-A13018-15
    Gongloff failed to prove what it averred.            Gongloff asserts that the court
    erred when it faulted Gongloff for failing to show that Kimball “explicitly or
    impliedly represented that the structure could safely sustain all required
    construction and in situ loads.”               Trial Court Opinion, 4/18/13, at 3.7
    Gongloff takes particular umbrage with the trial court’s language that “[no]
    representation to that effect was shown,” id., because it contradicts what is
    required when considering a motion for judgment on the pleadings. Gongloff
    avers that use of the word “shown” indicates that instead of accepting
    Gongloff’s assertion that Kimball either expressly or impliedly represented
    that the structure could safely sustain the construction and in situ loads as
    ____________________________________________
    7
    In its appellate brief, Gongloff, for the first time, maintains that it
    identified an express representation by Kimball as to the ability of the
    structure to safely sustain all required construction loads. Gongloff claims
    that the allegation included in paragraph fifty of its amended complaint that
    Kimball either explicitly or impliedly represented that its structural design
    was adequate was premised upon Rider E to the Agreement between the
    University and Kimball. The Rider provided that the University’s approval of
    “plans and specifications shall not diminish [Kimball’s] obligation to provide
    plans and specifications that are adequate to accomplish the purposes of the
    project.” Kimball’s Ans. and New Matter, Ex. A. Gongloff, however, did not
    identify Rider E as an express representation by Kimball in its amended
    complaint or in the related proceedings before the trial court. Thus, we will
    not consider the significance of its language on appeal. See Majorsky v.
    Douglas, 
    58 A.3d 1250
    , 1258 (Pa. Super. 2012) (rules of appellate
    procedure mandate that “issues not raised in the lower court are waived and
    cannot be raised for the first time on appeal) (quoting Pa.R.A.P. 302(a)).
    - 17 -
    J-A13018-15
    true, the trial court determined that Gongloff failed to prove the assertion—
    an obligation in conflict with Gongloff’s burden at this stage of the litigation.
    We agree with Gongloff that the trial court’s finding that Gongloff failed
    to show an express or implied representation implicates matters related to
    proof, as opposed to matters accepted as true.             We thus review the
    allegations of the amended complaint to determine whether Gongloff has
    alleged sufficient facts to meet the Bilt–Rite exception to the economic loss
    doctrine.
    First, Gongloff alleged that Kimball supplied its design to the parties
    working on the convocation project “in order to provide guidance . . . as to
    how the Convocation Center was to be built.” Am. Comp. at ¶ 49. Taken as
    true, this language sufficiently alleges that Kimball understood it was
    “foreseeable that the information [would] be used and relied upon by third
    persons[.]” Bilt–Rite, 866 A.2d at 287. Second, Kimball clearly qualifies as
    a design profession “in the business of supplying information[.]” Id.; Am.
    Compl. at ¶ 5.     Third, Gongloff alleged the following instances where the
    feasibility of construction of the convocation center’s roof in accordance with
    Kimball’s design was called into question or determined to be impossible,
    thereby permitting an inference that the design included false information:
    •   during pre-construction meetings, Vulcraft and Carney stated that the
    design of the never-before-utilized roof system was faulty, particularly
    - 18 -
    J-A13018-15
    that “the header beams that supported the roof trusses were
    drastically undersized.” Id. at ¶ 17.
    •   Brian Gongloff, Gongloff’s General Manager, articulated concerns
    “about the adequacy of the roof truss system in the context of the
    safety of Gongloff’s employees working on the roof during its
    erection.” Id. at ¶ 18.
    •   On April 14, 2010, Vulcraft disseminated a letter “stating that the
    entire long-span truss roof system, as designed by Kimball, was not
    adequate to bear the construction loads to which it would be
    subjected.” Id. at ¶ 21.
    •   Kimball acknowledged that “under construction loads, the as-designed
    trusses were placing an excessive lateral load on the as-designed
    header beams that supported them, thereby subjecting the header
    beams to biaxial bending and overstressing them, as well as causing
    the header-to-column connections to fail.” Id. at ¶ 23.
    •   Gongloff was forced to develop “six site-specific truss-erection plans to
    try to keep up with Kimball’s ongoing but incompetent efforts to revise
    the design.” Id. at ¶ 24.
    •   “On May 3, 2010, Carney[] issued a letter confirming that Kimball’s
    roof design was grossly inadequate.” Id. at ¶ 25.
    - 19 -
    J-A13018-15
    •   On May 24, 2010, Kimball revised the connection details of the trusses
    to the supporting columns. “This revision was intended to remedy the
    deficiencies in [Kimball’s] original design.” Id. at ¶ 28.
    •   On or about July 15, 2010, Vulcraft warned that the inadequacy of the
    roof system prohibited implementation of standard steel decking
    procedures.     Gongloff was required to undertake an alternate
    cumbersome procedure that substantially increased its costs. Id. at ¶
    31.
    •   Similarly, the inadequacy of the roof system necessitated an expensive
    procedure for erection of the catwalk “that was not contemplated in
    the bid documents.” Id. at ¶ 32.
    •   The catwalk itself was improperly designed by Kimball.         “This error
    caused further delay, and additional work, as the trusses had to be
    reinforced in order to carry the catwalk.” Id. at ¶ 36.
    Additionally, in detailing the basis of its negligent representation claim,
    Gongloff alleged:
    50. In providing the structural design of the Convocation Center
    to these parties, [Kimball] either explicitly or implicitly
    represented to those parties, including Gongloff, that the
    structural design was adequate and that the structure could
    safely sustain all required construction loads and in situ loads
    and that normal construction methods could be employed to
    erect the structure.
    51. [Kimball’s] foregoing representation as to the adequacy of
    its structural design was materially false information, inasmuch
    as the structural design, including, specifically the design of the
    long-span-joists and their support system, was not adequate to
    - 20 -
    J-A13018-15
    safely sustain all required loads and normal construction
    methods could not, in fact, be utilized to erect the structure.
    Am. Compl. at ¶¶ 50, 51.
    We conclude that the amended complaint’s allegations that Kimball’s
    design documents constituted negligently-supplied false information have
    been pled with the appropriate level of specificity to state a cause of action
    for negligent misrepresentation under Section 552 of the Restatement
    (Second) of Torts. While Kimball might prove later in the litigation that the
    allegation that it provided false information concerning the integrity of its
    roof design was unsubstantiated, it is not entitled to judgment in its favor at
    this stage of the proceedings. Accordingly, the trial court’s order granting
    judgment on the pleadings in favor of Kimball was premature and is
    reversed.
    Order reversed and remanded for consistent proceedings. Jurisdiction
    relinquished.
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 7/8/2015
    - 21 -